1 Feed-in Tariff Review workshop BIS Conference Centre, London, 5 October 2015

2 Agenda Presentation on FIT Review consultation Gareth Redmond, Head of Renewables Programme Team, DECC Sarah Lowe, Lead Analyst, Feed-in Tariffs Q&A session chaired by Gareth Redmond Break for coffee Roundtable discussions Summing up of discussions 2

3 Context and rationale

4 State aid requirement The European Commission s State aid approval for FITs places an obligation on the Government to review scheme performance every three years. Previous tariff review took place as part of the comprehensive review of the scheme in

5 Levy Control Framework Spending in is projected to be 1.5bn above the 7.6bn LCF budget in 2020/21 (in 2011/2012) prices. FITs accounts for around 475m of this increase. These costs are paid through consumer electricity bills. 5

6 FIT deployment We are on track: to meet or exceed the EMR Delivery Plan 2020 deployment ranges to deliver at least 30% of our electricity from renewable sources by Since its launch in 2010, the FIT scheme has seen deployment and spend significantly outstrip expectations, including for nonsolar techs. Over 740,000 installations registered as of August In 2010 we anticipated 750,000 renewable installations by

7 FIT Review proposals

8 FIT Review proposals These proposals are intended for immediate implementation. Proposal Generation tariffs Description Revised generation tariffs and revision of some tariff bands for new installations. Degression Default degression for all technologies will be quarterly. Contingent degression will now be 0%, 5% or 10% for all technologies depending on deployment rate, and will be in addition to default degression. Deployment caps New expenditure under FITs is limited to an overall budget of m to 2018/19. Proposals to implement deployment and degression band caps to meet this budget. Closure of generation tariff to new installations Remove the generation tariff for new FIT applications from January 2016 if proposed cost control deployment caps are deemed unable to place the costs of the scheme on an affordable and sustainable trajectory or, alternatively, further reducing the size of the scheme s remaining budget available for the cap. 8

9 FIT Review proposals These proposals are intended for immediate implementation. Proposal Inflation indexation Installation extensions New technologies Extend FITs to projects based in Northern Ireland Buying overseas renewable electricity MCS standards Funding scheme administration Description Move from RPI-linked tariffs to a CPI-link for new installations. Prevent extensions to existing installations from claiming FITs. FITs should not be extended to any other technologies We are not proposing to extend FITs to Northern Ireland. Limit the amount of renewable electricity purchased from overseas which can be offset against market contribution for levelisation process. Link eligible technologies to specific MCS standards. Use interest accrued in the Levelisation Fund for scheme administration. 9

10 Future measures We are consulting on the following measures for future consideration: Proposal Export tariffs Remote reading of generation meters Grid management Anaerobic digestion sustainability criteria Minimum energy efficiency criteria Description Options to move to fully metered export for all generators and revise the export tariff so it is more reflective of system costs and benefits in the future. Views sought on how to move to remote generation meter reading. Views sought on obligation for all new FIT generators to inform their Distribution Network Operator (DNO) of their installation. Views sought on the introduction of sustainability criteria for feedstock to bring FITs into line with existing RHI and RO criteria. Views sought on increasing energy efficiency criteria for new FIT applications in the future 10

11 Where did we get our evidence from? FIT Review Stakeholder events

12 The evidence came from a survey-based research project run by consultants. 1. Parsons Brinckerhoff (PB) were awarded the contract to provide evidence 2. They used a survey based approach supplemented with literature reviews and internal expertise 3. DECC and AEA Ricardo provided peer review 4. AEA Ricardo gave additional support on hurdle rates. 12 FIT Review Stakeholder events

13 How did we set the proposed tariffs? FIT Review Stakeholder events

14 We set the proposed generation tariffs to target a specific rate of return The target rate of return (RoR) is set at the low end of the overlap between hurdle rate ranges for domestic and commercial investors Example: selecting a target rate of return for solar PV Investor categories Non-energy professionals Utilities Commercial Domestic Target rate of Technology return PV 4.0% Wind 5.0% Hydro 9.0% Hurdle rate ranges (%) 2.5% 4% 5% 10% 11% 14 FIT Review Stakeholder events

15 We considered several cash flows when setting the proposed generation tariffs. Income streams: Costs: 1. Bill savings = (home usage rate * generation * retail electricity price) 2. Export income = (export rate * generation * export tariff) 1. Capital Expenditure 2. Operating Expenditure Given these, set generation tariff to give target RoR We have deviated from calculated tariffs in 2 cases: 1. Large wind because the calculated tariff was negative. This implies some projects are already at grid parity. 2. Standalone PV this was capped at the large building mounted rate 15 FIT Review Stakeholder events

16 The proposed tariffs are set to target wellsited installations In line with the original intention of the scheme and in light of budget constraints, we are proposing to target well-sited installations that are assumed to have the following: 1. Central capex 2. High load factors (apart from hydro) By targeting support at sites with high load factors we aim to support the most efficient sites, which will deliver better value for money 16 FIT Review Stakeholder events

17 Current Tariffs for installations with an Proposed Generation Tariffs for Jan eligibility date on or after 1 October 2016 (p/kwh, Nominal prices) 2015 (p/kwh, 2015/16 values) Solar PV 0-10kW 1.63 <4kW kW kW kW kW kW kW 2.28 > 1000kW kW 5.94 Stand alone 1.03 Stand alone 4.28 Wind <50kW kW kW kW ,500kW 5.89 >1500kW 0.00 >1500kW 2.49 Hydro <100kW <15kW kW kw kW kW kW 8.91 >2000kW 2.18 >2000kW FIT Review Stakeholder events

18 How did we set the proposed caps? FIT Review Stakeholder events

19 Deployment caps are proposed to limit additional cost to 100m from Jan 2016 to April Tariffs are proposed to target a certain rate of return, and lead to a certain amount of projected deployment in the absence of caps. Caps are proposed as a back-up spend control tool in case actual deployment exceeds our projections. We have an agreement for new spending of m from Jan 2016 to April Ideally we d cap spend but this is too difficult to monitor in a timely way, so we propose caps based on deployment The central spend projection from new tariffs is c 90m from Jan 2016 to April 2019, so we propose caps that would allow 100m - c. 10% above the deployment projection. 19 FIT Review Stakeholder events

20 The resulting proposed deployment caps are above our central deployment projections Maximum Deployment (MW) PV Q Q Q Q Q Q Q Q Q Q Q Q Q <10kW kW >50kW Stand alone Wind <50kW >50kW Hydro All AD <500kW >500kW FIT Review Stakeholder events

21 How did we design the proposed degression mechanism? FIT Review Stakeholder events

22 We are proposing to maintain the 2 different types of degression Type of degression Aim Implementation Default (regardless of deployment) Contingent (depends on deployment) Ensure that the RoR of installers remains constant over time Prevent overcompensation if inputs change more than our assumptions e.g. costs are falling faster than expected Table published outlining how tariffs fall each quarter 5% degression if central projection is hit and 10% if cap is hit. 22 FIT Review Stakeholder events

23 Next steps Consultation closes on Friday 23 October. We will aim to produce a Government response by late November/early December. Changes to tariffs and introduction of caps would require changes to the Feed-in Tariff Order. This is subject to a 40 day procedure before changes could come into effect.

24 Q&A session

25 Break for coffee:

26 Roundtable discussions Nominate a chair from around the table Discussion on consultation questions DECC official to take notes and capture responses

27 Consultation questions: tariffs and cost control Do you agree or disagree with the proposed generation tariff rates set out above? Do you agree or disagree that the updated assumptions produced by Parsons Brinckerhoff are reflective of the current costs of deployment for UK projects in your sector? Do you agree or disagree with the proposal to introduce deployment caps under the FITs scheme? Do you agree or disagree with the proposed design of the system of caps? Do you agree or disagree with the proposed approach to implementing caps? If you disagree, are there any alternative approaches that you d suggest? 27

28 Final conclusions: Key information: Consultation will run for eight weeks to 23 October: /Consultation_on_a_review_of_the_Feed-in_Tariffs_scheme.pdf Submit responses to: Thank you for your attendance. 28

29 Additional slides

30 Total income streams impact Revenue stream (p/kwh) Value 1st Oct 2015 Value in Jan 2016 under proposed changes % change Generation tariff % Export tariff % Bill savings % Total average income per kwh %

31 Default degression table Generation tariff, p/kwh Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan <10kW kW kW PV kW > 1000kW Stand alone <50kW Wind kW >1500k W <100kW kw Hydro kW >2000k W

32 FiTs Model explanation Demand in the FIT model Hurdle rates are input as a distribution, aiming to represent the population of investors in each category They are combined with cost distributions and load factor assumptions to produce a distribution of levelised costs The available revenues in each tariff band are then compared with this distribution to determine the level of deployment in the period Example distribution of levelised costs The shaded area corresponds to the % of demand which will be incentivised to deploy Levelised costs ( /kwh) Levelised revenues available through tariffs and bill savings ( /kwh)

33 Definition of good evidence The tariffs proposed in the consultation are based on evidence gathered by independent consultants but subject to revision in light of fresh evidence submitted by industry. In order to consider changes to tariffs, we are looking for robust and verifiable evidence submitted through the e- consultation portal. Where available, this should include a range of data points from recent FIT-eligible installations. Examples include: Capital expenditure and operating expenditure: invoices and company reports Load factors: regular meter readings taken over a substantial period of time, designed power output for specific technologies Hurdle rates: Legal documentation of project finance agreements This is an indicative list and intended to be illustrative of the preferred kind of evidence. We will consider a range of evidence sources but unverified data may have to be discounted based on our assessment of its reliability. Commercially sensitive data will not be made public.

A review of DECC s Impact Assessment of Feed-in-Tariff rates for small-scale renewables

A review of DECC s Impact Assessment of Feed-in-Tariff rates for small-scale renewables A review of DECC s Impact Assessment of Feed-in-Tariff rates for small-scale renewables A report for the British Photovoltaic Association 22 October 2015 Cambridge Econometrics Covent Garden Cambridge

More information

Feed in Tariff (FIT) Terms and Conditions

Feed in Tariff (FIT) Terms and Conditions Feed in Tariff (FIT) Terms and Conditions 1. Definitions The following definitions shall apply: Accreditation means the process of accreditation via either the MCS or ROO-FIT route and Accredited shall

More information

Checklist for PV Installations Feb 2012

Checklist for PV Installations Feb 2012 Checklist for PV Installations Feb 2012 Installation of Solar Photovoltaic systems (PV) can generate an income in the form of the Feed In Tariff, which is paid for every kwh generated, plus a separate

More information

Domestic Feed in Tariff (FIT) Terms and Conditions

Domestic Feed in Tariff (FIT) Terms and Conditions Domestic Feed in Tariff (FIT) Terms and Conditions 1. Definitions The following definitions shall apply: Accreditation means the process of accreditation via either the MCS or ROO-FIT route and Accredited

More information

The Renewable Heat Incentive. A reformed and refocussed scheme SVT Response

The Renewable Heat Incentive. A reformed and refocussed scheme SVT Response The Renewable Heat Incentive A reformed and refocussed scheme SVT Response Neil Liddell-Young 27 th April 2016 No. Question Response 1 Do you agree with the proposed policy approach for degression and

More information

Contract length analysis for Feed-in Tariff with Contracts for Difference. Summary of onshore and offshore wind analysis

Contract length analysis for Feed-in Tariff with Contracts for Difference. Summary of onshore and offshore wind analysis Contract length analysis for Feed-in Tariff with Contracts for Difference Summary of onshore and offshore wind analysis August 2013 Contract length analysis for Feed-in Tariff with Contracts for Difference

More information

What next for UK auctions of renewable Contracts for Difference?

What next for UK auctions of renewable Contracts for Difference? What next for UK auctions of renewable Contracts for Difference? In February we saw the results of the first competitive auction for Contracts for Difference (CfDs), the primary support mechanism for incentivising

More information

First Utility Feed-in Tariffs v3

First Utility Feed-in Tariffs v3 Feed-In Tariff Statement of Terms Please read these terms carefully 1 Definitions Accreditation MCS Microgeneration Certification Scheme, which certifies Microgeneration products and installers in accordance

More information

REA response to Consultation on Minima and Maxima in the CfD Allocation Process

REA response to Consultation on Minima and Maxima in the CfD Allocation Process REA response to Consultation on Minima and Maxima in the CfD Allocation Process The Renewable Energy Association (REA) is pleased to submit this response to the above consultation. The REA represents a

More information

Solar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net demand profiling

Solar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net demand profiling Sources: www.engineersjournal.ie; www.investopedia.com; www.theguardian.com Solar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net

More information

The role of electricity demand reduction in managing Levy Control Framework costs

The role of electricity demand reduction in managing Levy Control Framework costs BRIEFING PAPER, October 2013 The role of electricity demand reduction in managing Levy Control Framework costs Simon Skillings, Senior Associate, E3G 1 > There is a risk that offshore wind projects will

More information

THAMESWEY SOLAR LIMITED

THAMESWEY SOLAR LIMITED THAMESWEY SOLAR LIMITED BUSINESS PLAN 2017-19 Address: 2 nd Floor, Gloucester Chambers, Jubilee Square, Woking, Surrey GU21 6GA Registered Address: The St Botolph Building, 138 Houndsditch, London, EC3A

More information

Change of Ownership for Feed in Tariffs (FIT) Form Change of Responsibility Form First Utility accepts no liability for the accuracy for this form.

Change of Ownership for Feed in Tariffs (FIT) Form Change of Responsibility Form First Utility accepts no liability for the accuracy for this form. This form should be used to notify First Utility of transfer of responsibility from the FIT Generator to another party. Examples might be where a FIT Generator no longer resides at the installation address

More information

Feed-in Tariff (FiT) Terms and Conditions Last updated 16 May 2016

Feed-in Tariff (FiT) Terms and Conditions Last updated 16 May 2016 Feed-in Tariff (FiT) Terms and Conditions Last updated 16 May 2016 1. How this Agreement works 1.1 This Agreement (including your FiT Plan and any appendices) is between you and us. It s important for

More information

TNUoS Forecasting Seminar. National Grid House, Warwick 23 November 2017

TNUoS Forecasting Seminar. National Grid House, Warwick 23 November 2017 TNUoS Forecasting Seminar National Grid House, Warwick 23 November 2017 0 Welcome Paul Wakeley Revenue Manager 1 Housekeeping 2 National Grid TNUoS Team Louise Schmitz Oversees the TNUoS and the CUSC Development

More information

STANDARD FEED IN TARIFF (FIT) STATEMENT OF TERMS for Green Energy (UK) plc

STANDARD FEED IN TARIFF (FIT) STATEMENT OF TERMS for Green Energy (UK) plc STANDARD FEED IN TARIFF (FIT) STATEMENT OF TERMS for Green Energy (UK) plc These general statement of terms for the generation and export (where applicable) feed-in-tariff by Green Energy (UK) plc (the

More information

SSE FEED IN TARIFF (FIT) STATEMENT OF TERMS

SSE FEED IN TARIFF (FIT) STATEMENT OF TERMS SSE FEED IN TARIFF (FIT) STATEMENT OF TERMS This FIT Statement of Terms for the provision of Generation and Export (where applicable) Feed-in-Tariffs by SSE Energy Supply Limited (trading as Southern Electric,

More information

Introduction to EMR for New Suppliers. Thursday 3 December 2015

Introduction to EMR for New Suppliers. Thursday 3 December 2015 Introduction to EMR for New Suppliers Thursday 3 December 2015 Agenda Item Time Lead Welcome and information about the day 10.15 LCCC Overview of Electricity Market Reform 10.20 LCCC The LCCC Forecasting

More information

TNUoS Tariffs in 10 minutes March 2018

TNUoS Tariffs in 10 minutes March 2018 TNUoS s in 10 minutes March 2018 An overview of TNUoS tariffs This information paper provides an overview of National Grid s Transmission Network Use of System (TNUoS) tariffs, applicable to transmission

More information

Further information on mid-year tariff changes following the September 2010 Customer Seminars

Further information on mid-year tariff changes following the September 2010 Customer Seminars Further information on mid-year tariff changes following the September 2010 Customer Seminars National Grid received a number of questions at the Customer Seminars on National Grid s proposal to update

More information

Introduction to EMR Arrangements. Thursday 18 May 2017

Introduction to EMR Arrangements. Thursday 18 May 2017 Introduction to EMR Arrangements Thursday 18 May 2017 Welcome Health & Safety Agenda Item Time Lead Registration 09.30 EMRS Welcome 10.00 EMRS Overview of Electricity Market Reform 10.05 LCCC Forecasting

More information

REPORT TO THE PUBLIC UTILITIES BOARD

REPORT TO THE PUBLIC UTILITIES BOARD REPORT TO THE PUBLIC UTILITIES BOARD CURTAILABLE RATE PROGRAM APRIL 1, 2011 MARCH 31, 2012 JULY 2012 TABLE OF CONTENTS Page No. SUMMARY... 1 BACKGROUND... 1 PERFORMANCE FOR 2011/12... 3 Curtailment Options...3

More information

The Energiesprong concept is based on the assumption that the capital investment required to deliver net-zero-energy refurbishments is covered by:

The Energiesprong concept is based on the assumption that the capital investment required to deliver net-zero-energy refurbishments is covered by: Energiesprong UK Limited National Energy Centre Davy Avenue, Knowlhill Milton Keynes MK5 8NG 30 November 2015 Energiesprong UK finance model London Introduction The purpose of the financial model is to

More information

The Levy Control Framework

The Levy Control Framework Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 Our vision is to help the nation spend wisely. Our

More information

Value of DER. Con Edison and Orange & Rockland. Developer Workshop

Value of DER. Con Edison and Orange & Rockland. Developer Workshop Value of DER Con Edison and Orange & Rockland Developer Workshop July 24, 2017 1 Housekeeping In case of emergency Dial 911 or alert the Security Desk Con Edison s TLC Address: 43-82 Vernon Blvd, LIC,

More information

Welcome. Welcome to the VDER Phase I Solar Installer Roundtable Info Session April 26, 2017

Welcome. Welcome to the VDER Phase I Solar Installer Roundtable Info Session April 26, 2017 Welcome Welcome to the VDER Phase I Solar Installer Roundtable Info Session April 26, 2017 1 Installed Capacity, MW Installed Capacity, MW State of the Market 150 100 50 0 NYC Installed Capacity by Borough

More information

2010 No. 678 ELECTRICITY. The Feed-in Tariffs (Specified Maximum Capacity and Functions) Order 2010

2010 No. 678 ELECTRICITY. The Feed-in Tariffs (Specified Maximum Capacity and Functions) Order 2010 STATUTORY INSTRUMENTS 2010 No. 678 ELECTRICITY The Feed-in Tariffs (Specified Maximum Capacity and Functions) Order 2010 Made - - - - 8th March 2010 Laid before Parliament 9th March 2010 Coming into force

More information

Brexit and electricity interconnectors. Jason Mann

Brexit and electricity interconnectors. Jason Mann Brexit and electricity interconnectors Jason Mann 12 May 2018 Expansion of UK interconnection capacity driven by strong fundamentals and benign policies - but complicated by Brexit Mounting political pressures

More information

THE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM FOR NON-RESIDENTIAL CUSTOMERS

THE NARRAGANSETT ELECTRIC COMPANY RENEWABLE ENERGY GROWTH PROGRAM FOR NON-RESIDENTIAL CUSTOMERS Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to

More information

Whereas, solar energy is an abundant, domestic, renewable, and non-polluting energy resource.

Whereas, solar energy is an abundant, domestic, renewable, and non-polluting energy resource. An Act Relating to the Establishment of a Community Solar Program For Vertically-Integrated States Whereas, solar energy is an abundant, domestic, renewable, and non-polluting energy resource. Whereas,

More information

Offshore Wind Cost Reduction: Findings of The Crown Estate and the Cost Reduction Taskforce

Offshore Wind Cost Reduction: Findings of The Crown Estate and the Cost Reduction Taskforce Offshore Wind Cost Reduction: Findings of The Crown Estate and the Cost Reduction Taskforce BIEE Parker Seminar 10 th October 2012 Richard Howard, Chief Economist richard.howard@thecrownestate.co.uk CONTENTS

More information

A Closer Examination of Wind Generation in Ireland

A Closer Examination of Wind Generation in Ireland Industry Insight June 2015 A Closer Examination of Wind Generation in Ireland How the changing market is making it hard for generators to forecast revenues With enviable wind resources, ambitious renewables

More information

Targeted Charging Review. Andrew Self, Ofgem

Targeted Charging Review. Andrew Self, Ofgem Targeted Charging Review Andrew Self, Ofgem Targeted Charging Review: Significant Code Review, CFF Andrew Self TCR update Re-cap on the webinar content View on next steps Chance for questions Aim of today

More information

The QCA reviews the Gazetted Tariffs each year and the revised tariffs are applied from 1 July 2014.

The QCA reviews the Gazetted Tariffs each year and the revised tariffs are applied from 1 July 2014. FACTSHEET Q&A: Large Business Demand Tariffs Need information about business tariffs? Most customers in regional and rural Queensland are on a standard retail contract, paying regulated retail electricity

More information

Whereas, solar energy is an abundant, domestic, renewable, and non-polluting energy resource.

Whereas, solar energy is an abundant, domestic, renewable, and non-polluting energy resource. An Act Relating to the Establishment of a Community Solar Program For Restructured States Whereas, solar energy is an abundant, domestic, renewable, and non-polluting energy resource. Whereas, local solar

More information

Monthly Financial Report

Monthly Financial Report AGENDA ITEM NO: 4.C.1 Monthly Financial Report with data through February 2019 (Unaudited) The data contained in this report has not been independently audited. Alameda Municipal Power Financial Report

More information

Flexible Plug and Play

Flexible Plug and Play Flexible Plug and Play Understanding best practice regarding interruptible connections for wind generation: lessons from national and international experience Michael G. Pollitt, Karim L. Anaya EPRG-University

More information

How to get a CfD: Allocation Process and the Transition from the RO 11/06/14

How to get a CfD: Allocation Process and the Transition from the RO 11/06/14 How to get a CfD: Allocation Process and the Transition from the RO 11/06/14 Agenda 1. EMR objectives and the CfD instrument 2. CfD supported by a robust legislative architecture 3. Already attracting

More information

RE Growth Enrollment and Tariff Overview

RE Growth Enrollment and Tariff Overview RE Growth Enrollment and Tariff Overview Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Presentation

More information

Lessons from the Past

Lessons from the Past Lessons from the Past Country Specific Issues in Investment Arbitrations Tim Rauschning Vienna, 17 November 2017 Legal and Tax Advice www.luther-lawfirm.com Outline Background International Legal Framework

More information

Renewable Energy Guidance

Renewable Energy Guidance NewClimate Institute, Verra Renewable Energy Guidance Guidance for assessing the greenhouse gas impacts of renewable energy policies May 2018 How to describe the policy or action being assessed 5. DESCRIBING

More information

Gabriel Zeitouni, COWI A/S

Gabriel Zeitouni, COWI A/S Incentives for renewable energy investments through PPA contracts in Panama Introduction to PPA Assessment Tool Gabriel Zeitouni, COWI A/S 1 Who am I? Gabriel Zeitouni M.Sc. Sustainable Energy Wind Power

More information

Gas, oil and coal prices were subsidised by 3.63bn in 2010 Or were they? Wind power still gets lower public subsidies than fossil fuel tax breaks

Gas, oil and coal prices were subsidised by 3.63bn in 2010 Or were they? Wind power still gets lower public subsidies than fossil fuel tax breaks INTRODUCTION On 27 th February 2012, the UK national daily newspaper The Guardian published an article 1 headed Wind power still gets lower public subsidies than fossil fuel tax breaks Financial support

More information

2011 Budget Initial Stakeholder Call

2011 Budget Initial Stakeholder Call 2011 Budget Initial Stakeholder Call Michael Epstein Director of Financial Planning June 23, 2010 Agenda TOPIC PRESENTER Introduction Steve Berberich Budget principles & strategic initiatives Steve Berberich

More information

The following words and terms shall have the following meanings when used in this Tariff:

The following words and terms shall have the following meanings when used in this Tariff: Sheet 1 1. Introduction This tariff ( Tariff ) describes the terms and conditions under which an Applicant for an eligible distributed generation project ( DG Project ) will receive funding pursuant to

More information

How to treat requests to share grid connections

How to treat requests to share grid connections How to treat requests to share grid connections There may be a number of reasons why commercial generators might request to convert an existing grid offer into a shared arrangement. Some would be looked

More information

Schedule GTSR-GR Sheet 1 GREEN TARIFF SHARED RENEWABLES GREEN RATE

Schedule GTSR-GR Sheet 1 GREEN TARIFF SHARED RENEWABLES GREEN RATE Southern California Edison Revised Cal. PUC Sheet No. 59547-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 56750-E Schedule GTSR-GR Sheet 1 APPLICABILITY This Schedule is applicable

More information

Feed-in tariff determination Best practice and cross-country coordination

Feed-in tariff determination Best practice and cross-country coordination Feed-in tariff determination Best practice and cross-country coordination Dr. Corinna Klessmann, Ecofys 26 January 2012 9 th Workshop of the International Feed-in Cooperation (IFIC) Content I. Best practice

More information

November HSBC Green Bond Report

November HSBC Green Bond Report November 2018 2 Introduction It s no exaggeration to say green bonds are the pathfinder for the low carbon transition. And, speaking for HSBC, we are dedicated to promoting the principles that have shaped

More information

UK Onshore Wind. Investment Fundamentals

UK Onshore Wind.   Investment Fundamentals UK Onshore Wind www.fimltd.co.uk Investment Fundamentals Wind is a proven asset class for both private and institutional direct investors. UK wind provides investors with a low risk investment. It is 100%

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 58755-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 55676-E APPLICABILITY Schedule NEM-V Sheet 1 Applicable to Qualified Customers

More information

Monthly Financial Report

Monthly Financial Report AGENDA ITEM NO: 4.C.1 Monthly Financial Report with data through October 2017 (Unaudited) The data contained in this report has not been independently audited. Alameda Municipal Power Financial Report

More information

Investigation into the 2017 auction for low carbon electricity generation contracts

Investigation into the 2017 auction for low carbon electricity generation contracts A picture of the National Audit Office logo Report by the Comptroller and Auditor General Department for Business, Energy & Industrial Strategy Investigation into the 2017 auction for low carbon electricity

More information

Annex C Renewables Obligation transition

Annex C Renewables Obligation transition Annex C Renewables Obligation transition INTRODUCTION 188. The Government recognises that significant investments have been made under the current Renewables Obligation (RO), with around 9 GW of installed

More information

MHC s bold idea on solar premium feed-in tariff reform gaining traction in Queensland

MHC s bold idea on solar premium feed-in tariff reform gaining traction in Queensland Annual Installations ( 000) MHC Perspective MHC s bold idea on solar premium feedin tariff reform gaining traction in Queensland By Ryan Wavish and Lars Karlbom Emerging Issue: Following our article in

More information

REG Interim Results Six months ending 31 December th February 2014

REG Interim Results Six months ending 31 December th February 2014 REG Interim Results Six months ending 31 December 2013 10 th February 2014 Andrew Whalley David Crockford Chief Executive Finance Director Introduction to REG REG is primarily a developer, owner and operator

More information

iles Hanglin savills.com

iles Hanglin savills.com ommunicating the Real Value of Solar Assets arge-scale Solar UK 2015 iles Hanglin savills.com OLAR ROOFTOP INVESTMENT 1 UK Energy Supply and the Issues 2 UK Property and the Solar Solutions? 3 The Investment

More information

Solar Bond Case Study

Solar Bond Case Study Solar Bond Case Study Andy Heald, Co-Founder, Generation Community www.apse.org.uk Social finance for solar energy Gen Community 30 th October 2014 Oxford Andy Heald Director Gen Community Generating community

More information

Investigation into the 2017 auction for low carbon electricity generation contracts

Investigation into the 2017 auction for low carbon electricity generation contracts A picture of the National Audit Office logo Report by the Comptroller and Auditor General Department for Business, Energy & Industrial Strategy Investigation into the 2017 auction for low carbon electricity

More information

Unipro PJSC 2016 Full year results

Unipro PJSC 2016 Full year results Unipro PJSC 2016 Full year results 16 March 2017 2016 results stable operating earnings hit by a one off effect EBITDA 1,2 EBIT 1,2 Highlights 24.9bn 17.7bn 12M 2015 12M 2016 17.4bn 12M 2015 11.0bn 12M

More information

Community Solar Rate Rider: Schedule No February 13, 2018

Community Solar Rate Rider: Schedule No February 13, 2018 Community Solar Rate Rider: Schedule No. 500 February 13, 2018 1 Community Solar Agenda Design Principles Program Highlights Pricing Methodology Example Customer Impact Conclusion Next Steps 2 Design Principles

More information

FP FORESIGHT UK INFRASTRUCTURE INCOME FUND

FP FORESIGHT UK INFRASTRUCTURE INCOME FUND FP FORESIGHT UK INFRASTRUCTURE INCOME FUND Targeting annual income of 5% through active management of UK listed renewable energy and infrastructure investment companies. INVESTOR GUIDE This Investor Guide

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 64404-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58701-E Schedule MASH-VNM Sheet 1 APPLICABILITY Applicable to Qualified

More information

Interruptible connections: Lessons from Flexible Plug and Play. Sotiris Georgiopoulos

Interruptible connections: Lessons from Flexible Plug and Play. Sotiris Georgiopoulos Interruptible connections: Lessons from Flexible Plug and Play Sotiris Georgiopoulos Flexible Plug and Play Objective: Cheaper and faster connection of DG to constrained parts of the network by trialing

More information

Performance-Based Ratemaking

Performance-Based Ratemaking Performance-Based Ratemaking Rhode Island Utility Business Models Discussion April 24, 2017 Tim Woolf Consultant for the Division of Public Utilities and Carriers Outline Financial incentives under traditional

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 58755-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 55676-E Schedule NEM-V Sheet 1 APPLICABILITY Applicable to Qualified Customers

More information

GET FIT Programme. Energy Sector Working Group. Maputo, 25 May Julia Crause Infrastructure, Southern Africa KfW Development Bank

GET FIT Programme. Energy Sector Working Group. Maputo, 25 May Julia Crause Infrastructure, Southern Africa KfW Development Bank GET FIT Programme Energy Sector Working Group Maputo, 25 May 2016 Julia Crause Infrastructure, Southern Africa KfW Development Bank Agenda 1 GET FIT Uganda Results and Approach 2 Potential GET FiT Programme

More information

Actual neighborhood of Sunrun customer homes

Actual neighborhood of Sunrun customer homes This presentation contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Forward-looking statements

More information

Second Quarter 2016 Supplementary Slides

Second Quarter 2016 Supplementary Slides Second Quarter 2016 Supplementary Slides August 9, 2016 2016 SunPower Corporation Safe Harbor Statement This presentation contains forward-looking statements within the meaning of the Private Securities

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 64409-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58722-E Schedule NEM Sheet 1 APPLICABILITY Applicable to Eligible Customer-Generators

More information

Summary of Value of Distributed Energy Resources Phase 1 Order

Summary of Value of Distributed Energy Resources Phase 1 Order Summary of Value of Distributed Energy Resources Phase 1 Order Context of Order 2 As part of Reforming the Energy Vision (REV), NYS is transitioning away from net energy metering (NEM) NYS Public Service

More information

All Energy 2015 CfD: The New Normal?

All Energy 2015 CfD: The New Normal? All Energy 2015 CfD: The New Normal? Sarah-Jane McArthur, Associate 6 May 2015 Key Themes CfD 101 Reflections on allocation process Reflections on the auction outcome What next for the winners What next

More information

1: Levelized Cost of Energy. Calculation. Methodology and Sensitivity

1: Levelized Cost of Energy. Calculation. Methodology and Sensitivity 1: Levelized Cost of Energy Calculation Methodology and Sensitivity What is LCOE? Levelized Cost of Energy (LCOE) is the constant unit cost (per kwh or MWh) of a payment stream that has the same present

More information

Installed Capacity (ICAP) Market

Installed Capacity (ICAP) Market Installed Capacity (ICAP) Market Amanda Carney Associate Market Design Specialist, Capacity Market Design, NYISO New York Market Orientation Course (NYMOC) October 16-19, 2018 Rensselaer, NY 1 ICAP Market

More information

D2.6 Business Model Report

D2.6 Business Model Report D2.6 Business Model Report United Kingdom An analysis of future viable business models in a lower-subsidy world This project has received funding from the European Union s Horizon 2020 research and innovation

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION, ITS COMPLIANCE AND IMPLEMENTATION OF RENEWABLE ENERGY CERTIFICATE FRAMEWORK)

More information

Thank you for the opportunity to comment on the Review of the Solar Bonus Scheme.

Thank you for the opportunity to comment on the Review of the Solar Bonus Scheme. 29 September 2010 Solar Bonus Review Industry & Investment NSW Level 17, 227 Elizabeth Street Sydney, NSW 2000 Solarbonus.review@industry.nsw.gov.au Thank you for the opportunity to comment on the Review

More information

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016 The Economics and Financing of Distributed Generation Investment Budapest, Hungary November 17, 2016 Topics to Cover How to Finance Distributed Generation Investments 1 Importance of financial aspects

More information

Supporting investments into renewable electricity in context of deep market integration of RES-e after 2020:

Supporting investments into renewable electricity in context of deep market integration of RES-e after 2020: Supporting investments into renewable electricity in context of deep market integration of RES-e after 2020: Study on EU-, regional- and national-level options FINAL REPORT 1 Disclaimer The information

More information

CAPITAL MARKETS DAY Deutsches Eigenkapitalforum Frankfurt / Main,

CAPITAL MARKETS DAY Deutsches Eigenkapitalforum Frankfurt / Main, CAPITAL MARKETS DAY 2018 71 86 100 118 150 2202020 5002025 Deutsches Eigenkapitalforum Frankfurt / Main, 28.11.2018 1 DISCLAIMER This presentation is for information purposes only and does not constitute

More information

09 MAY 2017 MEDIA STATEMENT NAMPOWER TARIFF ADJUSTMENT FOR THE FINANCIAL PERIOD 2017/2018

09 MAY 2017 MEDIA STATEMENT NAMPOWER TARIFF ADJUSTMENT FOR THE FINANCIAL PERIOD 2017/2018 09 MAY 2017 MEDIA STATEMENT NAMPOWER TARIFF ADJUSTMENT FOR THE FINANCIAL PERIOD 2017/2018 MEMBERS OF THE MEDIA, COLLEAGUES, LADIES & GENTLEMEN It is my honour to announce that the Board of Directors of

More information

Eskom Presentation Standing Committee on Appropriations

Eskom Presentation Standing Committee on Appropriations Eskom Presentation Standing Committee on Appropriations 12 June 2015 Contents Content 1. Introduction 2. Financial situation 3. Eliminating Load shedding 2 Executive summary (1 of 2) Eskom is a fully integrated

More information

2019 Budget and Grid Management Charge Initial Stakeholder Meeting

2019 Budget and Grid Management Charge Initial Stakeholder Meeting 2019 Budget and Grid Management Charge Initial Stakeholder Meeting July 24, 2018 Agenda Topic: Welcome and Introductions Presenter: Kristina Osborne 2019 Budget Process & GMC Rate Outlook April Gordon

More information

GREEK RENEWABLES SUPPORT SCHEME PROPOSALS

GREEK RENEWABLES SUPPORT SCHEME PROPOSALS BRIEFING GREEK RENEWABLES SUPPORT SCHEME PROPOSALS MARCH 2016 BRIEF OUTLINE OF THE SCHEME PHOTOVOLTAIC PROJECTS TRANSITIONAL PROVISIONS NON-INTERCONNECTED ISLANDS COMPETITIVE BIDDING PROCESS FROM 2017

More information

PPL CORPORATION Poised for growth. Investing in our future.

PPL CORPORATION Poised for growth. Investing in our future. PPL CORPORATION Poised for growth. Investing in our future. 2nd Quarter Earnings Call August 3, 2017 Cautionary Statements and Factors That May Affect Future Results Any statements made in this presentation

More information

Brooklyn Queens Demand Management Demand Response Forum

Brooklyn Queens Demand Management Demand Response Forum Brooklyn Queens Demand Management Demand Response Forum Start Time: 2:00 PM Networking reception to follow presentation To receive future BQDM updates please subscribe to our mailing list: https://conedbqdmauction.com/subscribe

More information

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Support mechanisms for RES-e

Support mechanisms for RES-e Support mechanisms for RES-e Regional ECREEE Training Workshop on National Renewable Energy Policy and Incentive Schemes Praia, 9-11 April 2012 Sofía Martínez International Relations Department Table of

More information

RIDER 783 ADJUSTMENT OF CHARGES FOR DEMAND SIDE MANAGEMENT ADJUSTMENT MECHANISM

RIDER 783 ADJUSTMENT OF CHARGES FOR DEMAND SIDE MANAGEMENT ADJUSTMENT MECHANISM NORTHERN INDIANA PUBLIC SERVICE COMPANY First Revised Sheet No. 222 Original Volume No. 13 Original Sheet No. 222 TO WHOM AVAILABLE DEMAND SIDE MANAGEMENT ADJUSTMENT MECHANISM This Rider shall be applicable

More information

Brooklyn Queens Demand Management Demand Response Webinar

Brooklyn Queens Demand Management Demand Response Webinar Brooklyn Queens Demand Management Demand Response Webinar Start Time: 10:00 AM To receive future BQDM updates please subscribe to our mailing list: https://conedbqdmauction.com/subscribe Please see our

More information

Choosing Appropriate Incentives to Deploy Renewable Energy

Choosing Appropriate Incentives to Deploy Renewable Energy Choosing Appropriate Incentives to Deploy Renewable Energy Workshop, World Bank Headquarters Global Head of Climate Change Investment Research Climate Change Advisors http://www.dbcca.com/research January

More information

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and

More information

Downing Renewables EIS. Half-Yearly Report for the six months ended 30 September 2014

Downing Renewables EIS. Half-Yearly Report for the six months ended 30 September 2014 Downing EIS Half-Yearly Report for the six months ended 30 September 2014 About the Service Introduction Downing EIS initially launched in September 2012 to provide investors with access to investments

More information

Weiqiao Textile Company Limited Interim Results Presentation 16 September 2008

Weiqiao Textile Company Limited Interim Results Presentation 16 September 2008 Weiqiao Textile Company Limited 2008 Interim Results Presentation 16 September 2008 2 Disclaimer This presentation may include certain forward-looking statements. The actual results or development of Weiqiao

More information

Renewable Energy Fund

Renewable Energy Fund For discussion purposes only not suitable for retail clients Renewable Energy Fund Trusted Alternatives Summary Document March 2013 Under The Enterprise Investment Scheme Summary Document The following

More information

SMA SOLAR TECHNOLOGY AG Analyst / Investor Presentation: Macquarie Green Energy Conference / Roadshow London

SMA SOLAR TECHNOLOGY AG Analyst / Investor Presentation: Macquarie Green Energy Conference / Roadshow London SMA SOLAR TECHNOLOGY AG Analyst / Investor Presentation: Macquarie Green Energy Conference / Roadshow London Pierre-Pascal Urbon, CEO Ulrich Hadding, CFO October 5-6, 2018 SMA Solar Technology AG Disclaimer

More information

GOVERNMENT OF PUERTO RICO STATE OFFICE OF ENERGY POLICY. GREEN ENERGY FUND Tier 2 Reference Guide (Revised on September 24, 2014)

GOVERNMENT OF PUERTO RICO STATE OFFICE OF ENERGY POLICY. GREEN ENERGY FUND Tier 2 Reference Guide (Revised on September 24, 2014) GOVERNMENT OF PUERTO RICO STATE OFFICE OF ENERGY POLICY GREEN ENERGY FUND Tier 2 Reference Guide (Revised on September 24, 2014) TABLE OF CONTENTS CHAPTER ONE GENERAL... 1 I. Title and Introduction...

More information

FOCUS ON EDF EN Analyst Group Lunch Meeting - 6 July 2017

FOCUS ON EDF EN Analyst Group Lunch Meeting - 6 July 2017 FOCUS ON EDF EN Analyst Group Lunch Meeting - 6 July 2017 Antoine Cahuzac - Group Senior Executive VP of Renewable Energies and CEO of EDF Énergies Nouvelles Bruno Fyot COO of EDF EN Denis Rouhier CFO

More information

CMA Report and Summer Budget Implications for the UK energy sector July 2015

CMA Report and Summer Budget Implications for the UK energy sector July 2015 CMA Report and Summer Budget 2015 Implications for the UK energy sector July 2015 Two announcements this week are likely to have big implications for the way the UK energy market evolves over the next

More information

H results. innogy SE 11 August 2017 Bernhard Günther CFO

H results. innogy SE 11 August 2017 Bernhard Günther CFO H1 2017 results innogy SE 11 August 2017 Bernhard Günther CFO Notice This document contains forward-looking statements. These statements are based on the current views, expectations, assumptions and information

More information