Annex C. Sample ToR for Independent Procurement Review

Size: px
Start display at page:

Download "Annex C. Sample ToR for Independent Procurement Review"

Transcription

1 1. Introduction Annex C. Sample ToR for Independent Procurement Review TERMS OF REFERENCE INDEPENDENT PROCUREMENT REVIEW (IPR) 1.1. The procurement team of the World Bank requires an independent review of the procurement and contracting that have been undertaken in [insert country] for [insert project(s)] The review will be carried out at the headquarters of the Implementing Agencies for each of the projects Under the Bank s Procurement Regulations for Borrowers, the Bank is expected to assure itself that procurement and contracting for Bank projects is carried out in accordance with the Legal Agreement (LA). Only contracts procured following such procedures are eligible for financing using the proceeds of the Bank s loan To this end, the Procurement Regulations for Borrowers provide for the following review procedures: For those contracts specified in the Procurement Plan as subject to Prior Review, and for any procurement that involves the use of Best and Final Offer, negotiations (for competitive procurement processes for goods, works and non-consulting services), competitive dialogue, and sustainable procurement, the Bank prior reviews the following documents: The GPN and SPN If prequalification/initial selection is used, the invitation to prequalify/be initially selected, the prequalification/initial selection document, and the prequalification/ initial selection evaluation report. For Consulting Services, the Request for Expressions of Interest, including the complete TOR, and the Shortlist assessment report The bidding/request for proposals documents, and any amendments to them The first request by the Borrower to Bidders/Proposers to extend the Bid/Proposal validity period, if it is longer than four (4) weeks, and all subsequent requests for extension, irrespective of the period The Bid/Proposal evaluation report and recommendations for contract award, including documents demonstrating that any procurement complaints have been addressed to the satisfaction of the Bank. In twoenvelope or multistage selection processes, the Bid/Proposal evaluation report for each envelope/stage before proceeding to the next stage of the procurement process All requests for cancellation of a procurement process and/or rebidding/reinvitation of proposals.

2 A change the borrower s contract award recommendation arising from analysis of a complaint after the Bank s prior review and no-objection The minutes of negotiations and the draft contract initialed by both parties, if the procurement process involves negotiations between the Borrower and Bidder/Proposer/Consultant If requested by the Bank, the Contract Management Plan, including the Key Performance Indicators (KPIs); also, if requested by the Bank, ongoing reports of progress based on the agreed KPIs For all other contracts, the Bank reviews contracts and award decisions after the award of the contract (on the basis of documents provided to the Bank before the first withdrawal or replenishment application in respect of the contract). This is referred to as Post Review For contracts on account of which disbursements are to be made on the basis of Statements of Expenditure (SOEs), the Bank reviews most of these contracts and their award decisions ex-post, in the field during implementation support missions To facilitate compliance by Borrowers and review by the Bank, the Bank requires the use of its Standard Procurement Documents (SPDs). Nevertheless, the review of procurement is a very staff-intensive activity and often requires specialist procurement staff. It gives a significant degree of responsibility and discretion to staff, but does not have a built-in system for routinely monitoring the quality, consistency, and timeliness of the reviews Independent Procurement Review (IPR) serves an important role in the Bank s general review responsibility by: Objectives contributing to the Bank s ability to maintain its fiduciary responsibilities with regard to the procurement function; identifying weaknesses and related risks in both the Borrower s and the Bank s procedures with regard to the selected projects, recommending corrective action, and recording findings and recommendations in PRAMS to monitor implementation of corrective actions; identifying systemic weaknesses in countries and providing recommendations for corrective action; contributing to the improvement of project implementation and risk management; reminding Bank management, staff, and Borrowers of the importance of their respective fiduciary responsibilities; and creating a deterrent to negligence in procurement management, decision making, and oversight, to ensure that an environment conducive to fraudulent and corrupt practices is not allowed to develop and that any such practices are brought to light and eliminated.

3 1.1. The objective of the IPR is to review the procurement, contracting, and implementation processes that have been followed for contracts in the projects to confirm consistency with the LA The purpose of the IPR is to: verify that the procurement and contracting processes have been followed; perform an independent review and qualitative analysis of the Bank s procurement supervision; verify technical compliance, physical completion, and achievement of value for money in each contract; and identify additional risks and mitigation measures to improve risk management and address risks more effectively To this end, the consultant will: determine whether the procurement and contracting processes were carried out in accordance with the LA and achieved value for money; determine to the extent possible whether identified noncompliance with the LA, inappropriate practices, or questionable decisions/actions may have been related to corrupt practices; evaluate the quality, timeliness, and reliability of the Bank s reviews and checks in ensuring that procurement, contracting, and disbursement are being carried out in accordance with the LA; and in light of any deficiencies, identify ways of improving the procurement and contracting process, identify associated risks, and propose risk mitigation measures. Scope of the IPR 1.1. The IPR will cover a sample of selected contracts financed from the proceeds of the loans (or credits) for the following investment projects: Project name Rationale for selection Loan no. Loan amount (in US$ million) Loan funds disbursed until [date of review] (in US$ million) List projects that would be covered by the review preferably at least one per sector, to have a representative sample 1.2. The name of the implementing agency will be given to the selected auditor at least two weeks before s/he departs for the country where the IPR is required, to enable the collection of all the relevant materials before work in the field begins.

4 1.3. The consultant should conduct a thorough review of the sample of contracts that have been selected, making visits to project sites and physical inspections of the goods and works procured as needed. Where appropriate, prices and quality should also be compared with similar contracts financed by agencies in the country and the region and verified against international market prices for the items in question To cover systematically the various objectives and scope defined in the TORs, the review should focus on four main areas: compliance of the procurement procedures, process, documents, and decisions with the LA; timeliness of the procurement/contracting process and decisions, including the Bank s reviews; compliance of the delivered goods and completed works and services with the requirements and specifications defined in the contract; and value for money. 2. Methodology 2.1. The IPR should follow three broad phases: Design of the scope and program of the review, defining the essential information requirements and contacts Field work Preparation of the IPR Report following discussions of the preliminary report with the Bank (and the Borrower if the Bank so decides) If the subject of the IPR involves a very large number of contracts, a preliminary decision on appropriate sampling, consistent with the IPR s scope and objectives, should be agreed upon by the Bank and documented In the design of the IPR, the consultant should use standard auditing methodologies. The consultant is encouraged to give consideration to the notes on procurement sampling set out in the attached Note on Sampling as broad guidelines for the methodology. If the consultant intends to introduce variations or substantial changes to these broad guidelines, that intention should be indicated in the technical proposal and agreed upon by the Bank The consultant should perform his/her duties in the field with full respect for and communication with officials of the Borrower. 3. IPR Report 3.1. On completing the review, and before completing the IPR Report, the consultant should present his/her initial findings to the Bank in the form of a Preliminary IPR Summary The IPR Report should focus on the IPR findings and recommendations without going into details of what transpired during the review. Details of the review methodology and

5 procedures, evidence substantiating the review findings, and elaboration on the recommendations should be covered in the Annexes Except as otherwise justified by the consultant, the report should be structured as follows: Summary of findings and recommendations Outline of the IPR Objectives and TORs Scope, approach, and review sample Findings on: Specific contracts Specific projects/agencies Country issues Bank s actions General issues Identified risks Recommendations (if any), including proposed risk mitigation measures for each identified risk ANNEXES Terms of Reference Review Methodology IPR Data (by contract and by project) - details of all findings of the review with evidence substantiating the findings. - tables and graphs illustrating the detailed analysis carried out during the review The Bank should review the Preliminary IPR Summary and the draft IPR Report and give the consultant a set of comments addressing all of the findings and recommendations. The consultant must not be required or expected to change his/her report to reflect the Bank s comments. If there is disagreement between the Bank and the consultant, the consultant should retain his/her findings and recommendations, but must incorporate the Bank s position, verbatim, in the report, making it clear that this is the Bank s position on the issue. The primary output of the review will be the final IPR Report, which will be the sole responsibility of the consultant and will represent the opinions of the consultant All reports will be in English. 4. Time Schedule

6 4.1. All IPR work would take place in the country identified in section 1 above with each of the projects executing agencies and other entities indicated to the consultant at contract negotiations. The consultant will select the contract sample after two or three days of work in the executing agency The documents and information listed in Attachment 3 will be available with the particular executing agency. The consultant will then carry out a detailed review of the procurement process and documentation for all IPR sample contracts, verification of technical compliance, physical verification of goods and works, cost analysis, and, where appropriate, comparison of prices with international/local price comparators. This activity may take one to two weeks. The activity should include a review of the Bank s process and decision making in the supervision review of the procurement and contracts. The consultant may contact the liaison person at Headquarters in writing to seek information not available in the field. The Bank will make every effort to respond to the inquiry promptly. At the end of this stage, the consultant should have a list of outstanding issues to present to the Bank together with the preliminary findings The draft final report will be presented to the Bank after the Bank has given an opinion in writing on the preliminary findings. Within two weeks after receiving the Bank s comments, the consultant will submit the Final IPR Report to the Bank. Depending on the scope of the work undertaken, the IPR should be completed within four to six weeks of the Bank s instructions to proceed with the IPR. 5. Staffing 5.1. The team will comprise the Team Leader (e.g., Senior Procurement staff from the office of the Accredited Practice Manager) and the procurement consultant (firm or individuals hired by the Bank for this task), working in close coordination with procurement staff assigned to individual projects The procurement consultant performing the IPR should have wide experience in public procurement under Bank-financed projects. The Bank will review and clear the curriculum vitae of the person(s) who will lead the assignment and be chiefly responsible for the field work before the commencement of the IPR, and no change in staffing will be made without the Bank s prior concurrence.

7 6. Data, Documents, Services, and Facilities 6.1. The consultant should aim to give the executing agency advance notice of the information and documents he/she will require The Bank will nominate a Bank contact to facilitate the work of the consultant. The Bank contact person will be the main means of communication among the consultant, the Bank, and the executing agency The Bank contact at Headquarters will be: [insert name] [insert phone] [insert address]

8

TERMS OF REFERENCE FOR AUDITS OF NIM/NGO PROJECTS

TERMS OF REFERENCE FOR AUDITS OF NIM/NGO PROJECTS United Nations Development Programme Office of Audit and Investigations Annex I TERMS OF REFERENCE FOR AUDITS OF NIM/NGO PROJECTS 2014 02 November 2014 TABLE OF CONTENTS Page INTRODUCTION... 3 A. Background...

More information

Technical Cooperation: Guidelines for Clients Managing Donor Funded Consultancy Assignments. October 2014

Technical Cooperation: Guidelines for Clients Managing Donor Funded Consultancy Assignments. October 2014 Technical Cooperation: Guidelines for Clients Managing Donor Funded Consultancy Assignments October 2014 Definitions and Abbreviations Affiliate: AICU: Assignment: Consultant(s): Commitment Number: CRF:

More information

THE WORLD BANK Procurement Regulations for IPF Borrowers

THE WORLD BANK Procurement Regulations for IPF Borrowers THE WORLD BANK Procurement Regulations for IPF Borrowers PROCUREMENT IN INVESTMENT PROJECT FINANCING Goods, Works, Non-Consulting and Consulting Services July 2016 Revised November 2017 Revised on November

More information

Evaluated Bid price PROCUREMENT GUIDANCE. Abnormally Low Bids and Proposals

Evaluated Bid price PROCUREMENT GUIDANCE. Abnormally Low Bids and Proposals Evaluated Bid price PROCUREMENT GUIDANCE Abnormally Low Bids and Proposals Guide to the identification i and treatment of Abnormally Low Bids and Proposals July 2016 Published February 1, 2016 Second Edition

More information

THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria

THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria THE GLOBAL FUND to Fight AIDS, Tuberculosis and Malaria Guidelines for Annual Audits of Program Financial Statements Table of Contents 1. Introduction 2. Operational Policies and Practices 3. Follow-up

More information

Guidelines for Financial Assurance Planning

Guidelines for Financial Assurance Planning For Global Fund Grants Guidelines for Financial Assurance Planning June 2016 Geneva, Switzerland The financial assurance plan provides improvements to the way the Global Fund obtains financial assurance

More information

External Audit. April 2012

External Audit. April 2012 External Audit April 2012 Audit Definition Ex post review of the books of account, financial statements, records of transactions & financial systems Examines the adequacy of accounting systems & procedures,

More information

DOCUMENTS CO-FINANCING FRAMEWORK AGREEMENT. between ASIAN INFRASTRUCTURE INVESTMENT BANK. and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

DOCUMENTS CO-FINANCING FRAMEWORK AGREEMENT. between ASIAN INFRASTRUCTURE INVESTMENT BANK. and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT IOFFICIA DOCUMENTS CO-FINANCING FRAMEWORK AGREEMENT between ASIAN INFRASTRUCTURE INVESTMENT BANK and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT and INTERNATIONAL DEVELOPMENT ASSOCIATION April

More information

Guidelines for the management of TCfunded consultancy assignments. EBRD clients

Guidelines for the management of TCfunded consultancy assignments. EBRD clients Guidelines for the management of TCfunded consultancy assignments EBRD clients Definitions and Abbreviations Affiliate AICU Assignment CCPD Consultant(s) Commitment Number CRF CSU CV Donor ESP Experts

More information

Evaluated Bid price PROCUREMENT GUIDANCE. How to complain

Evaluated Bid price PROCUREMENT GUIDANCE. How to complain Evaluated Bid price PROCUREMENT GUIDANCE Procurement-related elated Complaints How to complain December 2016 Published December 1, 2016, First Edition Copyright 2016 The World Bank 1818 H Street NW Washington

More information

REPORT 2015/041 INTERNAL AUDIT DIVISION. Audit of the United Nations Mine Action Service of the Department of Peacekeeping Operations

REPORT 2015/041 INTERNAL AUDIT DIVISION. Audit of the United Nations Mine Action Service of the Department of Peacekeeping Operations INTERNAL AUDIT DIVISION REPORT 2015/041 Audit of the United Nations Mine Action Service of the Department of Peacekeeping Operations Overall results relating to the effective management of mine action

More information

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TABLE OF CONTENTS Introduction... 3 A. Background... 7 B. Project Management... 7 C. Consultations with concerned parties...

More information

CONTENTS. Page EXECUTIVE SUMMARY I. OVERVIEW 1 II. FINDINGS AND RECOMMENDATIONS 2 III. CONCLUDING REMARKS 19

CONTENTS. Page EXECUTIVE SUMMARY I. OVERVIEW 1 II. FINDINGS AND RECOMMENDATIONS 2 III. CONCLUDING REMARKS 19 CONTENTS Page EXECUTIVE SUMMARY i I. OVERVIEW 1 II. FINDINGS AND RECOMMENDATIONS 2 III. CONCLUDING REMARKS 19 CURRENCY EQUIVALENTS (as of 28 February 2016) Currency unit = Papua New Guinea Kina (PGK) 1

More information

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan Technical Assistance Report Project Number: 46539 Regional Capacity Development Technical Assistance (R CDTA) August 2014 Improving the Financial Management Capacity of Executing Agencies in Afghanistan

More information

DIRECTIVE ON OPERATIONS PROCUREMENT A. OVERRIDING OBJECTIVE B. DEFINITIONS

DIRECTIVE ON OPERATIONS PROCUREMENT A. OVERRIDING OBJECTIVE B. DEFINITIONS DIRECTIVE ON OPERATIONS PROCUREMENT August 18, 2017 A. OVERRIDING OBJECTIVE 1. Purpose. The purpose of this Directive on Operations Procurement (Directive) is to enable the Bank s staff to implement the

More information

CHARTER OF THE AUDIT COMMITTEE OF THE BOARD OF TRUSTEES OF FS CREDIT INCOME FUND ADOPTED AS OF SEPTEMBER 2017

CHARTER OF THE AUDIT COMMITTEE OF THE BOARD OF TRUSTEES OF FS CREDIT INCOME FUND ADOPTED AS OF SEPTEMBER 2017 CHARTER OF THE AUDIT COMMITTEE OF THE BOARD OF TRUSTEES OF FS CREDIT INCOME FUND ADOPTED AS OF SEPTEMBER 2017 The board of trustees (the Board ) of FS Credit Income Fund, (the Company ) has determined

More information

Bank Operations and the Role of Procurement

Bank Operations and the Role of Procurement Bank Operations and the Role of Procurement PSLO Retreat April 23, 2012 Fadia Saadah, OPCPQ A Menu of Complementary Instruments Menu Investment Lending Development Policy Lending Program-for- Results Financing

More information

WIPO General Assembly

WIPO General Assembly E WO/GA/39/6 REV. ORIGINAL: ENGLISH DATE: SEPTEMBER 23, 2010 WIPO General Assembly Thirty-Ninth (20 th Extraordinary) Session Geneva, September 20 to 29, 2010 REVIEW OF THE INTERNAL AUDIT CHARTER prepared

More information

SAMPLE REQUEST FOR PROPOSALS UNDER JAPANESE ODA LOANS

SAMPLE REQUEST FOR PROPOSALS UNDER JAPANESE ODA LOANS CONSULTANTS SAMPLE REQUEST FOR PROPOSALS UNDER JAPANESE ODA LOANS SELECTION OF CONSULTANTS Japan International Cooperation Agency (JICA) September 2009 version 1.0 CONTENTS Preface... i Section 1. Letter

More information

Procurement in IPF and Other Operational Procurement Matters. Bank Access to Information Policy Designation Public

Procurement in IPF and Other Operational Procurement Matters. Bank Access to Information Policy Designation Public Bank Directive Procurement in IPF and Other Operational Procurement Matters Bank Access to Information Policy Designation Public Catalogue Number OPSVP5.05-DIR.114 Issued Effective July 1, 2016 Retired

More information

STATE OF NEW MEXICO Office of the State Auditor

STATE OF NEW MEXICO Office of the State Auditor STATE OF NEW MEXICO Office of the State Auditor AUDIT DOCUMENTATION REVIEW GUIDE Revised November 2006 To be used for review of audits of the Fiscal year ended June 30, 2006 AGENCY UNDER REVIEW AGENCY

More information

NEW PROCUREMENT FRAMEWORK Procurement-related Complaints

NEW PROCUREMENT FRAMEWORK Procurement-related Complaints NEW PROCUREMENT FRAMEWORK Procurement-related Complaints PRIVATE SECTOR WEBINAR Operations, Policy and Country Services Standards, Procurement and Financial Management Department Expectations This webinar

More information

C A R I B B E A N C O M M U N I T Y C L I M A T E C H A N G E C E N T E R ( C C C C C ) REQUEST FOR PROPOSAL

C A R I B B E A N C O M M U N I T Y C L I M A T E C H A N G E C E N T E R ( C C C C C ) REQUEST FOR PROPOSAL C A R I B B E A N C O M M U N I T Y C L I M A T E C H A N G E C E N T E R ( C C C C C ) REQUEST FOR PROPOSAL Household Baseline Survey, Bartica, Guyana Contract #29/2017/ Italian Government /CCCCC October

More information

Loan Administration Change Initiative (LACI) Implementation Handbook

Loan Administration Change Initiative (LACI) Implementation Handbook Loan Administration Change Initiative (LACI) Implementation Handbook Preface This Handbook sets forth the main concepts of the Loan Administration Change Initiative (LACI) and provides guidance to Bank

More information

DESK REVIEW UNDP AFGHANISTAN OVERSIGHT OF THE MONITORING AGENT OF THE LAW AND ORDER TRUST FUND FOR AFGHANISTAN

DESK REVIEW UNDP AFGHANISTAN OVERSIGHT OF THE MONITORING AGENT OF THE LAW AND ORDER TRUST FUND FOR AFGHANISTAN UNITED NATIONS DEVELOPMENT PROGRAMME DESK REVIEW OF UNDP AFGHANISTAN OVERSIGHT OF THE MONITORING AGENT OF THE LAW AND ORDER TRUST FUND FOR AFGHANISTAN Report No. 1310 Issue Date: 9 October 2014 Table of

More information

REPORT 2016/038 INTERNAL AUDIT DIVISION. Audit of the Office for the Coordination of Humanitarian Affairs operations in South Sudan

REPORT 2016/038 INTERNAL AUDIT DIVISION. Audit of the Office for the Coordination of Humanitarian Affairs operations in South Sudan INTERNAL AUDIT DIVISION REPORT 2016/038 Audit of the Office for the Coordination of Humanitarian Affairs operations in South Sudan Overall results relating to the effective management of operations in

More information

Proposed International Standard on Auditing. Review of Interim Financial Information Performed by the Auditor of the Entity.

Proposed International Standard on Auditing. Review of Interim Financial Information Performed by the Auditor of the Entity. IFAC International Auditing and Assurance Standards Board June 2003 Exposure Draft Response Due Date September 30, 2003 Proposed International Standard on Auditing Review of Interim Financial Information

More information

Contact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué Issy-les-Moulineaux

Contact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué Issy-les-Moulineaux Contact address: Global Food Safety Initiative Foundation c/o The Consumer Goods Forum 22/24 rue du Gouverneur Général Eboué 92130 Issy-les-Moulineaux France Secretariat email: gfsinfo@theconsumergoodsforum.com

More information

Armenia: Infrastructure Sustainability Support Program

Armenia: Infrastructure Sustainability Support Program Technical Assistance Report Project Number: 46220 Policy and Advisory Technical Assistance (PATA) December 2012 Armenia: Infrastructure Sustainability Support Program The views expressed herein are those

More information

Support to Farmers Organisations in Africa Programme (SFOAP) Main Phase Start-up Workshop Fiduciary Aspects Addis Ababa, March 2013

Support to Farmers Organisations in Africa Programme (SFOAP) Main Phase Start-up Workshop Fiduciary Aspects Addis Ababa, March 2013 Support to Farmers Organisations in Africa Programme (SFOAP) Main Phase Start-up Workshop Fiduciary Aspects Addis Ababa, 12-15 March 2013 1 FM Seminar Overview FM and Fiduciary Responsibilities Overview;

More information

INTERNATIONAL PAPER COMPANY

INTERNATIONAL PAPER COMPANY INTERNATIONAL PAPER COMPANY AUDIT AND FINANCE COMMITTEE CHARTER (Amended and Restated as of December 12, 2017) Purpose and Role of Audit and Finance Committee The Audit and Finance Committee (the Committee

More information

Revenue Mobilization Program for Results: VAT Improvement Program (VIP) (P129770)

Revenue Mobilization Program for Results: VAT Improvement Program (VIP) (P129770) Public Disclosure Authorized SOUTH ASIA Bangladesh Governance Global Practice Requesting Unit: SACBD Responsible Unit: GGOES IBRD/IDA Program-for-Results Financing FY 2014 Team Leader(s): Furqan Ahmad

More information

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS Strengthening Public Financial Resource Management through Information and Communication Systems Technology Systems (TRTA MON 51084) OUTLINE TERMS OF REFERENCE FOR CONSULTANTS 1. The transaction technical

More information

Corporate Governance of Federally-Regulated Financial Institutions

Corporate Governance of Federally-Regulated Financial Institutions Draft Guideline Subject: -Regulated Financial Institutions Category: Sound Business and Financial Practices Date: I. Purpose and Scope of the Guideline The purpose of this guideline is to set OSFI s expectations

More information

Terms of Reference for Financial Audit of Implementing Partners. UNICEF Nigeria Country Office Expenditures

Terms of Reference for Financial Audit of Implementing Partners. UNICEF Nigeria Country Office Expenditures Terms of Reference for Financial Audit of Implementing Partners UNICEF Nigeria Country Office 2012-2013 Expenditures A. Background and Scope of Audit Harmonized Approach to Cash Transfer (HACT) is a response

More information

UNICEF Moldova. Terms of Reference

UNICEF Moldova. Terms of Reference UNICEF Moldova Terms of Reference Individual Consultancy on Public Finance for Development of the National Action Plan for Gradual Implementation of the Sanitary and Hygiene Norms for Preschools Duration

More information

Joint Partnership Arrangement

Joint Partnership Arrangement Joint Partnership Arrangement Concerning Common Arrangements for Joint Support to the Health Strategic Plan 2008-2015 between the Royal Government of Cambodia and the 2nd Health Sector Support Program

More information

BANK DIRECTIVE. Procurement in IPF and Other Operational Procurement Matters. Bank Access to Information Policy Designation Public

BANK DIRECTIVE. Procurement in IPF and Other Operational Procurement Matters. Bank Access to Information Policy Designation Public BANK DIRECTIVE Procurement in IPF and Other Operational Procurement Matters Bank Access to Information Policy Designation Public Catalogue Number [To be assigned by the P&PF Administrator upon issuance]

More information

Audit Committee Charter

Audit Committee Charter Audit Committee Charter Updated February 23, 2017 Membership and Meetings Membership The Committee shall be comprised of no fewer than three members as appointed by the Board of Directors upon recommendation

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism the European Economic Area (EEA) Financial Mechanism 2014-2021 Adopted by the EEA Financial Mechanism Committee pursuant to Article 10.5 of Protocol 38c to the EEA Agreement on 8 September 2016 and confirmed

More information

FM Harmonization Frequently Asked Questions August 2013

FM Harmonization Frequently Asked Questions August 2013 FM Harmonization Frequently Asked Questions August 2013 The harmonization of Financial Management (FM) arrangements by Development Partners (DPs) can assist in reducing the burden of multiple FM systems

More information

FINANCE CONSULTANT FOR ASEAN COOPERATIVE PROJECT ON FINANCING MECHANISMS DESIGN FOR ENERGY EFFICIENCY AND CONSERVATION (EE&C) PROJECT IMPLEMENTATION

FINANCE CONSULTANT FOR ASEAN COOPERATIVE PROJECT ON FINANCING MECHANISMS DESIGN FOR ENERGY EFFICIENCY AND CONSERVATION (EE&C) PROJECT IMPLEMENTATION Call for Expert ASEAN Centre for FINANCE CONSULTANT FOR ASEAN COOPERATIVE PROJECT ON FINANCING MECHANISMS DESIGN EFFICIENCY AND CONSERVATION (EE&C) PROJECT IMPLEMENTATION About ACE Established on 1 January

More information

PROCUREMENT POLICIES AND PROCEDURES

PROCUREMENT POLICIES AND PROCEDURES PROCUREMENT POLICIES AND PROCEDURES Table of Contents INTRODUCTION... 2 I. GENERAL CONSIDERATIONS... 2 Borrower/Grantee Responsibility... 2 Planning... 2 Applicability... 3 Eligibility... 3 Advance Contracting

More information

ADOPTED AS OF MARCH 30, 2017

ADOPTED AS OF MARCH 30, 2017 CHARTER OF THE AUDIT COMMITTEES OF THE BOARDS OF TRUSTEES OF FS GLOBAL CREDIT OPPORTUNITIES FUND, FS GLOBAL CREDIT OPPORTUNITIES FUND A, FS GLOBAL CREDIT OPPORTUNITIES FUND D, FS GLOBAL CREDIT OPPORTUNITIES

More information

Standard Request for Proposals Selection of Consultants

Standard Request for Proposals Selection of Consultants STANDARD PROCUREMENT DOCUMENTS Standard Request for Proposals Selection of Consultants Caribbean Development Bank October 2011 Foreword 1. This Standard Request for Proposals ( SRFP ) has been prepared

More information

Institutional Strengthening for Aviation Regulation

Institutional Strengthening for Aviation Regulation Technical Assistance Report Project Number: 43429 Regional capacity development technical assistance (R-CDTA) December 2010 Institutional Strengthening for Aviation Regulation The views expressed herein

More information

IAASB EXPOSURE DRAFT OF INTERNATIONAL STANDARD ON AUDITING 550 (REVISED) ON RELATED PARTIES

IAASB EXPOSURE DRAFT OF INTERNATIONAL STANDARD ON AUDITING 550 (REVISED) ON RELATED PARTIES ED of proposed International Standard on Auditing 550 (Revised) Related Parties January 2006 To: Members of the Hong Kong Institute of CPAs All other interested parties IAASB EXPOSURE DRAFT OF INTERNATIONAL

More information

Position Title: Accountable and reporting to: PROCUREMENT SPECIALIST Project Manager - Somalia ICT Sector Support Project:

Position Title: Accountable and reporting to: PROCUREMENT SPECIALIST Project Manager - Somalia ICT Sector Support Project: TERMS OF REFERENCE Position Title: Accountable and reporting to: PROCUREMENT SPECIALIST Project Manager - Somalia ICT Sector Support Project: 1.0 Background: The ICT Sector Unit of the World Bank Group

More information

TERMS OF REFERENCE. Investec Limited Group Audit Committee

TERMS OF REFERENCE. Investec Limited Group Audit Committee TERMS OF REFERENCE Investec Limited Group Audit Committee Overview The Audit Committee (the Committee) of Investec Limited and subsidiaries, being the Investec Limited Group (the Group) is mandated by

More information

NORTHERN TRUST CORPORATION AUDIT COMMITTEE CHARTER

NORTHERN TRUST CORPORATION AUDIT COMMITTEE CHARTER NORTHERN TRUST CORPORATION AUDIT COMMITTEE CHARTER Effective October 20, 2009 (Supersedes the Audit Committee Charter Adopted October 21, 2008) The By-laws of Northern Trust Corporation (the Corporation

More information

Annual Report of the Audit Committee

Annual Report of the Audit Committee Executive Board Annual Session Rome, 13 17 June 2016 Distribution: General Date: 13 May 2016 Original: English Agenda Item 6 WFP/EB.A/2016/6-D/1/Rev.2 Resource, Financial and Budgetary Matters For consideration

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to

More information

DRAFT REPORT 2011/2217(DEC)

DRAFT REPORT 2011/2217(DEC) EUROPEAN PARLIAMT 2009-2014 Committee on Budgetary Control 06.02.2012 2011/2217(DEC) DRAFT REPORT on discharge in respect of the implementation of the budget of the European Environment Agency for the

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.02 Page 1 of 2 PROJECT ADMINISTRATION MISSIONS A. Introduction 1. ADB missions dispatched for loan and technical assistance (TA) project administration are classified

More information

Tamil Nadu Project Agreement

Tamil Nadu Project Agreement Public Disclosure Authorized OFFICIAL DOCUMENTS Public Disclosure Authorized LOAN NUMBER 8488-IN Tamil Nadu Project Agreement (Tamil Nadu Sustainable Urban Development Project) Public Disclosure Authorized

More information

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Department of Fisheries Ministry of Natural Resources Teone, Funafuti TUVALU Email: proptuv@gmail.com / proptuv@tuvalufisheries.tv

More information

HIRE OF A CONSULTANCY FIRM TO CONDUCT AN EXTERNAL AUDIT OF THE WORLD BANK- FUNDED PROJECTS FOR FINANCIAL YEARS &

HIRE OF A CONSULTANCY FIRM TO CONDUCT AN EXTERNAL AUDIT OF THE WORLD BANK- FUNDED PROJECTS FOR FINANCIAL YEARS & HIRE OF A CONSULTANCY FIRM TO CONDUCT AN EXTERNAL AUDIT OF THE WORLD BANK- FUNDED PROJECTS FOR FINANCIAL YEARS 2016-2017 & 2018-2019 TERMS OF REFERENCE Funded by the World Bank December 2016 TDRs_ Audits

More information

Definition. World Bank Seminar on Procurement November 15-18, 2010, Kyiv, Ukraine. Consultant Services

Definition. World Bank Seminar on Procurement November 15-18, 2010, Kyiv, Ukraine. Consultant Services World Bank Seminar on Procurement November 15-18, 2010, Kyiv, Ukraine Consultant Services 1 Definition 1.3 For the purpose of these Guidelines, the term consultants includes a wide variety of private and

More information

In accordance with Law no. 297/2004 and Regulation CNVM no. 1/2006. Registered office: Targu Mures, Mures County, 35 Voinicenilor Street

In accordance with Law no. 297/2004 and Regulation CNVM no. 1/2006. Registered office: Targu Mures, Mures County, 35 Voinicenilor Street To, The Financial Supervision Authority The Bucharest Stock Exchange THE CURRENT REPORT SC ROMCAB SA In accordance with Law no. 297/2004 and Regulation CNVM no. 1/2006 Date of the report 26 January 2016

More information

Liaoning Project Agreement

Liaoning Project Agreement Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 7918-CN Public Disclosure Authorized Liaoning Project Agreement (Liaoning and Shandong Technical and Vocational Education and Training Project) Public

More information

CHARTER of the AUDIT COMMITTEE of the BOARD of DIRECTORS of TYSON FOODS, INC.

CHARTER of the AUDIT COMMITTEE of the BOARD of DIRECTORS of TYSON FOODS, INC. I. PURPOSE CHARTER of the AUDIT COMMITTEE of the BOARD of DIRECTORS of TYSON FOODS, INC. The primary function of the Audit Committee (the "Committee") is to assist the Board of Directors of Tyson Foods,

More information

ERO Enterprise Self- Logging Program

ERO Enterprise Self- Logging Program ERO Enterprise Self- Logging Program February 1, 2016 NERC Report Title Report Date I Introduction This document provides a description of the ERO Enterprise Self-Logging Program. Registered entities found

More information

Group Audit Committee Terms of Reference

Group Audit Committee Terms of Reference Group Audit Committee Terms of Reference Document Title: Group Audit Committee Terms of Reference Approved by Court: 27 July 2016 Review frequency: Annually BOIG Classification: Red Group Audit Committee

More information

INTERREG - IPA CBC ROMANIA-SERBIA PROGRAMME

INTERREG - IPA CBC ROMANIA-SERBIA PROGRAMME ANTI-FRAUD STRATEGY INTERREG - IPA CBC ROMANIA-SERBIA PROGRAMME VERSION 2016 1 TABLE OF CONTENTS PRINCIPLE 4 FOREWORD 4 LEGAL BASIS 4 DEFINITIONS 5 I. GENERAL CONSIDERATIONS 5 I.1. AIM 5 I.2. MISSION 6

More information

Audit and Risk Committee Charter

Audit and Risk Committee Charter Original effective date: 07/14/2014 Date of last approval: 03/24/2016 Approved by: Board of Directors Business unit: HealthEquity, Inc. TABLE OF CONTENTS 1 RESPONSIBILITIES AND DUTIES... 2 2 MEMBERSHIP...

More information

Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.266 dated September 2014 A8.

Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.266 dated September 2014 A8. Prepared by Office of Procurement and Real Property Management. This replaces Administrative Procedure No. A8.266 dated September 2014 A8.266 A8.266 Purchasing Cards 1. Purpose A8.200 Procurement July

More information

Project Reporting: GCF Legal Agreements and GCF Monitoring & Evaluation

Project Reporting: GCF Legal Agreements and GCF Monitoring & Evaluation Project Reporting: GCF Legal Agreements and GCF Monitoring & Evaluation ARMENIA De-risking and Scaling-up Investment in Energy Efficient Building Retrofits UNDP-GCF Project INCEPTION WORKSHOP Cynthia Page,

More information

Decision on the method of exercising supervision of credit institutions and imposing supervisory measures. Article 1

Decision on the method of exercising supervision of credit institutions and imposing supervisory measures. Article 1 Pursuant to Article 175, paragraph (3) of the Credit Institutions Act (Official Gazette 159/2013) and Article 43, paragraph (2) item (9) of the Act on the Croatian National Bank (Official Gazette 75/2008

More information

European Commission Directorate General for Development and Cooperation - EuropeAid

European Commission Directorate General for Development and Cooperation - EuropeAid European Commission Directorate General for Development and Cooperation - EuropeAid Practical guide to procedures for programme estimates (project approach) Version 4.0 December 2012 CONTENTS 1. INTRODUCTION...

More information

MARTIN MARIETTA MATERIALS, INC. AUDIT COMMITTEE CHARTER

MARTIN MARIETTA MATERIALS, INC. AUDIT COMMITTEE CHARTER MARTIN MARIETTA MATERIALS, INC. AUDIT COMMITTEE CHARTER The Audit Committee will, except when such powers are by statute or the Articles of Incorporation or the Bylaws reserved to the full Board or delegated

More information

Worcestershire County Council: Use of External Consultants

Worcestershire County Council: Use of External Consultants Worcestershire County Council: Use of External Consultants Risk and Assurance Services Providing assurance on the management of risks Report status Final Report date 30th November 2015 Prepared by Christopher

More information

AUDIT COMMITTEE CHARTER. Purpose. Composition

AUDIT COMMITTEE CHARTER. Purpose. Composition AUDIT COMMITTEE CHARTER Purpose The Audit Committee (the Committee ) is established by the Board of Directors (the Board ) primarily for the purpose of overseeing the accounting and financial reporting

More information

General principles and indicative list of eligible costs covered under GCF fees and project management costs

General principles and indicative list of eligible costs covered under GCF fees and project management costs General principles and indicative list of eligible costs covered under GCF fees and project management costs This document is as adopted by the Board in decision B.19/09. It was sent to the Board for consideration

More information

Validation of Zambia Validation Report Adam Smith International Independent Validator 10 August 2017

Validation of Zambia Validation Report Adam Smith International Independent Validator 10 August 2017 1. EXECUTIVE SUMMARY Validation of Zambia Validation Report Adam Smith International Independent Validator 10 August 2017 The Government of Zambia committed to implementing the EITI in 2008 and a multi-stakeholder

More information

MASHRUUCA TAAKULAYNTA ISGAARSIINTA ICT SECTOR SUPPORT PROJECT (P152358)

MASHRUUCA TAAKULAYNTA ISGAARSIINTA ICT SECTOR SUPPORT PROJECT (P152358) DOWLADDA PUNTLAND EE SOOMAALIYA PUNTLAND STATE OF SOMALIA JAMHUURIYADDA FEDRAALKA SOOMAALIYA MASHRUUCA TAAKULAYNTA ISGAARSIINTA ICT SECTOR SUPPORT PROJECT (P152358) WasaaraddaWarfaafintaIsgaarsiintaBoostadaHiddaha&Dhaqanka

More information

AUDIT COMMITTEE CHARTER

AUDIT COMMITTEE CHARTER AUDIT COMMITTEE CHARTER The Audit Committee of the Board of Trustees (the Committee ) of Sierra Total Return Fund (the Fund ) monitors the integrity of the financial statements of the Fund and the qualifications,

More information

(Punjab Barrages Improvement Phase-II Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. and PROVINCE OF PUNJAB

(Punjab Barrages Improvement Phase-II Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. and PROVINCE OF PUNJAB Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 7900-PK Public Disclosure Authorized Project Agreement (Punjab Barrages Improvement Phase-II Project) Public Disclosure Authorized between INTERNATIONAL

More information

JORDAN. Terms of Reference

JORDAN. Terms of Reference JORDAN Terms of Reference Jordan: Strengthening municipal financial management systems to sustain service delivery in municipalities affected by the refugee crisis Assessment of Municipal Public Financial

More information

International Bank for Reconstruction and Development International Development Association

International Bank for Reconstruction and Development International Development Association Report No. 49153-AL International Bank for Reconstruction and Development International Development Association Albania - Integrated Coastal Zone Management and Clean-Up Project Progress Report on the

More information

SYSCO CORPORATION AUDIT COMMITTEE CHARTER

SYSCO CORPORATION AUDIT COMMITTEE CHARTER APPROVED MAY 2013 SYSCO CORPORATION AUDIT COMMITTEE CHARTER I. Organization The Board of Directors of Sysco Corporation shall establish an Audit Committee whose members shall be appointed by the Board

More information

FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS)

FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) OPERATIONS POLICY AND COUNTRY SERVICES APRIL 2, 2002 FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS) CONTENTS Page I. Introduction..1 II.

More information

Terms of Reference (TOR) External Value for Money Audit (VFM) Textbooks Production/Distribution. Danish Funded Education Programmes ( )

Terms of Reference (TOR) External Value for Money Audit (VFM) Textbooks Production/Distribution. Danish Funded Education Programmes ( ) 1. Background Terms of Reference (TOR) External Value for Money Audit (VFM) Textbooks Production/Distribution Danish Funded Education Programmes (2003-2013) 1.1. Background of the project Denmark has supported

More information

QUESTIONNAIRE ON FISCAL INSTITUTIONS [COUNTRY]

QUESTIONNAIRE ON FISCAL INSTITUTIONS [COUNTRY] QUESTIONNAIRE ON FISCAL INSTITUTIONS [COUNTRY] This questionnaire is designed to gather basic information on fiscal institutions and practices as a basis for review of a country's fiscal management system

More information

South Sudan Common Humanitarian Fund (South Sudan CHF) Terms of Reference (TOR)

South Sudan Common Humanitarian Fund (South Sudan CHF) Terms of Reference (TOR) South Sudan Common Humanitarian Fund (South Sudan CHF) Terms of Reference (TOR) 14 February 2012 List of Acronyms AA Administrative Agent AB Advisory Board CAP Consolidated Appeal Process CHF Common Humanitarian

More information

WSSCC, Global Sanitation Fund (GSF)

WSSCC, Global Sanitation Fund (GSF) Annex I WSSCC, Global Sanitation Fund (GSF) Terms of Reference Country Programme Monitor (CPM) BURKINA FASO 1 Background The Water Supply and Sanitation Collaborative Council (WSSCC) was established in

More information

not have participated in the preparation of the Company s or any of its subsidiaries financial statements at any time during the past three years;

not have participated in the preparation of the Company s or any of its subsidiaries financial statements at any time during the past three years; SABRE CORPORATION AUDIT COMMITTEE CHARTER I. Statement of Purpose The Audit Committee (the Committee ) is a standing committee of the Board of Directors (the Board ). The purpose of the Committee is to

More information

EXTERNAL END OF PROJECT PERFORMANCE EVALUATION

EXTERNAL END OF PROJECT PERFORMANCE EVALUATION EXTERNAL END OF PROJECT PERFORMANCE EVALUATION 1. Background TERMS OF REFERENCE PT. Rainforest Alliance (RA) is leading a consortium group in implementing the Cocoa Revolution: High-Yielding Climate Smart

More information

AUDIT COMMITTEE CHARTER. Purpose

AUDIT COMMITTEE CHARTER. Purpose AUDIT COMMITTEE CHARTER Purpose The Audit Committee (the Committee ) is appointed by the Board of Directors of Cabot Corporation (the Company ) to (a) appoint and oversee the performance of the independent

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

Modernization of WBC universities through strengthening of structures and services for knowledge transfer, research and innovation

Modernization of WBC universities through strengthening of structures and services for knowledge transfer, research and innovation Internal Monitoring Report Project Acronym: WBCInno strengthening of Project full title: structures and services for knowledge transfer, research and innovation Project No: 530213-TEMPUS-1-2012-1-RS-TEMPUS-JPHES

More information

Specific Agreement on Research Collaboration between Sweden and Makerere University during the period 3 November June 2020

Specific Agreement on Research Collaboration between Sweden and Makerere University during the period 3 November June 2020 Specific Agreement on Research Collaboration between Sweden and Makerere University during the period 3 November 2015 30 June 2020 between The Uganda state owned Makerere University ( Mak ) and The Swedish

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020366 Public Disclosure Authorized Public Disclosure Authorized Project ID P107666 Country Peru Project

More information

EA-0/09: Procedure. For. Internal Audits. Publication Reference PURPOSE. This procedure describes the process for EA internal audits.

EA-0/09: Procedure. For. Internal Audits. Publication Reference PURPOSE. This procedure describes the process for EA internal audits. Publication Reference EA-0/09: 2015 Procedure For Internal Audits PURPOSE This procedure describes the process for EA internal audits. October 2015_rev01 1 of 9 Authorship This document has been written

More information

Internal, Operational, and Compliance Auditing

Internal, Operational, and Compliance Auditing CHAPTER 21 Internal, Operational, and Compliance Auditing Review Questions 21 1 Internal auditing may be defined as an independent, objective assurance and consulting activity designed to add value and

More information

Danida Business Finance. Rules for Procurement

Danida Business Finance. Rules for Procurement Danida Business Finance Rules for Procurement March 2017 1 The present rules concern procurement supported by Danida Business Finance (DBF), Ministry of Foreign Affairs of Denmark. They are intended to

More information

REQUIRED DOCUMENT FROM HIRING UNIT

REQUIRED DOCUMENT FROM HIRING UNIT Terms of reference GENERAL INFORMATION Title: Finance Management Technical Assistance Consultant for the Global Fund Principal Recipient Aisyiyah (National Consultant) Project Name: Management and Technical

More information

Financial Audit Manual

Financial Audit Manual GAO/PCIE United States General Accounting Office President s Council on Integrity and Efficiency Financial Audit Manual Update to Part II - Tools GAO-03-466G Update to Part II [This page intentionally

More information

POLICY ISSUES. Agenda item 5 WFP ANTI-FRAUD AND ANTI-CORRUPTION POLICY. For information*

POLICY ISSUES. Agenda item 5 WFP ANTI-FRAUD AND ANTI-CORRUPTION POLICY. For information* Executive Board Annual Session Rome, 7 11 June 2010 POLICY ISSUES Agenda item 5 For information* WFP ANTI-FRAUD AND ANTI-CORRUPTION POLICY E Distribution: GENERAL WFP/EB.A/2010/5-B 24 May 2010 ORIGINAL:

More information

Benin 27 August 2015

Benin 27 August 2015 Benin 27 August 2015 PAGE 1 OF 6 (Please submit completed form to countries@gcfund.org) Executive Summary(in one page) Country (or region) Benin Submission Date 27/08/2015 NDA or Focal Point Directorate

More information

PEFA Handbook. Volume III: Preparing the PEFA Report FINAL VERSION

PEFA Handbook. Volume III: Preparing the PEFA Report FINAL VERSION PEFA Handbook Volume III: Preparing the PEFA Report FINAL VERSION March, 2016 PEFA Secretariat Washington DC USA 1 P age Preface PEFA 2016 HANDBOOK About PEFA The Public Expenditure and Financial Accountability

More information