Risk Assessment of the Niagara Tunnel Project

Similar documents
METHODOLOGY For Risk Assessment and Management of PPP Projects

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Project Risk Management

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS

Project Management Certificate Program

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Fundamentals of Project Risk Management

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

P3 Fundamentals and Best Practices in Resource and Project Management

CONTINGENCY. Filed: EB Exhibit D2 Tab 2 Schedule 7 Page 1 of 10

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

INSE 6230 Total Quality Project Management

Chapter-8 Risk Management

NIAGARA TUNNEL PROJECT QUALITATIVE RISK ASSESSMENT REPORT

Managing Project Risk DHY

Federal Transit Administration United States Department of Transportation Washington, DC 20590

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

EFFECTIVE TECHNIQUES IN RISK MANAGEMENT. Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011

Introduction to Life Cycle Risk Management Glossary

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

Chapter 7: Risk. Incorporating risk management. What is risk and risk management?

Project Theft Management,

CEVP Cost Estimate Validation Process


L U N D S U N I V E R S I T E T. Projektledning och Projektmetodik

Information Technology Project Management, Sixth Edition

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

Risk vs. Uncertainty: What s the difference?

RISK EVALUATION OF PRODUCTION AND IMPLEMENTATION OF THE PROJECT

Senior Director, Fire Life Safety & Risk Management

California Department of Transportation(Caltrans)

Risk Management FUN! Humor Me

Fraud Risk Management

Quantitative Risk Analysis with Microsoft Project

ERM Benchmark Survey Report

Procedure for Address Business Risk and Opportunities

PROJECT SCENARIOS, BUDGETING & CONTINGENCY PLANNING

Introduction to Risk for Project Controls

Product Recall Risk Assessment By Tony Munns. Product recall is a key area of risk for today s company. With greater focus

Risk Management. CITS5501 Software Testing and Quality Assurance

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Frumkin, 2e Part 5: The Practice of Environmental Health. Chapter 29: Risk Assessment

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Enterprise Risk Management Integrated Framework

About the Risk Quantification of Technical Systems

Risk and Uncertainty Management Best Practices and Misapplications for Cost and Schedule Estimates SPE 97269

RISK MANAGEMENT MADE EASY. Susan Parente Project Management Symposium.

Desjardins Trust Inc. Financial Information and Information on Risk Management (unaudited)

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty?

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

A Study on Risk Analysis in Construction Project

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001

CRAVE. Cost Risk Assessment + Value Engineering. CSVA 2011 Conference Toronto, Ontario Nov 14-16, Ken L. Smith, PE, CVS

RISK M A N A G E M E N T P L A N

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Risk Management for Tunnel Planning, Design and Construction

GENERAL RISK CONTROL AND MANAGEMENT POLICY

Monte Carlo for selecting risk response strategies

Guidance Note: Stress Testing Credit Unions with Assets Greater than $500 million. May Ce document est également disponible en français.

ENTERPRISE RISK MANAGEMENT (ERM) The Conceptual Framework

Reliability Risk Analysis

Project Risk Management

Project Risk Management with

Condensed Interim Consolidated Financial Statements of. Canada Pension Plan Investment Board

USF System Compliance & Ethics Program. Risk Assessment Process. Enterprise-Wide Risk Assessment

A Framework for Risk Assessment in Egyptian Real Estate Projects using Fuzzy Approach

AMA Implementation: Where We Are and Outstanding Questions

Download slides on SEO Südwest

LCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP

QUANTITATIVE AND QUALITATIVE RISK ASSESSMENTS A HIGHLY NEGLECTED METHODOLOGY

M_o_R (2011) Foundation EN exam prep questions

Management Services Reviewer by Ma. Elenita Balatbat-Cabrera

UPDATED IAA EDUCATION SYLLABUS

Probabilistic Benefit Cost Ratio A Case Study

Risk Manage Manag ment men & the PMBOK John H. Dittmer, VI PMP, PMP CISSP CISSP ISSMP

TONY MILSOM Specialist Risk Engineering KPC

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568

1. Define risk. Which are the various types of risk?

DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK?

MINI GUIDE. Project risk analysis and management

Basel II, Pillar 3 Disclosure for Sun Life Financial Trust Inc.

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Risk Management Made Easy. I. S. Parente 1

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

MOUNTAIN PROVINCE DIAMONDS INC. Three and Nine Months Ended September 30, 2017 (Unaudited)

Wintrust Financial Corporation

Common Safety Methods CSM

Transcription:

Canadian Society of Value Analysis October 24, 2006 Risk Assessment of the Presented by: David Eden, P. Eng., Ontario Power Generation Susan Sherman, P.Eng.,URS Canada Inc Overview Qualitative Risk Analysis Quantitative Risk Analysis Case Study 1

Finding the Right Approach Qualitative versus quantitative risk analysis Establishing correct approach for the specific challenge Risk management tools for infrastructure projects Qualitative Risk Analysis Identify potential hazards facing the project For each hazard rate likelihood of occurrence (1 to 5) rate consequences (1 to 5) by category identify existing mitigation measures identify further mitigation measures Sort hazards into priority order Review and monitor throughout project 2

Qualitative Risk Analysis Identifies broad spectrum of hazards Focuses on what, who, and how of risk mitigation Used to prioritize risks Qualitative Risk Analysis High level qualitative risk register Basis for developing individual risk registers Focuses on managing risks Top risks reported to top management Risk Subregisters Developed from high level risk register Focus for detailed, real-time risk management Roll up into high level risk register 3

Qualitative Risk Analysis Recognized approach for tunnel projects Usually a prerequisite for obtaining insurance for tunnel construction Code of Practice for Risk Management of Tunnel Works, prepared for the Association of British Insurers (ABI) and the British Tunnelling Society (BTS) Qualitative Risk Analysis Strengths Tool for identifying and managing risks during a project or operation Focuses on prevention and responsibility rather than impacts Limitations Does not provide useful information for project costing and budgeting 4

Quantitative Risk Analysis Risk Identification and Strategy using QUantitative Evaluation Methods pioneered by Adrian Bowden of URS Business Risk Strategies Used to establish realistic estimates to cover the cost of unforeseen events Used to model uncertainty in all cost estimates Can be based on any unit Quantitative Risk Analysis Establish a list of risks (risk register) For each hazard estimate a probability of occurrence identify consequence(s) Use Monte Carlo methods to combine 5

Quantitative Risk Analysis Probability of Hazard X 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 0 1 Occurs (no/yes) 4% 3% 2% 1% 0% Delay Distribution 0 20 40 60 Delay (weeks) Quantitative Risk Analysis Risk Cost determined by two methods: Chance method straight probabilistic approach Threshold method includes full cost of risks above a set threshold 6

Quantitative Risk Analysis Probabilistic Costing Use to establish unexpected events portion of project contingency or reserve Establish a total risk-inclusive bid price Analyze bids for construction Compare different construction methods Able to integrate multiple variables in one analysis Quantitative Risk Analysis Probabilistic Costing Combined Probability Distribution of project cost and delay uncertainties Combine hazards using Monte Carlo simulation 80th percentile of resulting distribution typically used for project estimate 7

Quantitative Risk Analysis Strengths of Probabilistic Costing Strengths Provides a well-supported contingency amount for project budget purposes Supports benefit/cost analysis of options (e.g. different construction methods) Can be useful in analysis of bids Limitations Does not handle risks with very low probability (<5%) Quantitative Risk Analysis Threshold Method Establish risk threshold for the project Amount of impact acceptable in any given year without setting aside any special reserves Rank hazards by risk quotient Total Risk Cost is the sum of occurrence costs (not risk quotients) of risks that are higher than the risk threshold limit 8

Quantitative Risk Analysis Threshold Method Establish amount of money Corporation is prepared to spend on risk mitigation Use benefit / cost analysis to establish how to spend this money to best reduce Total Risk Cost Quantitative Risk Analysis Threshold Method Strengths Analyzes and manages ongoing risk Provides an estimate of Total Risk Cost that does not underestimate impacts Analyzes where risk mitigation budget should be spent to best advantage Includes high risk events, regardless of likelihood Limitations Not suitable for estimating project contingencies or cumulative delay 9

Case Study 1 Case Study 1 10

Case Study 1 Qualitative Risk Assessment Basis for detailed risk register Managing the project Insurance requirements Chance Method Risk Assessment Project budgeting Case Study 1 Expert Panel Consultant Team Risk Analysis consultant Technical consultants Expert Panel OPG project team staff OPG internal Risk Analysis group preliminary design/oversight consultants 11

Case Study 1 Subregisters Approvals and permitting Stakeholder issues Planning and conceptual design Financial and contractual Logistics and access Final design and construction Environmental issues Safety and security Case Study 1 Consequence Categories Financial Project schedule Corporate reputation Regulatory / legal Health and safety Environment 12

Case Study 1 Illustrative Qualitative Rating Scale Rating 1 2 3 4 5 Time Period 1-2 weeks 2-4 weeks 1-2 months 4-6 months 1-2 years Qualitative Risk Analysis 13

Case Study 1 Principles for Chance Method Analysis Seeded from qualitative risk register using likelihood ratings and consequence ratings Eliminated hazards that had no cost or schedule impact Expert Panel reviewed elements and ratings Quantitative Risk Register Case Study 1 Chance Method Risk Analysis Project delays Directly estimated as critical path delays (net of "float") Financial impacts Direct costs Economic losses, including delay impacts 14

Case Study 1 Financial Impact Estimate Cumulative Probability- 100% 80% 60% 40% 20% 0% Project Cost Uncertainty 80th percentile 0 60,000 Cost ($000's) Case Study 1 Delay Impact Estimate 100% Project Delay Uncertainty Cumulative Probability- 80% 60% 40% 20% 80th percentile 0% 0.00 100.00 Delay (weeks) 15

Case Study 1 Results Qualitative risk register to be used during construction for regular risk monitoring Used chance method to help set internal contingencies 16