1 Request for Clarification: Production Efficiency: Custom and Strategic Energy Management Request For Proposal Questions and Answers ID Respondent Questions Energy Trust of Oregon Responses 1 May we reformat the excel spreadsheets (technical capability matrix, budget proposal) to fit 8.5 x 11 page layout and 11 point font size requirements? requirement. 2 May we re-type Appendix C Cover Sheet content so that it fits the 8.5x11 page and 11 point font size requirements, or should we submit on the pdf form that was in the RFP package? Yes, you are welcome to reformat the excel sheets to fit an 8.5 x 11 page layout, provided you adhere to the 11 point font size Please use the.pdf form that was provided as Appendix C. 3 Is it possible for a provider to respond to the RFP but only for electric solutions rather than both electric and gas? No, proposals must address both electric and gas opportunities in the respondent s territory. 4 Is the use of sub-contractors encouraged by Energy Trust? Energy Trust is interested in proposals that help us meet the goals outlined in the RFP. We do not have a preference regarding whether respondents use subcontractors or not. Respondents must be able to meet the goals and qualifications outlined in the RFP. 5 Will the scoring of a response be different based on whether a bidder doesn't use subs? 6 Can you provide a copy of Energy Trust s standard Terms and Conditions? 7 Can you share any high-level data on the electrical load (amw) in each territory? 8 Given that some gas customers are served on eligible tariffs and some are served on ineligible transport tariffs, can you provide any estimate of how much eligible tariff gas load there is in each territory? Scoring criteria is identified in section 6.3 of the RFP. No, however some of the standard provisions that would be included are noted in section 7.10 of the RFP. Requested information not available. Requested information not available. 1

2 9 Can you provide a more detailed description of the physical dividing line between territory 1 and 2? 10 Will existing open contracts with Energy Trust (SEM, TAS) be transitioned to the PDC in January 2019? Do the open contracts need to be included in our 2019 budget? 11 How much site training time will be required at Energy Trust s office for (onsite) transition trainings, such as CRM, IT, etc.? 12 If a non-incumbent respondent were to take over a territory, would we have access to an extensive history, including past technical studies and SEM completion reports, past record of projects implemented including technical studies performed, energy use history on the electric and gas side, and PDCprepared account plans? Yes, a document identifying the zip codes in territories 1 and 2 will be added to the google drive. Energy Trust anticipates that it will continue to manage and close out all assigned work under its existing ATAC contracts by the end of 2018 and all assigned work under its existing SEM contracts by early These contracts will not be transitioned. Respondents should budget for the transition work described in section 4.2 of the RFP, which includes transition of any new SEM First Year/Continuous work or technical study work that is launched during the transition period (for completion in 2019). Proposed 2019 budgets should address PDC s full delivery of the new program design. Trainings will be identified following selection and will include, at a minimum, two (onsite) trainings on how to access and use Energy Trust systems. Additional orientation trainings on Energy Trust processes and requirements, as well as transition meetings, will be necessary. Respondent s Task 1 operational plan, as described in section 4.2 of the RFP should address respondent s proposed training needs and activities during transition. An incoming PDC will have access to customer project files for their awarded territory and the customer and project information available in the Energy Trust systems of record. Consistent with agreements with its electric and gas funding utilities, Energy Trust receives certain utility customer energy usage data for use in implementing, administering, and/or evaluating Energy Trust programs. All such data is subject to specific confidentiality requirements. Access requires that the PDC (and any of its relevant subcontractors) sign a specific company nondisclosure agreement. Additionally all individuals receiving access to the data are required to sign a specific individual nondisclosure agreement. These nondisclosure agreements have been approved as to form by the utilities and are required without modification. 2

3 13 Do we need Energy Trust permission to authorize (e.g. issue a work order) a technical analysis study on a "project by project" basis, or does the PDC authorize work to manage to the budget without prior approval? 14 Does Energy Trust provide oversight of the budget for TAS; for example, if the RFP submitted budget calls for $300,000 for TAS, and there is an over or under this amount, does Energy Trust adjust the budget, or is the PDC responsible for over/under? 15 What are the expectations for M&V at completion? Our understanding is that many or most projects are inspected to verify set-points, but not measured? Can you offer any shareable data on what fraction of projects or savings are subjected to post-install measurements? Has that historically been a PDC task or a technical study task? 16 Would a lighting system operations and maintenance (O&M) project identified and supported by a custom PDC count toward the custom O&M track? 17 For recent years, can you share any data for what fraction of custom capital and O&M track savings were supported by an Energy Trust technical study (ATAC) versus the technical analysis done in some other fashion? 18 On the bottom of page 9, the sentence reads Energy Trust expects that one PDC can deliver the Custom and SEM offerings more efficiently than separate contractors. This could be interpreted as saying that Energy Trust prefers that the PDC integrate SEM as their own offering, delivered by their own organization, not by a separate SEM firm contractor working as a sub to the PDC. At the top of page 20, the sentence reads Also, under the new design, it will be the PDC s responsibility to have qualified Energy Trust envisions that technical studies will continue to be proposed and authorized on a project by project basis, but the PDC will manage their service incentive spends to their established annual service incentive budget. Energy Trust s role will include authorizing a PDC-proposed study for a participant and final review of studies for conformance with program requirements and service incentive payment. Once the service incentive budget is set, the PDC will be required to manage spending to meet the budget. PDCs verify all custom projects at completion to ensure that the project as-installed meets program requirements and to confirm energy savings projections. This includes reviewing installed equipment and set-points. Depending on the nature of the project, the verification may require data logging. The level of detail for each verification is determined during the analysis stage and included within the technical study. See section 5.4 of the TAS Template provided in the RFP. All lighting savings are acquired in the standard track. All Energy Trust custom capital and custom O&M projects require a technical study. The PDC prime structures their own team, whether by using staff or subcontractor personnel. Energy Trust is interested in proposals that will help us meet the goals outlined in the RFP and continue to serve customers with excellent customer service. Energy Trust has a continued interest in expanding awareness and knowledge of SEM throughout Oregon, and is interested in having more than one SEM provider in the program 3

4 personnel, whether in-house or subcontracted, to deliver both the SEM coaching and SEM technical model development services to Energy Trust for participant sites located in PDC s territory. This could be interpreted as saying that Energy Trust is open to either approach, where a traditional energy engineering firm may be the PDC prime, and then subcontract to an SEM subject matter expert. 1) Would Energy Trust please clarify the intent? 2) Does Energy Trust prefer one approach over the other? 19 Does Energy Trust intend to have PDCs bill Energy Trust for SEM costs; on a time and materials basis, or a percent completion of a fixed cost budget? 20 RFP budgets for SEM include fixed costs and variable costs per participant. How does Energy Trust intend to deal with over and under budget situations when the number of participants varies from the submitted budget? 21 Please confirm that the First Year SEM is cohort-based and the Continuous SEM is currently individual-customer based. 22 Can the SEM provider be separated into Coach and Modeler/Report Writer as two separate firms? 23 Can Energy Trust please provide a more detailed history of participation or at least participation in 2018 of First Year SEM participants by territory? Energy Trust anticipates that, with the program re-design, industrial program SEM services would be billed as time and materials, in alignment with Energy Trust commercial SEM services; however, this determination is subject to change. Respondents are responsible for budgeting for SEM savings, knowing there may be changes to the number of participants. PDCs will manage to their established not-to-exceed contract budget for managing and delivering their program services, including SEM services to participants. Energy Trust would not monitor SEM costs on a per-participant basis under the program re-design (see the answer to #19 above). First Year SEM is cohort-based but may be delivered on an individual-customer basis in special cases. Continuous SEM is currently delivered on an individual-customer basis but Energy Trust is interested in respondent ideas for integrating cohort elements into the Continuous SEM offering. Energy Trust requires that separate personnel fill the roles of PDC account manager, SEM provider and energy engineer/analyst. How these roles are staffed in the proposal is determined by the respondent. Energy Trust requires the respondent to meet the goals and qualifications outlined in the RFP, including but not limited to enhancing the customer experience. First Year engagements, from , by territory: - Territory 1: 13 - Territory 2: 24 - Territory 3: 28 4

5 24 First Year SEM is within territories but Continuous SEM is across territories. Can Energy Trust please provide an estimate of participants for each territory for Continuous SEM? 25 In the new model, which party (Energy Trust or PDC) has the decision about investing in an SEM engagement? Or an ATAC study? 26 Will PDC be responsible for entering customer/project information into CRM and Project Tracker? 27 Please provide examples of market intelligence that are captured in CRM? 28 Does processing incentive payments include cutting checks by the PDC for the customer incentive payments? 29 Does the Vendor Incentive Funding payment process shift to the PDCs in the new design? 30 As part of program enhancements and capital upgrades, will Energy Trust consider a program that includes the option to upgrade backup generators for customers to ensure they are compliant with federal, state and local requirements? 31 Where do the Program Enhancements fall in the proposal scoring table (Section 6.3) or are they excluded from scoring impact? 32 Confirm that the same person can fill more than one role (e.g. account manager, SEM provider, energy analyst) as long as it is not for the same customer. Currently there are 32 active Continuous SEM engagements: - Territory 1: 7 - Territory 2: 16 - Territory 3: 9 PDCs will propose SEM participants to meet SEM savings goals and Energy Trust will have final approval of participant eligibility for SEM enrollment. See Appendix L for more information. For technical studies, the PDC will propose which projects warrant technical study. Energy Trust will have final approval of proposals for technical studies. Yes. See section 4.5 for more details. Examples include; vertical market type, site contacts and project history. The PDC will be responsible for project processing, entering all data and information into the Energy Trust system of record. Energy Trust will approve payment, issue checks and mail checks to the participant. PDCs also have the option to hand deliver checks to a participant; subject to security requirements. The Vendor Incentive Funding (VIF) is a vendor offering that is managed by Energy Trust, and should not be considered in the RFP saving targets or budgets. Respondents can submit all potential program enhancements and assumptions according to section 4.6 (Task 5: Program Enhancements). Program enhancements that reduce costs, increase savings, broaden participation or address market challenges could improve a respondent s score under strength of proposal. Yes, as long as the respondent can demonstrate adequate levels of checks and balances between the different roles to ensure strong delivery of SEM and customer service. Proposals should allow for the application of consistent, effective quality control procedures, while also maintaining effective communications and management. 5

6 33 Can respondents include Energy Trust Industrial program staff as a reference per Section of the RFP? 34 What is the definition of a significant role/key partner in regard to the requirement of submitting Financial documents submissions? E.g. Do we include financial documents for the ATAC/SEM subcontractors in our pool? 35 Is the Appendix D Excel spreadsheet excluded from the page limit in the Price Proposal? 36 Would you like to see one technical study in an Appendix mentioned on page 21 or one technical study for each of the typical systems found in an industrial facility mentioned on Appendix F? 37 Pricing will hinge on key assumptions around the number of SEM Engagements and Technical Analysis Studies conducted. Appendix I states that the PDC portion of the budget will be billed T&M, not to exceed. Can Energy Trust clarify the contract and billing mechanism for the SEM and ATAC portions of the contract and how variations in SEM participants and TAS quantities will be handled? If we have more or less SEM participants or studies required, will the budget scale accordingly? No. Energy Trust is seeking references from other persons/companies familiar with respondent s work performing services similar to those described in the RFP. Please note that Energy Trust additionally asks that respondents include a brief description of the specific services the respondent provided for each reference listed and how those services relate to work that the respondent is proposing to perform. Respondents may also include additional references knowledgeable of proposed team member services. The respondent is responsible for determining whether an identified subcontractor team member would perform a significant role in their proposal for program implementation and handling of program funds, and would likely be considered a key partner. If so, then respondent must provide the financial information as required under section of the RFP. Energy Trust reserves the right to ask for additional financial information for any respondent subcontractor after proposal submission. Yes. This will not count against page limit. Energy Trust requires the respondent to submit Appendix D as an Excel file when submitting an electronic version of the response. One technical study only. Respondents must budget for technical studies and SEM activities needed to hit energy savings goals. The PDC will be required to manage to its budget amounts for delivering the services to participants and achieving goals regardless of billing structure. 6

7 38 In the pricing template, is Energy Trust expecting staff level detail for each task? For example, tabs 4-6 have 24 tasks. If on average, five people will be working on each task, does Energy Trust expect to see over 100 rows in these tabs or should we limit our response to one row per task with a blended labor rate of the staff assigned? 39 Can Energy Trust please provide the quantity of estimated pipeline projects and savings for natural gas and electricity in all three territories? 40 In Appendix G, page 20, Figure 19: Can you clarify what is in the numerator and denominator for custom study service incentives? Does it include mega-projects? Does the denominator include the identified savings from all studies or only the savings from measures that were implemented? 41 In Appendix G, page 11, Figure 8: The average custom track project size has been trending down and was about 320,000 kwh in Are the figures shown in that trend graph inclusive of the occasional mega-project? 42 In Appendix G, page 19, Figure 16: We are assuming that the cost presented in this graph include both custom track and standard track delivery, but do not include SEM services or custom study costs (i.e., service incentives) in the numerator. Is that correct? 43 In the Appendix D-Pricing spreadsheet, there are three tabs for providing pricing by territory. All activities presently have one row, providing room for one name, rate, and hours. Can we add rows to the spreadsheet if we have activities that we anticipate serving with multiple people at different rates and hours? Or should we use the one row with weighted averages? Energy Trust requires the respondent to separate each individual staff member by task. The subtotal field under each task will develop a weighted average rate by task automatically. Please include all relevant subtasks under each task. Please review the RFP savings targets for 2019, and Appendix G for more information on overall gas savings and historical savings acquisition for the Production Efficiency program. Figure 19 is only technical studies for custom projects; this rate excludes SEM. Megaprojects are also excluded. The savings are not tied to studies but to the savings acquired in the annual year. Megaprojects are excluded. Correct. Yes. The respondent may add rows to spreadsheets. 7

Planning, Engineering, and Environmental Services for the Seawall Resiliency Project

Planning, Engineering, and Environmental Services for the Seawall Resiliency Project Planning, Engineering, and Environmental Services for the Seawall Resiliency Project RFP Written Questions and Responses May 12, 2017 1) Under task 1.03 Existing Conditions Review and Documentation, it

More information

Addendum No. 2 Q&A Responses ADDENDUM NO. 2. State of Florida Department of Management Services

Addendum No. 2 Q&A Responses ADDENDUM NO. 2. State of Florida Department of Management Services Addendum No. 2 Q&A Responses ADDENDUM NO. 2 State of Florida Department of Management Services INVITATION TO Negotiate (ITN) No. 02 973 000 A Management Consulting and Auditing Services August 30, 2012

More information

CITY & COUNTY OF SAN FRANCISCO CONTRACT MONITORING DIVISION CMD ATTACHMENT 3

CITY & COUNTY OF SAN FRANCISCO CONTRACT MONITORING DIVISION CMD ATTACHMENT 3 CITY & COUNTY OF SAN FRANCISCO Requirements for Contracts For Contracts $300,000 & over that are Advertised on or after August 1, 2016 PART I. GENERAL 1.01 SAN FRANCISCO ADMINISTRATIVE CODE CHAPTERS 12B

More information

Addendum #1 provides responses to written inquiries received by the deadline stated in the Request for Proposals.

Addendum #1 provides responses to written inquiries received by the deadline stated in the Request for Proposals. July 7, 2017 Reference Request for Proposals #3000008300 soliciting Proposals from qualified Proposers to administer the Flexible Spending Arrangement (FSA) plans (health care and dependent care) and COBRA

More information

REQUEST FOR PROPOSALS:

REQUEST FOR PROPOSALS: NOTICE TO BIDDERS Request for Proposals for Electric Generation Service and Government Energy Aggregation Services for the Plumsted Community Energy Aggregation Program PLEASE TAKE NOTICE that the Plumsted

More information

APPENDIX 1 RFP Independent Adjusting Services - Catastrophe

APPENDIX 1 RFP Independent Adjusting Services - Catastrophe ADDENDUM NO.: 1 REQUEST FOR PROPOSALS NO.: 17-0006 INDEPENDENT ADJUSTING SERVICES-NON-LITIGATED/CATASTROPHE 5/12/17 Citizens Property Insurance Corporation (Citizens) hereby formally amends the above referenced

More information

OFFICE OF PROCUREMENT AND CONTRACTING 301 Largo Road, Largo Maryland

OFFICE OF PROCUREMENT AND CONTRACTING 301 Largo Road, Largo Maryland OFFICE OF PROCUREMENT AND CONTRACTING 301 Largo Road, Largo Maryland 20774-2199 REQUEST FOR PROPOSAL #18-02 EMPLOYEES BASIC LIFE, ACCIDENTAL DEATH AND DISABILITY Addendum No. 2 Issued: Monday, October

More information

Notice of Request for Proposals For Guaranteed Energy Savings Performance Contract

Notice of Request for Proposals For Guaranteed Energy Savings Performance Contract Notice of Request for Proposals For Guaranteed Energy Savings Performance Contract BID: 2015-PC TO: North Carolina Pre-Qualified ESCOs Issuer: Wake County Public Schools SUBJECT: REQUEST FOR PROPOSALS:

More information

Instructions on Completing the 2015 Revised Estimates Submission in EFIS 2.0

Instructions on Completing the 2015 Revised Estimates Submission in EFIS 2.0 Instructions on Completing the 2015 Revised Estimates Submission in EFIS 2.0 PURPOSE The Revised Estimates submission identifies the level of services and associated expenditures and revenues projected

More information

City And County Of San Francisco Office Of Contract Administration LED LUMINAIRE WITH WIRELESS MONITORING AND CONTROL SYSTEM

City And County Of San Francisco Office Of Contract Administration LED LUMINAIRE WITH WIRELESS MONITORING AND CONTROL SYSTEM City And County Of San Francisco 79000 Office Of Contract Administration APPENDIX I LED LUMINAIRE WITH WIRELESS MONITORING AND CONTROL SYSTEM APPENDIX I HRC FORMS HRC Attachment 3 Requirements for Contracts

More information

A Guide for Nonprofits Receiving Fiscal and Compliance Monitoring

A Guide for Nonprofits Receiving Fiscal and Compliance Monitoring A Guide for Nonprofits Receiving Fiscal and Compliance Monitoring Citywide Nonprofit Monitoring and Capacity Building Program Table of Contents What is the Purpose of the Program?.....3 How Does the Program

More information

City of Forest Park Request for Proposals. Landscape Installation, 803 & 785 Forest Parkway, Forest Park Ga

City of Forest Park Request for Proposals. Landscape Installation, 803 & 785 Forest Parkway, Forest Park Ga City of Forest Park Request for Proposals Landscape Installation, 803 & 785 Forest Parkway, Forest Park Ga. 30297 Mandatory Pre-Proposal Conference at August 19, 2014 at 10:00 am Proposal Deadline September

More information

A Guide for Nonprofits Receiving Fiscal and Compliance Monitoring

A Guide for Nonprofits Receiving Fiscal and Compliance Monitoring A Guide for Nonprofits Receiving Fiscal and Compliance Monitoring Citywide Nonprofit Monitoring and Capacity Building Program Table of Contents What is the Purpose of the Program?.....3 How Does the Program

More information

GUIDE FOR COMPLETING CO-PLAN DD 2794: COST AND SOFTWARE DATA REPORTING (CSDR) & EARNED VALUE MANAGEMENT (EVM) CO-PLAN

GUIDE FOR COMPLETING CO-PLAN DD 2794: COST AND SOFTWARE DATA REPORTING (CSDR) & EARNED VALUE MANAGEMENT (EVM) CO-PLAN GUIDE FOR COMPLETING CO-PLAN DD 2794: COST AND SOFTWARE DATA REPORTING (CSDR) & EARNED VALUE MANAGEMENT (EVM) CO-PLAN JANUARY 2017 The CSDR/EVM Co-Plan is a joint effort between the Office of the Secretary

More information

Gas Cooling Application - July 1, 2016 through June 30, 2017

Gas Cooling Application - July 1, 2016 through June 30, 2017 Gas Cooling Application - July 1, 2016 through June 30, 2017 Customer Information Company Name (as listed on utility bill) Doing Business as (if applicable) Installation Start Date: Installation Completion

More information

Request for Proposal #2036. Orange Coast College Exterior Lighting Energy Efficiency Project Implementation

Request for Proposal #2036. Orange Coast College Exterior Lighting Energy Efficiency Project Implementation Request for Proposal #2036 Orange Coast College Exterior Lighting Energy Efficiency Project Implementation I. NOTICE A. Statement of Proposal NOTICE IS HEREBY GIVEN that Coast Community College District

More information

INQUIRIES AND RESPONSES

INQUIRIES AND RESPONSES May 3, 2016 Reference Request for Proposals #3000005388 soliciting Proposals from qualified Proposers to provide Pharmacy Benefit Manager (PBM) Services for Office of Group Benefits Self-Funded Health

More information

Performance Lighting Application - July 1, 2015 through June, Customer Information

Performance Lighting Application - July 1, 2015 through June, Customer Information Customer Information Company Name (as listed on utility bill) Doing Business as (if applicable) Anticipation Installation Date: (cannot begin prior to approval by Market Manager Electric Utility Serving

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT PROPOSITION 39 EFFICIENCY PROGRAM REQUEST FOR QUALIFICATIONS (RFQ) FOR: UTILITY AUDITING SERVICES

SAN FRANCISCO UNIFIED SCHOOL DISTRICT PROPOSITION 39 EFFICIENCY PROGRAM REQUEST FOR QUALIFICATIONS (RFQ) FOR: UTILITY AUDITING SERVICES SAN FRANCISCO UNIFIED SCHOOL DISTRICT PROPOSITION 39 EFFICIENCY PROGRAM REQUEST FOR QUALIFICATIONS (RFQ) FOR: UTILITY AUDITING SERVICES August 12, 2015 TABLE OF CONTENTS I. INTRODUCTION TO RFQ SUBMITTAL

More information

Lisa Alderson, Contracts and Procurement Supervisor

Lisa Alderson, Contracts and Procurement Supervisor TO: FROM: Prospective Offerors Lisa Alderson, Contracts and Procurement Supervisor SUBJECT: Addendum No. 2 Request for Proposals P38-160 DATE: July 18, 2018 This addendum provides responses to prospective

More information

ADDENDUM NO. 2 REQUEST FOR INFORMATION. for. Contracted Marketer. Landfill Biomethane Gas from Keithville, Louisiana.

ADDENDUM NO. 2 REQUEST FOR INFORMATION. for. Contracted Marketer. Landfill Biomethane Gas from Keithville, Louisiana. ADDENDUM NO. 2 to REQUEST FOR INFORMATION for Contracted Marketer Landfill Biomethane Gas from Keithville, Louisiana April 25, 2016 This addendum includes answers to questions from interested firms: Q.

More information

Affordable Care Act: State Resources FAQ

Affordable Care Act: State Resources FAQ Affordable Care Act: State Resources FAQ Enhanced Funding for Medicaid Eligibility Systems Operation and Maintenance Under the Medicaid program, CMS has provided 90 percent federal matching funds for the

More information

Ohio Public Employees Retirement System. Request for Proposal

Ohio Public Employees Retirement System. Request for Proposal Ohio Public Employees Retirement System For: SharePoint Upgrade Date: September 9, 2016 Project Name: SharePoint 2007 Upgrade 277 East Town Street Columbus, Ohio 43215 1-800-222-PERS (7377) www.opers.org

More information

NC Dept. of Administration

NC Dept. of Administration NC Dept. of Administration State Construction Office REQUEST FOR PROPOSAL FOR GUARANTEED ENERGY SAVINGS PERFORMANCE CONTRACTING January 8, 2016 RFP # 12328 REQUEST FOR PROPOSALS FOR NC Dept. of Administration,

More information

ARTICLE 8: BASIC SERVICES

ARTICLE 8: BASIC SERVICES THE SCOPE OF SERVICES ADDED BY THIS AMENDMENT IS FOR A CM AT RISK PROJECT ONLY. THE SCOPE OF SERVICES SPECIFIED BELOW INCLUDES ARTICLES 8.1, 8.3, 8.4, 8.5, 8.6, 8.7 AND 8.8. THE SERVICES SPECIFIED IN ARTICLE

More information

Invitation to Bid (ITB) Medical and Dental Supplies. No S ADDENDUM NO. 2. Questions and Answers & ITB Revisions

Invitation to Bid (ITB) Medical and Dental Supplies. No S ADDENDUM NO. 2. Questions and Answers & ITB Revisions Invitation to Bid (ITB) Medical and Dental Supplies 19-42000000-S ADDENDUM NO. 2 Questions and Answers & ITB Revisions Page 1 of 8 Contained herein are the answers to the questions submitted to the Department

More information

All text in Red Italics is sample verbiage or instructions and may to be removed from the final document.

All text in Red Italics is sample verbiage or instructions and may to be removed from the final document. ESA / IGA Schedules Project Documents include the following Schedules which are incorporated herein and made a part of the IGA and ESA when approved by the ISSUER and ESCO: Schedule A Schedule B Schedule

More information

Default Aversion Services

Default Aversion Services September 22, 2014 ITN Number: 2014 12 ITN Services: The State College of Florida is soliciting proposals from qualified vendors to provide Student Loan Default Prevention Management Services. This contract

More information

REQUEST FOR PROPOSALS FOR INVESTMENT ADVISORY SERVICES

REQUEST FOR PROPOSALS FOR INVESTMENT ADVISORY SERVICES REQUEST FOR PROPOSALS FOR INVESTMENT ADVISORY SERVICES CONTACT: Michelle Durgy, michelle.durgy@sfgov.org, (415) 554-5210 Background San Francisco is the fourth largest city in California and serves as

More information

CITY & COUNTY OF SAN FRANCISCO CONTRACT MONITORING DIVISION CMD ATTACHMENT 8A

CITY & COUNTY OF SAN FRANCISCO CONTRACT MONITORING DIVISION CMD ATTACHMENT 8A CITY & COUNTY OF SAN FRANCISCO Requirements for SFPUC Regional Architecture, Engineering, & Contracts For Contracts covered under SEC.14B.21 that are advertised on or after February 1, 2018 PART I. GENERAL

More information

Answer: FABF s preference is to invest in the Global REIT strategy via a separately-managed account. Commingled funds will be considered secondarily.

Answer: FABF s preference is to invest in the Global REIT strategy via a separately-managed account. Commingled funds will be considered secondarily. Responses to questions for the Firemen s Annuity & Benefit Fund of Chicago Search for Investment Advisor (SIA): Global REIT Manager 1. How strict is the minimum requirement which states that "The Firemen's

More information

ADDENDUM #1 & ACKNOWLEDGEMENT. 1 Questions & Answers Questions & Answers have been attached to this addendum.

ADDENDUM #1 & ACKNOWLEDGEMENT. 1 Questions & Answers Questions & Answers have been attached to this addendum. RFP 19-15 NJ integrated Eligibility System Independent Verification & Validation Addendum #1 & Acknowledgement ADDENDUM #1 & ACKNOWLEDGEMENT To: All Vendors Date: October 16, 2018 Changes to Specifications

More information

RE: Request for Proposals (RFP) Consultant Services for Public Transit Board Training

RE: Request for Proposals (RFP) Consultant Services for Public Transit Board Training State of Vermont Agency of Transportation Contract Administration Finance & Administration One National Life Drive [phone] 802-828-2641 Montpelier VT 05633-5001 [fax] 802-828-5545 http://vtrans.vermont.gov/

More information

STATE OF LOUISIANA DIVISION OF ADMINISTRATION THE OFFICE OF GROUP BENEFITS (OGB) REQUEST FOR PROPOSALS (RFP) FOR

STATE OF LOUISIANA DIVISION OF ADMINISTRATION THE OFFICE OF GROUP BENEFITS (OGB) REQUEST FOR PROPOSALS (RFP) FOR STATE OF LOUISIANA DIVISION OF ADMINISTRATION THE OFFICE OF GROUP BENEFITS (OGB) REQUEST FOR PROPOSALS (RFP) FOR PHARMACEUTICAL BUSINESS MANAGER (PBM) AUDIT SERVICES Issued December 10, 2003 Division of

More information

CITY & COUNTY OF SAN FRANCISCO CONTRACT MONITORING DIVISION. CMD ATTACHMENT 1 Requirements for Construction Contracts

CITY & COUNTY OF SAN FRANCISCO CONTRACT MONITORING DIVISION. CMD ATTACHMENT 1 Requirements for Construction Contracts CITY & COUNTY OF SAN FRANCISCO Requirements for For Contracts $300,000 & over that are Advertised on or after August 1, 2016 PART I. GENERAL 1.01 SAN FRANCISCO ADMINISTRATIVE CODE CHAPTERS 12B AND 14B

More information

Notice of Request for Proposals For Guaranteed Energy Savings Performance Contract

Notice of Request for Proposals For Guaranteed Energy Savings Performance Contract Notice of Request for Proposals For Guaranteed Energy Savings Performance Contract BID: Q15-55 TO: ALL PROSPECTIVE BIDDERS FROM: ZAKIA ALAM, PURCHASING & CONTRACTS MANAGER SUBJECT: REQUEST FOR PROPOSALS:

More information

Gas Heating Application - July 1, 2015 through June,

Gas Heating Application - July 1, 2015 through June, Gas Heating Application - July 1, 2015 through June, 30 2016 Customer Information Company Name (as listed on utility bill) Gas Utility Serving Applicant Doing Business as (if applicable) Gas Account Number*

More information

COLLATERAL VERIFICATION REVIEWS FREQUENTLY ASKED QUESTIONS

COLLATERAL VERIFICATION REVIEWS FREQUENTLY ASKED QUESTIONS NEW OR UPDATED ITEMS FOR 2013 Private Transfer Covenants The Federal Housing Finance Agency (FHFA) issued a final rule effective July 16, 2012, that prohibits the acceptance of loan collateral encumbered

More information

City of Coolidge 130 W. Central Avenue Coolidge, Arizona (520) TDD: (520) / Fax: (520)

City of Coolidge 130 W. Central Avenue Coolidge, Arizona (520) TDD: (520) / Fax: (520) REQUEST FOR PROPOSALS Energy Performance Contracting Services INTRODUCTION The City of Coolidge will accept competitive sealed proposals for energy performance contracting services at the address or physical

More information

REQUEST FOR PROPOSAL. Architectural and Space Planning Services

REQUEST FOR PROPOSAL. Architectural and Space Planning Services COLORADO HOUSING AND FINANCE AUTHORITY REQUEST FOR PROPOSAL (RFP) COLORADO HOUSING AND FINANCE AUTHORITY 1981 BLAKE STREET DENVER, CO 80202 REQUEST FOR PROPOSAL Architectural and Space Planning Services

More information

Bradley Lake Hydropower Project Operator

Bradley Lake Hydropower Project Operator ADDENDUM ONE Request for Proposal 18043 Bradley Lake Hydropower Project Operator March 27, 2018 EMAIL TO: All RFP recipients on record. The Request for Proposal (RFP) is hereby clarified or changed as

More information

Request for Proposal (RFP) for. Implementation Contractor. for. Ameren Missouri Demand Side Management Program Implementation Cycle III

Request for Proposal (RFP) for. Implementation Contractor. for. Ameren Missouri Demand Side Management Program Implementation Cycle III Request for Proposal (RFP) for Implementation Contractor for Ameren Missouri Demand Side Management Program Implementation Cycle III Issued: July 31, 2017 This document and its supporting materials is

More information

Fayette County Youth Soccer League. Request for Proposal

Fayette County Youth Soccer League. Request for Proposal Fayette County Youth Soccer League Request for Proposal Accounting Services February 15, 2011 Page 1 of 9 TABLE OF CONTENTS 1.0 BACKGROUND...3 1.1 Overview...3 1.2 Terms and Conditions...3 2.0 REQUEST

More information

Group Life Insurance Request for Proposals RFP# Questions and Answers Posted 2/28/2017. Please see Appendix Q. Please see Appendix P.

Group Life Insurance Request for Proposals RFP# Questions and Answers Posted 2/28/2017. Please see Appendix Q. Please see Appendix P. Group Life Insurance Request for Proposals RFP# 6100041420 Questions and Answers Posted 2/28/2017 Question 1. Can you please provide 5 years of experience/claim history? 2. Can you please provide a census?

More information

Collection Services Request for Proposal # 14/15-07 Questions and Answers

Collection Services Request for Proposal # 14/15-07 Questions and Answers Collection Services Request for Proposal # 14/15-07 Questions and Answers Question 1: I reviewed the above referenced RFP and was curious if Florida Department of Revenue would consider selling these accounts

More information

The contract period will run from January 1, 2018 through December 31, 2020.

The contract period will run from January 1, 2018 through December 31, 2020. Request for Proposal RFP for ISO-NE Consulting Support RFP Release Date: 10/25/2017 Bidder Questions Due: 11/8/2017 Answers Posted: 11/15/2017 Proposals Due: 11/29/2017 Summary The Vermont Energy Investment

More information

Con Edison Performance-Based Gas Demand Response Pilot Guidelines

Con Edison Performance-Based Gas Demand Response Pilot Guidelines Con Edison Performance-Based Gas Demand Response Pilot Guidelines 2018/19 Capability Period Last updated: 09/10/2018 Performance-Based Gas DR Pilot Guidelines Consolidated Edison Contents Acronyms and

More information

Pre-approval prior to installation is required.

Pre-approval prior to installation is required. Customer Information Company Name (as listed on utility bill) Doing Business as (if applicable) Anticipation Installation Date: (cannot begin prior to approval by Program Manager Facility Address NJ Electric

More information

RFP # FACILITIES MANAGEMENT SERVICES

RFP # FACILITIES MANAGEMENT SERVICES RFP # 991-13-004 FACILITIES MANAGEMENT SERVICES ISSUE DATE: MARCH 22, 2013 1 TABLE OF CONTENTS I. INTRODUCTION A. PURPOSE OF THIS REQUEST FOR PROPOSALS... 4 B. VISION... 4 C. SCOPE OF WORK... 4 D. SCOPE

More information

RFA ENROLLMENT ASSISTANCE PROGRAM (EAP) SERVICES FOR THE HEALTHCHOICES PROGRAM Questions & Answers

RFA ENROLLMENT ASSISTANCE PROGRAM (EAP) SERVICES FOR THE HEALTHCHOICES PROGRAM Questions & Answers 1 2 3 4 5 General What are the top challenges experienced by DHS that the Department would like to solve with this procurement? The RFA describes the general and specific objectives of this procurement

More information

Request for Proposal for Actuarial Audit Services. March 20, 2017

Request for Proposal for Actuarial Audit Services. March 20, 2017 Request for Proposal for Actuarial Audit Services March 20, 2017 Proposal Submission Deadline Friday, April 21, 2017 I. INTRODUCTION Sacramento County Employees Retirement System (SCERS) is a public retirement

More information

INVITATION TO NEGOTIATE (ITN) FOR INFORMATION TECHNOLOGY OPERATIONS AND MAINTENANCE SERVICES ITN NO: DMS-17/ THE STATE OF FLORIDA

INVITATION TO NEGOTIATE (ITN) FOR INFORMATION TECHNOLOGY OPERATIONS AND MAINTENANCE SERVICES ITN NO: DMS-17/ THE STATE OF FLORIDA 4050 Esplanade Way Tallahassee, Florida 32399-0950 Tel: 850.488.2786 Fax: 850. 922.6149 Rick Scott, Governor Erin Rock, Secretary INVITATION TO NEGOTIATE (ITN) FOR INFORMATION TECHNOLOGY OPERATIONS AND

More information

Cleveland County REQUEST FOR PROPOSAL FOR GUARANTEED ENERGY SAVINGS PERFORMANCE CONTRACTING 8/29/2016 RFP # 1

Cleveland County REQUEST FOR PROPOSAL FOR GUARANTEED ENERGY SAVINGS PERFORMANCE CONTRACTING 8/29/2016 RFP # 1 Cleveland County REQUEST FOR PROPOSAL FOR GUARANTEED ENERGY SAVINGS PERFORMANCE CONTRACTING 8/29/2016 RFP # 1 Rev 7/15/2016 Cleveland County RFP #1 Page 0 REQUEST FOR PROPOSALS FOR Cleveland County STATE

More information

RFP # Certified Public Accounting Services. Addendum #1 Date issued and released, August 7, 2018

RFP # Certified Public Accounting Services. Addendum #1 Date issued and released, August 7, 2018 RFP #18-008 Certified Public Accounting Services Addendum #1 Date issued and released, August 7, 2018 Correction to RFP #18-008: Please note that Oakland Affordable Housing Preservation Initiatives is

More information

Online Testing System & Examinee Scoring System

Online Testing System & Examinee Scoring System 2018 Online Testing System & Examinee Scoring System TECHNOLOGY SOLUTIONS Ramsay Corporation uses technology solutions to simplify the testing and reporting process. This document provides an overview

More information

NEW MEXICO MEDICAL INSURANCE POOL REQUEST FOR PROPOSALS FOR AN EXECUTIVE DIRECTOR

NEW MEXICO MEDICAL INSURANCE POOL REQUEST FOR PROPOSALS FOR AN EXECUTIVE DIRECTOR NEW MEXICO MEDICAL INSURANCE POOL REQUEST FOR PROPOSALS FOR AN EXECUTIVE DIRECTOR I. INTRODUCTION A. PURPOSE OF THIS REQUEST FOR PROPOSALS The New Mexico Medical Insurance Pool ( NMMIP ) seeks an Executive

More information

Missouri Housing Development Commission

Missouri Housing Development Commission Missouri Housing Development Commission REQUEST FOR PROPOSALS FOR INSURANCE BROKER SERVICES RESPONSE DEADLINE: Five (5) hard copies and one (1) electronic copy by email Due by Wednesday, February 11, 2015

More information

In this chapter: Budgets and Planning Tools. Configure a budget. Report on budget versus actual figures. Export budgets.

In this chapter: Budgets and Planning Tools. Configure a budget. Report on budget versus actual figures. Export budgets. Budgets and Planning Tools In this chapter: Configure a budget Report on budget versus actual figures Export budgets Project cash flow Chapter 23 479 Tuesday, September 18, 2007 4:38:14 PM 480 P A R T

More information

Request for Proposals. For Verification Services for the.bank and.insurance Generic Top-Level Domains. Public Document- Issue Date: 22 April 2014

Request for Proposals. For Verification Services for the.bank and.insurance Generic Top-Level Domains. Public Document- Issue Date: 22 April 2014 Request for Proposals For Verification Services for the.bank and.insurance Generic Top-Level Domains Public Document- Issue Date: 22 April 2014 Deadline for Submissions: 28 May 2014 / 21:00 UTC Table of

More information

REQUEST FOR PROPOSAL (RFP) FOR SWAP PORTFOLIO MONITOR SERVICES AND SWAP ADVISORY CONSULTANT SERVICES FOR THE DEPARTMENT OF TREASURY

REQUEST FOR PROPOSAL (RFP) FOR SWAP PORTFOLIO MONITOR SERVICES AND SWAP ADVISORY CONSULTANT SERVICES FOR THE DEPARTMENT OF TREASURY REQUEST FOR PROPOSAL (RFP) FOR SWAP PORTFOLIO MONITOR SERVICES AND SWAP ADVISORY CONSULTANT SERVICES FOR THE DEPARTMENT OF TREASURY Date Issued: January 25, 2011 Responses Due by: 4 P.M. Eastern Standard

More information

INSTALLER QUICK START GUIDE

INSTALLER QUICK START GUIDE INSTALLER QUICK START GUIDE Thank you for participating in the Mass Solar Loan Program. This information packet includes: Step-by-step instructions for participating in the program Page 2 Mass Solar Loan

More information

ADDENDUM #1 RFQ # , Request for Qualifications for Architectural Services

ADDENDUM #1 RFQ # , Request for Qualifications for Architectural Services ADDENDUM #1 RFQ #1718-01, Request for Qualifications for Architectural Services This Addendum forms a part of the Request for Qualifications (RFQ) and modifies the original RFQ. Consultant must acknowledge

More information

Arkansas Health Insurance Marketplace 1501 North University Avenue, Suite 970 Little Rock, AR REQUEST FOR PROPOSAL

Arkansas Health Insurance Marketplace 1501 North University Avenue, Suite 970 Little Rock, AR REQUEST FOR PROPOSAL Arkansas Health Insurance Marketplace 1501 North University Avenue, Suite 970 Little Rock, AR 72207-5186 RFP Number: 01-2014 Service: Outside Legal Counsel Date: REQUEST FOR PROPOSAL Buyer: Amanda Spicer

More information

INQUIRIES AND RESPONSES

INQUIRIES AND RESPONSES March 27, 2015 Reference Request for Proposals #800100-03132015 to provide Administrative Services Only (ASO) for Self Funded Medical Plans for the State of Louisiana, Office of Group Benefits which is

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS SUPERIOR COURT OF CALIFORNIA COUNTY OF STANISLAUS REGARDING: Microsoft Excel Training Courses PROPOSALS DUE: May 26, 2015 NO LATER THAN 4:00 P.M. PACIFIC TIME 1 rev 12/16/13 1.0 BACKGROUND

More information

FORMAL INVITATION FOR BEST VALUE BID (BVB) THREE YEAR CONTRACT FOR SECURITY SERVICES ADDENDUM 4

FORMAL INVITATION FOR BEST VALUE BID (BVB) THREE YEAR CONTRACT FOR SECURITY SERVICES ADDENDUM 4 SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT Issued By: Clifford Gorman Date Issued: April 28, 2016 BID NO.: 16-8067 FORMAL INVITATION FOR BEST VALUE BID (BVB) THREE YEAR CONTRACT FOR SECURITY SERVICES

More information

Wilkes Community College

Wilkes Community College Wilkes Community College REQUEST FOR PROPOSAL FOR GUARANTEED ENERGY SAVINGS PERFORMANCE CONTRACTING April 1, 2016 RFP #_2016-010_ Performance Contract RFP 4/01/2016 Page 1 REQUEST FOR PROPOSALS FOR Wilkes

More information

Notice Type: Request for Proposal

Notice Type: Request for Proposal Notice Type: Request for Proposal Short Title: Efficiency Vermont Residential & Business Customer Satisfaction surveys Introduction Posted date: March 18, 2019 Questions due: March 27, 2019 Answers Posted:

More information

Rolling Plains Management Corporation 118 North First Street P.O. Box 490 Crowell, Texas REQUEST FOR PROPOSALS FOR

Rolling Plains Management Corporation 118 North First Street P.O. Box 490 Crowell, Texas REQUEST FOR PROPOSALS FOR Rolling Plains Management Corporation 118 North First Street P.O. Box 490 Crowell, Texas 79227 REQUEST FOR PROPOSALS FOR CONTRACTORS FOR THE AMY YOUNG BARRIER REMOVAL PROGRAM July 30, 2018 1 TABLE OF CONTENTS

More information

WageWorks FAQs - May 16 Version

WageWorks FAQs - May 16 Version - May 16 Version Associate Experience 1. Can I use a template reimbursement Services Agreement (RSA) / Contract like the sample in the Associate Package for the Employers who are renewing onto the take

More information

Medicaid Non-Emergency Transportation Request for Proposals. Responses to Questions Received by the March 11 Deadline (Posted March 17, 2011)

Medicaid Non-Emergency Transportation Request for Proposals. Responses to Questions Received by the March 11 Deadline (Posted March 17, 2011) Medicaid Non-Emergency Transportation Request for Proposals Responses to Questions Received by the March 11 Deadline (Posted March 17, 2011) 1. Could the MPO please provide a link to (or an electronic

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR THE FIRST 5 LA FACILITY RENOVATION PROJECT REQUEST FOR PROPOSALS (RFP)

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR THE FIRST 5 LA FACILITY RENOVATION PROJECT REQUEST FOR PROPOSALS (RFP) PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR THE FIRST 5 LA FACILITY RENOVATION PROJECT REQUEST FOR PROPOSALS (RFP) Los Angeles County Children and Families First Proposition 10 Commission (aka First

More information

New Homes Baseline and Market Characterization Evaluation Question & Answer July 19, 2016

New Homes Baseline and Market Characterization Evaluation Question & Answer July 19, 2016 New Homes Baseline and Market Characterization Evaluation Question & Answer July 19, 2016 1. Could you clarify the expected completion date for the project? Section 2.1 of the RFP lists August 31, 2017

More information

Bond Collateral Assistance Fund RFP. Information Session January 25, 2017

Bond Collateral Assistance Fund RFP. Information Session January 25, 2017 Bond Collateral Assistance Fund RFP Information Session January 25, 2017 Agenda 1. RFP Background 2. Program Goals & Target Audience 3. Challenges Accessing Surety Bonding 4. Components of Program 5. Consultant

More information

Request for Qualifications RFQ Continuing Services Contracts for Professional Engineering Services

Request for Qualifications RFQ Continuing Services Contracts for Professional Engineering Services Request for Qualifications RFQ 19-001 Continuing Services Contracts for Professional Engineering Services City of Winter Garden 300 West Plant Street Winter Garden, FL 34787 (407) 656-4111 LEGAL ADVERTISEMENT

More information

Multifamily Energy Efficiency Program

Multifamily Energy Efficiency Program Multifamily Energy Efficiency Program Rebate Reservation Request To reserve incentives from the PNM Multifamily Energy Efficiency Program, please complete this form and return to multifamily@pnm.com or

More information

Best Practices for Multiple Vendor 403(b) Plans. Form 5500 Aggregation. Version: F Date: September 13, 2010

Best Practices for Multiple Vendor 403(b) Plans. Form 5500 Aggregation. Version: F Date: September 13, 2010 Best Practices for Multiple Vendor 403(b) Plans Form 5500 Aggregation Version: F5500-2.0 Date: September 13, 2010 Best Practices for Multiple Vendor 403(b) Plans Form 5500 Aggregation (Version: F5500-2.0)

More information

THE STATE OF FLORIDA, DEPARTMENT OF MANAGEMENT SERVICES, DIVISION OF STATE GROUP INSURANCE REQUEST FOR PROPOSAL GROUP VISION INSURANCE BENEFITS

THE STATE OF FLORIDA, DEPARTMENT OF MANAGEMENT SERVICES, DIVISION OF STATE GROUP INSURANCE REQUEST FOR PROPOSAL GROUP VISION INSURANCE BENEFITS THE STATE OF FLORIDA, DEPARTMENT OF MANAGEMENT SERVICES, DIVISION OF STATE GROUP INSURANCE REQUEST FOR PROPOSAL GROUP VISION INSURANCE BENEFITS RFP : DMS 13/14-030 ADDENDUM 1 The Department hereby formally

More information

OFFICE OF PROCUREMENT AND CONTRACTING 301 Largo Road, Largo Maryland

OFFICE OF PROCUREMENT AND CONTRACTING 301 Largo Road, Largo Maryland OFFICE OF PROCUREMENT AND CONTRACTING 301 Largo Road, Largo Maryland 20774-2199 REQUEST FOR PROPOSAL #18-01 NEW HEALTH CARE PLAN MEDICAL, PRESCRIPTION DRUG, DENTAL & VISION Addendum No. 2 Issued: Monday,

More information

Request for Proposals (RFP) Addendum #2

Request for Proposals (RFP) Addendum #2 Request for Proposals (RFP) Addendum #2 Banking & Credit Card Processing Services RFI Schedule CIS 1212 Court St. NE Salem, OR 97301 (503) 763-3800 Issuance of RFP: November 13, 2018 Submission of Questions

More information

Contracts & Grants ESTABLISHING THE CONTRACT OR GRANT SYSTEM ACCESS & USER GROUP SECURITY ONLINE FINANCIAL REPORTS

Contracts & Grants ESTABLISHING THE CONTRACT OR GRANT SYSTEM ACCESS & USER GROUP SECURITY ONLINE FINANCIAL REPORTS Contracts & Grants ESTABLISHING THE CONTRACT OR GRANT SYSTEM ACCESS & USER GROUP SECURITY ONLINE FINANCIAL REPORTS GUIDELINES FOR ADMINISTERING THE AWARD CONTRACT/GRANT REPORTING TOOLS FOR ADMINISTERING

More information

STATE OF NEW YORK PUBLIC SERVICE COMMISSION

STATE OF NEW YORK PUBLIC SERVICE COMMISSION STATE OF NEW YORK PUBLIC SERVICE COMMISSION At a session of the Public Service Commission held in the City of COMMISSIONERS PRESENT: CASE 16-M-0015 - Petition of Municipal Electric and Gas Alliance, Inc.

More information

PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY. Invitation No: RP Date : Addendum No: 1 Title: Flexible Spending Account Administrator

PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY. Invitation No: RP Date : Addendum No: 1 Title: Flexible Spending Account Administrator PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY Invitation No: RP-067-17 Date : Addendum No: 1 Title: 4/4/2017 The following shall clarify and/or modify the original RFP documents issued by the University of

More information

Request for Qualifications and Proposals for Single Family Market Rate Program Administrator

Request for Qualifications and Proposals for Single Family Market Rate Program Administrator Request for Qualifications and Proposals for Single Family Market Rate Program Administrator MISSOURI HOUSING DEVELOPMENT COMMISSION RESPONSE DEADLINE: Wednesday, October 11, 2017 Noon Central Time Submit

More information

BPA Energy Efficiency Option 1 Custom Project Calculator Instructions

BPA Energy Efficiency Option 1 Custom Project Calculator Instructions B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA Energy Efficiency Option 1 Custom Project Calculator Instructions Revised 12/3/2012 Table of Contents Purpose of Option 1 Custom Project Calculator

More information

FAYETTE COUNTY SCHOOL DISTRICT REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT AT RISK SERVICES

FAYETTE COUNTY SCHOOL DISTRICT REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT AT RISK SERVICES FAYETTE COUNTY SCHOOL DISTRICT REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT AT RISK SERVICES The Fayette County School District (FCSD) desires to retain the services of a professional Construction

More information

Request for Proposals RFP#8-012 FLEET MANAGEMENT SERVICES

Request for Proposals RFP#8-012 FLEET MANAGEMENT SERVICES Request for Proposals RFP#8-012 FLEET MANAGEMENT SERVICES Prepared by: Ken Crawford DUE: April 17, 2018 2:00 PM Mountain Time Ogden City School District Purchasing Department Room #210 1950 Monroe Blvd.

More information

PENSION ADMINISTRATION SOLUTION REQUEST FOR INFORMATION

PENSION ADMINISTRATION SOLUTION REQUEST FOR INFORMATION Page 1 of 34 PENSION ADMINISTRATION SOLUTION REQUEST FOR INFORMATION Notice to Prospective Responders February 27, 2013 You are invited to review and respond to the California State Teachers Retirement

More information

ADMINISTRATIVE ANALYST (Class Code 1590) TASK LIST

ADMINISTRATIVE ANALYST (Class Code 1590) TASK LIST ADMINISTRATIVE ANALYST (Class Code 1590) TASK LIST A. General Administration 1. Writes narrative material such as letters, memos, and reports on various personnel, budgetary, contractual, grant, and policy

More information

BID PROPOSAL. PROPOSAL OF, a corporation, a partnership consisting of. an individual doing business as

BID PROPOSAL. PROPOSAL OF, a corporation, a partnership consisting of. an individual doing business as Job No. 07-7003 Water Transmission Main Rogers Ranch to I.H. 10 Project Solicitation No. B-10-050-DD BID PROPOSAL PROPOSAL OF, a corporation, a partnership consisting of an individual doing business as

More information

RSU # 78 RFP # 1 BASELINE ASSESSMENT OF FACILITY

RSU # 78 RFP # 1 BASELINE ASSESSMENT OF FACILITY RSU # 78 RFP # 1 BASELINE ASSESSMENT OF FACILITY RFP Coordinator: Brian Foster, Superintendent Tel: (207) 864-3312 e-mail: bfoster@rangeleyschool.org Fax: _(207) 864-2451 From the time this RFP is issued

More information

Ohio Public Employees Retirement System. Request for Proposal

Ohio Public Employees Retirement System. Request for Proposal Ohio Public Employees Retirement System For: IT Contract Services Senior Cobol Programmer Date: 4/7/14 Project Name: Member Systems Support 277 East Town Street Columbus, Ohio 43215 1-800-222-PERS (7377)

More information

MISSOURI HOUSING DEVELOPMENT COMMISSION

MISSOURI HOUSING DEVELOPMENT COMMISSION MISSOURI HOUSING DEVELOPMENT COMMISSION Request for Qualifications and Proposals for Underwriters and Selling Group Members Released: January 7, 2016 Responses Due: February 16, 2016 Noon Central Time

More information

Florida Department of Children and Families

Florida Department of Children and Families 2. Provide support to the ACCESS Florida System Replacement Project where necessary and as directed throughout the duration of the contract. This Statement of Purpose provides only a summary of the Department

More information

MEMORANDUM. May 13, 2016

MEMORANDUM. May 13, 2016 Agenda Item #2.F May 17,2016 Action MEMORANDUM May 13, 2016 TO: County Council FROM:~\ieslie Rubin, Senior Legislative Analyst and Audit Contract Administrator 2.@:ephanie Bryant, Legislative Analyst Office

More information

SOLICITATION/ADVERTISEMENT

SOLICITATION/ADVERTISEMENT SOLICITATION/ADVERTISEMENT City of Homewood, Alabama will receive responses to a Request for Proposals for the selection of an Energy Services Company (ESCO). City of Homewood, Alabama intends to select

More information

Quick Call for Proposals. State of Minnesota. Minnesota Department of Transportation. Quick Call for Proposals ( Quick Call )

Quick Call for Proposals. State of Minnesota. Minnesota Department of Transportation. Quick Call for Proposals ( Quick Call ) State of Minnesota Minnesota Department of Transportation ( Quick Call ) Fiber Optic Training Course for Intelligent Traffic Systems March 15, 2019 Proposals must be received no later than 11:00 AM, Central

More information

Bidder s Conference: Philadelphia Works Board Room September 26, :00 PM to 3:00 PM

Bidder s Conference: Philadelphia Works Board Room September 26, :00 PM to 3:00 PM Request for Proposals Vocational Skills Training for Fiscal Year 2019 Bidder s Conference: Philadelphia Works Board Room September 26, 2018 1:00 PM to 3:00 PM 20180701VSTRFPELM Introduction Philadelphia

More information

Frequently Asked Questions on Exchanges, Market Reforms and Medicaid

Frequently Asked Questions on Exchanges, Market Reforms and Medicaid DEPARTMENT OF HEALTH & HUMAN SERVICES Centers for Medicare & Medicaid Services 7500 Security Boulevard, Mail Stop C2-21-15 Baltimore, Maryland 21244-1850 Date: December 10, 2012 Subject: Frequently Asked

More information

Follow-Up on VFM Section 3.05, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW

Follow-Up on VFM Section 3.05, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 1 Section 1.05 Ministry of Infrastructure (formerly the Ministry of Economic Development, Employment and Infrastructure) Infrastructure Ontario Alternative Financing and Procurement Follow-Up on

More information