Revisions to Cost-type Contracts: Controlling Scope, Schedule, and Cost

Size: px
Start display at page:

Download "Revisions to Cost-type Contracts: Controlling Scope, Schedule, and Cost"

Transcription

1

2 Revisions to Cost-type Contracts: Controlling Scope, Schedule, and Cost Breakout Session #D03 Jo Ellyn Cunningham July 23, :15 AM 1

3 Contract Types Two Basic Pricing Arrangements: Fixed Price: FFP, FFP/EPA, FP+AF, FP+I, FF Rate, Cost-Share Cost Reimbursement: CNF, CPFF, CPIF, CPAW, Cost-Share T&M, LH 2

4 Cost-Type Contracts Cost Risk: High >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> Low Requirement Definition Vague >>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> Well Defined Production Stage Concept Exploratory Test/ Full scale Full Contract Studies, & Development Demo Development Production Basic Research Type Varied CPFF CPIF, CPIF, FPIF, FFP, FPIF, FPIF or FFP or FPEPA 3

5 Cost Plus Fixed Fee (CPFF) / Time & Materials (T&M) - Contrast CPFF Completion CPFF Term (LOE) T&M PWS/SOW PWS/SOW PWS/SOW POP POP POP Estimated Cost Estimated Cost Ceiling Price Estimated Cost Estimated Cost Allowable Fixed Fee Fixed Fee Charges Total Cost & Fee Total Cost & Fee LOE Language tying fee to range of hours 4

6 Cost-Reimbursement Contract Administration Where the rubber meets the road 5

7 T&M vs. Cost-Type T&M: Contractor s labor rates: Loaded to include direct, indirect, General & Administrative (G&A) costs, & profit. Typically agreed to prior to award for current year & out years 6

8 T&M: T&M vs. Cost-Type Materials & Other Direct Costs (ODCs) typically are provided at Contractor s cost. However, Contractor may add overhead (OH) to ODCs, IF he has not already recovered these costs in his Labor rates, & it is his standard accounting practice. Profit/fee is based on level of risk, performance & technical innovation. 7

9 T&M vs. Cost-Type COST-TYPE - Handled differently: Cost elements are reviewed separately to include: direct labor, subcontractor labor, materials, other direct costs, overhead & other indirect costs, General & Administrative (G&A) & profit/fee. Direct costs are costs directly associated with a specific project, & include labor, travel, & purchases. 8

10 COST-TYPE: T&M vs. Cost-Type Indirect costs change, based on company projections & the changing costs of operating a business. Indirect costs are common costs that can t be directly assigned to specific projects, & are allocated using a systematic cost allocation basis. Profit/fee is based on level of risk, performance & technical innovation. 9

11 Cost-Reimbursable (With or Without Fee) Contract Mods THESE ARE NOT TIME & MATERIALS OR LABOR HOUR CONTRACTS You cannot just Add Money 10

12 Modifications to T&M Contracts Issues you must address: Option years & Rate Change Requests: Direct Labor Rate changes Indirect Rate changes Audit contractor s proposed revised rates? Consider cost of audits Use GII/DOL factors? 11

13 Modifications to T&M Contracts Issues you must address, continued: Adding Funding: Will additional funding & work scope lower indirect rates? Assuming no GII/DOL provisions, has contractor experienced any changes in his indirect rates? 12

14 Modifications to T&M Contracts Questions the Buyer/Contract Specialist (CS) must ask: What caused the change? Use loaded rates agreed upon at contract award? If applicable to this mod, ask for List of Materials (LOM) & costs specific to mod request. Contractor developed LOMs should not be changed after the fact unless Government has caused the change, or unknown conditions exist. Always ask for justification. 13

15 Modifications to T&M Contracts Questions Buyers/Contract Specialists must ask, continued: If Contractor is suggesting a labor rate change, ask for written justification for consideration. Must be a good reason. If SCA contract, compare rates against agreed upon Wage Determination in contract. Update if & when an Option is being exercised. 14

16 Modifications to T&M Contracts Questions Buyers/Contract Specialists must ask, continued: If Adding Funding: Why is additional funding needed if Government has not caused or asked for a change in work? If justified, add value of modification to previously obligated amount. Remember: The Contractor won this award by proposing an estimated price that demonstrated he/she understood the work. Be cautious about contractor initial buy-in to a job. 15

17 Important Concepts Scope: Authorized work per Performance Work Statement (PWS) Scope Creep: New work (beyond PWS authorization) that usually results from discussions between Government & contractor engineers & program managers, who neglected to keep contract specialists on both sides informed! (BEWARE Apparent Authority!) Cost Overrun: No new work is authorized, but costs incurred exceeded those costs authorized by the contract. Contractor overruns are solely at Contractor s own risk. Government is NOT obligated to cover any costs above the authorized contract amount. Contractor must provide Notice to Government when costs reach 75% of the estimated costs when there is a potential for overrun. (FAR ) 16

18 Important Concepts, Continued Cost No Fee: Contractor receives no fee. Cost Plus Fixed Fee: Allowable costs up to a specified ceiling amount, plus negotiated fee fixed at contract inception. Fee does not vary with costs incurred; it may be adjusted as changes to the work are authorized by the CS or KO. 17

19 Modifications to Cost-No Fee Contracts Issues Buyers/CSs must address: Costs incurred to date (existing scope) Estimated Costs to Complete (existing scope) Estimated Costs for New Scope Is this revision for an overrun? Identify the reason for an overrun. 18

20 Modifications to Cost-No Fee Contracts Issues Buyers/CSs must address, continued: Address Contractor s Quote(s), Buyer s/contract Specialist s (CS) Position, Negotiated Settlement, & Net Impact Estimated Schedule for Incurred Costs Monitor invoices. Key Words to Remember: Scope Creep, Scope Growth, Cost Overrun 19

21 Modifications to Cost-Plus Type Contracts Questions the Buyer/CS must address: What are costs-to-date & estimated Cost-to-Complete of Existing Scope? Is this modification for an Overrun on a Cost-Plus- Fixed-Fee contract? Does the Modification request include an overrun & New Work? What are estimated costs for New Scope, plus Fee, commensurate with risk, for New Scope? Identify the reason for an overrun. 20

22 Modifications to Cost-Plus Type Contracts Questions Buyer/CS must address, continued: Profit or fee negotiated, for new work ONLY, should be specifically identified. If an overrun is considered in the same modification, keep it separate. Will Contractor be required to submit certified cost & pricing data, or other than certified cost & pricing data? Under what circumstances? (Hint TINA). Does modified cost properly exclude non-recurring costs such as tooling, design, & development costs & learning curve? 21

23 Modifications to Cost-Plus Type Contracts Questions Buyers/CSs must address, continued: Review Contractor s Proposal(s); Document Government s Position & Negotiated Settlement, & Document Net Impact. Define how additional Fee (if any) will be paid out! Tie fee payments to deliverables received & accepted by the Government. Incentivize Contractor Performance! DO NOT pay a monthly or quarterly fee amount. Monitor invoices to insure Contractor is not invoicing inappropriately for fee. Avoid appearance of Cost Plus Percentage of Cost!! This is Illegal! 22

24 Modifications to Cost-Plus Type Contracts Questions Buyers/CSs must address, continued: Fee should be based on the arrangement identified in the RFP, i.e., fee will be paid at completion of each separate task, OR at completion of milestone, etc. DO NOT treat the fee as if it were part of any progress payments. Progress payments are used for FFP contracts, not CPFF. If new work, Use DD Form 1547 (for non-competitive) when mod exceeds $100K & contract total is $50M or greater per year. 23

25 Modifications to Cost-Plus Type Contracts Avoid the appearance of Cost Plus Percentage of Cost!! Definition for Cost Plus Percentage of Cost: The following criteria is used to determine whether a contract has a CPPC arrangement: 1. Payment is on a predetermined percentage rate. 2. The predetermined percentage rate is applied to actual performance costs. 3. The Contractor s entitlement is uncertain at the time of contracting; &, 4. The Contractor s entitlement increases commensurately with increased performance costs. 24

26 Cost-Reimbursement Contracts: Completion vs. Term The scope of work can be written two ways for a cost reimbursable contract: Completion Term Form As found in FAR (d) 25

27 Cost-Reimbursement Scope Approach: Completion vs. Term Completion States a definite goal or target & specifying an end product. Contractor must complete & deliver specified end product (e.g., a final report of research accomplishing the goal or target) within the estimated cost, as a condition for payment of the entire fixed fee. If work cannot be completed within estimated cost, Government may require more effort without increase in fee, provided Government increases the estimated cost. 26

28 Cost-Reimbursement Scope Approach: Completion vs. Term Term Form Obligates contractor to devote a specified level of effort for a stated time period. If performance is considered satisfactory by Government, fixed fee is payable at expiration of agreedupon period, upon contractor statement that level of effort specified in contract has been expended in performing the contract work. Renewal for further periods of performance is a new acquisition that involves new cost & fee arrangements. 27

29 Quarterly or Monthly Cost Status Reports Regularly Required Cost Status Report Enable Better Contract Management: Technical progress for period ended Cost to date for period ended Estimated costs for next quarter Technical activities/milestone completion planned for next quarter Estimated Cost to complete Contract 28

30 Ask the Right Questions: Line Customers What is the technical status of the contract? What is driving the increase? Cost Growth? Scope Growth? Constructive Changes? Effect on Schedule? Get Project Manager & Budget Analyst Input 29

31 Ask the Right Questions: Contractors What is the technical status of contract performance? What is driving the increased schedule &/or costs? Scope changes? Source? Constructive Changes? Suppliers? Subcontractors? 30

32 The Trinity: Scope, Schedule, & Cost SCOPE SCHEDULE COST 31

33 Adding Scope, Schedule, Cost Step One Existing Scope: Get cost-to-date & estimate to complete existing, current work Get technical status to date Obtain hours to date & estimated hours- tocomplete for CPFF LOE Contracts. If there is a projected overrun, make sure that Contractor does not mix up cost for new work with overrun in order to get fee on the overrun. 32

34 Adding Scope, Schedule, Cost Step Two Scope Change Evaluate labor, material, travel, indirect costs, profit for new work. Negotiate Schedule & Cost Plus Fee for New Work. Step Three Summarize Changes. Map out how much must be added to the contract to account for (1) cost status of existing contract & (2) proposed new work. 33

35 CPFF Completion Changes: Fee-bearing Costs & Non-fee-bearing Costs If PWS/SOW Scope is increased, the increased cost is fee-bearing. If your action has the effect of requiring the Contractor to perform more work, (constructive change), that cost increase could be fee-bearing Defective Specifications Contractor gets order to speed up work in face of excusable delays. Non Cooperation or Interference, e.g. your organization impedes performance 34

36 CPFF Changes: Fee-bearing Costs & Non-fee-bearing Costs If increased cost is the result of Cost Growth, the increased cost is non-fee bearing. More hours needed than originally estimated Material Cost Increases Proposed subs not available, requiring Contractor to use more expensive subs. 35

37 CPFF Changes: Overruns If there is an overrun or revised estimate to complete (anticipated overrun) Contractor needs to provide detail on the overrun: Cost & technical status of work to date What cost elements make up the overrun What technical work will be performed with the overrun. What conditions drove the overrun. 36

38 CPFF Changes: Descopes De-scope: Preferable to a Partial Termination Step One Get cost-to-date & estimate to complete for current work. Get technical status to date 37

39 CPFF Changes: Descopes Step Two Evaluate labor, material, travel, indirect costs, profit for new work. Negotiate Cost Plus Fee for Deleted Work: Look for the following when evaluating the proposal: Underestimating labor, material Omitting types of labor or material Omitting Indirect Costs Omitting Profit 38

40 CPFF Changes: Descopes Step Two, Continued Closely review original proposal to see if there was anything originally proposed that is missing from deduct proposal Step Three Summarize Changes. Map out how much must be added to &/or deleted from the contract to account for (1) cost status of existing contract, & (2) proposed deleted work. 39

41 Example 1: Scope Increase to CPFF Completion-type Contract CS Issued Increased Scope Change on CPFF Completion, Without Getting Cost-to-Complete Status (Bad Move!) Original Quotation Instructions to Contractor: Propose Estimated Cost & Fixed Fee for adding one support package: Original Negotiated New Contract Contract Increase Value Cost $1,218,354 $118,868 $1,337,222 Fee $ 92,778 $ 7,132 $ 99,910 CPFF $1,311,132 $126,000 $1,437,132 40

42 Example 1(a): Scope Increase to CPFF Completion-type Contract Increased Scope Change on CPFF Completion, Buyer/CS Obtained Cost to Complete Status, & Balanced the Books (Much better approach): Quotation Instructions for Existing Status (Step 1) Provide Cost to Date through the Most Current Accounting Period, for existing work. Provide Technical Progress Status To Date through most current Accounting Period, for existing work. Provide Estimated Cost to Complete for existing work. 41

43 Example 1(a): Scope Increase to CPFF Completion-type Contract Increased Scope Change on CPFF Completion, Buyer/CS Obtained Cost to Complete Status, & Balanced the Books : Now Address New Work (Step 2) Propose Estimated Cost & Fixed Fee for adding one support package. Let s look at the difference in the results when the more detailed Quotation Instructions were provided! 42

44 Example 1(a): STEP ONE BALANCE THE BOOKS (1) (2) Actuals to Estimate Total Initial Date plus to Complete Contract Cost Contract Fee Original Work* Amount Growth Cost $1,093,098 $209,565 $1,302,663 $1,218,354 $84,309 Fee $ 92,778 $ $ 92,778 $ 92,778 $ 0 CPFF $1,185,876 $209,565 $1,395,441 $1,311,132 $84,309 Follow up Question to Contractor Why the $84,309 cost growth? Contractor s Response Subcontractor shut down, causing Prime to go to more expensive shop. *NOTE: Not fee bearing, because it was not an increase in scope. 43

45 Example 1(a): STEP TWO NEGOTIATE THE INCREASED SCOPE NEGOTIATE THE INCREASED SCOPE Evaluate labor, material, travel, indirect costs, & profit for new work; Negotiate Cost Plus Fee for New Work. Below is result of Cost analysis for new work: Negotiated Cost $34,559 Fee $ 2,073 CPFF $36,632 44

46 Example 1(a): STEP THREE SUMMARIZE CONTRACT ACTION Per Contract To Complete Added Scope New Contract Value Cost $1,218,354 $84,309 $34,559 $1,337,222 Fee $ 92,778 $ 0 $ 2,073 $ 94,851 CPFF $1,311,132 $84,309 $36,632 $1,432,073 45

47 Example 1(a): BALANCING THE BOOKS ADVANTAGE! Example 1 vs. 1(a), e.g. Balancing books vs. not balancing the books Example 1 Example 1(a) New Contract Value New Contract Value Difference Cost $1,337,222 $1,337,222 Fee $ 99,910 $ 94,851 $5,059 (savings) CPFF $1,437,132 $1,432,073 $5,059 46

48 Example 2: Adding New Term to CPFF- Level Of Effort Contract Adding new Term Without Getting Cost & Hours- to- Complete Status, e.g. Balancing the Books (OOPS!) Quotation Instructions: Propose Estimated Cost & Fixed Fee for adding 4 months. Contract Cost & Fee Thru 8/31/07 Term Neg. 9/1/ Value New Contract Cost $74,425,817 $3,826,414 $78,252,231 Fixed Fee $ 5,694,078 $ 305,108 $ 5,999,186 Total $80,119,895 $4,131,522 $84,251,417 47

49 Example 2(a): Adding New Term to CPFF-Level Of Effort Contract, Correctly! Increased Scope Change on CPFF LOE, CS Obtained Cost to Complete Status, & Balanced the Books : Quotation Instructions (Good Work!) Step 1 Address Existing Work Provide Cost to Date through the Most Current Accounting Period of existing work. Provide Hours through Most Current Accounting Period. Provide Estimate to Complete through Balance of Contract Term. 48

50 Example 2(a): Adding New Term to CPFF-Level Of Effort Contract, Correctly! Quotation Instructions, Continued: Step 2 Address New Work Propose Estimated Hours to Complete through Balance of Contract Term Provide CPFF & Hours for new Term Let s look at the difference in the results when the more detailed Quotation Instructions were provided! 49

51 Example 2(a): Adding New Term to CPFF-Level Of Effort Contract, Correctly! STEP ONE - BALANCE THE BOOKS Actual hours plus estimated hours to complete original work were below negotiated range of hours that Fee was based upon, for period ending 8/31/07. Thus full fee for period ending 8/31/07 was not earned in accordance with the Contract terms. Buyer/CS negotiated fee reduction of $117,714. Actual plus Estimated Term Costs for P/E 8/31/07 were $72,782,

52 Example 2(a): Adding New Term to CPFF-Level Of Effort Contract, Correctly! STEP TWO NEGOTIATE COST & FEE FOR NEW TERM Neg. 9/1/07 12/31/07 Cost $3,826,414 Fixed Fee $ 305,108 Total $4,131,522 51

53 Example 2(a): Adding New Term to CPFF-Level Of Effort Contract, Correctly! STEP THREE SUMMARIZE CONTRACT ACTION Actual Cost New + Re-negotiated New Term Contract Fee through 8/31/07 Neg. 9/1/07-12/31/07 Value Cost $72,782,403 $3,826,414 $76,608,817 F. Fee $ 5,576,364 $ 305,108 $ 5,881,472 Total $78,358,767 $4,131,522 $82,490,289 52

54 Example 2 versus 2(a), e.g. Balancing the Books vs. Not Balancing the Books Example 2 Example 2(a) New Contract Value New Contract Value Difference Cost $78,252,231 $76,608,817 <$1,643,414> Fee $ 5,999,186 $ 5,881,472 <$ 117,714> CPFF $84,251,417 $82,490,289 <$1,761,128> 53

55 Example 2 versus 2(a), e.g. Balancing the Books vs. Not Balancing the Books KEY POINT 1: In Example 2, Buyer/CS asked for estimated costs for the extended term, without asking for cost to date & estimate to complete current term first. Contract was in an underrun situation. Buyer/CS did not ask for correct information; thus, in the New Contract Value, too much cost was added. 54

56 Example 2 versus 2(a), e.g. Balancing the Books vs. Not Balancing the Books KEY POINT 2: In Example 2, Buyer/CS did not ask for hours for the current term to determine if the contractual LOE had been provided. Thus, the Contractor earned fee for the current term to which they were not entitled. As a result, the new contract value for Example 2 contained too much fee. 55

57 Example 3: De-Scoped Effort Delete Task #4 It Is No Longer Required: Quotation Instructions: Step 1: Provide Cost to Date through Most Current Accounting Period for existing work. Provide Estimated Cost to Complete for existing work. Get Technical Status on current work. 56

58 Example 3: De-Scoped Effort Delete Task #4 No Longer Required: Quotation Instructions: Step 2: Propose Detailed Deducted Estimated Cost & Fixed Fee for deleting Task #4. Use current costs to price the proposal. Let s See How the Savvy Buyer/CS Accomplished This. 57

59 Example 3: De-Scoped Effort STEP ONE: BALANCE THE BOOKS This is the Original Contract s Estimated Cost & Fee Cost $1,500,000 Fee $ 120,000 Total $1,620,000 Your Contractor informs you that cost to date for the most current accounting period is $1,000,000. Estimate at Completion for current work is $1,500,000, which is your current Contractual Estimated Cost. 58

60 Example 3: De-Scoped Effort STEP TWO: NEGOTIATE COST & FEE FOR DELETED WORK Proposed Negotiated Cost <$100,000> <$200,000> Fee < $0 > <$ 16,000 Total <$100,000> <$216,000> Contractor proposed only direct costs in deduct, with no overhead, G&A or profit. Buyer/CS argued that negotiated deduct must include current costs, associated indirect costs & fee. Negotiated amount includes those elements. 59

61 Example 3: De-Scoped Effort STEP THREE SUMMARIZE CONTRACT ACTION Per Contract Negotiated Deduct New Contract Value Cost $1,500,000 <$200,000> $1,300,000 Fee $ 120,000 <$ 16,000> $ 104,000 CPFF $1,620,000 <$216,000> $1,404,000 60

62 Fee Scenario # 1 Contractor proposed to perform work under the original PWS for: $100, $8, (8% fee)= $108, total estimated cost. Contractor completes the work satisfactorily and submits a final invoice to the Government for a total of $93,000.00, indicating work is complete. Questions: 1. How much fee is the contractor entitled to for this work? 2. What happens to the remaining $7, of the originally estimated cost? Answers: 1. $8, CS should deobligate the funds and give them back to the customer to reuse. 61

63 Fee Scenario # 2 Contractor proposed to perform the work in the PWS/SOW for: $100, $8, (8% fee) = $108, total estimated cost. Contractor submits a request for change, indicating he needs to add 200 hours additional labor as he did not complete the work for the number of hours he/she originally proposed. The Government has agreed to fund the overrun, recognizing there was no change to the work. Question: 1. What fee will you pay the Contractor for this overrun? Answer: 1. None. The overrun is due to underestimation of hours by the Contractor, and the Government has not made or caused a change. 62

64 Fee Scenario # 3 Contractor proposed to perform the work in the PWS/SOW for: $100, $8, (8% fee) = $108, estimated total cost. Contractor submits a request for more funds to complete the original work; the Government has made no change. Government has asked Contractor to add 2 within-scope tasks. Question: 1. What will happen to the fee under the 2 circumstances above? (Separate responses required) Answers: 1. After you determine the increased value of the overrun, NO additional fee will be added for the increase. 2. New work will include a newly negotiated fixed fee (keep these transactions separate in the modification. 63

65 Fee Scenario # 4 Contractor proposed original work for: $100, $8, (8% fee)= $108, estimated total cost. Government decided 7 months into the 12 month performance period that one task will not be performed, and they need to descope the task. Question: 1. What happens to the fee under this scenario? Answer: 1. Buyer/CS will need to determine value of descoped work and associated fee from original proposal, or (if it was not broken out) negotiate the reduction to include all costs plus representative fee. 64

66 Group Exercise: Fixing the Mismanaged CPFF You have inherited a CPFF contract that was treated like a T&M for the last 2 amendments, over a two-year period. Funding was added without obtaining any cost information of any kind twice! Need amendment to extend the contract for a fourth year, & add funding to cover the estimated costs. Contractor provided detailed cost proposal $795,

67 Group Exercise: Fixing the Mismanaged CPFF Contractor quoted indirect rate of 387%; it was 186% when contract was placed 3 years ago. Requester thinks 4 th year s level of effort will be about $900, The current contract value is $750, What are the issues you must address? How will you resolve each one? 66

68 Fixing the Mismanaged CPFF-Resolutions -Request Financial approval for total estimated funding required for all five years, assuming that all options may be exercised (if this has not already been done). -Define the existing scope of work, based on LOE through end of existing POP. Must do this through mutual agreement, since last 2 mods did not address a scope of work. -Require contractor to provide a quote for existing scope that shows both actual costs incurred to date through end of last month, as well as estimate to complete existing scope of work. - Get assistance from auditor. -Determine, if possible if there were cost overruns probably difficult if not impossible at this point. -Review proposal for new scope with Program Manager; ask him to comment on reasonableness of labor hours and mix, materials and any other direct costs. -Get a rationale from contractor for all proposed elements of cost. - Create Excel spreadsheet. Use auditor and PM inputs to negotiate costs and fee. Document negotiation. 67

69 Summary Consider getting Quarterly Cost Status Reports Avoid adding & deleting funding off CPF s as if they are T&M s. Go through the proper processes. Ask the right questions of Line & Contractors. Evaluate Cost Status vs. Technical Completion for Cost Type Contracts. Understand what is fee bearing & what is not. 68

70 69 Questions?

71 Contact Information Jo Cunningham Work Phone:

Click to edit Master title style

Click to edit Master title style Third level Click Price to and edit Master Cost title style Analysis: Document your Contract Files and Impress Click to edit Auditors Master text styles Breakout Third Session level #D14 Jo Cunningham

More information

DATA ITEM DESCRIPTION

DATA ITEM DESCRIPTION DATA ITEM DESCRIPTION Title: DD Form 1921, Cost Data Summary Report Number: Approval Date: 20031031 AMSC Number: D7514 DTIC Applicable: Preparing Activity: (D) OSD/PA&E/CAIG Limitation: GIDEP Applicable:

More information

Comparison of Major Contract Types. Incentive Firm (FPIF) Moderately uncertain

Comparison of Major Contract Types. Incentive Firm (FPIF) Moderately uncertain Principal Risk to be Mitigated Firm Fixed-Price (FFP) None. Thus, the contractor assumes all cost risk. Use When.. The requirement is well-defined. Contractors are experienced in meeting it. Market conditions

More information

Proposal Pricing Instructions Page 1 of 7 Supplier Proposal Adequacy Checklist Instructions

Proposal Pricing Instructions Page 1 of 7 Supplier Proposal Adequacy Checklist Instructions Proposal Pricing Instructions Page 1 of 7 Supplier Proposal Adequacy Checklist Instructions Unless a valid exemption applies, Cost or Pricing Data is required to support proposals exceeding $750,000. Contractors

More information

DFARS Procedures, Guidance, and Information

DFARS Procedures, Guidance, and Information PGI 216.4 INCENTIVE CONTRACTS PGI 216.401 General. (Revised June 14, 2018) (c) Incentive contracts. DoD has established the Award and Incentive Fees Community of Practice (CoP) under the leadership of

More information

Growing Pains: The Art of Subcontract Management for Small Business

Growing Pains: The Art of Subcontract Management for Small Business Growing Pains: The Art of Subcontract Management for Small Business Breakout Session # B02 Jeffery A. White, C.P.M, President/CEO J.A. White & Associates, Inc. Date: March 17, 2016 Time: 2:00pm 3:15pm

More information

Top 10 Problems with Problems with Multiple Award Task Order/Deliver Order IDIQ RFP s

Top 10 Problems with Problems with Multiple Award Task Order/Deliver Order IDIQ RFP s Top 10 Problems with Problems with Multiple Award Task Order/Deliver Order IDIQ RFP s Top 10 Problems with Multiple Award Task Order/Deliver Order IDIQ RFP s Brian Greenberg, CPCM, Fellow Chief Operating

More information

INSE 6230 Total Quality Project Management. Project Quality Management Project Procurement Management

INSE 6230 Total Quality Project Management. Project Quality Management Project Procurement Management Project Quality Management Project Procurement Management Definitions based on: Ability to satisfy the needs The totality of characteristics of an entity that bear on its ability to satisfy stated or

More information

PANEL E: Costly Mistakes!

PANEL E: Costly Mistakes! PANEL E: Costly Mistakes! How to avoid the most common pitfalls that face a growing company. Lessons learned from an operational and legal perspective that may help you make money and stay out of jail!

More information

Indirect Rates the Basics In Deltek GCS Premier

Indirect Rates the Basics In Deltek GCS Premier Indirect Rates the Basics In Deltek GCS Premier COPYRIGHT INFORMATION While NeoSystems has made every attempt to ensure the accuracy of these materials, some errors may exist. NeoSystems is not responsible

More information

PEGASUS RESEARCH INSTITUTE THE DEVELOPMENT OF A COST ACCOUNTING AND PROJECT MANAGEMENT SYSTEM FOR A SMALL DEFENSE CONTRACTOR INSTRUCTOR NOTES

PEGASUS RESEARCH INSTITUTE THE DEVELOPMENT OF A COST ACCOUNTING AND PROJECT MANAGEMENT SYSTEM FOR A SMALL DEFENSE CONTRACTOR INSTRUCTOR NOTES PEGASUS RESEARCH INSTITUTE THE DEVELOPMENT OF A COST ACCOUNTING AND PROJECT MANAGEMENT SYSTEM FOR A SMALL DEFENSE CONTRACTOR INSTRUCTOR NOTES by Richard E. McDermott, Ph.D., Weber State University Contact

More information

CONTRACT INCENTIVES AND DISINCENTIVES

CONTRACT INCENTIVES AND DISINCENTIVES CONTRACT INCENTIVES AND DISINCENTIVES June 20, 2018 Fred Schlich Fred.Schlich@DAU.mil +1 334 728 2256 CONTRACT INCENTIVES AND DISINCENTIVES Why What How How Much How Many and much more 2 WHY HAVE INCENTIVES

More information

(17) Delete Section J, Attachment 6: Past Performance Tables

(17) Delete Section J, Attachment 6: Past Performance Tables PAGE 2 of 14 The purpose of this modification is to: (1) Correct the Clinger-Cohen Act citation under Section B.2 AUTHORITY; (2) Clarify the CAF formula and make it optional to include CAF in Loaded Hourly

More information

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 3, Lesson 2 Contract Financing

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 3, Lesson 2 Contract Financing STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 3, Lesson 2 Contract Financing October 2017 CON170, Unit 3 Lesson 2 Contract Financing - Page 1 STUDENT PREPARATION Required Student Preparation

More information

Guidance on Using Incentive and Other Contract Types

Guidance on Using Incentive and Other Contract Types Guidance on Using Incentive and Other Contract Types April 2016 Table of Contents Page 4-5 Background Contract Type as an Element of Overall Compensation Contract Performance Risk Page 5-7 Market Risk

More information

Guidance on Using Incentive and Other Contract Types

Guidance on Using Incentive and Other Contract Types Guidance on Using Incentive and Other Contract Types April 2016 Table of Contents Page 4-5 Background Contract Type as an Element of Overall Compensation Contract Performance Risk Page 5-7 Market Risk

More information

A Contractor s Guide to Surviving a Government Shutdown

A Contractor s Guide to Surviving a Government Shutdown A Contractor s Guide to Surviving a Government Shutdown By Tom Marcinko BACKGROUND As the late great Yogi Berra once said, It s deja vu all over again! The never ending political stalemate in Washington

More information

DEFENSE ACQUISITION UNIVERSITY CON Negotiation and Administration of Supply Contracts

DEFENSE ACQUISITION UNIVERSITY CON Negotiation and Administration of Supply Contracts 1 Given a complex fiscal law issue, and working in a team environment, generate a strategy which will resolve that issue. Interpret the major fiscal law statutes and regulations governing Federal contracting.

More information

Project Organization Part 2 & 3 Payment & Award Method

Project Organization Part 2 & 3 Payment & Award Method 1.040/1.401 Project Management Spring 2007 Project Organization Part 2 & 3 Payment & Award Method Dr. SangHyun Lee Department of Civil and Environmental Engineering Massachusetts Institute of Technology

More information

Falsification of Documents. Next Slide

Falsification of Documents. Next Slide Falsification of Documents Table of Contents Risk Assessment Research and Planning Risk Assessment Review of Permanent File Risk Assessment Initial Review of Proposal Document Risk Assessment Discussion

More information

Peer Review Recommendations, Lessons Learned

Peer Review Recommendations, Lessons Learned Peer Review s, Lessons Learned Pricing Feedback Weapon System, Production Lot Buy (Sole Source) Recommended that the team (preparing to negotiate the undefinitized contract action) coordinate with DCMA

More information

DATA ITEM DESCRIPTION

DATA ITEM DESCRIPTION DATA ITEM DESCRIPTION Title: Cost Data Summary Report (DD Form 1921) Number: DI-FNCL-81565C Approval Date: 20110518 AMSC Number: D9193 Limitation: DTIC Applicable: GIDEP Applicable: Preparing Activity:

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide, 6th Edition DAY 5

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide, 6th Edition DAY 5 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide, 6th Edition DAY 5 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Plan Risk Responses: Tools and Techniques Strategies for Negative Risks

More information

Part V in a Series: Cost Analysis and Cost Realism and Their Expanding Roles in Contract Pricing. government contracting

Part V in a Series: Cost Analysis and Cost Realism and Their Expanding Roles in Contract Pricing. government contracting Part V in a Series: Cost Analysis and Cost Realism and Their Expanding Roles in Contract Pricing 1 Your instructor... Bill Walter, CPA Managing Director DHG GovCon Advisory Bill.Walter@dhgllp.com 1410

More information

Guard Your Investment in Valuable Contracts

Guard Your Investment in Valuable Contracts Guard Your Investment in Valuable Contracts 1 PRESENTERS Mark Steranka Partner Moss Adams Consulting Robert Gutierrez, CPA, JD Manager Moss Adams Consulting 2 AGENDA Why Audit Contracts Federal Contracts

More information

GCS 224 Surviving DCAA Audits with GCS Premier. Presented by: Nicole Mitchell, Aronson & Company

GCS 224 Surviving DCAA Audits with GCS Premier. Presented by: Nicole Mitchell, Aronson & Company GCS 224 Surviving DCAA Audits with GCS Premier Presented by: Nicole Mitchell, Aronson & Company Agenda Government Contract Audits and the Role of DCAA and DCMA Basic Attributes of a Government Approved

More information

Information Technology Project Management Fifth Edition

Information Technology Project Management Fifth Edition Information Technology Project Management Fifth Edition By Jack T. Marchewka Northern Illinois University 4-1 Copyright 2015 John Wiley & Sons, Inc. Project Planning: The Project Infrastructure Chapter

More information

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Financial Proposal. Part 6

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Financial Proposal. Part 6 ARTES Competitiveness & Growth Full Proposal Requirements for the Content of the Financial Proposal Part 6 Statement of Applicability and Proposal Submission Requirements Applicable Domain(s) Space Ground

More information

5. All expenditures must be ones that are accounted for by the Applicant on its financial records under Generally Accepted Accounting Principles.

5. All expenditures must be ones that are accounted for by the Applicant on its financial records under Generally Accepted Accounting Principles. Section I. Grant Budget Instructions The budget should include all costs required to achieve the project goals, the amount to be reimbursed by Masstech, and the amount to be funded by Match sources (which

More information

Keys to Submitting an Adequate Incurred Cost Proposal

Keys to Submitting an Adequate Incurred Cost Proposal Keys to Submitting an Adequate Incurred Cost Proposal Presented By: Kiran Pinto, Senior Manager, Watkins Meegan Keith Romanowski, Compliance Director, WJ Technologies March 20, 2013 Agenda Who Needs to

More information

That seems to be a problematic approach, right? Think about it: Solving Executive Compensation Concerns with Blended Rates. Written by Nick Sanders

That seems to be a problematic approach, right? Think about it: Solving Executive Compensation Concerns with Blended Rates. Written by Nick Sanders The allowability of contractor executive compensation is a complex, tricky, thing made more tricky by recent statutory and regulatory changes. We have written about some of those rece nt changes before.

More information

COST AND PRICING: NO CONTRACT IS REALLY FINAL. Terry Albertson Skye Mathieson Liz Buehler

COST AND PRICING: NO CONTRACT IS REALLY FINAL. Terry Albertson Skye Mathieson Liz Buehler COST AND PRICING: NO CONTRACT IS REALLY FINAL Terry Albertson Skye Mathieson Liz Buehler 79 Three Phases Proposal Performance and Billing Final Payment 80 Proposal Forward pricing rates Labor rates Indirect

More information

Procurement Fraud s Anatomy. By Tom Caulfield CFE/CIG/CIGI

Procurement Fraud s Anatomy. By Tom Caulfield CFE/CIG/CIGI Procurement Fraud s Anatomy By Tom Caulfield CFE/CIG/CIGI LEARNING OBJECTIVES 1. Identify statutes, regulations, and key personnel associated with the contracting process. 2. Identify the primary acquisition

More information

MG-3 - Supplier Cost Price Analyses Best Practices for Evaluating Supplier Proposals and Quotes

MG-3 - Supplier Cost Price Analyses Best Practices for Evaluating Supplier Proposals and Quotes International Cost Estimating & Analysis Association - Supplier Cost / Price Analyses June 10-13, 2014 Presented By: David Eck, CPA Director Mike Mardesich, CPA Manager Dixon Hughes Goodman Government

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

Government Contracts Pricing Strategies and Rate Structures

Government Contracts Pricing Strategies and Rate Structures Government Contracts Pricing Strategies and Rate Structures Presented By: Brandon Smith bsmith@anglincpa.com Jon Levin jlevin@maynardcooper.com Provisional Billing Rates Provisional, Target, Budget, Billing,

More information

Section B Services, Ordering and Prices

Section B Services, Ordering and Prices Section B Services, Ordering and Prices B.1 Background Federal Strategic Sourcing was mandated by the Office of Management and Budget's (OMB s) Office of Federal Procurement Policy, and implemented by

More information

TITLE 70: DEPARTMENT OF FINANCE SUBCHAPTER COST AND PRICE ANALYSIS REGULATIONS

TITLE 70: DEPARTMENT OF FINANCE SUBCHAPTER COST AND PRICE ANALYSIS REGULATIONS SUBCHAPTER 70-30.1 COST AND PRICE ANALYSIS REGULATIONS Part 001 General Provisions 70-30.1-001 Overview and Summary 70-30.1-005 Scope 70-30.1-010 Definitions Part 100 Policy; Cost or Pricing Data 70-30.1-101

More information

The University Maryland Baltimore County

The University Maryland Baltimore County The University Maryland Baltimore County Office of Sponsored Programs Subaward Policies and Procedures Purpose The purpose of the University Maryland Baltimore County Subaward Policies and Procedures is

More information

DATA ITEM DESCRIPTION

DATA ITEM DESCRIPTION DATA ITEM DESCRIPTION Title: Cost Data Summary Report (DD Form 1921) Number: DI-FNCL-81565B Approval Date: 20070420 AMSC Number: D7721 DTIC Applicable: Preparing Activity: (D)OSD/PA&E/CAIG Limitation:

More information

Incurred Cost Submissions

Incurred Cost Submissions Incurred Cost Submissions Further information is available in the Information for Contractors Manual under Enclosure 6 The views expressed in this presentation are DCAA's views and not necessarily the

More information

ARCHITECT/ENGINEER CONTRACTS, FEE ESTIMATION, AND REQUESTS FOR PAYMENT

ARCHITECT/ENGINEER CONTRACTS, FEE ESTIMATION, AND REQUESTS FOR PAYMENT ARCHITECT/ENGINEER CONTRACTS, FEE ESTIMATION, AND REQUESTS FOR PAYMENT Overview Introduction This document supplements the Smithsonian Institution Office of Facilities Engineering & Operations Special

More information

Types of Government Contracts

Types of Government Contracts Types of Government Contracts A primer on four common types found in RFPs There are several types of government contracts, and the differences between them are not trivial. Each requires a unique approach

More information

Indirect Rates for Cost Plus Contracting Jenny W Clark. Jenny Clark

Indirect Rates for Cost Plus Contracting Jenny W Clark. Jenny Clark Indirect Rates for Cost Plus Contracting Jenny W Clark Jenny Clark jwclark@solvability.com Jenny W Clark The Oprah of Federal Contracting Solvability, Inc. www.solvability.com Phone 256-882-6276 E-mail

More information

Aerospace Industry - Audit Techniques Guide - January 2005

Aerospace Industry - Audit Techniques Guide - January 2005 Aerospace Industry - Audit Techniques Guide - January 2005 NOTE: This guide is current through the publication date. Since changes may have occurred after the publication date that would affect the accuracy

More information

Using GCS to Drive Decision Making Susan Smith, WJ Technologies Antoinette Merrill, Summit Consulting

Using GCS to Drive Decision Making Susan Smith, WJ Technologies Antoinette Merrill, Summit Consulting GCS Premier It s Not Just A History Lesson Using GCS to Drive Decision Making Susan Smith, WJ Technologies Antoinette Merrill, Summit Consulting GCS Premier It s Not Just A History Lesson Objective: To

More information

Allowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management

Allowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management Allowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management Breakout Session #: B11 Presented by: Melanie Burgess and Phillip Seckman Date: July 22, 2013

More information

DISASTER DOCUMENTATION

DISASTER DOCUMENTATION DISASTER DOCUMENTATION Procurement & Recordkeeping Contracts Labor Equipment Materials Forms Federal Procurement / Contracting Guidance DISASTER DOCUMENTATION PART I Procurement & Record Keeping Overview........................

More information

BETTER JACKSONVILLE PLAN HDR ENGINEERING CONTRACT. March 07, 2006 REPORT #613

BETTER JACKSONVILLE PLAN HDR ENGINEERING CONTRACT. March 07, 2006 REPORT #613 BETTER JACKSONVILLE PLAN HDR ENGINEERING CONTRACT March 07, 2006 REPORT #613 OFFICE OF THE COUNCIL AUDITOR Suite 200, St. James Building March 7, 2006 Honorable Members of the City Council City of Jacksonville

More information

Limitations on Pass-Through Charges. Government Contracts Update Volume 2, Nov. 2011

Limitations on Pass-Through Charges. Government Contracts Update Volume 2, Nov. 2011 Limitations on Pass-Through Charges Government Contracts Update Volume 2, Nov. 2011 11/22/2011 Vol. 2, Nov 2011 Page 1 of 4 Limitations on Pass-Through Charges Two new clauses were added to the FAR effective

More information

Pricing Subcontracts to Win Work and Make a Profit

Pricing Subcontracts to Win Work and Make a Profit Pricing Subcontracts to Win Work and Make a Profit Breakout Session C02 Rita L. Wells, PhD Senior Acquisition Executive, Suntiva Deidre A. Lee Consultant Date: Thursday, March 17, 2016 Time: 3:45pm 5:00pm

More information

SPECIAL CONDITIONS OF TENDER

SPECIAL CONDITIONS OF TENDER Page 1 SPECIAL CONDITIONS OF TENDER A. INTRODUCTION The following documents are available on http://emits.esa.int/ under "Reference Documentation" --> "Administrative Documents": ESA Procurement Regulations

More information

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. Accounts Payable Obligations to pay for goods and services that have

More information

In this chapter: Budgets and Planning Tools. Configure a budget. Report on budget versus actual figures. Export budgets.

In this chapter: Budgets and Planning Tools. Configure a budget. Report on budget versus actual figures. Export budgets. Budgets and Planning Tools In this chapter: Configure a budget Report on budget versus actual figures Export budgets Project cash flow Chapter 23 479 Tuesday, September 18, 2007 4:38:14 PM 480 P A R T

More information

Earned Value Management Tutorial Module 4: Budgeting. Prepared by:

Earned Value Management Tutorial Module 4: Budgeting. Prepared by: Earned Value Management Tutorial Module 4: Budgeting Prepared by: Module 4: Budgeting Welcome to Module 4. The objective of this module is to introduce you to Budgeting Concepts and Definitions. The Topics

More information

Proposal Adequacy Checklist

Proposal Adequacy Checklist The offeror shall complete the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror s checklist,

More information

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME WORKING NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP/ COORDINATION GROUP

More information

GSA Audits From Anxiety to Zen

GSA Audits From Anxiety to Zen GSA Audits From Anxiety to Zen Wednesday, September 20, 2017 Dismas N. Locaria, Esq. CPT. Scott M. Davidson, USA, Ret. Partner, Venable LLP Managing Principal, The GCO Consulting Group dlocaria@venable.com

More information

Project Management Certification. Multiple Choice Questions

Project Management Certification. Multiple Choice Questions Project Management Certification (PMP) Project Management Certification (PMP) Multiple Choice Questions QUESTION 1 In Project Cost Management, which input is exclusive to the Determine Budget process?

More information

Contract Administration Final Exam

Contract Administration Final Exam Contract Administration Final Exam 1. You want to solicit bids for a one year contract for concrete to support your roadway construction work. At this time, prices are fluctuating due to high demand and

More information

CONTRACT COST STATEMENT

CONTRACT COST STATEMENT Lockwood, Andrews & Newnam, Inc. Austin, Texas Lockwood, Andrews & Newnam, Inc. CONTRACT COST STATEMENT For the Period February 5, 2005 - May 31, 2009 November 23, 2009 TABLE OF CONTENTS Independent Accountant

More information

DELIVERY ORDER 1. CONTRACT NO. 2. DELIVERY ORDER NO. 3. EFFECTIVE DATE 4. PURCHASE REQUEST NO. ORIG 03/09/2006 MOD 04/21/2008

DELIVERY ORDER 1. CONTRACT NO. 2. DELIVERY ORDER NO. 3. EFFECTIVE DATE 4. PURCHASE REQUEST NO. ORIG 03/09/2006 MOD 04/21/2008 DELIVERY ORDER FINAL 1. CONTRACT NO. 2. 3. EFFECTIVE DATE 4. PURCHASE REQUEST NO. ORIG 03/09/2006 MOD 04/21/2008 N00167-08-MR-65330 5. ISSUED BY CODE N00167 6. ADMINISTERED BY CODE S2101A NSWC, CARDEROCK

More information

Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective

Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective Breakout Session #: C16 Presented by: Philip R. Seckman Christopher W. Myers Date: July 22, 2013 Time: 4:00-5:15 Agenda

More information

New revenue guidance Implementation in Industrial Products

New revenue guidance Implementation in Industrial Products No. US2017-16 August 17, 2017 What s inside: Overview... 1 Step 1: Identify the contract with the customer... 2 Step 2: Identify performance obligations... 4 Step 3: Determine... 5 Step 4: Allocate...8

More information

LONG INTERNATIONAL. James M. Bolin

LONG INTERNATIONAL. James M. Bolin James M. Bolin LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com James M. Bolin Table of

More information

6/25/2014. Navy Small Business Innovation Research (SBIR) Program. Navy Needs Are Diverse

6/25/2014. Navy Small Business Innovation Research (SBIR) Program. Navy Needs Are Diverse Navy Small Business Innovation Research (SBIR) Program 1 Navy Needs Are Diverse 2 1 SBIR Program Phases I, II III Feasibility Study Phase I contracts award with SBIR funding up to $80k with a $70k option.

More information

Subcontract Pricing Deficiencies. Next Slide

Subcontract Pricing Deficiencies. Next Slide Subcontract Pricing Deficiencies Table of Contents Risk Assessment Research and Planning Risk Assessment Review of Contract and Price Negotiation Memorandum (PNM) Risk Assessment Overrun/Underrun Analysis

More information

GEO AGREEMENT NO. S#### STATE OF FLORIDA GRANT ASSISTANCE PURSUANT TO

GEO AGREEMENT NO. S#### STATE OF FLORIDA GRANT ASSISTANCE PURSUANT TO DISCLAIMER: This grant agreement template is provided for reference only and may be subject to change. GEO AGREEMENT NO. S#### STATE OF FLORIDA GRANT ASSISTANCE PURSUANT TO THIS AGREEMENT is entered into

More information

RE: Request for Proposals (RFP) Consultant Services for Public Transit Board Training

RE: Request for Proposals (RFP) Consultant Services for Public Transit Board Training State of Vermont Agency of Transportation Contract Administration Finance & Administration One National Life Drive [phone] 802-828-2641 Montpelier VT 05633-5001 [fax] 802-828-5545 http://vtrans.vermont.gov/

More information

Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts.

Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts. Page 1 of 11 Modification Details Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts. 1. Make the following Changes in Section G: a. ADD HQ G-2-0005 Payment

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3

More information

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation

More information

AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME

AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME WORKING NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP VERSION 1 APPROVED

More information

Chapter 12. Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims

Chapter 12. Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims Chapter 12 Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims Table of Contents 12-000 Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment

More information

Acceptable costs in SBO and TBM projects (COST MODEL)

Acceptable costs in SBO and TBM projects (COST MODEL) 1. Introduction Acceptable costs in SBO and TBM projects (COST MODEL) 1.1. Purpose of the cost model This document contains important guidelines for: - the preparation of a project budget (in the project

More information

Essentials of Government Contracting Post-Award

Essentials of Government Contracting Post-Award Essentials of Government Contracting Post-Award Presented by: Marsha Cervantez Sofia Iqbal Chris Mikaelian Manager, Government Contracts Contract Negotiator Manager, Government Contracts GDC4 Systems,

More information

REQUEST FOR PROPOSAL FOR. Full Cost Allocation Plan and Citywide User Fee and Rate Study. Finance Department CITY OF HUNTINGTON BEACH

REQUEST FOR PROPOSAL FOR. Full Cost Allocation Plan and Citywide User Fee and Rate Study. Finance Department CITY OF HUNTINGTON BEACH REQUEST FOR PROPOSAL FOR Full Cost Allocation Plan and Citywide User Fee and Rate Study Finance Department CITY OF HUNTINGTON BEACH Released on October 17, 2007 Full Cost Allocation Plan and Citywide User

More information

Contract Compliance and the Federal Acquisition Regulation (FAR) ORA CERTIFICATE PROGRAM (MODULE 11) 20 APRIL 2016

Contract Compliance and the Federal Acquisition Regulation (FAR) ORA CERTIFICATE PROGRAM (MODULE 11) 20 APRIL 2016 Contract Compliance and the Federal Acquisition Regulation (FAR) ORA CERTIFICATE PROGRAM (MODULE 11) 20 APRIL 2016 Learning Objectives Participants will learn about the history of the Federal Acquisition

More information

Terms & Conditions of Sale

Terms & Conditions of Sale MSI undertakes to carry out maintenance and repair work on the Customer s aircraft or its components and to procure spare parts and equipment required for the execution of maintenance and repair orders.

More information

Case Study. IR-SIP Risk Management Plan Outline

Case Study. IR-SIP Risk Management Plan Outline Case Study IR-SIP Risk Management Plan Outline Baselined: Last Modified: Owner: Purpose: Section 1. Introduction 1.1 Purpose and Scope 1.2 Assumptions, Constraints, and Policies 1.3 Related Documents and

More information

International Cost Estimating & Analysis Association. Supplier Cost/Price Analyses June 20, 2013

International Cost Estimating & Analysis Association. Supplier Cost/Price Analyses June 20, 2013 International Cost Estimating & Analysis Association Supplier Cost/Price Analyses June 20, 2013 David Eck and Todd W. Bishop Dixon Hughes Goodman LLP Government Contract Consulting Services Group Agenda

More information

Truth in Negotiations Act (TINA) Essentials

Truth in Negotiations Act (TINA) Essentials Truth in Negotiations Act (TINA) Essentials Breakout Session #: F03 Presented by: Brent Calhoon, Partner, Baker Tilly Shingai Mavengere, Senior Manager, Baker Tilly Date: Tuesday, July 23 Time: 4:00pm-5:15pm

More information

Request for Proposals. For. Financial Aid Services. Issued by: Pennsylvania State System of Higher Education Office of the Chancellor

Request for Proposals. For. Financial Aid Services. Issued by: Pennsylvania State System of Higher Education Office of the Chancellor Request for Proposals For Issued by: Pennsylvania State System of Higher Education RFP # 2010-QCC-RLG-04 Issue Date: January 22, 2010 Response Date: February 12, 2010 Table of Contents Page Part I General

More information

Pricing Risk In Your Next Contract

Pricing Risk In Your Next Contract Pricing Risk In Your Next Contract Breakout Session #C06 Robert E. Jones, CPA, CPCM, Fellow Government Contracts & Accounting Expert Left Brain Professionals Inc. Date: Monday, December 4, 2017 Time: 2:45

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

SUBPART CONTRACT PRICING (Revised November 24, 2008)

SUBPART CONTRACT PRICING (Revised November 24, 2008) SUBPART 215.4--CONTRACT PRICING (Revised November 24, 2008) 215.402 Pricing policy. Follow the procedures at PGI 215.402 when conducting cost or price analysis, particularly with regard to acquisitions

More information

Research Administration Start to Finish. (GC1000) Complete Course

Research Administration Start to Finish. (GC1000) Complete Course Part II Research Administration Start to Finish (GC1000) Complete Course Award Administration (Module 2.00) In this module Project Start-Up Expenditures Expense Monitoring Compliance Spending Awards Personnel

More information

SPECIAL TENDER CONDITIONS FOR THE

SPECIAL TENDER CONDITIONS FOR THE Page 1 SPECIAL TENDER CONDITIONS FOR THE Integrated Applications Promotion (IAP) Programme (CALL FOR PROPOSALS) FEASIBILITY STUDIES Page 2 A. INTRODUCTION The following documents are available on http://emits.esa.int/

More information

RHODE ISLAND AIRPORT CORPORATION. Procurement Rules. Adopted: April 27, 1994

RHODE ISLAND AIRPORT CORPORATION. Procurement Rules. Adopted: April 27, 1994 RHODE ISLAND AIRPORT CORPORATION Procurement Rules Adopted: April 27, 1994 TABLE OF CONTENTS SECTION 1 - DEFINITIONS 1 SECTION 2 - GENERAL PROVISIONS 11 2.1 PURPOSES AND POLICIES 11 2.1.1 Administrative

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor Address Address City, Zip Work Phone Number: Cell Phone Number:

More information

ISSUE PAPER. Acquisition Policy Changes: Impacts on Contract Profitability

ISSUE PAPER. Acquisition Policy Changes: Impacts on Contract Profitability ISSUE PAPER Acquisition Policy Changes: Impacts on Contract Profitability Federal acquisition policy expressly recognizes the importance of the contractor s ability to earn reasonable returns on business

More information

Request for Proposal

Request for Proposal Request for Proposal RFP No. 2017 11 001 Consulting Services for Emergency Operations Response Plans Issue Date Monday, November 20, 2017 ISSUED BY OFFICE OF PROCUREMENT RICE UNIVERSITY 6100 MAIN ST.,

More information

Technical Line FASB final guidance

Technical Line FASB final guidance No. 2017-27 25 August 2017 Technical Line FASB final guidance How the new revenue standard affects engineering and construction entities In this issue: Overview... 1 Identifying performance obligations

More information

The ABCs of the UCF: A look at Section L and Section M

The ABCs of the UCF: A look at Section L and Section M The ABCs of the UCF: A look at Section L and Section M By: Jennifer Leotta Abstract This paper will examine the government cost analyst s role in the contract award process. Specifically, it will look

More information

JANUARY 2004 LAWRENCE WASDEN

JANUARY 2004 LAWRENCE WASDEN Office of the Attorney General Idaho Lemon Law JANUARY 2004 LAWRENCE WASDEN Attorney General Statehouse Boise, ID 83720-0010 www.ag.idaho.gov State of Idaho Office of Attorney General Lawrence Wasden My

More information

C. Appropriation a funding amount approved and designated by the City Commission as part of the capital budget process for project implementation.

C. Appropriation a funding amount approved and designated by the City Commission as part of the capital budget process for project implementation. City Commission Policy # 218 DEPARTMENT: Administration & Professional Services DATE ADOPTED: January 9, 1991 DATE OF LAST REVISION: April 27, 2016 218.01 AUTHORITY 218.02 PURPOSE City Commission adoption

More information

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 Page 1 ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 [COVER LETTER] From:... (Tenderer to insert name of the company/institute submitting the tender) Date:...

More information

New York University UNIVERSITY POLICIES

New York University UNIVERSITY POLICIES New York University UNIVERSITY POLICIES Title: Managing Subawards Issued by NYU Policy Effective Date: December 1, 2017 Supersedes: December 26, 2014 Issuing Authority: Responsible Officer: Sponsored Programs

More information