Cost Recovery Issues After A Termination For Convenience
|
|
- Ralph Bridges
- 5 years ago
- Views:
Transcription
1
2 Cost Recovery Issues After A Termination For Convenience Breakout Session # C15 Leslie Anderson, Program Manager, BAE Systems Greg Bingham, Vice President, The Kenrich Group Chelsea Taylor, Manager, The Kenrich Group July 28, :00pm
3 Agenda 1. Overview of Termination for Convenience Issues 2. FAR 49.1 General Principles 3. FAR 49.2 Additional Principles for Fixed-Price Contracts 4. FAR 49.3 Additional Principles for Cost-Reimbursement Contracts 5. FAR Termination Cost Principle 6. FAR Part 12 Commercial Item Termination 7. Audit Issues in Terminations for Convenience 8. Questions & Answers 2
4 Termination for Convenience - Overview Federal Acquisition Regulation (FAR) requires that a Termination for Convenience clause be included in most federal procurement contracts. This grants the Government the right to terminate contracts, or partially terminate contracts, for convenience. 3
5 Overview of Termination Process The Process for terminating a contract for convenience is specified in FAR Part 49. Contracting Officer must send a written Termination Notice to the contractor. Upon receiving the Notice of Termination, the contractor is required to stop all work immediately under the terminated portion of the contract, and terminate all related subcontracts. 4
6 Overview of Termination Process The contractor must deliver to the Government a Termination Inventory that lists materials produced or acquired under the contract and Government-furnished property and account for all inventory related to the terminated portion of the contract. Contractor must dispose of all remaining property. Contractor also begins the process of settling with its subcontractors. 5
7 Termination Settlement The contractor has one year from the effective date of the termination to submit a settlement proposal to the Contracting Officer. The amount of the settlement proposal reflects all of the costs for which the contractor believes it is entitled to be reimbursed. 6
8 Details of Termination Process FAR Part 49 Subpart General Principles Subpart Additional Principles for Fixed-Price Contracts Terminated for Convenience Subpart Additional Principles for Cost- Reimbursement Contracts Terminated for Convenience Subpart Termination for Default Subpart Contract Termination Clauses Subpart Contract Termination Forms and Formats 7
9 General Principals FAR Contractor Responsibilities Stop Work Immediately Terminate All Subcontractors Advise TCO of Special Circumstances Precluding Work Stoppage Perform the Continued Portion of the Contract Protect and Preserve Government Property Notify the TCO of any Legal Proceedings Settle with Subcontractors/Suppliers (Subject to TCO Approval) Submit a Termination Settlement Proposal (TSP) Dispose of Termination Inventory 8
10 General Principals Additional Termination Activities Cost Accumulation Budgeting/Forecasting Inventory Identification and Classification Data Management Reductions in Force Training/Reassignment Any Other Tasks Requested by TCO 9
11 General Principals FAR Partial Payments Available after submission of Interim or Final TSP if authorized in the contract Submit requests on SF 1440 No fee on SF 1440 terminated effort, except for undelivered acceptable finished product SF 1440 eligible cost recovery ranges from 90% - 100% of costs incurred 10
12 Details of Termination Process FAR Part 49 Subpart General Principles Subpart Additional Principles for Fixed-Price Contracts Terminated for Convenience Subpart Additional Principles for Cost- Reimbursement Contracts Terminated for Convenience Subpart Termination for Default Subpart Contract Termination Clauses Subpart Contract Termination Forms and Formats 11
13 Fixed-Price Contracts FAR Subpart 49.2 Key Points FAR Reference Settlement Profit Factors Loss Contract Recovery Adjustment Settlement Proposal Bases
14 The Fair Compensation Principle "A settlement should compensate the contractor fairly for the work done and the preparations made for the terminated portion of the contract, including a reasonable allowance for profit. (Emphasis Added) FAR (a) See also - FAR (c) Settlement proposals must be in reasonable detail supported by adequate accounting data.... When actual, standard, or average costs are not reasonably available, estimated costs may be used... And - FAR (d) If an overall settlement of costs is agreed upon, agreement on each element of cost is not necessary... 13
15 Do the Cost Principles Apply? YES - Relevant clauses read that all termination costs shall be in accordance with the applicable Cost Principle (See FAR ) NO - See the Fair Compensation Principle at FAR YES / NO - See case law precedent 14
16 Settlement Profit Factors FAR (b) 1. Extent and difficulty of work performed as compared with the total contract requirements 2. Engineering work, production scheduling, planning, technical study and supervision 3. Contractor efficiency related to (i) quality, (ii) cost reduction, (iii) resource management and (iv) inventory disposal 4. Capital investment and risk assumed 5. Inventive and developmental contributions 15
17 Settlement Profit Factors FAR (b), (cont.) 6. Complexity of manufacturing techniques 7. Contractor s profit rate assuming a completed contract 8. Profit rate contemplated by the parties during contract negotiations 9. Subcontracting environment, including effort to negotiate settlements of terminated subcontracts Summary: Broad TCO discretion to determine profit 16
18 Equitable Adjustment After Partial Termination FAR Contractor may request an Equitable Adjustment on continued work Contracting Officer has authority, unless delegated to the TCO Follow Cost/Pricing Proposal Format (15.408) Costs included in a Request for Equitable Adjustment shall not also be included in the termination settlement proposal ( TSP ) Subcontractor shall complete TINA Certification 17
19 Details of Termination Process FAR Part 49 Subpart General Principles Subpart Additional Principles for Fixed-Price Contracts Terminated for Convenience Subpart Additional Principles for Cost- Reimbursement Contracts Terminated for Convenience Subpart Termination for Default Subpart Contract Termination Clauses Subpart Contract Termination Forms and Formats 18
20 Additional Principles for Cost Reimbursement Contracts FAR Subpart 49.3 Key Points FAR Reference Vouching Fee Adjustment
21 Vouching FAR Continue normal cost-reimbursement billing procedures after termination Voucher period ends the last day of the sixth month following the month of termination Creates incentive to maximize termination effort during voucher period 20
22 Fee Adjustment FAR a) Generally based on percent complete Considers extent and difficulty of work performed - Fee does not include subcontract effort included in subcontractor TSPs b) The ratio of costs incurred to the total estimated cost of performing the contract is only one factor in computing the percentage of completion. (49.115) Target Fee Applies 21
23 Contract Termination Forms FAR Subpart 49.6 Cost Type Fixed Price Form Form No. SF- Short Form Inventory Basis Total Cost Basis Amendment of Solicitation / Contract Modification 30 Inventory Schedule B 1428/29 Inventory Schedule E for Use With Short Form Settlements 1434 Inventory Basis Settlement Proposal 1435 Total Cost Basis Settlement Proposal 1436 Cost Reimbursement Settlement Proposal 1437 Short Form Settlement Proposal 1438 Schedule of Accounting Information 1439 Partial Payment Request
24 General Principles Cost Principles Use FAR Termination Costs - Contract terminations generally give rise to the incurrence of costs or the need for special treatment of costs that would not have arisen had the contract not been terminated. FAR (a) Common Items (b) Continuing Costs (c) Initial Costs (d) Loss of Useful Value (e) Rental Under Unexpired Leases (f) Alterations of Leased Property (g) Settlement Expenses (h) Subcontractor Claims 23
25 Common Items FAR (a) Transfer items to other work when reasonable Contemporaneous purchases indicate items are usable on other work Common items charged to termination should exceed requirements on other work 24
26 Cost Continuing After Termination FAR (b) Despite all reasonable efforts by the contractor, costs which cannot be discontinued immediately after the effective date of termination are generally allowable... Examples Include: - Idle Facilities - Unabsorbed or Extended Overhead - Severance Pay 25
27 Cost Continuing After Termination FAR Example Idle Facilities (b) The costs of idle facilities are unallowable unless the facilities (1) are necessary to meet fluctuations in workload; or (2) were necessary when acquired and are now idle because of changes in requirements, production economies, reorganization, termination, or other causes which could not have been reasonably foreseen
28 Cost Continuing After Termination FAR (g) Example Severance Pay (2) Severance pay is allowable only to the extent that, in each case, it is required by: (i) Law; (ii) Employer-Employee agreement; (iii) Established policy that constitutes, in effect, an implied agreement on the contractor s part; or (iv) Circumstances of the particular employment... 27
29 Cost Continuing After Termination Reduction in Force (RIF) Issues Separate policies for divisions/locations Differing benefits for each employee category Calculation of required reductions (all related to the termination?) Bumping (termination of personnel not assigned to the terminated contract) 28
30 Cost Continuing After Termination Reduction in Force (RIF) Issues (cont.) Relevant Costs Severance payments Job search costs Outplacement services COBRA benefits (subject to HIPAA restrictions) Key Issues: comply with policies and document steps taken 29
31 Termination Costs FAR (c) Initial Costs Starting Load & Preparatory Costs (c) Initial Costs. Initial costs, including starting load and preparatory costs, are allowable as follows: (1) Starting load costs not fully absorbed because of termination are nonrecurring labor, material, and related overhead costs incurred in the early part of production... (2) Preparatory costs incurred in preparing to perform the terminated contract include such costs as those incurred for initial plant rearrangement and alterations, management and personnel organization, and production planning... 30
32 Termination Costs FAR (d) Loss of Useful Value (d) Loss of useful value of special tooling, and special machinery and equipment is generally allowable, provided (1) the special tooling, or special machinery and equipment is not reasonably capable of use in other work of the contractor; (2) the Government s interest is protected by transfer of title. 31
33 Termination Costs FAR (e) Rental Under Unexpired Leases (e) Rental costs under unexpired leases, less the residual value of such leases, are generally allowable when shown to have been reasonably necessary for the performance of the terminated contract, if (1) the amount of rental claimed does not exceed the reasonable use value of the property...; and (2) the contractor makes all reasonable efforts to terminate, assign, settle, or otherwise reduce the cost of such lease. 32
34 Termination Costs FAR (f) Alteration of Leased Property (f) The cost of alterations and reasonable restorations required by the lease may be allowed when the alterations were necessary for performing the contract. 33
35 Termination Costs FAR (g) Settlement Expenses (1) Settlement expenses, including the following, are generally allowable: (i) Accounting, legal, clerical, and similar costs reasonably necessary for- (a) The preparation and presentation... of settlement claim to the Contracting Officer; and (b) The termination and settlement of subcontracts. (ii) Reasonable costs for the storage, transportation, protection, and disposition of property acquired or produced for the contract. (iii) Indirect costs related to salary and wages incurred as settlement expenses in (i) and (ii);... (2) If settlement expenses are significant, a cost account or work order shall be established to separately identify and accumulate them. 34
36 Termination Costs FAR (h) Settlement with Subcontractors Limited to settlements allocable to the termination ( ) Appropriate Indirect Costs (31.203) Proportionate to benefits received Not claimed elsewhere Contractor does not earn profit on subcontract effort included in the termination settlement proposal 35
37 Termination Costs Reaccounting : A General Explanation The issue generally is the reclassifying of indirect costs to direct and the inclusion of them in a settlement proposal. The premature end of a contract can throw askew The Contractor s original business plans for cost absorption. This may necessitate a new approach to recovery of costs. 36
38 Commercial Item Termination FAR (a) General the requirements of Part 49 do not apply when terminating contracts for commercial items 37
39 Commercial Item Termination FAR (c) Termination For Cause (a) Notify Contracting Officer as soon as possible of any excusable delay (b) Government remedies (c) Written notice of termination from Contracting Officer 38
40 Commercial Item Termination FAR (d) Termination for the Government s Convenience the contractor shall be paid -- (i)(a) The percentage of the contract price reflecting the percentage of the work performed prior to the notice of the termination for fixed-price or fixed price with economic price adjustments, or (B) An amount for direct labor hours (as defined in the Schedule of the contract) determined by multiplying the number of direct labor hours expended before the effective date of termination by the hourly rate(s) in the Schedule; and 39 (ii) Any charges the contractor can demonstrate directly resulted from the termination. The contractor may demonstrate such charges using its standard record keeping system and is not required to comply with the cost accounting standards or the contract cost principles in Part 31. The Government does not have any right to audit the contractor s records solely because of the termination for convenience.
41 Audit Issues Encountered After A Termination 1. Limitation of Funds vs. Termination Responsibilities which contract clause rules? 2. Funding for lower-tier suppliers and subcontractors 3. Unsettled contract changes with Lower-Tier or Upper-Tier Contractors (e.g., undefinitized changes, Requests For Equitable Adjustments) 4. Scope of Ongoing Work (e.g., charge numbers, scope definition, continuing to voucher past the six month period) 5. Form of Termination Settlement proposal on fixed-price contracts (i.e., SF 1435 Inventory Basis vs. SF 1436 Total Cost Basis) 40
42 Audit Issues Continued 6. Recovery of the cost of layoffs and severance (e.g., demonstrating that the termination caused the severance, how much of the severance cost should the terminated contract bear) 7. Cash Flow Issues (e.g., vouchering for six months, SF 1440 Application for Partial Payment, Recovery Of Settlement Expenses, and Settlements with Subcontractors) 8. Inventory (e.g., Ongoing Protection, Physical Count, Spoilage, Inventory Schedules Within 120 Days) 9. Auditing of subcontractors who are also competitors (e.g., obtaining Cost or Pricing Data, DCAA Audits, Third Party Audits) 41
43 Audit Issues Continued 10. Fee on Cost-Plus Contracts and FAR Fixed fee and measurement of completion percentage Award fee and the application of award fee plans which do not anticipate termination 11. Profit on fixed-price contracts and the nine factors at FAR Loss on fixed-price contracts and the loss ratio provisions of FAR Termination Forms (e.g., SF1439 Schedule of Accounting Information) 42
44 Audit Issues Continued 14. Dealing with DCAA Audit Reports Extensive qualifications or limitations We do not consider to be acceptable as the basis for the settlement of a fair and reasonable amount. Extensive delay in conducting audit 15. Fraud Referrals and other allegations 16. Records Retention 17. Reliance on copies 43
45 Audit Issues Continued 18. Interpretation of FAR (d) 19. Questioning completion of work 20. DCAA s audit standards compared to preponderance of the evidence 21. Settlement Negotiation Memorandum and FAR and FAR Settling prior to the finalization of indirect rates 23. Settlement contingent on subcontractor settlements or other issues 44
46 Audit Issues Continued Interpretation of FAR (d) A contractor is responsible for accounting for costs appropriately and for maintaining records, including supporting documentation, adequate to demonstrate that costs claimed have been incurred, are allocable to the contract, and comply with applicable cost principles in this subpart and agency supplements. The Contracting officer may disallow all or part of a claimed cost that is inadequately supported 45
47 Audit Issues Continued Reliance on copies [The Contractor] did not maintain original source documentation for all transaction selected for testing [S]upport provided included documentation received by [the Contractor] in an electronic formation (invoices received via ). [W]e are unable to evaluate [the Contractor s] process for maintaining the integrity of documents received electronically. Accordingly, we were unable to determine whether reliance could be placed on the copies provided and relied on during our audit. Example DCAA Audit Report 46
48 Greg Bingham Greg Bingham is a Vice President with The Kenrich Group, LLC. He has over 25 years of experience in the fields of business and litigation consulting including investigation of allegations of fraud or overbilling. Professional Experience Mr. Bingham has assisted clients on Government Contract matters including: 1) regulatory consulting on allowable costs issues arising from the Cost Principles found at Part 31 of the Federal Acquisition Regulation ( FAR ) as well as allocation of cost issues associated with the Cost Accounting Standards ( CAS ), 2) consulting on matters involving allegations of defective pricing, false claims, mischarges and other improper billings to the Government, 3) the Earned Value Management Systems requirements of Department of Defense regulation R (April 5, 2002), 4) financial statement and special purpose auditing, 5) management consulting and 6) Foreign Military Sales issues and foreign sales issues. This experience has provided him with substantial knowledge of the program management, financial and accounting records and systems maintained by companies who sell to the Federal Government. Greg s work has included the quantification of cost impacts and negotiation with Government auditors and oversight personnel. Greg has planned and performed reviews of various defense contractors systems including material management, accounting, inventory and internal policies and procedures along with the evaluation of operating inefficiencies and internal control deficiencies. Masters of Business Administration University of Texas at Austin Bachelor of Science in Electrical Engineering University of Kentucky Contact Information: 1919 M Street, NW Suite 620 Washington, DC Tel: (202) Fax: (202) gbingham@kenrichgroup.com 47
49 Selected Termination Experience Future Combat System Termination. Various roles. Army Armed Reconnaissance Helicopter (ARH)-70A Termination USPS Convenience Termination and Dispute with Subcontractor Convenience Termination of Crusader Artillery Program. Oversaw evaluation and settlement with approximately 50 subcontractors A-12 Termination. Primary Focus was More Than Three Hundred Subcontractors and Suppliers Convenience Termination of Power Plant Construction Project Compaq v Hardware Technologies Dispute Over Convenience Termination of IDIQ Contract Earth Tech v IT Corporation Dispute Over Costs in Convenience Termination of IDIQ Contract InTown Termination for Default Overturned and Convenience Termination Settlement. Provided Testimony at Mediation Which Proved Successful Obayashi Super Collider Convenience Termination Raytheon v Datatape Termination of Subcontractor for Default. Default Converted to Convenience. Evaluated Termination for Convenience Claims Raytheon Default Termination and Claims 48
50 Chelsea Taylor Chelsea Taylor is a Manager with The Kenrich Group, LLC. She is a Certified Fraud Examiner with extensive experience in government contracts, construction, utilities, and other commercial industries. The support she provides to clients has included compliance review, damages analysis, and litigation support.. Professional Experience Chelsea has worked on multiple government contract matters helping government contractors with: (1) consulting on compliance with FAR Part 31 Cost Principles for Government audits and disputes between contractors and the Government; (2) the preparation, review, and negotiation of termination settlement proposals (TSPs), (3) the preparation and review of Incurred Cost Submissions; (4) preparation, review, and analysis of Requests for Equitable Adjustment ( REAs ) and claims; (5) damages analysis resulting from defective pricing, false claims, Truth in Negotiations Act (TINA) claims, Contract Disputes Act (CDA) claims, and (6) analyzing cost realism in bid protests, among other matters. Bachelor of Science in Commerce, with Concentrations in Finance and International Business University of Virginia Contact Information: 1919 M Street, NW Suite 620 Washington, DC Tel: (202) Fax: (202) ctaylor@kenrichgroup.com Chelsea s experience in terminations has included auditing TSPs in accordance with FAR Part 49 and CAM Chapter 12, as well as other termination-related regulations. Chelsea has also assisted clients in negotiations with the client s prime contractor, the Government s Termination Contracting Officer, and negotiating termination settlements with hundreds of lower-tier subcontractors with TSPs ranging from the hundreds of dollars to the hundreds of millions of dollars. Chelsea has worked with numerous foreign suppliers in Canada, Belgium, Turkey, the United Arab Emirates, and the United Kingdom, among others. 49
51 Citations and Documents 1. Slides Relating to Termination for Convenience Issues 2. FAR 49.1 General Principles 3. FAR 49.2 Additional Principles for Fixed-Price Contracts 4. FAR 49.3 Additional Principles for Cost-Reimbursement Contracts 5. FAR Termination Cost Principle 6. FAR Termination Cost Reimbursement 7. Selected Termination Forms 8. DCAA Contract Audit Manual Chapter Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment Proposals or Claims (excerpt relating to terminations) 9. Administering Subcontracts After A Termination For Convenience, by Patricia Meagher and Greg Bingham, Briefing Papers, March 2004, Thomson West Publishers 50
TERMINATION AHEAD SLOW DOWN
Contract Terminations Not So Convenient Presented by Paul Slemons & Darrell M. Hineman TERMINATION AHEAD SLOW DOWN Please Read This presentation has been prepared for information purposes and general guidance
More informationChapter 12. Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims
Chapter 12 Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims Table of Contents 12-000 Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment
More informationGOVERNMENT CONTRACT COSTS, PRICING & ACCOUNTING REPORT
Reprinted with permission from Government Contract Costs, Pricing& Accounting Report, Volume 12, Issue 1, K2017 Thomson Reuters. Further reproduction without permission of the publisher is prohibited.
More informationTerminations: How to Cope with the Premature Death of Your Contract Presented By:
Terminations: How to Cope with the Premature Death of Your Contract Presented By: Cheryl Anderson canderson@redstonegci.com Jon Levin jlevin@maynardcooper.com Topics Covered Overview of Terminations Terminations
More informationClaim Quantum and Audit Issues
Claim Quantum and Audit Issues Breakout Session #: B06 Timothy Overman & Tanner Courrier Date: Monday, July 25 Time: 2:30pm 3:45pm 1 Timothy Overman Tim Overman is Managing Vice President of the Dallas
More informationClick to edit Master title style
Click to edit Master title style Fourth level The Cost Accounting Standards and Consequences of Noncompliance Click to edit Master text styles Click to edit Master title style Breakout Third Session level
More informationItem No. Adequacy Consideration Adequate Notes
References: CAM 12-200 Section 2 - General Audit Guidance for Termination of Negotiated Contracts CAM 12-300 Section 3 - Auditing Terminations of Fixed-Price Contracts Audit Program 17100 Termination,
More informationSequestration and Terminations for Convenience
Sequestration and Terminations for Convenience J. Clark Pendergrass Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 jcp@lanierford.com www.lanierford.com
More informationCONTRACT ADMINISTRATION AND AUDIT SERVICES
CHAPTER 3042 CONTRACT ADMINISTRATION AND AUDIT SERVICES Subchapter 3042.002 Interagency agreements. Subchapter 3042.1 Contract Audit Services 3042.102 Assignment of contract audit services. 3042.170 Contract
More informationManaging Contract Terminations to Protect or Improve Your Profit Position A Guide to Winning Settlement Proposals. Mark J. Meagher Britton Nohe-Braun
Managing Contract Terminations to Protect or Improve Your Profit Position A Guide to Winning Settlement Proposals Mark J. Meagher Britton Nohe-Braun November 14, 2017 Agenda Terminations overview Current
More informationInternational Cost Estimating & Analysis Association. Supplier Cost/Price Analyses June 20, 2013
International Cost Estimating & Analysis Association Supplier Cost/Price Analyses June 20, 2013 David Eck and Todd W. Bishop Dixon Hughes Goodman LLP Government Contract Consulting Services Group Agenda
More informationItem No. Adequacy Consideration Adequate Notes
References: CAM 12-200 Section 2 - General Audit Guidance for Termination of Negotiated Contracts CAM 12-300 Section 3 - Auditing Terminations of Fixed-Price Contracts Audit Program 17100 Termination,
More informationCost Estimating and Truthful Cost or Pricing Data Requirements
Cost Estimating and Truthful Cost or Pricing Data Requirements Steven M. Masiello Jeremiah J. McIntyre Agenda Cost Estimating FAR cost estimating DFARS cost estimating system rule Government Proposal Analysis
More informationM52: Delays, Stop Work Orders, and Termination in Grants and Contracts
M52: Delays, Stop Work Orders, and Termination in Grants and Contracts Presented by: J. Michael Slocum, Esquire SLOCUM & BODDIE, P.C. 5400 Shawnee Road, Suite 300 Alexandria, Virginia 22312 (703) 451-9001
More informationPitfalls Of State And Local Contracting
Pitfalls Of State And Local Contracting Breakout Session #: D16 Mike LaCorte and David Black Date: Tuesday, July 26 Time: 11:15am 12:30pm 1 Mike LaCorte Masters of Science in Taxation Florida Atlantic
More informationMonitoring Subcontracts
Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Page 1 Subcontracts What should a contractor know about subcontracting:
More informationGovernment Contracts Pricing Strategies and Rate Structures
Government Contracts Pricing Strategies and Rate Structures Presented By: Brandon Smith bsmith@anglincpa.com Jon Levin jlevin@maynardcooper.com Provisional Billing Rates Provisional, Target, Budget, Billing,
More informationGOVERNMENT CONTRACT COSTS, PRICING & ACCOUNTING REPORT
Reprinted with permission from Government Contract Costs, Pricing& Accounting Report, Volume 12, Issue 2, K2017 Thomson Reuters. Further reproduction without permission of the publisher is prohibited.
More informationAGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE
AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE THIS AGREEMENT, entered into this day of, by and between the Arkansas State Highway
More informationIt s inevitable, really.
It s inevitable, really. Given the budget pressure on the Federal government which already includes the use of Continuing Resolutions in lieu of budget appropriations, and may well include automatic sequestration
More informationEnhance Your Understanding of the Truth in Negotiations Act (TINA)
Enhance Your Understanding of the Truth in Negotiations Act (TINA) Breakout Session # B10 Janie L Maddox, Lecturer, U.S. Naval Postgraduate School Brent Calhoon, Partner, Baker Tilly Samantha Schwellenbach,
More informationTruth in Negotiations Act (TINA) Essentials
Truth in Negotiations Act (TINA) Essentials Breakout Session #: F03 Presented by: Brent Calhoon, Partner, Baker Tilly Shingai Mavengere, Senior Manager, Baker Tilly Date: Tuesday, July 23 Time: 4:00pm-5:15pm
More informationChallenges of Contracting with the Federal Government November 19 th, 2015
Challenges of Contracting with the Federal Government November 19 th, 2015 The Fundamentals of Government Contracting Webinar Series 1 Your Presenters David King Dixon Hughes Goodman, LLP 703.970.0433
More informationDCMA Manual Terminations. Implements: DCMA-INST 2501, Contract Maintenance, August 15, October 10, 2014
DCMA Manual 2501-06 Terminations Office of Primary Responsibility Contract Maintenance Effective: October 2, 2018 Releasability: Cleared for public release Implements: DCMA-INST 2501, Contract Maintenance,
More informationReferences: CAM Section 2 - General Audit Guidance for Termination of Negotiated Contracts
References: CAM 12-200 Section 2 - General Audit Guidance for Termination of Negotiated Contracts CAM 12-400 Section 4 - Auditing Terminations of Cost-Type Contracts Audit Program 17100 Termination, Cost
More informationVSRA Contract Compliance Seminar August 23, 2011
VSRA Contract Compliance Seminar August 23, 2011 Topics Overview What s new? Defense Federal Acquisition Regulation Supplement; Business Systems Definition and Administration (DFARS Case 2009-D038) Reporting
More informationDEFENSE ACQUISITION UNIVERSITY CON Negotiation and Administration of Supply Contracts
1 Given a complex fiscal law issue, and working in a team environment, generate a strategy which will resolve that issue. Interpret the major fiscal law statutes and regulations governing Federal contracting.
More informationDEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Disallowance of Costs
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Disallowance of Costs Contracts Directorate DCMA-INST 128 OPR: DCMA-AQ 1. PURPOSE. This Instruction: a. Revises DCMA Instruction (DCMA-INST)
More informationPricing Subcontracts to Win Work and Make a Profit
Pricing Subcontracts to Win Work and Make a Profit Breakout Session C02 Rita L. Wells, PhD Senior Acquisition Executive, Suntiva Deidre A. Lee Consultant Date: Thursday, March 17, 2016 Time: 3:45pm 5:00pm
More informationPitfalls Of State And Local Contracting
Pitfalls Of State And Local Contracting Breakout Session # A05 William D. Guernier, Vice President, The Kenrich Group Erin L. Felix, Associate, Polsinelli Date: December 12, 2016 Time: 1:00PM - 2:15PM
More informationCOMPENSATION & PAYMENT PROVISIONS (COST REIMBURSABLE)
COMPENSATION & PAYMENT PROVISIONS (COST REIMBURSABLE) 1 Note: Articles flagged with an asterisk (*) are Flow-down requirements as defined in Article SUBCONTRACTORS AND SUPPLIERS in Contract Document GENERAL
More informationTITLE 70: DEPARTMENT OF FINANCE SUBCHAPTER COST AND PRICE ANALYSIS REGULATIONS
SUBCHAPTER 70-30.1 COST AND PRICE ANALYSIS REGULATIONS Part 001 General Provisions 70-30.1-001 Overview and Summary 70-30.1-005 Scope 70-30.1-010 Definitions Part 100 Policy; Cost or Pricing Data 70-30.1-101
More informationAccounting System Requirements
Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily
More informationSubcontract and Material Vendor Costs. Steven M. Masiello Gale R. Monahan January 13, 2015
Subcontract and Material Vendor Costs Steven M. Masiello Gale R. Monahan January 13, 2015 mckennalong.com Subcontractor Cost Allowability Standards for Government Subcontracting DCMA/DCAA Subcontract Cost
More informationMG-3 - Supplier Cost Price Analyses Best Practices for Evaluating Supplier Proposals and Quotes
International Cost Estimating & Analysis Association - Supplier Cost / Price Analyses June 10-13, 2014 Presented By: David Eck, CPA Director Mike Mardesich, CPA Manager Dixon Hughes Goodman Government
More information5 Contract Pricing Price Evaluation General a Use
5 Contract Pricing 5 Contract Pricing...................................................... 175 5.1 Price Evaluation................................................................. 175 5.1.1 General....................................................................
More informationSUBPART OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised December 9, 2005)
SUBPART 225.8--OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised December 9, 2005) 225.802 Procedures. (b) Information on memoranda of understanding and other international agreements is available
More informationChanges, Terminations, and Claims
Changes, Terminations, and Claims J. Clark Pendergrass Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 jcp@lanierford.com www.lanierford.com Copyright
More informationCLAIMS, CHANGES, & TERMINATIONS. Chris Haile Tully McLaughlin Sharmistha Das
CLAIMS, CHANGES, & TERMINATIONS Chris Haile Tully McLaughlin Sharmistha Das 205 Agenda: Contract Changes Claims Administration and Procedure Terminations 206 Contract Changes Administration of Changes
More informationSUBPART OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised June 29, 2018)
SUBPART 225.8--OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised June 29, 2018) 225.802 Procedures. (b) Information on memoranda of understanding and other international agreements is available
More information(We have reported on several of the CWC hearings and reports before. To find those stories, type CWC in the search window on the website.
On July 26, 2010, the Commission on Wartime Contracting in Iraq and Afghanistan (CWC) held a hearing entitled Subcontracting: Who s Minding the Store to address concerns about the subcontracting process
More informationAllowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management
Allowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management Breakout Session #: B11 Presented by: Melanie Burgess and Phillip Seckman Date: July 22, 2013
More informationCOMMON CLAIMS UNDER CONSTRUCTION CONTRACTS
888 17 th Street, NW, 11 th Floor Washington, DC 20006 Tel: (202) 857-1000 Fax: (202) 857-0200 COMMON CLAIMS UNDER CONSTRUCTION CONTRACTS You may download these slides at www.pilieromazza.com/presentations
More informationMaster Document Audit Program. Version 4.21, dated March 2018 B-1 Planning Considerations
Activity Code 17200 B-1 Planning Considerations Claim Audit, Other Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team and internal
More informationSIGAR. Construction of the Special Forces Kandak in Kandahar: Audit of Costs Incurred by Environmental Chemical Corporation APRIL
SIGAR Special Inspector General for Afghanistan Reconstruction SIGAR 16-30 Financial Audit Construction of the Special Forces Kandak in Kandahar: Audit of Costs Incurred by Environmental Chemical Corporation
More informationAdequacy of Proposals for. Global Supply Chain
Adequacy of Proposals for Global Supply Chain 1 Adequacy of Proposals Objectives This resource document covers the following: An overview of the proposal process, including applicable FAR (Federal Acquisition
More informationSUBPART OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised December 31, 2012)
SUBPART 225.8--OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised December 31, 2012) 225.802 Procedures. (b) Information on memoranda of understanding and other international agreements is available
More informationPCI s Trending Cost & Pricing Series 2017 Defective Pricing Hazards and Defenses December 21, government contracting
PCI s Trending Cost & Pricing Series 2017 Defective Pricing Hazards and Defenses December 21, 2017 1 Your hosts Bill Walter Executive Director Government Contract Advisory Services Dixon Hughes Goodman
More informationSUBPART OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised April 26, 2007)
SUBPART 225.8--OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised April 26, 2007) 225.802 Procedures. (b) Information on memoranda of understanding and other international agreements is available
More informationPANEL E: Costly Mistakes!
PANEL E: Costly Mistakes! How to avoid the most common pitfalls that face a growing company. Lessons learned from an operational and legal perspective that may help you make money and stay out of jail!
More informationMaster Document Audit Program. Version 6.21, dated March 2018 B-1 Planning Considerations
Activity Code 17200 B-1 Planning Considerations Claim Audit, Delay Disruption Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team and
More informationU.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS
U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS I. DEFINITIONS A. Agreement means the agreement between City and Contractor to
More informationCAS - Part II. The Cost Allocation Standards Dixon Hughes Goodman, LLP
CAS - Part II The Cost Allocation Standards 1 Agenda Session I Administration: CAS Overview Applicability Types of Coverage CAS Administration Part II - The Cost Allocation Standards Part III - The Cost
More informationNew to Cost Reimbursement Contracts? Meet Your New Friends
New to Cost Reimbursement Contracts? Meet Your New Friends Breakout Session #: G07 Brent Calhoon Partner Baker Tilly Shingai Mavengere Director, Government Accounting UnitedHealthcare Military & Veterans
More informationContract Modification Authority Decision Help Guide
Contract Modification Authority Decision Help Guide The purpose of this tool is to aid you in the selection of a modification authority to cite in Block 13 of the SF30. START Is the Contract/Order FAR-Based?
More informationExploring Unallowable Costs David Eck Mike Mardesich September 22, 2016
Exploring Unallowable Costs David Eck Mike Mardesich September 22, 2016 The Fundamentals of Government Contracting Webinar Series 1 Your Presenters David Eck Dixon Hughes Goodman LLP 214.334.3233 david.eck@dhgllp.com
More informationGOVERNMENT CLAUSES SUPPLEMENT GCS-001 (Rev. NC)
(A) The FAR and DFARS clauses cited in paragraph D below, where applicable by their terms, are incorporated herein by reference, as if set out in full text. The effective version of each FAR or DFARS clause
More informationTop 10 Problems with Problems with Multiple Award Task Order/Deliver Order IDIQ RFP s
Top 10 Problems with Problems with Multiple Award Task Order/Deliver Order IDIQ RFP s Top 10 Problems with Multiple Award Task Order/Deliver Order IDIQ RFP s Brian Greenberg, CPCM, Fellow Chief Operating
More informationSupplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions
General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the products or services furnished are for use in connection with a U.S.
More informationCost Accounting Standards
Cost Accounting Standards Bill Walter Partner - Government Contract Consulting McLean, Virginia (703) 970-0509 bill.walter@dhgllp.com 1 Agenda Session I Administration: CAS Overview Applicability Types
More informationN G-0001 Clause Number Clause Date Clause Title (OCT 2005) PACKAGING AND MARKING OF REPORTS (NAVAIR) (JUN 1998)
N00421-14-G-0001 Clause Number Clause Date Clause Title 5252.247-9507 (OCT 2005) PACKAGING AND MARKING OF REPORTS 5252.247-9508 (JUN 1998) PROHIBITED PACKING MATERIALS 5252.247-9509 (JUL 1998) PRESERVATION,
More informationSIGAR. Department of State s Afghanistan Justice Sector Support Program II: Audit of Costs Incurred by Pacific Architects and Engineers, Inc.
SIGAR Special Inspector General for Afghanistan Reconstruction SIGAR 15-69 Financial Audit Department of State s Afghanistan Justice Sector Support Program II: Audit of Costs Incurred by Pacific Architects
More informationBAA Process. DARPA Contracts Management Office Christopher L. Glista Contracting Officer. SubT Proposers Day January 18, 2018
DARPA Contracts Management Office Christopher L. Glista Contracting Officer SubT Proposers Day January 18, 2018 1/25/2018 1 Approved for Public Release; Distribution Unlimited What is a BAA? Solicitation
More informationVirginia Department of Transportation Indirect Cost Rate Submission and Review Process Effective January 1, 2019
Virginia Department of Transportation Indirect Cost Rate Submission and Review Process Effective January 1, 2019 1. Policy, Regulation and Guidance a) In order to ensure that consultant costs reimbursed
More informationTINA Sweeps and Defective Pricing (Part 1 of 2) Written by Nick Sanders
Many government contract compliance practitioners are aware of the Truth-in-Negotiations Act (or Truthful Cost or Pricing Data) or whatever the kids are calling it these days (I m calling it TINA). Whatever
More informationFalsification of Documents. Next Slide
Falsification of Documents Table of Contents Risk Assessment Research and Planning Risk Assessment Review of Permanent File Risk Assessment Initial Review of Proposal Document Risk Assessment Discussion
More informationAGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES FOR
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES FOR By and Between WILLIAM S. HART UNION HIGH SCHOOL DISTRICT And Dated as of TABLE OF CONTENTS Page RECITALS... 1 PART 1 PROVISION OF CM SERVICES... 1 Section
More informationIntroduction to the Cost Accounting Standards Mike Mardesich & Brad Tress April 25, 2017
Introduction to the Cost Accounting Standards Mike Mardesich & Brad Tress April 25, 2017 The Fundamentals of Government Contracting Webinar Series 1 Your Presenters Mike Mardesich Dixon Hughes Goodman
More informationThe Impact of Budget Reductions on the Procurement Process
The Impact of Budget Reductions on the Procurement Process Jeff Newman 1 Introduction Actual and potential funding gaps/deficiencies and budget cuts will impact the procurement process, and affect existing
More information(Revised April 28, 2014) ADVANCE PAYMENT POOL (DEC 1991)
(Revised April 28, 2014) 252.232-7000 Advance Payment Pool. As prescribed in 232.412-70(a), use the following clause: ADVANCE PAYMENT POOL (DEC 1991) (a) Notwithstanding any other provision of this contract,
More informationFEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS
FEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS I. DEFINITIONS A. Agreement means the agreement between City and Contractor to which this document (Federal Emergency
More informationGCS 224 Surviving DCAA Audits with GCS Premier. Presented by: Nicole Mitchell, Aronson & Company
GCS 224 Surviving DCAA Audits with GCS Premier Presented by: Nicole Mitchell, Aronson & Company Agenda Government Contract Audits and the Role of DCAA and DCMA Basic Attributes of a Government Approved
More informationSUBPART CONTRACT PRICING (Revised November 24, 2008)
SUBPART 215.4--CONTRACT PRICING (Revised November 24, 2008) 215.402 Pricing policy. Follow the procedures at PGI 215.402 when conducting cost or price analysis, particularly with regard to acquisitions
More informationSIGAR OCTOBER. Special Inspector General for Afghanistan Reconstruction. SIGAR Financial Audit
SIGAR Special Inspector General for Afghanistan Reconstruction SIGAR 19-01 Financial Audit Department of the Air Force s Construction of the Afghan Ministry of Defense Headquarters Support and Security
More informationCONTRLXCT-PRICING-- Lssues,'Relatod to DCAN Staff Levels
AD-A267 786 totho Chairman-, Conunfttee on Affairs,-V.*S Senate CONTRLXCT-PRICING-- Lssues,'Relatod to DCAN Staff Levels WNSUD-93-225 United States General Accounting Office Washington, D.C. 20548 National
More informationPART 31 - CONTRACT COST PRINCIPLES AND PROCEDURES
Appendix 17 - Federal Acquisition Regulation PART 31 - CONTRACT COST PRINCIPLES AND PROCEDURES This appendix contains sections 31.000 to 31.204 of the Federal Acquisition Regulation Section 31 - Contract
More information(APR 1984) Gratuities (MAY 2014) Covenant Against Contingent Fees (SEP 2006) Restrictions On Subcontractor Sales To The
N00019-18-C-1007 Clause Number Date Title 52.246-15 (APR 1984) Certificate of Conformance 5252.223-9502 (APR 2009) HAZARDOUS MATERIAL (NAVAIR) 5252.247-9507 (OCT 2005) PACKAGING AND MARKING OF REPORTS
More informationAPPENDIX A. A-000 Contract Cost Principles And Procedures A-001 Scope of Appendix... A1 A-100 Section RESERVED. A-200 Section RESERVED
A(1) APPENDIX A Table of Contents Paragraph Page A-000 Contract Cost Principles And Procedures A-001 Scope of Appendix... A1 A-100 Section 1 --- RESERVED A-200 Section 2 --- RESERVED A-300 Section 3 ---
More informationNational Contract Management Association of Boston 57th Annual March Workshop
National Contract Management Association of Boston 57th Annual March Workshop Pricing and estimating March 7, 2018 Agenda Introductions Overview and background of the pricing and estimating process Certified
More informationDISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY ATTACHMENT C GENERAL PROVISIONS GOODS AND SERVICES CONTRACTS December 20, 2012 DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY GENERAL PROVISIONS GOODS AND
More informationSection 7. General Conditions of Contract for the Procurement of Works
Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5
More informationMAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS
MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3
More informationSection B Services, Ordering and Prices
Section B Services, Ordering and Prices B.1 Background Federal Strategic Sourcing was mandated by the Office of Management and Budget's (OMB s) Office of Federal Procurement Policy, and implemented by
More informationMaricopa County Policy/Contract Template Reference. Procurement Standards (http://www.ecfr.gov/cgi-bin/text-idx?node=2: )
200.317 Procurements by states. When procuring property and services under a Federal award, a state must follow the same policies and procedures it uses for procurements from its non-federal funds. The
More informationSuccessfully Crafting and Prosecuting Contract Disputes Act Claims Against the Government
Successfully Crafting and Prosecuting Contract Disputes Act Claims Against the Government Webinar July 28, 2015 Sandy Hoe shoe@cov.com 202-662-5394 Justin Ganderson jganderson@cov.com 202-662-5422 Agenda
More informationPresented by CohnReznick s Government Contracting Industry Practice. Kristen Soles, CPA, Partner & Kiran Pinto, CPA, Senior Manager
A u d i t R e a d y : A n I n s i d e r s G u i d e t o G o v e r n m e n t C o n t r a c t A u d i t s & C o m p l i a n c e Presented by CohnReznick s Government Contracting Industry Practice Kristen
More informationContract Compliance and the Federal Acquisition Regulation (FAR) ORA CERTIFICATE PROGRAM (MODULE 11) 20 APRIL 2016
Contract Compliance and the Federal Acquisition Regulation (FAR) ORA CERTIFICATE PROGRAM (MODULE 11) 20 APRIL 2016 Learning Objectives Participants will learn about the history of the Federal Acquisition
More informationSubcontract Pricing Deficiencies. Next Slide
Subcontract Pricing Deficiencies Table of Contents Risk Assessment Research and Planning Risk Assessment Review of Contract and Price Negotiation Memorandum (PNM) Risk Assessment Overrun/Underrun Analysis
More informationWhat Government Contractors Should Know:
What Government Contractors Should Know: 10 Regulatory Compliance and DCAA Guidance Updates to be Aware of Now and Heading into 2017 Craig Stetson, Managing Director, Capital Edge Consulting, Inc. Introduction
More informationSTANDARD CONTRACT PROVISIONS
Government of the District of Columbia STANDARD CONTRACT PROVISIONS For Use With Specifications for District of Columbia Government Construction Projects (Revised January 2007) PLEASE RETAIN FOR YOUR REFERENCE
More informationMeeting the challenge
Government Contract Services Meeting the challenge Ernst & Young LLP s Government Contract Services (GCS) can help you meet the challenges of government contracting. As the largest buyer of goods and services
More informationStandard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:
Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,
More informationFAR GOVERNMENT CONTRACT PROVISIONS
PAGE 1 OF 10 INCORPORATION OF FAR CLAUSES The following terms and conditions apply for purchase orders, subcontracts, or other applicable agreements issued in support of a US Government contract, in addition
More informationDEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Termination for Convenience
DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Termination for Convenience Contracts Directorate DCMA-INST 101 OPR: DCMA-AQ SUMMARY OF CHANGES. This revision adds references and text
More informationGovernment Contracts Recovery
Government Contracts Recovery Frequently Asked Questions About Requests for Equitable Adjustment and CDA Claims June 14, 2017 Stephen McBrady Skye Mathieson Laura Baker Charles Baek Agenda Introduction
More information2. Bidder shall notify Buyer if a former employee of Buyer is representing Bidder in connection with its proposal or any resulting order.
Page: 1 of 5 General Instructions to Bidder 1. Bidder will carefully review all documents cited in Buyer's solicitation to ensure the following: a. All information required to properly respond to this
More informationFAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS. FAR Number Title Latest Update MATERIAL REQUIREMENTS AUG 2000
FAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS 1. The following FAR clauses apply to all non-commercial orders: 52.211-5 MATERIAL REQUIREMENTS AUG 2000 52.215-20 REQUIREMENTS FOR COST OR PRICING DATA
More informationICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA
ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA A COMPARATIVE ANALYSIS OF THE 1997 CHANGES TO THE AIA GENERAL CONDITIONS TO THE CONTRACT FOR CONSTRUCTION (A201) STUART
More informationSUBCONTRACTOR S RELEASE OF CLAIMS
SUBCONTRACTOR S RELEASE OF CLAIMS Pursuant to the terms of the referenced purchase order and/or Subcontract Agreement and in consideration of the sum of which has been or is to be paid to above (hereinafter
More information(Revised December 22, 2016) General. For guidance on evaluating offers of foreign end products, see PGI
Part 225 Foreign Acquisition Defense Federal Acquisition Regulation Supplement (Revised December 22, 2016) 225.001 General. For guidance on evaluating offers of foreign end products, see PGI 225.001. 225.003
More information