Case No. 52 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Mahati Hydro Power Projects Pvt. Ltd.

Size: px
Start display at page:

Download "Case No. 52 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Mahati Hydro Power Projects Pvt. Ltd."

Transcription

1 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai Tel /65/69 Fax Website: / www. merc.gov.in Case No. 52 of 2017 In the matter of Petition of Mahati Hydro Power Projects Pvt. Ltd. for reimbursement of evacuation arrangement costs of its Veer Small Hydro Project by Maharashtra State Electricity Transmission Co. Ltd. Coram Shri Azeez M. Khan, Member Shri Deepak Lad, Member Mahati Hydro Power Projects Pvt. Ltd. : Petitioner V/s Maharashtra State Electricity Transmission Co. Ltd. : Respondent No.1 Maharashtra Electricity Development Agency : Respondent No. 2 Appearance For the Petitioner For the Respondent No. 1 For the Respondent No. 2 For Authorized Consumer Representative Smt. Dipali Sheth (Adv.) Shri Abhijeet Joshi (Adv.) None Dr. Ashok Pendse, TBIA ORDER Dated: 10 April, 2018 Mahati Hydro Power Projects Pvt. Ltd ( Mahati ), 32-33, Shankarshet Road, Behind S.T. Workshop, Pune, has filed a Petition on 23 February, 2017 seeking payment by Maharashtra State Electricity Transmission Co. Ltd. (MSETCL) and Maharashtra Energy Development Agency (MEDA) of the balance amount of the expenditure incurred towards the evacuation arrangement beyond the inter-connection point. MERC Order in Case No. 52 of 2017 Page 1 of 13

2 2. Mahati s prayers are as follows: (a) Direct the Respondent No. 1 and/or Respondent No. 2 to pay Rs. 1,44,25,000/- (Rupees One Crore Forty Four Lacs and Twenty Five Thousand Only) towards the balance payment for construction / creation of the evacuation arrangement beyond the inter-connection point; (b) Direct the Respondent No. 1 and/or Respondent No. 2 to pay interest on the balance unpaid dues from their respective due dates as per the below table: Amount Rate of Interest Due from Status Rs. 28,85,000/- 18% p.a. May, 2013 Pending Till date Rs. 28,85,000/- 18% p.a. May, 2014 Pending Till date Rs. 28,85,000/- 18% p.a. May, 2015 Pending Till date Rs. 28,85,000/- 18% p.a. May, 2016 Pending Till date Rs. 28,85,000/- 18% p.a. May, 2017 Not Due (c) Direct Respondents to comply with the provisions of the GoM Policies, GOM Procedures July 14, 2010 and Order dated November 09, 2005 in letter and spirit; (d) Direct Respondent No. 1 and/or Respondent No. 2 to make timely payment of the installment due in May, 2017; (e) Direct Respondents to comply with the conditions agreed upon in the aforesaid MOU date October 8, 2013; (f) Direct Respondents to pay costs for the present Petition 3. The Petition states as follows: 3.1 Mahati is a Hydro Power Generating Company in Maharashtra incorporated under the provisions of the Companies Act, The Government of Maharashtra, Water Resources Department (GoMWRD) has issued a Policy dated 15 September, 2005 to encourage the development of Small Hydro Projects (SHPs) in Maharashtra through private participation on Build, Operate and Transfer (BOT) and Build, Own, Operate and Transfer (BOOT) basis. 3.3 Vide its Order dated 9 November, 2005 in Case No. 25 of 2004 ( 2005 SHP Order ), which was for determination of the Tariff for SHPs, the Commission has held that the MERC Order in Case No. 52 of 2017 Page 2 of 13

3 transmission costs shall be borne by the State Transmission Utility (STU) [which is MSETCL]. 3.4 Vide letter dated 17 July, 2007, GoMWRD allotted the development of the Power Plant at the Veer Left Bank Canal downstream of Veer Dam, Tehsil Purandhar, District Pune to Mahati, and the same was accepted on 9 August, Pursuant to the Government of Maharashtra (GoM) Policy on development of Non- Conventional Energy Sources dated 14 October, 2008 ( GoM Policy, 2008 ), Mahati developed the Power Plant at Veer, which was commissioned on 20 May, The GoM Policy, 2008 was amended vide GoM, Industries, Energy & Labour Department (IE&LD) s Resolution dated 3 August, 2009 ( GoM Policy, 2009 ). Section 1.1 of the GoM Policy, 2008 was amended to require Generators to sell 100% electricity generated through Non-Conventional Energy sources to Licensees or clients in Maharashtra to avail benefits under the GoM Policy, 2008: GoM Policy, If the Promoters / Developers / Investors wish to avail the benefits allowed under this policy then, it is obligatory for them to sell the 50% of electricity generated from the Projects commissioned under this policy to Maharashtra State Distribution Company Limited (MSEDCL) at the rate fixed up by MERC under a long term Power purchase / agreement. It shall be obligatory to sell the remaining 50% electricity within the state of Maharashtra only. Amendment made to Section 1.1 by GoM Policy, It shall be binding on Promoters/ Developers/ Investors to sell 100% Electricity generated through nonconventional energy Source to Licensee or Client in the State. 100% electricity generated from small hydro power project upto 25 MW under Irrigation Department is permitted to sell any licensee or a client. 3.7 GoMWRD issued Govt. Resolution No. HEP 1209(143/2009)/HP dated 31 October, 2009 ( GoMWRD GR 2009 ) providing for 100% sale of electricity generated through SHPs to be sold to consumers or Distribution Licensees in Maharashtra. 3.8 Pursuant to the GoM Policy, 2008, GoM issued further procedural directions on 14 July, 2010 ( GoM Procedures of 2010 ), which provided that 50% of the cost of evacuation arrangement is to be refunded by MEDA through the Green Energy Fund (GEF) and the balance cost is to be refunded by MSETCL to the Developer in 5 equal annual instalments starting from May, 2013, i.e. one year after commissioning of the Power Plant. MERC Order in Case No. 52 of 2017 Page 3 of 13

4 3.9 Vide Order dated 27 October, 2014 in Case No. 73 of 2014, the Commission held that there should not be any cap on the reimbursement of the cost of evacuation arrangement by MSETCL irrespective of Government Policies: Regulation 17.1 of the MERC (RPO-REC) Regulations, 2010, clearly stipulates the responsibility of the Distribution Licensee with regard to the evacuation arrangements. It also provides that the evacuation infrastructure cost beyond the inter-connection point is to be borne by the Licensee and recovered from the consumers through a suitable pricing framework developed by the Commission. This responsibility of the Licensee cannot be modified or capped by any contrary in IE&LD s Policy dated 14 July, 2010 or any other such instrumentality As per Regulation 17.1 of the MERC (Renewable Purchase Obligation (RPO), its Compliance and Implementation of REC Framework) Regulations ( RPO Regulations ), 2010, the Maharashtra State Electricity Distribution Co. Ltd. (MSEDCL) is required to bear the cost of evacuation arrangement, which is to be recovered from its consumers. The RPO Regulations, 2010 provide that the Licensees shall bear the costs of development of evacuation infrastructure beyond the inter-connection point. In the present matter, the evacuation infrastructure was developed beyond the inter-connection point by Mahati and was handed over to MSETCL after commissioning. Hence, the cost is to be reimbursed to Mahati as per the RPO Regulations, Vide letter dated 23 October, 2012, Mahati submitted a proposal for sale of electricity from its SHP at the Average Pooled Purchase Cost (APPC) rate under the Renewable Energy Certificate (REC) mechanism to MSEDCL. Vide its letter dated 20 November, 2012, MSEDCL accepted the proposal of Mahati, making it eligible for REC as specified in the RPO Regulations, Mahati confirmed its acceptance as per letter dated 6 December, It also entered into an Energy Purchase Agreement (EPA) for sale of energy generated from its SHP to MSEDCL at the APPC rate from the date of commissioning to 31 March, Clause 4 of the Memorandum of Understanding (MoU) dated 8 October, 2013 provided that the amount to be refunded for the evacuation arrangement would be the actual expenditure or the estimated cost as per MSETCL, whichever is lower. The estimated cost and the actual expenditure incurred for the evacuation infrastructure are as below: MSETCL Estimated cost Actual expenditure incurred by Mahati Rs Lakh Rs Lakh 3.13 Therefore, as per the MoU, MSETCL is liable to reimburse Rs. 1, 44, 25,000/- (i.e. the MSETCL estimated cost of Rs. 1,99,25,000 minus Rs. 55,00,000/- refunded by MEDA). The evacuation expenditure actually incurred by Mahati has not been considered as per the Commission s Order dated 9 November, 2005 in Case No. 25 of 2004 on the determination of SHP Tariff. Therefore, Mahati is entitled to MERC Order in Case No. 52 of 2017 Page 4 of 13

5 reimbursement of the evacuation arrangement costs from MSETCL as per that Order read with the Order in Case No. 73 of 2014 (cited above) and the GoM Policy, 2008 read with the GoM Policy, 2009 and the MoU The SHP is connected to the 132 kv Transmission Network of MSETCL, and the work of power evacuation arrangement was carried out by Mahati as per the terms and conditions of the GoM Policies and also the Connection Agreement/ Approval. Vide letter dated 19 June, 2013, Mahati submitted detailed Bill of Material with cost to MSETCL for verification and refund of the evacuation arrangement cost. After verification and audit by MSETCL s Executive Engineers/Superintending Engineers, it was sent to the Head Office of MSETCL. In response, MSETCL, vide letters dated 30 November, 2013 and 4 December, 2013 asked Mahati for various documents Vide letter dated 17 December, 2013, Mahati submitted the required documents and clarifications and requested reimbursement of the evacuation arrangement cost. As per the requirements for reimbursement of evacuation arrangements stated in the GoM Policy, 2008, Power Evacuation Certificates dated 11 March, 2014 and 3 December, 2016 were issued by the Maharashtra State Load Despatch Centre (MSLDC), which were also submitted to MSETCL vide letter dated 28 March, As per the permissions granted by MSEDCL from time to time, the energy generated by the SHP is sold to Licensee / consumer/client(s) only in Maharashtra for consumption through Distribution Open Access. The details of sale of energy in Maharashtra since commissioning are as below: PERIOD BUYER MODE May 20, 2012 to March, MSEDCL APPC basis April 01, 2013 to March 31, 2014 Mahindra Hinoday Open Access Industries, Bhosari, Pune April 01, 2014 to March 31, 2015 Taj Lands End, Mumbai Open Access April 01, 2015 to March 31, 2016 Taj Lands End, Mumbai Open Access April 01, 2016 to June 30, 2016 No Generation due to nonavailability - of water July 01, 2016 to March 31, 2017 Taj Lands End, Mumbai Open Access 3.17 The above details have already been indicated in the Power Evacuation Certificates dated 11 March, 2014 and 3 December, 2016 (upto July, 2016) issued by the Office of the Chief Engineer, MSLDC, Airoli, Navi Mumbai. MERC Order in Case No. 52 of 2017 Page 5 of 13

6 3.18 Vide letter dated 4 June, 2014, MSETCL stated that Mahati is not eligible for the refund of evacuation cost as : a) Power is sold to private consumers through Open Access, and b) Mahati does not have a long-term EPA with a Distribution Licensee MSETCL has completely misunderstood and misinterpreted the GoM Policy, 2008 and its amendment in As the conditions mentioned in MSETCL s letter dated 4 June, 2014 were incorrect, Mahati, vide its letters dated 21 June, 2014, 14 August and 2 November, 2015, 10 December, 2016 and 8 February, 2017, followed up and explained its eligibility for refund of the evacuation cost, and requested MSETCL to refund the amount incurred on the power evacuation arrangement Mahati successfully installed and commissioned the power evacuation infrastructure beyond the inter-connection point in accordance with the GoM Policies as per the requirements specified by MSETCL and under its supervision. The evacuation arrangement has been transferred to MSETCL vide MoU dated 8 October, The Power Evacuation Certificates issued by MSLDC on 11 March, 2014 and 3 December, 2016 show that, since commissioning of the SHP, Mahati has sold 100% energy to MSEDCL and private consumers only in the Maharashtra. Therefore, Mahati has duly fulfilled the condition of 100% sale of electricity in Maharashtra as stipulated in the GoM Policies for refund of evacuation cost Pursuant to commissioning of the SHP, on 8 October, 2013 MEDA has refunded Rs. 55 lakh towards evacuation cost through the GEF In accordance with the GoM Policies read with Order dated 27 October, 2014 in Case No. 73 of 2014 and the MoU of 8 October, 2013, MSETCL is liable to refund Rs. 1,44,25,000/- as the balance amount of Rs. 55,00,000/- has been refunded by MEDA. MSETCL is required to reimburse the remaining cost of the evacuation arrangement in five equal instalments from one year after commissioning of the SHP, i.e. from May, Accordingly, five instalments of Rs lakh each were payable by MSETCL and/or MEDA as follows: Sr. No. Amount/Rs. Due Date Status 1. 28,85,000 May 2013 Not paid 2. 28,85,000 May 2014 Not paid 3. 28,85,000 May 2015 Not paid 4. 28,85,000 May 2016 Not paid 5. 28,85,000 May In its Reply dated 6 July, 2017 (submitted at the time of the hearing), MSETCL has stated as follows: MERC Order in Case No. 52 of 2017 Page 6 of 13

7 4.1 MSETCL has not processed the refund request of Mahati as it has failed to submit a copy of its long-term EPA with a Distribution Licensee or any consumer to whom it is supplying power through Open Access. MSETCL has demanded a copy of the EPA as per its practice. 4.2 Para 3.71 of the Commission s SHP Tariff Order in Case No. 25 of 2004 states that the Order applies to the supply of electricity from SHPs to Distribution Licensees in Maharashtra. Also, para of the Order states that the EPA period for BOT for SHP shall be 30 years. However, the tariff shall be applicable for 20 years. 4.3 Regulation 11.2 of the RPO Regulations, 2010 requires that Captive Users and Open Access Consumers shall purchase Renewable Energy (RE) as stated in Regulation 7.1 and accordingly enter into long-term arrangement to meet their RPO. Mahati is a SHP and is supplying electricity through Open Access. Hence, according to Regulation 11.2, it must enter into a long-term EPA with its consumers. Hence, it can be inferred that an Obligated Entity under the RPO Regulations shall not avail RE without a long-term EPA. 4.4 Regulation 2.1 (ff) of the MERC (Terms and Conditions for Determination of RE Tariff) Regulations ( RE Tariff Regulations ), 2010 defines the useful life of the Mini/Micro Hydro and SHPs as 35 years. Regulation 6.2 also states that the tariff period for SHPs up to and including 5 MW shall be 35 years. 4.5 In view of the above provisions, it is the accepted practice of MSETCL to demand a longterm EPA. Accordingly, vide its letter dated 4 June, 2014, MSETCL had informed Mahati that, to be eligible for refund of evacuation charges, it must submit a long-term EPA with a Distribution Licensee in Maharashtra. 4.6 MSETCL has estimated Rs lakh as the cost for evacuation arrangement though the GR dated 14 July, 2010 [GoM Procedure of 2010] has capped it at Rs crore. However, the Commission, vide its Order dated 27 October, 2014 in Case No. 73 of 2014, has ruled that the responsibility of the Licensee for evacuation cannot be modified or capped by any contrary dispensation in IE&LD s Policy or any other such instrumentality. However, if the cap is removed, it will burden the end consumers. Even if the cap is removed and MSETCL s estimate in considered, the liability of MSETCL will be 50% and 50 % will be that of MEDA. 4.7 Mahati is not entitled to Rs lakh. The actual cost as per MBR to be refunded is Rs lakhs. Further, Rs lakh includes the cost of the metering arrangement, which is not part of the evacuation arrangement. Metering cost relates to the Distribution Licensee for the purpose of billing and must be excluded. 5. At the hearing held on 6 July, 2017: 5.1 Mahati reiterated the submissions in its Petition, and emphasized the following: MERC Order in Case No. 52 of 2017 Page 7 of 13

8 (i) Mahati has developed a 4.8 MW SHP at Veer, Tehsil: Purandhar, District, Pune commissioned on 20 May, (ii) The GoM Policy, 2008 was amended by the GoM Policy As per Section 1.1 of the amended Policy, the Generator has to sell 100% of electricity generated through non-conventional energy sources to a Licensee or client in Maharashtra State to avail its benefits. (iii) The GoM Procedures of 2010 for non-conventional Power Projects provide that 50% of the cost of power evacuation arrangement is to be refunded by MEDA from the GEF and the balance is to be refunded by MSETCL in 5 annual instalments starting from May, 2013, i.e. one year after commissioning of the Power Plant. (iv) Vide its Order dated 27 October, 2014 in Case No. 73 of 2014, the Commission has removed the cap on reimbursement of evacuation arrangement costs by MSETCL irrespective of Government Policies. (v) Clause 4 of the MoU dated 8 October, 2013 provides that the amount to be refunded for the evacuation arrangement would be the actual expenditure or MSETCL s estimated cost, whichever is lower. The estimated cost and actual expenditure incurred for creation of evacuation infrastructure are as below: MSETCL estimated cost - Rs lakh Actual expenditure incurred - Rs lakh (vi) MEDA has refunded Rs. 55 lakh towards evacuation cost through the GEF on 8 October, 2013 and the balance is awaited from MSETCL. (vii) Mahati has submitted the certifications issued by MSLDC on 11 March, 2014 and 3 December, 2016 stating that 100 % energy was sold in Maharashtra. Despite this, MSETCL has not refunded the balance amount incurred on power evacuation. (viii) Vide letter dated 4 June, 2014, MSETCL stated that Mahati is not eligible for the refund of evacuation cost as the power is sold to private consumers through Open Access and it does not have a long-term EPA with a Distribution Licensee. (ix) Mahati has submitted the Power Evacuation Certificates from MSLDC. It has sold the entire power in Maharashtra. As per GoM s Policy, the power can be sold to any consumer in Maharashtra and there is no need of a long-term EPA. Hence, Mahati is entitled to refund of the power evacuation cost. 5.2 MSTECL responded that: (i) MSETCL has not refunded the cost of power evacuation as Mahati has not supplied power to a Distribution Licensee through a long-term EPA. MERC Order in Case No. 52 of 2017 Page 8 of 13

9 (ii) The actual cost as per MBR is Rs lakhs. Hence, Mahati is entitled to refund of only Rs lakhs and not Rs lakhs as claimed. Further, the actual cost of Rs includes the cost of metering of Rs lakh, which is not part of the evacuation arrangement and is not required to be refunded. MSETCL will refund the balance amount. 5.3 To a query of the Commission regarding the requirement of a long-term EPA, MSETCL stated that all other SHPs have EPAs with Distribution Licensees except Mahati. 5.4 As regards subsidy from MEDA and GoM s Policies, the Commission observed that, in order to promote non-conventional and RE and considering its nature, it had held long back that it is the duty of the concerned Transmission/Distribution Licensee to make or pay for the evacuation arrangements. Hence, vide Order dated 27 October, 2014 in Case No. 73 of 2014, it has not agreed with the cap on reimbursement on the evacuation arrangement cost. It is up to Mahati and MSETCL to decide the scope of work of power evacuation for reimbursement purposes. Commission s Analysis and Ruling 6. The 4.8 MW SHP at Veer, District Pune was commissioned by Mahati in May, The power is being evacuated through MSETCL s 132 kv Transmission Network. The power evacuation arrangement was undertaken by Mahati considering the specifications of MSETCL. Clause 4 of the MoU between Mahati and MSETCL dated 8 October, 2013 regarding the transfer of power evacuation assets to MSETCL provides that the amount to be refunded for the evacuation arrangement would be the actual expenditure incurred by Mahati or MSETCL s estimated cost, whichever is lower. The estimated cost, the actual expenditure incurred on the evacuation infrastructure and the reimbursements made to Mahati are as follows: i. MSETCL s approved estimated cost: Rs lakh; ii. Actual cost as approved by MSETCL: Rs lakh; iii. Actual expenditure claimed to have been incurred by Mahati: Rs lakh; iv. Reimbursement by MEDA from GEF: Rs. 55 lakh; v. No reimbursement from MSETCL; 7. MSLDC s Power Evacuation Certificates (for the period upto July, 2016) stating that the entire energy generated from Mahati s SHP is sold in Maharashtra have been provided to MSETCL on 28 March, The details are summarized at para earlier in this Order. Mahati has also sold power to MSEDCL under a short-term EPA at the APPC rate. 8. MSETCL s contentions with regard to the remaining reimbursement of the expenses incurred by Mahati towards the power evacuation arrangements are as follows: MERC Order in Case No. 52 of 2017 Page 9 of 13

10 a. Mahati has not submitted any long-term EPA with a Distribution Licensee or a consumer to whom it is supplying power through Open Access. In support of this requirement, MSETCL has cited the Commission s SHP Order of 2005, the RPO Regulations, 2010, and its own Board Resolution and practice. b. GoM has capped the total cost of the evacuation arrangements at Rs crore for the purposes of reimbursement. However, vide its Order dated 27 October, 2014 in Case No. 73 of 2014, the Commission has removed this cap stating that evacuation arrangements are the responsibility of MSETCL/MSEDCL. The Commission s decision to remove the cap will burden the consumers. c. Even if the cap is removed, as per GoM s Policy, 50 % of the reimbursement of the cost is the liability of MEDA and MSEDCL s liability is limited to only the remaining 50 %. d. Mahati is not entitled to Rs. 224 lakh, which is the expenditure it claims to have incurred. The actual cost as assessed by MSETCL is Rs lakh (as per the corrected detailed statement on record in these proceedings). Moreover, this amount of Rs lakh includes Rs lakh (the lower of the MSETCL estimated and the actual cost) of metering arrangements, which cannot be considered as a part of the power evacuation arrangements. The metering cost relates to the Distribution Licensee for the purpose of billing and is, therefore, to be excluded. 9. The relevant Orders of the Commission and GoM s Policies regarding the evacuation of power from SHPs provide as follows: a) Clause 1.1 of the GoM Policy, 2008 (quoted at para. 3.6 above) provided that, for refund of the power evacuation arrangement cost, 50% of the electricity from the Project had to be sold to MSEDCL at the Commission-approved rate under a long-term EPA, and the remaining 50% to others within Maharashtra. After transfer of the evacuation infrastructure to MSEDCL or MSETCL, as the case may be, MEDA would refund 50% of the approved expenses on the evacuation arrangements to the Developer from the GEF. b) The 2008 Policy was amended in August, 2009 by the GoM Policy, 2009 to require only that the entire SHP generation be sold to Licensees and/or other clients within Maharashtra, and the percentage allocation between them was removed: 1.1 It shall be binding on Promoters/ Developers/ Investors to sell 100% Electricity generated through non-conventional energy source to Licensee or Client in the State. 100% electricity generated from small hydro power project upto 25 MW under Irrigation Department is permitted to sell any licensee or a client. MERC Order in Case No. 52 of 2017 Page 10 of 13

11 c) Thereafter, the GoM Procedures of 2010 (issued in July, 2010) stipulated that 50% of the cost of power evacuation from RE Projects be refunded by MEDA from the GEF to the Developer, and that the remaining amount be reimbursed by MSETCL in 5 equal annual instalments from the year following the commissioning of the Plant. d) The GoM Procedures of 2010 also provided that 100% of the electricity generated from non-conventional energy source would be sold to Distribution Licensees or other clients in the State; and stipulated that the Developer submit a copy of the EPA with the Licensee to MEDA. MSLDC certification regarding the sale of the generation in Maharashtra was to be furnished to MEDA annually. 10. a) As regards the responsibility of developing the evacuation infrastructure, the RE Tariff Regulations, 2010 provided as follows (and the provision in the subsequent Regulations of 2015 is similar): 17.1 The licensees shall be responsible for development of evacuation infrastructure beyond the inter-connection point while developer/generating company will have to develop evacuation infrastructure from generation facility up to the interconnection point at its own expense; Provided that, the evacuation infrastructure cost beyond the inter-connection point shall be borne by the licensees and shall be recovered from the consumers as per suitable pricing framework developed by the State Commission; b) The term inter-connection point was defined in both the RE Tariff Regulations, 2010 and the RPO Regulations, 2010 as follows: "Inter-connection Point" shall mean the interface point of renewable energy generating facility with the transmission system or distribution system, as the case may be: (ii) in relation to mini/micro hydro power, small hydro power, biomass power, non-fossil fuel based co-generation power projects and solar thermal power projects, the inter-connection point shall be line isolator on outgoing feeder on HV side of generator transformer. c) The subsequent RE Tariff Regulations, 2015 and RPO Regulations, 2016 also define inter-connection point similarly. d) Hence, the capital cost considered for the determination of generic tariffs in the RE Regulations do not include the capital cost for evacuation arrangements beyond the inter-connection point. MERC Order in Case No. 52 of 2017 Page 11 of 13

12 11. These regulatory provisions have their genesis in various Orders of the Commission providing the dispensation for different types of RE Projects issued more than a decade ago. In its 2005 SHP Order, the Commission had ruled as follows: Cost of Evacuation Facilities and Infrastructure 3.20 Thus with reference to the cost of evacuation facilities the Commission mandates that the Project holder shall bear the cost of switchyard and interconnection facilities at the site upto the point of energy metering at the project switchyard. The STU will bear the cost of transmission lines and associated facilities beyond the point of energy metering for the evacuation of power. The Project holder shall provide an interest free advance to the STU equivalent to 50% of the cost of works to be carried out by the STU for power evacuation purposes. In case there is more than one such Project holder sharing the evacuation facilities to be set up by the STU, the advance amount shall be shared amongst the holders in equal proportion. The STU shall refund this interest free advance to the holder(s) in five equal instalments, spread over a period of 5 years, commencing from one year after the date of commissioning of the project. Sale of Power 3.58 Generated electricity can be sold to any consumer located in the State of Maharashtra or any willing distribution licensee or any power trading company. There shall be no limitation on the supply of energy units by the Developer to the Distribution Licensees. However, Maharashtra State Electricity Distribution Company shall have the first right of refusal. Sale of power shall be in accordance with the Orders, Regulations and Directions of the Commission. 12. The Commission s long-standing dispensation, since its SHP Tariff Order of 2005 (quoted above) and in the RPO Regulations, 2010 and 2015, that the power evacuation infrastructure cost is to be borne by the concerned Licensee and that there is no ceiling on the reimbursement of such cost to the Developer was reiterated by the Commission in its Order dated 27 October, 2014 in Case No. 73 of 2014, among others: 15. Regulation 17.1 of the MERC (RPO-REC) Regulations, 2010, clearly stipulates the responsibility of the Distribution Licensee with regard to the evacuation arrangements. It also provides that the evacuation infrastructure cost beyond the inter-connection point is to be borne by the Licensee and recovered from the consumers through a suitable pricing framework developed by the Commission. This responsibility of the Licensee cannot be modified or capped by any contrary dispensation in IE&LD s Policy dated 14 July, 2010 or any other such instrumentality. 19. The Commission also notes that, as is clear from the foregoing, some provisions of IE&LD s Policy set out in GRs dated 14 October, 2008, 3 August, 2009 and 14 July, 2010 are contrary to the provisions of the Regulations and related Orders of the Commission. They are also contrary to the 2005 Policy of another arm of GoM itself, namely the Water Resources Department MERC Order in Case No. 52 of 2017 Page 12 of 13

13 13. As will be evident from the above, MSETCL s understanding that the Commission removed the ceiling of Rs crore on the total cost admissible for reimbursement for the first time vide its Order dated 27 October, 2014 is entirely incorrect. The Commission had never mandated such a ceiling. 14. The dispensations of the Commission as well as of GoM provide for sale of the entire electricity generated to Licensees or others in Maharashtra. There is no requirement that this must be on the basis of long-term EPAs. Whether or not transactions of a shorter period would qualify against the RPO targets of Licensees or other Obligated Entities under the RPO Regulations is a separate matter and has nothing to do with the reimbursement of the cost of evacuation arrangements. 15. The fact that MEDA has provided Rs. 55 lakh through the GEF but that amount is less than 50% of the cost is not relevant since, under the long-standing dispensation of the Commission, it is the responsibility of MSETCL to provide the evacuation arrangement or to reimburse its cost. 16. As regards the metering cost, it is to be borne by the Developer, as would be clear from the Commission s Open Access Regulations of 2005, 2014 and 2016 and other dispensations of the Commission. It is also clear from the EPA with MSEDCL. 17. In view of the foregoing, MSETCL shall reimburse Rs lakh (i.e. the approved cost of the evacuation arrangements (Rs lakh) minus the metering cost (Rs lakh) and minus Rs. 55 lakh provided by MEDA) to Mahati within 2 months, along with applicable interest from the date the respective instalments were due till the date of payment. MSETCL is entitled to the expenses incurred towards the evacuation arrangements through its Aggregate Revenue Requirement, but not to the interest amount arising from the delay in payment. The Petition of Mahati Hydro Power Projects Pvt. Ltd. in Case No. 52 of 2017 stands disposed of accordingly. Sd/- (Deepak Lad) Member Sd/- (Azeez M. Khan) Member MERC Order in Case No. 52 of 2017 Page 13 of 13

Case No. 125 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

Case No. 125 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

CASE NO. 55 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. M/s Shah Promoters and Developers

CASE NO. 55 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. M/s Shah Promoters and Developers Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 E-mail: mercindia@merc.gov.in Website:

More information

CASE NO. 142 of Suo moto proceeding in the matter of Show-Cause Notice issued in Order dated 8 February, 2017 in Case No. 89 of 2015.

CASE NO. 142 of Suo moto proceeding in the matter of Show-Cause Notice issued in Order dated 8 February, 2017 in Case No. 89 of 2015. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

CASE No. 113 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member

CASE No. 113 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION, ITS COMPLIANCE AND IMPLEMENTATION OF RENEWABLE ENERGY CERTIFICATE FRAMEWORK)

More information

CASE No. 103 of CASE No. 104 of 2016

CASE No. 103 of CASE No. 104 of 2016 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Case No. 1 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member

Case No. 1 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: mercindia@merc.gov.in Website:

More information

CASE No. 107 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana

CASE No. 107 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

CASE No. 105 of Coram Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Transmission Co. Ltd.

CASE No. 105 of Coram Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Transmission Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/ 65/ 69 Fax No. 022 22163976 Email: mercindia@merc.gov.in

More information

CASE No. 150 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Vidarbha Industries Power Limited ORDER

CASE No. 150 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Vidarbha Industries Power Limited ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

Case No. 27 of In the matter of

Case No. 27 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

CASE NO. 93 of Maharashtra State Electricity Distribution Co.Ltd. Maharashtra Energy Development Agency

CASE NO. 93 of Maharashtra State Electricity Distribution Co.Ltd. Maharashtra Energy Development Agency Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Proposal of Government of Maharashtra Consultant s detailed note on Power Purchase Rate etc. of Small Hydro Power Projects Abbreviations BEST BOT CERC CPP

More information

Case No. 134 of CORAM Smt. Chandra Iyengar, Chairperson Shri. Azeez M. Khan, Member Shri. Deepak J. Lad, Member

Case No. 134 of CORAM Smt. Chandra Iyengar, Chairperson Shri. Azeez M. Khan, Member Shri. Deepak J. Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

CASE No. 48 of In the matter of Appointment of Committee for study of subsidy, and related matters.

CASE No. 48 of In the matter of Appointment of Committee for study of subsidy, and related matters. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.com

More information

Chhattisgarh State Electricity Regulatory Commission

Chhattisgarh State Electricity Regulatory Commission Øekad 62] jk;iqj]] 'kqøokj] fnukad 4 ekpz 2011 & QkYxqu 13] 'kd 1932 Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur Raipur, Dated March 04, 2011 No. 36/CSERC/2011

More information

Shri Azeez M. Khan, Member Shri Deepak Lad, Member. The Tata Power Company Ltd. Maharashtra State Electricity Distribution Co. Ltd.

Shri Azeez M. Khan, Member Shri Deepak Lad, Member. The Tata Power Company Ltd. Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

Case No. 24 of In the matter of Application of Reliance Infrastructure Ltd. for Amendment of Transmission Licence No.

Case No. 24 of In the matter of Application of Reliance Infrastructure Ltd. for Amendment of Transmission Licence No. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

CASE No. 73 of hours for a period of six months from 1 April, 2019 to 30 September, Coram. I. M. Bohari, Member Mukesh Khullar, Member

CASE No. 73 of hours for a period of six months from 1 April, 2019 to 30 September, Coram. I. M. Bohari, Member Mukesh Khullar, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

CASE No. 2 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana

CASE No. 2 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Case No. 56 of In the matter of Compliance of directives issued to MSEDCL under Order dated May 17, 2007 passed in Case No. 82 of 2006.

Case No. 56 of In the matter of Compliance of directives issued to MSEDCL under Order dated May 17, 2007 passed in Case No. 82 of 2006. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964-65-69 Fax 22163976 Email: mercindia@mercindia.org.in Website:

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017 ELECTRICITY ACT, 2003 No. MERC/Legal/2017/1771 - In exercise of

More information

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL)

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) REVISED PETITION FOR APPROVAL OF TRUE UP OF FY 2015-16 & FY 2016 17 AND PROVISIONAL TRUE UP of FY 2017-18

More information

TRANSMISSION LICENCE NO. 1 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

TRANSMISSION LICENCE NO. 1 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Case No. 61 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 61 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

Case No. 129 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 129 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

Case No. 113 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 113 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

Case No. 52 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 52 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

CASE No. 162 of In the matter of

CASE No. 162 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

MERC (MULTI YEAR TARIFF) (FIRST AMENDMENT) REGULATIONS, 2017 STATEMENT OF REASONS

MERC (MULTI YEAR TARIFF) (FIRST AMENDMENT) REGULATIONS, 2017 STATEMENT OF REASONS MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Websites: www.mercindia.org.in

More information

Case No. 101 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. Mukesh Khullar, Member

Case No. 101 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. Mukesh Khullar, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

CASE No. 28 of Dr Pramod Deo, Chairman Shri A. Velayutham, Member ORDER

CASE No. 28 of Dr Pramod Deo, Chairman Shri A. Velayutham, Member ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005. Tel. 22163964 / 22163965, Fax No. 22163976 E-mail mercindia@mercindia.com

More information

CASE No. 121 of and. M. A. No. 11 of 2015

CASE No. 121 of and. M. A. No. 11 of 2015 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Case No. 47 of In the matter of

Case No. 47 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax. 022 221639761 E-mail: mercindia@merc.gov.in

More information

1.1 These regulations shall extend to whole of the State of Punjab.

1.1 These regulations shall extend to whole of the State of Punjab. THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION The, 2018 No.PSERC/Secy/Regu. - In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

Grievance No. K/E/953/1159/ ID No

Grievance No. K/E/953/1159/ ID No Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph 2210707, Fax 2210707, E-mail : cgrfkalyan@mahadiscom.in No.EE/CGRF/Kalyan Zone/ Date

More information

Case No. 170 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. I.M. Bohari, Member Shri Mukesh Khullar, Member ORDER

Case No. 170 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. I.M. Bohari, Member Shri Mukesh Khullar, Member ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre No. 1, 13 th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E mail: mercindia@merc.gov.in Website:

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Case No. 30 of In the matter of Petition filed by MSETCL for approval of SLDC Budget for FY and FY

Case No. 30 of In the matter of Petition filed by MSETCL for approval of SLDC Budget for FY and FY Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website: www.mercindia.org.in;

More information

Case Nos. 157, 166 of 2016 and Case No 18 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. CASE No.

Case Nos. 157, 166 of 2016 and Case No 18 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. CASE No. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY No. 419 9 Shrawan, 1932(s) Ranchi, Saturday 31th July, 2010 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION, RANCHI (RENEWABLE PURCHASE OBLIGATION

More information

CASE No. 186 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. M/s Global Energy Pvt. Ltd. Tata Power Company Ltd.

CASE No. 186 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. M/s Global Energy Pvt. Ltd. Tata Power Company Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION No. / /2017/MPERC.- In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other powers enabling

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010 UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION No. UPERC/Secy/Regulation/10-787 Lucknow : Dated, 17 th August, 2010 In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity

More information

BIHAR ELECTRICITY REGULATORY COMMISSION

BIHAR ELECTRICITY REGULATORY COMMISSION BIHAR ELECTRICITY REGULATORY COMMISSION Bihar Electricity Regulatory Commission (Renewable Purchase Obligation, its Compliance and REC Framework Implementation) Regulations, 2010. NOTIFICATION The 16 th

More information

Vidarbha Industries Power Limited - Transmission

Vidarbha Industries Power Limited - Transmission Vidarbha Industries Power Limited - Transmission Revised Petition towards: Approval of Capital Cost and Determination of Aggregate Revenue Requirement ( ARR ) for the period FY 14-15 to FY 15-16 Filed

More information

GOVERNMENT OF KERALA

GOVERNMENT OF KERALA 183 GOVERNMENT OF KERALA Kerala Small Hydro Power Policy 2012 1. Order G.O.(P) 25/2012/PD Dated: Thiruvananthapuram, 03.10.2012 2. Title Kerala Small Hydro Power Policy 2012 3. Objective To increase the

More information

The Chief Engineer Maharashtra State Load Despatch Center Phone Fax Executive Summary MSLDC s Budget

The Chief Engineer Maharashtra State Load Despatch Center Phone Fax Executive Summary MSLDC s Budget Office of The Chief Engineer Maharashtra State Load Despatch Center Thane Belapur Road, Airoli, Navi Mumbai 400 708 (INDIA) (ISO 9001 2000 certified unit of Mahatransco) Phone (022) (O) 2760 1931 (P) 2760

More information

TRANSMISSION LICENCE NO. 2 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

TRANSMISSION LICENCE NO. 2 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission Notification no. UPERC / Secy / CNCE Regulation, 2009/ 696 Dated: 22.3.2010 In exercise of powers conferred under section 181 read with section 9, 61, 86

More information

CASE No. 159 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member

CASE No. 159 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

RfS & Rs with compare to other states, there is no such charge

RfS & Rs with compare to other states, there is no such charge Replies to Queries of 1000 MW Solar Power Tender discussed during Pre-Bid Meeting on 19.12.2018 Sl. No. Clause No. Existing Clause Bidders' Query MSEDCL's Reply 1 Bid information sheet 2 Clause 1.2.2 of

More information

Case No. 3 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member. Reliance Infrastructure Ltd.

Case No. 3 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member. Reliance Infrastructure Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/ 65/ 69 Fax 022 22163976 Email: mercindia@mercindia.org.in

More information

BEFORE THE ELECTRICITY OMBUDSMAN (Appointed by the Maharashtra Electricity Regulatory Commission under Section 42(6) of the Electricity Act, 2003)

BEFORE THE ELECTRICITY OMBUDSMAN (Appointed by the Maharashtra Electricity Regulatory Commission under Section 42(6) of the Electricity Act, 2003) BEFORE THE ELECTRICITY OMBUDSMAN (Appointed by the Maharashtra Electricity Regulatory Commission under Section 42(6) of the Electricity Act, 2003) 606, KESHAVA, Bandra Kurla Complex, Bandra (East), Mumbai

More information

Case No. 206 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Company Limited

Case No. 206 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Company Limited Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

CHAPTER I: PRELIMINARY Short title, commencement and interpretation

CHAPTER I: PRELIMINARY Short title, commencement and interpretation Notification dated 20.2.2009 Bhopal: dated 31 st January, 2009 No. 254-MPERC-2009. In exercise of the powers conferred by Section 181 read with Subsection (b) of Section 86 of the Electricity Act 2003

More information

Case No. 86 of In the matter of

Case No. 86 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Bhopal: Dated 5 th May 2006

Bhopal: Dated 5 th May 2006 Bhopal: Dated 5 th May 2006 No. 1192/MPERC/2006. In exercise of the powers conferred by section 181 (g) read with section 32(3) of the Electricity Act, 2003 enacted by the parliament, the Madhya Pradesh

More information

Implementation of Solar Based Projects in MP Dated 20 July, 2012

Implementation of Solar Based Projects in MP Dated 20 July, 2012 86 Compendium of Policies, Regulations, Technical Standards & Financing Norms for Solar Power Projects GOVERNMENT OF MADHYA PRADESH Implementation of Solar Based Projects in MP Dated 20 July, 2012 1. Title

More information

Before the. Case No. 75 of 2007

Before the. Case No. 75 of 2007 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail: mercindia@mercindia.org.in

More information

New and Renewable Energy Department Vallabh Bhavan, Bhopal

New and Renewable Energy Department Vallabh Bhavan, Bhopal New and Renewable Energy Department Vallabh Bhavan, Bhopal English Translation of Policy for implementation of Small Hydel-Power based Electricity Projects in Madhya Pradesh, 2011 (As Amended on 15th February

More information

Case No. 67 of Dr. Pramod Deo, Chairman Shri A. Velayutham, Member Shri S. B. Kulkarni, Member O R D E R

Case No. 67 of Dr. Pramod Deo, Chairman Shri A. Velayutham, Member Shri S. B. Kulkarni, Member O R D E R Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in Case No.

More information

Case No. 38 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member

Case No. 38 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in/mercindia@merc.gov.in

More information

1 Grievance No. K/E/847/1035 of & No. K/E/848/1036 of

1 Grievance No. K/E/847/1035 of & No. K/E/848/1036 of 1 Grievance No. K/E/847/1035 of 2014-15 & Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph 2210707, Fax 2210707, E-mail : cgrfkalyan@mahadiscom.in

More information

Case No. 62 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 62 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Executive Summary of Tata Power Generation True up Petition for FY as well as MYT Petition for FY to FY

Executive Summary of Tata Power Generation True up Petition for FY as well as MYT Petition for FY to FY Executive Summary of Tata Power Generation True up Petition for FY 2011-12 as well as MYT Petition for FY 2012-13 to FY 2015-16 Tata Power G Page 1 TABLE OF CONTENTS TABLE OF CONTENTS... 2 LIST OF TABLES...

More information

NOTIFICATION. No.HPERC/dis/479: Shimla the 30 th March, 2012

NOTIFICATION. No.HPERC/dis/479: Shimla the 30 th March, 2012 HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA NOTIFICATION No.HPERC/dis/479: Shimla the 30 th March, 2012 WHEREAS the Distribution Licensee incurs an extra power purchase cost vis-a- vis the

More information

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No.

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No. 2 EXECUTIVE SUMMARY The Tata Power Company Limited ( Tata Power ) is a company established in 1919. On April 1, 2000, The Tata Hydro-Electric Power Supply Company Limited (established in 1910) and The

More information

M.P. Electricity Regulatory Commission Bhopal

M.P. Electricity Regulatory Commission Bhopal SMP-20/2010 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Wind Electric Generators 1. LEGISLATIVE PROVISIONS 1.1 Section 86(1) (e) of the Electricity Act 2003

More information

Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018

Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018 Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018 S No. Existing provision/ Draft amended proposed Modified proposed

More information

BIHAR ELECTRICITY REGULATORY COMMISSION PATNA

BIHAR ELECTRICITY REGULATORY COMMISSION PATNA BIHAR ELECTRICITY REGULATORY COMMISSION PATNA NOTIFICATION 2 nd August, 2010 No. BERC-Regl/Solar-2/2010-03 In exercise of powers conferred under Section 61 read with Section 181(2)(zd) of the Electricity

More information

Case No. 56 of In the matter of

Case No. 56 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964/ 65/ 69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Power Purchase Obligation (Compliance by purchase of Renewable Energy/Renewable Energy Certificates) Regulations, 2012 (Regulation No. 1 of 2012).

Power Purchase Obligation (Compliance by purchase of Renewable Energy/Renewable Energy Certificates) Regulations, 2012 (Regulation No. 1 of 2012). ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION RENEWABLE POWER PURCHASE OBLIGATION (COMPLIANCE BY PURCHASE OF RENEWABLE ENERGY/RENEWABLE ENERGY CERTIFICATES) REGULATIONS, 2012 Regulation No. 1 of 2012

More information

Sub: In the matter of petition for non-compliance of solar RPO by obligated entities for FY to FY

Sub: In the matter of petition for non-compliance of solar RPO by obligated entities for FY to FY ORDER (Date of hearing: 14 th October,2014) (Date of order: 20 th October,2014) M/s Green Energy Association, - Petitioner Sargam,143,Taqdir Terrace, Near Shirodkar High School, Dr. E. Borjes Road, Parel(E),

More information

In the matter of Retrospective Recovery regarding IT/ITES Consumer

In the matter of Retrospective Recovery regarding IT/ITES Consumer .(A Govt. of Maharashtra Undertaking) CIN: U40109MH2005SGC153645 PHONE NO. : 25664314/25664316 Consumer Grievance Redressal Forum FAX NO. 26470953 Vidyut Bhavan, Gr. Floor, Email: cgrfbhandupz@gmail.com

More information

SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal

SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Municipal Solid Waste based power generating plants in Madhya Pradesh June 2016 1. LEGISLATIVE PROVISIONS

More information

Case No. 26 of Shri. V. P. Raja, Chairman Shri. S. B. Kulkarni, Member

Case No. 26 of Shri. V. P. Raja, Chairman Shri. S. B. Kulkarni, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

BRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST)

BRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST) BRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST) EXECUTIVE SUMMARY OF Annual Performance Review for FY 2008-09 & ARR for FY 2009-10 along with Truing Up of Accounts for FY 2007-08 TO Maharashtra

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM RP 6/2017 In the matter of : Review petition filed by M/s Kanan Devan Hill Plantations Company Private Limited (KDHPCL) seeking review

More information

2. APPLICABILITY AND SCOPE

2. APPLICABILITY AND SCOPE ANNEXURE- I MODEL PROCEDURE / GUIDELINES FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT OR DISTRIBUTION LICENSEE, AS THE CASE MAY BE, UNDER REC MECHANISM BY STATE AGENCY 1. OBJECTIVE 1.1. This

More information

Bhopal, Dated:

Bhopal, Dated: Bhopal, Dated: 08.12.2015 No. /MPERC /2015 - In exercise of powers conferred under sub-section zp of Section 181 of the Electricity Act, 2003 (36 of 2003), and all other powers enabling it in this behalf,

More information

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. (Date of Order: )

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. (Date of Order: ) HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA IN THE MATTER OF:- (Date of Order: 25.07.2018) Petition No.: 26/2018(Suo-Moto) CORAM Sh. S.K.B.S. Negi Chairman Sh. Bhanu Pratap Singh Member

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 and all powers enabling it in this behalf, the Uttar Pradesh Electricity

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964/ 65/ 69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) Ph: & Ext: - 122

Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree, Jahangir Meherwanji Road, Kalyan (West) Ph: & Ext: - 122 Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph: 2210707 & 2328283 Ext: - 122 IN THE MATTER OF GRIEVANCE NO. K/ E/237/262 OF 2009-2010

More information

Petition No. 975 of 2014 and 1017 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Date of Order:

Petition No. 975 of 2014 and 1017 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Date of Order: Petition No. 975 of 2014 and 1017 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order: 27.11.2015 IN THE MATTER OF: AND IN THE MATTER OF M/s Lalitpur Power Generation

More information

EXTRA ORDINARY 13 SHRAVANA (S) BIHAR ELECTRICITY REGULATORY COMMISSION

EXTRA ORDINARY 13 SHRAVANA (S) BIHAR ELECTRICITY REGULATORY COMMISSION REGISTERED NO. PT.-40 The B Bihar Gazett te EXTRA ORDINARY PUBLISHED BY AUTHORITY 13 SHRAVANA (S) (NO.PATNA 541) PATNA, WEDNESDAY, 4TH AUGUST 2010 BIHAR ELECTRICITY REGULATORY COMMISSION NOTIFICATION The

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : /

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : / CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi 110 001 : 011-23353503/23752958 Public Notice No. : L-1/94/CERC/2011 Dated: 26 th June, 2015

More information

ORDER. Case No. 112 of 2008

ORDER. Case No. 112 of 2008 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022-22163964/6569 Fax 022-22163976 Email: mercindia@mercindia.org.in

More information

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT Energy Department Government of Bihar 2012 ( 1 ) Table of Content 1. Objective 2. Title and Enforcement 3. Scope and Coverage 4. Nodal Agency 5. Classification

More information

CONSUMER GRIEVANCE REDRESSAL FORUM KOLHAPUR

CONSUMER GRIEVANCE REDRESSAL FORUM KOLHAPUR CONSUMER GRIEVANCE REDRESSAL FORUM KOLHAPUR Phones : 0231-2666001 & Kolhapur Zone, 2666002 Vidyut Bhavan, 2 nd floor, Fax No. 0231-2666001 Tarabai Park, Kolhapur 416 003. e-mail-cgrfkolhapur@mahadiscom.in

More information

[ADJUDICATION ORDER NO. PKB/AO 37/2011]

[ADJUDICATION ORDER NO. PKB/AO 37/2011] BEFORE THE ADJUDICATING OFFICER SECURITIES AND EXCHANGE BOARD OF INDIA [ADJUDICATION ORDER NO. PKB/AO 37/2011] UNDER SECTION 15-I OF SECURITIES AND EXCHANGE BOARD OF INDIA ACT, 1992 READ WITH RULE 5 OF

More information

Jammu and Kashmir State Electricity Regulatory Commission (J&K SERC) (Security Deposit) Regulation, 2008.

Jammu and Kashmir State Electricity Regulatory Commission (J&K SERC) (Security Deposit) Regulation, 2008. Jammu and Kashmir State Electricity Regulatory Commission (J&K SERC) (Security Deposit) Regulation, 2008. Notification No. 9 of 2008. In exercise of the power conferred under section 17(2) (f) of the J&K

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION (DRAFT)

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION (DRAFT) CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI New Delhi, the 20 th of June 2013 NOTIFICATION (DRAFT) No.L-1/132/2013/CERC.- In exercise of the powers conferred under Section 178 of the Electricity

More information

2. APPLICABILITY AND SCOPE

2. APPLICABILITY AND SCOPE ANNEXURE- I MODEL PROCEDURE / GUIDELINES FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT OR DISTRIBUTION LICENSEE, AS THE CASE MAY BE, UNDER REC MECHANISM BY STATE AGENCY 1. OBJECTIVE 1.1. This

More information