Risk Based Verification

Size: px
Start display at page:

Download "Risk Based Verification"

Transcription

1 OFFSHORE SERVICE SPECIFICATION DNV-OSS-300 Risk Based Verification APRIL 2004 This document has been amended since the main revision (April 2004), most recently in April See Changes on page 3. The electronic pdf version of this document found through is the officially binding version

2 FOREWORD DET NORSKE VERITAS (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property and the environment, at sea and onshore. DNV undertakes classification, certification, and other verification and consultancy services relating to quality of ships, offshore units and installations, and onshore industries worldwide, and carries out research in relation to these functions. DNV service documents consist of amongst other the following types of documents: Service Specifications. Procedual requirements. Standards. Technical requirements. Recommended Practices. Guidance. The Standards and Recommended Practices are offered within the following areas: A) Qualification, Quality and Safety Methodology B) Materials Technology C) Structures D) Systems E) Special Facilities F) Pipelines and Risers G) Asset Operation H) Marine Operations J) Cleaner Energy O) Subsea Systems Det Norske Veritas AS April 2004 Any comments may be sent by to For subscription orders or information about subscription terms, please use Computer Typesetting (Adobe Frame Maker) by Det Norske Veritas This service document has been prepared based on available knowledge, technology and/or information at the time of issuance of this document, and is believed to reflect the best of contemporary technology. The use of this document by others than DNV is at the user's sole risk. DNV does not accept any liability or responsibility for loss or damages resulting from any use of this document.

3 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Changes Page 3 CHANGES INTRODUCTION This Service Specification was approved by the Director of Technology in April Publication of this Service Specification will make the Service Specification DNV-OSS-303 obsolete. This general document gives the common framework and an overview of processes in risk based verification. It introduces a levelled description of verification involvement during all phases of an asset s life. The document facilitates a categorisation into risk levels High, Medium and Low, assisting in an evaluation of the risk level. The document assists in planning the verification through the making of a Verification Plan. Providing an international standard allowing a transparent and predictable verification scope, as well as defining terminology for verification involvement. Amendments April 2012 The restricted use legal clause has been deleted from the front page. Amendments October 2011 A restricted use legal clause has been added on the front page.

4 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 4 Contents see note on front cover CONTENTS Sec. 1 General... 6 A. General... 6 A 100 Introduction... 6 A 200 Objectives... 6 A 300 Scope of application... 6 A 400 Structure of DNV Offshore Service Specifications related to verification... 6 A 500 Structure of this document... 6 A 600 Structure of related DNV documents... 7 B. Definitions and Abbreviations... 7 B 100 General... 7 B 200 Definitions... 7 B 300 Abbreviations... 9 C. References... 9 C 100 General... 9 Sec. 2 Principles of Risk Based Verification A. General A 100 Objectives B. General Verification Principles B 100 Purpose of Verification B 200 Verification as a Complementary Activity B 300 Verification Based on Risk B 400 Verification Management C. Risk Based Verification Concept C 100 Elements of the service C 200 Asset Planned C 300 Asset Specification C 400 Risk Assessment C 500 Definition of Verification Involvement C 600 Verification Plan C 700 Verification Execution C 800 Asset Completed D. Risk-Differentiated Levels of Verification D 100 Levels of verification E. Defining a Verification Plan E 100 Risk based verification planning E 200 Selection of Level of Verification E 300 Acceptance criteria F. Simplified Verification Planning F 100 General G. Detailed Verification Planning G 100 General H. Risk Based Verification and National Regulations H 100 General App. A Benefits of DNV Risk Based Verification A. General A 100 Background information A 200 Verification trends A 300 Benefits of DNV Risk Based Verification A 400 Other DNV services related to Risk Based Verification App. B Verification and Certification Documents A. Verification Documents A 100 Purpose of Verification Documents A 200 Validity of Verification Documents A 300 Verification Documents Provided B. Certification documents B 100 General B 200 Validity of Certification documents... 23

5 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Contents Page 5 App. C Example List of Typical High Risk Elements A. High Risk Elements A 100 Offshore installations App. D Detailed Performance Requirements and Verification Activity Descriptions 27 A. Performance Requirements A 100 Setting performance requirements B. Verification Activities B 100 Developing Verification Activity Lists... 27

6 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 6 Sec.1 see note on front cover SECTION 1 GENERAL A. General A 100 Introduction 101 This DNV Offshore Service Specification (DNV-OSS) gives an overview of DNV Verification Services. A 200 Objectives 201 The main objectives of this document are to: describe DNV s Risk Based Verification services provide a common communication platform for describing the extent of verification activities, i.e. how to define a verification scope give guidance to owners and other parties for selecting the level of involvement of the verifier provide an opportunity to establish efficient, cost effective, predictable and transparent verification plans. A 300 Scope of application 301 This specification applies to verification during the asset owner s control of the process leading up to the completion of a physical asset, and further during the lifetime of the asset until abandonment. 302 This specification is primarily aimed at oil and gas related facilities and installations located onshore or offshore. The principles may also be applied to general industrial developments. 303 This specification may be adopted for full field development, particular phases of an asset realisation process or for particular elements. The owner may chose to utilise DNV s resources for all or selected parts of the scope. 304 DNV s Risk Based Verification services may be carried out on assets specified in: DNV s Offshore Standards, International or national standards, or Owner s specification A 400 Structure of DNV Offshore Service Specifications related to verification 401 The DNV Offshore Service Specifications related to verification are organised according to the pyramidal principles in Figure 1. DNV- OSS-300 General service overview DNV-OSS-3nn Object specific detailed specifications Figure 1 Hierarchy of DNV s offshore service specifications for verification 402 The top level document DNV-OSS-300, describes the overall philosophy and services. The objectspecific documents describe the principles and give detailed information regarding the potential scope of work for the verification of each object. 403 An object-specific DNV-OSS provides a basis for the development of scope of work for verification activities. Section 2 gives the service overview and principles for scope of work descriptions. Detailed examples of scope of work tables are found in appendices to the object specific documents. 404 Some of the object-specific documents also give requirements to achieve and maintain a DNV Certificate of Conformity (Ref. Appendix B). A 500 Structure of this document 501 This document contains two sections and four appendices: Section 1 gives the scope of the document, definitions and references.

7 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Sec.1 Page 7 Section 2 explains the philosophy and principles of Risk Based Verification. It explains the risk-differentiated levels of involvement, the elements in the RBV chain and the different methodologies within risk assessment to develop a Verification Plan. Appendix A gives the benefits of a targeted and planned verification. Appendix B gives an overview of the main verification and certification documents issued by DNV, including the DNV Certificate of Conformity and the DNV Statement of Compliance. Appendix C is an example list of typical high risk elements for the main types offshore installations Appendix D gives information on how to develop detailed performance requirements and verification activities. A 600 Structure of related DNV documents 601 The DNV document systems consist of a three-level hierarchy with these main features: Principles and procedures related to DNV s services are separate from technical requirements and are presented in DNV Offshore Service Specifications. The documents described in Figure 1 belong here. Technical requirements are issued as self-contained DNV Offshore Standards. Associated product documents are issued as DNV Recommended Practices. 602 The hierarchy is designed with these objectives: Offshore Service Specifications present the scope and extent of DNV s services. Offshore Standards are issued as neutral technical standards to enable their use by national authorities, as international codes and as company or project specifications without reference to DNV s services. The Recommended Practices give DNV s interpretation of safe engineering practice for general use by industry. The latest revision of all DNV documents may be found in the publications list on the DNV web site B. Definitions and Abbreviations B 100 General 101 The following definitions should be applied only in the context of this document, and may not necessarily be appropriate for services outside the Risk Based Verification approach as described. B 200 Definitions 201 Asset: Loose term used to describe the item to be made or maintained. Can refer to a full field development, a topside facility, a pipeline system, a compressor station etc. or a part of these. It is interchangeable with the term Object. 202 Certificate of Conformity: A document signed by a qualified party affirming that, at the time of assessment, the product or service met the stated requirements (BS 4778: Part 2). For this OSS, a Certificate is a short document (often a single page) stating conformity with specified requirements. The results from associated verification shall be contained in a separate (single or multiple volume) report. 203 Certification: Used in this document to mean all the activities associated with the process leading up to the Certificate. In the DNV- OSS when Certification is used it designates the overall scope of work or multiple activities for the issue of a Certificate, whilst Verification is also used for single activities associated with the work. This in essence means that Certification is Verification for which the deliverable includes the issue of a Certificate. Other (related) definitions are: BS 4778: Part 2: Certification: The authoritative act of documenting compliance with requirements. EN 45011: Certification of Conformity: Action by a third party, demonstrating that adequate confidence is provided that a duly identified product, process or service is in conformity with a specific standard or other normative document. ISO 8402: 1994: Verification: Confirmation by examination and provision of objective evidence that specified requirements have been fulfilled.

8 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 8 Sec.1 see note on front cover 204 Element: Loose term which can mean anything from a drilling rig to a system or a component. the level of detail will depend on the situation. In a hierarchic structure elements are below asset. 205 Hazard: A deviation (departure from the design and operating intention) which could cause damage, injury or other form of loss (Chemical Industries Association HAZOP Guide). 206 HAZOP (HAZard and OPerability study): The application of a formal systematic critical examination to the process and engineering intentions of new or existing facilities to assess the hazard potential of maloperation or mal-function of individual items of equipment and their consequential effects on the facility as a whole (Chemical Industries Association HAZOP Guide). 207 HAZID, (HAZard IDentification): A technique for the identification of all significant hazards associated with the particular activity under consideration. (ISO-17776) 208 Life cycle: Loose term which includes all phases of an asset; concept studies, front end engineering design (FEED), design, procurement, fabrication, hook-up, commissioning, operation/ production, maintenance, inspection and abandonment. 209 Object: Loose term used to describe the item to be made or maintained. Can refer to a full field development, a topside facility, a pipeline system, a compressor station etc. or a part of these. It is interchangeable with the term Asset. 210 Owner: In the document used not just to describe the actual owner, but also to used to reflect DNV s contractual partner. In many projects the owner authorises the contractor to act on his behalf and it shall then mean the contractual partner. 211 Performance requirement: A description of the essential requirements to be met, maintained or provide on demand by an element. Appendix D may be used for guidance. 212 Risk: The qualitative or quantitative likelihood of an accident or unplanned event occurring, considered in conjunction with the potential consequences of such a failure. In quantitative terms, risk is the quantified probability of a defined failure mode times its quantified consequence. Risk is not only related to physical failure modes, but also to operational errors, human errors and so on. For some risks the functional failures or physical failure modes contribute less than 20% while more than 80% of the risk relates to other devices. 213 Risk Reduction Measures: Those measures taken to reduce the risks to the operation of the system and to the health and safety of personnel associated with it or in its vicinity by: Reduction in the probability of failure. Mitigation of the consequences of failure The usual order of preference of risk reduction measures is: a) Inherent Safety. b) Prevention. c) Detection. d) Control. e) Mitigation. f) Emergency Response. 214 Safety Objectives: The safety goals for the construction, operation and decommissioning of the asset including acceptance criteria for the level of risk acceptable to the Owner. 215 Statement of Compliance: A statement or report signed by a qualified party affirming that, at the time of assessment, the defined asset phase, or collection of activities, met the requirements stated by the Owner. 216 Verification is confirmation by examination and provision of objective evidence that specified requirements have been fulfilled (ISO 8402: 1994). The examination shall be based on information, which can be proved true, based on facts obtained through observation, measurement, test or other means. See also Certification.

9 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Sec.1 Page 9 B 300 Abbreviations 301 DNV OS OSS QRA RBV Det Norske Veritas Offshore Standard, used in the form DNV-OS Offshore Service Specification, used in the form DNV-OSS Quantitative Risk Analysis Risk Based Verification C. References C 100 General 101 A guide to Hazard and Operability studies, 1979, Chemical Industries Association Limited. London 102 ISO 8402 Quality Vocabulary, 1994, International Organization for Standardization, Geneva 103 BS4778 Quality Vocabulary, Part 2 Quality concepts and Related Definitions, 1991, British Standard Institute, London 104 EN General Criteria for Certification Bodies Operating Product Certification, 1998, European Committee for Standardization, Brussels 105 ISO Petroleum and natural gas industries Offshore production installations - Guidelines on Tools and Techniques for Hazard Identification and Risk Assessment, 2000, International Organization for Standardization, Geneva.

10 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 10 Sec.2 see note on front cover SECTION 2 PRINCIPLES OF RISK BASED VERIFICATION A 100 Objectives 101 The objectives of this section are to provide: A. General an introduction to the DNV Risk Based Verification Concept and the elements of the Risk Based Verification Chain an introduction to the principles of risk differentiated levels of verification activities guidelines on the selection of levels of verification. B. General Verification Principles B 100 Purpose of Verification 101 Verification constitutes a systematic and independent examination of the various lifecycle phases of an asset to determine whether it is (or continues to be) in compliance with some or all of the asset specifications. 102 Verification activities are expected to identify errors or failures in the work associated with the asset and to contribute to reducing the risks to the operation of the asset and to the health and safety of personnel associated with it or in its vicinity or other unwanted situations. B 200 Verification as a Complementary Activity 201 Verification shall be complementary to routine design, construction and operations activities and not a substitute for them. Therefore, although verification will take into account the work, and the assurance of that work, carried out by the owner and its contractors, it is inevitable that verification will duplicate some work that has been carried out previously by other parties involved in the asset or system. B 300 Verification Based on Risk 301 Verification based on risk is founded on the premise that the risk of failure can be assessed in relation to a level that is acceptable and that the verification process can be used to manage that risk. The verification process is therefore a tool to maintain the risk below the acceptance limit. 302 Verification based on risk aims to be developed and implemented in such a way as to minimise additional work, and cost, but to maximise its effectiveness. The development of a risk based verification plan shall depend on a risk assessment and the findings from the examination of quality management systems, documents and production activities. B 400 Verification Management 401 The philosophy and verification methods used shall be described in a Verification Plan to ensure satisfactory completion of verification. The philosophy and these methods should ensure that verification: has a consistent and constructive approach to the satisfactory completion and operation of the asset is available world-wide wherever the owner or his contractors operate uses up-to-date methods, tools and procedures uses qualified and experienced personnel. 402 All verification activities shall be carried out by competent personnel. Competence includes having the necessary theoretical and practical knowledge and experience of the activity being examined. An adequate verification of some activities may require access to specialised technical knowledge. 403 As well as demonstrating competence of individuals, the verification organisation shall also be able to show competence and experience in verification work for relevant assets. C. Risk Based Verification Concept C 100 Elements of the service 101 The risk based verification concept can be visualised to involve the elements in Figure 1. It is a chain with iterative loops.

11 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Sec.2 Page 11 Asset Planned Asset Specification including overall Owner acceptance criteria, performance requirements and verification objectives Risk Assessment including identification of hazards and ranking of hazards based on risk evaluation Definition of Verification Involvement including detailing of acceptance criteria and performance requirements Verification Plan including list of verification activities Figure 1 The DNV Risk Based Verification Chain Verification Execution including reporting of compliance or noncompliance Asset Completed 102 Asset is used collectively. It is an onshore or offshore installation or part thereof, a system or process, or a development phase such as feasibility, design, construction, commissioning, operation and decommissioning. 103 The Asset Planned and Asset Decommissioned are the boundaries of the Risk Based Verification process. 104 Asset Specification, Risk Assessment and Definition of Verification Involvement are inputs into the Verification Plan, while Verification Execution is the implementation of the Verification Plan. The Risk Based Verification service comprises of one, some or all of these main elements. C 200 Asset Planned 201 Asset Planned is the starting point for any project or project phase and is the decision of the owner. It comprises a general description of the project in the form of functionality, safety, capacity, economics etc. C 300 Asset Specification 301 Asset Specification has been identified as a separate element to focus on the need to address objectives, acceptance criteria and performance requirements to the asset. 302 This element in the chain comprises: detailing of the description at the system level of the project in the form of functionality, safety, capacity, economics etc. identification or definition of verification philosophy, safety objectives etc., including selection of safety and/or business and/or environmental focus and goals identification of codes and technical specifications (e.g. standard company material specifications) to be adopted definition of high level performance requirements for the asset and identification of main elements and specific performance requirements thereof.

12 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 12 Sec.2 see note on front cover 303 The detailing of elements and requirements will vary from project to project. The timing for detailing will also vary and is affected by matters like contract type and philosophy, owners involvement in the process, level of innovative elements in the project, life time business philosophy etc. C 400 Risk Assessment 401 Risk Assessment is the identification of hazards, frequencies of occurrence, consequences and risk drivers. The risk can be defined on a general level for the project, for different phases of a project or for detailed elements of the asset. 402 The risk can be evaluated based on safety, environmental impact, economics, schedule, Public Relations, reputation or other criteria set by the owner. 403 Risk Assessment can be based on engineering judgement (pragmatic) or on analytical processes. In section E different methods have been described to arrive at the conclusions necessary to formulate a risk based verification plan. 404 Once the risks have been identified their extent can be reduced to a level as low as reasonably practicable or as low as corporately required, by means of one or both of: reduction in the probability of failure mitigation of the consequences of failure. Reasonable Practicability The term as low as reasonably practicable (ALARP) has come into use through the United Kingdom s The Health and Safety at Work etc. Act Reasonable Practicability is not defined in the Act but has acquired meaning by interpretations in the courts. It has been interpreted to mean that the degree of risk from any particular activity can be balanced against the cost, time and trouble of the measures to be taken to reduce the risk. It follows, therefore, that the greater the risk the more reasonable it would be to incur substantial cost, time and effort in reducing that risk. Similarly, if the risk was very small it would not be reasonable to expect great expense or effort to be incurred in reducing it. 405 The systematic assessment of risks and the implementation of measures to reduce these, results in a relative ranking of the risk level of the elements and /or sub-elements of the asset. 406 The ranking of the elements will differ depending on the acceptance criteria; safety, environmental impact, economics, schedule, public relations, reputation or others. Different criteria may be applied to factor the importance of these. C 500 Definition of Verification Involvement 501 Definition of verification involvement or level(s) includes defining the cut-off level under which no verification activity shall be performed and to define the appropriate level of involvement for the others. 502 Based on the relative risk level of the elements the verification intensity should increase towards the highest risk elements. Verification of risk reducing measures e.g. in the form of risk reducing barriers, should be directed towards the risk reducing measures (barriers) which claims to have the highest risk reducing effects. 503 In this process the overall acceptance criteria from the Asset Specification should be cascaded down to more detailed performance requirements for individual elements or groups of elements. 504 The risk ranking is used in the selection of the appropriate verification activity level and type to be described in the verification plan. C 600 Verification Plan 601 The Verification Plan is the pivot element in the DNV Risk Based Verification systematics. 602 The Verification Plan is the scope of work (SOW) for verification. It should be revisited, re-evaluated and possibly revised as the project progresses and new information becomes available. 603 The more specific the Verification Plan, the more predictable the verification activities will be. 604 The Verification Plan repeats the verification objective and the criteria for selecting the highest risk elements and the verification involvement, as given by the Owner. It includes the findings from the risk assessment step, defines which asset specifications shall be verified, and also the level of involvement by party and type of verification activity.

13 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Sec.2 Page The Verification Plan further consists of listing the elements and their performance requirements together with the type and depth of scrutiny to which each shall be subjected. 606 The verification involvement level can be described using the tables in Sect.2 of the relevant object specific DNV-OSS. 607 Detailed scope of work tables listing all the sub-elements of an asset, can either be developed from the tables in Sec. 2 of the relevant object specific DNV-OSS or they can be based on the example tables included in the appendices. 608 For information typical high risk elements with respect to safety of personnel, often termed Safety Critical Elements, are presented in Appendix C. C 700 Verification Execution 701 Verification Execution is document review, independent analyses, inspection, monitoring, site visits, process audits, technical audits, testing, etc. according to the Verification Plan. 702 Information arising from execution should be used to identify continuous improvements to the Verification Plan. E.g. evidence of good systematic control may be used to reduce the verification activities. 703 The purpose of verification activities is to confirm compliance or identify non-compliance with the asset specification. C 800 Asset Completed 801 Asset Completed is the end point of any lifecycle phase or phases, which complies with the relevant planned asset and the asset specification. D. Risk-Differentiated Levels of Verification D 100 Levels of verification 101 The level of verification activity should be differentiated according to the risk to the asset or element or phases thereof. If the risk to the asset is higher, the level of verification involvement is higher. Conversely, if the risk to the asset is lower, the level of verification activities can be reduced, without any reduction in their effectiveness. 102 It is emphasised that the activity level describes the depth of the verification involvement. It follows, therefore, that an increase in the level of involvement above that considered necessary, based on an evaluation of the risks, involves minimal extra risk reduction for increased cost. This practice is unlikely to be costeffective. 103 Verification of assets or elements thereof are typically categorised into Low, Medium and High. Low is the level of verification applied where the risks to the asset are lower than average. For example, it has benign contents, it is located in congenial environmental conditions, or the contractors are well experienced in the design and construction of similar assets. This level may also be appropriate when the Owner (or other parties) performs a large degree of verification and/or quality assurance work. Medium is the customary level of verification activity and is applied to the majority of assets. High is the level of verification applied where the risks to the asset is higher than average. For example, it has highly corrosive contents, it is in adverse environmental conditions, it is technically innovative or the contractors are not well experienced in the design and construction of similar assets. This level may also be appropriate when the Owner chooses to have a small technical involvement or performs little own verification. The terms Basic, Regular and Special are sometimes used to describe the level of involvement. If these are used in connection with DNV Risk Based Verification, then Basic shall mean Low, Regular shall mean Medium and Special shall mean High. 104 Illustrations of the levels of involvement are given in Figures 2 and 3. Figure 2 illustrates the levels as a function of probability and consequence of failure. Figure 3 illustrates how increasing depth of scrutiny is assigned to elements with increasing risk levels. An element can be everything from a drilling rig to an important component or system, depending on the detailing level of the risk assessment being carried out.

14 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 14 Sec.2 see note on front cover Figure 2 Levels of verification Probability of Failure Low High Low MEDIUM LOW Consequence of Failure Increasing Risk HIGH High Elements A B C D E F G H I Axis of increasing risk and depth of scrutiny Figure 3 Increasing verification scrutiny as a function of increasing risk level for each element 105 It is the prerogative of the owner of the asset system to choose the level of verification. The selection should be documented. 106 Different levels of verification can be chosen for different lifecycle phases of the asset, or even within the same phase if necessary. For example, asset design may be innovative and considered high risk whereas the installation method is well known and considered low risk. The converse might be true also. 107 The level of verification can be reduced or increased during a phase if the originally chosen level is considered too rigorous or too lenient, as new information on the risks to the asset becomes available. Care should be taken to ensure that short term gains do not influence the reduction of verification, which could lead to a long term detriment. 108 Verification should be planned in close co-operation with the Owner and each of the contractors, to provide a scope of work that is adjusted to the schedule of each lifecycle element, i.e. to make the verification activities, surveillance and hold points, an integrated activity and not a delaying activity. Many Contractors have adequate quality control systems and quality control departments, with competent personnel to perform, for example, inspection at plants and specialist engineers competent to review and verify the performance of plants. In that case, all verification work need not be done by DNV personnel. Where applicable, the various inspections may be carried out by competent persons other than DNV personnel. In that situation a substantial part of DNV s verification activities may be encompassed by: - reviewing the competence of the Contractor s personnel, - auditing their working methods and their performance of that work, and - reviewing the documents produced by them. 109 Verification should direct greatest effort at those elements of the asset or system whose failure or reduced performance will have the most significant impact on safety or the other defined project risks. These elements are termed high risk elements or sometimes Critical Elements.

15 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Sec.2 Page The degree of confidence placed in verification reports depends on the degree of confidence in the verification activities carried out. Therefore, the verification plan must be transparent and give clear details of the level of verification for both elements and phases. E. Defining a Verification Plan E 100 Risk based verification planning 101 The selection of the level of verification shall depend on the risk level of each element having an impact on the management of hazards and associated risk levels of the asset. 102 The effort spent to select the overall level of verification and the detailing and differentiation between different elements will vary from project to project. It is a business decision on how to balance the effort of upfront planning with that of some additional effort during verification execution. 103 The tools used to arrive at a Verification Plan range from engineering judgement risk assessment to analytical risk assessments. The former generally reflects less effort in the up-front planning stage while the latter directs more efforts into the particulars of a specific project. 104 The span in the method is illustrated in Figure 4. Most projects will utilise a combination of tools. Typically, for a tender phase it may be useful to utilise engineering judgement to make an initial Verification Plan. When updating the Verification Plan the appropriate analytical tools can be utilised. E 200 Selection of Level of Verification 201 Suitable selection factors include: overall asset specification assessment of the risks associated with the asset and the measures taken to reduce these risks degree of technical innovation in the asset system experience of the contractors in carrying out similar work quality management systems of the Owner and their contractors. 202 To facilitate the selection of the level of verification a set of trigger questions based on the above list of selection factors, has been prepared and is included in the object specific DNV-OSS. 203 To further assist in the selection of general level of verification Table E1 can give some guidance. 204 The level of verification is selected for each individual element and should reflect the risk level as well as the type of performance requirements. To achieve a consistent verification involvement relative to risk level a practical and visual approach can be to plot the elements and relative risk levels as in Figure 3. Decide on the maximum level of involvement (L, M or H) and draw the line to the left of which no verification shall be made. The area enveloping the elements to be verified can then be split in to areas with uniform verification involvement. E 300 Acceptance criteria 301 Defined acceptance criteria are essential to confirm compliance and identify non-compliance.

16 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 16 Sec.2 see note on front cover 302 The format and detailing may differ. Assets, elements or lifecycle phases for which technical standards or company specifications exist, may have relatively short and simple acceptance criteria. For assets, elements or lifecycle phases not readily covered by prescriptive standards, greater effort is directed into the particulars of the specific project and this often results in more detailed performance requirements. Table E1 Levels of verification and guidance on typical involvement at system level Level Typical System Characteristics Description of typical verification involvement Low Proven designs with relatively harmless content and/or installed in benign environmental conditions. State of the art design, manufacturing and installation by experienced contractors. Low consequences of failure from a commercial, safety or environmental point of view. Relaxed to normal completion schedule. Review of General Principles and production systems during design and construction. Review of principal design documents, construction procedures and qualification reports. Site attendance only during system testing. Less comprehensive involvement than level Medium. Medium High Asset in moderate or well controlled environmental conditions. Plants with a moderate degree of novelty Medium consequences of failure from a commercial, safety or environmental point of view. Ordinary completion schedule. Innovative designs. Extreme environmental conditions. Plants with a high degree of novelty or large leaps in technology. Contractors with limited experience or exceptionally tight completion schedule. Very high consequences of failure from a commercial, safety or environmental point of view. Review of General Principles and production systems during design and construction. Detailed review of principal and other selected design document with support of simplified independent analyses. Full time attendance during (procedure) qualification and review of the resulting reports. Audit based or intermittent presence at site. Review of General Principles and production systems during design and construction. Detailed review of most design document with support of simplified and advanced independent analyses. Full time attendance during (procedure) qualification and review of the resulting reports. Full time presence at site for most activities. More comprehensive involvement than level Medium.

17 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover Sec.2 Page 17 Asset Specification Simplified verification planning, based on Engineering judgement Combined verification planning Detailed verification planning, based on Analytical risk assessment: Risk assessment based on trigger questions. HAZID for the asset. This may be done stepwise with increasing detailing on the more complex components/processes. Risk Assessment Definition of Verification Level Conclude on overall verification involvement; H, M or L Prepare Verification Plan based on predefined tables. Include adjustments to tailor for the particular asset. Confirm acceptance criteria to be sufficient. Identify elements for verification and prepare verification plan based on any combination of the simplified and detained verification planning. The predefined tables may be useful references Frequency of occurrence Analytical assessment of risk and identification of relative risk levels. The relative risk may be grouped into Low, Medium or High Consequence Define acceptance criteria or performance requirements in more detail Prepare Verification Plan based on the assessed risks, risk drivers and acceptance criteria as defined above. The type and depth of verification is described using the same terminology as used in the predefined tables. Verification Plan Figure 4 Verificaton planning

18 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 18 Sec.2 see note on front cover F. Simplified Verification Planning F 100 General 101 Simplified verification planning is mainly based on engineering judgment and reflects DNV's in-house experience as well as the industry experience as reflected in a number of technical standards. Both have been used to make up the object specific DNV-OSS s. 102 The steps in the simplified verification planning are as follows: Use trigger questions to assess the overall risk level of the project (or manageable elements thereof). Evaluate the risk against the relevant owner or project acceptance criteria (often this can be directly tied to the owner core values or a sub-set of these) and decide whether the general verification involvement shall be Low, Medium or High. Use the detailed scope of work tables in the object DNV-OSS to make a first draft of a Verification Plan Generate the project specific Verification Plan by include a project specific engineering judgment to adjust the table to suit the project Perform the verification execution according to the Verification Plan, making revision to the plan if and when necessary. 103 Care shall be taken not to use this process without sufficient attention to its built-in simplifications. Particularly the use of example tables in the appendices can never replace the need for project specific assessments. They can, however, be very useful starting and reference points. G. Detailed Verification Planning G 100 General 101 The analytical verification planning is based on the use of (quantitative) risk methods to establish project specific identification of the relative risk level of the project elements. 102 Depending on the project size and type the risk assessment will often include an initial qualitative risk assessment screening prior to a full quantitative risk analysis, QRA. 103 A description on how to carry out HAZID, HAZOPD and QRA in general is not given in this DNV-OSS. The methodology is described in numerous books and publications on the subject. 104 Particularly for projects or project elements were there are limited or inadequate prescriptive technical standards or if the performance requirements are of a nature that make available prescriptive standards inadequate, it is advisable to invest more time and effort in the planning stages. 105 With limited prescriptive standards the need and also the effort required to define the acceptance criteria for individual or groups of elements will normally increase. Appendix D addresses how to formulate detailed performance requirements and also how these and the risk elements are developed into verification activity lists, which are finally included in the Verification Plan H. Risk Based Verification and National Regulations H 100 General 101 Many national authorities have specific requirements to the verification activities. These can be in the form of minimum requirements to documentation of risk and risk reducing measures, which documents shall be presented to the authorities, mandatory use of standards etc. The authorities may also have requirements to roles and responsibility, independence of verifier, content and form of verification activities, terminology etc. 102 The particulars of the relevant national requirements shall be observed when planning and performing Risk Based Verification. The Offshore Installations (Safety Case) Regulations in UK can be an example of particular National Authority requirements. The risk based verification approach fits very well with these regulations, but one needs to ensure that the correct documents and terminology are used and understood e.g. Major Accidents Hazards, Safety-Critical Elements, Performance Standards etc.

19 Amended April 2012 Offshore Service Specification DNV-OSS-300, April 2004 see note on front cover App.A Page 19 APPENDIX A BENEFITS OF DNV RISK BASED VERIFICATION A. General A 100 Background information 101 This appendix gives background information on verification and the possible benefits thereof. A 200 Verification trends 201 Verification has historically been carried out with a variety of scope and depth of involvement. The depth of involvement, or level of verification, has not always been very transparent. 202 There are national authorities requiring verification or even certification of offshore or onshore installations (assets) and have appointed specific organisations qualified for this work. 203 Some of these national authorities may have detailed requirements to the verification or certification activity, while others leave the definition of the necessary work up to the appointed organisation. Other national authorities require specific documents to be verified and approved by them, some hold the owner responsible for the verification activities, others again may not have any specific requirements. 204 The trend is that authorities remove themselves from the prescriptive regimes and convert to functional requirements and safety and risk approaches. It is therefore believed that there will be a stronger demand for measurable objectives to be presented by the owners. The objectives are linked, as a minimum, to the expectations from the authorities on safety to the work force, the public and the environment. Economics may be an additional minimum requirement from the owner and his partners. 205 As a means to fulfilling these expectations business today is often characterised by a defined desire to systematically balance expected costs and benefits. The aim is an optimum control of the uncertainties (or risks) related to the objectives. 206 Even where national authorities do not require verification of installations (assets), verification (or certification) is a convenient tool for the owner to get an independent evaluation of the contractor(s) work or to show financiers, partners, insurers and the public that the asset complies with relevant safety levels and other requirements in the asset specification. 207 It is good business practice to subject important work to a third-party check as this reduces the possibility of errors remaining undetected. Third-party verification will ensure that the verifier has an independent view and perspective when performing this activity. Furthermore, it will avoid the situation where errors could be overlooked by engineers or others because of their closeness to the work with the asset. 208 Systematic risk based assessment methods are more often used to identify the risk associated with the elements. Based on this identified risk, focus is put on the relevant acceptance criteria pertaining to integrity, functionality, survivability, availability, reliability, maintainability, and environmental impact of an asset throughout its lifecycle. 209 The result of the systematic identification of risk can be utilised in the design and construction by the Contractor and by the Owner or a 3 rd party to optimise the verification activities through a well defined and transparent verification plan. 210 Not all projects nor all high risk elements have great degrees of novelty or innovation requiring a large degree of sophistication when predicting risk. The high risk elements or phases can often be determined by what is addressed in international technical standards and from general experience. For these projects the ability to communicate the correct or desired level of verification may be the most time consuming exercise. 211 At the other end of the scale are the projects that have greater uncertainty, and often appears to be high risk, but which need to be systematically addressed to be able to identify the hazards, the probability and consequences of occurrence and the risk levels of the elements. For these projects the correct identification and ranking of the risk of the elements is essential for the project optimisation process and planning of the verification activities. However, it is also for these necessary to be able to communicate the level of verification and link it to the associated risk. 212 For almost all projects, interface activities are important and many have experienced that inadequate interface management can be very costly and time consuming. A 300 Benefits of DNV Risk Based Verification 301 Business today is characterised by the need to balance cost and benefits through a better understanding and mastering of the assets and their associated risks. Risk Based Verification aims at balancing the efforts to control the operational and technological risks and for an optimum control of risks and uncertainties from the concept stage to decommissioning or abandonment of any asset. It may provide cost and time savings compared with prescriptive verification or certification by focusing on risk and by prioritising verification efforts.

20 Offshore Service Specification DNV-OSS-300, April 2004 Amended April 2012 Page 20 App.A see note on front cover 302 The use of a more elaborate analytical method to plan the verification may give substantial cost benefits during the verification execution. Particularly for projects characterised by the following: a high degree of complexity significant elements of new or unproven technology proven elements being introduced to new operating conditions or applications participants having limited experience in a type of asset or development challenging development programmes. 303 DNV aims through Risk Based Verification, to instil confidence in our customers. Through independent and competent scrutiny the intent is to confirm that the asset is designed, constructed and/or operated so that: it is fit for its intended purpose, its level of integrity is as high as reasonably practicable the associated risk to health, life, property and environment is as low as reasonably practicable. 304 Such confidence arising from Risk Based Verification is not necessarily limited to DNV s traditional customers it can be extended to contractors or other project participants, owners, financiers, partners, insurers etc. that an asset complies with a relevant basis, even in areas where formal references may be missing or are under development. 305 The advantages for DNV s customers in applying a Risk Based Verification approach may include: reduced probability of undesirable events improved availability and reliability cost and time savings through avoiding undue attention to areas and activities that are low contributors to risk contributing to optimised expenditure (CAPEX, OPEX and RISKEX) in high risk areas early involvement in projects to ensure correct decisions and minimal rework a demonstrable and auditable case for safety or other owner or project core values active support to, and demonstration of achievement of, these core values confirmation, and increased visibility, of the above to (project) partners and other stakeholders and to Regulatory Bodies. 306 For a new asset development Risk Based Verification services should seek to reduce any uncertainty in the design as early as possible, and if any weaknesses are revealed allow for effective management of necessary changes, ref. Figure 2 Effects of Early Involvement. DNV s verification experience reinforces the important message of early involvement and the need for in-depth knowledge of the activities required to obtain optimal resource allocation for the verification process. A proactive approach is required and places particular emphasis on roles and responsibilities. Increase Ability to Influence Cost of Change Concept Time Commissioning Figure 1 Effect of early involvement 307 The above processes should consider all phases of the asset lifecycle. For example during the offshore commissioning phase of a new asset there may be temporary items of equipment provided which should be identified as high risk elements (e.g. temporary fire/gas detection). 308 DNV believes that a strong focus on the development of the Verification Plan will support a common interpretation of verification philosophies and requirements (which may differ from one project to another), and this should facilitate a more cost effective verification execution and provide for greater potential value to be obtained from the overall verification process. 309 Database applications (for example DNV s Verifier software) can be implemented to assist with development and execution of Verification Plans, including the capability to record the status of all verification

Classification Based on Performance Criteria Determined from Risk Assessment Methodology

Classification Based on Performance Criteria Determined from Risk Assessment Methodology OFFSHORE SERVICE SPECIFICATION DNV-OSS-121 Classification Based on Performance Criteria Determined from Risk Assessment Methodology OCTOBER 2008 This document has been amended since the main revision (October

More information

OFFSHORE CODES INFORMATION TO USERS DET NORSKE VERITAS

OFFSHORE CODES INFORMATION TO USERS DET NORSKE VERITAS OFFSHORE CODES INFORMATION TO USERS FOREWORD (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property and the environment, at sea and onshore. DNV undertakes

More information

Having regard to the Treaty establishing the European Atomic Energy Community, and in particular Articles 31 and 32 thereof,

Having regard to the Treaty establishing the European Atomic Energy Community, and in particular Articles 31 and 32 thereof, L 219/42 COUNCIL DIRECTIVE 2014/87/EURATOM of 8 July 2014 amending Directive 2009/71/Euratom establishing a Community framework for the nuclear safety of nuclear installations THE COUNCIL OF THE EUROPEAN

More information

The basics of verification. Richard Nott Lloyd s Register EMEA

The basics of verification. Richard Nott Lloyd s Register EMEA The basics of verification Richard Nott Lloyd s Register EMEA Introductions Richard Nott Manager, Compliance and Engineering Services Lloyd s Register EMEA Agenda The Offshore Installation (Safety Case)

More information

COUNCIL OF THE EUROPEAN UNION. Brussels, 4 June /14 Interinstitutional File: 2013/0340 (NLE) ATO 45

COUNCIL OF THE EUROPEAN UNION. Brussels, 4 June /14 Interinstitutional File: 2013/0340 (NLE) ATO 45 COUNCIL OF THE EUROPEAN UNION Brussels, 4 June 2014 10410/14 Interinstitutional File: 2013/0340 (NLE) ATO 45 NOTE from: General Secretariat of the Council to: Delegations No. Cion prop.: 15030/13 ATO 119

More information

An Introductory Presentation for ECU Staff

An Introductory Presentation for ECU Staff Risk Management at ECU An Introductory Presentation for ECU Staff Phillip Draber Manager, Risk and Assurance Outcomes By the end of this session you should: Be able to complete and document risk management

More information

APPENDIX 1. Transport for the North. Risk Management Strategy

APPENDIX 1. Transport for the North. Risk Management Strategy APPENDIX 1 Transport for the North Risk Management Strategy Document Details Document Reference: Version: 1.4 Issue Date: 21 st March 2017 Review Date: 27 TH March 2017 Document Author: Haddy Njie TfN

More information

Procedure: Risk management

Procedure: Risk management Procedure: Risk management Purpose To outline the procedures involved for identification, assessment and management of risks. Procedure Introduction 1. This procedure outlines the University s Risk Awareness

More information

Common Safety Methods CSM

Common Safety Methods CSM Common Safety Methods CSM A common safety method on risk evaluation and assessment Directive 2004/49/EC, Article 6(3)(a) Presented by: matti.katajala@safetyadvisor.fi / www.safetyadvisor.fi Motivation

More information

SIL and Functional Safety some lessons we still have to learn.

SIL and Functional Safety some lessons we still have to learn. SIL and Functional Safety some lessons we still have to learn. David Craig, Amec This paper reflects AMEC s recent experience in undertaking functional safety assessments (FSA) (audits against IEC 61511)

More information

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards A framework for the integration of risk management into the project and construction industry, following

More information

Risk Management Framework

Risk Management Framework Risk Management Framework Anglican Church, Diocese of Perth November 2015 Final ( Table of Contents Introduction... 1 Risk Management Policy... 2 Purpose... 2 Policy... 2 Definitions (from AS/NZS ISO 31000:2009)...

More information

European Railway Agency Recommendation on the 1 st set of Common Safety Methods (ERA-REC SAF)

European Railway Agency Recommendation on the 1 st set of Common Safety Methods (ERA-REC SAF) European Railway Agency Recommendation on the 1 st set of Common Safety Methods (ERA-REC-02-2007-SAF) The Director, Having regard to the Directive 2004/49/EC 1 of the European Parliament, Having regard

More information

Risk Assessment Policy

Risk Assessment Policy Risk Assessment Policy Updated: April 2018 Date of next Review: April 2019 Policy Lead: Bursar Checked by: Middle Leadership Team 1. INTRODUCTION Beachborough School will have hazards which if not controlled

More information

Information security management systems

Information security management systems BRITISH STANDARD Information security management systems Part 3: Guidelines for information security risk management ICS 35.020; 35.040 NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT

More information

CEN GUIDE 414. Safety of machinery Rules for the drafting and presentation of safety standards. Edition 3,

CEN GUIDE 414. Safety of machinery Rules for the drafting and presentation of safety standards. Edition 3, CEN GUIDE 414 Safety of machinery Rules for the drafting and presentation of safety standards Edition 3, 2017-10-11 Supersedes CEN Guide 414:2014 European Committee for Standardization Avenue Marnix, 17

More information

RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES

RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES GUIDE FOR RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES JUNE 2003 American Bureau of Shipping Incorporated by Act of Legislature of the State of New York 1862 Copyright 2003 American

More information

ISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management

ISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management INTERNATIONAL STANDARD ISO/IEC 27005 Second edition 2011-06-01 Information technology Security techniques Information security risk management Technologies de l'information Techniques de sécurité Gestion

More information

ISO INTERNATIONAL STANDARD. Safety of machinery Risk assessment Part 1: Principles

ISO INTERNATIONAL STANDARD. Safety of machinery Risk assessment Part 1: Principles INTERNATIONAL STANDARD ISO 14121-1 First edition 2007-09-01 Safety of machinery Risk assessment Part 1: Principles Sécurité des machines Appréciation du risque Partie 1: Principes Reference number ISO

More information

MISSION VALUES. This Framework has been printed by:

MISSION VALUES. This Framework has been printed by: www.cudgc.sk.ca MISSION We instill public confidence in Saskatchewan credit unions by guaranteeing deposits. As the primary prudential and solvency regulator, we promote responsible governance by credit

More information

We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field.

We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field. Welcome We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field. To login to the audio portion of the web conference, dial

More information

SECTION II.7 MANAGING PROJECT RISKS

SECTION II.7 MANAGING PROJECT RISKS SECTION II.7 MANAGING PROJECT RISKS 1. WHAT ARE RISK ANALYSIS AND RISK MANAGEMENT? Any uncertainty in the scope of the Project, the cost of delivery and time scale for delivery, will present either a risk

More information

The DCA Certification Scheme: Guidelines for DATA CENTRES

The DCA Certification Scheme: Guidelines for DATA CENTRES The DCA Certification Scheme: Guidelines for DATA CENTRES 2015, Data Centre Alliance Limited (www.datacentrealliance.org). All rights reserved. This publication may not be reproduced in Whole or in part;

More information

PRACTICE NOTE 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS

PRACTICE NOTE 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS PRACTICE NOTE 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS (Issued December 2003; revised September 2004 (name change)) PN 1010 (September 04) PN 1010 (December

More information

The Accreditation and Verification Regulation - Verifier s risk analysis

The Accreditation and Verification Regulation - Verifier s risk analysis EUROPEAN COMMISSION DIRECTORATE-GENERAL CLIMATE ACTION Directorate A - International and Climate Strategy CLIMA.A.3 - Monitoring, Reporting, Verification Guidance Document The Accreditation and Verification

More information

Contract Management in Offshore & Marine, EPCIC and Shipyard

Contract Management in Offshore & Marine, EPCIC and Shipyard An Intensive 5 Day Training Course Contract Management in Offshore & Marine, EPCIC and Shipyard 18-22 Nov 2018, Dubai 28 Apr - 02 May 2019, Dubai 17-21 Nov 2019, Dubai 18-JUL-18 This course is Designed,

More information

Risk Management Procedure

Risk Management Procedure Risk Management Procedure 2017 Number: Date Written: Authorised by: Review Date: Version 4.0 15 December 2016 Bernie Wilson 30 December 2018 Contents Amendment and Review... 2 Document Control / Amendments...

More information

DRAFT SAINT LUCIA NATIONAL STANDARD DNS/ISO 31000: 2009 RISK MANAGEMENT PRINCIPLES AND GUIDELINES (ISO 31000: 2009, IDT) Stage 40 Enquiry Stage

DRAFT SAINT LUCIA NATIONAL STANDARD DNS/ISO 31000: 2009 RISK MANAGEMENT PRINCIPLES AND GUIDELINES (ISO 31000: 2009, IDT) Stage 40 Enquiry Stage DRAFT SAINT LUCIA NATIONAL STANDARD DNS/ISO 31000: 2009 RISK MANAGEMENT PRINCIPLES AND GUIDELINES (ISO 31000: 2009, IDT) Stage 40 Enquiry Stage DECEMBER 2017 Copyright SLBS Saint Lucia Bureau of Standards,

More information

Kidsafe NSW Risk Management Plan. August 2014

Kidsafe NSW Risk Management Plan. August 2014 Kidsafe NSW Risk Management Plan August 2014 Document Control Document Approval Name & Position Signature Date Document Version Control Version Status Date Prepared By Comments Document Reviewers Name

More information

Scouting Ireland Risk Management Framework

Scouting Ireland Risk Management Framework No. SID 124A/15 Gasóga na héireann/scouting Ireland Issued Amended 20 th June 2015 Deleted Source: National Management Committee Scouting Ireland Risk Management Framework Revision Date Description # 20/06/2015

More information

Analytics across the asset life cycle

Analytics across the asset life cycle Analytics across the asset life cycle Analytics provides a powerful look forward so that asset rich organisations can chose to react or not to react with changes to the conditions and environment that

More information

Contract HSE Management/Part I

Contract HSE Management/Part I Contract HSE Management/Part I HEALTH, SAFETY AND ENVIRONMENT PROCEDURE Contract HSE Management/Part I DOCUMENT ID - PR-10-POGC-001 REVISION - 1.0 Pages 9 Revision 1.0 Contract HSE Management/Part II Document

More information

Detailed Recommendations 10: Develop Environmental Cost Analysis

Detailed Recommendations 10: Develop Environmental Cost Analysis Detailed Recommendations 10: Develop Environmental Cost Analysis 10 This is a background paper to the report: Establishing China s Green Financial System published by the Research Bureau of the People

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY

MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY ` MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY 1. Vision To develop organizational wide capabilities in Risk Management so as to ensure a consistent,

More information

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Ahsan Jamal Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Introduction For the last couple of years, we have seen enormous growth in the construction industry of Pakistan due to

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

Risk Analysis and Management. May 2011 ISO 14971

Risk Analysis and Management. May 2011 ISO 14971 Risk Analysis and Management Qsite May 2011 ISO 14971 1 Agenda Definitions Risk Management Development Phases Process Hazards Evaluation Residual Risk 2 Why Do We Need Risk Analysis 1. Quantify the risk

More information

Formal Safety Assessment

Formal Safety Assessment Formal Safety Assessment Overview and IACS Experience Presentation at MSC 75-16 May 2002 MSC 75-1/47 Contents FSA -Overview What it is and how it can be used Some FSA Criticism IACS and FSA Experiences

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.x INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES DRAFT, MARCH 2008 This document was prepared

More information

Classification of Contracts under International Financial Reporting Standards IFRS [2005]

Classification of Contracts under International Financial Reporting Standards IFRS [2005] IAN 3 Classification of Contracts under International Financial Reporting Standards IFRS [2005] Prepared by the Subcommittee on Education and Practice of the Committee on Insurance Accounting Published

More information

Approved by: Diocesan Council 17 December 2015

Approved by: Diocesan Council 17 December 2015 DIOCESAN COUNCIL POLICY 39 Risk Management Approved by: Diocesan Council 17 December 2015 1 PREAMBLE The Perth Diocesan Trustees under the authority of the Diocesan Trustees Statute 1952 have the responsibility

More information

Chapter 8: Lifecycle Planning

Chapter 8: Lifecycle Planning Chapter 8: Lifecycle Planning Objectives of lifecycle planning Identify long-term investment for highway infrastructure assets and develop an appropriate maintenance strategy Predict future performance

More information

RISK MANAGEMENT POLICY October 2015

RISK MANAGEMENT POLICY October 2015 RISK MANAGEMENT POLICY October 2015 1. INTRODUCTION 1.1 The primary objective of risk management is to ensure that the risks facing the business are appropriately managed. 1.2 Paringa Resources Limited

More information

Classification of Contracts under International Financial Reporting Standards

Classification of Contracts under International Financial Reporting Standards Educational Note Classification of Contracts under International Financial Reporting Standards Practice Council June 2009 Document 209066 Ce document est disponible en français 2009 Canadian Institute

More information

Job Safety Analysis Preparation And Risk Assessment

Job Safety Analysis Preparation And Risk Assessment Job Safety Analysis Preparation And Risk Assessment Sample Only Reference CPL_PCR_JSA_Risk_Assessment Revision Number SAMPLE ONLY Document Owner Sample Date 2015 File Location Procedure Revision Date Major

More information

Risk Management Strategy Highland Council Pension Fund

Risk Management Strategy Highland Council Pension Fund Risk Management Strategy Highland Council Pension Fund Approved Pensions Committee 9 August 2018 3 1. Introduction 1.1 Risk management is a key element of Corporate Governance and the Highland Council

More information

ALARP Guidance Part of the Petroleum Safety Framework and the Gas Safety Regulatory Framework

ALARP Guidance Part of the Petroleum Safety Framework and the Gas Safety Regulatory Framework ALARP Guidance Part of the Petroleum Safety Framework and the Gas Safety Regulatory Framework DOCUMENT TYPE: Policy Proposal Document REFERENCE: CER/15/212 DATE PUBLISHED: 6 October 2015 VERSION 3.0 QUERIES

More information

REGULATION. on Internal Governance Arrangements, the Management body and the Internal Capital Adequacy Assessment Process for Banks and Savings banks

REGULATION. on Internal Governance Arrangements, the Management body and the Internal Capital Adequacy Assessment Process for Banks and Savings banks Pursuant to point 1 of Article 58 and points 1, 2 and 3 of Article 135 of the Banking Act (Official Gazette of the Republic of Slovenia, No. 25/15; hereinafter: the ZBan-2) and the second paragraph of

More information

The IASB s technical agenda

The IASB s technical agenda IFRS Foundation The IASB s technical agenda Martin Edelmann September 2016 The views expressed in this presentation are those of the presenter, not necessarily those of the International Accounting Standards

More information

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011 Topic RISK MANAGEMENT Procedure 07.01 Category Risk Management Updated 07/2011 RELATED POLICIES, PROCEDURES AND FORMS Policies Procedures Forms Risk Management Policy Code of Conduct Public Interest Disclosure

More information

Risk Management Policy and Strategy

Risk Management Policy and Strategy Risk Management Policy and Strategy Version: 2.1 Bodies consulted: Approved by: Directors and Managers responsible for risk Board of Directors Date Approved: 28 March 2017 Lead Manager: Lead Director:

More information

Stochastic SIL Verification for Complex Safety Instrumented Systems

Stochastic SIL Verification for Complex Safety Instrumented Systems Stochastic SIL Verification for Complex Safety Instrumented Systems Sara Shahidi and Dr. Mehran Pourzand, Monaco Engineering Solutions Limited To ensure a Safety Instrumented System (SIS) is capable of

More information

Table of Contents Advantages Disadvantages/Limitations Sources of additional information. Standards, textbooks & web-sites.

Table of Contents Advantages Disadvantages/Limitations Sources of additional information. Standards, textbooks & web-sites. Table of Contents Table of Contents 1. Consequence Analysis & Risk Reduction Option Selection 1.1. A description of the techniques, including its purpose 1.1.0.. Introduction 1.1.0.3. Consequence Analysis

More information

Recommendation of the Council on Good Practices for Public Environmental Expenditure Management

Recommendation of the Council on Good Practices for Public Environmental Expenditure Management Recommendation of the Council on for Public Environmental Expenditure Management ENVIRONMENT 8 June 2006 - C(2006)84 THE COUNCIL, Having regard to Article 5 b) of the Convention on the Organisation for

More information

EU Council Adopts Revised Nuclear Safety Directive

EU Council Adopts Revised Nuclear Safety Directive GLOBAL NUCLEAR GROUP CLIENT PUBLICATION 14 August 2014 EU Council Adopts Revised Nuclear Safety Directive If you wish to receive more information on the topics covered in this publication, you may contact

More information

Risk Management Strategy

Risk Management Strategy Risk Management Strategy 2016 2019 Version: 6 Policy Lead/Author & Deputy Director of Quality position: Ward / Department: Nursing Directorate Replacing Document: Version 5 Approving Committee Quality

More information

Reservoir safety risk assessment a new guide

Reservoir safety risk assessment a new guide Reservoir safety risk assessment a new guide Mark Morris 1,2, Mike Wallis 1, Alan Brown 3, David Bowles 4, John Gosden 3, Dr Andy Hughes 5, Alex Topple 1, Paul Sayers 6 and Keith Gardiner 7 1 HR Wallingford

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK RISK MANAGEMENT FRAMEWORK 1 RISK MANAGEMENT FRAMEWORK... 1 INTRODUCTION... 3 AN EFFECTIVE ENTERPRISE RISK MANAGEMENT SYSTEM... 4 Guiding Principles... 4 RISK GOVERNANCE... 5 Mandate and Commitment... 5

More information

INTERNATIONAL AUDITING PRACTICE STATEMENT 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS

INTERNATIONAL AUDITING PRACTICE STATEMENT 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS INTERNATIONAL AUDITING PRACTICE STATEMENT 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS (This Statement is effective) CONTENTS Paragraph Introduction... 1 12 Guidance

More information

28 July May October 2016

28 July May October 2016 Policy Name Risk Management Policy & Procedure Related Policies and Legislation AISWA Guidelines Risk Management Policy Category Planning & Management Relevant Audience Date of Issue / Last Revision All

More information

Group Financial Statements

Group Financial Statements Group Financial Statements Group Financial Statements 80 Statement of Directors Responsibilities 81 Independent Auditor s UK Report 87 Independent Auditor s US Report 88 Group Financial Statements 88 Group

More information

Learning Le cy Document

Learning Le cy Document PROGRAMME CONTROL Quantitative Risk Assessment Procedure Document Number: CR-XRL-Z9-GPD-CR001-50004 Document History: Revision Prepared Date: Author: Reviewed by: Approved by: Reason for Issue 1.0 15-06-2015

More information

risk management and assessment for business Risk Reduction Practical Solutions Egyptian Petroleum Ministry, Cairo, Egypt 14 th October 2014

risk management and assessment for business Risk Reduction Practical Solutions Egyptian Petroleum Ministry, Cairo, Egypt 14 th October 2014 Risktec Solutions risk management and assessment for business Risk Reduction Practical Solutions Egyptian Petroleum Ministry, Cairo, Egypt 14 th October 2014 Gareth Book, Director, Risktec Solutions Risk

More information

ISO INTERNATIONAL STANDARD. Lifts (elevators), escalators and moving walks Risk assessment and reduction methodology

ISO INTERNATIONAL STANDARD. Lifts (elevators), escalators and moving walks Risk assessment and reduction methodology INTERNATIONAL STANDARD ISO 14798 First edition 2009-03-01 Lifts (elevators), escalators and moving walks Risk assessment and reduction methodology Ascenseurs, escaliers mécaniques et trottoirs roulants

More information

CONTROLLED DOCUMENT. Version Number: 4.1. On: January 2018 Review Date: June 2016 Distribution: Essential Reading for: Information for: 1 of 15

CONTROLLED DOCUMENT. Version Number: 4.1. On: January 2018 Review Date: June 2016 Distribution: Essential Reading for: Information for: 1 of 15 Risk Management Strategy and Policy CONTROLLED DOCUMENT CATEGORY: CLASSIFICATION: PURPOSE: Controlled Number: Document Strategy/Policy Governance To set out the principles and framework for the management

More information

Auckland Transport HS03-01 Risk and Hazard Management

Auckland Transport HS03-01 Risk and Hazard Management Auckland Transport HS03-01 Risk and Hazard Management (Procedure uncontrolled when printing) Relating to Standard: HS03 Risk and Hazard Management Standard December 2016 Health and Safety-Procedure-HS03-01

More information

Risk Management Policy. September 2015

Risk Management Policy. September 2015 Risk Management Policy September 2015 Contents Policy Statement... 3 AA s Commitment to Risk Management... 3 Risk Management Principles... 4 Governance Framework... 6 Roles and Responsibilities... 7 Board...

More information

Risk Management Guideline

Risk Management Guideline Risk Management Guideline [Selected Pages] Version 1.1 (August 2012) 1 P a g e 1 Objective This Guideline outlines the processes used at Panoramic Resources Limited (Panoramic) to identify and manage risk

More information

PETROLEUM: Major accident prevention policy and safety case requirements

PETROLEUM: Major accident prevention policy and safety case requirements H E A LT H & S A F E T Y AT WO R K HSWA AC T INTERPRETIVE GUIDELINES PETROLEUM: Major accident prevention policy and safety case requirements These guidelines cover parts 3 and 4 of the Health and Safety

More information

Internal Audit Report

Internal Audit Report Internal Audit Report Community Infrastructure Levy (CIL) and Section 106 (S106) Phase I, Income, May 2017 To: Commissioning Director of Growth and Development, LBB Resources Director, LBB Commissioning

More information

APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY OF INTERNATIONAL MARITIME

APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY OF INTERNATIONAL MARITIME Journal of KONES Powertrain and Transport, Vol. 21, No. 4 2014 ISSN: 1231-4005 e-issn: 2354-0133 ICID: 1130510 DOI: 10.5604/12314005.1130510 APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK RISK MANAGEMENT FRAMEWORK Approving authority Approval date University Council 5 August 2013 (3/2013 meeting) Advisor Vice President (Corporate Services) vpcorporateservices@griffith.edu.au (07) 373 57343

More information

NATIONAL RISK MANAGEMENT SYSTEM

NATIONAL RISK MANAGEMENT SYSTEM Scouts Australia NATIONAL RISK MANAGEMENT SYSTEM 2003 First Published 2003 Reviewed August 2006 in consideration of AS/NZS 4360-2004 and Organisational Performance Since First Published. Amendment by Chair

More information

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com NEGOTIATION REVIEW Negotiating Risk By Roger Greenfield contact@thegappartnership.com thegappartnership.com Negotiating risk Risk: one of the most under valued variables available during contract negotiations.

More information

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION TO THE COMMISSION. Revision of the Internal Control Standards and Underlying Framework

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION TO THE COMMISSION. Revision of the Internal Control Standards and Underlying Framework COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 16 October 2007 SEC(2007)1341 EN COMMUNICATION TO THE COMMISSION Revision of the Internal Control Standards and Underlying Framework - Strengthening Control

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION FROM THE COMMISSION

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION FROM THE COMMISSION COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 7.1.2004 COM(2003) 830 final COMMUNICATION FROM THE COMMISSION on guidance to assist Member States in the implementation of the criteria listed in Annex

More information

Decommissioning Basis of Estimate Template

Decommissioning Basis of Estimate Template Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare

More information

DECISION ON RISK MANAGEMENT BY BANKS

DECISION ON RISK MANAGEMENT BY BANKS RS Official Gazette, Nos 45/2011, 94/2011, 119/2012, 123/2012, 23/2013 other decision I, 43/2013, 92/2013, 33/2015, 61/2015, 61/2016 and 103/2016 Pursuant to Article 28, paragraph 7, Article 30, paragraph

More information

Security Risk Management

Security Risk Management Security Risk Management Related Chapters Chapter 53: Risk Management Also Chapter 32 Security Metrics: An Introduction and Literature Review Chapter 62 Assessments and Audits 2 Definition of Risk According

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.6 INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES OCTOBER 2007 This document was prepared

More information

RISK MANAGEMENT MANUAL

RISK MANAGEMENT MANUAL ABN 70 074 661 457 RISK MAGEMENT MANUAL QUALITY ASSURANCE - ISO 9001 ENVIRONMENTAL MAGEMENT - ISO 14001 OCCUPATIOL HEALTH AND SAFETY - AS 4801 This is a Controlled Document if stamped CONTROLLED in RED.

More information

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0 UCISA TOOLKIT Major Project Governance Assessment version 1.0 Contents Introduction 1 Roles and responsibilities 2 Definition of a Major Project 3 Guidance for using the Toolkit 4 Governance elements 4

More information

CMP for Special Regs and Safety Issues. 1. INTRODUCTION Purpose Scope Submissions to Australian Sailing:...

CMP for Special Regs and Safety Issues. 1. INTRODUCTION Purpose Scope Submissions to Australian Sailing:... CMP Policy - AS i Australian Sailing CMP for Special Regs and Safety Issues 1. INTRODUCTION... 1 1.1. Purpose... 1 1.2. Scope... 1 1.3. Submissions to Australian Sailing:... 1 2. CHANGE MANAGEMENT PROCEDURE

More information

Enterprise Risk Management process at Dragon Oil

Enterprise Risk Management process at Dragon Oil Enterprise Risk Management Risk Management Process Dragon Oil s business is potentially exposed to different risks. However, some business risks can be accepted by the Group provided that acceptance of

More information

PRINCE2 Sample Papers

PRINCE2 Sample Papers PRINCE2 Sample Papers The Official PRINCE2 Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined

More information

Guide. Commission Recommendation

Guide. Commission Recommendation Guide to the Commission Recommendation on the management of financial resources for the decommissioning of nuclear installations, spent fuel and radioactive waste (2006/851/Euratom) 1 2 Objective of the

More information

Section Defining Risk Management. 11. Principles of Risk Management

Section Defining Risk Management. 11. Principles of Risk Management Section 2 10. Defining Risk Management Enterprise risk management is the process, affected by an entity's board of directors, management and other personnel, applied in strategy setting and across the

More information

Understanding Energy Contracts

Understanding Energy Contracts An Intensive 5 Day Training Course Understanding Energy Contracts 13-17 Aug 2018, London 06-NOV-17 This course is Designed, Developed, and will be Delivered under iso Quality standards Understanding Energy

More information

1.1. This document forms the Council s Risk Management Strategy. It sets out:

1.1. This document forms the Council s Risk Management Strategy. It sets out: 1. Introduction Bovey Tracey Town Council RISK MANAGEMENT STRATEGY 1.1. This document forms the Council s Risk Management Strategy. It sets out: - What is risk management - Why the Council needs a risk

More information

Proposal for a COUNCIL REGULATION. establishing an Instrument for Nuclear Safety Cooperation. {SEC(2011) 1472 final} {SEC(2011) 1473 final}

Proposal for a COUNCIL REGULATION. establishing an Instrument for Nuclear Safety Cooperation. {SEC(2011) 1472 final} {SEC(2011) 1473 final} EUROPEAN COMMISSION Brussels, 7.12.2011 COM(2011) 841 final 2011/0414 (NLE) Proposal for a COUNCIL REGULATION establishing an Instrument for Nuclear Safety Cooperation {SEC(2011) 1472 final} {SEC(2011)

More information

ANNEXES. Statement of the Resources Director. Legal_service_aar_2016_final Page 43 of 60

ANNEXES. Statement of the Resources Director. Legal_service_aar_2016_final Page 43 of 60 Ref. Ares(2017)1737664-31/03/2017 ANNEXES ANNEX 1: Statement of the Resources Director I declare that in accordance with the Commission s communication on clarification of the responsibilities of the key

More information

APPLICATION OF LOPA AND SIL ASSESSMENT TO A NEW COMAH PLANT

APPLICATION OF LOPA AND SIL ASSESSMENT TO A NEW COMAH PLANT APPLICATION OF LOPA AND ASSESSMENT TO A NEW COMAH PLANT Jerry Mullins Principal Consultant, Abbott Risk Consulting, Manchester, UK High hazard industries such as those regulated by COMAH face a number

More information

Demonstrating Continuous Risk Reduction

Demonstrating Continuous Risk Reduction Demonstrating Continuous Risk Reduction Alastair Bird 1, Angus Lyon 1, and Volton Edwards 2 1 DNV 2 bp Trinidad and Tobago Measurement of risk at large industrial sites has generally been achieved through

More information

Strategic flood risk management

Strategic flood risk management Report by the Comptroller and Auditor General Department for Environment, Food & Rural Affairs and Environment Agency Strategic flood risk management HC 780 SESSION 2014-15 5 NOVEMBER 2014 4 Key facts

More information

Risk Management Plan PURPOSE: SCOPE:

Risk Management Plan PURPOSE: SCOPE: Management Plan Authority Source: Vice-Chancellor Approval Date: 16/05/2018 Publication Date: 17/05/2018 Review Date: 17/05/2021 Effective Date: 16/05/2018 Custodian: General Counsel and University Secretary

More information

OHS RISK MANAGEMENT GUIDELINES

OHS RISK MANAGEMENT GUIDELINES OHS RISK MANAGEMENT GUIDELINES Contents 1 Introduction...2 2 Related UOW Documents...2 3 References and Applicable Legislation...2 4 Definitions...2 5 Responsibilities...3 5.1 Employees...3 5.2 Supervisors...3

More information

CITY OF JOHANNESBURG METROPOLITAN MUNICIPALITY GROUP RISK AND ASSURANCE SERVICES GROUP RISK MANAGEMENT POLICY

CITY OF JOHANNESBURG METROPOLITAN MUNICIPALITY GROUP RISK AND ASSURANCE SERVICES GROUP RISK MANAGEMENT POLICY CITY OF JOHANNESBURG METROPOLITAN MUNICIPALITY Effective Date 1 July 2015 TABLE OF CONTENTS 1. POLICY STATEMENT... 3 2. POLICY CONTEXT... 4 3. PURPOSE... 5 4. POLICY SCOPE AND APPLICATION... 6 5. RISK

More information