GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD TARIFF ORDER. Case No.897/2006

Size: px
Start display at page:

Download "GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD TARIFF ORDER. Case No.897/2006"

Transcription

1 GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD TARIFF ORDER Case No.897/2006 Gujarat Energy Transmission Corporation Limited (GETCO) 31 st March 2007 i

2 C O N T E N T S Chapter Title Pate No. 1 Introduction 1 2 Summary of GETCO Tariff Petition 5 3 Brief Outline of objections raised, response 7 of GETCO and Commission s comments 4 Compliance of Directives 23 5 Transmission System of GETCO and its 31 performance 6 Annual Transmission Charges 41 7 Directives 59 ii

3 List of Tables Table Title No. 1. Project Annual Transmission Charges 2. Net Annual Transmission Charges Projected by GETCO 3. Transmission System of GETCO Network Additions during the years & Existing capacity of GETCO Loading of Transmission System 7. Likely load addition during Likely loading of GETCO Transmission System Availability of GETCO Transmission System 10. Energy input and drawal and Transmission loss Projected Energy Transmission & Losses Proposed Capital Expenditure Funding of Capital Expenditure Final Opening Balance Sheet of GETCO 15. Manpower Cost 16. Projected Repair and Maintenance Expenses 17. Administrative and General Expenses O&M Charges 19. O&M Charges Approved by the Commission 20. Loans and Interest on Loans 21. Interest on loan approved by the Commission 22. Calculation of Depreciation FY Assets Capitalization and Depreciation approved by the Commission Calculation of Advance Against Depreciation by GETCO Interest on Working Capital 26. Interest on Working Capital Approved by the Commission Return on equity claimed by GETCO 28. Return on Equity Approved by the Commission 29. O&M charges for dedicated Transmission Lines 30. Details of Other Income 31. Annual Transmission Charges 32. Annual Transmission Charges iii

4 BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT AHMEDABAD Case No. 897/2006 Date of Order 31 st March 2007 Quorum Shri G. Subba Rao (Chairman) Dr. Man Mohan (Member) ORDER 1. INTRODUCTION 1.1 Back ground The Government of Gujarat unbundled and restructured the Gujarat Electricity Board with effect from The Generation, Transmission and Distribution businesses of the erstwhile Gujarat Electricity Board were transferred to seven successor companies. The seven successor companies are as follows: i) Gujarat State Electricity Corporation Limited (GSECL) A Generation Company. ii) Gujarat Energy Transmission Corporation Limited (GETCO) A Transmission Company Four Distribution companies iii) Dakshin Gujarat Vij Company Limited (DGVCL) iv) Madhya Gujarat Vij Company Limited (MGVCL) v) Uttar Gujarat Vij Company Limited (UGVCL) 1

5 vi) vii) Paschim Gujarat Vij Company Limited (PGVCL) and Gujarat Urja Vikas Nigam Limited (GUVNL) A Holding Company and it is also responsible for purchase of electricity from various sources and supply to Distribution Companies The Government of Gujarat vide notification dated 3 rd October 2006 notified the final opening balance sheets of the transferee companies as on 1 st April 2005, containing the value of assets and liabilities, which stand transferred from erstwhile Gujarat State Electricity Board to the transferee companies including Gujarat Energy Transmission Corporation Limited (GETCO). Assets and liabilities (Gross block, loans and equity) of Transmission facilities of GEB have been considered by the Commission based on the Financial Restructuring Plan (FRP) approved by Government of Gujarat. The last petition filed by GETCO was prepared considering on as available basis FRP data. The present petition (second petition) has incorporated the latest FRP data to arrive at the assets and liabilities of Transmission facilities. The company has started functioning w.e.f. 1 st April 2005 with an opening Balance Sheet as on 1 st April 2005 notified by the State Government on 3 rd October GETCO gave a presentation on its proposal to the Commission on 18 th January The Commission obtained further information and clarifications from GETCO. GETCO furnished supplementary information after the presentation and also further information / data as required by the Commission on a detailed study of the petition. 1.2 PUBLIC NOTICE AND PUBLIC PARTICIPATION PROCESS The Public Notice regarding Petition No.897/2006 was published by GETCO in the Indian Express (English daily) and Sandesh (Gujarathi daily). Through this notice, the public were invited to forward objections and suggestions on the petition. The public notice in the newspapers were published on January 3 rd, 2007 and time was given to the public up to February 3 rd, 2007 for forwarding their suggestions / objections. 2

6 1.2.2 The Commission has received six objections to the petition filed by the GETCO. The Commission considered these objections received and sent communication to the objectors inviting them to take part in the public hearing process by presenting their views in person before the Commission. Each objector was provided with a time slot on the days of public hearing from 19 th to 22 nd February 2007 for presenting their views on GETCO petition before the Commission at the Court Hall, Commission s office in Ahmedabad. The names of persons and organizations who filed these objections are as follows: 1. Laghu Udhyog Bharati Gujarat, Ahmedabad. 2. Indian Wind Energy Association, New Delhi. 3. Gujarat Alkalis and Chemicals, Vadodara. 4. Gujarat State Fertilizers and Chemicals Limited, Vadodara. 5. Torrent Power Limited, Ahmedabad. 6. Mr Raj Tillan. All the above persons presented their objections during public hearing also. The main issue which objector raised about this petition and GETCO s responses to these at the public hearing are briefly outlined in chapter Taking into account the following responses, the Commission condones the delay in filing the tariff petition by GETCO and other successor entities of GEB. Government of Gujarat has notified opening balance sheet of all companies on the basis of FRP in the month of October Hence Accounts for the year were finalized in the month of November / December 2006 and the petition for the year was to be prepared and submitted on the basis of finalized Accounts for the year

7 1.2.4 State Advisory Committee Meeting A meeting of the State Advisory Committee (constituted under Section-87 of the EA, 2003) was convened on 9th February A presentation was made on the petitions of GSECL/GETCO and four Discoms. The Chairperson of GUVNL/GSECL/GETCO had made a presentation on the salient features of the ARR petitions. 4

8 2. Summary of GETCO Tariff Petition 2.0 Summary of GETCO Tariff Petition Gujarat Energy Transmission Corporation (GETCO) submitted the petition on 28 th December 2006 seeking approval for Annual Revenue Requirement and determination of Transmission charges for the year The transmission charges are to be recovered mostly from Gujarat Urja Vikas Nigam Limited (GUVNL). GUVNL purchases power from GSECL, Central Sector Generating Stations, IPPs and other sources and supplies to the Distribution Companies and licensees in Gujarat GUVNL has an agreement with GETCO for transmission of power from GSECL generating stations, IPPs, input points of Power Grid Corporation and other interconnecting points for supply to DISCOMs and licensees. The transmission charges are also recoverable from the other users of the Transmission network of GETCO. GETCO has projected a Revenue Requirement of Rs lakhs for the year as detailed in Table-1 below: Table-1 Sl.No. Details Project Annual Transmission Charges (Rs. lakhs) Cost (Rs.lakhs) 1. Employee Cost Repairs and Maintenance Administrative and General Expenses ULDC charges Depreciation Advance Against Depreciation Interest on loans Interest on Working Capital Return on Equity Total Fixed Costs Less Expenses Capitalized Total Transmission charges 100, Less other income Net Annual Transmission charges

9 The projected transmission charges per MW per day based on capacity to be handled would be as under Table-2 Net Annual Transmission Charges Projected by GETCO Sl.No. Particulars Unit Loading of Transmission System as TSA MW Capacity for calculation of transmission MW 9981 charges 3. Cost of Transmission Rs. lakhs Proposed Transmission Charges Rs./MW/day* 2705 Rs./MW/month Existing Transmission Charges Rs./MW/day Increase proposed (%) (-)04.47 * 366 days in The ARR indicated above is exclusive of income tax, incentives, any statutory taxes, levies, duties, cess, any other surcharges etc. GETCO sought Commission s approval for - (1) The Net Annual Transmission charges proposed at Rs lakhs. (2) Transmission per / MW/per day. (3) Operation and Maintenance Charges from users of dedicated transmission lines. (4) Capital Expenditure proposed. 6

10 3. Brief Outline of Objections raised, Response of GETCO and Commission s Comments 3.1 The summary of objections raised by various objectors, response of GETCO and the comments of Commission are briefly given below: I. Objector / Objectors: Laghu Udyog Bharati, Ahmedabad. The objections raised briefly are: 1. Fixing of transmission charges There is no need to make any change in the transmission charges. If ARR projections are made on realistic basis then there would be no gap. 2. O&M charges In the case of Transmission lines feeding dedicated consumers, all expenses are covered while computing ARR inclusive of O&M charges. This will be a case of double charging. The demand for O&M charges is not in accordance with the Electricity Act, 2003 and the GERC guidelines. As such it is required to be quashed. 3. Parallel operation charges As GETCO is not in a position to show what its system PF is and what the CPP s supply PF is the reason given for low PF of CPPs is imaginary. 4. Transmission losses GETCO has not been able to achieve 4.27% transmission losses approved by the Commission for Reduction of loses can be achieved by taking up Energy Audit. 5. Depreciation: 7

11 The presentation of GETCO for depreciation is incorrect. The Commission may look into this aspect, since many lines, transformers and substations have completed their useful life. 6. Energy Audit (i) (ii) Existing meters are not functioning properly. High accuracy meters need to be provided on all feeders to assess feeder wise losses. GETCO shall itself seek accreditation as certified energy auditors and establish its own energy audit wing of Bureau of Energy Efficiency (BEE) Certified Energy Auditors. All the steps of energy saving measures shall be taken under the guidance of its energy audit wing. 7. Reactive compensation (i) GETCO should provide adequate reactive compensation by installing static capacitors etc to meet the reactive power requirements of the system to improve the voltage levels and reduce transmission losses. (ii) GETCO has not submitted the PF of the system, feeder-wise, the details of auto control of reactive power and savings actually made. Response of GETCO: 1. The estimation of ARR has been submitted on the basis of established norms. The proposed transmission charges work out to be lower compared to the prevailing charges. 2. O&M charges are not included in the calculation of transmission charges. However, actual revenue realized will be considered under other income and the ARR will be adjusted to that extent in future. 3. The petition for approval for Parallel Operation Charges is before the Commission and hence, the impact of POC has not been considered in this petition. 4. The actual status of the Transmission losses is 4.35%, which is lower than in some other states - Uttar Pradesh (4.97%) and Andhra Pradesh (6.02%). Further reduction of losses is difficult despite sincere efforts being made to reduce the loss and hence the loss of 4.35% has been proposed. 8

12 5. GETCO has not furnished the O&M charges, Supervision charges in respect of dedicated lines. 6. Depreciation shall be computed according to norms (terms and conditions of tariff) of CERC/GERC till 90% of the Historical cost of the asset. Depreciation has been estimated with the consideration of actual position of assets notified by the government in the opening balance sheet. 7. GETCO has not responded to the issue relating to energy audit. 8. In compliance to the directives, the installation of reactive compensation is being implemented Commission s Comments: GETCO has not responded to the issue relating to conduct of energy audit. It is necessary to conduct energy audit feeder-wise to arrive at realistic losses and take necessary steps for loss reduction. The Commission considered the other issues raised by the objector and the response of GETCO later in the order. II. Objector / Objectors: Indian Wind Energy Association, New Delhi. The objections raised are: 1. O&M charges from dedicated users of transmission system: There is no provision in GERC Regulations or orders to levy O&M charges from dedicated users of Transmission lines. (i) The Commission shall direct the GETCO to substantiate its proposal to levy such charge within the regulatory framework. (ii) If O&M charges are levied, it would amount to excess recovery (iii) Any charges or tariff shall reflect cost and have certain basis for recovery of underlying costs. (iv) The Commission may direct the GETCO to furnish cost data and revenue collected for and (v) It would not be appropriate to recover O&M charges for dedicated transmission lines based on O&M norms of GERC and they may be determined at 15% of O&M cost norm as proposed by the GETCO. 9

13 (vi) The wind energy developers would need to adequately compensate for O&M costs associated in the evacuation infrastructure. 2. Supervision charges (i) The Commission may direct the petitioner to furnish details of supervision charges during and as the connected transmission lines are old and depreciated. (ii) Supervision charges of 15% shall be levied only on labor component and not on capital equipment cost of the evacuation infrastructure with a ceiling limit that Labour component shall not exceed 5% of capital cost. (iii) The petitioner should furnish details of revenue earned by way of levy of supervision charges during and Response of GETCO: The Indian Wind Energy Association raised issue, which pertain to concessions etc to promote non-conventional energy (wind farms). These may be de-linked from the tariff hearing and considered separately. Commission s Comments: Regarding Supervision Charges, during the course of hearing, GUVNL representative mentioned that the issue of Supervision charges was taken up with the Government as the Indian Wind Energy Association (InWEA) had represented before the Government. In a High level meeting headed by the Chief Secretary, Government of Gujarat, it was decided that the Supervision Charges for Wind energy generators may be reduced to 7.5% from 15%. As such this issue is already been redressed, the Commission feels that there is no need to relook at this stage. The other points which the Indian Wind Energy Association raised are examined later in the order. III. Objector/Objectors: Gujarat State Fertilizers & chemicals Ltd. Vadodara. 10

14 The objections raised are: 1. Applicability of transmission charges: The proposed transmission charges cannot be made applicable to the intervener mutatis mutandis to an ordinary consumer as the intervening transmission lines are financed by intervener company. The cost contribution by the intervener company cannot be ignored. The Commission shall provide some relief to the intervener company for its contribution. Though a double circuit line is laid to the intervener s manufacturing unit, power supply is not being made on that line. Hence the rate of depreciation proposed is unreasonable and unjustified. 2. Methodology and calculation of ARR: a) Depreciation Rate of depreciation proposed is not correct, it is unreasonable and unjustified as the connected transmission lines are old and depreciated. b) Return on equity The return on equity cannot be considered for determining transmission charges in the case of intervener who has certain assets financed. c) O&M and other charges Except O&M charges, no other charges can be levied on the intervener. d) Income tax Income tax on surplus revenue generated cannot be and should not be under equity and law be passed on to the consumers / beneficiaries including intervener, from whom the revenue is generated. 3. Transmission losses 11

15 The proposed increase in transmission losses from 4.27% to 4.35% may not be allowed and the same may be fixed at 4.12% or such lower percentage. 4. Parallel operation charges The levy of parallel operation charges, in addition to existing contract demand charges, wheeling charges and transmission losses may not be permitted. 5. Supply of power The petitioner is supposed to supply of power to the intervener as per the MOU with GSFC. Response of GETCO: 1. The intervener might have invested for grid connectivity at the required point. It is well settled that the transmission assets established are the properties of the licensee concerned, notwithstanding that a part of the cost of establishing the same is contributed by any consumer. 2. The capital base of the petitioner is according to the transfer value and financials which the Government of Gujarat notified. And this is a statutory notification binding on all. Accordingly, for all purposes including for the determination of the amount on which depreciation is to be allowed, the above values have to be considered. The allegations to the contrary are wrong and are denied. 3. The equity as given by the government is considered at the beginning of FY to arrive at the return on equity. 4. The intervener is also utilizing the transmission network of petitioner by virtue of permitted allocations and therefore should be treated at par with other users of the transmission network and has to be charged at par with others. The actual position of assets as notified by the government in the opening balance sheet has been considered for the purpose of depreciation. 12

16 5. The weighted average rate for depreciation for FY works out to be 3.37%. 6. Income tax recovery has been proposed as in the GERC (Terms and Conditions of tariff) Regulations, The actual status of the Transmission losses is low compared to other states for instance Uttar Pradesh (4.97%) and Andhra Pradesh (6.02%). Further reduction of losses is difficult despite sincere efforts being made and hence the loss of 4.35% has been proposed. 8. A petition is pending for the approval of Parallel Operation Charges is before the Commission and the impact of same has not been considered. 9. Under Open Access Regulations, 2005, there cannot be discrimination among the beneficiaries. Commission s Comments: The issues raised by the Intervener / Objector regarding depreciation and return on equity on consumer contribution will be examined with reference to the Regulations. As a separate petition has been filed by the GSFC in some of the above matters, it will be decided after hearing the parties. IV. Objector/Objectors: Gujarat Alkalies & Chemicals Ltd. Vadodara. The objections raised are: 1. Applicability of transmission charges: The proposed transmission charges cannot be made applicable to the intervener mutatis mutandis to an ordinary consumer as certain transmission lines supplying power to their Vadodara Complex are financed by intervener company. 2. Methodology and calculation of ARR: a) Depreciation Rate of depreciation proposed is unreasonable and unjustified as the transmission line feeding the load is more than 30 years old. b) Return on equity: 13

17 The return on equity cannot be considered for determining transmission charges in the case of intervener company as certain assets have been financed by them. c) O&M and other charges Except O&M charges, no other charges can be levied on the intervener. d) Income tax Income tax on surplus revenue generated cannot be and should not be under equity and law be passed on to the consumers / beneficiaries including intervener, from whom the revenue is generated. 3. Transmission losses The proposed increase in transmission losses from 4.27% to 4.35% may not be allowed and the same may be fixed at 4.12% or such lower percentage. 4. Parallel operation charges The levy of parallel operation charges, in addition to existing contract demand charges, wheeling charges and transmission losses may not be permitted. 8. Supply of power The petitioner is supposed to supply of power to the intervener in accordance with the MOU entered between the erstwhile GEB and GPPCL and participating industries. Response of GETCO: 1. The intervener might have invested for the grid connectivity at required point. It is well settled that the transmission assets established are the properties of the 14

18 licensee concerned, notwithstanding that any part of the cost of establishing the same is contributed by any consumer. 2. The capital base of the petitioner is according to the transfer value and financials notified by the Government of Gujarat, which is a statutory notification binding on all. Accordingly to all intents and purposes including for the determination of the amount on which depreciation is to be allowed, above value has to be used. The allegations to the contrary are wrong and are denied. 3. The equity as given by the government is considered at the beginning of FY to arrive at the return on equity. 4. The intervener is also utilizing the transmission network of petitioner by virtue of permitted allocations and therefore should be treated at par with other users of the transmission network and has to be charged at par with others. The actual position of assets as notified by the government in the opening balance sheet has been considered for the purpose of depreciation. The weighted average rate for depreciation for FY works out to be 3.37%. 5. Income tax recovery has been proposed as in the GERC (Terms and Conditions of tariff) Regulations, The actual status of the Transmission losses is low compared to some other states for example, Uttar Pradesh (4.97%) and Andhra Pradesh (6.02%). Further reduction of losses is difficult despite sincere efforts being made and hence the loss of 4.35% has been proposed. 7. A petition for the approval of Parallel Operation charges is pending before the Commission and the impact of same has not been considered. 8. Under Open Access Regulations, 2005, there cannot be discrimination among the beneficiaries. Commission s Comments: The issues raised by the intervener / objector regarding depreciation and return on equity on consumer contribution will be examined with reference to the Regulations. As a separate petition has been filed by the GACL in some of the above matters, it will be decided after hearing the parties. V. Objector/Objectors: Torrent Power Ltd. Ahmedabad The objections raised in brief are: 15

19 1. Energy balance The energy sent out to Ahmedabad and Surat as also the energy accounted by DISCOMs are not tallying with actuals. The Commission should therefore direct the petitioner to provide reconciliation of energy balance to arrive at a correct figure of transmission losses. 2. Transmission losses: (i) The Commission may approve transmission losses for after arriving at current level of transmission losses, after reconciling the actual figurers for and estimated figures for and (ii) The Commission may direct the petitioner to clarify whether transmission losses calculated are upto 66 kv only or include the losses of 11 kv feeders supply for power to DISCOMs. (iii) The Commission may direct the petitioner to provide the details of voltage level wise transmission losses. 3. Transmission charges (i) The Commission may determine recovery of transmission charges on voltage level basis also. (ii) The Commission may consider the revenue from O&M charges and parallel operation charges while determining the transmission charges. 4. Transmission tariff: The Commission may consider the reasonableness of expenditure while determining the transmission charges so as not to burden the consumers. GETCO Response: 1. According to the accounting method of SLDC, the energy purchased by AEC and SEC during April to November was being accounted under the heads of UGVCL and DGVCL respectively. However, the energy purchased by AEC and SEC during December to March was accounted under the heads of GUVNL. 16

20 Thus, the energy balance has been checked and there is no discrepancy in computation of overall transmission loss as the total energy balance remained unchanged. 2. Based on the actual figures of transmission for the year , energy balance is as follows: Energy received MUs. Energy sent MUs. Transmission losses 2224 MUs. Percentage losses 4.35% Transmission losses are worked out up to L.V. side of power transformers only. The transmission losses are not being computed and accounted on voltage level basis. 3. Parallel operation charges are yet to be determined by the Commission and hence that impact has not been considered. However, revenue realized from this shall be taken under the income and the ARR would reduce to that extent in the future. 4. The voltage level losses are not available. But the transmission charges have to be kept uniform independent of voltage. Commission s Comments The issues raised by the objector have been examined and appropriate decisions are taken while determining the transmission charges. Suitable directions will also be issued to the petitioner to conduct proper energy audit to arrive at voltage-wise losses. VI. Objector/Objectors: Raj Tillan The objector has raised a number if issues, some are related to the present tariff petition and some for seeking additional information/clarifications in general from GETCO. The objections related to the present petition are briefly summarized below: 17

21 1. It is not disclosed in the tariff petition whether GUVNL is a trading licensee. If under the restructuring scheme of the Government of Gujarat, GUVNL gets the status of a sole holding company of the unbundled entities and a deemed trading licensee, the same is not tenable in terms of section 131 of the Electricity Act Diluting the concentration of conflicting function (Regulatory and Commercial) is one of the main aims of Electricity Act Segregation of licensee and utility should have been done since 1 st June 2004 when the Government of Gujarat declared GETCO as the State Transmission Utility. 3. The revenue requirement for FY is Rs. 10,058 million whereas the same was Rs million in the previous year. This translates to a growth of 19.2% not in line with a modest load growth of 4%. 4. The details of revenue break up from core and non-core business is not given. Further it would be helpful to know the accounting of inadvertent flow of energy from CPPs or wind generation and if this goes in reducing the transmission losses or otherwise. 5. The details of O&M charges from dedicated transmission users is missing 6. The Commission may direct the petitioner to make a full and unshielded disclosure that they are not charging parallel operation charges. 7. Considering month wise availability, the months with the highest and the months with the lowest line availability may be shown. Whether availability calculation includes planned shutdown or otherwise. 8. The load growth is too low. It is essential to justify the low load growth. 9. The wheeled units stated are 1538 MU. It is not clear if these units are from CPP or purchased units from CPP or inadvertent flow or sum of all. 10. Most of the transmission lines have bi-directional flow. This means double counting of transmission capacity. How is transmission capacity defined? 18

22 11. The transmission losses are shown to be lower than that of Uttar Pradesh or Andhra Pradesh. This does not give a true picture as the calculation of the same depends on many factors like degree of loading vis-à-vis capacity, configuration of network, relative location of generating stations and load etc. 12. O&M cost being critical, comparison must be made with equally well-managed utilities from neighboring states. 13. The renovation and modernization expenditure should be disallowed, as the asset value does not justify this expenditure. 14. For exercise on energy balance, energy audit looks a good idea but high cost meters may be deployed only when low losses are being reduced further. 15. Performance of metering under the operating condition does not measure up to the required accuracy as the burden on CT and PT are quite high. 16. The petitioner should furnish cost data for reactive power before allowing for charging the same. In addition certain suggestions are also made by the objector. Response of GETCO: Some of the objections listed above are also raised by other objectors for which GETCO has responded as narrated earlier. The response of GETCO to the objectors are given here briefly. 1. As the Intervention Petition is vexatious, GETCO is dealing with certain specific issues which are related to GETCO. In this affidavit not venturing into other aspects of the Intervention Petition which have no relevance to the petition filed by GETCO. However, specifically deny all the allegations, imputations and insinuations contained in the Intervention Petition. 2. The Annual Revenue Requirements and consequently the tariff for GETCO are to be decided according to the provisions of the Electricity Act, 2003, to the extent applicable the provisions of the Gujarat Electricity Industry Reorganization and Reforms Act, 2003 (the State Act), the Rules and Regulations framed therein and taking into account the National Electricity Policy and the Traffic Policy notified by the Central Government under section 3 of the 19

23 Electricity Act, The Intervenor cannot raise issues on various policies or as to the structure of re-organization adopted in the State of Gujarat under the provisions of the Electricity Act, Reference to the policy adopted in the United States of America or otherwise in other countries are totally irrelevant and outside the scope of the jurisdiction of this Hon ble Commission in the present petition. 3. In accordance with the provisions of the Electricity Act, 2003, GETCO is entitled to claim tariff and charges, namely, the transmission charges, parallel operation / grid support charges, re-active energy charges and any other charges related to the utilization of the services of GETCO or for the benefit derived by any person by use of the transmission system and the facilities of GETCO. If the contention of the Intervenor is that some of the services rendered by GETCO do not fall within the purview of the Electricity Act, 2003, the implication would be that GETCO is free to refuse to give such services and GETCO cannot be compelled to provide such services by any Order passed by this Hon ble Commission. In that event, such services would be covered by section 41 of the Electricity Act, 2003, namely, other businesses of GETCO and, therefore, GETCO is free to charge the beneficiaries of such services any amount as GETCO may consider appropriate. It is, therefore, not correct on the part of the Intervenor to contend that GETCO is obliged to provide certain services as the Transmission Utility but at the same time GETCO is not entitled to either claim tariff from the Hon ble Commission for such services or otherwise is not entitled to claim charges from the beneficiaries of such services under the Bilateral Agreement. The arguments to the contrary raised by the Intervenor are selfdefeating and have no merits. 4. GUVNL and DISCOMs are licensees and are entitled to approach this Hon ble Commission for their respective tariff and charges. The present petition is confined to the tariff and charges payable for the services rendered by GETCO. 5. In the present petition before this Hon ble Commission, GETCO has impleaded GUVNL as Respondent in view of the fact that the transmission services pertaining to transmission and conveyance of electricity to the distribution system and network is undertaken by GETCO and such services are not 20

24 provided by GUVNL. It is wrong and denied that there is any collusion between GETCO and GUVNL as alleged. 6. GETCO is not trading in electricity. GETCO performs only transmission services for which it is entitled to claim tariff and charges. The allegations to the contrary are specifically denied. 7. The present petition has been filed for determination of Annual Revenue Requirements of GETCO. Based thereon, the applicable tariff needs to be determined to meet the Annual Revenue Requirements. 8. GETCO is the State Transmission Utility and is the main transmission company in the State of Gujarat. The status of GETCO is recognized under section 39 of the Electricity Act, GETCO is also undertaking the statutory functions of the State Load Despatch Centre in terms of Section 33 of the Electricity Act, In terms of section 14 of the Electricity Act, the State Transmission Utility is deemed to be the transmission licensee. There is no need as at present for segregation of the functions of the licensee and the transmission utility. GETCO has been notified by the Government of Gujarat as the State Transmission Utility. It is for the Government of Gujarat to consider as to whether any other entity should be notified as such as either the State Transmission Utility or to operate the State Load Despatch Centre. The issue raised by the Intervenor in this regard in the present petition is wholly outside the purview of the present proceedings. 9. GETCO has filed the revenue requirements in the format prescribed by the Hon ble Commission. GETCO has given all the requisite details. It is wrong and denied that GETCO has concealed any particulars. The allegations in this regard made by the Intervenor are specifically denied. 10. The transmission lines of GETCO are being used for the purpose of transmission of electricity of GUVNL and are also available to open access consumers in accordance with the regulations framed by the Hon ble Commission. In any event these issues sought to be raised by the Intervenor are totally outside the 21

25 purview of the present proceedings. GETCO is acting in accordance with the regulations framed by the Hon ble Commission. 11. The issues sought to be raised by the Intervenor on the various provisions of the Transfer Scheme and arrangements made are again outside the purview of the present proceedings. Commission s Comments: Various issues raised by the objector and the response of the GETCO are examined and appropriate decisions taken by the Commission while determining the transmission charges. 22

26 3.2 Other Objections / Issues The Union Territory of Dadra & Nagar Haveli, Silvassa and Union Territory of Daman & Diu GETCO raised the issue of non receipt of transmission charges from the Union Territory of Dadra & Nagar Haveli and also from Union Territory of Daman & Diu for the use of GETCO transmission system for transmission of Central Sector Power to them. GETCO has also made the Union Territory of Dadra & Nagar Haveli and the Union Territory of Daman & Diu as respondents to this petition. During the course of hearing representative of abovementioned Union Territories asked for time to submit objection in the above matter. The Commission gave time up to 15 th March However, for the above matter, the Union Territories filed separate petitions (No /2007); the Commission will address this issue separately. Pro-rata Charges: Some of the objectors stated during the hearing that recently GETCO has issued a Commercial Circular No. 1 wherein they have proposed to recover pro-rata Charges depending upon the voltage level. The Objectors further mentioned that the LT, HT and EHT consumers are the consumers of Distribution Licensee and not of the GETCO. Therefore GETCO has no authority to recover such Pro-rata Charges. They also stated that earlier erstwhile GEB was charging a Development Charge of Rs. 900/KVA which is now discontinued. With this new circular it appears that the earlier Development charge is now reintroduced and these charges are comparatively high. The GETCO has replied to this objection stating that they are investing in the Transmission System and if don t get such charges than development of Transmission System would have adversely affected. They have also mentioned about the relevant provision of the Regulation No. 9 of Commission s View: 23

27 As this issue required detailed analysis, the Commission is of the view that this can be looked into separately at the later stage. However, GETCO was requested to reconsider this issue on its own. Now it has been informed to the Commission that the Pro-rata Charges have been reduced from around Rs to around at Rs per KVA. 24

28 4. Compliance of Directives 4.1 Compliance of Directions issued by the Commission. The Directives issued by the Commission in its Tariff Order dated 6 th May, 2006 and their compliance by GETCO are detailed below: Directive 1: Transmission Plan GETCO shall prepare transmission plan for XI Plan Period and submit for approval of the Commission. The plan shall cover (i) the transmission lines required for evacuation of power from new generating stations coming up in the State and input points of PGCIL to transmit the power to various load centers in the State (ii) System augmentation required to improve the reliability of the system, reduce the loss, and improve the voltage levels etc. The transmission plan shall be supported by cost benefits analysis. Compliance / Action Taken : Transmission plan for XI th plan period is under preparation and the same shall be submitted to the commission on its finalization GETCO shall keep in mind the specific points mentioned in the directives. Comments of the Commission: The Transmission plan may be submitted early. Directive-2: Energy Audit GETCO is managing transmission system covering 400, 220, 132 and 66 kv voltages. High accuracy meters shall be provided on all the feeders to assess feeder-wise loss, transformation loss at each sub-station. This will help in identifying high loss feeders / areas to take corrective action to reduce the loss. The energy audit will also bring up whether the meters provided for EHV consumers (66 kv and above) are functioning properly. The status of providing meters on all the feeders, the analysis of the data obtained based on meter readings, voltage-wise and feeder-wise losses and feeders which have high level of losses and action initiated to reduce the loss shall be submitted to the Commission by 30th September Compliance / Action Taken: The installation of high precision static meters on the feeders at all sub stations is in final stage of completion. The common polling software for automatic polling of the meter data into substations PC is also under installation at the sub satiations. The 25

29 performance of pilot common polling software for automatic polling the data is under observation. Feeder wise loss and transformer loss at each substation is presently being monitored at Sub station / division level and immediate corrective actions are being taken in consultation with the next higher authority for controlling the same within range of 3%. Further the losses are being consolidated circle wise and overall losses are analyzed. Based on this analysis, lapses are identified and the same are attended immediately. The status of providing such meters is as under: Out of nos. of high accuracy static meters received till date, nos. of meters are installed and Order for 1700nos. of meters and its accessories is already placed. Procurement of balance computers with UPS,Printers etc is also under process. Comments of the Commission: Action taken in providing high accuracy meters is noted. Based on the metering provided, feeder-wise and voltage-wise losses may be arrive at. Directive 3: R&M of Transmission System It would be necessary to refurbish the transmission system including replacement of conductors on certain transmission lines, upgrading of transmission lines, replacement of aged, obsolete switch gear etc. Action Plan for the R&M of transmission system shall be submitted to the Commission by September Compliance / Action Taken: R & M of the transmission has already been taken up. Brief details of the activities that have been initiated for R & M work are as under: 1. One to one replacement: Orders have been placed for the equipments for one to one replacement for Phase I and Phase II The expenditure for Phase I for is Rs Crores. Out of 8 (Lots) orders M /s ABB (Lots III) have already started supply of 66 kv breakers and their installation. So far inspection of 67 Nos. of breakers is carried out. The installation work is under progress. 2. Strengthening of 132 KV bus at 220 KV Ranasan s/s The estimated amount for this work is Rs crore. Civil work has already been started. The drawings for bus structure are under process of approval. The tenders are invited. The procurement of equipment is under progress. 3. Providing of 66KV breakers, CTs at various substations: At some of the substations 66 KV breakers & CTs are not provided in the initial stage. Hence Rs. 4 crore is allocated in the budget for providing 66 Kv breakers 26

30 and CTs during the year Some of the breakers and CTs have been allotted from available stock in construction store. For balance requirement, procurement is under process. 4. Replacement of equipments against old equipment, augmentation of substation capacity, strengthening of EHV line by replacement of conductor, earth wire, insulator etc. The work of strengthening of 132KV line is completed and the work of balance 66 KV line will be completed by November 2006 for R&M work. The augmentation of substations will be carried out based on availability of transformers. Also the old equipment considered for replacement will also be replaced during the year on availability of equipment. Specific budget provision made for this work is Rs crores. 5. Purchase of equipment for condition monitoring of s/s, Hotline maintenance, safety purpose: The safety articles viz hand gloves, helmets, earthening rods, safety bolts etc are inspected and DI is issued. Balance quantity is expected for inspection shortly. The work orders for testing equipments are already placed and materials for the same will be available. For balance testing equipments, tenders are to be invited. Comments of the Commission: Action taken on R&M of transmission system is noted. Directive 4: Modernization of State Load Dispatch Centre With the unbundling of GEB, providing open access on transmission system, and proposed introduction of intra-state ABT, the role of State Load Dispatch Centre will be critical in managing the system. Action shall be taken for modernization / augmentation of the Load Dispatch Centre if any required to meet the requirements. Compliance / Action Taken: Unbundling of GEB has resulted in the creation of various companies in addition to the two licensees (TPAECo., SECo.). Providing open access on transmission system and introduction of intra state ABT is being implemented according to GERC order. A state of the art SLDC and ALDC have been set up consisting of the following: 3 nos. ALDCs are set up at Jambuva, Gandhinagar & Jetpur under ULDC scheme for effective control and supervision of intra-state transmission system. So each ALDC will exercise the control and supervision of transmission system of their respective jurisdiction. ALDCs will also exercise the monitoring of drawl of power by DISCOM under the intra state ABT regime. Necessary infrastructure which includes setting up of SCADA system, Computer system etc. has been created. 27

31 The ABT meter data processing for the purpose of energy accounting will be routed through ALDC. Necessary computer hardware / software in this regard is installed and are under testing at ALDC. For effective system operation and control of the respective jurisdiction, SCADA system is installed at each ALDC, which provides on line real time data and facilitate network analysis. ALDCs will also exercise the monitoring of Drawl of power by DISCOM under the intra state ABT regime with the help of SCADA system. The staff setup has been strengthened at SLDC/ALDC to address open access & ABT issues effectively. The existing setup of SLDC is evaluated regularly to plan & to meet the requirements in respect of efficient operation, address regulatory requirements, WRLDC requirements etc. The infrastructure for the implementation of Intra-state ABT is setup at SLDC level for the purpose of Scheduling,Energy Accounting and providing open access & storage of relevant data which includes setting up of server based computer system. It would be noteworthy to mention here that upgrading of SLDC will be a continuous process rather than one time set up in new era. Comments of the Commission: Action taken is noted. It is stated that three ALDCs are being established for 4 (four) DISCOMs. It is presumed that Jambua ALDC would serve DGVCL and MGVCL. Ultimately the control of ALDCs shall be handed over to the respective DISCOMs. Directive 5: Data Management With the providing of open access on transmission system, the users of transmission system may require on line data on the capacity margin available on the transmission system periodically. Such data shall be made available on line to the users of transmission system. It is understood that there is a proposal to allocate the power purchase agreements (PPA) to various DISCOMs and GUVNL and also introduction of intra-state ABT requires enormous data made available to all stakeholders. GETCO / SLDC shall compile all the data required and make it available to all stakeholders for smooth operations of system. Action taken shall be reported to the Commission. 28

32 Compliance / Action Taken: Providing open access on transmission system to various users and introduction of intra state ABT require enormous data to be handled and processed in order to make available in desired format to various stakeholders and open access users. It includes on line data of the capacity margin available on transmission system, various schedules like Declaration, Entitlement, Drawl, etc. It has to cover larger time horizon while handling this data. To make this available to all stakeholders, including open access users for smooth operation, designing of independent website for SLDC, which will be maintained and updated by SLDC, is under progress. The following actions have been taken: 1. Domain has been registered as and web space is acquired. 2. Details of the information to be posted is under preparation and information flow is being finalized for ease of all users of the system. 3. Extensive help of IT department is taken for design and development of the website and to handle and process large amount of data. Comments of the Commission: Action taken is noted. The data should be kept continuously updated. Directive 6: Audited Accounts GETCO shall submit the Audited Accounts for the year while filing the tariff petition in future. Compliance / Action Taken: Finally audited accounts shall be submitted on finalizing the same by statutory auditor and CAG. As of now, GETCO has submitted this petition on the basis of provisional annual accounts for FY Comments of the Commission: Action taken is noted. The accounts may be got audited by CAG early. 29

33 Directive 7: Metering GETCO shall install 0.2 class meters suitable for ABT at the interface points for accounting the energy supplied to the DISCOMs since DISCOMs handle 11 kv and below. It would be fairly large number of interface points (supply points) between GETCO and DISCOMs and it would be necessary to provide metering at all the inter-face points. GETCO and DISCOMs may jointly identify the metering points and provide required number of meters. The details of interface metering points and status of metering shall be provided to the Commission. Action Taken / Compliance: The Installation of 610 nos. of 0.2 S class ABT Compliant meters at identified interface points on the basis of boundary metering concept has been completed. Discom / Licensee wise details are as under: Sr. No. Licensee Meters 1 DGVCL MGVCL UGVCL 96 4 PGVCL Torrent AEC 5 6 Torrent SEC 18 TOTAL 610 Comments of the Commission: Action taken is noted. Balance metering if any may be completed early. Directive 8: Reactive Compensation GETCO shall provide adequate Reactive Compensation by installing static capacitors etc. to meet the reactive Power requirements of the system to improve the voltage levels and reduce Transmission Losses. Action taken/ Compliance: Following actions have been performed in compliance with above directive: 1. At present GETCO have installed following reactive compensation instruments in the system as on Shunt Capacitor MVAr Bus Reactor 350 MVAr Line Reactor 200 MVAr 2. The procurement action for providing 4x25 MVAr bus reactor is already initiated, which are to be installed at 220KV bus as Pannandhro, Nakhtrana, Nani Khakhar and Anjar. 30

34 3. The system study for installation of reactive compensation in western region is carried out by WRPC. A meeting of study committee was held on to discuss the HT Shunt capacitor requirement in Western Region. As an out come of the study report, it is informed by WRPC that requirement of capacitor bank for GETCO system during is NIL. Comments of the Commission: GETCO made a provision of Rs.463 lakhs for providing shunt capacitors during The requirement of reactive compensation may be reviewed in the context of observation of WRPC that such requirement during is NIL and action taken to provide required compensation during

State Load Dispatch Centre (SLDC)

State Load Dispatch Centre (SLDC) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for, Approval of Provisional ARR for FY 2016-17 For State Load Dispatch Centre (SLDC) Case No. 1546 of 2015 31 st March, 2016 6 th Floor,

More information

Gujarat Energy Transmission Corporation Limited (GETCO)

Gujarat Energy Transmission Corporation Limited (GETCO) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2014-15, Approval of Provisional ARR for FY 2016-17 For Gujarat Energy Transmission Corporation Limited (GETCO) Case No. 1545 of

More information

Madhya Gujarat Vij Company Limited (MGVCL)

Madhya Gujarat Vij Company Limited (MGVCL) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2016-17 and Determination of Tariff for FY 2018-19 For Madhya Gujarat Vij Company Limited (MGVCL) Case No. 1701/2018 31 st March,

More information

Dakshin Gujarat Vij Company Limited (DGVCL)

Dakshin Gujarat Vij Company Limited (DGVCL) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2016-17 and Determination of Tariff for FY 2018-19 For Dakshin Gujarat Vij Company Limited (DGVCL) Case No. 1700/2018 31 st March,

More information

Paschim Gujarat Vij Company Limited (PGVCL)

Paschim Gujarat Vij Company Limited (PGVCL) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2016-17 and Determination of Tariff for FY 2018-19 For Paschim Gujarat Vij Company Limited (PGVCL) Case No. 1702/2018 31 st March,

More information

Gujarat Energy Transmission Corporation Limited (GETCO)

Gujarat Energy Transmission Corporation Limited (GETCO) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order For Gujarat Energy Transmission Corporation Limited (GETCO) Case No. 1375 of 2013 29 th 6 th Floor, GIFT ONE, Road 5C, GIFT City Gandhinagar-382 335

More information

Gujarat Energy Transmission Corporation Limited (GETCO)

Gujarat Energy Transmission Corporation Limited (GETCO) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2011-12 and For Gujarat Energy Transmission Corporation Limited (GETCO) Case No. 1262 of 2012 28 th 1st Floor, Neptune Tower, Opp.:

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION MERGEFORMAT. Tariff Order. Truing up for FY , Approval of Final ARR for FY ,

GUJARAT ELECTRICITY REGULATORY COMMISSION MERGEFORMAT. Tariff Order. Truing up for FY , Approval of Final ARR for FY , SHAPE \* GUJARAT ELECTRICITY REGULATORY COMMISSION MERGEFORMAT Tariff Order Truing up for FY 2015-16, Approval of Final ARR for FY 2016-17, Approval of Multi-Year ARR for FY 2017-18 to FY 2020-21 and Determination

More information

Paschim Gujarat Vij Company Ltd.

Paschim Gujarat Vij Company Ltd. BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR CASE NO. Filing of the Petition for True Up of FY 2015-16 & Determination of Multi-Year ARR for FY 2016-17 to FY 2020-21 & Determination

More information

Madhya Gujarat Vij Company Ltd.

Madhya Gujarat Vij Company Ltd. BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR Summary of Case 1549 /2015 In respect of Petition for True Up of & Determination of Provisional ARR and Tariff for Under GERC (Multi Year

More information

Gujarat Energy Transmission Corporation Limited (GETCO)

Gujarat Energy Transmission Corporation Limited (GETCO) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2015-16, Approval of Final ARR for FY 2016-17, Approval of Multi-Year ARR for FY 2016-17 to 2020-21, and Determination of Tariff

More information

Torrent Power Limited Distribution Dahej

Torrent Power Limited Distribution Dahej g- GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY and Determination of Tariff for FY 2018-19 For Torrent Power Limited Distribution Dahej Case No. 1698 of 2018 4 th April, 2018

More information

Order on. Petition No. 21/2014

Order on. Petition No. 21/2014 MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 4 th and 5 th Floor, Metro Plaza, Bittan Market, Bhopal - 462 016 Order on ARR & Retail Power Supply Tariff for Electricity Distribution Business of Special

More information

Uttar Gujarat Vij Company Limited

Uttar Gujarat Vij Company Limited GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order:, For Uttar Gujarat Vij Company Limited Suo - Motu Case No.1194 of 2012 2 nd 1 st Floor, Neptune Tower, Opp.: Nehru Bridge, Ashram Road Ahmedabad-380

More information

Madhya Gujarat Vij Company Ltd.

Madhya Gujarat Vij Company Ltd. BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR Summary of Case 1624 /2016 In respect of Petition for True up of & Determination of Multi-Year ARR for to & Determination of final ARR for

More information

Torrent Power Limited - Distribution Surat

Torrent Power Limited - Distribution Surat GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2016-17 and Determination of Tariff for FY 2018-19 For Torrent Power Limited - Distribution Surat Case No. 1697 of 2018 31 st March,

More information

Dakshin Gujarat Vij Company Limited (DGVCL)

Dakshin Gujarat Vij Company Limited (DGVCL) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order For Dakshin Gujarat Vij Company Limited (DGVCL) Case No. 1371 of 2013 29 th 6 th Floor, GIFT ONE, Road 5C, GIFT CITY Gandhinagar-382 335 (Gujarat),

More information

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL)

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) REVISED PETITION FOR APPROVAL OF TRUE UP OF FY 2015-16 & FY 2016 17 AND PROVISIONAL TRUE UP of FY 2017-18

More information

Torrent Power Limited - Generation Ahmedabad

Torrent Power Limited - Generation Ahmedabad GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2014-15, Approval of Provisional ARR for FY 2016-17 and Determination of Tariff for FY 2016-17 For Torrent Power Limited - Generation

More information

Madhya Gujarat Vij Company Ltd.

Madhya Gujarat Vij Company Ltd. BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR Summary of Case No. 1761 /2018 In respect of Petition for True up of & Mid-Term Review of ARR for to & Tariff determination for Filed by:-

More information

Vidarbha Industries Power Limited - Transmission

Vidarbha Industries Power Limited - Transmission Vidarbha Industries Power Limited - Transmission Revised Petition towards: Approval of Capital Cost and Determination of Aggregate Revenue Requirement ( ARR ) for the period FY 14-15 to FY 15-16 Filed

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION

GUJARAT ELECTRICITY REGULATORY COMMISSION GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for 2015-16, Approval of ARR for 2016-17 to 2020-21 and Determination of Tariff for 2017-18 For TORRENT POWER LIMITED - DISTRIBUTION SURAT

More information

Case No. 30 of In the matter of Petition filed by MSETCL for approval of SLDC Budget for FY and FY

Case No. 30 of In the matter of Petition filed by MSETCL for approval of SLDC Budget for FY and FY Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Uttar Gujarat Vij Company Limited (UGVCL)

Uttar Gujarat Vij Company Limited (UGVCL) GUJARAT ELECTRICITY REGULATORY COMMISSION (GERC) AHMEDABAD TARIFF ORDER FOR Uttar Gujarat Vij Company Limited (UGVCL) Case No. 945 of 2008 17 January 2009 C O N T E N T S Chapter Title Page 1 Introduction

More information

Notified on : 22 January 2010 Bhopal, Dated: 9 th December, 2009

Notified on : 22 January 2010 Bhopal, Dated: 9 th December, 2009 Notified on : 22 January 2010 Bhopal, Dated: 9 th December, 2009 No. 2734/MPERC/2009. In exercise of powers conferred under Section 181(2) (zd) read with Section 45 and 61 of the Electricity Act, 2003

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission Notification no. UPERC / Secy / CNCE Regulation, 2009/ 696 Dated: 22.3.2010 In exercise of powers conferred under section 181 read with section 9, 61, 86

More information

TARIFF ORDER. Petition No. 250/2017. For. Electricity Department, UT of Dadra and Nagar Haveli (Transmission Division)

TARIFF ORDER. Petition No. 250/2017. For. Electricity Department, UT of Dadra and Nagar Haveli (Transmission Division) TARIFF ORDER True-up of FY 2014-15, FY 2015-16 and FY 2016-17, Annual Performance Review of FY 2017-18 and Approval of Aggregate Revenue Requirement (ARR) and determination of tariff for FY 2018-19 Petition

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION 1st Floor, Neptune Tower, Ashram Road, Ahmedabad

GUJARAT ELECTRICITY REGULATORY COMMISSION 1st Floor, Neptune Tower, Ashram Road, Ahmedabad GUJARAT ELECTRICITY REGULATORY COMMISSION 1st Floor, Neptune Tower, Ashram Road, Ahmedabad-380009 Minutes of the meeting of the Coordination Forum held on 29 th July,2006 in Hotel hider Residency, Ahmedabad.

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION. Notification No. 13 of 2005

GUJARAT ELECTRICITY REGULATORY COMMISSION. Notification No. 13 of 2005 GUJARAT ELECTRICITY REGULATORY COMMISSION OPEN ACCESS REGULATION Notification No. 13 of 2005 In exercise of the powers conferred on it by Section 181 read with Sections 39(2)(d), 40(c), 42 (2)(3)(4), 86(1)(c)

More information

Kandla Port Trust (KPT)

Kandla Port Trust (KPT) GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order For Kandla Port Trust (KPT) Case No. 1474 of 2015 23 rd April, 2015 6 th Floor, GIFT ONE, Road 5C, GIFT City, Gandhinagar 382335 (Gujarat) India Phone:

More information

Multi Year Tariff Order For Himachal Pradesh State Load Dispatch Society (HPSLDS) For the period FY 15 to FY 19

Multi Year Tariff Order For Himachal Pradesh State Load Dispatch Society (HPSLDS) For the period FY 15 to FY 19 Multi Year Tariff Order For Himachal Pradesh State Load Dispatch Society (HPSLDS) For the period FY 15 to FY 19 Himachal Pradesh Electricity Regulatory Commission 10 th June, 2014 Himachal Pradesh Electricity

More information

Torrent Power Limited - Distribution Ahmedabad

Torrent Power Limited - Distribution Ahmedabad GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2016-17 and Determination of Tariff for FY 2018-19 For Torrent Power Limited - Distribution Ahmedabad Case No. 1696 of 2018 31 st

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW PETITION NO. 1058/2015

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW PETITION NO. 1058/2015 UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW PETITION NO. 1058/2015 DETERMINATION OF ANNUAL REVENUE REQUIREMENT (ARR) AND TARIFF FOR FY 2016-17 AND TRUE UP OF ARR AND REVENUE FOR FY 2013-14

More information

CHAPTER I: PRELIMINARY Short title, commencement and interpretation

CHAPTER I: PRELIMINARY Short title, commencement and interpretation Notification dated 20.2.2009 Bhopal: dated 31 st January, 2009 No. 254-MPERC-2009. In exercise of the powers conferred by Section 181 read with Subsection (b) of Section 86 of the Electricity Act 2003

More information

Bhopal: Dated 5 th May 2006

Bhopal: Dated 5 th May 2006 Bhopal: Dated 5 th May 2006 No. 1192/MPERC/2006. In exercise of the powers conferred by section 181 (g) read with section 32(3) of the Electricity Act, 2003 enacted by the parliament, the Madhya Pradesh

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM RP 6/2017 In the matter of : Review petition filed by M/s Kanan Devan Hill Plantations Company Private Limited (KDHPCL) seeking review

More information

Jharkhand State Electricity Regulatory Commission

Jharkhand State Electricity Regulatory Commission Order on Approval of Business Plan And ARR for MYT Control Period FY 2016-17 to FY 2020-21 And Transmission and SLDC Tariff for FY 2016-17 for Jharkhand Urja Sancharan Nigam Ltd (JUSNL) Ranchi February

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION No. ---/---/---/GERC Dated: 13/01/2017. NOTIFICATION No. of 2017

GUJARAT ELECTRICITY REGULATORY COMMISSION No. ---/---/---/GERC Dated: 13/01/2017. NOTIFICATION No. of 2017 GUJARAT ELECTRICITY REGULATORY COMMISSION -------- No. ---/---/---/GERC Dated: 13/01/2017 NOTIFICATION No. of 2017 In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 (36

More information

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No.

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No. 2 EXECUTIVE SUMMARY The Tata Power Company Limited ( Tata Power ) is a company established in 1919. On April 1, 2000, The Tata Hydro-Electric Power Supply Company Limited (established in 1910) and The

More information

Case No. 170 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. I.M. Bohari, Member Shri Mukesh Khullar, Member ORDER

Case No. 170 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. I.M. Bohari, Member Shri Mukesh Khullar, Member ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre No. 1, 13 th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E mail: mercindia@merc.gov.in Website:

More information

1. He is HT Consumer having contract demand of 475 KVA. 2. They applied for additional load of 175 KVA on

1. He is HT Consumer having contract demand of 475 KVA. 2. They applied for additional load of 175 KVA on BEFORE THE CONSUMER GRIEVANCES REDRESSAL FORUM MADHYA GUJARAT VIJ CO LIMITED CORPORATE OFFICE, 5 TH FLOOR SP VIDYUT BHAVAN, RACECOURSE, VADODARA 390 007 Subject Complainant Respondent Date of hearing Consumer

More information

BIHAR ELECTRICITY REGULATORY COMMISSION. Case No. 54 of for BIHAR STATE POWER TRANSMISSION COMPANY LIMITED (BSPTCL)

BIHAR ELECTRICITY REGULATORY COMMISSION. Case No. 54 of for BIHAR STATE POWER TRANSMISSION COMPANY LIMITED (BSPTCL) BIHAR ELECTRICITY REGULATORY COMMISSION Case 54 of 2015 Tariff Order Truing-up for FY 2014-15, Annual Performance Review (APR) for FY 2015-16, Annual Revenue Requirement (ARR) for FY 2016-17 to FY 2018-19

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION

GUJARAT ELECTRICITY REGULATORY COMMISSION GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order Truing up for FY 2015-16, Approval of ARR for FY 2016-17 to FY 2020-21 and Determination of Tariff for FY 2017-18 For TORRENT POWER LIMITED - DISTRIBUTION

More information

GOVERNMENT OF KERALA

GOVERNMENT OF KERALA 183 GOVERNMENT OF KERALA Kerala Small Hydro Power Policy 2012 1. Order G.O.(P) 25/2012/PD Dated: Thiruvananthapuram, 03.10.2012 2. Title Kerala Small Hydro Power Policy 2012 3. Objective To increase the

More information

AMENDMENT ORDER DATED

AMENDMENT ORDER DATED KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM Petition No. : OP 37/2013 In the matter of Petitioner : Amendment to ARR & ERC of M/s Kanan Devan Hills Plantations Company Limited for

More information

BEFORE THE HON BLE MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (MPERC) BHOPAL

BEFORE THE HON BLE MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (MPERC) BHOPAL BEFORE THE HON BLE MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (MPERC) BHOPAL IN THE MATTER OF Provisional approval of Generation tariff of M.P. s 57% share of power in Sardar Sarovar Project (6x200+5x50

More information

AGREEMENT FOR SYNCHRONOUS OPERATION OF CAPTIVE POWER PLANTS OF.. WITH JHARKHAND STATE ELECTRICITY BOARD SYSTEM

AGREEMENT FOR SYNCHRONOUS OPERATION OF CAPTIVE POWER PLANTS OF.. WITH JHARKHAND STATE ELECTRICITY BOARD SYSTEM AGREEMENT FOR SYNCHRONOUS OPERATION OF CAPTIVE POWER PLANTS OF.. WITH JHARKHAND STATE ELECTRICITY BOARD SYSTEM AN AGREEMENT FOR SYNCHRONOUS OPERATION OF Captive Power Plant of M/s.. of.. MW is made on

More information

AGGREGATE REVENUE REQUIREMENT AND RETAIL SUPPLY TARIFF ORDER FOR FY Petition Nos.

AGGREGATE REVENUE REQUIREMENT AND RETAIL SUPPLY TARIFF ORDER FOR FY Petition Nos. MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 TH Floor Metro Plaza, Bittan Market", Bhopal - 462 016 AGGREGATE REVENUE REQUIREMENT AND RETAIL SUPPLY TARIFF ORDER FOR FY 2012-13 Petition Nos. 72/2011

More information

MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION

MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION Tariff Order For True up for FY 2014-15 And Annual Revenue Requirement & Transmission Tariff For FY 2017-18 MEGHALAYA POWER TRANSMISSION CORPORATION LIMITED

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Sri. T.M.Manoharan, Chairman Sri.P.Parameswaran, Member Sri.Mathew George, Member 15 th May, 2013 Petition OP No. 42/2012 In the

More information

MYT PETITION FOR JUBILANT INFRASTRUCTURE LTD

MYT PETITION FOR JUBILANT INFRASTRUCTURE LTD BEFORE THE HON BLE GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD Filing No. Case No.. /2012 IN THE MATTER OF Filing of Petition under section 62 of the Electricity Act, 2003 for Aggregate Revenue

More information

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA Petition No. 36/2015 IN THE MATTER OF Petition under regulation 14 of the HPERC (Recovery of Expenditure for Supply of Electricity) Regulations,

More information

Petition for True-Up of FY And Determination of Tariff for FY

Petition for True-Up of FY And Determination of Tariff for FY BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION, GANDHINAGAR Petition for True-Up of FY 2013-14 And Determination of Tariff for FY 2015-16 Under GERC (Multi Year Tariff) Regulations, 2011 along with

More information

PRELIMINARY. (2) These Regulations shall come into force from the date of their publication in the Official Gazette.

PRELIMINARY. (2) These Regulations shall come into force from the date of their publication in the Official Gazette. No. JERC-10/2009:- In exercise of powers conferred on it under Section 61 read with Section 181 of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in this behalf, the Joint State

More information

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, "Metro Plaza", E-5, Arera Colony, Bittan Market, Bhopal - 462016 Petition No75/2012 PRESENT: Rakesh Sahni, Chairman A. B. Bajpai, Member Alok

More information

GOVERNMENT OF MADHYA PRADESH

GOVERNMENT OF MADHYA PRADESH 206 Compendium of State Government Policies on Renewable Energy Sector in India GOVERNMENT OF MADHYA PRADESH Wind Power Project Policy of Madhya Pradesh, 2012 (As Amended on 21 st February 2013) 1. Order

More information

CASE NO. 117/2016. Represented by: Shri Vikrambhai L. Shah, Authorized representative. V/s.

CASE NO. 117/2016. Represented by: Shri Vikrambhai L. Shah, Authorized representative. V/s. GUJARAT ELECTRICITY REGULATORY COMMISSION BEFORE THE ELECTRICITY OMBUDSMAN, GUJARAT STATE Polytechnic Compound, Barrack No.3, Ambawadi, Ahmedabad-380015 CASE NO. 117/2016 Appellant: M/s. T. T. Limited

More information

Scanned by CamScanner

Scanned by CamScanner Scanned by CamScanner BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION PANCHKULA Case No. HERC/PRO- 65 of 2014 Date of Hearing : 08.01.2015 Date of Order : 05.02.2015 In the matter of Filing of Petition

More information

TARIFF ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION CASE NO: TP 34 / IN RE THE TARIFF PETITION OF WEST BENGAL

TARIFF ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION CASE NO: TP 34 / IN RE THE TARIFF PETITION OF WEST BENGAL TARIFF ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION IN CASE NO: TP 34 / 07-08 IN RE THE TARIFF PETITION OF WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED UNDER SECTION 64(3)(a)

More information

Petition No. 05 of 2016

Petition No. 05 of 2016 MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5th Floor, "Metro Plaza", Bittan Market, Bhopal - 462 016 Petition No. 05 of 2016 PRESENT: Dr. Dev Raj Birdi, Chairman A.B. Bajpai, Member Alok Gupta, Member

More information

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 22 ND MEETING OF COMMERCIAL SUB-COMMITTEE OF SRPC HELD AT BANGALORE ON

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 22 ND MEETING OF COMMERCIAL SUB-COMMITTEE OF SRPC HELD AT BANGALORE ON SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 22 ND MEETING OF COMMERCIAL SUB-COMMITTEE OF SRPC HELD AT BANGALORE ON 31.07.2013 1. INTRODUCTION 1.1 The 22 nd Meeting of the Commercial Sub-

More information

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, "Metro Plaza", Bittan Market, Bhopal - 462 016 Petition No.55 of 2012 PRESENT: Rakesh Sahni, Chairman IN THE MATTER OF: C.S. Sharma, Member

More information

TARIFF ORDER TRUE-UP FOR FY & FY AND ARR FOR FY to FY AND TARIFF FOR FY

TARIFF ORDER TRUE-UP FOR FY & FY AND ARR FOR FY to FY AND TARIFF FOR FY ASSAM ELECTRICITY REGULATORY COMMISSION (AERC) TARIFF ORDER TRUE-UP FOR FY 2014-15 & FY 2015-16 AND ARR FOR FY 2016-17 to FY 2018-19 AND TARIFF FOR FY 2017-18 Assam Electricity Grid Corporation Limited

More information

1.1 These regulations shall extend to whole of the State of Punjab.

1.1 These regulations shall extend to whole of the State of Punjab. THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION The, 2018 No.PSERC/Secy/Regu. - In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other

More information

ORDER ON TRUE-UP OF ARR FOR THE PERIOD April 06 to March 07

ORDER ON TRUE-UP OF ARR FOR THE PERIOD April 06 to March 07 MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 4 th and 5 th Floor, Metro Plaza, Bittan Market, Bhopal - 462 016 ORDER ON TRUE-UP OF ARR FOR THE PERIOD April 06 to March 07 Petition Nos. PRESENT: 22/08

More information

ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION IN CASE NO.: APR 32 / 12 13

ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION IN CASE NO.: APR 32 / 12 13 ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION IN CASE NO.: APR 32 / 12 13 IN RE THE APPLICATION OF WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED FOR ANNUAL PERFORMANCE REVIEW

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION

KERALA STATE ELECTRICITY REGULATORY COMMISSION KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM OA 7/2017 In the matter of Applicant : Application for the approval of revised ARR & ERC for the year 2017-18 filed by M/s KINESCO Power

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 and all powers enabling it in this behalf, the Uttar Pradesh Electricity

More information

GUJARAT URJA VIKAS NIGAM LTD., VADODARA

GUJARAT URJA VIKAS NIGAM LTD., VADODARA GUJARAT URJA VIKAS NIGAM LTD., VADODARA INVITATION OF BIDS FOR PROCUREMENT OF POWER ON SHORT-TERM BASIS THROUGH TARIFF BASED COMPETITIVE BIDDING PROCESS Request for Proposal (As per Guidelines for short-term

More information

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016 1 BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016 IN THE MATTER OF: Petition under Section 86 read with Section 181 of the Electricity Act, 2003 for amendment of

More information

Before the MP Electricity Regulatory Commission 5 TH Floor, "Metro Plaza", E-5, Arera Colony, Bittan Market : BHOPAL.

Before the MP Electricity Regulatory Commission 5 TH Floor, Metro Plaza, E-5, Arera Colony, Bittan Market : BHOPAL. In the Matter of - Before the MP Electricity Regulatory Commission 5 TH Floor, "Metro Plaza", E-5, Arera Colony, Bittan Market : BHOPAL. Petition 53 of 2013 Filing of application for True-up of the Transmission

More information

Summary of Tariff Petition for BECL 2 x 250 MW Lignite based Thermal Power Plant at Bhavnagar

Summary of Tariff Petition for BECL 2 x 250 MW Lignite based Thermal Power Plant at Bhavnagar Summary of Tariff Petition for BECL 2 x 250 MW Lignite based Thermal Power Plant at Bhavnagar In terms of sections 61, 62, 64 and 86 of the Electricity Act, 2003, the tariff for the generation and sale

More information

M/s. Ramdev Chemical Industries, Plot No. 3441/B, GIDC Ind.Estate ANKLESHWAR Dist. Bharuch. Represented by: Shri J.N.Gandhi, Learned Advocate

M/s. Ramdev Chemical Industries, Plot No. 3441/B, GIDC Ind.Estate ANKLESHWAR Dist. Bharuch. Represented by: Shri J.N.Gandhi, Learned Advocate GUJARAT ELECTRICITY REGULATORY COMMISSION BEFORE THE ELECTRICITY OMBUDSMAN, GUJARAT STATE Polytechnic Compound, Barrack No.3, Ambawadi, Ahmedabad-380015 CASE NO. 72/2017 Appellant: M/s. Ramdev Chemical

More information

Madhya Pradesh Poorv Ksthera Vidyut Vitaran Company Limited

Madhya Pradesh Poorv Ksthera Vidyut Vitaran Company Limited MYT ARR Filing for 10-11 to 12-13 AGGREGATE REVENUE REQUIREMENT AND TARIFF PROPOSAL PETITION FOR FY 2010-11 Madhya Pradesh Poorv Ksthera Vidyut Vitaran Company Limited Block No. 7, Shakti Bhawan, Vidyut

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM O.A No.15/2016

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM O.A No.15/2016 KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM O.A No.15/2016 In the matter of : Amendment to the Order on truing up of accounts for financial year 2009-10 of M/s KPUPL Applicant : M/s

More information

Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited Block No. 7, Shakti Bhawan, Vidyut Nagar, Jabalpur

Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited Block No. 7, Shakti Bhawan, Vidyut Nagar, Jabalpur ANNUAL REVENUE REQUIREMENT AND TARIFF PROPOSAL PETITION FOR FY 2015-16 Submitted By: Madhya Pradesh Power Management Company Limited Shakti Bhawan, Vidyut Nagar, Jabalpur Madhya Pradesh Poorv Kshetra Vidyut

More information

SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal

SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Municipal Solid Waste based power generating plants in Madhya Pradesh June 2016 1. LEGISLATIVE PROVISIONS

More information

Bhopal, Dated:

Bhopal, Dated: Bhopal, Dated: 08.12.2015 No. /MPERC /2015 - In exercise of powers conferred under sub-section zp of Section 181 of the Electricity Act, 2003 (36 of 2003), and all other powers enabling it in this behalf,

More information

Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL.

Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL. Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL. GUVNL has floated two tenders for procurement of power from

More information

Multi Year Tariff Order For Himachal Pradesh State Electricity Board Limited (HPSEBL) For the period FY to FY

Multi Year Tariff Order For Himachal Pradesh State Electricity Board Limited (HPSEBL) For the period FY to FY Multi Year Tariff Order For Himachal Pradesh State Electricity Board Limited (HPSEBL) For the period FY 2014-15 to FY 2018-19 Himachal Pradesh Electricity Regulatory Commission June 12, 2014 BEFORE THE

More information

ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR CASE NO: TP 59 / 13 14

ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR CASE NO: TP 59 / 13 14 ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR 2015 2016 IN CASE NO: TP 59 / 13 14 IN RE THE TARIFF APPLICATION OF THE WEST BENGAL POWER DEVELOPMENT CORPORATION LIMITED FOR THE

More information

ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR ************

ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR ************ ODISHA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR - 751 012 ************ Present: Shri S. P. Nanda Chairperson Shri B. K. Misra, Member Shri S. P. Swain, Member Case

More information

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, "Metro Plaza", Bittan Market, Bhopal

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, Metro Plaza, Bittan Market, Bhopal MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, "Metro Plaza", Bittan Market, Bhopal - 462 016 Petition No.16 of 2014 PRESENT: Dev Raj Birdi, Chairman A.B. Bajpai, Member Alok Gupta, Member

More information

Jammu & Kashmir State Electricity Regulatory Commission

Jammu & Kashmir State Electricity Regulatory Commission Jammu & Kashmir State Electricity Regulatory Commission Order on Annual Performance Review FY 2014-15 And transmission tariff for FY 2015-16 for Power Development Department Transmission, Govt. of J&K

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD. CORAM Dr. P.K. Mishra, Chairman Shri Pravinbhai Patel, Member. Order No.

GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD. CORAM Dr. P.K. Mishra, Chairman Shri Pravinbhai Patel, Member. Order No. GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD CORAM Dr. P.K. Mishra, Chairman Shri Pravinbhai Patel, Member Order No. 3 of 2010 Amendment to Order No.3 of 2006 dated 11 th August, 2006 in the matter

More information

Procedure for Scheduling

Procedure for Scheduling Short-Term Open Access in Inter-State Transmission (Bilateral Transaction) Procedure for Scheduling (As per CERC Open Access Regulations, 2008 (dated 25.01.2008) & subsequent (Amendment) Regulations, 2009

More information

BRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST)

BRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST) BRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST) EXECUTIVE SUMMARY OF Annual Performance Review for FY 2008-09 & ARR for FY 2009-10 along with Truing Up of Accounts for FY 2007-08 TO Maharashtra

More information

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW. Petition Nos. 921, 917, 918, 919, 920, 885, 886, 887, 888, 889 / 2013

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW. Petition Nos. 921, 917, 918, 919, 920, 885, 886, 887, 888, 889 / 2013 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW Petition Nos. 921, 917, 918, 919, 920, 885, 886, 887, 888, 889 / 2013 and Petition Nos. 916, 894 / 2013 IN THE MATTER OF: Application

More information

Power Purchase Agreement between. Gujarat State Electricity Corporation Limited. (The Seller) and. Gujarat Urja Vikas Nigam Limited.

Power Purchase Agreement between. Gujarat State Electricity Corporation Limited. (The Seller) and. Gujarat Urja Vikas Nigam Limited. Power Purchase Agreement between Gujarat State Electricity Corporation Limited (The Seller) and Gujarat Urja Vikas Nigam Limited (The Procurer) IN RESPECT OF DHUVARAN CCPP III 395 MW GAS BASED COMBINED

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM Application No : OA 12/2017 In the matter of : Applicant Application for the approval of revised ARR & ERC for the year 2017-18 filed by

More information

NOTIFICATION. No.HPERC/dis/479: Shimla the 30 th March, 2012

NOTIFICATION. No.HPERC/dis/479: Shimla the 30 th March, 2012 HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA NOTIFICATION No.HPERC/dis/479: Shimla the 30 th March, 2012 WHEREAS the Distribution Licensee incurs an extra power purchase cost vis-a- vis the

More information

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website: www.mercindia.org.in;

More information

Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited Block No. 7, Shakti Bhawan, Vidyut Nagar, Jabalpur

Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited Block No. 7, Shakti Bhawan, Vidyut Nagar, Jabalpur AGGREGATE REVENUE REQUIREMENT FOR MYT FY 2017 TO FY 2019 AND TARIFF PROPOSAL PETITION FOR FY 2017-18 Submitted By: Madhya Pradesh Power Management Company Limited Shakti Bhawan, Vidyut Nagar, Jabalpur

More information

Executive Summary. Annual Performance Review towards: Truing up of ARR of FY09, APR of FY10 and Determination of ARR and Tariff for FY11

Executive Summary. Annual Performance Review towards: Truing up of ARR of FY09, APR of FY10 and Determination of ARR and Tariff for FY11 RInfra-Distribution (RInfra-D) Wire and Retail Annual Performance Review towards: Truing up of ARR of FY09, APR of FY10 and Determination of ARR and Tariff for FY11 Executive Summary Filed with Maharashtra

More information

Case No. 125 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

Case No. 125 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION (MSERC)

MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION (MSERC) MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION (MSERC) Tariff Order For Annual Revenue Requirement & Generation Tariff For FY 2015 16 List of Contents ORDER... 1 1. Introduction... 5 1.1 1.2 1.3 1.4

More information

TARIFF ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR CASE NO: TP 60 / 13-14

TARIFF ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR CASE NO: TP 60 / 13-14 TARIFF ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR 2014 2015 IN CASE NO: TP 60 / 13-14 IN RE THE TARIFF APPLICATION OF THE WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS,

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS, Approach Paper for MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS, 2014 Issued By: Maharashtra Electricity Regulatory

More information

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, "Metro Plaza", E-5, Arera Colony, Bittan Market, Bhopal - 462016 Petition 06/2013 PRESENT: Rakesh Sahni, Chairman A. B. Bajpai, Member Alok

More information

REGULATORY INFORMATION REPORT FOR THE QUARTER : 1st

REGULATORY INFORMATION REPORT FOR THE QUARTER : 1st REGULATORY INFORMATION REPORT FOR THE QUARTER : 1st 2008-09 PREPARED BY : "UGVCL,Mehsana" SUBMITTED TO : GUJARAT ELECTRICITY REGULATORY COMMISSION DATE : April:08 To June:08 Page 1 C:\Documents and Settings\UB

More information