Contractor s Legal Guidance Note
|
|
- Crystal Cole
- 6 years ago
- Views:
Transcription
1 Contractor s Legal Guidance Note Spring Edition 2010 Express Acceleration This Spring edition of the Contractor s Legal Guidance Bulletin picks up where the Autumn 2009 edition left off, by moving on from a basic explanation of the concept of acceleration to an examination of both legal and practical issues that may arise in connection with this phenomenon. The Autumn 2009 edition assumed the perspective of the contractor who is directly contracting with the developer. This Spring edition retains that perspective and considers two more usual forms of 'express' (otherwise known as 'directed') acceleration: first, the performance of the same work within an intentionally shorter period, and second, the performance of increased or delayed work within the same period.
2 A framework for project management This edition begins by setting out a set of general criteria, in the form of a textual algorithm (see below), as a working framework by which decisions on the alternative courses of action to be taken where there is a direction to take accelerative measures. Given, in reality, the wide variety of forms which contractual provisions will take, and the wide variety of factual circumstances out of which contractual provisions will arise, these suggestions cannot be regarded as universally applicable. But it is hoped that they will commend a particular line of inquiry in response to a request to accelerate. In short, as ever, the content of this note is no substitute for specific legal advice of an experienced practicing lawyer specialising in this field. Rather, it is a general starting position for a reasoned consideration of the underlying legal issues. 2
3 Express power to accelerate? According to the above framework, the first question arising for consideration is whether or not there is an express provision in the contract for acceleration; and if so, whether it has been properly invoked in the particular case. If there is neither then in the face of a request to accelerate the Contractor may wish to consider entering into a discussion with the developer with a view to negotiating acceptable terms for acceleration. Whether or not the Contractor is willing to entertain the (non-binding) request for acceleration, he may wish to inform the developer of his view as to the non-binding nature of the request. This response may take the form of a formal challenge or it may simply be communicated in the course of the negotiations, or by other informal means. Contractor responsible for underlying delay? If an express power to require acceleration has been exercised then the following question arises: whether or not the contractor is delayed by events or circumstances for which the contractor is legally responsible. This may not be the case at all. There may be no critical delay but the developer may simply wish the same scope of works to be completed within a shorter period. This is what we have defined as the first type of acceleration. Alternatively, the developer may wish to reduce the scope of works and may request that the reduced scope of works be completed within a commensurately reduced period. Strictly speaking, this later case does not really involve acceleration, although it will require a revised programme, and it may occasion additional cost for the contractor. In either case, almost invariably, the contractor will be entitled to compensation of some sort, and the contractor will often be strictly obliged to notify and to promote this entitlement early if it is to be sustained. At the same time, the acceleration clause will require appropriate accelerative measures to be devised and executed. Occasionally, the developer may be entitled to require uncompensated acceleration. These circumstances might involve a manifestation of the second type of acceleration: where the contractor finds himself in a position where the works are in delay and the contractor cannot persuade the developer that this is due to matters for which the developer retains legal responsibility in other words, that the delay is excusable. In this case, as alluded to above, the contractor may be confronted by an acute dilemma, namely: whether or not to accelerate? In this situation, the key questions appear to be this: Does the risk of liability for delay arising from a refusal to accelerate and a failure to obtain an EOT outweigh the inevitable costs occasioned by the accelerative measures? Will those measures be wholly successful in extinguishing the delay? If the advantages of acceleration outweigh the disadvantages then, all other things being equal, the appropriate course will be to devise and execute suitable accelerative 3
4 measures. And the converse applies: if the costs of acceleration outweigh the likely liability for delay then the rational course may be to challenge the request. Default curing under the FIDIC Books If actual progress is too slow to complete within the Time for Completion, and/or progress has fallen (or will fall) behind the current programme, other than as a result of excusable delay, then the Engineer may instruct the Contractor to submit a revised programme and supporting report describing the revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for Completion. Unless the Engineer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in the working hours and/or in the numbers of Contractor s Personnel and/or Goods, at the risk and cost of the Contractor. If these revised methods cause the Employer to incur additional costs, the Contractor shall, subject to Sub-Clause 2.5 [Employer s Claims], pay these costs to the Employer, in addition to delay damages (if any) under Sub-Clause 8.7. Thus, generally speaking, the Contractor must bear the risk and cost of accelerative measures that are necessary to overcome actual or anticipated delay to Completion. Sub-Clause 8.6 [Rate of Progress] does not alter that principle. What it does do is provide a basis and mechanism for the Employer to recover for additional costs incurred by the Employer where, absent Sub-Clause 8.6, no such legal right may exist. In this regard, one should keep in mind that a Contractor whose progress is too slow to complete within the Time for Completion may or may not be in breach of contract. This will depend on a number of factors, including the existence of any interim obligations (eg, sectional completion), other requirements set out in the Particular Conditions, and the seriousness of the programme slippage. Pre-emptive acceleration Under the FIDIC Conditions of Contract there is scope for a shrewd Contractor to avoid responsibility for additional costs incurred by the Employer. If the Contractor decides, himself, to submit a revised programme in order to comply with his primary obligation to complete the Works within the Time for Completion then he may head off any instruction under Sub- Clause 8.6. By doing so, the Contractor will not necessarily attract a liability for these costs by other means, since all he is doing is discharging the obligation under Sub-Clause 8.3 to submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor's obligations. Sub-Clause 8.3 does not contain an indemnity provision akin to that contained in Sub-Clause 8.6. Furthermore, any instruction to undertake accelerative measures that differ from those encompassed in the voluntary revised programme may constitute a Variation for which a right to an increase in the Contract Price arises. 4
5 Conclusion Responsibility for the financial consequences of acceleration is ultimately a legal question, albeit that it is often dependant on technical issues concerned with the existence, factual causes of and consequences of underlying delay to the progress of the works. The existence, nature and applicability of the developer's power to require acceleration on the part of his contractor is fundamental to any determination of the legal consequences of the putative exercise of such a power. Other considerations and issues (as highlighted in this note) are also worthy of careful attention, all in the context of the governing law of the contract, and common sense. A robust entitlement to recover compensation for express acceleration can only benefit from a suitably vigorous and well-timed legal evaluation of the legal merits of the situation and advice on the optimal strategic options. Too often the lawyer is called to the scene only after the contractor has staked his credibility on a particular characterization of his right to be compensated for accelerative measures, in circumstance where prior professional legal advice might have identified other, better strategies. This bulletin does not constitute legal advice. Specific legal advice should be taken before acting on any of the topics covered Pinsent Masons
Session 3 by Zoltán Záhonyi, FIDIC AIT,
Session 3 by Zoltán Záhonyi, FIDIC AIT, zoltan.zahonyi@zandpartners.com Contents of Session 3 Session 3: FIDIC 1999 Red Book Part 2 The Quality Issues (Plant, Materials and Workmanship) The Time is of
More informationDelay Expert practical tips for making delay claims
Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of
More informationSub Contract Agreement
Sub Contract Agreement In a building project there is always a contractor. There need not be any sub-contractors However there will invariably be sub-contractors. There are two types of sub-contractors
More informationWorkshop 4 FIDIC Contracts (Update on New Documents)
Workshop 4 FIDIC Contracts (Update on New Documents) Employer s New Obstacle: Commencement Date and Related Clauses Dr.Sarwono Hardjomuljadi Tuesday, 04 October 2011, 14.00 15.30 Employer s New Obstacle:
More informationAgainst All Odds. TE&A's Special Edition Issue. by Clive Horridge
Against All Odds TE&A's Special Edition Issue by Clive Horridge Against All Odds by Clive Horridge Page 2 of 12 Not just a Phil Collins song-title depicting a common scenario of dispair, it is the case
More informationHeadland Machinery Pty Ltd ( Headland ) Sale and Installation of Parts Terms and Conditions
Headland Machinery Pty Ltd ( Headland ) Sale and Installation of Parts Terms and Conditions These are the terms and conditions upon which Headland (as named in section 1.1(o) below) sell and quote for
More informationAdvanced Business & Contract Law This course can be presented in-house for you on a date of your choosing
Advanced Business & Contract Law This course can be presented in-house for you on a date of your choosing The Banking and Corporate Finance Training Specialist Course Objectives Participants will: Be introduced
More informationCHAPTER 1 25 INTRODUCTION
CHAPTER 1 25 INTRODUCTION 1.1 Introduction Construction project is unique production due to its natural condition, which is produced by the contractor for the owner/client/employer within specified time
More informationin Documents Containing Audited Financial Statements
Issued June 2005 Effective for audits of financial statements for periods beginning on or after 15 December 2004 Hong Kong Standard on Auditing 720 Other Information in Documents Containing Audited Financial
More informationSTANDARD TERMS AND CONDITIONS FOR THE COMMERCIAL HIRE OF GOODS AND EQUIPMENT
STANDARD TERMS AND CONDITIONS FOR THE COMMERCIAL HIRE OF GOODS AND EQUIPMENT These Standard Terms and Conditions together with the Offer to Hire Form, Payment Terms and Special Conditions, the Offer by
More informationCUK Insider s Guide to IR35
The UK's most visited IT Contractor Site - Online since 1998 CUK Insider s Guide to IR35 Compiled with from advice from Ray McMahon, ex Tax Inspector Contents: What is IR35? 2 How will I know if I m caught
More informationNew Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking
New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice
More informationAppendix K Model Letters for Use by the Engineer
175 Model Letters for Use by the Engineer Introduction This Appendix provides model letters for use by the Engineer primarily for formal correspondence with the Contractor. These model letters do not distinguish
More informationHEARING HEARD IN PUBLIC. HOLT, Paul Ruben Registration No: PROFESSIONAL CONDUCT COMMITTEE JUNE 2016 Outcome: Erased with Immediate Suspension
HEARING HEARD IN PUBLIC HOLT, Paul Ruben Registration No: 60781 PROFESSIONAL CONDUCT COMMITTEE JUNE 2016 Outcome: Erased with Immediate Suspension Paul Ruben HOLT, a dentist, United Kingdom; BDS Lond 1985,
More informationREPORT TO THE TRUSTEES OF THE INDUSTRIAL BANK OF JAPAN PENSION SCHEME
REPORT TO THE TRUSTEES OF THE INDUSTRIAL BANK OF JAPAN PENSION SCHEME A Introduction The Principal Employer of the IBJ Scheme, Mizuho Corporate Bank Limited, is also the principal employer of the Fuji
More informationCosmos Projects - Standard Terms and Conditions of Sub-Contract
Cosmos Projects - Standard Terms and Conditions of Sub-Contract These standard terms and conditions shall apply to any Sub Contract between Cosmos Projects Limited ( CPL ) and any Sub-Contractor following
More informationCopyright Mark Roysner, Esq., Roysner & Associates. All rights reserved.
By Mark Roysner, Esq. Law Office of Mark Roysner Legal Consultants to the Meetings & Exhibition Industry 22287 Mulholland Hwy., Ste 382. Calabasas, CA 91302 Tel. 818-224-8095 Fax 818-222-6236 roysner@roysnerlaw.com
More informationConstruction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.
Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project
More informationY2K: Best Practice in the Foreign Exchange Market
October 18, 1999 Y2K: Best Practice in the Foreign Exchange Market The Foreign Exchange Committee (sponsored by, but independent of, the Federal Reserve Bank of New York) (the "FX Committee") is today
More informationConditions of Sale Scania Australia Pty Ltd General Terms (ACN Scania ) 1. General Customer Goods Manufacturer Purchase Price
Conditions of Sale General Terms Scania Australia Pty Ltd (ACN 000 537 000 Scania ) These terms and conditions, as varied from time to time,( The General Terms ) apply to all goods and services sold or
More informationStandard forms of partnering contracts The ultimate contractual commitment? Part 4
Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard
More informationSuspension and Termination
Suspension and Termination Nicholas Gould Partner, Fenwick Elliott LLP Visiting Professor, King s College London Termination Typical contract provisions (dual notices) Suspension The grounds for suspension
More informationTerms and Conditions
Terms and Conditions SERVICES Taking such steps as are reasonable to enable MFA to be satisfied within the limits of the professional skill and care set out in clause 2-1 that the plans and works comply
More informationEmployee Misconduct: A Practical Approach to Conducting Internal Investigations with Criminal and Regulatory Aspects
Employee Misconduct: A Practical Approach to Conducting Internal Investigations with Criminal and Regulatory Aspects An investigation into employee misconduct is invariably a delicate process and one typically
More informationDATED July 2017 ALTUS STRATEGIES PLC AIM COMPLIANCE CODE
DATED July 2017 ALTUS STRATEGIES PLC AIM COMPLIANCE CODE Tel +44 (0)370 903 1000 Fax +44 (0)370 904 1099 mail@gowlingwlg.com www.gowlingwlg.com CONTENTS CLAUSE HEADING PAGE ALTUS STRATEGIES PLC... 1 AIM
More informationSuitability Rule or Reasonable Basis for Advice Rule
Suitability Rule or Reasonable Basis for Advice Rule An Authorised Representative needs to demonstrate that: Sufficient information about the client's needs and circumstances has been gathered, and That
More informationFederal Acquisition Regulations: What Every Surety Professional Should Make Sure Their Clients Know
Federal Acquisition Regulations: What Every Surety Professional Should Make Sure Their Clients Know Surety Association of San Diego April 12, 2011 What are the Federal Acquisition Regulations? The Federal
More informationInterim Award In Multi-Tier Dispute Resolution Clauses
Interim Award In Multi-Tier Dispute Resolution Clauses The Singapore s Court of Appeal has recently ruled on the enforceability of Interim Awards in multi-tier dispute resolution clauses. The Court in
More informationRULES FOR MEMBERSHIP IRISH PAPER CLEARING COMPANY LIMITED
RULES FOR MEMBERSHIP OF IRISH PAPER CLEARING COMPANY LIMITED (As adopted by the Board of Directors and approved by resolution(s) of the Company and current as of 2 nd December 2011) INDEX A. INTRODUCTION
More informationA COMPARISON BETWEEN THE NEC3 AND NEC4 PSC
First Edition January 2018 A COMPARISON BETWEEN THE NEC3 AND NEC4 PSC Author: Natalie Reyneke Employers need professionals to design their works it is the reality of construction contracts. Contractors
More informationCONSTRUCTION CONTRACT
CONSTRUCTION OR: Name Mailing Address City, State, Zip Code Telephone Number Fax Number E-mail address BID ACCEPTANCE DATE: COMPLETION DATE: DATE: TOTAL BID : TABLE OF CONTENTS ARTICLE 1 PARTIES... Page
More informationInsurance Contract Law: Enterprise Act 2016, A new remedy of damages for late payment (and a note on fraud) Rhys Clift, Partner, Hill Dickinson LLP
Insurance Contract Law: Enterprise Act 2016, A new remedy of damages for late payment (and a note on fraud) Rhys Clift, Partner, Hill Dickinson LLP 1 APPLICATION AND IMPLICATIONS? Will the contract you
More informationStatement of Financial Accounting Standards No. 78
Statement of Financial Accounting Standards No. 78 FAS78 Status Page FAS78 Summary Classification of Obligations That Are Callable by the Creditor an amendment of ARB No. 43, Chapter 3A December 1983 Financial
More informationShort Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of
Short Course on Construction Law with particular reference to the JBCC 2000 Series of Contracts in particular the application of JBCC Principal Building Agreements Edition 5 (2007) and Edition 4.1 (2005),
More informationThe New NZS 3910:2013
The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first
More informationTaking your career to a new level Contract / Procurement / Negotiation Specialist - Professional Development Programme
Contract / Procurement / Negotiation Specialist - Professional Development Programme Contract / Procurement/ Negotiation Specialist - Professional development programme The programme in summary What is
More informationBIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017
BIDP Standard FORMS & JBCC Minor WORKS Commentary ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW 01160007 04 th NOVEMBER 2017 Types of Contract Fixed Price Contracts For Specified work for a sum not adjustable
More informationSoftware and Software Tools Ownership and Use Contracting Considerations When Creating Digital, Online and Mobile Content
Software and Software Tools Ownership and Use Contracting Considerations When Creating Digital, Online and Mobile Content By Candice Kersh Partner at Frankfurt Kurnit Klein & Selz Introduction Technology
More informationNEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.
Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and
More informationResponse to Department of Health Consultation Introducing Fixed Recoverable Costs in Lower Value Clinical Negligence claims.
Response to Department of Health Consultation Introducing Fixed Recoverable Costs in Lower Value Clinical Negligence claims May 2017 Introduction The Council is concerned that the proposals may impede
More informationDOUKPSC04 Rev Feb 2013
DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby
More informationIChemE publishes new Silver Book professional services contract to complete its set of standard forms
IChemE publishes new Silver Book professional services contract to complete its set of standard forms IChemE Silver Book The Institution of Chemical Engineers (IChemE) has recently published a new form
More informationChristophe Guibert de Bruet
Time Bars under the FIDIC Conditions of Contract Lausanne, 25 October 2013 Christophe Guibert de Bruet OVERVIEW I. Contractor s Claims: Sub-Cl. 20.1 II. III. IV. Time-Bar Limitation Overview Time-Bar Limitation:
More informationContractor and subcontractor insolvency January 2010
Contractor and subcontractor insolvency January 2010 1 Early warning signs: what sort of behaviour or warning signs might indicate a contractor beginning to get into trouble? 1.1 The contractor's employees
More informationABF Anti-Bribery Policy
ABF Anti-Bribery Policy Introduction Associated British Foods plc (ABF) is committed to acting professionally, fairly and with integrity in all its business dealings. As part of its commitment to ethical
More informationReviewable contracts A contradiction with consumer implications? Adrian Pinnington
Healthcare Conference 5-7 October 2003 Reviewable contracts A contradiction with consumer implications? Adrian Pinnington Firstly I would like to point out that I am here today to play a role to role-play
More informationMDB Harmonised Particular Conditions
FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st
More informationDECISION OF THE TRIBUNAL
BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL [2014] NZREADT 48 READT 006/14 IN THE MATTER OF BETWEEN an appeal under s.111 of the Real Estate Agents Act 2008 BARFOOT & THOMPSON LTD Appellant AND
More informationConditions of Contract for PLANT and Design-Build
Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE
More informationCONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk
More informationVIRIDOR WASTE MANAGEMENT LIMITED TERMS AND CONDITIONS OF TRADE
VIRIDOR WASTE MANAGEMENT LIMITED TERMS AND CONDITIONS OF TRADE The Supplier will collect/accept Waste for disposal and will supply/deliver quarried or other material subject to the conditions set out below:
More informationWestpac Protected Equity Loan. Notice to investors
12 November 2016 Westpac Protected Equity Loan Notice to investors The purpose of this notice is to provide updated information to investors in Westpac Protected Equity Loan ( Westpac PEL ) issued by Westpac
More informationAttachment A GENERAL TERMS AND CONDITIONS
Attachment A GENERAL TERMS AND CONDITIONS DEFINITIONS -- As used throughout this contract, the following terms shall have the meaning set forth below: A. "Commission" shall mean the Washington State Parks
More informationDate of Decision: 31 October 2014 DECISION
ACCIDENT COMPENSATION APPEAL AUTHORITY NEW ZEALAND [2014] NZACA 18 ACA 9/14 (formerly ACA 9/13) Gary Richard Baigent Applicant ACCIDENT COMPENSATION CORPORATION Respondent Before: D J Plunkett Counsel
More informationencouragement to move on with optimisms. Opening Session : Employer (Respondent)
359 can summarise it as the establishment of common facts, grounds, understandings, and so on, emitting the scent of constructiveness, progress and agreeability of the parties as encouragement to move
More informationFacility Agreement Continuing Credit Facility - Line of Credit Terms & Conditions
Facility Agreement Continuing Credit Facility - Line of Credit Terms & Conditions Version 2, March 2013 Contents Section 1 Section 2 LINE OF CREDIT....1 DRAWDOWNS... 1 Section 3 REPAYMENTS........1 Section
More informationSRI LANKA AUDITING STANDARD 720 OTHER INFORMATION IN DOCUMENTS CONTAINING AUDITED FINANCIAL STATEMENTS CONTENTS
SRI LANKA AUDITING STANDARD 720 OTHER INFORMATION IN DOCUMENTS CONTAINING (Effective for all the audits carried out on or after..) CONTENTS Paragraph Introduction 1-8 Access to Other Information 9 Consideration
More informationTerms of Business. For United Kingdom independent financial advisers in respect of Legg Mason Funds ICVC
Terms of Business For United Kingdom independent financial advisers in respect of Legg Mason Funds ICVC June 2016 Terms of Business These Terms of Business set out the basis upon which the Company will
More information2018 FABULOUS PHOENIX 4 TH FOOD VENDOR REGULATIONS
2018 FABULOUS PHOENIX 4 TH FOOD VENDOR REGULATIONS Food sales are limited to those items listed on your application and approved by the Food Vendor Coordinator. Vendors may not subcontract space or allow
More informationSTEP STANDARD PROVISIONS: COMMENTARY BY JAMES KESSLER, Barrister (This commentary does not form part of the Standard Provisions)
STEP STANDARD PROVISIONS: COMMENTARY BY JAMES KESSLER, Barrister (This commentary does not form part of the Standard Provisions) INTRODUCTION TO THE STANDARD PROVISIONS Any properly drafted will or settlement
More informationFIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management
FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract
More informationA Trustee s top three part three
BERMUDA BRITISH VIRGIN ISLANDS CAYMAN ISLANDS CYPRUS DUBAI HONG KONG LONDON MAURITIUS MOSCOW SÃO PAULO SINGAPORE conyersdill.com June 2011 A Trustee s top three part three In the first two parts of this
More informationPeninsula Business Services Ltd v Donaldson [2016] UKEAT 0249_15_0903. Case Summary
Peninsula Business Services Ltd v Donaldson [2016] UKEAT 0249_15_0903 Case Summary The EAT has ruled that there is no obligation upon an employer to provide childcare vouchers that are ordinarily provided
More informationForeign business partners under the FCPA
W O R L D - C H E C K W H I T E P A P E R Foreign business partners under the FCPA by Tom Fox Statement of intent The FCPA risk of engaging a Foreign Business Partner overseas is an increasing concern
More informationCOURT-FREE CATASTROPHIC CLAIMS BILL BRAITHWAITE QC
COURT-FREE CATASTROPHIC CLAIMS BY BILL BRAITHWAITE QC PERSONAL INJURY LAWYER OF THE YEAR 2010 AND 2012 UKABIF INNOVATOR OF THE YEAR 2010 NEUTRAL FACILITATION the parties to agree at the outset or during
More informationDemand Curve Definitions
Demand Curve Definitions Presented by Andrew P. Hartshorn Market Structures Working Group Albany, NY August 27, 2003 Capacity $10,000 Capacity Price Energy+Reserves Energy Quantity 1 WHY A DEMAND CURVE?
More information(2) ( The Contractor ) Communication Professional. to provide support as a Communication Professional as per our booking confirmation.
CONTRACT FOR SERVICES This is an agreement between: (1) ( The Principal ) terptree ltd (2) ( The Contractor ) Communication Professional to provide support as a Communication Professional as per our booking
More informationTen Plus Pointers for Drafting Procurement Documents
TENDERING LAW 2014 UPDATE PAPER 2.2 Ten Plus Pointers for Drafting Procurement Documents These materials were prepared by David W. Little of Fasken Martineau DuMoulin LLP, Vancouver, BC, for the Continuing
More informationWorking Group on Review of Investment Trust and Investment Corporation Regulation. Final Report
PROVISIONAL TRANSLATION December 7, 2012 Working Group on Review of Investment Trust and Investment Corporation Regulation Final Report 1. Introduction (1) Historical background The Act on Investment Trusts
More informationStandard Form Project Agreement (hub DBFM Projects)
Standard Form Project Agreement (hub DBFM Projects) Version 2: June 20122.1: October 2013 . THIS STANDARD FORM PROJECT AGREEMENT MUST BE USED IN CONJUNCTION WITH THE STANDARD PROJECT AGREEMENTS USER S
More informationUnderstanding Your Safety Responsibilities
Understanding Your Safety Responsibilities Cameron Dean Partner McCullough Robertson Lawyers Background The enforcement of safety and health obligations in the Queensland mining industry by way of prosecutions
More informationHEARING HEARD IN PUBLIC
HEARING HEARD IN PUBLIC PEZESHKI, Peyman Registration No: 83524 PROFESSIONAL CONDUCT COMMITTEE FEBRUARY - MAY 2017 Most recent outcome: Suspension extended for 12 months (with a review) ** ** See page
More informationPOLICY BRIEFING The Private Finance Initiative: Treasury Select Committee report
The Private Finance Initiative: Treasury Select Committee report Date: 23 August 2011 Author: Janet Sillett Overview In a statement accompanying the publication of the Treasury Select Committee's report
More informationFIDIC WORKSHOP 2016 GROUP 6
FIDIC WORKSHOP 2016 GROUP 6 QUESTION 1 WHAT ARE THE ESSENTIAL REQUIREMENTS FOR FORMATION OF CONTRACT? DISCUSS WHETHER A BINDING AND ENFORCEABLE CONTRACT HAS BEEN CONCLUDED BETWEEN JOLLY AND CAN-DO. 1.
More informationSUBCONTRACTOR TERMS AND CONDITIONS
SUBCONTRACTOR TERMS AND CONDITIONS ARTICLE 1.0 GENERAL OBLIGATIONS The Prime Contract, including all general conditions; appendices; special and supplemental conditions or provisions; drawings or plans;
More informationWhy is Credit Management important?
Why is Credit Management important? Cash flow is crucial for the survival and success of any business. It is generally accepted that cash flow is the single most pressing concern of most small and medium-sized
More informationPolicy on Gifts & Hospitality & Payments & Benefits
Policy on Gifts & Hospitality & Payments & Benefits Classification: NOT PROTECTIVELY MARKED 1. PURPOSE OF POLICY 1.1 If employees, board/committee members, involved residents (ie members of the Customer
More informationConstruction Law Update: Spotlight on the NEC3 Engineering and Construction Contract
London Bristol Dublin Dubai Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract Tom Pemberton, Partner James Vernon, Associate 12 April 2016 Introductions Tom Pemberton
More informationIN THE EMPLOYMENT COURT AUCKLAND [2013] NZEmpC 15 ARC 84/12. VULCAN STEEL LIMITED Plaintiff. KIREAN WONNOCOTT Defendant
IN THE EMPLOYMENT COURT AUCKLAND [2013] NZEmpC 15 ARC 84/12 IN THE MATTER OF a challenge to a determination of the Employment Relations Authority BETWEEN AND VULCAN STEEL LIMITED Plaintiff KIREAN WONNOCOTT
More informationEXHIBIT A SCOPE OF WORK AND RELATED INFORMATION PORTABLE FIRE EXTINGUSHER SERVICES
EXHIBIT A SCOPE OF WORK AND RELATED INFORMATION PORTABLE FIRE EXTINGUSHER SERVICES 1. All prospective Contractors must; be State of Connecticut licensed for this work; demonstrate a minimum of 5 years
More informationMODEL DEED OF GUARANTEE AND INDEMNITY (2003 Edition)
MODEL DEED OF GUARANTEE AND INDEMNITY (2003 Edition) The Steering Committee has updated and revised the Model Deed of Guarantee and Indemnity launched in 2001. The updated version is referred to as the
More informationSPECIAL RESOLUTION REGIME: SAFEGUARDS FOR PARTIAL PROPERTY TRANSFERS
SPECIAL RESOLUTION REGIME: SAFEGUARDS FOR PARTIAL PROPERTY TRANSFERS BBA Response to the HM Treasury Consultation Document 1. The British Bankers Association (BBA) welcomes the opportunity to comment on
More informationThe Indemnity Dilemma
The Indemnity Dilemma September 1989 Written By: Mark C. Friedlander t 312.258.5546 mfriedlander@schiffhardin.com SCHIFF HARDIN LLP 6600 Sears Tower Chicago, Illinois 60606 t 312.258.5500 f 312.258.5600
More informationCASEN 2011, ECLAC clarifications Background on the National Socioeconomic Survey (CASEN) 2011
CASEN 2011, ECLAC clarifications 1 1. Background on the National Socioeconomic Survey (CASEN) 2011 The National Socioeconomic Survey (CASEN), is carried out in order to accomplish the following objectives:
More informationBoard Protocols Related Party Transactions
Board Protocols Related Party Transactions 3P Learning Limited 16 December 2014 Board Protocols Contents 1 Purpose 1 2 2 3 Related Party Transaction Protocols 3 King & Wood Mallesons i 1 Purpose 1.1 In-line
More informationICT SERVICES AGREEMENT SCHEDULES SCHEDULE 9.1 STAFF TRANSFER
ICT SERVICES AGREEMENT SCHEDULES SCHEDULE 9.1 STAFF TRANSFER CONTENTS Section A: Section B: Section C: Product Description Guidance Pro-forma/Example Schedule ICT_schedule9.1_v2.1 1 Section A Product Description
More informationOPINION NO. 44. (Issued: November 1995) LIMITATIONS ON ACCEPTING GIFTS UNDER THE CODE OF JUDICIAL ETHICS AND CCP 170.9
OPINION NO. 44 (Issued: November 1995) LIMITATIONS ON ACCEPTING GIFTS UNDER THE CODE OF JUDICIAL ETHICS AND CCP 170.9 I. Introduction Last year the CJA Ethics Committee issued its Formal Opinion 43; that
More informationConsumer lending. terms and conditions
Consumer lending terms and conditions 1 Important information Who we are Teachers Mutual Bank Limited ABN 30 087 650 459 AFSL/Australian Credit Licence 238981. In this document, the Bank, we, us and our
More informationTerms and conditions of sale of material
C1 DEFINITIONS In the Agreement, except where the context otherwise requires: Agreement means an agreement made in accordance with C3. Acceptance (of Order) means Western Power s written acceptance of
More informationConstitution. Southern Cross Media Group Limited (formerly known as Macquarie Media Holdings Limited) (ACN ) A Company limited by Shares
Southern Cross Media Group Limited (formerly known as Macquarie Media Holdings Limited) (ACN 116 024 536) A Company limited by Shares As amended on Allens Arthur Robinson The Chifley Tower 2 Chifley Square
More informationFOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
Cça -I II FEDERATION INTERNATIONALE DES INGENIEURS-CONSFILS INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS INTERNATIONALE VEREINIGUNG BERATENI)ER INGENIEIJRE FEDERACION INTERNACIONAL DE INGENIEROS CONSULTORES
More informationThe Code of Ethics for Arbitrators in Commercial Disputes Effective March 1, 2004
The Code of Ethics for Arbitrators in Commercial Disputes Effective March 1, 2004 The Code of Ethics for Arbitrators in Commercial Disputes was originally prepared in 1977 by a joint committee consisting
More informationFinancing in Ukraine. Key issues. Regulatory requirements. NBU registration. 1 Financing in Ukraine. Briefing note September 2016.
1 Financing in Ukraine Briefing note September 2016 Financing in Ukraine July 2015 Whether lending directly to a Ukrainian borrower, or relying on guarantees or security from a Ukrainian obligor, there
More informationBRODIES BREXIT GUIDE. FINANCIAL SERVICES AND BREXIT
BRODIES BREXIT GUIDE. FINANCIAL SERVICES AND BREXIT What might Brexit mean for financial services? On 29 March 2017 the UK s Article 50 Notice was delivered to the European Council in Brussels, triggering
More informationFinancial Services Guide
Financial Services Guide This guide is designed to assist you in deciding whether to use the services offered by us. It contains important information about: the services we can offer you how we and our
More informationDerivatives Update. Enron Australia v TXU Electricity. Contents. May 2004
Derivatives Update Enron Australia v TXU Electricity May 2004 Contents 2. Overview Enron v TXU : the facts Position under English law 3. Moral hazard - a new low Credit/systemic risk - a new high What
More informationA review of recent developments and trends in FCA Enforcement
BANKING AND FINANCIAL SERVICES LITIGATION GROUP WEBCAST SERIES 2017 A review of recent developments and trends in FCA Enforcement Alex Irvine, associate In July 2017, the FCA published its Enforcement
More informationEurope s Emerging Bad Banks : Opportunities for Investors
July 2009 Europe s Emerging Bad Banks : Opportunities for Investors BY CONOR DOWNEY, ALBERTO DEL DIN, HERGEN HAAS AND DAVID LACAZE Across Europe governments are establishing so-called bad banks to assist
More information10.7 Dealing with HMRC
10.7 Dealing with HMRC 10.7.1 Getting a Revenue opinion HMRC has a specialist unit dealing with IR35 inquiries and in the author s experience the staff there are very professional. Contact details are
More informationDistribution of monies under the UK Asbestos Trust
Trust Deed Distribution of monies under the UK Asbestos Trust Dated 10 October 2006 As amended by the 2016(ii) (Tenth Anniversary) Amending Deed dated 5 January 2017 T&N Limited, acting by the Administrators
More information