PROCUREMENT IN WORLD BANK INVESTMENT PROJECT FINANCE PROCUREMENT POLICY (DRAFT)

Similar documents
PROCUREMENT IN WORLD BANK INVESTMENT PROJECT FINANCE BORROWER S PROCUREMENT PROCEDURES (DRAFT)

Annex H Comparison between BP11.00 and New Procurement Framework

Annex G Comparison between OP11.00 and new Procurement Framework

PROCUREMENT POLICIES AND PROCEDURES

Program-for-Results Financing 1

GUIDELINES. On Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants

Guidelines on Preventing and Combating Fraud and Corruption in Program-for-Results Financing. Dated February 1, 2012

Program-for-Results Financing

Procurement. OP January 2011 Page 1 of 10. Revised July 1, 2014

Executive Board Annual Session Rome, May 2015 POLICY ISSUES ENTERPRISE RISK For approval MANAGEMENT POLICY WFP/EB.A/2015/5-B

THE WORLD BANK Procurement Regulations for IPF Borrowers

NONCOMPLIANCE IN PROCUREMENT GUIDANCE NOTE ON PROCUREMENT JUNE 2018 ASIAN DEVELOPMENT BANK

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.109

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.110

GUIDELINES. On Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants. Dated October 15, 2006

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.108

General Risk Control and 20/10/15

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

Tax Administration Diagnostic Assessment Tool MODULE 11: ACCOUNTABILITY AND TRANSPARENCY

MATRIX OF STRATEGIC VISION AND ACTIONS TO SUPPORT SUSTAINABLE CITIES

SUMMARY OF BINDING CORPORATE RULES

Bank Directive. Bank Access to Information Policy Designation Public. Catalogue Number LEGVP5.09-DIR.117. Issued July 19, Effective July 1, 2016

International Finance Corporation s Policy on Social & Environmental Sustainability

GUIDELINE NO.4 PENSION PLAN GOVERNANCE GUIDELINES SELF-ASSESSMENT QUESTIONNAIRE AND

PROGRAM-FOR-RESULTS FINANCING INTERIM GUIDANCE NOTE TO STAFF: FIDUCIARY SYSTEMS ASSESSMENT. Operations Policy and Country Services

1 July Guideline for Municipal Competency Levels: Chief Financial Officers

Joint Partnership Arrangement

Evidence of compliance

April 2015 FC 158/12 E. Hundred and Fifty-eighth Session. Rome, May Anti-Fraud and Anti-Corruption Policy

Procurements by states General procurement standards.

(Real Estate Cadastre and Registration Project Additional Financing) between. FORMER YUGOSLAV REPUBLIC OF MACEDONIA (the Borrower) and

DOCUMENTS CO-FINANCING FRAMEWORK AGREEMENT. between ASIAN INFRASTRUCTURE INVESTMENT BANK. and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

OP Investment Project Financing. Bank Access to Information Policy Designation Public

Auditor-General s Auditing Standards 2017

Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION

AFRICAN DEVELOPMENT BANK GROUP

Making it add up. A constructive critique of the EITI Reporting Guidelines and Source Book

LOAN AGREEMENT (Special Operations) (Higher Education Reform Project) between MONGOLIA. and ASIAN DEVELOPMENT BANK DATED 9 SEPTEMBER 2011

The OECD Guidelines for Multinational Enterprises

AG-3 Effectiveness and efficiency, waste and a lack of probity or financial prudence

Fitch Ratings, Inc Form NRSRO Annual Certification. Fitch s Code of Conduct may be accessed at

PROJECT AGREEMENT. (Hebei Energy Efficiency Improvement and Emission Reduction Project) between ASIAN DEVELOPMENT BANK. and

Section 3.07 is deleted and the following is substituted therefor:

Public consultation on the 2014 Review of the OECD Principles of Corporate Governance

Procurement Guidelines for AFD- Financed Contracts in Foreign Countries. Agence Française de Développement

INCLUSIVE HOUSING FINANCE PROGRAM

MADRAS FERTILIZERS LIMITED CORPORATE SOCIAL RESPONSIBILITY (CSR) POLICY

DC: AVNET, INC. VOLUNTARY EMPLOYEE SEVERANCE PLAN

Mentor Public Schools Board of Education 8.18 Policy Manual page 1 Chapter VIII Fiscal Management PROCUREMENT WITH FEDERAL GRANTS/FUNDS

Maricopa County Policy/Contract Template Reference. Procurement Standards ( )

Third Party Due Diligence: When is Enough, Enough?

Overview of Procurement and Integrity at the EIB. Andreja Neral Lamza & Mirela Lascu, European Investment Bank

New Development Bank Procurement Policy

CODE OF CONDUCT FOR SENIOR MANAGEMENT PERSONNEL

Statement of Recommended Practice. Practice Note 10: Audit of financial statements of public sector bodies in the United Kingdom

Recurrent Integrity Issues in Procurement. Gianpiero Antonazzo Senior Investigator INTEGRITY VICE PRESIDENCY

ENGINEERING CONSULTANCY SERVICES. Terms and Conditions

INVITATION TO BID. Contractor Services Associated With:

Unique Markets, Responsible Investing

GENERAL RISK CONTROL AND MANAGEMENT POLICY

PROCUREMENT POLICY. EDD Revision Date: 8/24/00 WDB Review Date: 6/21/07; 12/20/07; 12/17/15 EXECUTIVE SUMMARY: Purpose:

HALIFAX REGIONAL WATER COMMISSION PROCUREMENT POLICY. Edited May 22, 2012

Ethics & Compliance. Group Instruction for Charitable Contributions

Comparison of Federal Uniform Guidance and State Procurement Requirements For North Carolina Local Governments

Global Tax Strategy November 2017

Directive: Bank Directive: Sanctions for Fraud and Corruption in Bank Financed Projects

ANTI-FRAUD CODE CONTENTS INTRODUCTION GOAL CORPORATE REFERENCE FRAMEWORK CONCEPTUAL FRAMEWORK ACTION FRAMEWORK GOVERNANCE STRUCTURE

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE OF THE REGIONS

FSC Standard 23: Principles of Internal Governance and Asset Stewardship

CITIZEN ENGAGEMENT IN BUDGETING AND PUBLIC ACCOUNTABILITY

GUIDELINES PROCUREMENT NON-CONSULTING SERVICES UNDER IBRD LOANS AND IDA CREDITS & GRANTS BY WORLD BANK BORROWERS OF GOODS, WORKS AND

RELIANCE NIPPON LIFE ASSET MANAGEMENT LIMITED ( COMPANY ) CODE OF PRACTICES & PROCEDURES FOR

Intro Public-Private Partnership (P3) Finance Course

Response to the. Banking Ombudsman Scheme. on the. Consultation on proposed scheme rule changes

Stewardship Principles for Institutional Investors

Section (a) ADB and Uzbekenergo shall cooperate fully to ensure that the purposes of the Loan will be accomplished.

MEMORANDUM Municipal Way, Lansing (Delta Township), Michigan Enclosed for your consideration is MERS Request For Proposal (RFP).

Audit manual - general part

Conflict of Interest Policy

STANDARD BIDDING DOCUMENTS UNDER JAPANESE ODA LOANS

NEW PROCUREMENT FRAMEWORK Procurement-related Complaints

Guideline No. 4: Pension Plan Governance Guideline

AN APPROACH TO RISK-BASED MARKET CONDUCT REGULATION

MONTENEGRO SECURITIES AND EXCHANGE COMMISSION INTERNAL DEVELOPMENT STRATEGY OF THE SECURITIES AND EXCHANGE COMMISSION

DOE Best Practice Guidelines for Residential PACE Financing: Consumer Protections

Governance for Improved Service Delivery Region. Program-for-Results Program ID. Republic of Kenya Implementing Agency

Multi-Donor Health Results Innovation Trust Fund Grant Agreement

Credit Reference Agencies Call for information

Annex 2: SSHF Memorandum of Understanding [Template] STANDARD MEMORANDUM OF UNDERSTANDING (MOU) FOR SOUTH SUDAN HUMANITARIAN FUND

ADMINISTRATIVE POLICY. Page 1 of 9. Finance and Administration. Fiscal Roles and Responsibilities ADAMS STATE COLLEGE. EFFECTIVE DATE: June 15, 2006

Financing Agreement OFFICIAL OCUMENTS. Public Disclosure Authorized CREDIT NUMBER 5152-UZ. Public Disclosure Authorized

WK Update for Auditors and Audit Committees

CONTENTS. Page EXECUTIVE SUMMARY I. OVERVIEW 1 II. FINDINGS AND RECOMMENDATIONS 2 III. CONCLUDING REMARKS 19

NOW, THEREFORE, the UNDP and the Recipient Organizations (hereinafter referred to collectively as the Participants ) hereby agree as follows:

Financing Agreement CONFORMED COPY IDA CREDIT NUMBER 4825-KG IDA GRANT NUMBER H618-KG. (Emergency Recovery Project) between KYRGYZ REPUBLIC.

TO THE HEADS OF EXECUTIVE DEPARTMENTS AND ESTABLISHMENTS

CORPORATE GOVERNANCE POLICY

CODE OF BUSINESS CONDUCT & ETHICS FOR BOARD MEMBERS

ENVIRONMENTAL, SOCIAL AND GOVERNANCE POLICY

TABLE OF CONTENTS CHAPTER 1 PROCUREMENT THRESHOLDS AND PROCEDURES...

Transcription:

PROCUREMENT IN WORLD BANK INVESTMENT PROJECT FINANCE PROCUREMENT POLICY (DRAFT) JULY 8, 2014

Vision Statement for Procurement in World Bank Investment Project Finance Procurement in Bank Operations supports borrowers to achieve value for money with integrity in delivering sustainable development. To achieve this vision, the World Bank seeks assurance that acceptable procurement practices are applied to the financial resources it provides to borrowers, and it supports its borrower countries in enhancing and implementing sound procurement systems and institutions. To deliver this vision, World Bank s Procurement supports borrower countries in enhancing and implementing sound procurement systems and institutions. The World Bank may support country capacity building at the level of the project or as part of the country dialogue, using a range of measures, funding, technical support, and hands on implementation support depending on the specific context of the country, sector, agency, or project. The World Bank s assistance goes beyond procurement that is specific to World Bankfinanced projects to address good public procurement and governance generally. In providing such development support, the World Bank considers addressing all relevant aspects of the public financial management system and associated governance mechanisms. K-1

Preamble 1. The World Bank Procurement Framework governs the procurement of goods, works, consulting and non-consulting services required for an investment project 1 that is financed by the World Bank and executed by the borrower. 2. The Procurement Framework encompasses this Policy and its associated Directives and Procedures. This Policy sets out the substantive principles on which World Bank procurement is based, and the Directives and Procedures provide detailed statements on how World Bank staff should implement the Policy. As part of the Directives, Borrower s Procurement Procedures contain mandatory procedures that apply to the borrower and those carrying out a World Bank-financed project; they are incorporated by reference in the financing agreement. In addition, guidance notes provide advice and non-mandatory courses of action. 3. The financing agreement governs the legal relationships between the borrower and the World Bank; only the parties to the financing agreement may derive any rights from it or have any claim to loan proceeds. The relationship between the borrower and the providers of goods, works, consulting and non-consulting services for the project, including their respective rights and obligations, is not governed by the World Bank s Procurement Framework but by the procurement documents issued by the borrower and by the contracts between the borrower and the providers. 4. Nothing in the Directives or Borrower s Procurement Procedures may be used to evade or diminish the procurement principles established in this Policy. In all circumstances, interpretations and applications of the Directives and Procedures must remain consistent with the procurement principles set out in the Policy, and they are auditable as such. Core Procurement Principles 5. This principles-based and results-based framework establishes clear accountability for the conduct of procurement. All procurement under this Policy should be guided by the Core Principles. The Core Procurement Principles include attributes that have guided the World Bank s work in procurement since its inception, and they are consistent with international best practice in public procurement. By applying these principles, the 1 The Procurement Framework applies to investment projects, including contracts that may be subject to retroactive financing. It does not apply to operations financed under Program-for-Results financing (OP 9.00, Program-for-Results Financing), nor does it apply to policy lending operations (OP 8.60, Development Policy Lending) unless the World Bank agrees with the borrower on specific purposes for which loan proceeds may be used. K-2

World Bank meets the requirements in its Articles of Agreement (World Bank Articles of Agreement, Article III, Section 5(b), and IDA Articles of Agreement, Article V, Section 1(g)) to ensure that the proceeds of any loan are used only for the purposes for which the loan was granted, with due attention to considerations of economy and efficiency and without regard to political or other non-economic influences or considerations. (a) Value for money. Value for money means the effective, efficient, and economic use of resources, which requires an evaluation of relevant costs and benefits, along with an assessment of risks, on a whole-life or life cycle costs basis, as appropriate. (b) Economy. This principle takes into consideration factors such as sustainability, quality, and whole-life or life cycle cost that support value for money. It permits integrating into the procurement process economic, environmental, and social considerations that have been agreed with the borrower. It also permits augmenting identified sustainability criteria with specific criteria in support of the borrower s own sustainable procurement policy. (c) Integrity. The World Bank requires borrowers, sub-borrowers (and other beneficiaries of World Bank financing), bidders, providers, contractors, subcontractors, consultants, sub-consultants, any agents (whether declared or not), and any personnel thereof, to observe the highest standard of ethics during the procurement and execution of World Bank-financed contracts. It requires all stakeholders to refrain from fraudulent and corrupt practices defined in the World Bank Group anticorruption guidelines. The World Bank helps institutions in the public sector to strengthen the governance of their own procurement arrangements. The World Bank and all stakeholders involved in procurement are required to monitor, identify, recognize, and manage conflicts of interest (actual, potential, or perceived) in a satisfactory manner. (d) Fit for Purpose. This principle applies both to the intended outcomes and the procurement arrangements in determining the most appropriate approach to meet the development objectives and project outcomes. The procurement approach should take into account the context and the risk, value, and complexity of the procurement. (e) Efficiency. Project procurement arrangements should represent good value for money, with specifications and processes that are proportional to the value and risks of the procurement. They should be time-sensitive, generally striving to avoid delays, but also reflecting the needs of certain procurements (as in the health sector, or in emergency situations). (f) Transparency. The World Bank requires transparency in the procurement cycle, both as an inherent quality of good procurement and as a contribution to standards of accountability. Sufficient and relevant information must be made in an open manner publicly available to all interested parties consistently and in a timely K-3

manner through readily accessible, widely available avenues at reasonable or no cost. Transparency is established when all relevant aspects of procurement in an entity are available for appropriate scrutiny, supported by comprehensive documentation and disclosure. (g) Fairness. The World Bank requires that all eligible individuals and legal entities be given the same opportunities to compete for World Bank-financed activities. The procurement process must ensure equal opportunity and treatment for bidders; equitable distribution of rights and obligations between contracting authorities and contractors, providers and consultants; and credible mechanisms for addressing procurement related complaints and providing recourse. Governance 6. The governance of the procurement function in World Bank-financed operations is managed through clear and transparent lines of accountability and careful definition of the roles of responsible parties. The performance of individuals and institutions involved in procurement is auditable, and it is assessed in terms of not only policy compliance, but also outcomes. (a) Roles and Responsibilities. Responsibility for the implementation of the project, and therefore for the award and administration of contracts under the project, rests with the borrower. The World Bank, seeking to ensure that funds are used only for the purposes for which the financing was granted, exercises procurement oversight under a risk-based approach. To provide effective support to borrowers while managing fiduciary risks, the World Bank may, as appropriate, provide hands on support or delegate its oversight role to another party. The World Bank will always retain and reserve the right to review any activity or documentation for activities supported by World Bank financial resources. (b) Accountability. The World Bank s concept of accountability combines the requirements of transparency and responsibility; it holds those involved in the procurement process can be held accountable for their actions (or inactions). The Procurement Framework sets roles and responsibilities, establishing accountability both for means and ends that is, consistency with World Bank procurement Core Principles, procedural compliance, and achievement of value for money and sustainable results. (c) Conflict of Interest. The World Bank requires that all who are involved in a procurement process under World Bank-financed projects not have a conflict of interest. Providers of goods, works, consulting and non-consulting services must remain professional, objective, and impartial. They must at all times hold the borrower s interests paramount, without any consideration for future work; and must avoid conflicts with other assignments and their own corporate and/or personal interests. K-4

(d) Eligibility. To foster competition, the World Bank permits eligible individuals and legal entities from all countries to offer goods, works, consulting and nonconsulting services for World Bank-financed projects. The World Bank does not permit a borrower to deny participation in a procurement process or award to an individual or a legal entity for reasons unrelated to (a) its capability and resources to successfully perform the contract; (b) conflict of interest situations; (c) fraud and corruption issues; and (d) other conditions established in the Procurement Framework. (e) Remedies. The World Bank does not finance expenditures under a contract for goods, works, or consulting and non-consulting services if it concludes that the contract has not been awarded or executed in accordance with this Policy, as agreed in the financing agreement. (f) Complaints. Complaints may be brought at any time to the borrower and/or the World Bank about any part of the procurement process, from the earliest stages of project identification to the last day of the last warranty related to the specific procurement activity. To promote an open, fair, and transparent procurement process, complaints should be resolved objectively and in a timely manner. Applicability 7. This Policy and its associated Directives and Procedures cover the full procurement cycle of operational activities financed by the World Bank. In recognition of the need to apply the most effective procurement approach to a given operation, alternative procurement arrangements may also be used in full or in part, if their methods and procedures reflect the World Bank s Core Procurement Principles and there is an effective governance framework in place, effective performance, and provision for the World Bank to review any activity or documentation for activities supported by World Bank financial resources. Procurement Strategy for Development 8. To achieve projects development objectives, the World Bank requires the Borrower to develop a procurement strategy. The scope and details of the strategy should take into account, and be proportional to, the market, scale, risk, value, country context (e.g., fragile and conflict-affected situations, disaster/emergency, small economies, etc.), and the complexity and specific objectives of the operation (e.g. development of domestic contracting, manufacturing and consulting industries). 9. The procurement strategy forms the basis for procurement plans, which specify the approved procurement methods to be used for a particular operation according to the financing agreement. Procurement plans and their updates and modifications may be subject to the World Bank s prior review. K-5

Interpretation and Application 10. The World Bank Chief Procurement Officer is responsible to Management for formulating, updating, and interpreting the Procurement Framework in accordance with the procurement principles established in this Policy. In addition, this official is responsible for delegating procurement responsibility through the organization, and for monitoring and reporting on the implementation and application of the Procurement Framework. K-6