HKIS QSD PQSL Series Payment Valuation and Post-Contract Cost Monitoring

Size: px
Start display at page:

Download "HKIS QSD PQSL Series Payment Valuation and Post-Contract Cost Monitoring"

Transcription

1 HKIS QSD PQSL Series 2013 Payment Valuation and Post-Contract Cost Monitoring by Kenneth Poon FHKIS; FRICS; RPS Global Construction Consultants

2 Payment Valuation 1. Introduction Payment to contractors under most standard forms of construction contracts are normally under interim payments either based on monthly intervals or milestones (exceptions are contracts under PPP or PFI arrangement) Interim payments are vital for the cash flow of Contractors. Accurate assessments are therefore very important. Delay in payment will also amount to a fundamental breach of contract on the part of the Employer

3 Payment Valuation (Cont d) 2. Headings of Payment The normal headings of payment would be : a) Preliminaries incurred b) Works done c) Variations done d) Works carried out by NSC or NS e) Materials delivered on site and not yet installed f) Materials delivered off site (if allowed) g) Fluctuations to date (if allowed) h) Assessed loss and expenses claim

4 Payment Valuation (Cont d) 2. Headings of Payment (Cont d) Deductions shall be made for the following items : a) Retention b) Ascertained defective works to be rectified c) Contra-charges for works done by others on behalf of contractor d) Liquidated Damages to date (if any)

5 Payment Valuation (Cont d) 3. Carrying Out the Valuation (under the New Standard Form of Building Contract 2005) Contractor to submit an application to the Q.S. not less than 14 days before date on which the Interim Certificate is due to be issued (clause 32.1 (4)) Q.S. to make an interim valuation of the work in progress and submit his valuation to the Architect not less than 7 days before the Interim Certificate is due to be issued (clause 32.1 (5)) Note that the Q.S. will normally have only 7 days to do his valuation

6 Payment Valuation (Cont d) 4. Site Visits The contract requires the Q.S. to allow the Contractor to have the chance to be present when doing any site measurements and assessments Joint site visits with the Contractor for interim payment valuations are therefore necessary when work-in-progress is inspected Progress of work on site as seen on the date of valuation should be properly recorded. Any measurements taken jointly with the Contractor should be initiated by both parties

7 Payment Valuation (Cont d) 5. Valuation of Preliminaries Amounts for preliminaries items would normally be broken down into 3 categories according to the nature of the item : 1) Installation cost 2) Running/Maintenance cost 3) Removal cost The breakdown of each item can be discussed and agreed with the contractor at the start of the project.

8 Payment Valuation (Cont d) 5. Valuation of Preliminaries (Cont d) When there are signs that the construction period might be prolonged, suitable adjustments to the valuation method must be made as soon as possible to maintain a fair valuation of the cost that should be paid

9 Payment Valuation (Cont d) 6. Valuation of Materials on Site Materials on Site are valued by visual inspection and physical counting or measurements on site. When carrying out such valuations, the following points should be observed : 1) Do not blindly adopt the material prices given in the material invoices. Compare the price against the B.Q. rate and if it is disproportionately high, make suitable adjustments to avoid over-payment. 2) When using delivery notes to ascertain the quantities in lieu of detailed physical counting/measurement, remember to deduct the quantities already installed (plus wastage) and paid for under works done.

10 Payment Valuation (Cont d) 6. Valuation of Materials on Site (Cont d) 3) Compare the quantities on site against the quantities required for the to-be-completed works. 4) Do not bring forward materials on site assessed in previous payments to the new payment. The materials on site assessment for every payment valuation must be done from scratch every time. 5) Note that materials means materials to be incorporated into the permanent works. Plant and materials for temporary works are therefore not included. In such case, timber for formwork cannot be calculated as materials on site.

11 Payment Valuation (Cont d) 7. Payments to Nominated Sub-Contractors (NSC) and Nominated Suppliers (NS) Payments to NSC and NS should be carried out in the same manner as that for the Main Contract works The Q.S. should notify the NSC/NS on the amounts due to them (if any) in each Interim Valuation Payment issued. The NSC/NS can request the Employer to pay direct if they do not receive the payment from the Main Contractor Alternatively, the Q.S. can request the Main Contractor to give documentary proof that he has paid the NSC/NS according to the Interim Payment Certificates

12 Payment Valuation (Cont d) 8. Other Points The following points would be worth noticing : If a Contractor fail to submit their performance bond, the Employer may deduct the full bond amount (not the cost to provide the bond) from the interim payment valuations until such bond is provided The SFBC does not explicitly state that the contractor s submission of an application is a pre-requisite condition for issue of interim payment. The Q.S. should therefore prepare his interim payment valuation not withstanding whether an application is received or not

13 Payment Valuation (Cont d) 8. Other Points (Cont d) The Contractor s entitlement to assessed loss and expenses is not subject to retention (clause 32.4 (a)) After the Works are substantially completed, interim certificates shall only be issued when further amounts are, in the Q.S. opinion, due to the Contractor (clause 32.1 (3)) If the project is not completed by the Date or Extended Date for completion, liquidated and Ascertained Damages (LAD) may be offset from the valuation amount provided certain requirements have been complied (e.g. the Architect has issued the Failure to complete certificate). If LAD is not offset, a remark reserving the right to do so later should be expressly made

14 Post Contract Cost Monitoring 1. Introduction There are 3 main factors that may affect the total cost of a construction project during the post-contract stage : Design changes variations to the design, quality or quantity of the works; Supplementary information design of portions of the works that were not yet designed/completed; additional detailing of already designed works etc. External factors inflation, new government regulations, adverse weather, accidents etc.

15 Post Contract Cost Monitoring (Cont d) 2. Financial Statements One of the prime responsibilities of a Q.S. is to track down the cost of a construction project and to raise alarms when there may be potential budget over-runs The Financial Statements is the tool for the Q.S. to keep tracle of the continuously changing total cost of the project. Financial statements should therefore be continuously update notwithstanding whether the Employer requires it to be submitted or not

16 Post Contract Cost Monitoring (Cont d) 2. Financial Statements (Cont d) Financial Statements will normally have the following headings : 1) Provisional Sum for Contingencies. This is the built-in buffer for expenses to be spent in the construction stage. 2) Adjustment of Prime Cost Sums. A summary of the cost implication of NSC, NS and Direct Contractors. 3) Adjustment of Provisional Quantities, Provisional Sums and P.C. Rates. Preliminary assessment of the Supplementary information mentioned above.

17 Post Contract Cost Monitoring (Cont d) 2. Financial Statements (Cont d) 4) Variations. Preliminary assessments of Architect s instructions, site instructions etc. design changes. 5) Confirmation of Verbal Instruction (CVIs). Normally will become valid instructions if not rejected by the Architect within 7 days. Some Contracts have deleted such automatic validation. However, these should still be accounted for as the Architect can always confirm them at a later date. 6) Contractor s loss and expenses claims. Preliminary assessments of submitted or to-be-submitted claims that are known to the Q.S.

18 Post Contract Cost Monitoring (Cont d) 2. Financial Statements (Cont d) 7) Fluctuations. Assessment of the total fluctuations reimbursement to be paid under the contract (not only the fluctuations up to date). 8) Allowance for future variations. This is the most difficult part in the preparation of the Financial Statements to assess the quantum of future design changes that are being discussed but not yet confirmed close communication should be maintained with the Architect and the Project Manager to establish an accurate figure for this item.

19 Post Contract Cost Monitoring (Cont d) 3. Other Controls One of the most recent controls with an aim to enhance postcontract cost control is the use of Architect Instruction Preapprovals (A.I.P.). It normally works as follows : 1) When the Architect wants to issue an instruction, he will first submit an A.I. Request together with the intended scope and drawings. 2) The Q.S. shall, within 5-7 days, carry out a preliminary estimate of the financial effect of the instruction and report to the Project Manager. 3) The Project Manager shall consider and if satisfied, will approve the Architect to issue the instruction or reject his request.

20 Post Contract Cost Monitoring (Cont d) 3. Other Controls (Cont d) Note the following : The A.I.P. system is a pro-active manner to control the cost of a construction project and should be given its merits However, as there is no demarcation between (1) design changes changes which the Architect can control; and (2) supplementary information changes which the Architect has less control, the number of A.I.P.s become enormously large, making the system difficult to keep up with the works on site

21 Post Contract Cost Monitoring (Cont d) 3. Other Controls (Cont d) Note the following : The Q.S., in order to keep up with the pace of A.I.P.s, must develop skills to carry out preliminary assessments of instructions in the A.I.P. stage (just like preliminary cost estimates vs priced bills of quantities). Such skills are also required if we are to keep our Financial Statements always up to date

22 Post Contract Cost Monitoring (Cont d) 4. When to do A.I. Assessment and Re-measurements for the Final Account? The figures in the Financial Statements are preliminary assessments done within short periods of time Such figures should be replaced by accurate figures based on detail assessment and measurements as soon as possible after the instructions/supplementary information are issued

23 Post Contract Cost Monitoring (Cont d) A.I. Assessments Early assessment of A.I.s have the following advantages : 1) A lot of A.I.s do not contain the full information. Early assessment will allow the Q.S. to clarify the actual extent of work involved, making it easier to agree with the Contractor on its value 2) Early agreement would make the Financial Statement more accurate for its purpose

24 Post Contract Cost Monitoring (Cont d) Remeasurement Provisional Quantities/Sums should be remeasured once the first set of construction drawings are made available Do not wait for the construction works to be completed, trying to based your remeasurement on the As completed drawings

25 Post Contract Cost Monitoring (Cont d) Remeasurement Early remeasurement has the following advantages : 1) The remeasured amount will prove whether the original allowed quantities/sum was sufficient or not. 2) If there is a cost over-run, early remeasurement would allow time for the Employer to take measures to minimise the effect. 3) If there is a large cost-saving, early indication of the remeasured value to the Contractor will allow him to carry out cost control on his subcontractors to ensure his expense will not exceed what he will receive. This will help in the future finaliszation of the Final Account.

26 Post Contract Cost Monitoring (Cont d) 5. Conclusion Post contract cost monitoring is a monitoring process not a reporting process To monitor, the Q.S. must be proactive and advise the Employer early enough so that he can take actions that he deem necessary reporting the situation after anything can be done is not monitoring

27 Thank You All. Any Questions?

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Valuation for Interim Payment Certificates Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Valuation for Interim Payment Certificates Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant

More information

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 INTRODUCTION TO THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013 Sr. TANG Ki

More information

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017 BIDP Standard FORMS & JBCC Minor WORKS Commentary ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW 01160007 04 th NOVEMBER 2017 Types of Contract Fixed Price Contracts For Specified work for a sum not adjustable

More information

Preparing Interim Payment Valuations for Construction Works - Worked Examples and Solutions

Preparing Interim Payment Valuations for Construction Works - Worked Examples and Solutions Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2018-03-10 Preparing Interim Payment Valuations for Construction Works - Worked Examples and Solutions

More information

CONTINUING PROFESSIONAL DEVELOPMENT 2013

CONTINUING PROFESSIONAL DEVELOPMENT 2013 CONTINUING PROFESSIONAL DEVELOPMENT 2013 Certificates and Certifications by Architects under the PAM Form of Building Contract 2006 Prepared by Ar Mohd Zulhemlee An CERTIFICATES The need for Certificates:

More information

Form of Agreement Between the Client And the Quantity Surveyor

Form of Agreement Between the Client And the Quantity Surveyor Form of Agreement Between the Client And the Quantity Surveyor Second ACQS Edition (May 2009) Contents Agreement 1 Terms of Appointment 1. Quantity Surveyor's obligations 2 2. Client's obligations 2 3.

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

Payment Procedures Under the RIAI Form Of Contract and the Public Works Contract Where the Employer Provides the Design: a Comparative Study

Payment Procedures Under the RIAI Form Of Contract and the Public Works Contract Where the Employer Provides the Design: a Comparative Study Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2012-2 Payment Procedures Under the RIAI Form Of Contract and the Public Works Contract Where the

More information

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) Construction Industry Development Board Tel: 012 343 7136 or 012 481 9030 Fax: 012

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

QBCC PERIOD MINOR WORKS SUBCONTRACT

QBCC PERIOD MINOR WORKS SUBCONTRACT Build better. QBCC PERIOD MINOR WORKS SUBCONTRACT The General Conditions of the QBCC Period Minor Works Subcontract may not be suitable for all work and the QBCC does not make any representation as to

More information

FIDIC WORKSHOP 2016 GROUP 6

FIDIC WORKSHOP 2016 GROUP 6 FIDIC WORKSHOP 2016 GROUP 6 QUESTION 1 WHAT ARE THE ESSENTIAL REQUIREMENTS FOR FORMATION OF CONTRACT? DISCUSS WHETHER A BINDING AND ENFORCEABLE CONTRACT HAS BEEN CONCLUDED BETWEEN JOLLY AND CAN-DO. 1.

More information

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS TABLE OF CONTENTS Background 1 1. Introduction 1 2. Contract Works 1 3. Project

More information

referred to: 6 Statutory obligations 4 Statutory Obligations, Notices, Fees and Charges Statutory Requirements

referred to: 6 Statutory obligations 4 Statutory Obligations, Notices, Fees and Charges Statutory Requirements HKIS QSD PQSL Series 2014 by Sr. TANG Ki-cheung FHKIS RPS(QS) FSZCEA MHKIVM Director of K C Tang Consultants Ltd. Quantity Surveyors. Construction Cost and Contract Consultants Ltd. on 14 August 2014 (Thursday)

More information

19 Assignment and sub-letting 17 Assignment or Sub-letting. Assignment

19 Assignment and sub-letting 17 Assignment or Sub-letting. Assignment HKIS QSD PQSL Series 2015 by Sr. TANG Ki-cheung FHKIS RPS(QS) FSZCEA FHKIVM Director of K C Tang Consultants Ltd. Quantity Surveyors : Construction Cost and Contract Consultants on 21 May 2015 (Thursday)

More information

SPECIAL FEATURES IN THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013

SPECIAL FEATURES IN THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013 SPECIAL FEATURES IN THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013 Sr. TANG Ki-cheung FHKIS RPS(QS) FSZCEA MHKIVM Director of K C Tang Consultants

More information

Building & Construction Law all notes

Building & Construction Law all notes Building & Construction Law all notes Week 2 THE NATURE OF THE BUILDING AND CONSTRUCTION INDUSTRY Project participants Project stages Procurement methods Typical players and processes Typical project participants

More information

General terms of sale and delivery. The following conditions apply exclusively for companies

General terms of sale and delivery. The following conditions apply exclusively for companies General terms of sale and delivery The following conditions apply exclusively for companies 1. General information 1.1 Our deliveries and services are provided exclusively on the basis of these general

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date:... /... /.../ This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative)

More information

THE UNIVERSITY OF THE WEST INDIES, MONA CAMPUS Procurement Policies and Procedures Manual. Appendices APPENDICES

THE UNIVERSITY OF THE WEST INDIES, MONA CAMPUS Procurement Policies and Procedures Manual. Appendices APPENDICES APPENDICES 53 Appendix 1-1 Agreement Form This Agreement made the...day of...20...between...of...hereinafter called the Employer and...of...hereinafter called the Contractor of the other part. Whereas

More information

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner: Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

General Purchase Conditions of Avans University of Applied Sciences

General Purchase Conditions of Avans University of Applied Sciences General Purchase Conditions of Avans University of Applied Sciences page 2 of 16 Table of Contents 1 Definitions 3 2 Applicability 4 3 Quotation, Instruction and formation of the Agreement 4 4 Execution

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR SCHEDULES 8 + 9 2015 EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR

More information

AMENDMENTS TO GDLA 82 (re-printed 18 th June 2003) REVISED FAIR WAGES CLAUSE AND RELEVANT COMPLIANCE CERTIFICATES. Contents. - Clause 39 Fair Wages

AMENDMENTS TO GDLA 82 (re-printed 18 th June 2003) REVISED FAIR WAGES CLAUSE AND RELEVANT COMPLIANCE CERTIFICATES. Contents. - Clause 39 Fair Wages AMENDMENTS TO GDLA 82 (re-printed 18 th June 2003) REVISED FAIR WAGES CLAUSE AND RELEVANT COMPLIANCE CERTIFICATES Contents - Clause 39 Fair Wages - Clause 35 Certificates and Payments - Contractor s Rates

More information

Architect / Contract Administrator s Instruction

Architect / Contract Administrator s Instruction Architect / Contract Administrator s Instruction Instruction no: Sheet: of Under the terms of the -mentioned Contract, I/we issue the following instructions: Architect/Contract Administrator s estimate

More information

The RIAI Standard Form of Contract 2012 Edition: a Review

The RIAI Standard Form of Contract 2012 Edition: a Review Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2013-1 The RIAI Standard Form of Contract 2012 Edition: a Review Tony Cunningham Dublin Institute

More information

DISBURSEMENTS IN WORLD BANK OPERATIONS. Loan Closing Issues. The World Bank

DISBURSEMENTS IN WORLD BANK OPERATIONS. Loan Closing Issues. The World Bank DISBURSEMENTS IN WORLD BANK OPERATIONS Loan Closing Issues Important considerations: Outstanding commitments Closing date Grace period Payment of audit and retention Return of unutilized funds Closure

More information

GENERAL TERMS AND CONDITIONS. Researchpark Haasrode, Romeinsestraat 10, 3001 Heverlee, Belgium VAT (BE) RLP Leuven

GENERAL TERMS AND CONDITIONS. Researchpark Haasrode, Romeinsestraat 10, 3001 Heverlee, Belgium VAT (BE) RLP Leuven GENERAL TERMS AND CONDITIONS Researchpark Haasrode, Romeinsestraat 10, 3001 Heverlee, Belgium VAT (BE) 0840.120.364 RLP Leuven 1. SCOPE OF APPLICATION 1.1 Notwithstanding any communications to the contrary

More information

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015)

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) Ref: W/RFQ-GCC GENERAL CONDITIONS OF CONTRACT REQUEST FOR QUOTATION [Issued in terms of section

More information

AIRPORT AUTHORITY HONG KONG

AIRPORT AUTHORITY HONG KONG AIRPORT AUTHORITY HONG KONG GENERAL CONDITIONS OF CONTRACT BUILDING AND CIVIL WORKS ISSUE NO. 10 August 2011 [this page not used] GENERAL CONDITIONS OF CONTRACT FOR BUILDING AND CIVIL WORKS TABLE OF CONTENTS

More information

DIRECTORATE OF ESTATES AND FACILITIES

DIRECTORATE OF ESTATES AND FACILITIES DIRECTORATE OF ESTATES AND FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006

More information

Sub Contract Agreement

Sub Contract Agreement Sub Contract Agreement In a building project there is always a contractor. There need not be any sub-contractors However there will invariably be sub-contractors. There are two types of sub-contractors

More information

Appendix K Model Letters for Use by the Engineer

Appendix K Model Letters for Use by the Engineer 175 Model Letters for Use by the Engineer Introduction This Appendix provides model letters for use by the Engineer primarily for formal correspondence with the Contractor. These model letters do not distinguish

More information

Cosmos Projects - Standard Terms and Conditions of Sub-Contract

Cosmos Projects - Standard Terms and Conditions of Sub-Contract Cosmos Projects - Standard Terms and Conditions of Sub-Contract These standard terms and conditions shall apply to any Sub Contract between Cosmos Projects Limited ( CPL ) and any Sub-Contractor following

More information

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract

More information

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES PROLONGATION COST CLAIMS THE BASIC PRINCIPLES HKA Quantum Expert Craig Enderbury sets out the basic principles of prolongation cost claims using a simple and hypothetical example. He highlights the common

More information

HKIS Resolving Disputes between Contractors

HKIS Resolving Disputes between Contractors HKIS Resolving Disputes between Contractors 12 December 2012 (Wednesday) 7:00pm 7:45pm Gilbert Kwok FHKIS, FRICS Partner, Hong Kong and China Construction Group Clyde & Co For further information: gilbert.kwok@clydeco.com

More information

30 Questions You Should Ask Your Custom Home Builder

30 Questions You Should Ask Your Custom Home Builder 30 Questions You Should Ask Your Custom Home Builder 1) How long have you been building luxury custom homes? Your builder should at least 20 years experience in all facets of the new home construction

More information

Sequestration and Terminations for Convenience

Sequestration and Terminations for Convenience Sequestration and Terminations for Convenience J. Clark Pendergrass Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 jcp@lanierford.com www.lanierford.com

More information

Construction Law Update Comparing Contracts-A Review Of The AIA 201 and ConsensusDocs

Construction Law Update Comparing Contracts-A Review Of The AIA 201 and ConsensusDocs Construction Law Update Comparing Contracts-A Review Of The 201 and ConsensusDocs Michael P. Sams, Esq. Kenney & Sams, P.C. Old City Hall 45 School Street Boston, MA 02108 (617)-722-6045 mpsams@kandslegal.com

More information

Let us help you build your dream home

Let us help you build your dream home Let us help you build your dream home We ve made it easier for you to build a new home or make improvements to your existing one. First National Bank - a division of FirstRand Bank Limited. An Authorised

More information

STONE INTERIORS Terms of Trade. 1 Definitions. 2 Estimate Validity and Existence of Contract. 3 Cancellations

STONE INTERIORS Terms of Trade. 1 Definitions. 2 Estimate Validity and Existence of Contract. 3 Cancellations 1 Definitions 1.1 The Company means Stone Interiors Ltd 1.2 The Customer means the customer named on the Company s acknowledgement of order 1.3 The Contract means the contract for the sale of goods and/or

More information

Supplemental Cost Reimbursement Terms and Conditions

Supplemental Cost Reimbursement Terms and Conditions The provisions of these Supplemental Cost Reimbursement Terms and Conditions are in addition to the General Provisions incorporated by reference elsewhere into the Contract (or such other terms as may

More information

CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk

More information

Contract [Number] [Contract Name] Contract Documents. Minor Works / Direct Appoint

Contract [Number] [Contract Name] Contract Documents. Minor Works / Direct Appoint Contract [Number] [Contract Name] Contract Documents Minor Works / Direct Appoint This proforma document provides the basis for the development of physical works contract documents for the Transport Agency

More information

Subcontract Agreement

Subcontract Agreement Subcontract Agreement SA - 2009 Project: Trade: Subcontractor: SA - 2009 Number: FOREWORD A good working relationship between the Contractor and Subcontractor is critical to ensuring construction projects

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012 2 Februray 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Discussion on Contract Management

More information

Consultancy Services Contract

Consultancy Services Contract SERVICES AND RESOURCES INFRASTRUCTURE Consultancy Services Contract Based on AS 4122 2010 General Conditions of Contract for Consultants The University of Adelaide and The Consultant For Insert Project

More information

TDW Gesellschaft für verteidigungstechnische Wirksysteme mbh General Purchasing Terms and Conditions Dated:

TDW Gesellschaft für verteidigungstechnische Wirksysteme mbh General Purchasing Terms and Conditions Dated: TDW Gesellschaft für verteidigungstechnische Wirksysteme mbh Dated: 01.09.2015 1 Scope 1.1 The following General Purchasing Terms and Conditions of TDW Gesellschaft für verteidigungstechnische Wirksysteme

More information

Webinar: Making the Right Choices in Government Contracting Part 3

Webinar: Making the Right Choices in Government Contracting Part 3 Public Contracting Institute LLC Webinar: Making the Right Choices in Government Contracting Part 3 Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com. Email rliebermanconsultant@gmail.com.

More information

Standard Trading Terms and Conditions

Standard Trading Terms and Conditions Standard Trading Terms and Conditions 1. Interpretation 1.1. In these Terms and Conditions: 1.1.1. Agreement means the definition in clause 2.2 below. 1.1.2. Aqua-Tech means Baronial Pty Ltd (ACN 146 402

More information

These conditions apply to all supplies of goods and services supplied by us to you, unless otherwise clearly agreed in writing signed by us and you.

These conditions apply to all supplies of goods and services supplied by us to you, unless otherwise clearly agreed in writing signed by us and you. SERVICE CONDITIONS Truck Moves New Zealand (4218738) A company of Sheehans Automotive Management Ltd (1851618) Service Conditions In these standard service conditions we, us and similar expressions, refer

More information

Terms & Conditions Supply of Goods or Services

Terms & Conditions Supply of Goods or Services Terms & Conditions Supply of Goods or Services 1. DEFINITIONS In these terms and conditions: Agreement means an agreement between the Purchaser and Supplier for the supply of Goods or Services constituted

More information

EASTERN OREGON UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

EASTERN OREGON UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) EASTERN OREGON UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THIS CONTRACT IS BETWEEN: OWNER: Eastern Oregon University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as

More information

Part 2 Employer s preliminary notice of Fair Payment requirements 3. Part 4 Suggested modifications to SBCC Main Contracts 5

Part 2 Employer s preliminary notice of Fair Payment requirements 3. Part 4 Suggested modifications to SBCC Main Contracts 5 Contents Part 1 Introduction Page 1 Part 2 Employer s preliminary notice of Fair Payment requirements 3 Part 3 Incorporation of modifications 4 Part 4 Suggested modifications to SBCC Main Contracts 5 Standard

More information

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS 1. DEFINITIONS AND INTERPRETATION 1.1 Definitions In this Contract (as hereinafter defined)

More information

PFIZER LABORATORIES (PTY) LTD STANDARD TERMS AND CONDITIONS OF PURCHASE ("these Terms")

PFIZER LABORATORIES (PTY) LTD STANDARD TERMS AND CONDITIONS OF PURCHASE (these Terms) PFIZER LABORATORIES (PTY) LTD STANDARD TERMS AND CONDITIONS OF PURCHASE ("these Terms") 1. Interpretation and Definitions In these Terms: "the Contract" shall mean the contract between Pfizer and the Supplier

More information

THE HONG KONG INSTITUTE OF SURVEYORS

THE HONG KONG INSTITUTE OF SURVEYORS PART II ASSESSMENT 2013 DAY 2 Wednesday, 18 th September, 2013 NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of the questions. B. The number of main

More information

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/ MOMBASA Beach Hotel NGULIA Safari Lodge VOI Safari Lodge KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/2017-2018 KENYA

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1 COMPLIANCE TO CONDITIONS OF CONTRACT - SCC.1(Renovation) Please indicate clearly below your compliance to each clause of the Conditions of Contract. Where you are not in agreement, you should give your

More information

ARCHITECTURAL CONSULTANCY AGREEMENT TERMS AND CONDITIONS

ARCHITECTURAL CONSULTANCY AGREEMENT TERMS AND CONDITIONS TERMS AND CONDITIONS K20 ARCHITECTURE 325 COVENTRY STREET SOUTH MELBOURNE VICTORIA, 3205 AUSTRALIA t: +61 3 9699 4440 f: +61 3 9699 5550 e: melboffice@k20architecture.com www.k20architecture.com K2O.AU

More information

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE

More information

The Standard Form of Building Contract Edition

The Standard Form of Building Contract Edition The Standard Form of Building Contract 2019 Edition Issued by Since 8th May 2018 when Arbitration (Amendment) Act 2018 (the Act ) came into operation, the Kuala Lumpur Regional Centre for Arbitration (the

More information

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date NZS 3915:2005 COMMITTEE REPRESENTATION This Standard was prepared by Technical Committee P 3915 for the Standards Council established under the Standards Act 1988. Peter Fehl New Zealand Contractors Federation

More information

General terms and conditions of sale and delivery for Norsk Stål AS

General terms and conditions of sale and delivery for Norsk Stål AS General terms and conditions of sale and delivery for Norsk Stål AS Innhold 1. Application... 2 2. Offers and product information... 2 3. Product characteristics... 3 4. Quantity... 3 5. Trade terms...

More information

ARIZONA STATE UNIVERSITY - STANDARD FORM AGREEMENT BETWEEN OWNER AND ON THE BASIS OF A GUARANTEED MAXIMUM PRICE March 1, 2015 Edition

ARIZONA STATE UNIVERSITY - STANDARD FORM AGREEMENT BETWEEN OWNER AND ON THE BASIS OF A GUARANTEED MAXIMUM PRICE March 1, 2015 Edition ARIZONA STATE UNIVERSITY - STANDARD FORM AGREEMENT BETWEEN OWNER AND CM@RISK ON THE BASIS OF A GUARANTEED MAXIMUM PRICE March 1, 2015 Edition Standard Form Agreement Between Owner and CM@Risk (March 1,

More information

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND PROFESSIONAL ARCHITECT (PrArch) PROFESSIONAL SENIOR ARCHITECTURAL TECHNOLOGIST (PrSArchT) mark applicable registration

More information

Verband der deutschen Lack- und Druckfarbenindustrie e.v.

Verband der deutschen Lack- und Druckfarbenindustrie e.v. Verband der deutschen Lack- und Druckfarbenindustrie e.v. Translation only the German version is legally binding 29 November 2017 The German Paint and Printing Ink Association [Verband der deutschen Lack-

More information

COUNTY GOVERNMENT OF NYERI BILLS OF QUANTITIES

COUNTY GOVERNMENT OF NYERI BILLS OF QUANTITIES COUNTY GOVERNMENT OF NYERI DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT PROPOSED CONSTRUCTION OF GUMBA GICHAGI FOOTBRIDGE IN RUGI WARD CGN/INF/62/16-17 BILLS OF QUANTITIES ISSUED BY: COUNTY WORKS OFFICER COUNTY

More information

1 Exam Prep Business and Finance Practice Test 4

1 Exam Prep Business and Finance Practice Test 4 1 Exam Prep Business and Finance Practice Test 4 1. All the following are normally required for a loan application except. A. an income statement B. a balance sheet C. a tax return D. retained earnings

More information

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:-

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:- Anti-Bribery & Corruption Policy of Intent STONBURY LIMITED TERMS AND CONDITIONS FOR SUBCONTRACTORS 1. INTERPRETATION (1) In these sub-contract conditions of agreement, the following words and phrases

More information

In order to implement these measures the parties enter into this framework agreement (hereinafter referred to as FRAMEWORK AGREEMENT).

In order to implement these measures the parties enter into this framework agreement (hereinafter referred to as FRAMEWORK AGREEMENT). Framework Agreement between GAUDLITZ GmbH Callenberger Strasse. 42 D- 96450 Coburg (hereinafter referred to as GA) and (hereinafter referred to as Supplier) 1. Preamble GAUDLITZ is interested in obtaining

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR THE OREM CITY PARKING STUDY Issued February 26 th, 2018 City of Orem 56 North State Street Orem Utah 84057 TABLE OF CONTENTS 1.0 Introduction... 2 1.1 The Successful Applicant...

More information

W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES

W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES INVITATION FOR QUOTATIONS FOR CONSTRUCTION OF CIVIL WORKS UNDER SHOPPING PROCEDURES To Dear Sirs, Sub : INVITATION FOR QUOTATIONS FOR CONSTRUCTION

More information

Landscape Construction. For Hard & Soft Landscaping. Standard Terms and Conditions of Contract. Artisan Hardscape Solutions Ltd

Landscape Construction. For Hard & Soft Landscaping. Standard Terms and Conditions of Contract. Artisan Hardscape Solutions Ltd Landscape Construction For Hard & Soft Landscaping Standard Terms and Conditions of Contract Artisan Hardscape Solutions Ltd 1.0 DEFINITIONS 1.1 Client means the individual or organisation who buys or

More information

Government Contracts Pricing Strategies and Rate Structures

Government Contracts Pricing Strategies and Rate Structures Government Contracts Pricing Strategies and Rate Structures Presented By: Brandon Smith bsmith@anglincpa.com Jon Levin jlevin@maynardcooper.com Provisional Billing Rates Provisional, Target, Budget, Billing,

More information

MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT

MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT THE CONTRACT IS BETWEEN: OWNER: MARION COUNTY A political subdivision of the state of Oregon And TBD Contractor (referred

More information

JBCC CONTRACT PRICE ADJUSTMENT PROVISIONS (CPAP)

JBCC CONTRACT PRICE ADJUSTMENT PROVISIONS (CPAP) JBCC CONTRACT PRICE ADJUSTMENT PROVISIONS (CPAP) CPAP Indices Application Manual The CPAP indices are calculated and published by Stats SA and are licensed for distribution only on subscription from JBCC

More information

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising)

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Making and defending claims Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Public Works Contracts Dealing with Change Introduction Minimising Change Schedule

More information

ICES. Narrative. Applicant s name

ICES. Narrative. Applicant s name ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed

More information

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M. Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project

More information

NSW Residential Building Contract for New Dwellings

NSW Residential Building Contract for New Dwellings NSW Residential Building Contract for New Dwellings OWNERS: JOB: Lot 5382 Proposed Road Marsden Park NSW 2765 LOT: 5382 SITE: Proposed Road Marsden Park NSW 2765 To verify your builder is a HIA member

More information

to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the

to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the RESIDENTIAL BUILDING CONSUMER GUIDE AND DETERMINATION UNDER SECTION 14 OF THE RESIDENTIAL BUILDING WORK CONTRACTS AND DISPUTE RESOLUTION

More information

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below: DOMESTIC SUB-CONTRACT CONDITIONS These are the Domestic Sub-Contract Conditions referred to by the Articles of Agreement to which they are attached. In the event that these Domestic Sub-Contract Conditions

More information

AIA Document A133 TM 2009

AIA Document A133 TM 2009 AIA Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

More information

6/25/2014. Navy Small Business Innovation Research (SBIR) Program. Navy Needs Are Diverse

6/25/2014. Navy Small Business Innovation Research (SBIR) Program. Navy Needs Are Diverse Navy Small Business Innovation Research (SBIR) Program 1 Navy Needs Are Diverse 2 1 SBIR Program Phases I, II III Feasibility Study Phase I contracts award with SBIR funding up to $80k with a $70k option.

More information

AIA Document A102 TM 2007

AIA Document A102 TM 2007 AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the

More information

Conditions for the Carriage of Goods by Road

Conditions for the Carriage of Goods by Road Conditions for the Carriage of Goods by Road The Conditions set down the basis on which the Carrier will carry goods for the Customer (definitions of Carrier and Customer are given in Condition 1). The

More information

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC) NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session

More information

External Consultants & General Contractors Contracts

External Consultants & General Contractors Contracts The University of British Columbia Land and Building Services Prepared by: Frank Geyer Work Procedure Approved by: David Barnes External Consultants & General Contractors Contracts Issue Date: 21 November

More information

GUIDANCE FOR PROFESSIONAL CONSULTANTS

GUIDANCE FOR PROFESSIONAL CONSULTANTS Diocese of Westminster Education Service Page 1 MANDATORY DOCUMENTATION GUIDANCE FOR PROFESSIONAL CONSULTANTS RICS Standard Form of Consultant s Appointment RICS Standard Form of Consultant s Appointment

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date: This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative) [If

More information

CUSTOMER CONTRACT. Introduction. Contract Terms. Dear Customer

CUSTOMER CONTRACT. Introduction. Contract Terms. Dear Customer Origin Energy Electricity Limited ABN 33 07 052 287 CUSTOMER CONTRACT Introduction Dear Customer This customer contract is important. Please read it carefully and indicate whether you accept the terms

More information

ANNEX II SAMPLE FORM OF CONTRACT

ANNEX II SAMPLE FORM OF CONTRACT ANNEX II SAMPLE FORM OF CONTRACT Date Dear Sir/Madam, Ref.:76613 / / Supply of 3-phase power and supply & installation of submersible pumps at Konduwa bore field in Nyala, South Darfur The United Nations

More information