Chapter Five. Scale, Timing, Length, and Interdependencies in Project Selection

Size: px
Start display at page:

Download "Chapter Five. Scale, Timing, Length, and Interdependencies in Project Selection"

Transcription

1 Chapter Five Scale, Timing, Length, and nterdependencies in Project Selection 5.1 ntroduction n the previous chapter, it was concluded that a project s net present value (NPV) is the most important criterion for financial and economic evaluation. The NPV criterion requires that only projects with a positive NPV are approved. The next step is to endeavour to maximize the NPV in order to extract as much value from the project as possible. The aim should be to maximize the NPV of incremental net cash flows or net economic benefits. Of course, such optimization should not be pursued blindly, as it may have repercussions for other stakeholders that need to be considered in the final decision-making. Project analysts often encounter a range of other important considerations. These include changes in project parameters, such as the scale of investment, the date of initiation of a project, the length of project life, or interdependencies of project components. Each of these is addressed in this chapter using the criterion of a project s NPV. 5.2 Determination of Scale in Project Selection Projects are rarely, if ever, constrained by technological factors to a unique capacity or scale. Thus, one of the most important decisions to be made in the design of a project is the selection of the scale to which a facility should be built. n too many cases, scale selection has been treated as if it were a purely technical decision, neglecting its financial or economic aspects. When financial or economic considerations have been neglected at the design stage, the scale to which the project is built is not likely to be the one that would maximize the NPV. Thus, in addition to Chapter Five 123

2 technological factors, the size of the market, the availability of project inputs, and the quality of manpower, etc. will also have a role to play. The most important principle for selecting the best scale of a project (e.g., height of an irrigation dam or size of a factory) is to treat each incremental change in its size as a project in itself. An increase in the scale of a project will require additional expenditures and is likely to generate additional expected benefits over and above those that would have been produced by the project at its previous size. Using the present value of the incremental benefits and the present value of the incremental costs, the change in NPV stemming from changing scales of the project can be derived. n Figure 5.1, the cash flow profiles of a project are shown for three alternative scales. C 1 and B 1 denote the expected costs and benefits if the project is built at the smallest scale relevant for this evaluation. f the project is built at one size larger, it will require additional expenditure of C 2. Therefore, the total investment cost of the project at its expanded scale is (C 1 + C 2 ). t is also anticipated that the benefits of the project will be increased by an amount of B 2, implying that the total benefits from this scale of investment will now be (B 1 + B 2 ). A similar relationship holds for the largest scale of the project. n this case, additional expenditures of C 3 are required, and extra benefits of B 3 are expected. The total investment costs for this scale are (C 1 + C 2 + C 3 ), and the total benefits (B 1 + B 2 + B 3 ). Figure 5.1: Net Benefit Profiles for Alternative Scales of a Facility The goal is to choose the scale that has the highest NPV. f the present value of (B 1 C 1 ) is positive, it is a viable project. The next step 124 Scale, Timing, Length, and nterdependencies

3 is to determine whether the present value of (B 2 C 2 ) is positive. f the incremental NPV is positive, then this project at scale 2 is preferable to scale 1. This procedure is repeated until a scale is reached where the NPV of the incremental benefits and costs associated with a change in scale is negative. This incremental NPV approach helps in the choice of a scale that has maximum NPV for the entire investment. The NPV is the maximum because the incremental NPV for any addition to the scale of the project would be negative. f the initial scale of the project had a negative NPV but all the subsequent incremental NPVs for changes of scale were positive, it would still be possible for the overall project to have a negative NPV. Therefore, in order to select the optimum scale for a project, it is necessary to first ensure that the NPV of the overall project is positive, and that the NPV of the last addition to the investment to increase the project s scale is non-negative. This is illustrated in Figure 5.2, in which all project sizes between scale C and scale M yield a positive NPV. However, the NPV of the entire investment is maximized at scale H. After scale H, the incremental NPV of any expansion of the facility becomes negative. Therefore, the optimum scale for the project is H, even though the NPV for the entire project is still positive until scale M. Figure 5.2: Relationship between NPV and Scale The optimal scale of a project can also be determined by the use of the internal rate of return (RR), assuming that each successive increment Chapter Five 125

4 of investment has a unique RR. f this condition is met, the optimal scale of the facility will be the one at which the RR for the incremental benefits and costs equals the discount rate used to calculate the NPV of the project. This RR for the incremental investment required to change the scale of the project will be the marginal internal rate of return (MRR) for a given scale of facility. The relationships between the RR, the MRR, and the NPV of a project are shown in Figure 5.3. Figure 5.3: Relationships between the MRR, RR, and NPV From Figure 5.3, it can be observed that in a typical project, the MRR from incremental investments will initially rise as the scale is increased, but will soon begin to fall with further expansions. This path of the MRR will also cause the RR to rise for the initial ranges of scale and then to fall. At some point, the RR and the MRR must be equal and then change their relationship to each other. Prior to the point S 1 in Figure 5.3, the MRR of the project is greater than the RR: here, expansions of scale will cause the overall RR of the project to rise. At scales beyond S 1, the MRR is less than the RR: in this range, expansions of scale will cause the overall RR to fall. 126 Scale, Timing, Length, and nterdependencies

5 The point at which the RR equals the MRR always corresponds to the scale at which the RR is maximized. However, it is important to note that this is not the scale at which the NPV of the project is likely to be maximized. The NPV of a project obviously depends on the discount rate. Only when the relevant discount rate is precisely equal to the maximum RR will S 1 be the optimal scale. f the relevant discount rate is lower, it pays to expand the project s scale up to the point where the MRR is equal to the discount rate. As shown for the case in which the discount rate is 10 percent, this scale yields the maximum NPV at a scale of S 2 in Figure 5.3. To illustrate this procedure for determining the optimal scale of a project, consider the construction of an irrigation dam that could be built at different heights. Because of the availability of water, the expectation would be that expansions of the scale of the dam would reduce the overall level of utilization of the facilities when measured as a proportion of its total potential capacity. The information is provided in Table 5.1. Table 5.1: Determination of Optimal Scale of rrigation Dam (dollars) Time Scales Costs Benefits NPV RR S 0 3, S 1 4, S 2 5, S 3 6, S 4 7, S 5 8, Time Changes ncremental Chang in Scales Costs Benefits e in MR NPV R S 0 3, S 1 S 0 1, S 2 S 1 1, S 3 S 2 1, S 4 S 3 1, S 5 S 4 1, Notes: Discount rate (opportunity cost of funds) = 10 percent. The depreciation rate of the dam is assumed to be zero. Chapter Five 127

6 n this example, the NPV can be calculated for each scale of the dam from S 0 to S 5. Thus, the NPV for S 0 is 500; for S 1 S 0, it is 400; for S 2 S 1, 500; for S 3 S 2, 300; for S 4 S 3, 50; and for S 5 S 4, Applying the above rule for determining the optimal scale would lead to scale S 4 being chosen because beyond this point, additions to scale contribute negatively to the overall NPV of the project. At scale S 4, the NPV of the project is +750; at scale S 3, it is +700; and at S 5, it is Therefore, the NPV is maximized at S 4. f the project is expanded beyond scale 4, the NPV begins to fall, even though at scale S 5 the RR of the entire project is still (which is greater than the discount rate of 0.10). However, the MRR is only 0.09, placing the marginal return from the last addition to scale below the discount rate. 5.3 Timing of nvestments One of the most important steps in the process of project preparation and implementation is to decide on the appropriate time at which the project should start. This decision becomes particularly difficult for large indivisible projects, such as infrastructure investments in roads, water systems, and electricity generation facilities. f these projects are built too soon, a large amount of idle capacity will exist. n such cases, the forgone return (that would have been realized if these funds had been invested elsewhere) might be higher in value than the benefits gained in the first few years of the project s life. Conversely, if a project is delayed for too long, shortages of goods or services will persist and the output forgone will be greater than the alternative yield of the funds involved. Whenever a project is undertaken too early or too late, its NPV will be lower than the level it could have been if it had been developed at the right time. The NPV of a project may still be positive, but it will not be at its maximum. The determination of the correct timing of investment projects will be a function of how it is anticipated that future benefits and costs will move in relation to their present values. Situations in which the timing of investment projects becomes an important issue can be classified into four different cases. 1 For perpetuity, the RR can be calculated as the ratio of annual income to initial investment. 128 Scale, Timing, Length, and nterdependencies

7 Case A The benefits of the project are a continuously rising function of calendar time, but investment costs are independent of calendar time. Case B The benefits and investment costs of the project are rising with calendar time. Case C The benefits are rising and then falling with calendar time, while the investment costs are a function of calendar time. Case D The benefits and investment costs do not change systematically with calendar time. Case A: Potential Benefits Are a Rising Function of Calendar Time This is the case in which the benefits net of operating costs are continuously rising through time, and costs do not depend on calendar time. For example, the benefits of a road improvement project rise because of the growth in demand for transportation between two or more places. t can thus be expected that as population and income grow, the demand for the road will also increase through time. f the project s investment period ends in Period t, it can be assumed that its net benefit stream will start the year after construction and will rise continuously thereafter. This potential benefit stream is illustrated by the curve B(t) in Figure 5.4. f construction were postponed from t 1 to t 2, lost benefits amount to B 1, but the same capital in alternative uses yields rk, where K denotes the initial capital expenditure and r denotes the opportunity cost of capital for one period. Postponing construction from t 1 to t 2 thus yields a net gain of ADC. Similarly, postponing construction from t 2 to t 3 yields a net benefit of CDE. n this situation, the criterion for ensuring that investments are undertaken at the correct time is quite straightforward. f the present value of the benefits that are lost by postponing the start of the project from Period t to Period t+1 is less than the opportunity cost of capital multiplied by the present value of capital costs as of Period t, the project should be postponed because the funds would earn more in the capital market than if they were used to start the project. On the other hand, if the forgone benefits are greater than the opportunity cost of the investment, the project should proceed. n short, if rk t > B t+1, the decision should be to postpone the project; and if rk t < B t+1, the project should go ahead. Here t is the period in which the project is to begin, K t is the present value of the investment costs of the project as of Period t, Chapter Five 129

8 and B t+1 is the present value of the benefits lost by postponing the project for one period from t to t 1. Figure 5.4: Timing of Projects: Benefits Are Rising, but nvestment Costs Are ndependent of Calendar Time Rules: rk t > B t+1 Postpone rk t < B t+1 Start Case B: Both nvestment Costs and Benefits Are a Function of Calendar Time n this case, as illustrated in Figure 5.5, the investment costs and benefits of a project will grow continuously with calendar time. Suppose the capital cost is K 0 when the project is started in Period t 0 and the costs will become K 1 if it is started in Period t 1. The change in investment costs must be included in the calculations of optimum timing. When the costs of constructing a project are greater in Period 1 than in Period 0, there is an additional loss caused by postponement of (K 1 K 0 ), as shown by the area FGH in Figure Scale, Timing, Length, and nterdependencies

9 Figure 5.5: Timing of Projects: Both Benefits and nvestment Costs Are a Function of Calendar Time Rules: rk t > B t+1 + (K t+1 K t ) Postpone rk t < B t+1 + (K t+1 K t ) Start n Case A, when benefits are a positive function of calendar time, the decision rule for the timing of investments is to postpone if rk 0 > B 1 and to proceed as soon as B t+1 > rk t. Now, when the present value of the investment costs changes with the timing of the starting date, the rule is slightly modified: if rk 0 > [B 1 + (K 1 K 0 )], postpone the project; otherwise, undertake the project. The term (K 1 K 0 ) represents the savings of the increase in capital costs by commencing the project in Period t 0 instead of t 1. The rule shows a comparison of the area t 1 DEt 2 with (t 1 ACt 2 + FGH). Hence, if investment costs are expected to rise in the future, the optimal option would be for the project to be undertaken earlier than if investment costs remained constant over time. Case C: Potential Benefits Rise and Fall According to Calendar Time n the case in which the potential benefits of the project are also a function of calendar time, but are not expected to grow continuously Chapter Five 131

10 through time, at some date in the future they are expected to decline. For example, the growth in demand for a given type of electricity generation plant in a country is expected to continue until it can be replaced by a cheaper technology. As the alternative form of technology becomes cheaper and more easily available, it is expected that the demand faced by the initial plant will decline through time. f the net benefits from an electricity generation plant are directly related to the volume of production it generates, it would be expected that the pattern of benefits would appear similar to B(t) in Figure 5.6. Figure 5.6: Timing of Projects: Potential Benefits Rise and Decline with Calendar Time Rules: Start if rk ti < B ti+1 Stop if rsv tn B tn+1 SV tn+1 > 0 Do project if: NPV t i = t nå B i SV - K ti + tn > 0 i=t i+1 Do not do project if: NPV t i = (1+ r) i-t i (1+ r) t n -t i t nå B i SV - K ti + tn < 0 i=t i+1 (1+ r) i-t i (1+ r) t n -t i 132 Scale, Timing, Length, and nterdependencies

11 f the project with present value of costs of K 0 is undertaken in Period t 0, its first-year benefits will fall short of the opportunity cost of the funds shown by the area ABC. The correct point to start the project is t 1, when rk t1 < B t2, and if the following project s NPV (measured by the present value of the area under the B(t) curve minus K 1 ) is positive: NPV K /(1 r) n t2 [ B t /(1 r) ] t is obviously essential that this NPV be positive in order for the project to be worthwhile. The above formula assumes that the life of the project is infinite, or that after some time, its annual benefit flows fall to zero. nstead of lasting for its anticipated lifetime, the project could be abandoned at some point in time, with the result that a one-time benefit is generated, equal to its scrap value, SV. n this case, it pays to keep the project in operation only so long as B tn+1 > rsv tn SV tn+1, so it would make sense to stay in business during t n+1. f B tn+1 < rsv tn SV tn+1, it would make more sense to shut down operations at the end of t n. n practice, there are five special cases in relation to scrap value and change in scrap value of a project: t SV > 0 and ΔSV < 0, e.g., machinery SV > 0 but ΔSV > 0, e.g., land SV < 0 but ΔSV = 0, e.g., a nuclear power plant SV < 0 but ΔSV > 0, e.g., severance pay for workers SV < 0 and ΔSV < 0, e.g., clean-up costs n general, a project should be undertaken if the following condition is met: NPV t i = t nå B i SV tn > 0 (5.1) i=t i+1 - K (1+ r) i-t ti + i (1+ r) t n -t i f this condition cannot be met, and if NPV t i = t nå B i SV - K ti + tn < 0 i=t i+1 (1+ r) i-t i the project should not be undertaken. (1+ r) t n -t i Chapter Five 133

12 Case D: The Costs and Benefits Do Not Change Systematically with Calendar Time This is perhaps the most common situation, in which there is no systematic movement in either costs or benefits with respect to calendar time. As illustrated in Figure 5.7, if a project is undertaken in Period t 0, its profile begins with investment costs of K 0, followed by a stream of benefits shown as the area t 1 ABt n. Alternatively, if it is postponed for one period, investment costs will be K 1, and benefits will be t 2 CDt n+1. n this case, the optimal date to start the project is determined by estimating the NPV of the project in each instance and choosing the time to start the project that yields the highest NPV. t is important to note that in determining the timing of the project, the date to which the NPVs are calculated must be the same for all cases, even though the period in which the projects are to be initiated varies. Figure 5.7: Timing of Projects: Benefits and Costs Do Not Change Systematically with Calendar Time 134 Scale, Timing, Length, and nterdependencies

13 5.4 Adjusting for Different Lengths of Life f there is no budget constraint, and if a choice must be made between two or more mutually exclusive projects, investors seeking to maximize net worth should select the project with the highest NPV. f the mutually exclusive projects are expected to have continuously high returns over time, it is necessary to consider the lengths of life of the two or more projects. The reason for wanting to ensure that mutually exclusive projects are compared over the same span of time is to give them the same opportunity to accumulate value over time. One way to think about the NPV is as an economic rent that is earned by a fixed factor of production. n the case of two mutually exclusive projects, for example, the fixed factor could be the building site, a right-of-way, or a licence. That fixed factor should have the same amount of time to generate economic rents, regardless of which project is chosen. What is required is a reasonable method of equalizing lengths of life that can be applied. This is elaborated with the help of the following two examples. Example 1 Consider two mutually exclusive projects, Project A (three years) and Project B (four years), with the same scale of investment, and the net cash flows as shown in Table 5.2. All the net cash flows are expressed in thousands of dollars, and the cost of capital is 10 percent. Table 5.2: Net Cash Flows for Projects with Different Lengths of Life (thousand dollars) Time Period t 0 t 1 t 2 t 3 NPV@10% Net cash flows of Project A 10,000 6,000 6, Net cash flows of Project B 10,000 4,000 4,000 4, f the differences in the lengths of life were overlooked, Project B would be selected because it has the higher NPV. However, this would run the risk of rejecting the potentially better Project A with the shorter life. One approach to addressing this problem is to determine whether the projects could be repeated a number of times (not necessarily the same Chapter Five 135

14 number of times for each project) in order to equalize their lives. To qualify for this approach, both projects must be supra-marginal (i.e., have positive NPVs) and should be repeatable at least a finite number of times. Assume that Projects A and B above meet these requirements. f Project A was repeated three times and Project B twice, both projects would have a total operating life of six years, as shown in Table5.3. n year t 6, both projects can start up again, but there is no need to repeat this procedure. The construction of the repeated projects is initiated so as to maintain a level of service. For example, construction for the second Project B begins in year t 3 so that it is ready to begin operations when the first Project B stops providing a service. Given the equal lengths of life for the repeated projects, they can now be compared on the basis of their NPV: NPV of NPV of 410 Project A s repeats 410 (1.1) 410 (1.1) ' Project B' s repeats (1.1) 1,029 Given an equal opportunity to earn economic rents, Project A has a higher overall NPV and should be considered the more attractive project. Table 5.3: Net Present Value for Repeating Projects Time t 0 t 1 t 2 t 3 t 4 t 5 t 6 Project A s NPV for each repeat Project B s NPV for each repeat Example 2 This example refers to the case in which a choice is to be made between mutually exclusive projects representing different types of technology with different lengths of life. 136 Scale, Timing, Length, and nterdependencies

15 How can a decision be made between the two technologies using the NPV criterion? Suppose that the present value of the costs of Project [PV 0 ( C 0 )] is $100 and the present value of its benefits [PV 0 ( B 1 5 )] is $122. Similarly, the present value of the costs of Project [PV 0 ( C 0 )] is $200 and that of its benefits [PV 0 ( B 1 8 )] $225. A comparison of the NPVs of the two projects suggests that Project is preferred to Project because the NPV of Project is $25, whereas that of Project is only $22. However, since these two projects represent two different types of technology with different lengths of life, the NPV of Project is biased upward. n order to make a correct judgment, it is necessary to make the projects comparable by either adjusting the lengths of life or calculating the annualization of net benefits. One option is to adjust Project to make it comparable to Project. The benefits for only the first five years of Project should be included, and its costs should be reduced by the ratio of the present value of benefits from Years 1 5 to Years 1 8. This is expressed as follows: NPV 0 = PV 0 ( B 5 1 ) PV 0 ( C 0 ) Chapter Five 137

16 Adj NPV 0 = PV 0 ( PV 1 ) PV 0 ( C 0 ) 0( B PV0 ( B B 5 Substituting in the values of costs and benefits of the two projects in the example gives: ) ) PV ( B 8) = $225, PV C ) = $200, PV B ) = $180 Hence, 0 0 ( 0 NPV 0 = $122 $100 = $22 NPV 0 Adj 0( 1 5 = $180 $200(180/225) = $180 $160 = $20 After the adjustment, the NPV of Project is greater than that of Project ; this means that Project is better. The second way of making the two projects comparable is to adjust the length of Project. t is necessary to calculate the NPVs of Project (adjusted) and Project. The NPV of Project can be adjusted by doubling its length of life. The benefits of Years 6 8 are then added to the benefits of Years 1 5. The costs are increased by the value of the costs to lengthen the project to Year 8, which is the present value of the costs in Year 5, reduced by the ratio of the benefits of Years 6 8 to the benefits of Years This adjustment can be expressed as follows: 138 Scale, Timing, Length, and nterdependencies

17 Adj NPV 0 = PV 0 ( B 5 1 ) PV 0 ( C 0 ) + PV 0 ( B 8 6 ) PV 0 ( C 5 ) PV 0( B6 PV0 ( B6 Substituting in the present values of costs and benefits of the two projects in our example gives: 8 10 ) ) Adj NPV 0 = $122 $100 + $60 $80(60/110) = $38.36 NPV 0 = $225 $200 = $25 Using this method, the NPV of Project is still greater than that of Project. Therefore, Project is preferred to Project. The third way is to compare the annualization of the net benefits of the two projects. For Project, the NPV is $22 over a five-year period. The annualized value of the benefits can be calculated as follows (European Commission, 2005): Annualized value = [$ ] / [1 ( ) 5 ] = $5.80 For Project, the NPV is $25 over an eight-year period. The annualized value of the benefits is: Annualized value = [$ ] / [1 ( ) 8 ] = $4.69 Again, the higher NPV of Project than those of Project is due to a longer time horizon. When they are normalized for time period, it is shown that Project is in fact preferred. 5.5 Projects with nterdependent and Separable Components An investment program will often contain several interrelated investments within a single project. t has sometimes been suggested that in such integrated projects, it is correct to evaluate the project as a whole and to bypass the examination of each of the sub-components. This argument is generally not correct. The analyst should attempt to break the project down into its various components and examine the incremental costs and benefits associated with each of the components in Chapter Five 139

18 order to determine whether they increase or decrease the NPV of the project. Suppose the task is to appraise a project to build a large storage dam, planned to provide hydroelectric power, irrigation water, and recreational benefits. Upon first examination of this project, it might appear that these three functions of the dam are complementary, so that it would be best to evaluate the entire project as a package. However, this is not necessarily the case. The irrigation water might be needed at a different time of the year than the peak demand for electricity. The reservoir might be empty during the tourist season if the water is used to maximize its value in generating electricity and providing irrigation. Therefore, maximizing the NPV of the whole package may mean that the efficiency of some of the individual components will be reduced. n this case, the overall project might be improved if one or more of the components were dropped from the investment package. n appraising such an integrated investment package, the first step is to evaluate each of the components as an independent project. Thus, the hydroelectric power project would be evaluated separately. The technology used in this case would be the most appropriate for this size of electricity dam without considering its potential as a facility for either irrigation or recreational use. Similarly, the uses of this water supply in an independent irrigation project and in an independent recreational development should each be appraised on their own merits. Next, the projects should be evaluated as combined facilities, such as an electricity-cum-irrigation project, an electricity-cum-recreational project, and an irrigation-cum-recreational project. n each of these combinations, the technology and operating program should be designed to maximize the net benefits from the combined facilities. Finally, the combined electricity, irrigation, and recreational projects are evaluated. Again, the technology and operating plans will have to be designed to maximize the net benefits from the combined facilities. These alternatives must then be compared to find the one that yields the maximum NPV. t is frequently the case that the project that ends up with the highest NPV is the one containing fewer components than was initially proposed by its sponsor. A common investment problem of the type that involves separable component projects arises when a decision is being made as to whether or not existing equipment should be replaced. When faced with this decision, there are three possible courses of action: (a) Keep the old asset and do not buy the new asset now. 140 Scale, Timing, Length, and nterdependencies

19 (b) Sell the old asset and purchase the new one. (c) Keep the old asset and, in addition, buy the new one. The present value of all future benefits that could be generated by the old asset (evaluated net of operating cost) will be denoted by B o and the liquidation or scrap value of the old asset, if sold, SV o. The present value of future benefits (net of operating costs) from the new asset will be expressed as B n and the present value of the investment costs for the new asset as C n. The combined benefits from the use of the old and new assets together will be denoted as B n+o. The first step is to appraise each of the three alternatives to determine which of them are feasible, i.e., which of the three generate positive NPVs. These comparisons are as follows: n order that alternative (a) be feasible, the present value of the future benefits from the old asset must exceed its liquidation value, i.e., B o SV o > 0. n order for alternative (b) to be feasible, the present value of the future benefits from the new asset must be higher than the present value of its investment costs, i.e., B n C n > 0. n order for alternative (c) to be feasible, the total benefits produced by both assets combined must be greater than the costs of the new investment plus the liquidation value of the old asset. n this case, the old asset is retained, to be used along with the new asset. This is expressed as B n+o (C n + SV o ) > 0. f each of the alternatives is feasible, a comparison must be carried out to determine which component or combination yields the greatest NPV. To determine whether or not to replace the old asset with the new one, it is necessary to calculate whether (B n B o ) (C n SV o ) is more or less than 0. f it is less than 0, the assets should not be exchanged. However, retaining the old asset while purchasing the new one would still be a viable option if (B n+o B n ) SV o > 0. This condition for retaining the two assets amounts to each one justifying itself as the marginal asset. Alternatively, if (B n B o ) (C n SV o ) < 0 and (B n+o B o ) C n < 0, the old facilities should continue to be used without any new investment. Finally, if the conditions are (B n B o ) (C n SV o ) > 0 and (B n+o B n ) SV o < 0, the old asset should be replaced with the new one. One way to describe these comparisons is to define (B n+o B o ) as B n/o and (B n+o B n ) as B o/n. n this notation, B n/o is the incremental benefit Chapter Five 141

20 of the new asset in the presence of the old, and B o/n is the incremental benefit of the old asset in the presence of the new. The condition that is required for both assets to be present in the final package is that both B n/o > C n and B o/n > SV o. This means that each component must justify itself as the marginal item in the picture. This same principle governs in all cases where one has to deal with separable components of a project. Each separable component must justify itself as a marginal or incremental part of the overall project. The careful examination of the alternative components of a potentially integrated project is thus an important task in the preparation and appraisal phase of a project. Failure to do this may mean that potentially valuable projects are not implemented because they were evaluated as part of a larger, unattractive package. On the other hand, wasteful projects might be implemented because they have been included in a larger integrated project that as a whole is worthwhile, but could be improved if the wasteful components were eliminated. Complementarity and Substitutability among Projects Once project analysts start to consider the interrelations between projects, a substantial number of possibilities emerge. t is instructive to examine these possibilities in detail. Denoting PVB as present value of benefits and PVC as present value of costs, we have the following cases: PVB + PVB = PVB + Projects and are independents on the benefit side PVB + PVB > PVB + Projects and are substitutes on the benefit side PVB + PVB < PVB + Projects and are complements on the benefit side PVC + PVC = PVC + Projects and are independents on the cost side PVC + PVC > PVC + Projects and are complements on the cost side PVC + PVC < PVC + Projects and are substitutes on the cost side ndependent projects will not be dealt with here. Examples of such projects would be a spaghetti factory in San Francisco and a highway improvement on Long sland. One project essentially has nothing to do with the other. A case in which projects are substitutes on the benefit side has already been examined. t is impossible for a multi-purpose dam to generate, as a multi-purpose project, the sum total that could be achieved 142 Scale, Timing, Length, and nterdependencies

21 if the benefits of the same project (e.g., a dam), independently maximized for each separate purpose, were added together. Thus, multipurpose dams invariably entail substitution among the separate purposes. Complementarity on the benefit side is relatively easy to deal with. An automobile will not function on three wheels, or without a carburetor. Hence, the marginal benefit of adding the fourth wheel, or the carburetor, is enormous. A more subtle case of complementarity on the benefit side, well known in the literature of economics, is that of an apiary project together with an orchard. The presence of the orchard enhances the benefits of the apiary; the presence of the bees also enhances the value of the orchard. Whereas the separate purposes of multi-purpose dams are invariable substitutes on the benefit side, they are practically always complements on the cost side. To build one dam to serve several purposes will almost always cost less than the sum total of the two or more costs of building (at least hypothetically) separate dams to serve each of the separate purposes. Cases of substitutability on the cost side are harder to find, but they clearly exist. A dam project that will produce a larger lake will clearly be competitive with a highway whose natural route would cross the area to be flooded. The total costs of the two projects together will exceed the sum of the costs of the two, considered above. Similarly, a project to urbanize an area is likely to compound the costs of a highway project going through that area. Altogether, one must be alert to the possibilities of substitution and complementarity between and among projects. The underlying principle is always the same: maximize NPV. ts corollary is precisely the principle of separable components, as previously stated. Each separable component must justify itself as the marginal one. This becomes a problem where issues of substitutability are involved, though rarely so in cases of complementarity on both sides (benefits and costs). Perhaps the most interesting cases are those (like multi-purpose dams) in which complementarity on one side (in this case, the cost side) has to fight with substitutability on the other. 5.5 Conclusion The timing and scale of projects are often important considerations in project evaluation. This chapter has discussed the issues and presented some decision rules for projects according to the NPV criterion. n Chapter Five 143

22 addition, project analysts often face an issue of choosing between highly profitable, mutually exclusive projects with different lengths of life. Alternative approaches have been presented: either adjust the costs or benefits, or annualize the benefits in making a choice among mutually exclusive projects. n reality, an investment often contains several interrelated investments, either substitute or complementary. The concept of the NPV of the project s benefits and costs can provide a powerful tool for selecting a project with single component or combination of components. References European Commission mpact Assessment Guidelines (June 15) and Annexes to mpact Assessment Guidelines (June 15). Harberger, A.C Cost-Benefit Analysis of Transportation Projects, Project Evaluation Collected Papers. London: The Macmillan Press. Pacheco-de-Almeida, G. and P. Zemsky The Effect of Time-to-Build on Strategic nvestment under Uncertainty, RAND Journal of Economics 34(1), Szymanski, S The Optimal Timing of nfrastructure nvestment, Journal of Transport Economics and Policy 25(3), Scale, Timing, Length, and nterdependencies

2. Basic Concepts In Project Appraisal [DoF Ch. 4; FP Ch. 3, 4, 5]

2. Basic Concepts In Project Appraisal [DoF Ch. 4; FP Ch. 3, 4, 5] R.E.Marks 2003 Lecture 3-1 2. Basic Concepts In Project Appraisal [DoF Ch. 4; FP Ch. 3, 4, 5] 1. Which Investment Criterion? 2. Investment Decision Criteria 3. Net Present Value Annual User Charge / Value

More information

3: Balance Equations

3: Balance Equations 3.1 Balance Equations Accounts with Constant Interest Rates 15 3: Balance Equations Investments typically consist of giving up something today in the hope of greater benefits in the future, resulting in

More information

8: Economic Criteria

8: Economic Criteria 8.1 Economic Criteria Capital Budgeting 1 8: Economic Criteria The preceding chapters show how to discount and compound a variety of different types of cash flows. This chapter explains the use of those

More information

Benefit-Cost Analysis: Introduction and Overview

Benefit-Cost Analysis: Introduction and Overview 1 Benefit-Cost Analysis: Introduction and Overview Introduction Social benefit-cost analysis is a process of identifying, measuring and comparing the social benefits and costs of an investment project

More information

CHAPTER 22. Real Options. Chapter Synopsis

CHAPTER 22. Real Options. Chapter Synopsis CHAPTER 22 Real Options Chapter Synopsis 22.1 Real Versus Financial Options A real option is the right, but not the obligation, to make a decision regarding an investment in real assets, such as to expand

More information

Investment Appraisal

Investment Appraisal Investment Appraisal Introduction to Investment Appraisal Whatever level of management authorises a capital expenditure, the proposed investment should be properly evaluated, and found to be worthwhile

More information

Investment, Time, and Capital Markets

Investment, Time, and Capital Markets C H A P T E R 15 Investment, Time, and Capital Markets Prepared by: Fernando & Yvonn Quijano CHAPTER 15 OUTLINE 15.1 Stocks versus Flows 15.2 Present Discounted Value 15.3 The Value of a Bond 15.4 The

More information

PRINCIPLES OF FINANCIAL APPRAISAL

PRINCIPLES OF FINANCIAL APPRAISAL LOWER MEKONG PUBLIC POLICY INITIATIVE Technical Training in Project Appraisal for the Lower Mekong Basin PRINCIPLES OF FINANCIAL APPRAISAL Ho Chi Minh City Nov 28 - Dec 09, 2016 Financial Analysis: Basic

More information

Time and Agricultural Production Processes

Time and Agricultural Production Processes 324 21 Time and Agricultural Production Processes Chapters 2! 18 treated production processes in a comparative statics framework, and the time element was largely ignored. This chapter introduces time

More information

Global Financial Management

Global Financial Management Global Financial Management Valuation of Cash Flows Investment Decisions and Capital Budgeting Copyright 2004. All Worldwide Rights Reserved. See Credits for permissions. Latest Revision: August 23, 2004

More information

CHAPTER 12 APPENDIX Valuing Some More Real Options

CHAPTER 12 APPENDIX Valuing Some More Real Options CHAPTER 12 APPENDIX Valuing Some More Real Options This appendix demonstrates how to work out the value of different types of real options. By assuming the world is risk neutral, it is ignoring the fact

More information

Chapter 14 Solutions Solution 14.1

Chapter 14 Solutions Solution 14.1 Chapter 14 Solutions Solution 14.1 a) Compare and contrast the various methods of investment appraisal. To what extent would it be true to say there is a place for each of them As capital investment decisions

More information

AFM 271 Practice Problem Set #2 Spring 2005 Suggested Solutions

AFM 271 Practice Problem Set #2 Spring 2005 Suggested Solutions AFM 271 Practice Problem Set #2 Spring 2005 Suggested Solutions 1. Text Problems: 6.2 (a) Consider the following table: time cash flow cumulative cash flow 0 -$1,000,000 -$1,000,000 1 $150,000 -$850,000

More information

Chapter 6 Capital Budgeting

Chapter 6 Capital Budgeting Chapter 6 Capital Budgeting The objectives of this chapter are to enable you to: Understand different methods for analyzing budgeting of corporate cash flows Determine relevant cash flows for a project

More information

Cost Benefit Analysis (CBA) Economic Analysis (EA)

Cost Benefit Analysis (CBA) Economic Analysis (EA) Cost Benefit Analysis (CBA) Economic Analysis (EA) This is an overview of the preliminary work that should be completed before launching into a full CBA to determine the net economic worth of a proposal

More information

Investment Analysis and Project Assessment

Investment Analysis and Project Assessment Strategic Business Planning for Commercial Producers Investment Analysis and Project Assessment Michael Boehlje and Cole Ehmke Center for Food and Agricultural Business Purdue University Capital investment

More information

INVESTMENT APPRAISAL TECHNIQUES FOR SMALL AND MEDIUM SCALE ENTERPRISES

INVESTMENT APPRAISAL TECHNIQUES FOR SMALL AND MEDIUM SCALE ENTERPRISES SAMUEL ADEGBOYEGA UNIVERSITY COLLEGE OF MANAGEMENT AND SOCIAL SCIENCES DEPARTMENT OF BUSINESS ADMINISTRATION COURSE CODE: BUS 413 COURSE TITLE: SMALL AND MEDIUM SCALE ENTERPRISE MANAGEMENT SESSION: 2017/2018,

More information

Topic 2: Define Key Inputs and Input-to-Output Logic

Topic 2: Define Key Inputs and Input-to-Output Logic Mining Company Case Study: Introduction (continued) These outputs were selected for the model because NPV greater than zero is a key project acceptance hurdle and IRR is the discount rate at which an investment

More information

Project Appraisal and Selection

Project Appraisal and Selection Project Appraisal and Selection Project Appraisal Objectives Dr. DNS Dhakal Duke University Leadership for Results Program for Mid-Level Officers in the Nepalese Civil Service Kathmandu, Nepal 2 September

More information

DISCOUNTED CASH-FLOW ANALYSIS

DISCOUNTED CASH-FLOW ANALYSIS DISCOUNTED CASH-FLOW ANALYSIS Objectives: Study determinants of incremental cash flows Estimate incremental after-tax cash flows from accounting data and use them to estimate NPV Introduce salvage value

More information

COST-BENEFIT ANALYSIS Economics 437 / Economics 837 Spring 2014

COST-BENEFIT ANALYSIS Economics 437 / Economics 837 Spring 2014 COST-BENEFIT ANALYSIS Economics 437 / Economics 837 Spring 2014 Problem Set 2 Timing, Scale and Cost of capital Due May 21 @ 16:00 hrs 1 Timing, Scale and Cost of capital 1. Timing A small firm is considering

More information

Chapter 6: Supply and Demand with Income in the Form of Endowments

Chapter 6: Supply and Demand with Income in the Form of Endowments Chapter 6: Supply and Demand with Income in the Form of Endowments 6.1: Introduction This chapter and the next contain almost identical analyses concerning the supply and demand implied by different kinds

More information

4: Single Cash Flows and Equivalence

4: Single Cash Flows and Equivalence 4.1 Single Cash Flows and Equivalence Basic Concepts 28 4: Single Cash Flows and Equivalence This chapter explains basic concepts of project economics by examining single cash flows. This means that each

More information

University 18 Lessons Financial Management. Unit 2: Capital Budgeting Decisions

University 18 Lessons Financial Management. Unit 2: Capital Budgeting Decisions University 18 Lessons Financial Management Unit 2: Capital Budgeting Decisions Nature of Investment Decisions The investment decisions of a firm are generally known as the capital budgeting, or capital

More information

Measuring Sustainability in the UN System of Environmental-Economic Accounting

Measuring Sustainability in the UN System of Environmental-Economic Accounting Measuring Sustainability in the UN System of Environmental-Economic Accounting Kirk Hamilton April 2014 Grantham Research Institute on Climate Change and the Environment Working Paper No. 154 The Grantham

More information

ECON Micro Foundations

ECON Micro Foundations ECON 302 - Micro Foundations Michael Bar September 13, 2016 Contents 1 Consumer s Choice 2 1.1 Preferences.................................... 2 1.2 Budget Constraint................................ 3

More information

CAPITAL BUDGETING AND THE INVESTMENT DECISION

CAPITAL BUDGETING AND THE INVESTMENT DECISION C H A P T E R 1 2 CAPITAL BUDGETING AND THE INVESTMENT DECISION I N T R O D U C T I O N This chapter begins by discussing some of the problems associated with capital asset decisions, such as the long

More information

Topic 1 (Week 1): Capital Budgeting

Topic 1 (Week 1): Capital Budgeting 4.2. The Three Rules of Time Travel Rule 1: Comparing and combining values Topic 1 (Week 1): Capital Budgeting It is only possible to compare or combine values at the same point in time. A dollar today

More information

9 D/S of/for Labor. 9.1 Demand for Labor. Microeconomics I - Lecture #9, April 14, 2009

9 D/S of/for Labor. 9.1 Demand for Labor. Microeconomics I - Lecture #9, April 14, 2009 Microeconomics I - Lecture #9, April 14, 2009 9 D/S of/for Labor 9.1 Demand for Labor Demand for labor depends on the price of labor, price of output and production function. In optimum a firm employs

More information

Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS

Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS 10-1 a. Capital budgeting is the whole process of analyzing projects and deciding whether

More information

Chapter 26. Retirement Planning Basics 26. (1) Introduction

Chapter 26. Retirement Planning Basics 26. (1) Introduction 26. (1) Introduction People are living longer in modern times than they did in the past. Experts project that as life spans continue to increase, the average individual will spend between 20 and 30 years

More information

A cost is anything that reduces an objective and a benefit is anything that contributes to an objective.

A cost is anything that reduces an objective and a benefit is anything that contributes to an objective. McPeak Lecture 5 PAI 897 Costs and Benefits. A cost is anything that reduces an objective and a benefit is anything that contributes to an objective. One measure we may use of social welfare is national

More information

Chapter 19: Compensating and Equivalent Variations

Chapter 19: Compensating and Equivalent Variations Chapter 19: Compensating and Equivalent Variations 19.1: Introduction This chapter is interesting and important. It also helps to answer a question you may well have been asking ever since we studied quasi-linear

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

Capital Stock Conference March 1997 Agenda Item V. The use of the Perpetual Inventory Method in the UK; Practices and Problems

Capital Stock Conference March 1997 Agenda Item V. The use of the Perpetual Inventory Method in the UK; Practices and Problems Capital Stock Conference March 1997 Agenda Item V The use of the Perpetual Inventory Method in the UK; Practices and Problems 1 CONFERENCE ON CAPITAL STOCK - CANBERRA 1997 The Use of the Perpetual Inventory

More information

A GUIDE TO ASSIGNMENT 2

A GUIDE TO ASSIGNMENT 2 A GUIDE TO ASSIGNMENT 2 CALCULATION - SOLUTIONS APPROACH Chapter 2: evaluation This unit discusses techniques that can be used to decide whether it is feasible to proceed with a given project or not. It

More information

Capital Budgeting Process and Techniques 93. Chapter 7: Capital Budgeting Process and Techniques

Capital Budgeting Process and Techniques 93. Chapter 7: Capital Budgeting Process and Techniques Capital Budgeting Process and Techniques 93 Answers to questions Chapter 7: Capital Budgeting Process and Techniques 7-. a. Type I error means rejecting a good project. Payback could lead to Type errors

More information

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper june 07 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Contents: Page Preface Executive Summary 1 2 1 Service Costing in the General Government

More information

ACCA. Paper F9. Financial Management. December 2014 to June Interim Assessment Answers

ACCA. Paper F9. Financial Management. December 2014 to June Interim Assessment Answers ACCA Paper F9 Financial Management December 204 to June 205 Interim Assessment Answers To gain maximum benefit, do not refer to these answers until you have completed the interim assessment questions and

More information

ECONOMIC TOOLS FOR EVALUATING FISH BUSINESS. S.K.Pandey and Shyam.S.Salim

ECONOMIC TOOLS FOR EVALUATING FISH BUSINESS. S.K.Pandey and Shyam.S.Salim II ECONOMIC TOOLS FOR EVALUATING FISH BUSINESS S.K.Pandey and Shyam.S.Salim II Introduction In fisheries projects, costs are easier to identify than benefits because the expenditure pattern is easily visualized.

More information

Valuation and Tax Policy

Valuation and Tax Policy Valuation and Tax Policy Lakehead University Winter 2005 Formula Approach for Valuing Companies Let EBIT t Earnings before interest and taxes at time t T Corporate tax rate I t Firm s investments at time

More information

The application of linear programming to management accounting

The application of linear programming to management accounting The application of linear programming to management accounting After studying this chapter, you should be able to: formulate the linear programming model and calculate marginal rates of substitution and

More information

Answers To Chapter 7. Review Questions

Answers To Chapter 7. Review Questions Answers To Chapter 7 Review Questions 1. Answer d. In the household production model, income is assumed to be spent on market-purchased goods and services. Time spent in home production yields commodities

More information

*Efficient markets assumed

*Efficient markets assumed LECTURE 1 Introduction To Corporate Projects, Investments, and Major Theories Corporate Finance It is about how corporations make financial decisions. It is about money and markets, but also about people.

More information

1. Traditional investment theory versus the options approach

1. Traditional investment theory versus the options approach Econ 659: Real options and investment I. Introduction 1. Traditional investment theory versus the options approach - traditional approach: determine whether the expected net present value exceeds zero,

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

Introduction to Benefit Cost Analysis HST, IMK, ARF

Introduction to Benefit Cost Analysis HST, IMK, ARF Introduction to Benefit Cost Analysis HST, IMK, ARF Introduction Cost-benefit analysis is a set of practical procedures for guiding public expenditure decisions. 2 Present Value Project evaluation usually

More information

THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA. Contents. Chapter. 1. The COBA Method. 2. The Do-Minimum and Do-Something Options

THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA. Contents. Chapter. 1. The COBA Method. 2. The Do-Minimum and Do-Something Options THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA Contents Chapter 1. The COBA Method 2. The Do-Minimum and Do-Something Options 3. The Fixed Trip Matrix 4. Discounting and the Price Basis 5.

More information

MFE8812 Bond Portfolio Management

MFE8812 Bond Portfolio Management MFE8812 Bond Portfolio Management William C. H. Leon Nanyang Business School January 16, 2018 1 / 63 William C. H. Leon MFE8812 Bond Portfolio Management 1 Overview Value of Cash Flows Value of a Bond

More information

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Learning Objectives LO1 How to compute the net present value and why it is the best decision criterion. LO2 The payback rule and some of its shortcomings.

More information

Rural Financial Intermediaries

Rural Financial Intermediaries Rural Financial Intermediaries 1. Limited Liability, Collateral and Its Substitutes 1 A striking empirical fact about the operation of rural financial markets is how markedly the conditions of access can

More information

ACCA Paper F9 Financial Management. Mock Exam. Commentary, Marking scheme and Suggested solutions

ACCA Paper F9 Financial Management. Mock Exam. Commentary, Marking scheme and Suggested solutions ACCA Paper F9 Financial Management Mock Exam Commentary, Marking scheme and Suggested solutions 2 Suggested solutions Section A D Statement A is incorrect: Matching (not smoothing) is where liabilities

More information

Investment 3.1 INTRODUCTION. Fixed investment

Investment 3.1 INTRODUCTION. Fixed investment 3 Investment 3.1 INTRODUCTION Investment expenditure includes spending on a large variety of assets. The main distinction is between fixed investment, or fixed capital formation (the purchase of durable

More information

Cost-Benefit Analysis Concepts and Practice Boardman Greenberg Vining Weimer Fourth Edition

Cost-Benefit Analysis Concepts and Practice Boardman Greenberg Vining Weimer Fourth Edition Cost-Benefit Analysis Concepts and Practice Boardman Greenberg Vining Weimer Fourth Edition Pearson Education Limited Edinburgh Gate Harlow Essex CM20 2JE England and Associated Companies throughout the

More information

Chapter 2 Time Value of Money ANSWERS TO END-OF-CHAPTER QUESTIONS

Chapter 2 Time Value of Money ANSWERS TO END-OF-CHAPTER QUESTIONS Chapter 2 Time Value of Money ANSWERS TO END-OF-CHAPTER QUESTIONS 2-1 a. PV (present value) is the value today of a future payment, or stream of payments, discounted at the appropriate rate of interest.

More information

Copyright Disclaimer under Section 107 of the Copyright Act 1976, allowance is made for "fair use" for purposes such as criticism, comment, news

Copyright Disclaimer under Section 107 of the Copyright Act 1976, allowance is made for fair use for purposes such as criticism, comment, news Copyright Disclaimer under Section 107 of the Copyright Act 1976, allowance is made for "fair use" for purposes such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use

More information

Cash Flow and the Time Value of Money

Cash Flow and the Time Value of Money Harvard Business School 9-177-012 Rev. October 1, 1976 Cash Flow and the Time Value of Money A promising new product is nationally introduced based on its future sales and subsequent profits. A piece of

More information

BFC2140: Corporate Finance 1

BFC2140: Corporate Finance 1 BFC2140: Corporate Finance 1 Table of Contents Topic 1: Introduction to Financial Mathematics... 2 Topic 2: Financial Mathematics II... 5 Topic 3: Valuation of Bonds & Equities... 9 Topic 4: Project Evaluation

More information

Production, Revenue, and Cost

Production, Revenue, and Cost Production, Revenue, and Cost All businesses are formed to produce a set of goods and/or services for sale at a profit. Business can be classified into proprietorships, partnerships, and corporations.

More information

COMPARING ALTERNATIVES

COMPARING ALTERNATIVES CHAPTER 6 COMPARING FEASIBLE DESIGN Alternatives may be mutually exclusive (i.e., choice if one excludes the choice of any other alternative) because : The alternatives being considered may require different

More information

IAS Impairment of Assets. By:

IAS Impairment of Assets. By: IAS - 36 Impairment of Assets International Accounting Standard No. 36 (IAS 36) Impairment of Assets Objective 1. The objective of this Standard is to establish procedures that an entity applies to ensure

More information

The Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management

The Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management The Duration Derby: A Comparison of Duration Based Strategies in Asset Liability Management H. Zheng Department of Mathematics, Imperial College London SW7 2BZ, UK h.zheng@ic.ac.uk L. C. Thomas School

More information

MODULE 4 PLANNING AND CONTROL

MODULE 4 PLANNING AND CONTROL MODULE 4 PLANNING AND CONTROL OUTLINES The purpose of budgetary control system Alternative approaches to budgeting, including incremental budgeting, Zero-based budgeting, Activity-based budgeting, rolling

More information

Solution to Problem Set 2

Solution to Problem Set 2 M.I.T. Spring 1999 Sloan School of Management 15.15 Solution to Problem Set 1. The correct statements are (c) and (d). We have seen in class how to obtain bond prices and forward rates given the current

More information

Lecture 2 Dynamic Equilibrium Models: Three and More (Finite) Periods

Lecture 2 Dynamic Equilibrium Models: Three and More (Finite) Periods Lecture 2 Dynamic Equilibrium Models: Three and More (Finite) Periods. Introduction In ECON 50, we discussed the structure of two-period dynamic general equilibrium models, some solution methods, and their

More information

I. The Profit-Maximizing Firm

I. The Profit-Maximizing Firm University of Pacific-Economics 53 Lecture Notes #7 I. The Profit-Maximizing Firm Starting with this chapter we will begin to examine the behavior of the firm. As you may recall firms purchase (demand)

More information

INTERMEDIATE MICROECONOMICS LECTURE 9 THE COSTS OF PRODUCTION

INTERMEDIATE MICROECONOMICS LECTURE 9 THE COSTS OF PRODUCTION 9-1 INTERMEDIATE MICROECONOMICS LECTURE 9 THE COSTS OF PRODUCTION The opportunity cost of an asset (or, more generally, of a choice) is the highest valued opportunity that must be passed up to allow current

More information

2. A DIAGRAMMATIC APPROACH TO THE OPTIMAL LEVEL OF PUBLIC INPUTS

2. A DIAGRAMMATIC APPROACH TO THE OPTIMAL LEVEL OF PUBLIC INPUTS 2. A DIAGRAMMATIC APPROACH TO THE OPTIMAL LEVEL OF PUBLIC INPUTS JEL Classification: H21,H3,H41,H43 Keywords: Second best, excess burden, public input. Remarks 1. A version of this chapter has been accepted

More information

UNIT 5 COST OF CAPITAL

UNIT 5 COST OF CAPITAL UNIT 5 COST OF CAPITAL UNIT 5 COST OF CAPITAL Cost of Capital Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Concept of Cost of Capital 5.3 Importance of Cost of Capital 5.4 Classification of Cost

More information

Six Ways to Perform Economic Evaluations of Projects

Six Ways to Perform Economic Evaluations of Projects Six Ways to Perform Economic Evaluations of Projects Course No: B03-003 Credit: 3 PDH A. Bhatia Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800

More information

The Capital Expenditure Decision

The Capital Expenditure Decision 1 2 October 1989 The Capital Expenditure Decision CONTENTS 2 Paragraphs INTRODUCTION... 1-4 SECTION 1 QUANTITATIVE ESTIMATES... 5-44 Fixed Investment Estimates... 8-11 Working Capital Estimates... 12 The

More information

The Time Value. The importance of money flows from it being a link between the present and the future. John Maynard Keynes

The Time Value. The importance of money flows from it being a link between the present and the future. John Maynard Keynes The Time Value of Money The importance of money flows from it being a link between the present and the future. John Maynard Keynes Get a Free $,000 Bond with Every Car Bought This Week! There is a car

More information

WHAT IS CAPITAL BUDGETING?

WHAT IS CAPITAL BUDGETING? WHAT IS CAPITAL BUDGETING? Capital budgeting is a required managerial tool. One duty of a financial manager is to choose investments with satisfactory cash flows and rates of return. Therefore, a financial

More information

1 Ricardian Neutrality of Fiscal Policy

1 Ricardian Neutrality of Fiscal Policy 1 Ricardian Neutrality of Fiscal Policy For a long time, when economists thought about the effect of government debt on aggregate output, they focused on the so called crowding-out effect. To simplify

More information

Economic Risk and Decision Analysis for Oil and Gas Industry CE School of Engineering and Technology Asian Institute of Technology

Economic Risk and Decision Analysis for Oil and Gas Industry CE School of Engineering and Technology Asian Institute of Technology Economic Risk and Decision Analysis for Oil and Gas Industry CE81.98 School of Engineering and Technology Asian Institute of Technology January Semester Presented by Dr. Thitisak Boonpramote Department

More information

, the nominal money supply M is. M = m B = = 2400

, the nominal money supply M is. M = m B = = 2400 Economics 285 Chris Georges Help With Practice Problems 7 2. In the extended model (Ch. 15) DAS is: π t = E t 1 π t + φ (Y t Ȳ ) + v t. Given v t = 0, then for expected inflation to be correct (E t 1 π

More information

1 The EOQ and Extensions

1 The EOQ and Extensions IEOR4000: Production Management Lecture 2 Professor Guillermo Gallego September 16, 2003 Lecture Plan 1. The EOQ and Extensions 2. Multi-Item EOQ Model 1 The EOQ and Extensions We have explored some of

More information

2 USES OF CONSUMER PRICE INDICES

2 USES OF CONSUMER PRICE INDICES 2 USES OF CONSUMER PRICE INDICES 2.1 The consumer price index (CPI) is treated as a key indicator of economic performance in most countries. The purpose of this chapter is to explain why CPIs are compiled

More information

Sample Chapter REAL OPTIONS ANALYSIS: THE NEW TOOL HOW IS REAL OPTIONS ANALYSIS DIFFERENT?

Sample Chapter REAL OPTIONS ANALYSIS: THE NEW TOOL HOW IS REAL OPTIONS ANALYSIS DIFFERENT? 4 REAL OPTIONS ANALYSIS: THE NEW TOOL The discounted cash flow (DCF) method and decision tree analysis (DTA) are standard tools used by analysts and other professionals in project valuation, and they serve

More information

6 Calculating the Net Benefits to the Referent Group

6 Calculating the Net Benefits to the Referent Group 6 Calculating the Net Benefits to the Referent Group Introduction The referent group in a social benefit-cost analysis is unlikely to consist only of the equity holders of the private firm, at one extreme,

More information

FINANCIAL MANAGEMENT ( PART-2 ) NET PRESENT VALUE

FINANCIAL MANAGEMENT ( PART-2 ) NET PRESENT VALUE FINANCIAL MANAGEMENT ( PART-2 ) NET PRESENT VALUE 1. INTRODUCTION Dear students, welcome to the lecture series on financial management. Today in this lecture, we shall learn the techniques of evaluation

More information

Global Financial Management

Global Financial Management Global Financial Management Bond Valuation Copyright 24. All Worldwide Rights Reserved. See Credits for permissions. Latest Revision: August 23, 24. Bonds Bonds are securities that establish a creditor

More information

Homework 4. Public Projects. (a) Using the benefit cost ratio, which system should be selected?

Homework 4. Public Projects. (a) Using the benefit cost ratio, which system should be selected? Homework 4. Public Projects 1. A city government is considering two types of town-dump sanitary systems, Design A requires an initial outlay of $400,000, with annual operating and maintenance costs of

More information

The Benefit: Cost Ratio

The Benefit: Cost Ratio www.inffer.org The Benefit: Cost Ratio David Pannell The information to calculate the Benefit: Cost Ratio (BCR) is collected in the course of completing the Project Assessment Form (PAF). The variables

More information

Country-by-country Reporting

Country-by-country Reporting CIYPERC Working Paper Series 2017/02 Country-by-country Reporting An exploration of the data potential for tax authorities Richard Murphy City Political Economy Research Centre City, University of London

More information

Web Extension: Continuous Distributions and Estimating Beta with a Calculator

Web Extension: Continuous Distributions and Estimating Beta with a Calculator 19878_02W_p001-008.qxd 3/10/06 9:51 AM Page 1 C H A P T E R 2 Web Extension: Continuous Distributions and Estimating Beta with a Calculator This extension explains continuous probability distributions

More information

A guide to how we fund and deliver Flood Risk Management Schemes

A guide to how we fund and deliver Flood Risk Management Schemes A guide to how we fund and deliver Flood Risk Management s We are currently in the appraisal stages of many projects investigating whether schemes to manage flood risk can be provided throughout Cumbria.

More information

True_ The Lagrangian method is one way to solve constrained maximization problems.

True_ The Lagrangian method is one way to solve constrained maximization problems. LECTURE 4: CONSTRAINED OPTIMIZATION ANSWERS AND SOLUTIONS Answers to True/False Questions True_ The Lagrangian method is one way to solve constrained maximization problems. False_ The substitution method

More information

CHAPTER 6 ESTIMATING FIRM VALUE

CHAPTER 6 ESTIMATING FIRM VALUE 1 CHAPTER 6 ESTIMATING FIRM VALUE In the last chapter, you examined the determinants of expected growth. Firms that reinvest substantial portions of their earnings and earn high returns on these investments

More information

Engineering Economics and Financial Accounting

Engineering Economics and Financial Accounting Engineering Economics and Financial Accounting Unit 5: Accounting Major Topics are: Balance Sheet - Profit & Loss Statement - Evaluation of Investment decisions Average Rate of Return - Payback Period

More information

CHAPTER 9 CONCEPT REVIEW QUESTIONS

CHAPTER 9 CONCEPT REVIEW QUESTIONS CHAPTER 9 CONCEPT REVIEW QUESTIONS 1. Why is it important for the financial analyst to (a) focus on incremental cash flows, (b) ignore financing costs, (c) consider taxes, and (d) adjust for noncash expenses

More information

Extraction capacity and the optimal order of extraction. By: Stephen P. Holland

Extraction capacity and the optimal order of extraction. By: Stephen P. Holland Extraction capacity and the optimal order of extraction By: Stephen P. Holland Holland, Stephen P. (2003) Extraction Capacity and the Optimal Order of Extraction, Journal of Environmental Economics and

More information

MAXIMISE SHAREHOLDERS WEALTH.

MAXIMISE SHAREHOLDERS WEALTH. TOPIC 4: Project Evaluation 4.1 Capital Budgeting Theory: Another term for investing, capital budgeting involves weighing up which assets to purchase with the funds that a company raises from its debt

More information

March 30, Why do economists (and increasingly, engineers and computer scientists) study auctions?

March 30, Why do economists (and increasingly, engineers and computer scientists) study auctions? March 3, 215 Steven A. Matthews, A Technical Primer on Auction Theory I: Independent Private Values, Northwestern University CMSEMS Discussion Paper No. 196, May, 1995. This paper is posted on the course

More information

In Meyer and Reichenstein (2010) and

In Meyer and Reichenstein (2010) and M EYER R EICHENSTEIN Contributions How the Social Security Claiming Decision Affects Portfolio Longevity by William Meyer and William Reichenstein, Ph.D., CFA William Meyer is founder and CEO of Retiree

More information

New Statistics of BTS Panel

New Statistics of BTS Panel THIRD JOINT EUROPEAN COMMISSION OECD WORKSHOP ON INTERNATIONAL DEVELOPMENT OF BUSINESS AND CONSUMER TENDENCY SURVEYS BRUSSELS 12 13 NOVEMBER 27 New Statistics of BTS Panel Serguey TSUKHLO Head, Business

More information

SOLUTIONS TO END-OF-CHAPTER QUESTIONS CHAPTER 16

SOLUTIONS TO END-OF-CHAPTER QUESTIONS CHAPTER 16 SOLUTIONS TO END-OF-CHAPTER QUESTIONS CHAPTER 16 DEVELOP YOUR UNDERSTANDING Question 16.1 Podcaster University Press Payback Accounting book Economics book Annual Cumulative Annual Cumulative cash flows

More information

Economic Perspectives on the Advance Market Commitment for Pneumococcal Vaccines

Economic Perspectives on the Advance Market Commitment for Pneumococcal Vaccines Web Appendix to Accompany Economic Perspectives on the Advance Market Commitment for Pneumococcal Vaccines Health Affairs, August 2011. Christopher M. Snyder Dartmouth College Department of Economics and

More information

Chapter URL:

Chapter URL: This PDF is a selection from an out-of-print volume from the National Bureau of Economic Research Volume Title: Business Loan Costs and Bank Market Structure: An Empirical Estimate of Their Relations Volume

More information

MANAGEMENT INFORMATION

MANAGEMENT INFORMATION CERTIFICATE LEVEL EXAMINATION SAMPLE PAPER 1 (90 MINUTES) MANAGEMENT INFORMATION This assessment consists of ONE scenario based question worth 20 marks and 32 short questions each worth 2.5 marks. At least

More information