UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Size: px
Start display at page:

Download "UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION"

Transcription

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator ) Docket No. ER Corporation ) ) MOTION TO INTERVENE, LIMITED PROTEST AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY Under Rules 211 and 214 of the Rules and Regulations of the Federal Energy Regulatory Commission ( Commission or FERC ) 1 and the Commission s September 11, 2014 Combined Notice of Filings in the foregoing docket, Southern California Edison Company ( SCE ) submits this motion to intervene, comments and limited protest regarding the proposed pro forma Approved Project Sponsor Agreement ( APSA ) filed by the California Independent System Operator Corporation (the CAISO ) on September 10, I. INTRODUCTION In its Competitive Transmission Improvements stakeholder process, CAISO agreed to develop the APSA to (1) acknowledge acceptance of the selection of the approved Project Sponsor, (2) establish the obligations, roles and responsibilities of the Project Sponsor, including project specific milestones; and (3) memorialize any binding cost 1 18 C.F.R and 18 C.F.R Filing Letter re California Independent System Operator Corporation Pro Forma Approved Project Sponsor Agreement Docket No. ER ( CAISO APSA Filing Letter ). 1

2 control measures, including binding cost caps that the approved Project Sponsor agreed to in its application. SCE has an interest in the APSA, not only as a potential bidder in the competitive transmission process, but also as an interconnecting participating transmission owner ( PTO ) and a steward of its ratepayers. Additionally, under the CAISO Tariff, SCE may be required to serve as the backstop for projects terminating in its service territory, meaning that if the project is abandoned, CAISO may be able to require SCE to complete the project. SCE actively participated in the formation of the APSA and seeks to intervene in this docket for the reasons discussed below. II. SCE S SPECIFIC ISSUES WITH CAISO S APSA A. CAISO Should Clarify its Intent Regarding the Definition of Force Majeure in the APSA The definition of Force Majeure used in the latest draft of the APSA differs from the defined term used in the CAISO Tariff as follows (bold underline represents additions to the CAISO Tariff): any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, earthquake, or explosion, any order, regulation, or restriction imposed by governmental, military, or lawfully established civilian authorities, or any other cause beyond the reasonable control of the Parties that could not have been avoided through the exercise of Good Utility Practice. A Force Majeure event does not include (1) acts of negligence or intentional wrongdoing by the Party claiming Force Majeure; (2) economic conditions that render a Party s performance of this Agreement unprofitable or otherwise uneconomic; (3) economic hardship of either Party; 3 or (4) failure or delay in 3 The pro forma Large Generator Interconnection Agreement ( LGIA ) uses the CAISO Tariff definition of Force Majeure, but separately excludes economic hardship in Section

3 granting of necessary permits for reasons not caused by Force Majeure. SCE seeks to confirm that CAISO s intent in expressly excluding from Force Majeure economic conditions that render a Party s performance of this Agreement unprofitable or otherwise uneconomic is to exclude only those economic conditions that are not otherwise a Force Majeure. If economic conditions that render a Party s performance of this Agreement unprofitable or otherwise uneconomic result from an act of God or governmental regulation or restriction, such economic conditions would still qualify as Force Majeure. To the extent CAISO means to exclude from the definition of Force Majeure all economic consequences, regardless of how they arise, the APSA is not just and reasonable and should be revised by removing subsections (2) and (3) above. Relatedly, CAISO s ability to terminate under Section 5.8 requires unreasonable delay. This should not be required; if completion of the project proves infeasible, CAISO should not also need to show unreasonable delay in order to terminate the project. B. CAISO Should Initiate a Stakeholder Process to Determine Whether the Project Sponsor Should Be Required to Post Financial Security In its Designated Entity Agreement ( DEA ) filed in compliance with Order 1000, 4 PJM Interconnection, L.L.C. ( PJM ) requires the Designated Entity (the equivalent in PJM of CAISO s Project Sponsor) to post financial security of three percent of project costs to 4 On July 14, 2014, PJM submitted, in Docket ER , a pro forma Interconnection Coordination Agreement as Attachment LL of PJM s Open Access Transmission Tariff (OATT) and, in Docket No. ER , a pro forma Designated Entity Agreement as Attachment KK of PJM s OATT to comply with the Commission s directive in its May 15, 2014 order on PJM s compliance with Order No FERC approved PJM s agreements on the condition that PJM make minor modifications. See Order Conditionally Accepting Proposed Agreements Subject To A Further Compliance Filing, in Docket Nos. ER and ER (September 12, 2013). 3

4 cover the incremental costs of construction resulting from having to reassign the project if the Designated Entity defaults or abandons the project. 5 No one protested this requirement and the Commission approved the DEA without requiring modification to this provision. 6 CAISO s APSA requires no financial security. Without some reasonable financial security requirement, utility ratepayers may bear costs associated with transferring the project from an abandoning Project Sponsor to an alternative Project Sponsor or a backstop PTO, costs for which ratepayers receive no benefit. SCE has asked that CAISO consider whether to include a financial security requirement in its pro forma APSA and on April 18, 2014, SCE requested that CAISO initiate a stakeholder process on this issue. As of the time of this filing, CAISO has not initiated such a process. SCE requests that FERC direct CAISO to initiate this separate stakeholder process within a reasonable timeframe. The APSA may need to be revised depending on the outcome of this process. C. The Project Sponsor Should Not be Allowed to Assign Project Assets Absent CAISO Consent The APSA does not require the Project Sponsor to obtain CAISO consent before transferring its rights in the project to a third party such as a lender. That contradicts other CAISO agreements, the CAISO Tariff, and standard financial practices. The Transmission Control Agreement ( TCA ), which governs the assets once they are put under CAISO 5 Filing Letter re PJM Interconnection, L.L.C., Docket No. ER (3 rd Compliance Filing) ( PJM Filing Letter ) at See also, Order on Rehearing and Compliance, Docket No. ER , et al. at P 417 (June 19, 2014) ( [i]t may be appropriate to require additional collateral once a project has been selected in a regional transmission plan for purposes of cost allocation to ensure that the transmission developer has adequate resources to construct the transmission project. ). 4

5 operational control, restricts a PTO s ability to transfer the transmission assets. 7 Likewise, the CAISO Tariff restricts such transfer without CAISO consent, providing: The Approved Project Sponsor shall not sell, assign or otherwise transfer its rights to finance, construct and own the needed transmission solution, or any element thereof, before the facilities have been energized and, if applicable, turned over to the CAISO s Operational Control unless the CAISO has approved such proposed transfer, which approval shall not be unreasonably withheld. A Project Sponsor must meet certain qualification criteria to be considered in the competitive solicitation process. To allow assignment without CAISO consent, even to a lender, would allow a Project Sponsor to transfer the project to a non-qualified third-party, circumventing the qualification criteria essential to ensuring that a competent party will build the project. CAISO must ensure that the Project Sponsor has not inappropriately assigned its rights in a manner that could jeopardize ratepayers or be inconsistent with the CAISO Tariff or other provisions of the APSA. As PJM explained in a recent FERC filing:... [T]the requirement that assignments are valid only upon written consent of the other party, provides the protections necessary to ensure that an assignee can perform as well as the Designated Entity and that a reliability project will not be compromised by the assignment. PJM must have some control over entities that are constructing upgrades on the PJM system to ensure safety and reliability and, therefore, must have the ability to consent to all assignments. 8 The APSA provides that the Approved Project Sponsor shall have the right to assign this Agreement, without the consent of the CAISO, for collateral security purposes. 9 The APSA should be modified to require CAISO consent for all assignments, including collateral assignment, which consent will not be unreasonably withheld. CAISO should of the Transmission Control Agreement. 8 PJM Filing Letter at 30 (emphasis added). 9 CAISO ASPA Section

6 establish, in the APSA or in an attached form of consent to collateral assignment, the conditions upon which such consent would be granted. Such conditions should, at a minimum, include that 1) CAISO receives notice from the lender of any Project Sponsor default under the loan agreements, 2) the lender or its designee, upon stepping into the shoes of the Project Sponsor, must establish that it meets the qualification criteria and has the comparable ability to complete the project, and 3) upon stepping into the shoes of the Project Sponsor, the lender agrees to be bound by all the terms and conditions of the APSA. D. The APSA Should Provide Stronger Language Regarding a Project Sponsor s Obligation to Transfer Project Assets Upon Abandonment As a PTO with possible backstop obligations and on behalf of ratepayers, SCE has an interest in ensuring that asset transfer from a failed Project Sponsor to the backstop PTO or alternative Project Sponsor occurs quickly and without imposing unreasonable costs. The APSA language merely provides that the Project Sponsor agrees to work with CAISO, the alternate Project Sponsor, and, if applicable, the Interconnecting PTO to transfer responsibility for the Project to the alternative Project Sponsor. 10 This language is not sufficient; it only contemplates that the Project Sponsor will transfer responsibility to the alternate Project Sponsor and says nothing about rights. The APSA should require a Project Sponsor that abandons a needed project to transfer (a) all right, title, and interest in real and personal property, (b) all rights under agreements associated with the Project, including any interconnection agreements, and (c) any rights, title or interest that may have been pledged or assigned to any third parties 10 CAISO APSA Section

7 (including without limitation, lenders, contractors or subcontractors) to the alternative Project Sponsor, or a backstop PTO, if the alternative Project Sponsor or a backstop PTO is willing to assume such ownership interest, obligations, rights or agreements. CAISO concluded this language is unnecessary because a project sponsor has no motivation to hold rights in connection with a project when it is no longer in a position to recover the costs of the project as a participating transmission owner. Rather, it has every reason to transfer those rights to the extent it can. 11 SCE is concerned that such an assumption may not be warranted, in that retention of rights by a failed Project Sponsor gives the failed Project Sponsor leverage that could compromise timely and cost-effective transfer of the project to the backstop or alternative Project Sponsor. In any event, there is no reason to leave such important matters to mere assumption. E. The APSA Should be Modified to Preserve the Third-Party Beneficiary Rights of an Alternative Project Sponsor or Backstop PTO The APSA provides that it does not create rights for third parties to seek remedies for a party s breach of the APSA. 12 However, SCE believes that such rights may be necessary and appropriate to allow a PTO backstop or an alternative Project Sponsor selected by CAISO to fulfill its responsibilities under the CAISO Tariff and to protect ratepayers. For these limited purposes, third party rights should be provided under the APSA, to backstopping PTOs and any alternative Project Sponsor selected by CAISO. 11 CAISO APSA Filing Letter at APSA Section 25.5 ( This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest, and, where permitted, their assigns. ). 7

8 F. CAISO Should Require the Project Sponsor to Procure Insurance in Accordance with Good Utility Practice The APSA does not require the Project Sponsor to procure insurance beyond what is required by state law. CAISO argues that insurance would create an additional financial requirement above what is required by the tariff. But PJM s DEA requires that the Project Sponsor procure insurance in accordance with Good Utility Practice, even though this requirement is an additional financial requirement. And in its Order on PJM s DEA, FERC did not require PJM to modify this provision. CAISO further argues that the fact that the approved Project Sponsor has met the financial qualification criteria indicates a high likelihood that it is capable of weathering any liability findings. 13 SCE has no visibility into what threshold of financial integrity a Project Sponsor must meet to be selected the tariff lists the types of financial information that a bidder may provide and leaves the determination of how much is enough to the discretion of CAISO. SCE and its ratepayers will be affected, however, if the Project Sponsor fails to properly insure itself. Any Project Sponsor could face a catastrophic loss that could overwhelm its current credit and cash position particularly if the entity is a limited liability corporation formed for the single purpose of developing a single transmission asset. The potential for such catastrophic loss is why companies buy commercial insurance. If the Project Sponsor is underinsured and cannot cover its liabilities, CAISO and ultimately utility ratepayers may have to make up the shortfall. 13 CAISO APSA Filing Letter at 13. 8

9 SCE recommends that, as the very least, the APSA require the Project Sponsor to procure insurance in accordance with Good Utility Practice. G. The APSA Should Require CAISO Approval of Material Modifications Only The APSA provides that the Approved Project Sponsor may undertake modifications to its facilities only with the approval of the CAISO and requires ninety (90) days advance notice. 14 This requirement may be impractical for every change to the facility not in accordance with the specifications. SCE recommends that the APSA include a concept of materiality and require CAISO s pre-approval of only those modifications that are material in nature. III. MOTION TO INTERVENE SCE, a wholly-owned subsidiary of Edison International, is an investor-owned utility subject to the Commission s jurisdiction. SCE s principal place of business is 2244 Walnut Grove Avenue, Rosemead, California SCE is a PTO in CAISO and a potential party to the APSA. SCE and its ratepayers will be directly affected by the outcome of this proceeding. SCE therefore has a direct and substantial interest in, and may be affected by, the instant proceeding. No other party can adequately represent SCE s interest in this proceeding. 14 CAISO APSA Section

10 IV. COMMUNICATIONS SCE designates the following persons for official service, and all communications, pleadings and orders regarding this proceeding should be directed to them: Claire Torchia 2244 Walnut Grove Avenue Rosemead, CA David Schiada 3 Innovation Way Pomona, CA David.Schiada@sce.com V. CONCLUSION SCE respectfully requests that the Commission take account of SCE s comments in ruling on CAISO s proposed APSA. Respectfully submitted, /s/ Claire E. Torchia Claire E. Torchia SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Rosemead, CA Tel. (626) Fax (626) Claire.Torchia@sce.com Dated: October 1,

11 CERTIFICATE OF SERVICE I hereby certify that I have this day served the foregoing MOTION TO INTERVENE, LIMITED PROTEST AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Rosemead, California, this 1st day of October, 2014 /s/ Rodger Torres Rodger Torres, Case Analyst SOUTHERN CALIFORNIA EDISON CO Walnut Grove Avenue Post Office Box 800 Rosemead, California Telephone: (626)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation ) ) ) Docket No. ER13-872-000 MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corp., Docket No. ER15-1229-000 MOTION TO INTERVENE AND COMMENTS OF Pursuant to Rules 211

More information

September 21, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

September 21, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 DANIEL L. LARCAMP 202.274.2841 telephone 202.654.5616 facsimile daniel.larcamp@troutmansanders.com TROUTMAN SANDERS LLP Attorneys at Law 401 9th Street, N. W., Suite 1000 Washington, D.C. 20004-2134 202.274.2950

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service Company ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service Company ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Arizona Public Service Company ) Docket No. ER16-1342- MOTION FOR CLARIFICATION OR, IN THE ALTERNATIVE, REQUEST FOR REHEARING OF

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 101 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

KOOTENAI ELECTRIC COMMUNITY SOLAR PROGRAM APPLICATION & AGREEMENT

KOOTENAI ELECTRIC COMMUNITY SOLAR PROGRAM APPLICATION & AGREEMENT Thank you for your interest in the Kootenai Electric Community Solar Program (Program). By completing this Application (Application), you have an opportunity to participate in the Program. You agree to

More information

September 8, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

September 8, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Karen Koyano Principal Manager FERC Rates & Compliance September 8, 2016 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose:

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southern California Edison ) Docket No. ER Company )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southern California Edison ) Docket No. ER Company ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Southern California Edison ) Docket No. ER12-239-000 Company ) SOUTHERN CALIFORNIA EDISON COMPANY S REQUEST FOR LEAVE AND RESPONSE

More information

COMMUNITY SOLAR PARTICIPATION AGREEMENT

COMMUNITY SOLAR PARTICIPATION AGREEMENT COMMUNITY SOLAR PARTICIPATION AGREEMENT Thank you for your interest in Tacoma Power s Community Solar Program ( Program ). By completing this Agreement, you have an opportunity to participate in and facilitate

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 92 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. San Diego Gas & Electric Company ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. San Diego Gas & Electric Company ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION San Diego Gas & Electric Company ) Docket No. EL15-103-000 REQUEST FOR REHEARING OF PACIFIC GAS AND ELECTRIC COMPANY AND SOUTHERN

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) James A. Cuillier Director FERC Rates & Regulation Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate Annual

More information

February 25, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the LGIA.

February 25, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the LGIA. Regulation James A. Cuillier Director FERC Rates & Regulation February 25, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

LS Power. Presentation to the PJM Transmission Expansion Advisory Committee. December 9, Bringing Energy Forward

LS Power. Presentation to the PJM Transmission Expansion Advisory Committee. December 9, Bringing Energy Forward LS Power Presentation to the PJM Transmission Expansion Advisory Committee December 9, 2014 The Proposal (PJM Project ID: P2013_1-5A) New 500/230 kv transformer at Salem New Silver Run 230 kv switchyard

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 93 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

December 22, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

December 22, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 James A. Cuillier Director FERC Rates & Regulation December 22, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: FERC Docket No.

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket Nos. ER06-615-000 Operator Corporation ) ER07-613-000 ) ) (not consolidated) ) STATUS REPORT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Credit and Capital Issues Affecting the ) Docket No. AD09-2-000 Electric Power Industry ) COMMENTS OF SOUTHERN CALIFORNIA EDISON

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-641-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

Pursuant to Rules 211, 213, and 214 of the Rules and Regulations of the Federal

Pursuant to Rules 211, 213, and 214 of the Rules and Regulations of the Federal UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Winding Creek Solar LLC ) ) ) Docket Nos. EL15-52-000 QF13-403-002 JOINT MOTION TO INTERVENE, PROTEST, AND ANSWER OF SOUTHERN CALIFORNIA

More information

June 23,2006. Docket Nos. ER , ER , ER , E RO4-443-OO-.

June 23,2006. Docket Nos. ER , ER , ER , E RO4-443-OO-. The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-756-3300 Fax: 202-654-4872 Sean A. Atkins Direct Dial: 202-756-3072 June 23,2006 The Honorable Magalie Roman Salas Secretary Federal

More information

Project J290. AMENDED AND RESTATED FACILITIES CONSTRUCTION AGREEMENT by and among. Border Winds Energy, LLC, Otter Tail Power Company.

Project J290. AMENDED AND RESTATED FACILITIES CONSTRUCTION AGREEMENT by and among. Border Winds Energy, LLC, Otter Tail Power Company. SA 2678 BORDER WINDS-OTTER TAIL POWER FCA EFFECTIVE 07/19/2014 SUBSTITUTE ORIGINAL SERVICE AGREEMENT NO. 2678 PUBLIC VERSION Project J290 AMENDED AND RESTATED FACILITIES CONSTRUCTION AGREEMENT by and among

More information

LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) AMONG [INTERCONNECTION CUSTOMER] AND [PARTICIPATING TO] AND

LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) AMONG [INTERCONNECTION CUSTOMER] AND [PARTICIPATING TO] AND (LGIA) AMONG [INTERCONNECTION CUSTOMER] AND [PARTICIPATING TO] AND CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION PROJECT: Project Name (Q#) TABLE OF CONTENTS LARGE GENERATOR INTERCONNECTION AGREEMENT...

More information

August 16, Attachment 1 to the Formula Rate is the Formula Protocols, and Attachment 2 is the Formula Spreadsheet. 2

August 16, Attachment 1 to the Formula Rate is the Formula Protocols, and Attachment 2 is the Formula Spreadsheet. 2 Karen Koyano Principle Manager FERC Rates and Compliance Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to Section 205 of the Federal Power Act and

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, and Nora Mead Brownell. California Power Exchange Corporation Docket No.

More information

ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT

ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT THIS STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT ( Agreement ) is made and entered

More information

June 21, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Letter Agreement.

June 21, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Letter Agreement. Karen Koyano Principal Manager FERC Rates & Compliance June 21, 2017 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Quarterly Reports Docket No. RM01-8-000 Docket No. ER02-2001-000 COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY ON THE

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company, et al. ) ) ) Docket No. EL18-164-000 ANSWER OF SOUTHERN CALIFORNIA EDISON COMPANY TO ORDER INSTITUTING

More information

STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission

STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission This STANDARD INTERCONNECTION AGREEMENT, (the Agreement ), is entered into this day of, 20 by and between, hereinafter called Customer

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff CAISO TARIFF APPENDIX CC

California Independent System Operator Corporation Fifth Replacement Electronic Tariff CAISO TARIFF APPENDIX CC CAISO TARIFF APPENDIX CC Large Generator Interconnection Agreement for Interconnection Requests in a Queue Cluster Window that are tendered a Large Generator Interconnection Agreement on or after July

More information

Recitals: Whereas, Interconnection Customer is the State of Maryland ( State ) or a local governmental entity of the State of Maryland;

Recitals: Whereas, Interconnection Customer is the State of Maryland ( State ) or a local governmental entity of the State of Maryland; MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW FOR MARYLAND STATE AND LOCAL GOVERNMENT ENTITIES This Agreement

More information

January 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

January 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Regulation James A. Cuillier Director FERC Rates & Regulation January 31, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

BC Hydro Open Access Transmission Tariff Effective: 09 December 2010 OATT Attachment M-1 Appendix 5 Page 1

BC Hydro Open Access Transmission Tariff Effective: 09 December 2010 OATT Attachment M-1 Appendix 5 Page 1 APPENDIX 5 to SGIP BC Hydro OATT Attachment M-1 Appendix 5 Page 1 Standard Generator Interconnection Agreement (SGIA) Project Name Table of Contents BC Hydro OATT Attachment M-1 Appendix 5 Page 2 Article

More information

MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT

MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT APPENDIX A (insert date) MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT This Interconnection Agreement ( Agreement ) is

More information

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019)

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

ATTACHMENT AM METER AGENT SERVICES AGREEMENT FOR SPP MARKET BETWEEN CITY OF INDEPENDENCE, MISSOURI (MARKET PARTICIPANT) AND

ATTACHMENT AM METER AGENT SERVICES AGREEMENT FOR SPP MARKET BETWEEN CITY OF INDEPENDENCE, MISSOURI (MARKET PARTICIPANT) AND ATTACHMENT AM METER AGENT SERVICES AGREEMENT FOR SPP MARKET BETWEEN CITY OF INDEPENDENCE, MISSOURI (MARKET PARTICIPANT) AND WESTAR ENERGY, INC. (METER AGENT) OCTOBER 1, 2009 This Agreement made and entered

More information

Town of Highlands Board Approved as of May 17, 2012

Town of Highlands Board Approved as of May 17, 2012 TOWN OF HIGHLANDS INTERCONNECTION AGREEMENT FOR SMALL PHOTOVOLTAIC GENERATION FACILITY OF 10 kw OR LESS This PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR SMALL GENERATION 10 kw or less (the Agreement ),

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION EDF Trading North America, LLC, on behalf of AES Alamitos, LLC AES Huntington Beach, LLC and AES Redondo Beach, LLC Docket No. ER19-458-000

More information

February 29, Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter Agent Services Agreement

February 29, Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter Agent Services Agreement February 29, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 RE: Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter

More information

Reliability Must Run (RMR) and Capacity Procurement Mechanism (CPM) Enhancements

Reliability Must Run (RMR) and Capacity Procurement Mechanism (CPM) Enhancements Reliability Must Run (RMR) and Capacity Procurement Mechanism (CPM) Enhancements Submitted by Company Date Submitted Matt Lecar 415-973-7743 melj@pge.com Pacific Gas and Electric Company January 9, 2019

More information

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT [This contract has been approved by the California Public Utilities Commission in Decision 13-05-034. Modification of the terms and conditions of this contract will result in the need to obtain additional

More information

Revision to Electric Reliability Organization Definition of Bulk Electric System

Revision to Electric Reliability Organization Definition of Bulk Electric System UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Revision to Electric Reliability Organization Definition of Bulk Electric System ) ) ) ) ) Docket No. RM09-18-000 COMMENTS OF SOUTHERN

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Fernando E. Cornejo fernando.cornejo@sce.com Southern California Edison June 8, 2018 Please use this template to provide your written comments

More information

Regulation Director FERC Rates & Regulation. January 27, 2012

Regulation Director FERC Rates & Regulation. January 27, 2012 Regulation Director FERC Rates & Regulation January 27, 2012 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to

More information

Exhibit SCE-1

Exhibit SCE-1 Exhibit SCE-1 Exhibit SCE-2 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Southern California Edison Company ) Dkt. No. ER18- -000 ) DECLARATION OF BERTON J. HANSEN FOR

More information

CORE GAS AGGREGATION SERVICE AGREEMENT

CORE GAS AGGREGATION SERVICE AGREEMENT Distribution: PG&E Program Administrator (original) CTA PG&E Gas Contract Administrator PG&E Credit Manager For PG&E Use Only CTA Group No.: Billing Account No.: Date Received: Effective Service Date:

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation Docket No. ER14-1386- REQUEST FOR REHEARING OR, IN THE ALTERNATIVE, MOTION FOR

More information

STANDARD AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES WITH A CAPACITY LESS THAN OR EQUAL TO 10 MW

STANDARD AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES WITH A CAPACITY LESS THAN OR EQUAL TO 10 MW STANDARD AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES WITH A CAPACITY LESS THAN OR EQUAL TO 10 MW This Agreement is made and entered into this day of, by and between, a organized

More information

132 FERC 61,067 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

132 FERC 61,067 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 132 FERC 61,067 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. California

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION American Electric Power Service Corporation, ) Complainant ) v. ) Docket No. EL19-18-000 PJM Interconnection, L.L.C., ) Respondent

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E For Applying the Market Index Formula And As-Available Capacity Prices Adopted

More information

August 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

August 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Regulation Karen Koyano Principal Manager FERC Rates & Compliance August 25, 2017 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW This Agreement is made and entered into this day of, by

More information

Net Metering Program Capacity Allocation Procedures

Net Metering Program Capacity Allocation Procedures Net Metering Program Capacity Allocation Procedures The following required procedures for net metering capacity allocation (hereinafter, allocation ) shall apply to all projects with an existing allocation

More information

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, Tony Clark, Norman C. Bay, and Colette D. Honorable.

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Jaime Rose Gannon jrg@cpuc.ca.gov 415-846-4365 California Public Utilities Commission 3/11/2019 Please use this template to provide your

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION AES Huntington Beach, LLC ) Docket No. ER13-351-000 ANSWER OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION TO MOTION TO

More information

106 FERC 61,263 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

106 FERC 61,263 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 106 FERC 61,263 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell, and Joseph T. Kelliher. San Diego Gas & Electric Company

More information

151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION U.S. Department of Energy, Portsmouth/Paducah Project Office Docket No. RC08-5- REQUEST FOR REHEARING AND CLARIFICATION OF THE NORTH

More information

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 March 7, 2012 Re: California Independent

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) PJM Interconnection, L.L.C. ) Docket No. ER )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) PJM Interconnection, L.L.C. ) Docket No. ER ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) Docket No. ER19-24-000 ) ANSWER OF PJM INTERCONNECTION, L.L.C. TO PROTEST AND COMMENTS ( PJM ), pursuant to Rule 213 of the

More information

WATER TRANSMISSION GRID STUDY

WATER TRANSMISSION GRID STUDY WATER TRANSMISSION GRID STUDY REQUEST FOR PROPOSALS NORTH GEORGIA WATER RESOURCES PARTNERSHIP C/O NORTHWEST GEORGIA REGIONAL COMMISSION P.O. BOX 1798 1 JACKSON HILL DRIVE ROME, GEORGIA 30162-1798 April

More information

Solar Generator Interconnection Agreement

Solar Generator Interconnection Agreement Solar Generator Interconnection Agreement THIS AGREEMENT is made and entered into as of the last date of signature provided below, by and between Fort Collins Utilities ( FCU ) and ( Generator ), an electric

More information

December 10, Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter Agent Services Agreement

December 10, Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter Agent Services Agreement The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 December 10, 2014 RE: Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter

More information

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex Southern Companies Attachment J (LGIP), Page 1 ATTACHMENT J STANDARD LARGE GENERATOR INTERCONNECTION PROCEDURES (LGIP) including STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) Southern Companies

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Meridian Energy USA, Inc. ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Meridian Energy USA, Inc. ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Meridian Energy USA, Inc. ) Docket No. ER13-1333-000 MOTION TO INTERVENE AND PROTEST OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

150 FERC 61,056 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

150 FERC 61,056 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 150 FERC 61,056 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, Tony Clark, Norman C. Bay, and Colette D. Honorable.

More information

Tampa Electric Company FERC Electric Tariff First Revised Service Agreement No. 5

Tampa Electric Company FERC Electric Tariff First Revised Service Agreement No. 5 Tampa Electric Company TAMPA ELECTRIC COMPANY AGREEMENT FOR PARTIAL REQUIREMENTS ELECTRIC SERVICE FOR RESALE TO FLORIDA POWER CORPORATION UNDER RATE SCHEDULE AR-1WHOLESALE REQUIREMENTS TARIFF Tampa Electric

More information

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS

APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS APPENDIX IX ATTACHMENT 1 FORMULA RATE PROTOCOLS 1. INTRODUCTION SCE shall calculate its Base Transmission Revenue Requirement ( Base TRR ), as defined in Section 3.6 of the main definitions section of

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Participating Transmission Owners ) Docket Nos. RT04-2-000 Administrative Committee ) ER09-1532-000 ) MOTION FOR LEAVE TO INTERVENE

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C ) Docket Nos. ER17-211-000 Mid-Atlantic Interstate Transmission, LLC ) ER17-214-000 and ) ER17-216-000

More information

DRAFT - April 7, 2008

DRAFT - April 7, 2008 DRAFT - April 7, 2008 Sample 403(b) Information Sharing Agreement Background Information THIS SAMPLE INFORMATION SHARING AGREEMENT ( ISA ) HAS NOT BEEN REVIEWED, APPROVED, OR AUTHORIZED BY THE TREASURY

More information

The Cincinnati Gas & Electric Company Certified Supplier Service Agreement

The Cincinnati Gas & Electric Company Certified Supplier Service Agreement The Cincinnati Gas & Electric Company Certified Supplier Service Agreement This CERTIFIED SUPPLIER SERVICE AGREEMENT (Agreement) dated as of, 200 is between and among Cinergy Services, Inc. on behalf of

More information

CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY

CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY Otter Tail Power Company Original Sheet No. 1 CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY Otter Tail Power Company Substitute Original Sheet No. 2 Superseding Original Volume No.

More information

FERC Order 1000 Compliance Initiative. Straw Proposal (regional requirements), posted May 22, 2012

FERC Order 1000 Compliance Initiative. Straw Proposal (regional requirements), posted May 22, 2012 Stakeholder Comments Template FERC Order 1000 Compliance Initiative Straw Proposal (regional requirements), posted May 22, 2012 Please submit comments (in MS Word) to fo1k@caiso.com no later than the close

More information

KOSCIUSKO REMC AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION

KOSCIUSKO REMC AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION KOSCIUSKO REMC AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION This Interconnection Agreement ( Agreement ) is made and entered into this day of, 20, by Kosciusko Rural Electric Membership Corporation,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-1169-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

Now, therefore, in consideration of and subject to the mutual covenants contained herein, the Parties agree as follows:

Now, therefore, in consideration of and subject to the mutual covenants contained herein, the Parties agree as follows: Interconnection Agreement for Small Generator Facility Tier 1, Tier 2, Tier 3 or Tier 4 Interconnection (Small Generator Facilities with Electric Nameplate Capacities or 10 MW or smaller) Form 8 This Interconnection

More information

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Straw Proposal

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Straw Proposal Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements June 20, 2017 Market & Infrastructure Policy Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3.

More information

STANDARD LIGHTING CONTRACT (CUSTOMER OWNED) FORM 559

STANDARD LIGHTING CONTRACT (CUSTOMER OWNED) FORM 559 STANDARD LIGHTING CONTRACT (CUSTOMER OWNED) FORM 559 Contract Number: Notification Number: Part I Effective date of agreement: Company: CONSUMERS ENERGY COMPANY A Michigan Corporation ONE ENERGY PLAZA

More information

Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP)

Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP) Application Nos.: Exhibit No.: Witnesses James A. Cuillier Gary L. Allen (U -E) Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP) Cost Recovery And Renewable

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER19-385-000 Operator Corporation ) COMMENTS OF THE DEPARTMENT OF MARKET MONITORING FOR

More information

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 20 kw

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 20 kw MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 20 kw This Maryland Standard Agreement For Interconnection Of Small Generator Facilities With

More information

AUTOMATIC ROLLOVER SERVICES AGREEMENT

AUTOMATIC ROLLOVER SERVICES AGREEMENT 2001 Spring Road, Suite 700 Oak Brook, IL. 60523 630.368.5614 Telephone 630.368.5699 Fax www.mtrustcompany.com AUTOMATIC ROLLOVER SERVICES AGREEMENT This Automatic Rollover Services Agreement ( Agreement

More information

Standard Tariff for Electricity Purchases From And Sales to Qualifying Facilities. Applicant: Dated 20

Standard Tariff for Electricity Purchases From And Sales to Qualifying Facilities. Applicant: Dated 20 Applicant: Dated 20 Form of Standard Contract Standard Interconnection Agreement For Qualifying Facilities with a design Capacity of 25 Kilowatts or Less Preamble This Agreement is made as of the day of,

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION GenOn Energy Management. LLC ) Docket No. ER19-554-000 NRG California South LP ) MOTION TO INTERVENE AND COMMENTS OF THE DEPARTMENT

More information

FEDERAL RESOURCES SUPPLY COMPANY GENERAL TERMS AND CONDITIONS FOR THE PROVISION OF SERVICES

FEDERAL RESOURCES SUPPLY COMPANY GENERAL TERMS AND CONDITIONS FOR THE PROVISION OF SERVICES 1. Applicability. FEDERAL RESOURCES SUPPLY COMPANY GENERAL TERMS AND CONDITIONS FOR THE PROVISION OF SERVICES These terms and conditions for services (these Terms ) are the only terms and conditions which

More information

144 FERC 61,159 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C August 28, 2013

144 FERC 61,159 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C August 28, 2013 144 FERC 61,159 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426 August 28, 2013 In Reply Refer To: Kinetica Energy Express, LLC Docket No. RP13-1116-000 Crowell & Morning Attention: Jenifer

More information

160 FERC 61,007 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

160 FERC 61,007 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 160 FERC 61,007 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. California Independent System Operator

More information

STANDARD LIGHTING CONTRACT (COMPANY OWNED) FORM 548

STANDARD LIGHTING CONTRACT (COMPANY OWNED) FORM 548 Page 1 of 5 STANDARD LIGHTING CONTRACT (COMPANY OWNED) FORM 548 Contract Number: Notification Number: Part I Effective date of agreement: Company: CONSUMERS ENERGY COMPANY A Michigan Corporation ONE ENERGY

More information

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Southern California Edison Company FERC Electric Tariff, Second Revised Volume No. 6 Title Page SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Issued on: December 23, 2002 Effective: January

More information

RE: Revision to Southern California Edison Company s Formula Transmission Rate Annual Update in Docket No. ER (Amended TO8)

RE: Revision to Southern California Edison Company s Formula Transmission Rate Annual Update in Docket No. ER (Amended TO8) Regulation James A. Cuillier Director FERC Rates & Regulation Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Revision to Southern California Edison Company s Formula Transmission

More information

Business Associate Agreement RECITALS AGREEMENT

Business Associate Agreement RECITALS AGREEMENT Business Associate Agreement Read the Business Associate Agreement and sign electronically or download, print, and sign. Completed form may be uploaded to Provider Portal, faxed to Janssen CarePath at

More information

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C August 1, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 700 Louisiana Street, Suite 700 Houston, Texas 77002-2700 John A. Roscher

More information

Storage as a Transmission Asset Stakeholder Comment Template

Storage as a Transmission Asset Stakeholder Comment Template Storage as a Transmission Asset Stakeholder Comment Template Submitted by Company Date Submitted David Kates The Nevada Hydro Company, Inc. (707) 570-1866 david@leapshydro.com The Nevada Hydro Company,

More information

January 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. January 31, 2014 Great Lakes Gas Transmission Company 717 Texas Street, Suite 2400 Houston, TX 77002-2761 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

Website Terms of Use Agreement

Website Terms of Use Agreement Website Terms of Use Agreement This Terms of Use Agreement is a binding contract between you and Pluscios Management LLC ( Pluscios ). It governs your use of this website and all products, services, content,

More information