1 Social Monitoring Report Semi-Annual Monitoring Report July December 2015 VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line Prepared by the Southern Vietnam Power Projects Management Board for the National Power Transmission Corporation and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

2 NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD Project Number: Period: Jul - Dec, 2015 SEMI-ANNUAL INTERNAL MONITORING REPORT ON IMPLEMENTATION OF RESETTLEMENT PLAN POWER TRANSMISSION INVESTMENT PROGRAM - TRANCHE 2 PROJECT: 220KV CAU BONG - DUC HOA TRANSMISSION LINE HO CHI MINH CITY, Jan 2016

3 Semi-annual Internal Monitoring Report - January 2016 ABBREVIATIONS ADB AP AH CARB CPC DMS DP DPC EVN GoV HH IOL LURC NPT PPC REMDF ROW RP SES SPPMB SPS USD VND Asian Development Bank (project) Affected Person (project) Affected Household Compensation, Assistance and Resettlement Board Commune People s Committee Detailed Measurement Survey Displaced Persons District People s Committee Vietnam Electricity Government Household Inventory of Losses Land Use Rights Certificate National Power Transmission Corporation Provincial Peoples Committee Resettlement and Ethnic Minority Development Framework Right of Way Resettlement Plan Socio-Economic Survey Southern Power Projects Management Board Safeguard Policy Statement United States Dollars Viet Nam Dong 220KV Cau Bong Duc Hoa transmission line i

4 Semi-annual Internal Monitoring Report - January 2016 TABLE OF CONTENTS PART I - INTRODUCTION... 1 I. PROJECT DESCRIPTION... 1 II. PROJECT IMPACTS... 2 III. PROGRESS OF THE PROJECT IMPLEMENTATION Progress of the Project Construction Progress of URP Implementation... 3 IV. SAFEGUARD POLICY AND HUMAN RESOURCES Project Policy and Compliance with Government s Regulations and ADB s Requirements Safeguards team... 7 PART II - IMPLEMENTATION OF SAFEGUARD POLICY... 9 I. PUBLIC CONSULTATION, PARTICIPATION, AND INFORMATION DISCLOSURE.. 9 II. DETAILED MEASUREMENT SURVEY AND ENTITLEMENT III. COMPENSATION PAYMENT AND ASSISTANCE Compensation Payment and Assistance for AHs Compensation Payment and Assistance for Relocated HHs Other Support for Severely AHs and Vulnerable Groups IV. LAND ACQUISITION V. ISSUE CONCERNING GENDER VI. GRIEVANCES REDRESS MECHANISM PART III - MONITORING I. INTERNAL MONITORING II. MONITORING THE COMPLIANCE OF RP IMPLEMENTATION PART IV - CONCLUSION AND RECOMMENDATION I. CONCLUSION AND RECOMMENDATION Conclusion Recommendation II. PLAN FOR THE NEXT PERIOD PART V - APPENDIX Appendix 1. Project Impacts Appendix 2. Progress on RP implementation Appendix 3. Project Entitlement Matrix Appendix 4. Public Information Booklet Appendix 5. Some pictures from Public Consultation Meetings Appendix 6. List of HHs who had received advance payments KV Cau Bong Duc Hoa transmission line ii

5 Semi-annual Internal Monitoring Report - January Appendix 7. Decision No 6763/QD-UBND dated December 10th, 2015 on approving coefficient adjusted compensation price for calculating compensation plan.. 42 LIST OF TABLES Table 1: Location of points... 1 Table 2: Project Impacts... 2 Table 3: Construction works up to January Table 4: URP implementation progress up to January Table 5: Amount of advance payment for HHs up to the end of fourth quarter of Table 6: Members of monitoring team... 8 Table 7: Dates of public consultations in the RP implementation progress... 9 Table 8: DMS implementation progress in affected communes Table 9: Status of compensation payment Table 10: Sumary of submitted internal monitoring report KV Cau Bong Duc Hoa transmission line iii

6 PART I - INTRODUCTION I. PROJECT DESCRIPTION 1. The Cau Bong - Duc Hoa 220 kv Transmission Line (TL) Project has a total length of km. It startes in Nhuan Duc Commune of Cu Chi District, Ho Chi Minh City and end in Duc Hoa Substation of Tan My Commune, Duc Hoa District, Long An Province. A double circuit connection is created among the Cau Bong 220kV Substation which was financed partly by the World Bank and the new substations at Cu Chi financed by the Ho Chi Minh Electricity Company and the Duc Hoa 220kV Substation in neighboring Long An Province (to be partly financed by JICA). The corresponding TL uses partly the right-of-way (ROW) of the existing 110kV Phu Hoa Dong - Trang Bang TL and partly the ROW of the 110kV Tan Phu Trung Industrial Park TL. These existing 100kV TLs would be dismantled on that section of the ROW used by the new Project and the corresponding 110kV circuits would be relocated on the new TL. Table 1: Location of points No. Starting ending point City/ Province District Commune Length (m) 1 G3.11-G4.1 Ho Chi Minh 2 G4.1-G4.1A Ho Chi Minh Nhuan Duc, Trung Lap Ha 125 1,163 3 G4.1A-G4.1B Ho Chi Minh Nhuan Duc G4.1B-G4.1C Ho Chi Minh G4.1C-G4.1D Ho Chi Minh Nhuan Duc, Trung Lap Ha 3,559 6 G4.1D-G4.2 Ho Chi Minh Cu Chi Trung Lap Ha G4.2-G4.3 Ho Chi Minh Phuoc Hiep 1,760 8 G4.3-G4.4 Ho Chi Minh 444 Phuoc Thanh 9 G4.4-G4.5 Ho Chi Minh G4.5-G4.6 Ho Chi Minh 1,145 Thai My 11 G4.6-G4.7 Ho Chi Minh 323 Subtotal , G4.7-G4.8 Long An 2, G4.8-G4.9 Long An 834 Duc Hoa Tan My 14 G4.9-DC Long An DC-220kV Long An 70 Subtotal ,296 TOTAL , Land would be required for the following based on the above technical requirements: (i) right-of-way; (ii) suspension towers; and, (iii) tension towers. No land is required for the earth grounding zone because this is a 220kV TL and subject to a range of conditions. Cau Bong - Duc Hoa 220kV Transmission Line Project 1

7 Houses and other physical structures need not be relocated outside what is termed in Decree 14/2014/NP-CP dated 26th February 2014, the power transmission safety corridor. However, they have to be earthed if metal structures also constitute a portion of the physical structure or fireproofed if made of combustible construction materials. II. PROJECT IMPACTS 3. Results of Detailed Measurement Survey (DMS) showed that the implementation of the Project would cause land restrictions and acquisition in six (06) communes, of which five (05) communes belong to Cu Chi District, Ho Chi Minh City namely Nhuan Duc, Phuoc Hiep, Trung Lap Ha, Phuoc Thanh and Thai My, and one (01) commune of Tan My belongs to Duc Hoa District, Long An Province. Table 2: Project Impacts Province District and commune Number of AH Number of affected institution Cu Chi District Nhuan Duc commune 50 Ho Chi Minh City Phuoc Hiep commune 5 Trung Lap Ha commune 92 1 Phuoc Thanh commune 89 Thai My commune 49 1 Long An Province Duc Hoa District 11 Tan My commune 11 Total There are 296 households (1,206 persons) and 02 organizations namely Trung Lap Ha CPC and Tam Tan Farm affected by the restrictions and land acquisition. The Project will affect 266,704.2 m² of land, of which 252,625.5 m² is covered in restriction on lands under the ROW and 14,077.7 m² of land is permanently acquired. The Project affects 89,289.1 m 2 of rice, 14,370.1 m 2 of other annual crops (maize, cucumber, cassava, etc.), 76,006 trees (including fruit trees, timbers, ornamental trees and shade trees). There are 16 houses of 14 AHs which are located under the ROW. 5. Of 296 HHs and 2 organizations affected by land acquisition, there are 87 HHs having only land affected, 193 HHs having land and crops and trees affected, 14 HHs having land, houses and other structures. 6. There are not any public facilities, historical and cultural structures affected by the project implementation. Cau Bong - Duc Hoa 220kV Transmission Line Project 2

8 III. PROGRESS OF THE PROJECT IMPLEMENTATION 3.1 Progress of the Project Construction 7. There are three contractors carrying out the construction for the Cau Bong - Duc Hoa 220kV TL project that are the Song Da Joint-venture 11; Song Da Co. Ltd. 11 Thang Long and IEC. 8. The construction works of the Cau Bong - Duc Hoa 220kV TL was commenced in December However, the construction works of the project have only been implemented when there were agreement of affected households from April As the construction and installation progress, up to the end of June 2015, the works carried out by the three contractors of Song Da Joint-venture 11; Song Da Co. Ltd. 11 Thang Long and IEC have been under the planned progress as table below. Table 3: Construction works up to January 2016 Item Activities Unit Design volume Construction volume Completion rate 1 Foundation excavation Tower foundation % 2 Foundation concretion Tower foundation % 3 Backfilling Tower foundation % 4 Grounding for tower Tower % 5 Tower erection Tower % 6 Cable stringing m % 9. Plan of compensation and support have been delayed in comparison with the site clearance and construction progress as well as overall plan of the project. However, to meet with the progress of the construction works, at almost all positions, the contractors and AHs have signed an agreement in which the contractor pays AHs in advance to support for their affected land and assets and get site handover for construction of tower foundation and stringing cable. 3.2 Progress of URP Implementation 10. Up to the end of third quarter of 2015, Duc Hoa DPC issued the Decisions No. 5555/QD-UBND, 5557/QD-UBND, 5558/QD-UBND, 5559/QD-UBND, 5560/QD-UBND dated June 30, 2014 and 139/QD-UBND dated January 15th, 2015 approving the Compensation Plan of the Cau Bong - Duc Hoa 220kV TL Project through Tan My commune. After that, Duc Hoa DPC issued continuously the decision No. 2339/QD-UBND dated April 24th, 2015 and decision No. 4576/QD-UBND dated May 3rd, 2015 approving additional the compensation plan of the Cau Bong Duc Hoa 220KV TL project through Tan My commune. Until the end of this quarter, all AHs (11/11AHs and 1/1 organization) have received fully compensation for affected assets with total amount of VND 618,726,408. In general, the compensation implementation in Duc Hoa district has been carried out completely. Cau Bong - Duc Hoa 220kV Transmission Line Project 3

9 11. Until the end of fourth quarter, In Cu Chi district, DMS have been carried out completely for 39/39 (49 households and 2 organizations) tower foundations and 531/531 compensation records of 272 affected households within ROW. 39/39 tower foundations were handed over ground for project construction. 12. To resolve issues of project construction, dated October 1st, 2015 chairman of Cu Chi DPC commanded DCSCC to establish negotiation group and calculate temporary compensation plan to pay in advance for AHs. 13. On November 23rd, 2015, Cu Chi DPC issued the document No. 9088/UBND- BTGPMB on requesting Ho Chi Minh City s for approving coefficient adjusted of compensation price for calculating compensation, allowance for affected assets of the 220KV Cau Bong Duc Hoa project. 14. On December 10th, 2015, Ho Chi Minh City People s Committee issued the Decision No. 6763/QD-UBND on approving coefficient adjusted of compensation price for calculating compensation, allowance for affected assets of the 220KV Cau Bong Duc Hoa project (See appendix). 15. December 24th, 2015, Compensation plan for AHs have been established completely by Cu Chi DCSCC. Currently, the compensation plan were announcing at the project communes. 16. Until end of fourth quarter, 42/50 AHs belong to Nhuan Duc commune, 79/92 AHs of Trung Lap Ha commune, 72/87 AHs of Phuoc Thanh commune, 05/05 AHs of Phuoc Hiep commune and 37/49 AHs of Thai My communes have been paid compensation in advance with amount of 27,024,037,946 VND by Cu Chi CARB. 17. SPMB has contracted No. 08/2015/HDTV dated July 27, 2015 with the Asian Pacific Consultancy Joint Stock Company for the service of independent monitoring. The independent monitoring agency conducted the first monitoring on August, For the Cau Bong - Duc Hoa 220kV TL, the Resettlement Plan is carried out following its steps conformed to the project s policy, and the progress of RP implementation is as table below. Table 4: URP implementation progress up to January 2016 RP Implementation Activities Ho Chi Minh City Cu Chi Dist. Long An Duc Hoa Dist. Nhuan Duc Phuoc Hiep Trung Lap Ha Phuoc Thanh Thai My Tan My Information Disclosure and Public Consultation 100% 100% 100% 100% 100% 100% Detailed Measurement Survey 100% 100% 100% 100% 100% 100% Preparing Compensation Plan 100% 100% 100% 100% 100% 100% Consulting and Counseling with 100% 100% 100% 100% 100% 100% Cau Bong - Duc Hoa 220kV Transmission Line Project 4

10 RP Implementation Activities Ho Chi Minh City Cu Chi Dist. Long An Duc Hoa Dist. Nhuan Duc Phuoc Hiep Trung Lap Ha Phuoc Thanh Thai My Tan My the APs on compensation plan Finalizing the Compensation Plan and submit for approval Compensation Plan verifying and approval 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 50% Compensation Payment 0% 0% 0% 0% 0% 100% Site Clearance 100% 100% 100% 100% 100% 100% Independent Monitoring First monitoring Table 5: Amount of advance payment for HHs up to the end of fourth quarter of 2015 District/commune Amount (VND) Note Cu Chi district 27,024,037,946.8 Nhuan Duc Phuoc Hiep Phuoc Thanh Trung Lap Ha Thai My 3,194,191,826 Advance payment 783,052,380 Advance payment 8,469,703,159 Advance payment 10,139,795,002 Advance payment 4,437,295,579 Advance payment Duc Hoa district 618,726,408 Tan My 618,726,408 Compensation payment has been done Total 27,642,764,354 IV. SAFEGUARD POLICY AND HUMAN RESOURCES 4.1 Project Policy and Compliance with Government s Regulations and ADB s Requirements 19. The NPT has reconciled the provisions from Safeguard Requirement 2: Involuntary Resettlement of the SPS 2009 and other cross-cutting policy themes of ADB, and the relevant laws of the GoV, from where the legal and policy framework for the compensation, resettlement and rehabilitation of DPs were formulated. The framework is consistent with the governing policies of the REMDF concurred by ADB and NPT that will be applied in all TL projects of the Power Transmission Investment Program. 20. The ADB Safeguard Policy Statement (2009) consolidates three existing safeguard policies: Involuntary Resettlement (IR), Indigenous Peoples (IP), and Environment. The Cau Bong - Duc Hoa 220kV Transmission Line Project 5

11 objectives of the IR policy are to: (i) avoid involuntary resettlement wherever possible; (ii) minimize involuntary resettlement by exploring project and design alternatives; (iii) enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and (iv) improve the standards of living of the displaced poor and other vulnerable groups. 21. To address the discrepancies between ADB Safeguard Policy and relevant GoV regulations, the project principles on resettlement policy are as follows: a. Meaningful consultations have been carried out with the APs and concerned groups and ensure participation from planning up to implementation. The comments and suggestions of the APs and communities have been taken into account; b. The RP is disclosed to APs in a form and language that understandable to them; c. Involuntary resettlement and impacts on land, structures and other fixed assets are avoided or minimized where possible; d. Compensation and assistance is based on the principle of replacement cost; e. Severely affected household is entitled when they are losing 10% or more of the household s productive land; f. Special assistance has been incorporated in the resettlement plan to protect socially and economically vulnerable groups such as households headed by women, children, disabled, the elderly, landless and people living below the provincial poverty line; g. Gender concerns are incorporated through RP implementation; h. Reporting and independent monitoring is defined as a part of the subproject management system. Periodically independent monitoring on implementation of RP has been implemented. 22. Since the 1 st July, 2014, the updated and amended compensation and resettlement policy of the Government of Vietnam had been entered into force which are applied in the implementation of the updated RP include: (i) The newly revised Land Law 2013 No.45/2013/QH13 dated November 29 th, 2013; (ii) (iii) (iv) (v) (vi) Decree No.43/2014/ND-CP dated May 15 th, 2014 guiding the implementation of the Land Law 2013; Decree No.44/2014/ND-CP dated May 15 th, 2014 regulating land price; Decree No.45/2014/ND-CP dated May 15 th, 2014 regulating collection of land use levy; Decree No.47/2014/ND-CP dated May 15 th, 2014 on compensation, assistance, rehabilitation and resettlement in the event of land recovery by the State. Decision No. 23/2015/QD-UBND dated May 15th, 2015 of Ho Chi Minh City PC on regulating for compensation, allowance and resettlement when the state recover land on the Ho Chi Minh City area. 23. Details of project policy for compensation and allowances are indicated in the Entitlement Matrix (see Appendix 3). Cau Bong - Duc Hoa 220kV Transmission Line Project 6

12 4.2 Safeguards team 24. Monitoring and evaluation the implementation of compensation and assistance activities is continuously conducted to ensure that activities have been carried out effectively and sufficiently as per the RP and mitigation measures of the project. 25. The NPT and the SPPMB have joint responsibilities in the internal monitoring of the RP implementation with results will be reported to ADB on quarterly basis. All activities in resettlement are time bounded and the progress of implementation will be obtained by SPPMB from the field on monthly basis and transmit them to the PICs for its assessment, and adjust the work program if necessary. The monthly internal monitoring reports will cover those related to performance indicating the measurement of input indicators against proposed timetable and budget including the provision and physical delivery of compensation, repair of houses and structures and assistance to APs, including grievance and redress, among others. 26. SPPMB had assigned a full-time team allocated from its Compensation Department for supervising and implementation of the RP. Compensation Department has assigned tasks to support the Director Board on the implementation of compensation, land clearance, resettlement and environmental impact assessment. It has a total number of 22 staff specializing in both resettlement and environment aspects. For this project, five persons are frequently involved in the assigned works. 27. In additionally, in June 2014 two consultants (resettlement and environment) were recruited and mobilized on intermittent basis to support the implementation of project s resettlement and environment safeguard policy (resettlement consultant had terminated the contract from early of Until early of June 2016, SPMB has signed contract with other consultant for replacing the former consultant). PICs closely work with safeguards team under SPPMB in the implementation of RP. The resettlement consultant has assisted SPPMB team to: (i) (ii) (iii) (iv) (v) Continue undertaking the consultation and disclosure programs. Ensure that options or agreements reached with affected people (APs) in terms of replacement of assets, i.e. cash or in-kind are provided in a timely manner. Establish and implement liaison mechanisms to ensure proper technical and logistical support to SPPMB and DCARBs, as well as procedures for a centralized resettlement and social management information system and internal monitoring. Assist in the implementation of all resettlement activities, and ensure that the terms of references are properly and effectively achieved. Review and assess grievance redress mechanism and ensure that the responsibilities, reporting requirements, and budget allocation to support the committee's functions are in place. Carry out on-the-job training on consultation and grievance mechanism strategies to SPMB, CARBs and mass organizations, so they will be able to provide correct and clear information and culturally appropriate support to affected persons. Cau Bong - Duc Hoa 220kV Transmission Line Project 7

13 (vi) Assist in the preparation of quarterly progress and internal monitoring reports to be submitted to NPT and then forwarded to ADB. Table 6: Members of monitoring team No. Name Position Responsibility 1 Mr. Nguyen Hai Dang Head, Dept. Compensation Overall management of RP implementation of the project 2 Mr. Le Tuan Anh 3 Mr. Phan Van Tranh 4 Mr. Le Trong Man Deputy head, Compensation Dept. Expert, Compensation Dept. Expert, Compensation Dept. Supervising and reporting the progress of RP implementation of the project Supervising and reporting the progress of RP implementation of two subprojects Supervising implementation of RP 5 Mr. Nguyen Huynh Duc Tuan Expert, Compensation Dept. Supervising implementation of RP Mr. Le Trung Thong has 6 been replaced by Mr. Nguyen Truong Thong Resettlement Consultant Support SPPMB in the implementation of resettlement safeguard policy from May 31 th, Mr. Duong Dinh Dung Environmental Consultant Support SPPMB in the implementation of environmental safeguard policy Cau Bong - Duc Hoa 220kV Transmission Line Project 8

14 PART II - IMPLEMENTATION OF SAFEGUARD POLICY I. PUBLIC CONSULTATION, PARTICIPATION, AND INFORMATION DISCLOSURE 28. The Project PIB was distributed to the AHs, in which the following information included (i) a brief background of the Project, especially the main works to be undertaken and the scale of land acquisition; (ii) impacts on land and on-land assets; (iii) the entitlements due to affected land and assets; (iv) detailed plan of implementation of compensation, assistance and resettlement payments and (v) grievance redress mechanism. 29. Information disclosure and public consultation have been implementing continuously by SPMB. From July 1st, 2015 to July 14th, 2015 SPMB cooperated with stakeholders organized public consultations, information disclosure are including: (i) (ii) (iii) (iv) (v) (vi) Announcing decision of land acquisition for each households. Scope of project, right-of-way, and location of towers: AHs and local authorities were informed and understood about the importance and necessity of the project, project scope, locations of tower foundations and the ROW going through the communes. The local people and authorities are all come to common consent and support to the implementation of the project that will contribute to the development of local socioeconomic condition and national power grid development as well. Scope of land acquisition; alternatives of land acquisition mitigation: The project will have two types of impacts: land acquisition for construction of tower foundations and land use restriction under ROW. Potential impacts (both positive and negative) of the land acquisition on affected households/community, on culture, religion, ethnicity, and on women: For almost of AHs the land acquisition made minor impacts on their livelihood and religion. Entitlements of affected households/community; gender and ethnic minority policies and strategies: The AHs were informed and understood about the current policies and regulations of the GoV, as well as Ho Chi Minh City and Long An Province People s Committee on compensation, support and resettlement, and their entitlements and obligations during the implementation of the project. Income restoration activities for severely affected households, and vulnerable groups: No severely AHs is in existence so income restoration activities are not required. (vii) Procedures and action plan for compensation payment, support and resettlement: The procedures and plan for the implementation payment for compensation, support and resettlement must be publicly disclosed to all AHs to know to strictly implement and monitor according to project policies and entitlements. (viii) Grievance redress mechanism: AHs were disclosed and understood about the procedures and steps of logging complaints and grievance redress mechanism by four steps based on the principles of publicity, democracy, protection of rights and interests of the APs. Table 7: Dates of public consultations in the RP implementation progress Cau Bong - Duc Hoa 220kV Transmission Line Project 9

15 Communes Dates of Consultations Number of Participants Total Male Female Nhuan Duc July 4 th, Phuoc Hiep July 5 th, Phuoc Thanh July 2 sd, Trung Lap Ha July 1 st, Thai My July 3 rd, Tan My April 14 th, Total After compensation plan was established completely by Cu Chi DSCC, it has been announced at project communes for AHs referred before submitted for approving. 30. Public meetings and village discussions with affected households and local officials were carried out in this stage of the implementation of resettlement plan. These activities will be continued to ensure that affected households concerns and grievances are addressed and resolved in a timely and satisfactory manner. Affected households are fully aware of their rights for grievance mechanisms about any aspects of the project and they can lodge their complaints at any time during the project implementation. II. DETAILED MEASUREMENT SURVEY AND ENTITLEMENT 31. Detailed Measurement Survey (DMS) has been carried out since May It is already completed in August 2014 and now on the process of reviewing the ownership of APs property and approval of compensation plan. During DMS, enumeration was conducted fully and exactly for all lost land and assets on land of the AHs and affected communities. The results of the numeration was publicly disclosed and posted on commune s office for AHs to recheck and complain for correction (if any). There is no complaint related to the results of the DMS before the established compensation plan. The detailed measurement survey progress described as below: 1) In Duc Hoa district: DCSCC have surveyed DMS for 11/11 AHs and 1 organization (100%). 2) In Cu Chi district: a) Foundation: DCSCC have surveyed DMS for 39/39 positions with 49/49 AHs and 02 organizations (100%). b) ROW: 531/531 compensation records of 272/272 HHs who affected under ROW have been surveyed completely (100%). 32. The DMS implementation with participation of many stakeholders such as: Represent of DCSCC, SPMB, head of villages, cadastral officer of affected commune, APs. 33. During DMS, enumeration was conducted fully and exactly for all lost land and assets on land of the AHs and affected communities. The results of the numeration was publicly disclosed and posted on commune s office for AHs to recheck and complain for correction (if Cau Bong - Duc Hoa 220kV Transmission Line Project 10

16 any). APs were announced schedule for DMS before and required attending, so almost of APs attended in detailed measurement survey progress. After DMS, APs rechecked their affected assets and signed on the DMS minutes. They were supplied a copy minutes of DMS for storing. So far, No households who has complained related to the results of the DMS. DMS progress described as table below. Table 8: DMS implementation progress in affected communes District Commune Detailed Measurement Survey Starting date Finishing date Nhuan Duc 15/6/ /6/2014 Phuoc Hiep 15/6/ /6/2014 Cu Chi Phuoc Thanh 15/6/ /6/2014 Trung Lap Ha 15/6/ /6/2014 Thai My 15/6/ /6/2014 Duc Hoa Tan My 15/6/ /6/ Price survey and appraisal: Cu Chi district CARB and SPMB cooperated with price appraisal consultant for surveying affected assets price. On November 23th, 2015, Cu Chi DPC issued the document No. 9088/UBND-BTGPMB on requesting Ho Chi Minh City s for approving coefficient adjusted of compensation price for calculating compensation, allowance for affected assets of the 220KV Cau Bong Duc Hoa project. On December 10th, 2015, Ho Chi Minh City People s Committee issued the Decision No. 6763/QD-UBND on approving coefficient adjusted of compensation price for calculating compensation, allowance for affected assets of the 220KV Cau Bong Duc Hoa project 35. On December 24th, 2015, Compensation plan for AHs have been established completely by Cu Chi DCSCC. Currently, the compensation plan was announcing at the project communes. 36. Restoration of APs income. Severely affected households according to project policy will receive full assistances such as living stabilization assistance, occupation conversion assistance, and business stabilization assistance. Assistance in cash will be paid along with other compensation payments. So far, there are no AHs entitled as severely affected household. 37. The project policy recognizes specific group of AHs as vulnerable which includes (i) female headed households without support; (ii) disabled household heads; (iii) poor households; (iv) children and the elderly headed households who are landless and with no other means of support; (v) landless households; and (vi) ethnic minorities. According to Ho Chi Minh City regulations on the poor, none of AHs was considered as vulnerable as poor HH. No household shall become vulnerable due to the land acquisition of the Project. III. COMPENSATION PAYMENT AND ASSISTANCE 1.1 Compensation Payment and Assistance for AHs 38. In Duc Hoa District: Up to the last of third quarter of 2015, Duc Hoa DPC issued the Decisions No. 5555/QD-UBND, 5557/QD-UBND, 5558/QD-UBND, 5559/QD-UBND, Cau Bong - Duc Hoa 220kV Transmission Line Project 11

17 5560/QD-UBND dated June 30, 2014 and 139/QD-UBND dated January 15th, 2015 approving the Compensation Plan of the Cau Bong - Duc Hoa 220kV TL Project through Tan My commune. After that, Duc Hoa DPC issued continuously the decision No. 2339/QD- UBND dated April 24th, 2015 and decision No. 4576/QD-UBND dated May 3rd, 2015 approving additional the compensation plan of the Cau Bong Duc Hoa 220KV TL project through Tan My commune. Until the end of this quarter, all AHs (11/11AHs and 1/1 organization) have received fully compensation for affected assets with total amount of VND 618,726,408. In general, the compensation implementation in Duc Hoa district has been carried out completely. 39. In Cu Chi District: Until the end of fourth quarter, 42/50 AHs belong to Nhuan Duc commune, 79/92 AHs of Trung Lap Ha commune, 72/87 AHs of Phuoc Thanh commune, 05/05 AHs of Phuoc Hiep commune and 37/49 AHs of Thai My communes have been paid compensation in advance with amount of 27,024,037,946 VND by Cu Chi CARB. Until now, 54/285 AHs have not received compensation in advance, however they have handed over ground to the contractor for stringing cable. They were waiting until the compensation plan approved and paid for fully affected assets. Status of compensation payment described in Table 9. Commune Table 9: Status of compensation payment Amount of advance payment (VND) Total of HHs Have received Handed over ground Thai My 4,437,295, Phuoc Thanh 8,469,703, Phuoc Hiep 783,052, Trung Lap Ha 10,139,795, Nhuan Đuc 3,194,191, Total 27,024,037, Compensation Payment and Assistance for Relocated HHs 40. No one needs to be relocated due to the project implementation. 1.3 Other Support for Severely AHs and Vulnerable Groups 41. DMS found that there is not any AH entitled as severely or vulnerable groups. IV. LAND ACQUISITION 42. The results of the DMS indicated that there is no AP has to be relocated. Since the updated RP have been approved, the land acquisition activities are implemented based on agreement between AHs and contractors for handing over land in advance for tower foundation construction. AHs were paid compensation in advance and land handed over to contractors. 43. Up to the end of the 4th quarter, in Duc Hoa district, there are 4/4 tower positions handed over to the contractor. In Cu Chi district, although compensation plans have not been approved yet, all land areas acquired for tower construction have been handed over to the contractors for tower construction. There are 39/39 tower positions handed over to the Cau Bong - Duc Hoa 220kV Transmission Line Project 12

18 contractor for tower construction. Additionally, all affected households in both location have handed over ground to the contractor for cable stringing. 44. From November, 2015 until present, SPMB, Cu Chi district and contractor have cooperated closely together for paying compensation in advance for AHs and negotiating with AHs allow constructing before compensation payment. Almost AHs agreed and allowed the contractors to constructe. V. ISSUE CONCERNING GENDER 2. The results of the DMS found that more than 30% headed households are female for both TL projects. Women play an important role in implementation of RP as they have actively participated in decision making of their household and community, as well as the supervision of the project implementation activities. Women involve not only in domestic works but also in income generation and local associations activities. 3. Women are encouraged to participate in all project activities and play higher role in making family and community important decisions. Especially, during the process of public consultations with the APs, female APs are encouraged to raise their voice, actively engage in and fulfill their rights to be free and prior informed, involve in discussion and making decision, and monitoring and evaluation of all project activities. 4. To enhance the active participation of women and reduce the impact of land acquisition and clearance process on women in the project area, a gender strategy during the preparation and implementation of resettlement plan is necessary. The organization of public consultation to ensure men and women are engaged and listening to their opinions fully, the consultations ensure at least 30% women participants. In order to implement this objective, the consultation meeting should coordinate with locality and districts Women Union to organize the meeting such as invitation and arrange a suitable time for women to avoid the busy times such as family cooking, picking up the child/children...). 5. The gender Strategy is to help the AHs including both men and women participate in the implementation of RP and benefit distributed equitably between men and women from achievements of that development. The gender strategy in the stage of implementation of the RP includes the following: - Mobilize the participation of the women's unions in DCSCCs: DCSCC must include at least a representative of women of affected households. In this quarter, Districts are consolidating the district compensation and site clearance council. This work is to ensure that woman who participate in all activities of RP implementation. - Poor female headed households are vulnerable people so they need more assistant from the project: Strategy of disseminating Project s information to the community focused on them. They have been invited to participate in all public consultation meeting for disseminating Project's information; - Both men and women are encouraged to participate in DMS. They participated in DMS and spoke out their opinions about the implementation process of detail measurement survey; Cau Bong - Duc Hoa 220kV Transmission Line Project 13

19 - The Project have been working closely with the district women's unions, ward/commune women's unions to mobilize the participation of women in all activities of RP implementation (public consultation through questionnaires, people s meetings...). They raised concern issues of women to implementation process of compensation, allowance, resettlement and site clearance. Thence, they suggests solutions to redress these issues ensure women s benefits in all activities of RP implementation; - Women have invited to partipate in all public meetings and must ensure at least 30% of the participants as women. So far, in almost public meeting women have partipated and spoken out their opinions. Participation rates of women in public meetings described in Table 5; - The payment of compensation and assistance in cash will be given to the affected households in the presence of both husbands and wives; In case, husbands or wives absent, the compensation payment only is carried out when husbands/wives receive compensation have to have proxy letter of others and have confirmation of local authorities. - LURCs which are newly granted should be named both husbands and wives. VI. GRIEVANCES REDRESS MECHANISM 45. During the information disclosure and public consultation campaign, the resettlement consultant and SPMB disclosed to the AHs for them to understand about the procedures and steps of logging complaints and grievance redress mechanism by four steps based on the principles of publicity, democracy, protection of rights and interests of the APs. 46. Up to the end of first quarter, There are some AHs complain about some issues including: (1) Request additional compensation for affected structures or outside the transmission line; (2) Complain compensation price for trees, structures; (3) Allowance for vocational training and job creation; and (4) Requesting acquisitions for all land which has the remaining land small, bizarre shapes. To redress these issues, Cu Chi DPC has organized meeting for resolving. Mr. Nguyen Viet Dung has concluded to agree on additional compensation for those HHs at document No. 166/TB-VP dated June 3rd, 2015 (please reference appendix). This content has been mentioned in the previous report, so that this report will not be mentioned again. 6. Also in the first quarter, there are some HHs who have oral complaint about some issues as below: (i) (ii) The amount of money for temporary borrowing the land for construction (access road to tower location, excavated area) paid unevenly among AHs with the same affected area, type of land, crops and trees that resulted to compare enviously. For this case, SPMB right after this with the every individual AHs will work with contractors at the site to solve the issue. If any, contractors are requested to do land refill and other actions to ensure land is cultivable. Temporary impacts during the construction (on land, crops and trees) some cases did not compensated adequately by the contractors. Moreover, the restoration of land condition in some tower points did not strictly undertaken that caused difficulties for the AHs to restore their land condition or should take long time. For this case, SPMB Cau Bong - Duc Hoa 220kV Transmission Line Project 14

20 right after this with the every individual AHs will work with contractors at the site to solve the issue. Contractors should negotiate with AHs for agreed solutions. 47. The above-mentioned issues were answered by consultants and SPMB, while agreed with the APs about the work-plan for four parties (SPMB, contractors, CPC and AHs) to strictly resolve APs concerns and requirements. 48. Currently, there are no AHs who have complained compensation process. Cau Bong - Duc Hoa 220kV Transmission Line Project 15

21 PART III - MONITORING I. INTERNAL MONITORING 49. The SPPMB conducts internal monitoring of RP implementation and results of the internal monitoring are reported on quarterly basis to NPT and ADB. Internal monitoring activities are periodically carried out by SPPMB staffs to ensure the implementation of RP is on the right direction and any problems/issues that may be occurred, including complaints of the AHs shall be timely resolved. 50. The semi-annual monitoring report is prepared summarizing all activities relevant to the implementation of RP done during the six month period in compliance with the ADB requirements. This report incorporated monitoring results for the period from January to June 2015 to report the situation has been implemented and tasks taken to improve the situation, where needed. Related information has been collected monthly from the field to assess the progress of RP implementation and then consolidated. 51. SPPMB s consultant has periodically conducted field visits to project affected communes. Field surveys carried out during this period to (i) collect information on the opinions and the needs of AHs regarding the policy of the project; (ii) support in implementation of public consultation and information disclosure; (iii) collect and review grievance redress; (iv) coordinate with contractors of construction to ensure that allowance for temporary affected assets due to construction work is taken into account. Working with stakeholders such as CPCs, DCARBs, mass organizations, and in-depth interviewing APs has been applied to achieve the monitoring target. 52. Summary of submitted report on internal monitoring such as below: Table 10: Sumary of submitted internal monitoring report No. Type of report Status of submission I Quarter report 1 The third quarter, 2014 Submitted 2 The fourth quarter, 2014 Submitted 3 The first quarter, 2015 Submitted 4 The second quarter, 2015 Submitted 5 The third quarter, 2015 Submitted 6 The fourth quarter, 2015 Submitted II Semi-annual report 1 The semi report of 6 months early of 2015 Submitted 2 The semi report of 6 months end of 2015 Being submitted II. MONITORING THE COMPLIANCE OF RP IMPLEMENTATION 53. In addition to the internal monitoring taken by the SPPMB, it is always required to have a different objective information channel independently. The key objective of external Cau Bong - Duc Hoa 220kV Transmission Line Project 16

22 monitoring is to determine whether NPT/SPPMBs efforts on RP implementation have been properly conceived and executed consistent with the agreed actions in the RP. The external monitoring will verify in the filled-up DMS questionnaire and asset compensation forms (ACF) that all affected losses of APs, have been satisfactorily compensated and rehabilitation and transition assistance have been provided with. It will also ascertain whether the entitlements were adequate in meeting the objectives, and whether the objectives were suited to APs. 54. SPMB has contracted No. 08/2015/HDTV dated July 27, 2015 with the Asian Pacific Consultancy Joint Stock Company for the service of independent monitoring. The independent monitoring agency conducted the first monitoring on August, Cau Bong - Duc Hoa 220kV Transmission Line Project 17

23 PART IV - CONCLUSION AND RECOMMENDATION I. CONCLUSION AND RECOMMENDATION 1.1 Conclusion 55. In general, compensation implementation has done completely in Duc Hoa district. The compensation plan was approved by Duc Hoa DPC for 11 AHs and 1 organization. Until present, all AHs and organization have received compensation and handed over ground for project construction with total amount of 618,726,408 VND. 56. In Cu Chi district, the DMS has been completed. The district s division of natural resources and environment has determined completely the legal ownership, reviewing the origin of land title and relevant legal documents for formulating the compensation plan. 57. Until end of this quarter, Cu Chi CARB has paid in advance for 42/50 AHs belong to Nhuan Duc commune, 77/92 AHs of Trung Lap Ha commune, 72/87 AHs of Phuoc Thanh commune, 05/05 AHs of Phuoc Hiep commune and 35/49 AHs of Thai My with amount of 27,024,027,946 VND. 58. At the present, there are no complaint HHs. However some HHs have oral complaints on requesting for establishing temporary compensation plan and paying in advance for AHs. These issues were answered by Cu Chi DCSCC. 59. Until the end of 4th quarter of 2015, the 220KV Cau Bong Duc Hoa transmission line project has been put in operation. The compensation payment were been implementing by Cu Chi DCSCC, it expected completely in the first quarter of Recommendation 60. In order for the work of compensation, support and resettlement for the APs of the project to complete timely and efficiently, it is recommended that: (i) (ii) Present, The Cau Bong Duc Hoa 220KV TL has been put in operation but the compensation, support plan has not been approved for AHs at Cu Chi district. Therefore, to ensure the compensation payment will be carried out for all AHs soonest, Cu Chi district CARB should approve the compensation support plan as soon as possible. To avoid complaint of AHs, SPPMB should cooperate with Cu Chi DCSCC pay compensation for all AHs as soon as the compensation plan approved. II. PLAN FOR THE NEXT PERIOD 61. Compensation plans need to be reviewed as soon as be approved by local authorities for all AHs. Compensation payment should be paid soon. 62. Information dissemination, community consultations will be continuously conducted by consultant, SPPMB, DCSCC along with communes to ensure timely inform to APs about project implementation activities and resolve any complaints raised. Cau Bong - Duc Hoa 220kV Transmission Line Project 18

24 PART V - APPENDIX 5.1 Appendix 1. Project Impacts Affected land by provinces of Cau Bong - Duc Hoa 220kV TL Category of land Cu Chi (Ho Chi Minh City) Acquired Land in land (m 2 ) ROW (m 2 Total (m 2 ) ) Duc Hoa (Long An Province) Acquired Land in land (m 2 ) ROW (m 2 Total (m 2 ) ) Annual crop land 7, , , , ,697.9 Perennial tree land , ,963.2 Residential land Forest land 1, ,218.4 Garden land 4, ,261.0 Unused land , ,847.8 Public land , ,522.0 Total 11, , , , , ,249.3 Cau Bong - Duc Hoa 220kV Transmission Line Project 19

25 5.2 Appendix 2. Progress on RP implementation Status of compensation plan till January 2015 Province District Commune Project information dissemination Detailed Measurement Survey Making compensation plan Verify and approve the compensation plan Compensation payment Starting Finishing Starting Finishing Starting Finishing Submittin Date of Starting Finishing date date date date date date g date approval date date Nhuan Duc 28/11/ /11/ /6/ /6/ /9/ /12/2015 Not yet Not yet Not yet Not yet Ho Chi Minh city Cu Chi Phuoc Hiep 29/11/ /11/ /6/ /6/ /9/ /12/2015 Not yet Not yet Not yet Not yet Trung Lap Ha 28/11/ /11/ /6/ /6/ /9/ /12/2015 Not yet Not yet Not yet Not yet Phuoc Thanh 29/11/ /11/ /6/ /6/ /9/ /12/2015 Not yet Not yet Not yet Not yet Thai My 29/5/ /5/ /6/ /6/ /9/ /12/2015 Not yet Not yet Not yet Not yet Long An Duc Hoa Tan My 28/11/ /11/ /6/ /6/ /5/ /5/2014 5/6/ /6/2014 5/7/ /7/2015 Cau Bong - Duc Hoa 220kV Transmission Line Project 20

26 5.3 Appendix 3. Project Entitlement Matrix No. Type of Loss/Impacts Level of Impacts Eligible Persons Entitlements Implementation Issues I. LAND I.1. Agricultural Land 1 Productive Land Partially Owners with LURC, a. Cash compensation for acquired land at + AHs to be notified at least 90 days (for permanently acquired affected (less or in the process of replacement cost at current market rates for agricultural land) and 180 days (for non- than 10% of acquiring LURC and affected portion; agricultural land) prior to land acquisition the total productive land holding) owners eligible to acquire LURC according to Government policies b. Entitled to allowance for vocational trainings career change and job seeking in cash not exceed 5 times of the affected land value. (Land Law Article 67). + Full payment for AHs at least one (01) month before site clearance. (60 HHs) 2 Restrictions on land Partially All AHs have a. No compensation for land; + SPPMB and DCARB guide the AHs to use in ROW and/or totally affected productive land in ROW (292 HHs) b. Compensation for trees and other crops at market prices; c. Support for restrictions on land use on the productive land plots adjacent to residential land; support level is not higher than 80% of the same land type s price. AHs can still use land for production but they are not allowed to use land in ROW, ensuring safety for people and construction, consistent with the Decree No.14/2014/ND-CP. + Affected land in ROW will be rehabilitated by contractors after the Project construction and land in ROW could be used with the restricted purposes. grow plant higher than 4 m. + AHs can be required to cut affected trees, timbers. The Project will pay for the cutting. 3 Temporary impacts Temporary Users of affected For land area to be temporarily used during + Land characters and quality must be loss of land land (to be construction stage: (i) rental in cash which will restored before returning to the AHs; and assets on land determined Project during be no less than the net income that would have been derived from the affected property during disruption; (ii) restoration of the land + If the quality of land will be radically changed when returning to the AHs, Cau Bong - Duc Hoa 220kV Transmission Line Project 21

27 No. Type of Loss/Impacts Level of Impacts Eligible Persons Entitlements Implementation Issues implementation) within one (01) month after use; compensation is paid at full replacement cost or land for land compensation if contractor fails to restore the affected land within one (01) month after the use (agreement between parties will be monitored by external monitoring agency). requiring the AHs to change the land use purpose, then the AHs should be compensated for all envisaged cost of losses. + Contracts with the contractors should include an article regulating specifically the responsibilities of the contractors. I.2. Residential Land and/or Non-agricultural Land (e.g. commercial purpose) 1 Residential Land Partially All AHs have a. No compensation for land; Affected land in ROW will be rehabilitated and/or Nonagricultural Land in ROW and/or totally affected residential and/or non-agricultural land in ROW (7HHs) b. Allowance for purchasing fireproof materials and lightning arrestors for the existing house/structure or cash compensation at by contractors after the project construction and land in ROW could be used with the restricted purposes. replacement cost of affected house/structure; c. Support for utilization of restricted land. II. MAIN HOUSES AND OTHER STRUCTURES IN ROW II.1. Main houses 1 Main houses affected Partially Owners of the Retain houses according to the conditions The technical norms for partially or fully affected houses with or regulated by Article 13 of Decree affected house will be determined by the (affected area without acceptable No.14/2014/ND-CP, and Cash compensation DCARB with the technical assistance from less than 50% proof of ownership for directly affected parts of the houses at the District or Provincial Construction of total land over the land; with replacement cost and cost for dismantling the Department and concurred by the PDP area without or without building affected parts. during the DMS. any impact to the remaining structures of permit (14 HHs) + The calculation of rates will be based on the actual affected area and not the useable area. Cau Bong - Duc Hoa 220kV Transmission Line Project 22

28 No. Type of Loss/Impacts Level of Impacts Eligible Persons Entitlements Implementation Issues the house II.2. Other structures 1 Secondary Structures Structures lost All AHs have a. Cash compensation for the entire affected The calculation of rates will be based on (kitchen, latrines, and/or structures in ROW structures will be provided at 100% of the full the actual affected area and not the bathrooms, wells, damaged due (22 HHs) replacement cost for materials and labor, useable area. animal shelters, to location in without provision for deduction of depreciation fences, etc.) ROW or salvage value of construction materials, whether or not they have title to the affected land or permit to build the affected structure. The amount will be sufficient to rebuild a structure the same as the former one at current market prices; b. Provision of allowance for the installation of fireproofing materials and lightning arrestors. III. ON-LAND AFFECTED CROPS AND TREES 1 Annual crops (paddy Crops lost Owners regardless If standing crops are ripening and cannot be + APs have the right to use salvable trees. and other annual crops) and/or damaged due to location in ROW of tenure status harvested, cash compensation at replacement cost equivalent to the highest production of crop over the last three years multiplied by current market value of crops at the time of compensation. + APs will be given three (03) months notice in advance regarding evacuation so that the land on which their crops are planted will be recovered and that they must harvest their crops on time. 2 Trees and timbers Trees lost Owners regardless Cash compensation at replacement cost is + Compensation must equal in value to (fruit trees, timbers, and/or of tenure status equivalent to current market value given the trees that would be harvested had wood trees, etc.) damaged due type, diameter at breast height, age and acquisition not occurred. to location in productive value at the time of compensation. + APs will be given notice at least three Cau Bong - Duc Hoa 220kV Transmission Line Project 23

29 No. Type of Loss/Impacts Level of Impacts Eligible Persons Entitlements Implementation Issues ROW (03) months in advance regarding evacuation. Trees grown after issuance of the deadline will not be compensated. + AHs can be required to cut affected trees, timbers. The Project will pay for the cutting. IV. REHABILITATION ASSISTANCE IV.1. Allowance for Vocational Training, Career Change and Job Seeking 1 Households having Affected and All AHs with Assistance for vocational training, career agricultural land loss of land agricultural land change and job seeking: affected permanently acquired (290 HHs) + Cash compensation equal to 1.5 to 5 times of compensation value for affected land according to PPC s regulation. + If the AP has demand for training, he/she will be entitled to participate in a training course for free. IV.2. Allowances for houses in ROW 1 Assistance to improve Houses AHs with houses in + With houses Grade 4, allowance for At time of compensation, allowance will be house or install fire- partially or ROW (15HHs) installing fireproof materials and lightning adjusted for inflation to ensure that APs can proof materials and fully affected arrestors. do the improvement in safe manners. lightning arrestors, and assistance to mitigate impacts due to restricted usage and impacts on daily + With houses Grade 5, allowance for improvement. + Allowance due to restricted usage and impacts on daily-life activities. life activities Cau Bong - Duc Hoa 220kV Transmission Line Project 24

30 No. Type of Loss/Impacts Level of Impacts Eligible Persons Entitlements Implementation Issues V.5. Allowances for other structures in ROW 1 Assistance to improve Other AHs with other + With houses Grade 4, allowance for At time of compensation, allowance will be or install fireproof structures structures in ROW installing fireproof materials and lightning adjusted for inflation to ensure that APs can materials and partially or arrestors. do the improvement in safe manners. lightning arrestors fully affected + With houses Grade 5, allowance for improvement. V.6. Other Allowances 1 Loss of land and non- Affected households Every relocating AP will be provided with a Based on the actual situation of the locality, land assets whose houses will lump-sum one time allowance package to the PPC Chairman issues other allowances be relocated from cover the cost of domestic water, power and (according to the Article 23 in the Decree the ROW telephone connections at the new site as per No. 69/2009/ND-CP) to ensure PPC s decision at payment time but it is not accommodations, life stabilization and less than 3.5 million VND per household. production for DPs. Special cases have to be submitted to the Prime Minister for approval. VI. Incentive Bonus Loss of land and non- All AHs If APs hand over the affected land immediately land assets after receiving compensation and allowances will be awarded an incentive bonus of VND 5,000,000 as per regulations of the PPC Cau Bong - Duc Hoa 220kV Transmission Line Project 25

31 5.4 Appendix 4. Public Information Booklet National Power Transmission Corporation (NPT) Southern Vietnam Power Projects Management Board (SPPMB) Ho Chi Minh City/Long An Province People s Committees Cu Chi/Duc Hoa District People s Committees Cu Chi/Duc Hoa District Compensation and Resettlement Boards (DCARBs) Public Information Booklet Cau Bong - Duc Hoa 220kV Transmission Line Project I. PROJECT INTRODUCTION The two Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project and Cau Bong - Duc Hoa 220 kv Transmission Line Project are for Tranche 2 of the Power Transmission Investment Program of the Government of Vietnam (GOV). The Projects under the Program are designed to: (i) improve system stability and security, and improve the reliability of power supply in Southern Viet Nam; and (ii) enable evacuation of electricity to load centres from the both the planned public sector and private sector financed thermal power plants in southern Viet Nam. The Projects shall be financed through the Multi-Financing Facility (MFF) of Asian Development Bank (ADB). The National Power Transmission Corporation (NPT) is the Project executing agency (EA) while the Southern Vietnam Power Projects Management Board (SPPMB) is the implementing agency (IA). 1. Project Description The Cau Bong - Duc Hoa 220kV Transmission Line Project is designed to supply to 220kV Duc Hoa Substation to ensure reliable electricity supply to industrical zones in districts of Duc Hoa and Duc Hue, Long An Province and to load centres in the Northwest of Ho Chi Minh City, contribute to strenthening the connectivity capacity for power network of the region. The Cau Bong - Duc Hoa 220 kv Transmission Line Project has a total length of km, with total 43 towers, that will traverse to four communes of Ho Chi Minh city and Long An Province. Of which, 39 towers will traverse to five communes of Thai My, Nhuan Duc, Trung Lap Ha, Phuoc Thanh and Phuoc Hiep of Cu Chi District, Ho Chi Minh City and 4 towers will traverse Tan My commune of Duc Hoa District, Long An Province. Land will be required for the: (i) right-of-way; (ii) earth grounding zone; (iii) optical repeater systems; (iv) suspension towers; and (v) tension towers. 2. Scope of Land Acquisition and Resettlement The rights-of-way (ROWs) for Cau Bong - Duc Hoa Transmission Line Project shall require a total are 253,860.3 m² of land, of which 240,030.6 m² is covered in restriction on lands under the ROW and 13,830.7 m² of land is permanently acquired for permanent use of 43 suspension and tension towers. Cau Bong - Duc Hoa 220kV Transmission Line Project 26

32 The Project will impact on total of 290 affected household (AHs) who own the following affected properties: (i) 15 houses due to height limit under the ROW, (ii) 76,006 trees due to the clearing of ROWs. The AHs consist of 290 Ahs and two organizations. The affected households all belong to the mainstream society of Vietnam. No ethnic minority group shall be affected under the Subproject. II. INFORMATION REGARDING PROJECT COMPENSATION AND RESETTLEMENT POLICIES AND REGULATIONS Question 1: What is the Cau Bong - Duc hoa 220kV Transmission Lines Project? Answer: The Cau Bong - Duc Hoa 220kV Transmission Line Project is designed to supply to 220kV Duc Hoa Substation to ensure reliable electricity supply to industrical zones in districts of Duc Hoa and Duc Hue belong to Long An Province and to load centres in the Northwest of Ho Chi Minh City, contribute to strenthening the connectivity capacity for power network of the region. The Cau Bong - Duc Hoa 220kV Transmission Line Project has a total length of 13.42km, starting from G anchor tower turning from 220kV Cau Bong - Cu Chi Transmission Line to 220kV Cu Chi Substation and turn to Duc Hoa and ending at 220/110kV Duc Hoa Substation (Long An Province). Question 2: How will the Cau Bong - Duc Hoa 220kV Transmission Line Project affect the local population? Answer: The Project will cause the following effects: (i) Buildings and other structures and buildings on land lost permanently; (ii) Trees are cut off on the land affected permanently; and (iii) Reduction of the use of land, buildings / infrastructure in the safety corridor of high-voltage grid (ROW). Question 3: What is the main objective of the Project Resettlement Plan? Answer: The main objective of this Resettlement Plan is to ensure that all APs will be restored their socio-economic conditions at least equal to or better than they would have been in the absence of the Project. Poor households, difficult condition households and other vulnerable households (women-headed, eldly-, children-, disable person-headed, under-policy-assisted households) will be supported rehabilitating their socio-economic conditions equal to or better than prior Project conditions. Question 4: What if my land is affected by the Project? Answer: The affected land will be compensated for replacement land (if land fund available) OR in cash at replacement value at current market rates at the time of compensation. All affected households and local authorities will participate in replacement cost survey. If the leased land is recovered, compensation will not be made for the land but the investment costs in land. Question 5: Do we need to have a land title in the order to be compensated? Answer: No, lack of formal legal rights to land does not prevent any APs from receiving compensation or allowances and/or rehabilitation assistances. Those APs who possess a land use rights certificate (LURC) or any other form of written or verbal agreement to utilize the land are entitled to compensation for the lost land as well as assets on the land. Those APs who do not Cau Bong - Duc Hoa 220kV Transmission Line Project 27

33 have legal/legalizable or temporary/lease rights for land will still be compensated for the assets on the land, such as any structures, crops and trees. Question 6: Is the compensation applied for affected houses and structures? Answer: Yes. Compensation will be applied for all affected assets including houses, shops and other structures (kitchen, bathroom, toilet, well, livestock cages, fence, etc.) as well as other fixed assets at replacement value at current market prices (including materials and labour) without any deductions for building depreciation or salvageable building materials. This will ensure that APs are able to reconstruct their houses and other structures with better or at least the same quality as in the absence of the Project. Question 7: What about affected crops and trees? Answer: Affected crops, fruit and timber trees and tree fences will be compensated in cash at current market prices. Compensation for non-harvested crops will be based on the average production in the past 3 years multiplied by current market prices. Compensation for trees will be based on the type, age and productivity of trees. Question 8: In addition to compensation, how will the Project support us? Answer: In addition to compensation for affected land and asset as per Project policy, the Project will provide rehabilitation assistances to eligible APs to ensure that their living standard is restored or improved at least equal to or better than their pre-project level. Rehabilitation assistances for eligible APs include: Severely affected households: Households that lose 10% or more of their total productive land will receive rehabilitation assistances include (i) life stabilization assistance (ii) income restoration assistance such as agriculture extension assistance for better use of the remaining land area, participating in credit access programs or recruitment related to the Project. The assistances are presented in the Entitlement Matrix. Relocated households: Affected people who must be relocated have rights to get: (1) transition assistance; (2) life stabilization assistance for transitional period; and (3) assistance for house rental at replacement cost. The assistances are presented in the Entitlement Matrix. Business owners that lose income while they relocate or rebuild their shops/businesses: Households with small, unregistered businesses will receive cash compensation equal to the provincial minimum wage for 3 months. Owners of registered businesses will receive cash assistance due to loss of income equivalent to 30% taxable income in a year. Annual taxable turnover average is determined on the basis of financial statements of three years ago. Employees and hired laborers who lose their jobs: will receive cash compensation for lost salary/wages for each month they cannot work, if the loss is temporary; or, if the loss is permanent, cash compensation equivalent to the provincial minimum wage for 6 months or cash compensation for remaining contract period whichever is higher. Allowance for changing job: the affected households either have or not have registered certificate on their residential land that after relocation but they could not be continued, the person in working age who belonged to the affected households will be participated in the free Cau Bong - Duc Hoa 220kV Transmission Line Project 28

34 cost training course in one of the local vocation training centers, suitable for the facts of region and their ability. Question 9: How our affected public assets will be compensated? Answer: With respect to affected public assets, compensation will be provided to recover or newly construct depending on scope of impact after consulting with local authorities/affected community. Question 10: Does anybody in our community can claim for compensation? Answer: No. Entitled Affected Persons (APs) are those persons or households that are surveyed during the detailed measurement survey (DMS) activities. The APs and local authorities will be informed of the cut-off date (the date of completion of census) for the Project. Anyone moving into the Project area after cut-off date will not be entitled to compensation and assistance under the Project. Question 11: What can I do if I am not listed as affected people during the DMS but I am asked to be relocated? Answer: You are not in affected people list might be due to some mistakes during the DMS. However, you will get the same kind of compensation as other APs. DCARB will responsible for adding your name in the list of affected people. Question 12: How will APs be consulted and informed? Answer: A consultation and public information program will be organized in your commune to ensure that APs receive complete and timely information about the Project. APs will be provided information on project components, impacts, their rights and entitlements, grievance mechanism, rights of participation and consultation, resettlement activities, responsibilities of institutions and implementation schedule. APs will participate in resettlement planning and implementation and they will also be consulted on the following issues: a) resettlement options according to their entitlement, b) training and training preferences in current or new occupations, c) other project aspects. This program will enable the Project to design the resettlement and rehabilitation program to meet the needs of APs, and help APs to make informed decisions about compensation and relocation. Consultations with APs and local authorities will reduce the potential for conflicts and minimize the risk of project delays, and maximize the economic and social benefits of the Project. Question 13: In case where disagreement on compensation or dispute appears during Project implementation, do we have the right to complain? Answer: Yes, All affected people have the right to complain based on the following procedures and orders: First Stage - At Commune/Ward People s Committee (CPC): An aggrieved AP may bring his/her complaint to village head or any member of the CPC in either written or verbal form. It is incumbent upon said village head or member of CPC to notify the CPC about the complaint. The CPC will meet personally with the aggrieved AP and shall have thirdty (30) days following the Cau Bong - Duc Hoa 220kV Transmission Line Project 29

35 lodging of the complaint to resolve it. The CPC s secretariat is responsible for documenting and keeping files of all complaints that it handles. Second Stage - At District/Town People s Committee (DPC): If after thirdty (30) days the aggrieved AP does not hear from the CPC, or if the CPC gives its solutions, but the AP disagrees with the settlement decision, the AP may bring the case, either written or verbal, to any member of DPC. DPC shall have thirdty (30) days to resolve the case. The DPC is responsible for documenting and keeping files of all complaints that it handles. Third Stage - At Provincial People s Committee (PPC): If after thirdty (30) days the aggrieved AP does not hear from the DPC, or if the AP is not satisfied with the settlement decision, the AP may bring the case, either in writing or verbal, to any member of the PPC. The PPC shall have thirdty (30) days within which to resolve the complaint to the satisfaction of all concerned. The PPC secretariat is also responsible for documenting and keeping file of all complaints that it handles. Final Stage - People s Court: If after thirdty (30) days following the lodging of the complaint with the PPC, the aggrieved AP does not hear from the PPC, or if he/she is not satisfied with the settlement decision, the case may be brought to people s courts. Under no circumstance, the AP will be evicted from his/her property or for the Government to take over his/her property without the explicit permission of the people s court. Alll grievances and complaints of affected people on land acquisition, compensation and resettlement will be resolve consistent with the above stages and complainants will not shoulder any costs during grievance redress process. Question 14: As a resident in the project area, how can I help? Answer: We would like you to participate in all consultation meetings and other project related activities in order to ensure that you are fully informed and consulted. Your active participation during the detailed measurement survey (DMS) and implementation will allow us to determine measures to mitigate impacts, to identify problems or potentials problems and to identify ways of responding immediately to solve these problems. Question 15: How will we know if the objectives of this project are met? Answer: SPPMB will ensure internal monitoring all Project activities. In addition, SPPMB will engage an independent external monitoring agency to conduct external monitoring of resettlement activities during Project implementation. Every 6 months, the independent monitoring agency will submit a report to SPPMB and ADB on resettlement implementation progress. A post-resettlement impact evaluation will assess whether negative impacts have been mitigated adequately and preproject standards of living of APs have been restored as a result of resettlement and the Project. For further information and suggestions, please contact us to the following address: Southern Vietnam Power Projects Management Board (SPPMB) Tel: Fax: Cau Bong - Duc Hoa 220kV Transmission Line Project 30

36 Add: 610 Vo Van Kiet street, District 1, Ho Chi Minh City Cu Chi District Compensation and Resettlement Board (DCARB) Tel: Fax: Add: Zone 7, Cu Chi township, Cu Chi District, Ho Chi Minh City Duc Hoa District Compensation and Resettlement Board (DCARB) Tel: Fax: Add: Zone B, Hau Nghia township, Duc Hoa District, Long An Province Cau Bong - Duc Hoa 220kV Transmission Line Project 31

37 5.5 Appendix 5. Some pictures from Public Consultation Meetings Meeting in Nhuan Duc Commune Meeting in Trung Lap Ha Commune Cau Bong - Duc Hoa 220kV Transmission Line Project 32

38 Meeting in Thai My Commune Meeting in Phuoc Thanh Commune Cau Bong - Duc Hoa 220kV Transmission Line Project 33

39 5.6 Appendix 6. List of HHs who had received advance payments Cau Bong - Duc Hoa 220kV Transmission Line Project 34

40 Cau Bong - Duc Hoa 220kV Transmission Line Project 35

41 Cau Bong - Duc Hoa 220kV Transmission Line Project 36

42 Cau Bong - Duc Hoa 220kV Transmission Line Project 37

43 Cau Bong - Duc Hoa 220kV Transmission Line Project 38

44 Cau Bong - Duc Hoa 220kV Transmission Line Project 39

45 Cau Bong - Duc Hoa 220kV Transmission Line Project 40

46 Cau Bong - Duc Hoa 220kV Transmission Line Project 41

47 5.7 Appendix 7. Decision No 6763/QD-UBND dated December 10th, 2015 on approving coefficient adjusted compensation price for calculating compensation plan Cau Bong - Duc Hoa 220kV Transmission Line Project 42

VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line Social Monitoring Report Semi-Annual Monitoring Report January June 2015 VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line Prepared by the Southern Vietnam Power

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Social Monitoring Report Semi Annual Report January June 2016 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Prepared by the Southern Vietnam Power

More information

VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line Social Monitoring Report Quarterly Report April June 2015 VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line Prepared by the Southern Vietnam Power Projects Management

More information

VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line Social Monitoring Report Quarterly Report July September 2015 VIE: Power Transmission Investment Program, Tranche 2 Cau Bong-Duc Hoa Transmission Line Prepared by the Southern Vietnam Power Projects Management

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Duc Hoa Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Duc Hoa Transmission Line Social Monitoring Report Semi-Annual Report Jun-Dec 2014 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Duc Hoa Transmission Line Prepared by the Southern Power Projects Management

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Social Monitoring Report Quarterly Report April June 2016 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Prepared by the Southern Vietnam Power

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Social Monitoring Report Semi-Annual Report Jun-Dec 2014 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Prepared by the Southern Power Projects

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line Social Monitoring Report Semestral Report July to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My Industrial Zone Substation and 220kV Song May-Uyen Hung Transmission Line

More information

VIE: Power Transmission Investment Program Tranche 3

VIE: Power Transmission Investment Program Tranche 3 Social Monitoring Report 2 nd Quarterly Report June 2017 VIE: Power Transmission Investment Program Tranche 3 Installation of a second transformer bank for 220 kv Duc Hoa substation Installation of a second

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject

VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject Social Monitoring Report Final Report December 2016 VIE: Power Transmission Investment Program, Tranche 1 220kV Phu My 2 Industrial Zone Substation and Connection Lines Subproject Prepared by the Southern

More information

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line

VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Social Monitoring Report 3 rd Independent Monitoring Report June 2016 VIE: Power Transmission Investment Program, Tranche 2 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Prepared by the Southern Vietnam

More information

VIE: Power Transmission Investment Program, Tranche 1 Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 Song May-Uyen Hung Transmission Line Social Monitoring Report 5 th Independent Monitoring Report January April 2016 VIE: Power Transmission Investment Program, Tranche 1 Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province)

VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Social Monitoring Report July 2014 VIE: Power Transmission Investment Program, Tranche 2 500kV Pleiku-My Phuoc-Cau Bong Transmission Line (Binh Duong Province) Prepared by Central Vietnam Power Projects

More information

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR

COMPENSATION, ASSISTANCE AND RESETTLEMENT POLICY PROPOSED FOR Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= COMPENSATION,

More information

VIE: Power Transmission Investment Program, Tranche 3

VIE: Power Transmission Investment Program, Tranche 3 Social Monitoring Report 1st Semi-annual Report July 2017 VIE: Power Transmission Investment Program, Tranche 3 Prepared by Le Duc Huy for the National Power Transmission Corporation and the Asian Development

More information

Combined Resettlement Plan and Ethnic Minority Development Plan. VIE: GMS Kunming-Haiphong Transport Corridor Noi Bai-Lao Cai Highway Project

Combined Resettlement Plan and Ethnic Minority Development Plan. VIE: GMS Kunming-Haiphong Transport Corridor Noi Bai-Lao Cai Highway Project Combined Resettlement Plan and Ethnic Minority Development Plan December 2017 VIE: GMS Kunming-Haiphong Transport Corridor Noi Bai-Lao Cai Highway Project Prepared by Vietnam Expressway Corporation for

More information

Da Nang - Quang Ngai Expressway Development Project

Da Nang - Quang Ngai Expressway Development Project Public Disclosure Authorized Public Disclosure Authorized DA NANG-QUANG NGAI EXPRESSWAY PROJECT Due Dilligence report, Phu Ninh district, Quang Nam province MINISTRY OF TRANSPORT VIETNAM EXPRESSWAY CORPORATION

More information

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project

VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote Communes Sector Project. Sub-project: So Vin Hydropower Project Final Resettlement Monitoring Report Document stage: Final Project number: Loan 2517 May, 2017 VIE: Renewable Energy Development and Network Expansion and Rehabilitation for Remote s Sector Project Sub-project:

More information

Safeguards Monitoring Report

Safeguards Monitoring Report Safeguards Monitoring Report Semiannual Report Covering July-Dec 2016 period February 2017 (ESDIP) Tranche-2 Chimtala- Arghandi 220 kv DC Transmission Line Subproject (DABS - 006/ICB) Prepared by Da Afghanistan

More information

Viet Nam: Secondary Cities Development Project - Ha Tinh Subproject

Viet Nam: Secondary Cities Development Project - Ha Tinh Subproject Resettlement Monitoring Report # First Periodic Report September 2016 Viet Nam: Secondary Cities Development Project - Ha Tinh Subproject Prepared by Nguyen Van Trung, External Resettlement Monitoring

More information

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject : Rural Energy - Additional Financing (Phase 4) Subproject in Ha Nam NORTH

More information

PEOCS QUALITY MANAGEMENT SYSTEM ISO C6NG TY Ttl VAN XAY D/NG DION 3 R'P82 VO L t' RESETTLEMENT ACTION PLAN

PEOCS QUALITY MANAGEMENT SYSTEM ISO C6NG TY Ttl VAN XAY D/NG DION 3 R'P82 VO L t' RESETTLEMENT ACTION PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ELECTRICITY OF VIET NAM SOUTHERN POWER PROJECT MANAGEMENT BOARD R'P82 VO L. 14 LONG AN

More information

VIE: Ben Luc Long Thanh Expressway Project

VIE: Ben Luc Long Thanh Expressway Project Resettlement Plan TA 7155-VIE 19 July 2010 VIE: Ben Luc Long Thanh Expressway Project Vietnam Expressway Corporation ABBREVIATIONS ADB DP CPC DPC DCSCC DARD DOC DOF DONRE DPI DOT DMS EMA FS GoV HCMC HH

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Cam My and Thong Nhat Districts DONG NAI PROVINCE Stage 3

Cam My and Thong Nhat Districts DONG NAI PROVINCE Stage 3 THE SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT VIETNAM EXPRESSWAY CORPORATION (VEC) SOUTHERN EXPRESSWAY PROJECT MANAGEMENT UNIT (SEPMU) The Updated Resettlement Plan Cam My and Thong Nhat Districts

More information

NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board RESETTLEMENT PLAN (RP)

NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board RESETTLEMENT PLAN (RP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board -------------------------------

More information

Internal Resettlement Monitoring Report

Internal Resettlement Monitoring Report Internal Resettlement Monitoring Report Stage of document: Quarterly (Q4 2015) Project/Loan number: Loan 2789 Date: March 2016 VIE: TRANSPORT CONNECTIONS IN NORTHERN MOUNTAINOUSPROVINCES PROJECT Prepared

More information

VIETNAM INDUSTRIAL POLLUTION MANAGEMENT PROJECT (P113151)

VIETNAM INDUSTRIAL POLLUTION MANAGEMENT PROJECT (P113151) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM INDUSTRIAL POLLUTION MANAGEMENT PROJECT (P113151) Due Diligence Review of Involuntary

More information

GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum)

GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum) Resettlement Plan December 2014 GEO: Sustainable Urban Transport Investment Program, Tranche 2 Tbilisi-Rustavi Urban Road Link (Section-1: km 0 to 4 Tbilisi Phonichala) (Addendum) Prepared by the Municipal

More information

VIE: O Mon IV Combined Cycle Power Plant

VIE: O Mon IV Combined Cycle Power Plant Resettlement Due Diligence Report February 2011 VIE: O Mon IV Combined Cycle Power Plant Prepared by Can Tho Thermal Power Company for the Asian Development Bank. 1 O MON IV THERMAL POWER PLANT RESETTLEMENT

More information

Viet Nam: Northern Power Transmission Expansion Sector Project

Viet Nam: Northern Power Transmission Expansion Sector Project Validation Report Reference Number: PVR-485 Project Number: 38196-013 Loan Number: 2225 December 2016 Viet Nam: Northern Power Transmission Expansion Sector Project Independent Evaluation Department ABBREVIATIONS

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

The Provincial People s Committees of Thanh Hóa, Quảng Bình, Thừa Thiên - Huế, Quảng Nam, and Quảng Ngãi Province. To:

The Provincial People s Committees of Thanh Hóa, Quảng Bình, Thừa Thiên - Huế, Quảng Nam, and Quảng Ngãi Province. To: MINISTRY OF CONSTRUCTION THE SOCIALIST REPUBLIC OF VIETNAM Independence Freedom Happiness No: /BXD-QLN Subject: Guidelines on the implementation of Project s Component 1 funded by Green Climate Fund (GCF):

More information

LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program Loan 2) between

LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program Loan 2) between LOAN NUMBER 2956-VIE LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program Loan 2) between SOCIALIST REPUBLIC OF VIET NAM and ASIAN DEVELOPMENT BANK

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program)

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) 1. A project preparatory technical assistance (PPTA) for $700,000 in grant funds is

More information

REPORT ON Independent Resettlement Monitoring (Mission I)

REPORT ON Independent Resettlement Monitoring (Mission I) ELECTRICITY OF VIETNAM TRUNG SON HYDROPOWER PROJECT CONSTRUCTION OPERATION ROAD TRUNG SON HYDROPOWER PLANT REPORT ON Independent Resettlement Monitoring (Mission I) Monitored and reported by: Centre for

More information

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Resettlement Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP June 2012 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Ghupa-Sanghu

More information

THE PRIME MINISTER ------- No. 71/2010/QD-TTg SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom Happiness --------- Hanoi, November 09, 2010 DECISION PROMULGATING THE REGULATION ON PILOT INVESTMENT

More information

.~~~IO O12O RP82 OF VIT NAM ~~~ELECTRICITY. RESETTLIEMENT ACTION PlAsN (RAP) (FINAL REVISION) \} \ PECC4 POWER ENGINEERING CONSULTING COMPANY 4

.~~~IO O12O RP82 OF VIT NAM ~~~ELECTRICITY. RESETTLIEMENT ACTION PlAsN (RAP) (FINAL REVISION) \} \ PECC4 POWER ENGINEERING CONSULTING COMPANY 4 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized X RP82 VOL. 20 ~~~~~SOCIALIST REPUBLIC OF VIET NAM OF VIT NAM \} \ ~~~ELECTRICITY PECC4

More information

PROJECT AGREEMENT. (Viet Nam Water Sector Investment Program Project 2) between ASIAN DEVELOPMENT BANK. and

PROJECT AGREEMENT. (Viet Nam Water Sector Investment Program Project 2) between ASIAN DEVELOPMENT BANK. and LOAN NUMBER 2961-VIE PROJECT AGREEMENT (Viet Nam Water Sector Investment Program Project 2) between ASIAN DEVELOPMENT BANK and BAC GIANG WATER SUPPLY AND SEWERAGE ONE MEMBER LIMITED COMPANY BINH DUONG

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Country Partnership Strategy: Viet Nam, 2012 2015 SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Investment in the transport sector in Viet

More information

VIE: Central Mekong Delta Connectivity Project Can Tho City

VIE: Central Mekong Delta Connectivity Project Can Tho City Income Restoration Program February 2015 VIE: Central Mekong Delta Connectivity Project Can Tho City Prepared by Ministry of Transport, Cuu Long Corporation for Investment, Development and Project Management

More information

Initial Environmental Examination

Initial Environmental Examination Initial Environmental Examination June 2017 IND: Green Energy Corridor and Grid Strengthening Project (320 kv VSC-HVDC power transmission lines between Pugalur, Tamil Nadu and North Trichur, Kerala) Annexures

More information

Subproject: Cau Khai drainage system Yen Dinh district, Thanh Hoa province

Subproject: Cau Khai drainage system Yen Dinh district, Thanh Hoa province Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RP299 vol. 3 Ministry of Agriculture and Rural Development The World Bank Natural Disaster

More information

XII. CGIF Environmental and Social Safeguards Policy and Framework 1

XII. CGIF Environmental and Social Safeguards Policy and Framework 1 A. Policy XII. CGIF Environmental and Social Safeguards Policy and Framework 1 1. Credit Guarantee and Investment Facility (CGIF), a trust fund of the Asian Development Bank (ADB) was established to promote

More information

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT Himachal Pradesh Clean Energy Transmission Investment Program (RRP IND 43464) TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT A. INTRODUCTION 1. The

More information

Land Acquisition and Resettlement Plan Compliance Report. ARM: Sustainable Urban Development Investment Program Tranche 2

Land Acquisition and Resettlement Plan Compliance Report. ARM: Sustainable Urban Development Investment Program Tranche 2 Land Acquisition and Resettlement Plan Compliance Report May 2018 ARM: Sustainable Urban Development Investment Program Tranche 2 LARP Area (Babajanyan - Tichina Highway) Prepared by the AM Partners Consulting

More information

OPERATIONS MANUAL BANK POLICIES (BP)

OPERATIONS MANUAL BANK POLICIES (BP) BANK POLICIES (BP) OM Section F1/BP Page 1 of 2 These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. SAFEGUARD POLICY STATEMENT 1. The Asian Development

More information

VIE: Central Mekong Delta Region Connectivity Project

VIE: Central Mekong Delta Region Connectivity Project Social Monitoring Report Fifth Report August 2016 VIE: Central Mekong Delta Region Connectivity Project Prepared by Romeo Cleto, External Monitor, for the Ministry of Transport, Cuu Long Corporation for

More information

No.: 01/2016/BB-ĐHĐCĐ Ho Chi Minh City, 21 April, 2016 MINUTES OF THE 2015 ANNUAL GENERAL MEETING (AGM) HO CHI MINH CITY SECURITIES CORPORATION (HSC)

No.: 01/2016/BB-ĐHĐCĐ Ho Chi Minh City, 21 April, 2016 MINUTES OF THE 2015 ANNUAL GENERAL MEETING (AGM) HO CHI MINH CITY SECURITIES CORPORATION (HSC) Hochiminh City Securities Corporation (HSC) HEAD OFFICE Level 5 & 6, AB Tower, 76 Le Lai St., Ben Thanh Ward, District 1, HCMC, Vietnam T: (+84 8) 3823 3299 F: (+84 8) 3823 3301 E: info@hsc.com.vn W: www.hsc.com.vn

More information

Community Hygiene and Water Women-led Output based Aid Project (WOBA) in Vietnam. Introduction & Overview

Community Hygiene and Water Women-led Output based Aid Project (WOBA) in Vietnam. Introduction & Overview Community Hygiene and Water Women-led Output based Aid Project (WOBA) in Vietnam Introduction & Overview What is the difference between Equity and Equality? What is GESI? Gender equality is about transforming

More information

Section 3.06 is deleted and the following is substituted therefor:

Section 3.06 is deleted and the following is substituted therefor: 2 (c) Section 3.03 is deleted and the following is substituted therefor: Commitment Charge; Credit; Maturity Premium. (a) The Borrower shall pay a commitment charge on the unwithdrawn amount of the Loan

More information

IND: Bihar Power System Improvement Project

IND: Bihar Power System Improvement Project Resettlement Plan (Revised) Document Stage: Revised Project Number: 41626 (IND) July 2014 IND: Bihar Power System Improvement Project Prepared by: Bihar State Power Transmission Company Ltd. Government

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 38561 TECHNICAL ASSISTANCE (Financed by the Poverty Reduction Cooperation Fund) TO THE SOCIALIST REPUBLIC OF VIET NAM FOR DEVELOPING AGRICULTURAL INSURANCE December 2004

More information

Resettlement Planning Document.

Resettlement Planning Document. Resettlement Planning Document. Document: Land Acquisition and Resettlement Plan Document Stage: Final Project Number: 40190 June 2012 GMS - Flood and Drought Risk Management and Mitigation Project (FDRMMP)

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/24/2007 INTEGRATED SAFEGUARDS DATASHEET

More information

Agreement Amending Project Agreement

Agreement Amending Project Agreement Public Disclosure Authorized.:DUMENTS CREDIT NUMBER 2724 VN Public Disclosure Authorized Agreement Amending Project Agreement (Power Sector Rehabilitation and Expansion Project) among INTERNATIONAL DEVELOPMENT

More information

LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Long Thanh Dau Giay Expressway Construction Project) between SOCIALIST REPUBLIC OF VIET NAM

LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Long Thanh Dau Giay Expressway Construction Project) between SOCIALIST REPUBLIC OF VIET NAM LOAN NUMBER 2451-VIE LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Long Thanh Dau Giay Expressway Construction Project) between SOCIALIST REPUBLIC OF VIET NAM and ASIAN DEVELOPMENT BANK DATED

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE . Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDSPrepared/Updated: Date ISDS Approved/Disclosed I. BASIC INFORMATION 1. Basic

More information

Monthly Legal Briefing

Monthly Legal Briefing Monthly Legal Briefing Edition 1 January 2014 Banking & Finance Corporate Dispute Resolution Intellectual Property Real Estate & Infrastructure Banking & Finance Decree No. 01/2014/ND-CP on the purchase

More information

(i) Loan Disbursement Handbook means ADB s Loan Disbursement Handbook (2012, as amended from time to time);

(i) Loan Disbursement Handbook means ADB s Loan Disbursement Handbook (2012, as amended from time to time); 2 (f) GAP or Gender Action Plan means the gender action plan for the Project, including any update thereto, prepared and agreed between the Borrower and ADB and further set out in the PAM; (g) Goods means

More information

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project FINAL EVALUATION VIE/033 Climate Adapted Local Development and Innovation Project PROJECT SUMMARY DATA Country Long project title Short project title LuxDev Code Vietnam Climate Adapted Local Development

More information

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ).

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). WHEREAS (A) the Borrower has applied to ADB for a loan

More information

Socialist Republic of Viet Nam: Water Sector Investment Program Multitranche Financing Facility (MFF) Periodic Financing Request 3

Socialist Republic of Viet Nam: Water Sector Investment Program Multitranche Financing Facility (MFF) Periodic Financing Request 3 Appendix 3: Water Sector Investment Program (MFF0054-VIE) PFR3 Report VIE 41456-043 Project Administration Manual Project Number: 41456-043 Loan Number: XXXX March 2015 Socialist Republic of Viet Nam:

More information

COMPARATIVE ANALYSIS OF DMC LEGAL FRAMEWORK AND ADB SAFEGUARD POLICY STATEMENT BANGLADESH

COMPARATIVE ANALYSIS OF DMC LEGAL FRAMEWORK AND ADB SAFEGUARD POLICY STATEMENT BANGLADESH COMPARATIVE ANALYSIS OF DMC LEGAL FRAMEWORK AND ADB SAFEGUARD POLICY STATEMENT BANGLADESH Note: The following is based on the provisions of The Acquisition and Requisition of Immovable Property Ordinance

More information

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project Environmental Safeguard Monitoring Report Semi Annual Report July 2016 ADB Project Number: 48141-001 ADB Loan Number: 3210 FIJ: Transport Infrastructure Investment Sector Project Prepared by Fiji Roads

More information

PROJECT AGREEMENT. (Low-Carbon District Heating Project in Hohhot in Inner Mongolia Autonomous Region) between ASIAN DEVELOPMENT BANK.

PROJECT AGREEMENT. (Low-Carbon District Heating Project in Hohhot in Inner Mongolia Autonomous Region) between ASIAN DEVELOPMENT BANK. LOAN NUMBER 3218-PRC PROJECT AGREEMENT (Low-Carbon District Heating Project in Hohhot in Inner Mongolia Autonomous Region) between ASIAN DEVELOPMENT BANK and GOVERNMENT OF INNER MONGOLIA AUTONOMOUS REGION

More information

Vietnam Central Highland Poverty Reduction Project Findings and Arrangements to Enhance Ethnic Minority Participation September 24, 2013

Vietnam Central Highland Poverty Reduction Project Findings and Arrangements to Enhance Ethnic Minority Participation September 24, 2013 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized A. Overview Vietnam Central Highland Poverty Reduction Project Findings and Arrangements

More information

Lao PDR: Northern GMS Power Transmission Project

Lao PDR: Northern GMS Power Transmission Project Resettlement Plan July 2014 Lao PDR: Northern GMS Power Transmission Project Prepared by Electricity Du Laos for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 30 June 2014) Currency unit KN KN1.00

More information

MINUTES OF VPBANK S GENERAL SHAREHOLDERS MEETING (GSM) 2011

MINUTES OF VPBANK S GENERAL SHAREHOLDERS MEETING (GSM) 2011 Vietnam Prosperity Joint Stock Commercial Bank (VPBank) Business registration as per certificate of joint stock company registration, tax code 0100233583 issued for the first time by Department of Planning

More information

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project Technical Assistance Project Number: 50098 Project Preparatory Technical Assistance (PPTA) November 2016 Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project This document is being

More information

FACTSHEET ON MINIMUM WAGE LEGISLATION AROUND THE WORLD

FACTSHEET ON MINIMUM WAGE LEGISLATION AROUND THE WORLD FACTSHEET ON MINIMUM WAGE LEGISLATION AROUND THE WORLD According to the International Labour Office in Geneva in Switzerland, about 90% of the countries in the world have legislation in favour of minimum

More information

Thanh Thanh Cong Tay Ninh Joint Stock Company

Thanh Thanh Cong Tay Ninh Joint Stock Company Interim consolidated financial statements 31 December 2016 CONTENTS Pages General information 1-2 Report of management 3 Report on review of interim consolidated financial statements 4-5 Interim consolidated

More information

PROJECT AGREEMENT. (Hebei Energy Efficiency Improvement and Emission Reduction Project) between ASIAN DEVELOPMENT BANK. and

PROJECT AGREEMENT. (Hebei Energy Efficiency Improvement and Emission Reduction Project) between ASIAN DEVELOPMENT BANK. and LOAN NUMBER 2835-PRC PROJECT AGREEMENT (Hebei Energy Efficiency Improvement and Emission Reduction Project) between ASIAN DEVELOPMENT BANK and HEBEI PROVINCIAL GOVERNMENT DATED 6 MARCH 2012 PRC 44012 PROJECT

More information

Press Release. Press Release SAVILLS VIETNAM REPORT ON INDUSTRIAL SECTOR NATIONWIDE 1. OVERVIEW 24/09/2015

Press Release. Press Release SAVILLS VIETNAM REPORT ON INDUSTRIAL SECTOR NATIONWIDE 1. OVERVIEW 24/09/2015 24/09/2015 SAVILLS VIETNAM REPORT ON INDUSTRIAL SECTOR NATIONWIDE 1. OVERVIEW Co.,Ltd 18 th Floor, Continental Tower 81-85 Ham Nghi Street District 1, HCMC T: +84 8 3823 9205 savills.com.vn Large-scale

More information

Timor-Leste: Baucau to Viqueque Highway Project

Timor-Leste: Baucau to Viqueque Highway Project Resettlement Plan Project Number: 51115 June 2017 Timor-Leste: Baucau to Viqueque Highway Project Prepared by the Government of Timor-Leste for the Asian Development Bank. Table of Contents EXECUTIVE

More information

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ).

LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). LOAN AGREEMENT (Special Operations) LOAN AGREEMENT dated 17 January 2013 between KINGDOM OF CAMBODIA ( Borrower ) and ASIAN DEVELOPMENT BANK ( ADB ). WHEREAS (A) by a loan agreement of even date herewith

More information

Public-Private Partnerships (PPP) and Foreign Direct Investment Enterprises ( FDIE ) in Vietnam

Public-Private Partnerships (PPP) and Foreign Direct Investment Enterprises ( FDIE ) in Vietnam Public-Private Partnerships (PPP) and Foreign Direct Investment Enterprises ( FDIE ) in Vietnam Disclaimer: This Briefing is for information purposes only. Its contents do not constitute legal advice and

More information

TABLE OF CONTENTS CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 INTERIM FINANCIAL STATEMENTS REVIEW REPORT 4

TABLE OF CONTENTS CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 INTERIM FINANCIAL STATEMENTS REVIEW REPORT 4 TABLE OF CONTENTS PAGE CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 INTERIM FINANCIAL STATEMENTS REVIEW REPORT 4 SEPARATE STATEMENT OF FINANCIAL POSITION 6 SEPARATE STATEMENT OF INCOME

More information

TABLE OF CONTENTS CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 INTERIM FINANCIAL STATEMENTS REVIEW REPORT 4-5

TABLE OF CONTENTS CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 INTERIM FINANCIAL STATEMENTS REVIEW REPORT 4-5 TABLE OF CONTENTS PAGE CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 INTERIM FINANCIAL STATEMENTS REVIEW REPORT 4-5 SEPARATE STATEMENT OF FINANCIAL POSITION 6-8 SEPARATE STATEMENT OF INCOME

More information

In This Issue. Dear Reader, ISSUE NO 5.6 JULY 2014

In This Issue. Dear Reader, ISSUE NO 5.6 JULY 2014 1 Client Alert ISSUE NO 5.6 JULY 2014 www.indochinecounsel.com In This Issue Executive Summary 2 Transfer Of The Right To Use.vn Domain Names New Rules For Land Allocation And Land Lease New Regulations

More information

Financing Agreement CREDIT NUMBER VN. (Ho Chi Minh City Green Transport Development Project) between SOCIALIST REPUBLIC OF VIETNAM.

Financing Agreement CREDIT NUMBER VN. (Ho Chi Minh City Green Transport Development Project) between SOCIALIST REPUBLIC OF VIETNAM. Public Disclosure Authorized OFFICIAL DOCUMENTS CREDIT NUMBER 5654 - VN Public Disclosure Authorized Financing Agreement Public Disclosure Authorized (Ho Chi Minh City Green Transport Development Project)

More information

SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness No. 15/2015/NĐ-CP Hanoi, February 14, 2015 DECREE

SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness No. 15/2015/NĐ-CP Hanoi, February 14, 2015 DECREE THE GOVERNMENT ------- SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness --------------- No. 15/2015/NĐ-CP Hanoi, February 14, 2015 DECREE ON INVESTMENT IN THE FORM OF PUBLIC-PRIVATE PARTNERSHIP

More information

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2)

PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2) Social Monitoring Report Bi-annual Social Monitoring Report July 2014 PAK: MFF Power Distribution Enhancement Investment Program (Tranche 2) Prepared by Lahore Electric Supply Company, Punjab for the Asian

More information

Thanh Thanh Cong Tay Ninh Joint Stock Company

Thanh Thanh Cong Tay Ninh Joint Stock Company Interim separate financial statements 31 December 2016 GENERAL INFORMATION CONTENTS Pages General information 1-2 Report of management 3 Report on review of interim separate financial information 4-5 Interim

More information

Project Administration Manual

Project Administration Manual Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (RRP VIE 46391) Project Administration Manual Project Number: 46391 Loan Numbers: {LXXXX; LXXXX} August 2014 Socialist Republic of Viet

More information

Planning, Budgeting and Financing

Planning, Budgeting and Financing English Version Planning, Budgeting and Financing Post-Disaster Recovery and Reconstruction Activities in Khammouane Province, Lao PDR Developed under the Khammouane Development Project (KDP), Implemented

More information

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening

AZERBAIJAN MOTORWAY IMPROVEMENT AND DEVELOPMENT Baku Shamakhi Road Widening SFG1532 Public Disclosure Authorized AZERBAIJAN REPUBLIC Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT AZERROADSERVICE OPEN JOINT STOCK COMPANY AZERBAIJAN MOTORWAY IMPROVEMENT

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

QUANG NAM MINERAL INDUSTRY CORPORATION. Financial statements. For the year ended 31 December 2010

QUANG NAM MINERAL INDUSTRY CORPORATION. Financial statements. For the year ended 31 December 2010 QUANG NAM MINERAL INDUSTRY CORPORATION Financial statements For the year ended 31 December 2010 INDEX Page Report of Management 1-3 Auditors report 4 Financial statements Balance sheet 5-6 Income statement

More information

RESOLUTION. Annual General Meeting of Shareholders of Gemadept Corporation On 09 May, 2012

RESOLUTION. Annual General Meeting of Shareholders of Gemadept Corporation On 09 May, 2012 GEMADEPT CORPORATION THE SOCIALIST REPUBLIC OF VIET NAM Independence Freedom Happiness ----------------- o -------------- No: 103/GMD-DHDCD Ho Chi Minh City, 09 May, 2012 RESOLUTION Annual General Meeting

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Country Sector(s) PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

More information

Decree No.15/2015/ND-CP dated 14/02/2015 on Public Private Partnership Investment (PPP) (Effective from 10/4/2015)

Decree No.15/2015/ND-CP dated 14/02/2015 on Public Private Partnership Investment (PPP) (Effective from 10/4/2015) Decree No.15/2015/ND-CP dated 14/02/2015 on Public Private Partnership Investment (PPP) (Effective from 10/4/2015) 1 Old legal framework on PPP Decision No. 71/2010/QD-TTg on pilot PPP Projects Decree

More information

Multitranche Financing Facility Annual Report 2017

Multitranche Financing Facility Annual Report 2017 May 2018 Multitranche Financing Facility Annual Report 2017 This document is being disclosed to the public in accordance with ADB s Public Communications Policy 2011. ABBREVIATIONS ADB Asian Development

More information

(c) Section 3.07 is deleted and the following is substituted therefor:

(c) Section 3.07 is deleted and the following is substituted therefor: 2 outstanding Loan on which a higher Fixed Spread is applicable. The amount of the Rebate shall be determined by multiplying (i) the difference between the Fixed Spread applicable to the outstanding Loan

More information

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Phase 3 Consultation in Indonesia January 26-28, 2016 Objective Illustrate

More information

No.: 01/2015/BB-ĐHĐCĐ Ho Chi Minh City, April 16 th, 2015 MINUTES

No.: 01/2015/BB-ĐHĐCĐ Ho Chi Minh City, April 16 th, 2015 MINUTES Hochiminh City Securities Corporation (HSC) HEAD OFFICE Level 5 & 6, AB Tower, 76 Le Lai St., Ben Thanh Ward, District 1, HCMC, Vietnam T: (+84 8) 3823 3299 F: (+84 8) 3823 3301 E: info@hsc.com.vn W: www.hsc.com.vn

More information

Update on guidance for enterprise accounting regime in Vietnam. 11 Febuary 2015

Update on guidance for enterprise accounting regime in Vietnam. 11 Febuary 2015 Update on guidance for enterprise accounting regime 11 Febuary 2015 Grant Thornton Vietnam updates on Circular No. 200/2014/TT- BTC guidance for enterprise accounting regime: Circular No. 200/2014/TT-BTC

More information

CORPORATE GOVERNANCE REPORT 2015

CORPORATE GOVERNANCE REPORT 2015 DIGIWORLD CORPORATION SOCIALIST REPUBLIC OF VIETNAM Independence Freedom - Happiness ---o0o--- No.: 03/01-2016/HĐQT/ TP.HCM, January 25 th 2016 CORPORATE GOVERNANCE REPORT 2015 To : STATE SECURITIES COMMISSION

More information

TABLE OF CONTENTS CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 SEPARATE STATEMENT OF FINANCIAL POSITION 4-6

TABLE OF CONTENTS CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 SEPARATE STATEMENT OF FINANCIAL POSITION 4-6 TABLE OF CONTENTS PAGE CORPORATE INFORMATION 2 STATEMENT OF THE BOARD OF DIRECTORS 3 SEPARATE STATEMENT OF FINANCIAL POSITION 4-6 SEPARATE STATEMENT OF INCOME 7-8 SEPARATE STATEMENT OF CASH FLOWS 9-11

More information