1 May 7, 2014 Presentation to the School Board of Palm Beach County THE ESCO PROGRAM
2 ESCO DEFINED An Energy Service COmpany (ESCO) is a commercial or for profit business providing a broad range of energy solutions including: design and implementation of energy savings projects, retrofitting, energy conservation, energy infrastructure outsourcing and power generation and energy supply. A newer breed of ESCO now focuses more on innovative financing methods. More to come
3 ESCO SIMPLY STATED A financial mechanism to pay for today s facility upgrades with tomorrow s energy savings. RECOVERY.GOV U.S. Department of Energy
4 ESCO OVERVIEW A consultancy group engages in a performance based contract with a client firm to implement measures which reduce energy consumption and costs in a technically and financially viable manner. In Practice The ESCO starts by performing an analysis/audit of the property, designs an energy efficient solution, installs the required elements, and maintains the system to ensure energy savings during the pre determined payback period. [1] The savings in energy costs are often used to pay back the capital investment of the project (5 20 years or beyond). [2] If the project does not provide returns on the investment, the ESCO may be responsible to pay the difference (Contract driven). Major Steps in a Typical ESCO Project
5 ESCO CONSIDERATIONS Specific to Energy Cost Savings; there are three basic types of ESCO Projects: 1. Lighting System Retrofits 2. Mechanical Upgrades 3. Building Envelope Upgrades The cost saving potential for these different types of conservation can range dramatically. Each have their advantages and disadvantages! Note: The (3) items listed above are generally bundled to create one comprehensive project
6 ESCO LIGHTING SYSTEM RETROFITS This type of ESCO produces the most cost savings because these systems are very energy intensive and tend to be far less expensive than other conservation measures. Note: [1] The savings from lighting related conservation measures are generally reliable because the operating schedule is the primary, contributing factor. [2] Savings can be calculated without using a computerbased simulation; however, there are still challenges.
7 ESCO MECHANICAL UPGRADES This type of ESCO is specific to heating, ventilation and air conditioning (HVAC) systems which are very energy intensive, but they are difficult to fit into the ESCO model due to high initial costs. Note: [1] The payback period for HVAC systems may be lengthy depending on the scope of work. [2] HVAC measures can turn a five year lighting contract into a 20 year contract, if bundled.
8 ESCO BUILDING ENVELOPE MAINTENANCE PROGRAM (BEMP) This type of ESCO is specific to door, window replacement and reflective roofs. Note: [1] These measures are also difficult to fit into the ESCO model due to high initial costs. [2] BEMP measures are usually long term year contracts.
9 ESCO FINANCE ESCOs were traditionally focused on performing energy audits and then implementing the recommended projects. Financing was added to the program when it became evident that businesses and governments did not have the capital resources to fund the capital improvement projects. The concept of paid from future savings means financing. Just as Certificates of Participation are used to pay for the construction of a school from future tax revenues, the ESCO will leverage future energy savings to fund the project.
10 ESCO FINANCE The District has many options to pay for projects. Internal financing options include: Pay as you go use funds in the budget to pay for the project. The District is developing the FY15 budget and could prioritize needed energy projects. Short term financing just as the District financed the purchase of school buses, the District could choose to do short term financing to pay for projects. The principal and interest payments would need to be included in the capital budget and five year capital plan. The transaction could be structured for five years or could be a one year note that is extended annually for up to five years. The interest rate would depend on current market conditions and the term of the loan. At this time, those rates would be between 1 and 3%.
11 ESCO FINANCE External financing options: Traditional ESCO financing The District purchases the equipment from the ESCO. The ESCO will partner with a financial institution to provide financing. Principal and interest payments would be made from savings (Operating Budget). The transaction could also be structured so the principal and interest are paid from the capital budget, allowing the savings to be used to fund programs in the operating budget. Hybrid ESCO financing We have heard that some companies offer the option to provide the improvements through an operating lease. In theory, the District would grant a lease for the portion of the building where the improvements would take place. The vendor would own, operate and maintain the equipment. The District would pay annually for the cooled air, lighting, etc. Interest rates for external financing can be difficult to verify, but are expected in the 8 12% range.
12 ESCO FINANCE External financing options are very complex. Significant time would be involved in the review of the contracts. All options, with the exception of pay as you go, involve financing. The District has never obligated future operating dollars, limiting all borrowing to the capital budget. Such transactions should be carefully considered. The Finance Committee will be engaged once the results of the RFP are available. The District s Financial Advisor and Bond Counsel will also be engaged as needed to review contracts and financial proposals.
13 ESCO STAFF RESEARCH The Advantages and Disadvantages listed in the next two slides are from a combination of Industry Sources Therefore, staff will be utilizing a RFP to gather the pertinent information necessary to make the best possible recommendation regarding our facilities.
14 ESCO RESEARCH SUMMARY An ESCO constitutes a partnership between a facility owner and an energy service company and is considered a time and cost effective method for completing comprehensive energy upgrades. Advantages: 1. Guaranteed Performance 2. Participation 3. Responsibility 4. Verification 5. Accountability 6. Financing 7. Cost Certainty 8. Avoided Capital Costs
15 ESCO RESEARCH SUMMARY Continued Although ESCO s sound inviting on the surface, there are some inherent risks. The devil is in the details. Risks (Disadvantages) to Consider: 1. Savings Shortfalls 2. Long Term Liability 3. Potential Conflict of Interest 4. Changes/Limits to Facility Function 5. Transparency 6. Implications to Capital Asset Planning 7. Heavy Lease Load 8. Project Size and Scope
16 ESCO FURTHER CONSIDERATION Staff will engage the Construction Oversight Review Committee (CORC) and the District s Finance Committee for input.
17 ESCO CONSIDERATIONS FOR OUR SCHOOL DISTRICT A) Federal guidelines may change regarding fluorescent lights. We are now replacing T12 bulbs with T8 and may be required to go to T5 bulbs or LED fixtures. B) Responsible asset management may require that the District close, sell off or lease out facilities to reduce its financial burden, in consideration of declining enrollment. An ESCO will encumber the property. Shorter payback periods can reduce that risk. C) Important ESCO performance contract features that need to be considered: Ongoing maintenance of the lights and HVAC components that are constructed. HVAC maintenance must have a fast response time. Embrace the School Board's M/WBE Policy. Enforce the Jessica Lunsford Act for all ESCO personnel and subcontractors. Keeping the payback period short provides advantages to the District. Independent verification of the Energy Audit. Open competition is desirable. Most current ESCO models are noncompete.
18 ESCO CONSIDERATIONS FOR OUR SCHOOL DISTRICT (cont d) D) In some cases, replacing like for like in terms of lighting and HVAC may not resolve outstanding Building Code Issues. Resolving code issues may not reduce energy costs. E) Leased use of our Facilities seems likely to interfere with clear auditability for energy savings. ESCOs may incur additional costs for new leases. F) Avoiding Capital Cost is not avoiding all cost the burden will be shifted to the Operating Budget instead. G) There is a potential for Conflict of Interest if the ESCO controls and chooses all design and cost comparisons to be used in the Energy Audit. A hybrid could include design by the Owner s engineer, with financing / construction by the ESCO. H) We need trained staff to run this program, who can evaluate the fairness of the contract and monitor compliance.
19 ESCO It s all about the Financing
20 ESCO QUESTIONS?
FINDINGS IN SUPPORT OF AN ALTERNATE CONTRACTING PROCESS FOR AN ENERGY SAVINGS PERFORMANCE CONTRACT IN 5 COUNTY-OWNED BUILDINGS
FINDINGS IN SUPPORT OF AN ALTERNATE CONTRACTING PROCESS FOR AN ENERGY SAVINGS PERFORMANCE CONTRACT IN 5 COUNTY-OWNED BUILDINGS 1. GENERAL The Oregon Legislative Assembly encourages public agencies to consider
More informationAugust Report Number: P Dear Dr. Murphy and Members of the Board of Education:
THOMAS P. DiNAPOLI COMPTROLLER STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK 12236 August 2015 GABRIEL F. DEYO DEPUTY COMPTROLLER DIVISION OF LOCAL GOVERNMENT AND
More informationUS Experience with Energy Savings Performance Contracts
US Experience with Energy Savings Performance Contracts John A. Shonder Oak Ridge National Laboratory Building Systems 2006 Conference Helsinki, Finland March 22, 2006 Background U.S. is the world s largest
More informationEnergy Efficiency Simple, Safe Investment. Tim Gasper, PE Brady Energy Services (919)
Energy Efficiency Simple, Safe Investment Tim Gasper, PE Brady Energy Services (919) 781-0458 TJGasper@Trane.com Energy Efficiency in Attractions and Accommodations Energy Costs On average, America s 47,000
More informationRENOVATE AMERICA GREEN BOND PRE-ISSUANCE REVIEW
RENOVATE AMERICA GREEN BOND PRE-ISSUANCE REVIEW November 27, 2017 Introduction In 2017, Renovate America developed the HERO 2017 Green Bond Framework under which it intends to issue multiple series of
More informationOpportunity Assessment:
Opportunity Assessment: Using Energy Performance Contracting to Address School Facility Needs in Philadelphia March 20, 2017 Authored by: Emily Schapira and Laura Rigell Philadelphia Energy Authority 1400
More informationA Bill Regular Session, 2005 SENATE BILL 1091
Stricken language would be deleted from and underlined language would be added to the law as it existed prior to this session of the General Assembly. 0 State of Arkansas th General Assembly As Engrossed:
More informationDelaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016
Delaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016 Delaware Sustainable Energy Utility 500 West Loockerman Street, Suite 400 Dover, DE 19904 302-883-3048 1 Public
More informationFAQ : Guaranteed Energy Savings Program (GESP) Cities, Counties, Schools. General Program Questions. Q: Is GESP a grant program?
FAQ : (GESP) Cities, Counties, Schools Clean Energy Resource Teams 1 General Program Questions Q: Is GESP a grant program? A: No. GESP is state technical assistance, administered by the Department of Commerce
More informationA Simulation based Decision Model for Designing Contract Period in Energy Performance Contracting
A Simulation based Decision Model for Designing Contract Period in Energy Performance Contracting Presenter: Qianli Deng (Shally) Ph.D Candidate, University of Maryland, College Park Co author: Dr. Qingbin
More informationDear Superintendent Cardillo and Members of the Board of Education:
THOMAS P. DiNAPOLI COMPTROLLER STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK 12236 August 2015 GABRIEL F. DEYO DEPUTY COMPTROLLER DIVISION OF LOCAL GOVERNMENT AND
More informationR E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M
U N I V E R S I T Y O F N O R T H A L A B A M A R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M R F P 2 0 1 7-23
More informationTo: Mayor and City Council Through: Bill Monahan, City Manager. Subject: Proceeding with the ESCO Process
MILWAUKIE CITY COUNCIL STAFF REPORT Agenda Item: WS 4. Meeting Date: 9-16-14 To: Mayor and City Council Through: Bill Monahan, City Manager Subject: Proceeding with the ESCO Process From: Gary Parkin,
More informationTHEREFORE, the [enter appropriate legislative body] for County, Maryland approves the following Act:
[enter legislative body] FOR COUNTY, MARYLAND AN ACT for: the purpose of defining certain terms: establishing a clean energy loan program for commercial property owners; establishing the scope of and eligibility
More informationREQUEST FOR QUALIFICATIONS FOR A GUARANTEED ENERGY SAVINGS CONTRACT
Introduction REQUEST FOR QUALIFICATIONS FOR A GUARANTEED ENERGY SAVINGS CONTRACT COUNTY OF CHESTER, PENNSYLVANIA 313 W. MARKET STREET, SUITE 5402 WEST CHESTER, PA 19382 The County of Chester is requesting
More informationExperience with Traditional and Emerging ESCO Models. Peter White
Experience with Traditional and Emerging ESCO Models Peter White peter.z.white@jci.com 503-351-0900 Traditional: Performance Contracting A proven procurement model for building retrofits and key enabler
More informationB U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y
"INOGATE Technical Secretariat & Integrated Programme in support of the Baku Initiative and the Eastern Partnership energy objectives" B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U
More informationFIVE YEAR PLAN FOR ENERGY EFFICIENCY
FIVE YEAR PLAN FOR ENERGY EFFICIENCY Executive Summary Prepared for: Holy Cross Energy Navigant Consulting, Inc. 1375 Walnut Street Suite 200 Boulder, CO 80302 303.728.2500 www.navigant.com July 15, 2011
More informationExhibit DAS-1. Tucson Electric Power Company Demand-Side Management Program Portfolio Plan
Exhibit DAS-1 Tucson Electric Power Company Demand-Side Management Program Portfolio Plan 2008-2012 TABLE OF CONTENTS 1. Introduction...3 2. DSM Portfolio Performance Costs, Savings and Net Benefits...3
More informationEnergy Performance Contracting (EPC)
Energy Performance Contracting (EPC) D E F I N I T I O N A N D F U N D I N G 1 2 What is EPC? Sometimes used interchangably with the term ESCO meaning Energy Service Company. Energy Performance Contracting:
More informationTECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT
TECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT Table of Contents 1. Introduction 1 2. What is Energy Management Financing? 2 3. Barriers to Investing in Energy Management 3 1. Initial Costs 3 2.
More informationGuaranteed Energy Savings
Guaranteed Energy Savings Mark J. Gallick Account Manager Shayne Homan, P.E., C.E.M. - Director of Energy Services Brian Moore, LEED GA, CIPE Engineering Operations Manager Michael Grochalski, E.I.T.,
More informationDipl.-Ing. Detlef Loy
Dipl.-Ing. Detlef Loy Georg-Wilhelm-Str. 18 D-10711 Berlin Germany E-Mail: dloy@vossnet.de Advanced Lighting Components Building Control Systems Motors (for elevators, Ventilation etc.) Heating and Air
More informationINTRODUCTION. What Is Energy Performance Contracting?
1 INTRODUCTION What Is Energy Performance Contracting? Across the country, energy performance contracting (EPC) is offered by Energy Service Companies (ESCOs) as a practical way for public sector entities
More informationPENNSYLVANIA LAW RELATED TO GUARANTEED ENERGY SAVINGS CONTRACTS. Applicable Law Act 57 of 1998, Act 77 of 2004, and Act 39 of 2010
PENNSYLVANIA LAW RELATED TO GUARANTEED ENERGY SAVINGS CONTRACTS Applicable Law Act 57 of 1998, Act 77 of 2004, and Act 39 of 2010 The following text is taken from the printer s version of the Acts referenced
More informationBRIGHAM CITY CORPORATION REQUEST FOR PROPOSAL
BRIGHAM CITY CORPORATION REQUEST FOR PROPOSAL BRIGHAM CITY CORPORATION (www.brighamcity.utah.gov) located at 20 North Main Street Brigham City, Utah is requesting proposals from energy services companies
More informationMinnesota's Guaranteed Energy Savings Program (GESP)
Minnesota's Guaranteed Energy Savings Program (GESP) Division of Energy Resources & CERTs Roles Energy Savings Performance Contracting The Power of Bundling Energy Conservation Measures Minnesota s new
More informationIC Chapter Guaranteed Savings Contracts; Energy Efficiency Programs Used by School Corporations
IC 36-1-12.5 Chapter 12.5. Guaranteed Savings Contracts; Energy Efficiency Programs Used by School Corporations IC 36-1-12.5-0.5 "Actual savings" defined Sec. 0.5. As used in this chapter, "actual savings"
More informationU. S. Department of Housing and Urban Development Office of Public and Indian Housing
U. S. Department of Housing and Urban Development Office of Public and Indian Housing Special Attention of: NOTICE: PIH-2011-36 (HA) Public Housing Agencies; Issued: July 8, 2011 HUD Directors of Public
More informationGuaranteed Energy Savings Contract
REQUEST FOR PROPOSALS NUMBER RFP # MASD 13-01 December 20, 2013 MINERSVILLE AREA SCHOOL DISTRICT Guaranteed Energy Savings Contract SUPERINTENDENT'S OFFICE 1 Battlin Miners Drive P.O. Box 787 Minersville,
More informationDepartment of Community Affairs 2555 Shumard Oak Blvd. Tallahassee, FL 32399
Department of Community Affairs 2555 Shumard Oak Blvd. Tallahassee, FL 32399 Department of Environmental Protection Florida Energy Office 3800 Commonwealth Boulevard, Room 170J Tallahassee, FL 32303-3123
More informationMetropolitan Area Planning Commission Energy Performance Contracting Request for Qualifications (RFQ)
Metropolitan Area Planning Commission Energy Performance Contracting Request for Qualifications (RFQ) FREQUENTLY ASKED QUESTIONS Developed in collaboration with Peregrine Energy Group October 2011 Contents
More informationAppendix B. The EnergyRM EE PPA
Appendix B The EnergyRM EE PPA Description One specific variant of an EE PPA that is being discussed in Oregon and the Northwest is a model proposed by EnergyRM and Equilibrium Capital, which will be referred
More informationCT s Standardized Energy-Savings Performance Contracting (ESPC) Program. March 2015
CT s Standardized Energy-Savings Performance Contracting (ESPC) Program March 2015 Agenda What is Energy Savings Performance Contracting? How does the CT ESPC program work? How would I pay for an ESPC
More informationEnergy Saving Improvement Programs
Introducing Energy Saving Improvement Programs aka: ESIP; ESCO; P.L. 2009, c. 4; A-1185A Marc Pfeiffer, Deputy Director Division of Local Government Services What ESIP is All About Retrofitting public
More informationSchool Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year February 20, 2018
School Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year 2017-18 February 20, 2018 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...
More informationBriefing to the Dallas City Council s Budget, Finance and Audit Committee June 18, 2012
Briefing to the Dallas City Council s Budget, Finance and Audit Committee June 18, 2012 Energy Conservation is largely based on behavioral practices to use [energy] in a more efficient manner it is essential
More informationPresenters: Nick Alioto, Education Consultant Performance Services, Inc. (414)
Presenters: Nick Alioto, Education Consultant Performance Services, Inc. nalioto@performanceservices.com (414) 412-9366 Roger Dickson, Chief Finance & Operations Officer School District of New Berlin Roger.Dickson@nbexcellence.org
More informationUnderstanding EPAct Limited Time Tax Incentives for Efficient Lighting Solutions Including Certification and Compliance
Understanding EPAct 2005 Limited Time Tax Incentives for Efficient Lighting Solutions Including Certification and Compliance COMMERCIAL BUILDINGS TAX DEDUCTION Opportunity expires December 31, 2007 The
More informationContractor Guide. (314)
Contractor Guide www.stlouiscountysaves.com contractor@stlouiscountysaves.com (314) 332-2156 Introduction is a $10.4 million residential energy efficiency loan program supported by partnerships between
More informationENERGY SAVING PERFORMANCE CONTRACTING MANUAL FOR MISSISSIPPI S PUBLIC AGENCIES JULY 2014
ENERGY SAVING PERFORMANCE CONTRACTING MANUAL FOR MISSISSIPPI S PUBLIC AGENCIES JULY 2014 DISCLAIMER This manual has been prepared for the Mississippi Development Authority Energy and Natural Resources
More informationEnergy Efficiency Case Study: Performance Contracting
Energy Efficiency Case Study: Performance Contracting 3N 111(d) Meeting December 4, 2014 Ashley Patterson Director, Government Relations & Public Policy Ameresco Chris Hessler Partner AJW, Inc. ESCO Working
More informationMinnesota's Guaranteed Energy Savings Program (GESP)
Minnesota's Guaranteed Energy Savings Program (GESP) Division of Energy Resources Role Energy Savings Performance Contracting The Power of Bundling Energy Conservation Measures Minnesota s new Guaranteed
More informationRequest for Proposal on Qualifications (RFP/Q) Juniata County Government
Request for Proposal on Qualifications (RFP/Q) For Energy Performance Contracting Services For Juniata County Government Proposals Due June 5, 2015 by 4:00 p.m. Request for Qualifications: Energy Performance
More informationSMUD Home Performance Program: Neighborhoods Frequently Asked Questions (FAQs)
SMUD Home Performance Program: Neighborhoods Frequently Asked Questions (FAQs) THE PROGRAM Q) What is the neighborhood program in a nutshell? A) The Neighborhood program is a simple, low cost, retrofit
More informationBuilding Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits
Building Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits CUNY Institute for Urban Systems Building Performance Lab Introduction to Energy Audits 2 Topic
More informationPACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY
PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY VERSION 2.0 6 October 2016 TABLE OF CONTENTS OVERVIEW... 3 STATUTORY AND PROGRAMMATIC REQUIREMENTS... 4 PACE PROJECT PROCESS... 6 HOW PACE PROJECTS ARE ASSESSED...
More informationPROGRAM ELIGIBILITY CRITERIA
PROGRAM ELIGIBILITY CRITERIA All capitalized terms not defined herein will have the meanings as defined under the heading Definition below. 1.1 Participant Eligibility Criteria To be an Eligible Person
More informationSchool Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019
School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year 2018-19 February 21, 2019 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...
More informationFY 2016 Proposed Budget
FY 2016 Proposed Budget Budget Workshop July 22, 2015 Top-performing urban school district in Florida FY2016 Proposed Budget Adopted FY2015 Amended FY2015 (May 2015) Proposed FY2016 $ Increase/ (Decrease)
More informationCSBSA. May 23, Walter Matias Program Manager Institutional Sector
CSBSA May 23, 2007 Walter Matias Program Manager Institutional Sector walter.matias@enbridge.com 416-753-6605 Overview About Enbridge Gas Distribution Program Review Support Services Developments About
More informationGreen Income Tax Incentives. By Colleen M. Berndt, CPA Meyers Brothers Kalicka, P.C. MBKCPA.COM
Green Income Tax Incentives By Colleen M. Berndt, CPA Meyers Brothers Kalicka, P.C. MBKCPA.COM Residential Energy Property Credit Tax Credit: 30% of cost up to $1,500 Expires: December 31, 2010 Details:
More informationHow to select, prioritize, & justify economically viable energy projects
How to select, prioritize, & justify economically viable energy projects Eileen Westervelt, Senior Energy Engineer U of I Business Presenter s Innovation name Services; Professional Naperville, Title (eg.
More information5 Year Capital Projects Plan INITIAL DISCUSSION JANUARY 7, 2014
5 Year Capital Projects Plan INITIAL DISCUSSION JANUARY 7, 2014 5 Year Capital Projects Plan Provide the Board with possible major Capital Projects needed over the next 5 years. Provide the Board with
More informationRequest for Proposal
Request for Proposal *************************************************************************** PROJECT NO: - 001 PROJECT NAME: Act 32 Qualified Performance Contract ISSUE DATE: 5/25/2016 DUE DATE: 6/6/2016
More informationExecutive Director s Summary Report
Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust July 25, 2012 I. Communications a. Government Affairs The Trust has launched a Stakeholder Process for the development
More informationTHE GENERAL ASSEMBLY OF PENNSYLVANIA SENATE BILL
PRINTER'S NO. THE GENERAL ASSEMBLY OF PENNSYLVANIA SENATE BILL No. Session of 0 INTRODUCED BY McGARRIGLE, MENSCH, BLAKE, SCAVELLO, BARTOLOTTA, KILLION, RAFFERTY, DINNIMAN AND ARGALL, SEPTEMBER 0, 0 REFERRED
More informationExecutive Director s Summary Report
Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust November 19, 2014 I. Communications a. Awareness and Press Staff has scheduled the Annual Event for Thursday January
More informationProperty Assessed Clean Energy Programs and How PACE Can Benefit Your Community
Property Assessed Clean Energy Programs and How PACE Can Benefit Your Community WHAT IS PACE? Property Assessed Clean Energy (PACE) is a financing mechanism that enables low-cost, long-term funding for
More informationBiennial Report. State of Oregon Department of Energy. Small Scale Energy Loan Program
Biennial Report State of Oregon Department of Energy Small Scale Energy Loan Program Finances: July 1, 2008 through June 30, 2010 Loan Activity: Through December 31, 2010 Prepared for Governor Kitzhaber
More informationWorld Bank Presentation
World Bank Presentation State Energy Office Revolving Loan Programs Washington, D.C. February 20, 2008 Bill Nesmith National Association of State Energy Officials Loan Program Design Considerations Loan
More informationMultifamily Energy Efficiency Program
Multifamily Energy Efficiency Program Rebate Reservation Request To reserve incentives from the PNM Multifamily Energy Efficiency Program, please complete this form and return to multifamily@pnm.com or
More informationCity Sustainable Energy Plan (SEP) Financing Item 6B March 24, 2017 Board of Directors
Page 1 of 5 City Sustainable Energy Plan (SEP) Financing Item 6B March 24, 2017 Board of Directors Report: To: TCHC:2017-22 Board of Directors From: Building Investment, Finance and Audit Committee (BIFAC)
More informationEFFECTIVE IMPLEMENTATION OF IPMVP OPTION C- WHOLE BUILDING MEASUREMENT MEASUREMENT AND VERIFICATION PLANS
EFFECTIVE IMPLEMENTATION OF IPMVP OPTION C- WHOLE BUILDING MEASUREMENT MEASUREMENT AND VERIFICATION PLANS PREPARED BY TAC-TOUR ANDOVER CONTROLS TODD PORTER, KLIP WEAVER, KEVIN VAUGHN AUGUST 12, 2005 1
More informationAward of Performance Energy Engineering Services Contract
Finance, Administration and Oversight Committee Action Item III-E September 13, 2007 Award of Performance Energy Engineering Services Contract Washington Metropolitan Area Transportation Authority Board
More informationSelf-Funded Energy Management Programs
Self-Funded Energy Management Programs Joint Services Environmental Management Conference - Denver, CO March 23, 2006 Eric Ruffel, PE, CEM, LEED AP Energy Management Consultant Self-Funded Energy Projects
More informationCity of Binghamton. Challenges Municipalities Face. Binghamton Project Overview. City of Binghamton Energy Performance Contracting: Streetlights
Energy Performance Contracting: Streetlights Presented by: Chris Kalwara Account Executive Johnson Controls Direct Phone: (315) 569-9179 Challenges Municipalities Face Binghamton Project Overview Goals
More informationENERGY EFFICIENCY REVOLVING LOAN FUND
ENERGY EFFICIENCY REVOLVING LOAN FUND GUIDELINES ENERGY EFFICIENCY REVOLVING LOAN FUND The Mississippi Energy Efficiency Revolving Loan Fund, administered by the Mississippi Development Authority ( MDA
More informationBoard of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019
Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 PRESENTED BY Finance and Administration Florida Agricultural and Mechanical University 1 ACTION ITEM IV: Approval of
More informationRestructuring of the Heritage Property Tax Rebate Program
STAFF REPORT ACTION REQUIRED Restructuring of the Heritage Property Tax Rebate Program Date: May 28, 2014 To: From: Wards: Reference Number: Toronto Preservation Board Planning and Growth Management Committee
More informationFlemington Raritan Regional School District; Energy Saving Improvement Program (ESIP)
Flemington Raritan Regional School District; Energy Saving Improvement Program (ESIP) ESIP Energy Savings Plan June 11, 2012 Presenters: Jon Zeller, Account Executive Ryan Thordson, Manager Project Development
More informationPACE Financing. J. Caleb Bell, Partner Bricker & Eckler LLP
PACE Financing J. Caleb Bell, Partner Bricker & Eckler LLP 614.227.2384 jbell@bricker.com PACE Financing PACE = Property Assessed Clean Energy Ohio s PACE Law Energy SID A special type of financing district
More informationBrian J. McCarter. Profiting from the Connecticut Commercial PACE Financing Opportunity. Moderated by:
Profiting from the Connecticut Commercial PACE Financing Opportunity February 21, 2013 Moderated by: Brian J. McCarter Chairman & CEO Sustainable Real Estate Solutions, Inc. (SRS) Sponsored by: Speaker
More informationEnergy Services Coalition (ESC) Nevada Chapter. Local Public Sector ESPC Training. August 10, 2017
Energy Services Coalition (ESC) Nevada Chapter Local Public Sector ESPC Training August 10, 2017 1 Why do ESPC Projects Generate Happy Customers? Repurposes existing expenditures and invests in your own
More informationThe Sustainability Edge in Real Estate Investing
The Sustainability Edge in Real Estate Investing Commercial real estate can have a significant impact on the environment and an increasing number of real estate industry professionals are incorporating
More informationEnergy Savings Performance Contracting Program Process Description
Energy Savings Performance Contracting Program Process Description I. Program History The Energy Savings Performance Contracting (ESPC) program was developed to provide a means to install energy conservation
More informationReleased: January 8, 2010
Released: January 8, 2010 Commentary 2 The Numbers That Drive Real Estate 3 Recent Government Action 9 Topics for Buyers and Sellers 15 Brought to you by: KW Research Commentary December closed out the
More informationHow to Use Tax Strategies to Offset Dealership Construction Costs Six-figure offsets are possible if you plan carefully
How to Use Tax Strategies to Offset Dealership Construction Costs Six-figure offsets are possible if you plan carefully With Stephen Bedell, CPA of Crowe Horwath LLP Moderated by Mike Bowers, of DealersEdge
More informationPedernales Electric Cooperative
Pedernales Electric Cooperative PEC Empower Loans Member Manual PEC attempts to comply with federal and state laws regarding extensions of credit to its members. Members eligible for this financing program
More informationBruce Hobby, Associate AIA Fanning Howey George Kacan, AIA, REFP, LEED AP Fanning Howey. Contributions from: Collin Sandifer
Bruce Hobby, Associate AIA Fanning Howey George Kacan, AIA, REFP, LEED AP Fanning Howey Contributions from: Collin Sandifer TAC Agenda 1. Definitions What do we know? - What do we need to know? 2. Case
More informationBUSINESS INCENTIVE PROGRAM APPLICATION
BUSINESS INCENTIVE PROGRAM APPLICATION PART A APPLICANT INFORMATION (Financial incentive payment will be made to Applicant ONLY.) 1. Applicant: Legal Name of Business (the "Applicant"): Address: City:
More informationEnergy Efficiency Financing for the Commercial and Institutional Building Sector
Energy Efficiency Financing for the Commercial and Institutional Building Sector Dec. 5, 2013 Alex J Hill Philippe Dunsky Marina Malkova DUNSKY ENERGY CONSULTING (514) 504-9030 info@dunsky.ca OUTLINE /
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS The SMART FAQS are provided to answer questions regarding the SMART Initiative and will be updated on an ongoing basis. On November 4, 2014, Broward County voters approved a
More informationLEE COUNTY SCHOOL DISTRICT S CAPITAL PLANNING PROCESS
LEE COUNTY SCHOOL DISTRICT S CAPITAL PLANNING PROCESS A Capital Projects Management Team has been established consisting of the Superintendent, the Chief Administrative Officer, the Chief Academic Officer,
More informationGuaranteed Energy Savings Program (GESP) February 21, CERTS Conference
Guaranteed Energy Savings Program (GESP) February 21, 2013 2013 CERTS Conference Facility Issues Growing Deferred Maintenance Occupant Comfort and Productivity Health, Safety and Environmental Energy Price
More informationDepartment of Energy South Africa
Department of Energy South Africa Policy to support the Energy Efficiency and Demand Side Management Program for the Electricity Sector through the Standard Offer Incentive Scheme Draft: March 2010 1 TABLE
More informationGUARANTEED LONG-TERM SAVINGS PERSISTENCE AN OWNER S PERSPECTIVE
GUARANTEED LONG-TERM SAVINGS PERSISTENCE AN OWNER S PERSPECTIVE Tarek Bou-Saada, CEM Energy Manager Texas Health and Human Services Commission Charles Culp, Ph.D., P.E. Assoc. Professor, Dept of Architecture
More informationPACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY
PACE PROGRAM GUIDELINES TEXAS PACE AUTHORITY VERSION 3.0 13 January 2018 TABLE OF CONTENTS OVERVIEW... 3 STATUTORY AND PROGRAMMATIC REQUIREMENTS... 4 PACE PROJECT PROCESS... 6 HOW PACE PROJECTS ARE ASSESSED...
More informationUNIVERSITY of HOUSTON MANUAL OF ADMINISTRATIVE POLICIES AND PROCEDURES
UNIVERSITY of HOUSTON MANUAL OF ADMINISTRATIVE POLICIES AND PROCEDURES SECTION: Facilities Number: 09.04.04 AREA: Facilities Management and Maintenance Information SUBJECT: Maintenance Project Evaluation
More informationDelivering Efficiency as a Service: The Metrus ESA
Delivering Efficiency as a Service: The Metrus ESA May 22, 2018 Overview Metrus develops, finances, owns, and operates large-scale efficiency projects for Fortune 500 companies and major industrial customers.
More informationArkansas Energy Technology Loan
Arkansas Energy Technology Loan 2015 Program Guidebook Easy Energy Financing for a Sustainable Tomorrow. A r k a n s a s E c o n o m i c D e v e l o p m e n t C o m m i s s i o n - E n e r g y O f f i
More informationRichmond Building Energy Challenge
Richmond Building Energy Challenge Robert Greenwald, P.Eng., MBA, President (Principal) Robert Greenwald has 25 years of energy management experience including developing energy plans, determining opportunities,
More informationAMERESCO INVESTOR PRESENTATION JANUARY 2019
AMERESCO INVESTOR PRESENTATION JANUARY 2019 SAFE HARBOR Forward Looking Statements Any statements in this presentation about future expectations, plans and prospects for Ameresco, Inc., including statements
More informationQuarterly Report to the Pennsylvania Public Utility Commission
Quarterly Report to the Pennsylvania Public Utility Commission For the Period June 2014 through August 2014 Program Year 6, Quarter 1 For Pennsylvania Act 129 of 2008 Energy Efficiency and Conservation
More informationCity of Coolidge 130 W. Central Avenue Coolidge, Arizona (520) TDD: (520) / Fax: (520)
REQUEST FOR PROPOSALS Energy Performance Contracting Services INTRODUCTION The City of Coolidge will accept competitive sealed proposals for energy performance contracting services at the address or physical
More informationENERGY EATING INTO EBIT
A Power Efficiency White Paper ENERGY EATING INTO EBIT A report on the board-level need for energy representation THE SOLUTION This paper provides an insight into the issues which senior directors will
More informationREQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ #
Name: Lackawanna County Address: 200 Adams Ave Address: Scranton PA 18503 Introduction REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ # 345-12-1 Lackawanna County is requesting Qualifications
More informationUsing GRESB to leverage investment portfolio sustainability+ Goodman sustainability case study
Using GRESB to leverage investment portfolio sustainability+ Goodman sustainability case study Sustainability at Goodman Sustainability at Goodman Over the last 5-10 years, the investment community has
More informationExecutive Director s Summary Report
Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust July 20, 2016 1. Communications A.) Awareness and Press Outreach Events o Save the date for the Trust s Combined
More informationEU Funding for Sustainable Energy
EU Funding for Sustainable Energy 2014-2020 Green Economy e sostenibilità energetica Bologna, 17 September 2013 Hugh GOLDSMITH European Commission Directorate-General for and Urban 1 From 2007-2013 Cohesion
More information