CALIFORNIA CLEAN ENERGY JOBS ACT LAUSD PROPOSITION 39 ENERGY EFFICIENCY PROGRAM

Size: px
Start display at page:

Download "CALIFORNIA CLEAN ENERGY JOBS ACT LAUSD PROPOSITION 39 ENERGY EFFICIENCY PROGRAM"

Transcription

1 CALIFORNIA CLEAN ENERGY JOBS ACT LAUSD PROPOSITION 39 ENERGY EFFICIENCY PROGRAM Presentation 10/30/15 1

2 PROGRAM OVERVIEW 1. Background General Allocation Amounts Annual Funding Release 2. Project Types 3. Program Schedule 4. Flow Chart & Selection Criteria 5. Contracting Approach 6. Program Timeline & Cost Loading 7. Budget Summary 8. Project Cost Summary By School (Ph. 1 & 2) By Energy Measure (Ph.1 & 2) 9. Post Retrofit Estimates (Ph.1 & 2) 10. Lessons Learned 11. Program Impact 12. College and Career Readiness 2

3 BACKGROUND - GENERAL Approved by the Voters of California on November 6, Five (5) year program, starting from Fiscal Year (FY) Purpose is to create jobs through energy efficiency and clean energy projects Allocates grant funds to Local Educational Agencies (LEAs). Depending on tax revenues, up to $550 Million is available annually for allocation to all LEAs. 3

4 BACKGROUND ALLOCATION AMOUNTS Allocation amounts will be announced by the California Department of Education (CDE) each November. Annual allocations are based on District s prior year data of: Average Daily Attendance (ADA). Number of students eligible for Free and Reduced-Priced Meals (FRPM). The amount of tax revenue collected. LAUSD was allocated $26.2 Million & $22.0 Million for FY & FY 14-15, respectively. Assuming a $26.2 Million annual allocation, LAUSD can receive approximately $130 Million over the life of the 5 year program. 4

5 BACKGROUND ANNUAL FUNDING RELEASE Annual Expenditure Plan is submitted to the California Energy Commission (CEC) for review and approval for funds to be released. Within the Expenditure Plan, funds are requested on a school-by-school basis for Project costs related to the identified Energy Conservation Measures (ECMs). Eligible Projects must meet the Savings to Investment Ratio (SIR) of Upon approval, requested funds will be drawn down against the Allocation and released to the District. 5

6 PROJECT TYPES District focus is on Energy Efficiency and Retro-Commissioning projects that reduce energy use in existing building systems. Lighting HVAC Controls Plumbing Interior fixture - Retrofit or Replacement, w/ Dimmable Ballasts Exterior fixture - Retrofit or Replacement Rewire interior lights for Daylight control and dimming Air Handler & Package Units - Repair, Modify or Replace Pumps, Economizers and VFDs - Repair, Replace or New Adjust temperature set points Revise equipment operating schedules Energy Management Systems - HVAC Chiller control upgrades Occupancy & Daylight sensor Repair, Replace or New Lighting controls interior & exterior lighting Domestic Water Heaters - Repair, Modify or Replace Consider Condensing or Tankless Water Heaters Adjust temperature set points 6

7 Phased Program Schedule Fiscal Yr Ph. 1 FY /13 5/17 22Schools Schools Nov.30, CDE Allocation Ph. 2 FY /14 Nov.30, CDE Allocation 12/17 11 Schools Ph. 3 FY /15 Nov.30, CDE Allocation 12/18 16 Schools Ph. 4 FY /16 Nov.30, CDE Allocation 12/19 Ph. 5 FY October /17 Nov.30, CDE Allocation 12/20 Typical Tasks & Milestones per Phase 7

8 Flow Chart & Selection Criteria PRIORITY BASE LIST SCHOOL DISTRIBUTION PER PHASE SCHOOL SELECTION CRITERIA INVESTMENT GRADE AUDIT Reduce Electric & Gas Bills Highest Electric Bill Rank Schools on Highest Electrical Cost School Priority Base List Determine number of schools for Phase based on Allocation amount. Select next School on the list where the previous Phase ended. New School < 5 Yrs. Old? No. Major HVAC, Lighting Or Modernization in Planning, Design or Construction? No. Impacts of Minor On-Going Construction? No. Impacts on Major School Activities / Summer School? No. Recently Installed Solar System? No. Selected School Yes. Yes. Yes. Yes. Yes. Move to next school with highest electric bill. No. Have all Schools been Selected for Phase? Yes. Issue Task Order for Investment Grade Audits 8

9 CONTRACTING APPROACH Energy Services Companies (ESCOs) Current ESCOs were pre-qualified through an RFP/Best Value process. Task Orders Perform Investment Grade Audits Identify Energy Conservation Measures (ECMs) for District Selection Ensure Projects meet Savings to Investment Ratio of 1.05 Energy Savings Performance Contract Design and Construction of selected ECMs Perform Measure & Verification for California Energy Commission reporting Provide a 2 year Savings Guarantee California Conservation Corps (CCC) & Los Angeles Conservation Corps (LACC) Recognized Proposition 39 Resources Memorandum of Understanding Provide no-cost and low-cost energy audits, respectively Identify ECMs on a Master Plan level for non-selected schools Assist District with Workforce Development and Student Internship 9

10 PROGRAM TIMELINE J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M Phase 1 Design C B PC Construction Measure & Verification Phase 2 Select IGA B C Design PC Construction Measure & Verification Phase 3 Select IGA B Design PC Construction Measure & Verification Phase 4 Select IGA B Design PC Construction Measure & Verification Phase 5 Select IGA B Design PC Construction Measure & Verification Affiliated Charter Schools IGA Select = Site Selection B = Board Approval C = Contract Review PC = Pre Construction $140,000,000 PROP. 39 ALLOCATION AND PROGRAM COST LOADING $126,329,427 $120,000,000 $125,929,745 $126,329,427 $100,000,000 $100,329,427 ALLOCATION AMOUNT $96,665,808 $80,000,000 $74,329,427 $60,000,000 $40,000,000 $48,329,427 $64,380,611 ESTIMATED COSTS $20,000,000 $26,280,638 $23,210,820 $0 J F M A M J 14 J A S O N D J F M A M $3,371,138 J 15 $2,016,355 J A S O N D ACTUAL COSTS J F M A M J 16 J A S O N D J F M A M J 17 J A S O N D J F M A M Estimated Costs Prop 39 Allocation Actual Costs J 18 J A S O N D J F M A M J 19 J A S O N D J F M A M J 20 J A S O N D J F M A M J 21 10

11 BUDGET SUMMARY CEC ALLOCATION PROJECTED PROGRAM BUDGET Fiscal Year Amount Category Amount Project Funds FY14* $26,280,638 Investment Grade Audits $4,750,000 Project Funds FY15* $22,048,789 Design $4,668,740 Project Funds FY16** $26,000,000 Construction $98,366,030 Project Funds FY17** $26,000,000 Construction Soft Costs (District) $9,044,657 Project Funds FY18** $26,000,000 Energy Mgmt. Staff $7,000,000 1 Total: $126,329,427 M&O Training (up to 2%) $2,500,000 *Actual Total: $126,329,427 **Projected Prop 39 Projected Program Budget Construction 78% Design 4% Investment Grade Audits 4% Construction Soft Costs (District) 7% Energy Mgmt. Staff 5% M&O Training 2% Note 1: Not including Affiliated Charter Schools $15M over 5 years) 11

12 PROJECT COST SUMMARY - BY SCHOOL PH. 1 - EXPENDITURE PLAN SUBMITTAL for FY (CEC Approved) School Cost Per School Estimated Annual Energy Cost Savings SIR Status Marshall HS $1,836,073 $105, Construction Santee EC $2,859,789 $217, Construction Project Cost - Total: $4,695,862 $323, PH. 2 - EXPENDITURE PLAN SUBMITTAL for FY (CEC Approved) School Cost Per School Estimated Annual Energy Cost Savings SIR Status Audubon MS $3,131,773 $127, Design Bell HS $1,974,290 $95, Design Bernstein HS $2,015,955 $123, Design Cochran MS $2,298,063 $90, Design Contreras LC $1,600,105 $129, Design Kennedy HS $1,354,518 $94, Design King Drew HS $2,035,262 $126, Design Lincoln HS $1,706,845 $88, Design Panorama HS $767,946 $43, Design Roybal LC $2,100,552 $145, Design Van Nuys HS $1,605,662 $80, Design CEC = California Energy Commission SIR = Savings to Investment Ratio Project Cost - Total: $20,590,971 $1,144, Grand Total: $25,286,833 $1,468,

13 Ph. 1 & 2 - PROJECT COST SUMMARY - BY ENERGY MEASURE CATEGORY Energy Measure Category* Cost Per Category Cost Distribution Estimated Annual Energy Cost Savings Savings Distribution Estimated Utility Rebate Rebate Distribution Lighting $12,401, % $764, % $428, % HVAC $4,482, % $177, % $62, % HVAC Controls $2,579, % $246, % $50, % High Efficiency Transformers $2,470, % $135, % $95, % Lighting Controls $1,811, % $74, % $49, % Pumps, Motors,Drives $1,411, % $68, % $61, % Domestic Hot Water Heaters $130, % $ % $25, % *As Established by the CEC for Prop 39 Grand Total: $25,286, % $1,468, % $774, % 13

14 PH. 1 & 2 - POST RETROFIT ESTIMATES School Baseline kwh/yr Electric Gas Electric Costs Gas Costs Post Retrofit kwh/yr Baseline Therms/yr Post Retrofit Therms/yr Baseline $/yr Post Retrofit $/yr Baseline $/yr Post Retrofit $/yr Audubon MS 1,872,000 1,042,871 23,955 18,437 $301,066 $177,428 $20,398 $16,631 Bell HS 2,975,696 2,323,229 30,003 30,003 $499,131 $403,625 $30,971 $30,971 Bernstein HS 2,745,840 1,880,192 29,978 29,978 $422,571 $299,201 $23,845 $23,845 Cochran MS 1,860,120 1,242,755 11,639 9,814 $291,322 $201,992 $10,103 $8,829 Contreras LC 2,297,280 1,504,415 85,961 85,961 $421,274 $292,023 $60,698 $60,698 Kennedy HS 2,562,933 1,942,318 22,744 23,362 $418,692 $321,115 $19,718 $22,855 King Drew HS 2,933,052 2,085,005 16,859 15,614 $454,265 $328,113 $14,474 $14,014 Lincoln HS 2,523,260 1,800,798 25,148 18,303 $419,442 $337,319 $22,860 $16,637 Marshall HS 2,265,577 1,617,624 42,934 26,133 $322,048 $230,071 $35,280 $21,470 Panorama HS 2,484,760 2,159,860 30,138 31,956 $394,257 $349,336 $24,526 $26,026 Roybal LC 3,844,847 2,863,421 32,757 21,007 $469,768 $335,605 $46,133 $35,194 Santee EC 4,003,174 2,586, ,322 55,343 $506,223 $323,182 $75,872 $41,014 Van Nuys HS 2,060,040 1,530,866 14,116 13,863 $366,655 $286,769 $12,272 $11,468 Total: 34,428,579 24,580, , ,774 $5,286,714 $3,885,779 $397,150 $329,652 14

15 LESSONS LEARNED Contractor Resources and School Coordination Understand site coordination & logistics issues. Develop phasing plan & appropriate working hours to accommodate school schedule. Streamline Utility Rebate Process Prevent Delays in Application Review and Scheduling Pre-Inspection. Require Energy Service Companies to attend all Rebate Program training seminars sponsored by the Utility. Los Angeles Department of Water and Power Southern California Edison Southern California Gas Agency Collaboration with Department of State Architecture (DSA) Determining Type of Projects that Require DSA Approval. Streamlining Submittal and Approval Process. Streamline District s Process to Review and Approve New Technologies LED Lighting. Wireless Controls. Tankless Domestic Water Heaters. 15

16 OVERALL PROGRAM IMPACTS (Phases 1-5) Jobs Creation 550 Job Years (As estimated through the CEC Calculator). General Fund Savings $5.84 Million estimated in Annual Electric & Gas Savings. Improve Learning Environment Improved Lighting & Temperature Control in Classrooms. Lower Maintenance Costs New LED lighting with less replacement costs. Retrofitted and Retro-commissioned HVAC Systems to meet current requirements. Energy Management Systems to improve HVAC controls and operating schedules. Student Energy Auditor Training High School Seniors trained in performing energy surveys. Partner with the California Conservation Corps & Los Angeles Conservation Corps. 16

17 COLLEGE AND CAREER READINESS In Partnership with the California Conservation Corp (CCC) and the Los Angeles Conservation Corp (LACC), LAUSD will be able to deliver a workforce development program to high school students that: Contributes to the student s achievement of Career Preparation outcomes. Contributes to preparing the student with the basic skills necessary for higher-- intensity work-- based learning experiences(career Preparation and Career Training.) Provide activities that have consequences beyond the class or value beyond success in school and are judged by outside professionals from industry and the community using industry standards. 17

Proposition 39 is a Catalyst:

Proposition 39 is a Catalyst: Proposition 39 is a Catalyst: Leverage Utility Support to Reduce Even More Energy School Energy Coalition Energy Emporium Joey Barr April 1st, 2014 Agenda 2 Proposition 39 Overview Programs / Resources

More information

California Virtual Academies and Insight Schools of California

California Virtual Academies and Insight Schools of California California Virtual Academies and Insight Schools of California REQUEST FOR QUALIFICATIONS FOR DESIGN/BUILD OF PROPOSITION 39 ENERGY EFFICIENCY PROJECTS REQUEST FOR QUALIFICATIONS SUBMITTAL DEADLINE April

More information

Proposition 39 Program, Senate Bill 110 Overview, and ECAA-Ed Competitive Loan Program Concept

Proposition 39 Program, Senate Bill 110 Overview, and ECAA-Ed Competitive Loan Program Concept Proposition 39 Program, Senate Bill 110 Overview, and ECAA-Ed Competitive Loan Program Concept April 2018 1 Proposition 39 K-12 Background, Update and Reminders 2 Prop 39 K-12 Appropriations Fiscal Year

More information

Proposition 39. Years 4, 5 and Beyond. Fall ACBO Conference October 25, 2016

Proposition 39. Years 4, 5 and Beyond. Fall ACBO Conference October 25, 2016 Proposition 39 Years 4, 5 and Beyond Fall ACBO Conference October 25, 2016 JoAnn Higdon VP Administrative Services El Camino College Bob Bradshaw Manager Design & Construction El Camino College Lisa Hannaman

More information

P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y

P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y Measure Q Update P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y 1 5 2 0 1 5 Agenda 1. P R E L I M I N A R Y R E S P O N S E T O

More information

COVINA-VALLEY UNIFIED SCHOOL DISTRICT

COVINA-VALLEY UNIFIED SCHOOL DISTRICT COVINA-VALLEY UNIFIED SCHOOL DISTRICT REQUEST FOR PROPOSAL ENERGY PERFORMANCE CONTRACTING SERVICES RFP NO. 15-16-105 REQUEST FOR PROPOSAL SUBMITTAL DEADLINE NOVEMBER 6, 2015 AT 11:00AM SUBMIT TO: COVINA-VALLEY

More information

Flemington Raritan Regional School District; Energy Saving Improvement Program (ESIP)

Flemington Raritan Regional School District; Energy Saving Improvement Program (ESIP) Flemington Raritan Regional School District; Energy Saving Improvement Program (ESIP) ESIP Energy Savings Plan June 11, 2012 Presenters: Jon Zeller, Account Executive Ryan Thordson, Manager Project Development

More information

45 Day Budget Revision & Current Budget Update

45 Day Budget Revision & Current Budget Update 45 Day Budget Revision & Budget Update August 11, 2015 Anna Pimentel Director, Fiscal Services Jamie Metcalf Asst. in Training Director, Fiscal Services Ken Forrest Chief Business Officer 1 Context E.C.

More information

Money, Money, Money for Green Projects

Money, Money, Money for Green Projects Money, Money, Money for Green Projects Green California Schools and Community Colleges Summit October 30, 2015 + Money, Money, Money for Green Projects: State and Local Funding Green California Schools

More information

Proposition 39 Implementation Guidelines

Proposition 39 Implementation Guidelines Proposition 39: Clean Energy Jobs Act of 2012 California Community Colleges Proposition 39 Implementation Guidelines ADDENDUM TO THE MAY 29, 2013 CCC ENERGY PROJECT GUIDANCE Prepared by the California

More information

Building Optimization Analysis (BOA) Tool Training

Building Optimization Analysis (BOA) Tool Training Building Optimization Analysis (BOA) Tool Training Dave Moser, Senior Engineer, PECI Michelle Lichtenfels, Program Manager, PECI September 8 and 13, 2010 Training Objectives Use the BOA Tool to calculate

More information

Facility Condition Assessment Report. Coast Community College District

Facility Condition Assessment Report. Coast Community College District Facility Condition Assessment Report Coast Community College District February 28, 2003 Introduction To help document the need for funding the necessary replacement and upgrading of facilities within California

More information

Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019

Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 PRESENTED BY Finance and Administration Florida Agricultural and Mechanical University 1 ACTION ITEM IV: Approval of

More information

LOS ANGELES UNIFIED SCHOOL DISTRICT Proposition BB, Measure K, Measure R, and Measure Y School Bond Construction Programs Agreed-Upon Procedures

LOS ANGELES UNIFIED SCHOOL DISTRICT Proposition BB, Measure K, Measure R, and Measure Y School Bond Construction Programs Agreed-Upon Procedures LOS ANGELES UNIFIED SCHOOL DISTRICT Proposition BB, Measure K, Measure R, and Measure Y School Bond Construction Programs Agreed-Upon Procedures Report for the Year Ended June 30, 2013 and Statements of

More information

Minnesota's Guaranteed Energy Savings Program (GESP)

Minnesota's Guaranteed Energy Savings Program (GESP) Minnesota's Guaranteed Energy Savings Program (GESP) Division of Energy Resources & CERTs Roles Energy Savings Performance Contracting The Power of Bundling Energy Conservation Measures Minnesota s new

More information

Mt. Diablo Unified School District Facilities Financing Programs and 2010 Measure C Board of Education

Mt. Diablo Unified School District Facilities Financing Programs and 2010 Measure C Board of Education Mt. Diablo Unified School District Facilities Financing Programs and 2010 Measure C Board of Education Study Session March 9, 2015 Agenda Board of Education Study Session March 9, 2015 Program Update School

More information

All text in Red Italics is sample verbiage or instructions and may to be removed from the final document.

All text in Red Italics is sample verbiage or instructions and may to be removed from the final document. ESA / IGA Schedules Project Documents include the following Schedules which are incorporated herein and made a part of the IGA and ESA when approved by the ISSUER and ESCO: Schedule A Schedule B Schedule

More information

Garden City Public Schools Capital Reserve. Presentation to the Board of Education January 10, 2017

Garden City Public Schools Capital Reserve. Presentation to the Board of Education January 10, 2017 Garden City Public Schools Capital Reserve Presentation to the Board of Education January 10, 2017 Tonight s Agenda District Reserves Planning process General use Current reserves Capital Reserve Voter

More information

Guaranteed Energy Savings Contract

Guaranteed Energy Savings Contract REQUEST FOR PROPOSALS NUMBER RFP # MASD 13-01 December 20, 2013 MINERSVILLE AREA SCHOOL DISTRICT Guaranteed Energy Savings Contract SUPERINTENDENT'S OFFICE 1 Battlin Miners Drive P.O. Box 787 Minersville,

More information

Measure K Board Workshop December 1, 2008 Building on Success: Schools for the Next Generation

Measure K Board Workshop December 1, 2008 Building on Success: Schools for the Next Generation Measure K Board Workshop December 1, 2008 Building on Success: Schools for the Next Generation Workshop Items Citizens Oversight Committee Measure K Next Steps Projects in Planning Milestones Board s Vision

More information

PACE Financing. J. Caleb Bell, Partner Bricker & Eckler LLP

PACE Financing. J. Caleb Bell, Partner Bricker & Eckler LLP PACE Financing J. Caleb Bell, Partner Bricker & Eckler LLP 614.227.2384 jbell@bricker.com PACE Financing PACE = Property Assessed Clean Energy Ohio s PACE Law Energy SID A special type of financing district

More information

MT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE R, NOVEMBER 2001) PERFORMANCE AUDIT.

MT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE R, NOVEMBER 2001) PERFORMANCE AUDIT. (MEASURE R, NOVEMBER 2001) (MEASURE R, NOVEMBER 2001) CONTENTS Page Independent Auditor s Report... 1 Objectives... 2 Scope of the Audit... 2 Background Information... 3 Procedures Performed... 3 Results

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT MEASURE J BOND CONSTRUCTION PROGRAM

LOS ANGELES COMMUNITY COLLEGE DISTRICT MEASURE J BOND CONSTRUCTION PROGRAM Statement of Expenditures of Bond Proceeds and Unaudited Supplementary Schedule Year ended June 30, 2017 (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Statement

More information

Facility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA

Facility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA AGENDA benefits & limitations Rod Moore, RA, LEED AP, PMP Georgia Tech Benjamin Dutton, FFB, MCIOB, MRICS Faithful+Gould GT Facilities GT Program What is GT FCA Deliverables How GT uses FCA Information

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT MEASURE J BOND CONSTRUCTION PROGRAM

LOS ANGELES COMMUNITY COLLEGE DISTRICT MEASURE J BOND CONSTRUCTION PROGRAM Final Editorial Review Completed NDPPS USE ONLY NDPPS ID: 615508 Contact Name: Kristen Olko Special Instructions Version: 2 Statement of Expenditures of Bond Proceeds and Unaudited Supplementary Schedule

More information

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017 Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By

More information

Fiscal Year GUIDE TO UNDERSTANDING THE BUDGET CHERRY CREEK SCHOOL DISTRICT #5 ARAPAHOE COUNTY, COLORADO

Fiscal Year GUIDE TO UNDERSTANDING THE BUDGET CHERRY CREEK SCHOOL DISTRICT #5 ARAPAHOE COUNTY, COLORADO Fiscal Year 2015-16 GUIDE TO UNDERSTANDING THE BUDGET CHERRY CREEK SCHOOL DISTRICT #5 ARAPAHOE COUNTY, COLORADO ACKNOWLEDGMENTS Thank you to the members of the Budget Department for their dedicated efforts

More information

Chancellor s Message - Achievements

Chancellor s Message - Achievements Chancellor s Message - Achievements We have achieved significant educational and operational advances. To name a few: $41 million in savings from operations through the elimination of redundancies and

More information

Asset Management and Energy Initiatives. Kathleen Berube Sustainable Development Manager

Asset Management and Energy Initiatives. Kathleen Berube Sustainable Development Manager Asset Management and Energy Initiatives Kathleen Berube Sustainable Development Manager Pre Development Upgrades Add value Increase NOI Shortest Payback Low hanging fruit Villages of East River Washington

More information

West Contra Costa Unified School District

West Contra Costa Unified School District West Contra Costa Unified School District 2013-14 45 Day Budget Revision Executive Summary Board Meeting July 24, 2013 State Budget Impact on District Planning The 2013-14 budget for the State was adopted

More information

To: Mayor and City Council Through: Bill Monahan, City Manager. Subject: Proceeding with the ESCO Process

To: Mayor and City Council Through: Bill Monahan, City Manager. Subject: Proceeding with the ESCO Process MILWAUKIE CITY COUNCIL STAFF REPORT Agenda Item: WS 4. Meeting Date: 9-16-14 To: Mayor and City Council Through: Bill Monahan, City Manager Subject: Proceeding with the ESCO Process From: Gary Parkin,

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT BOND CONSTRUCTION PROGRAMS: PROPOSITION A PROPOSITION AA MEASURE J

LOS ANGELES COMMUNITY COLLEGE DISTRICT BOND CONSTRUCTION PROGRAMS: PROPOSITION A PROPOSITION AA MEASURE J BOND CONSTRUCTION PROGRAMS: PROPOSITION A PROPOSITION AA MEASURE J Statements of Expenditures of Bond Proceeds and Supplementary Schedules Year ended June 30, 2016 BOND CONSTRUCTION PROGRAMS Table of Contents

More information

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year February 20, 2018

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year February 20, 2018 School Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year 2017-18 February 20, 2018 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...

More information

DRAFT. Los Angeles Community College District

DRAFT. Los Angeles Community College District Los Angeles Community College District Statement of Expenditures of Bond Proceeds and Unaudited Supplementary Schedules for Propositions A, AA and J June 30, 2017 (With Independent Auditors Report Thereon)

More information

Minnesota's Guaranteed Energy Savings Program (GESP)

Minnesota's Guaranteed Energy Savings Program (GESP) Minnesota's Guaranteed Energy Savings Program (GESP) Division of Energy Resources Role Energy Savings Performance Contracting The Power of Bundling Energy Conservation Measures Minnesota s new Guaranteed

More information

Property Assessed Clean Energy Programs and How PACE Can Benefit Your Community

Property Assessed Clean Energy Programs and How PACE Can Benefit Your Community Property Assessed Clean Energy Programs and How PACE Can Benefit Your Community WHAT IS PACE? Property Assessed Clean Energy (PACE) is a financing mechanism that enables low-cost, long-term funding for

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT BOND CONSTRUCTION PROGRAMS. Table of Contents. Proposition AA Bond Construction Program

LOS ANGELES COMMUNITY COLLEGE DISTRICT BOND CONSTRUCTION PROGRAMS. Table of Contents. Proposition AA Bond Construction Program LOS ANGELES COMMUNITY COLLEGE DISTRICT BOND CONSTRUCTION PROGRAMS Table of Contents Tab Proposition A Bond Construction Program Proposition AA Bond Construction Program Measure J Bond Construction Program

More information

Progress Update Identified Needs & Capital Plan

Progress Update Identified Needs & Capital Plan Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary

More information

Protection notice / Copyright notice

Protection notice / Copyright notice Financing Infrastructure for K12 Presented by : Deval Allums Denise Granado Chavez November 22, 2013 Protection notice / Copyright notice Presentation Key Points Academics is priority #1, but operational

More information

Energy Savings Performance Contracting Program Process Description

Energy Savings Performance Contracting Program Process Description Energy Savings Performance Contracting Program Process Description I. Program History The Energy Savings Performance Contracting (ESPC) program was developed to provide a means to install energy conservation

More information

Delaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016

Delaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016 Delaware Public and Institutional Energy Performance Contracting Program Guidebook ~ 2016 Delaware Sustainable Energy Utility 500 West Loockerman Street, Suite 400 Dover, DE 19904 302-883-3048 1 Public

More information

Bond Oversight Committee Bond program. January 7, 2016

Bond Oversight Committee Bond program. January 7, 2016 Bond Oversight Committee 2014 Bond program January 7, 2016 Bond Oversight Committee 1 AGENDA Welcome, introductions, reminder of scope/role of BOC Stewart Jacobson, Chair Program Management: Max Cleaver

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018 SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center & Demolition Science Center

More information

Guaranteed Energy Savings Program (GESP) February 21, CERTS Conference

Guaranteed Energy Savings Program (GESP) February 21, CERTS Conference Guaranteed Energy Savings Program (GESP) February 21, 2013 2013 CERTS Conference Facility Issues Growing Deferred Maintenance Occupant Comfort and Productivity Health, Safety and Environmental Energy Price

More information

STATE CAPITAL OUTLAY PLANNING

STATE CAPITAL OUTLAY PLANNING STATE CAPITAL OUTLAY PLANNING CCC Chancellor s Office Cheryl Larry Lan Yuan San Mateo CCD Jose Nunez Karen Pinkham CCFC 2016 AGENDA Overview Eligibility Priority Review/Approval Effective Practices 1 Key

More information

Ballot Measures-T Section

Ballot Measures-T Section T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and

More information

Energy Management Solutions Incentives Application for Business Customers

Energy Management Solutions Incentives Application for Business Customers Follow the simple steps below to complete your Incentives Application: SEND TO: Southern California Edison, Business Incentives P.O. Box 800, Rosemead, CA 9770-0800 Fax: 626-6-24 E-mail: BusinessIncentives@sce.com

More information

Request for Proposal #2036. Orange Coast College Exterior Lighting Energy Efficiency Project Implementation

Request for Proposal #2036. Orange Coast College Exterior Lighting Energy Efficiency Project Implementation Request for Proposal #2036 Orange Coast College Exterior Lighting Energy Efficiency Project Implementation I. NOTICE A. Statement of Proposal NOTICE IS HEREBY GIVEN that Coast Community College District

More information

Wilkes Community College

Wilkes Community College Wilkes Community College REQUEST FOR PROPOSAL FOR GUARANTEED ENERGY SAVINGS PERFORMANCE CONTRACTING April 1, 2016 RFP #_2016-010_ Performance Contract RFP 4/01/2016 Page 1 REQUEST FOR PROPOSALS FOR Wilkes

More information

Delivering Efficiency as a Service: The Metrus ESA

Delivering Efficiency as a Service: The Metrus ESA Delivering Efficiency as a Service: The Metrus ESA May 22, 2018 Overview Metrus develops, finances, owns, and operates large-scale efficiency projects for Fortune 500 companies and major industrial customers.

More information

Bridgeville School District

Bridgeville School District Bridgeville School District Request for Quotes Informal quotes for project with estimated value under $15,000 Project Name: Proposition 39 Interior Lighting Retrofit Phase 2 Project Description: Contacts:

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT MEASURE J BOND CONSTRUCTION PROGRAM

LOS ANGELES COMMUNITY COLLEGE DISTRICT MEASURE J BOND CONSTRUCTION PROGRAM Final Editorial Review Not Completed PLEASE COMPLETE Date/Time Due Services Requested: Format Revisions Editorial Review Print Name: Kristen Olko Tel./Ext.: 213.533.3347 Special Instructions: _v4 Statement

More information

HILLSBOROUGH CITY SCHOOL DISTRICT REQUEST FOR STATEMENT OF QUALIFICATIONS AND REQUEST FOR PROPOSAL

HILLSBOROUGH CITY SCHOOL DISTRICT REQUEST FOR STATEMENT OF QUALIFICATIONS AND REQUEST FOR PROPOSAL HILLSBOROUGH CITY SCHOOL DISTRICT REQUEST FOR STATEMENT OF QUALIFICATIONS AND REQUEST FOR PROPOSAL FOR Energy Services Design-Build Contractor For Proposition 39 Funded Energy Efficiency & Conservation

More information

U. S. Department of Housing and Urban Development Office of Public and Indian Housing

U. S. Department of Housing and Urban Development Office of Public and Indian Housing U. S. Department of Housing and Urban Development Office of Public and Indian Housing Special Attention of: NOTICE: PIH-2011-36 (HA) Public Housing Agencies; Issued: July 8, 2011 HUD Directors of Public

More information

Build and Repair Schools Now Talking Points

Build and Repair Schools Now Talking Points Build and Repair Schools Now Talking Points The Coalition for Adequate School Housing (CASH) proposes that $3.0 billion in voter approved Proposition 51 state school bonds be sold in the 2018 19 fiscal

More information

Contractor Guide. (314)

Contractor Guide.  (314) Contractor Guide www.stlouiscountysaves.com contractor@stlouiscountysaves.com (314) 332-2156 Introduction is a $10.4 million residential energy efficiency loan program supported by partnerships between

More information

New Jersey Clean Energy Collaborative. Regulatory Reporting

New Jersey Clean Energy Collaborative. Regulatory Reporting New Jersey Clean Energy Collaborative New Jersey Clean Energy Collaborative Table of Contents Overview...1 Contents and Timetables...1 Quarterly Reports...1 Annual Reports...2 Performance Reports...2 Evaluation

More information

CH-UH Board of Education Meeting. June 27, 2017

CH-UH Board of Education Meeting. June 27, 2017 CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle

More information

PROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue

PROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS - BOND LANGUAGE Shall the Board of Education of the Farmington R-7 School District of St. Francois County, Missouri,

More information

Use of State and District Construction Funds

Use of State and District Construction Funds 8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,

More information

Why Schools and Businesses Want More Proposition 51 Bonds to be Sold Now

Why Schools and Businesses Want More Proposition 51 Bonds to be Sold Now Why Schools and Businesses Want More Proposition 51 Bonds to be Sold Now The Coalition for Adequate School Housing (CASH) proposes that $3.0 billion in voter approved Proposition 51 state school bonds

More information

CONTRA COSTA COMMUNITY COLLEGE DISTRICT CAPITAL OUTLAY BOND FUND 2002 ELECTION FINANCIAL REPORT

CONTRA COSTA COMMUNITY COLLEGE DISTRICT CAPITAL OUTLAY BOND FUND 2002 ELECTION FINANCIAL REPORT CONTRA COSTA COMMUNITY COLLEGE DISTRICT CAPITAL OUTLAY BOND FUND 2002 ELECTION FINANCIAL REPORT CONTRA COSTA COMMUNITY COLLEGE DISTRICT CAPITAL OUTLAY BOND FUND 2002 ELECTION TABLE OF CONTENTS FINANCIAL

More information

BERKELEY UNIFIED SCHOOL DISTRICT

BERKELEY UNIFIED SCHOOL DISTRICT BERKELEY UNIFIED SCHOOL DISTRICT TO: Javetta Cleveland and Neil Smith, Co-Superintendents FROM: Lew Jones, Director of Facilities DATE: June 26, 2013 SUBJECT: Approval of the 2013/14 Measure H Annual Plan

More information

REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ #

REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ # Name: Lackawanna County Address: 200 Adams Ave Address: Scranton PA 18503 Introduction REQUEST FOR QUALIFICATIONS GUARANTEED ENERGY SAVINGS CONTRACT RFQ # 345-12-1 Lackawanna County is requesting Qualifications

More information

Building Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits

Building Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits Building Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits CUNY Institute for Urban Systems Building Performance Lab Introduction to Energy Audits 2 Topic

More information

ANNOUNCEMENT. This request for qualifications seeks the following type of service providers:

ANNOUNCEMENT. This request for qualifications seeks the following type of service providers: ANNOUNCEMENT REQUEST FOR STATEMENT OF QUALIFICATIONS NOTICE FOR ENGINEERING SERVICES BY SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN AND CONSTRUCTION The San Francisco Unified School District

More information

PERRIS ELEMENTARY SCHOOL DISTRICT

PERRIS ELEMENTARY SCHOOL DISTRICT PERRIS ELEMENTARY SCHOOL DISTRICT 2006 & 2014 General Obligation Bond Authorizations Measures S & C Citizens' Oversight Committee Report March 1, 2018 2006 GENERAL OBLIGATION BOND ELECTION 2006 Measure

More information

Direct Install (DI) Program. Program Guide. Fiscal Year 2018 (7/1/2017 through 6/30/2018)

Direct Install (DI) Program. Program Guide. Fiscal Year 2018 (7/1/2017 through 6/30/2018) Direct Install (DI) Program Program Guide Fiscal Year 2018 (7/1/2017 through 6/30/2018) Table of Contents 1. Overall Program Description... 3 2. Target Market & Eligibility... 3 3. Program Website Link...

More information

Direct Install (DI) Program. Program Guide. Fiscal Year 2019 (7/1/2018 through 6/30/2019)

Direct Install (DI) Program. Program Guide. Fiscal Year 2019 (7/1/2018 through 6/30/2019) Direct Install (DI) Program Program Guide Fiscal Year 2019 (7/1/2018 through 6/30/2019) Table of Contents 1. Overall Program Description... 3 2. Target Market & Eligibility... 3 3. Program Website Link...

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT PROPOSITION AA BOND CONSTRUCTION PROGRAM

LOS ANGELES COMMUNITY COLLEGE DISTRICT PROPOSITION AA BOND CONSTRUCTION PROGRAM Statement of Expenditures of Bond Proceeds and Unaudited Supplementary Schedule Year Ended June 30, 2017 (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Statement

More information

DATE: September 12, 2017 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

DATE: September 12, 2017 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration DATE: September 12, 2017 REPORT NO. PW2017-061 TO: FROM: Chair and Members Committee of the Whole Operations and Administration E. (Beth) Goodger, General Manager Public Works Commission 1.0 TYPE OF REPORT

More information

R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M

R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M U N I V E R S I T Y O F N O R T H A L A B A M A R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M R F P 2 0 1 7-23

More information

Multifamily Energy Efficiency Program

Multifamily Energy Efficiency Program Multifamily Energy Efficiency Program Rebate Reservation Request To reserve incentives from the PNM Multifamily Energy Efficiency Program, please complete this form and return to multifamily@pnm.com or

More information

PROGRAM REVIEW FACILITIES PLANNING & SERVICES DIVISION

PROGRAM REVIEW FACILITIES PLANNING & SERVICES DIVISION 2013-14 PROGRAM REVIEW FACILITIES PLANNING & SERVICES DIVISION I. Division Purpose Plan, construct and maintain a safe, functional, clean and attractive physical environment for the users of El Camino

More information

Summary of Capital Budget Request Tennessee Board of Regents. of the. September 21, 2017

Summary of Capital Budget Request Tennessee Board of Regents. of the. September 21, 2017 Summary of Capital Budget Request 2018-2019 of the Tennessee Board of Regents September 21, 2017 1 This is the Summary of the Capital Budget Request for Fiscal Year 2018-2019 for the Finance and Business

More information

LOS ANGELES COMMUNITY COLLEGE DISTRICT BOND CONSTRUCTION PROGRAMS: PROPOSITION A PROPOSITION AA MEASURE J

LOS ANGELES COMMUNITY COLLEGE DISTRICT BOND CONSTRUCTION PROGRAMS: PROPOSITION A PROPOSITION AA MEASURE J BOND CONSTRUCTION PROGRAMS: PROPOSITION A PROPOSITION AA MEASURE J Statements of Expenditures of Bond Proceeds and Supplementary Schedules Year ended June 30, 2011 BOND CONSTRUCTION PROGRAMS Table of Contents

More information

Port Authority of the City of Saint Paul Property Assessed Clean Energy Program (PACE OF MN) ADMINISTRATIVE GUIDELINES

Port Authority of the City of Saint Paul Property Assessed Clean Energy Program (PACE OF MN) ADMINISTRATIVE GUIDELINES Port Authority of the City of Saint Paul Property Assessed Clean Energy Program () ADMINISTRATIVE GUIDELINES Saint Paul Port Authority 850 Lawson Commons 380 St. Peter Street Saint Paul, MN 55102 (651)

More information

SAN FRANCISCO COMMUNITY COLLEGE DISTRICT

SAN FRANCISCO COMMUNITY COLLEGE DISTRICT SCHEDULE OF PROCEEDS AND USE OF GENERAL OBLIGATION BONDS (ELECTION OF 2005, SERIES A) WITH INDEPENDENT AUDITOR S REPORT For the period from June 20, 2006 through June 30, 2006 SCHEDULE OF PROCEEDS AND

More information

REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS

REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS REQUEST FOR PROPOSAL (RFP) ENERGY SAVINGS PERFORMANCE CONTRACTING PROJECT INSTRUCTIONS TO BIDDERS 1. INTRODUCTION Van Dyke Public Schools is requesting proposals from Energy Services Companies (ESCOs)

More information

SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE

SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE FEBRUARY 8, 2019 INVESTMENT GRADE AUDIT SUMMARY REPORT SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE in support of Act 77/39 Guaranteed Energy Savings Agreement (GESA) Reynolds Energy Services, Inc. 3300 North

More information

DTE Energy Multifamily Program

DTE Energy Multifamily Program DTE Energy Multifamily Program 2016 Policies and Procedures Manual The DTE Energy Multifamily Program provides incentives for Multifamily property owners who upgrade their facilities with energy efficient

More information

Grossmont-Cuyamaca Community College District Project Labor Agreement Evaluation Plan

Grossmont-Cuyamaca Community College District Project Labor Agreement Evaluation Plan March 16, 2017 PROCEDURE MANUAL TABLE OF CONTENTS PLA EVALUATION PLAN PROCESS A. OVERVIEW... 2 Projects... 2 Controlling Laws and Regulations... 2 Roles and Responsibilities... 2 B. KEY PERFORMANCE INDICATORS

More information

2016 Statewide Retrocommissioning Policy & Procedures Manual

2016 Statewide Retrocommissioning Policy & Procedures Manual 2016 Statewide Retrocommissioning Policy & Procedures Manual Version 1.0 Effective Date: July 19, 2016 Utility Administrators: Pacific Gas and Electric San Diego Gas & Electric Southern California Edison

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

TRANSIT SYSTEM MAINTENANCE AND RENOVATION. VEHICLES - Caltrain

TRANSIT SYSTEM MAINTENANCE AND RENOVATION. VEHICLES - Caltrain Item 6 Enclosure Board November 13, 2018 2019 PROPOSITION K 5-YEAR PRIORITIZATION PROGRAM TRANSIT SYSTEM MAINTENANCE AND RENOVATION VEHICLES - Caltrain Pending Board Approval: November 27, 2018 Prepared

More information

Sacramento City College Strategic Planning System

Sacramento City College Strategic Planning System Sacramento City College Strategic Planning System Title: Plan Type: OPR: Collaborative Groups: Resource Management and Capital Outlay Master Plan 2018 Institutional VPA Resource Allocation Groups: Budget

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

LONG BEACH UNIFIED SCHOOL DISTRICT

LONG BEACH UNIFIED SCHOOL DISTRICT PROPOSITION 39 GENERAL OBLIGATION BONDS BOND BUILDING FUNDS MEASURE K AND MEASURE E FINANCIAL AND PERFORMANCE AUDITS Long Beach Unified School District TABLE OF CONTENTS Financial Audit of the Measure

More information

LONG BEACH UNIFIED SCHOOL DISTRICT PROPOSITION 39 GENERAL OBLIGATION BONDS MEASURE K, NOVEMBER 2008 FINANCIAL AND PERFORMANCE AUDITS

LONG BEACH UNIFIED SCHOOL DISTRICT PROPOSITION 39 GENERAL OBLIGATION BONDS MEASURE K, NOVEMBER 2008 FINANCIAL AND PERFORMANCE AUDITS PROPOSITION 39 GENERAL OBLIGATION BONDS MEASURE K, NOVEMBER 2008 FINANCIAL AND PERFORMANCE AUDITS Fiscal Year Ended June 30, 2016 TABLE OF CONTENTS June 30, 2016 Financial Audit of the Measure K Bond Fund...1

More information

Program and Project Status Update

Program and Project Status Update Program and Project Status Update Citizens Bond Oversight Committee Meeting October 14, 2014 Robert Ball, Bond Program Manager 1 Capital Improvement Program General Updates Close out of completed projects

More information

ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT MEASURE R GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016

ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT MEASURE R GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016 ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT 2004 MEASURE R GENERAL OBLIGATION BONDS PERFORMANCE AUDIT PERFORMANCE AUDIT CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE HISTORY... 2 ANTELOPE

More information

Ameren Missouri Electric Account Number(s) for building where equipment will be installed (please attach additional sheets if needed)

Ameren Missouri Electric Account Number(s) for building where equipment will be installed (please attach additional sheets if needed) Application Tax Credit Disclosure Has the Participant received either of the following tax credits for the site listed below? If the answer is Yes to either, the Site named herein is ineligible to participate

More information

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT Dublin, California. MEASURE B GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT Dublin, California. MEASURE B GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016 CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT MEASURE B GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016 PERFORMANCE AUDIT June 30, 2016 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE

More information

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019 School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year 2018-19 February 21, 2019 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...

More information

Glossary of Terms, Definitions and Commonly Used Acronyms (Prepared for Palomar College s ICOC, December 2007)

Glossary of Terms, Definitions and Commonly Used Acronyms (Prepared for Palomar College s ICOC, December 2007) Administrative Services Planning Council (ASPC): The shared governance council for the Finance and Administrative Services Division. Americans with Disabilities Act (ADA): Federal regulation that insures

More information

Snohomish PUD. Energy Services Team November 7, 2018

Snohomish PUD. Energy Services Team November 7, 2018 Snohomish PUD ENERGY SERVICES COMMERCIAL & INDUSTRIAL ENERGY EFFICIENCY PROG RAMS NON- L I G H T I N G T R A D E A L L I E S R O U N D TA B L E 2 0 1 9 P R O G R A M S K I C K - O F F Energy Services Team

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, additions and modernizations, as well as other school related projects. For more than a decade

More information

Energy Saving Improvement Programs

Energy Saving Improvement Programs Introducing Energy Saving Improvement Programs aka: ESIP; ESCO; P.L. 2009, c. 4; A-1185A Marc Pfeiffer, Deputy Director Division of Local Government Services What ESIP is All About Retrofitting public

More information

SOUTHERN CALIFORNIA EDISON & SOUTHERN CALIFORNIA GAS COMPANY ENERGY UPGRADE CALIFORNIA PROGRAM

SOUTHERN CALIFORNIA EDISON & SOUTHERN CALIFORNIA GAS COMPANY ENERGY UPGRADE CALIFORNIA PROGRAM SOUTHERN CALIFORNIA EDISON & SOUTHERN CALIFORNIA GAS COMPANY ENERGY UPGRADE CALIFORNIA PROGRAM CONTRACTOR PARTICIPATION AGREEMENT APPLICATION INSTRUCTIONS V3.0 Contents Section 1.0... 1 1 1.1 Begin Application...

More information

MEASURE AV GENERAL OBLIGATION BONDS PERFORMANCE AUDIT

MEASURE AV GENERAL OBLIGATION BONDS PERFORMANCE AUDIT MEASURE AV GENERAL OBLIGATION BONDS PERFORMANCE AUDIT FOR THE FISCAL YEAR ENDED JUNE 30, 2017 Measure AV GENERAL OBLIGATION BONDS Table of Contents June 30, 2017 Independent Auditors Report... 1 Page BACKGROUND

More information