Development Planning Division Technical Document Series No. 1. Guidelines for environmental appraisal at the DBSA. Final Draft 1 March 2010

Size: px
Start display at page:

Download "Development Planning Division Technical Document Series No. 1. Guidelines for environmental appraisal at the DBSA. Final Draft 1 March 2010"

Transcription

1 Guidelines for environmental appraisal at the DBSA Final Draft 1 March 2010 Version

2 Suggested citation Development Planning Division Guidelines for environmental appraisal at the DBSA. Technical Document Series No.1, DBSA: Midrand. Published by Development Planning Division Development Bank of Southern Africa PO Box 1234 Halfway House 1685 South Africa Telephone: Telefax: Intellectual Property and Copyright Development Bank of Southern Africa Limited This document is part of the knowledge products and services of the Development Bank of Southern Africa Limited and is therefore the intellectual property of the Development Bank of Southern Africa. All rights are reserved. This document may be reproduced for non-profit and teaching purposes. Whether this document is used or cited in part or in its entirety, users are requested to acknowledge this source. Please use the suggested citation given above. Legal Disclaimer In the preparation of this document, every effort was made to offer the most current, correct and clearly expressed information possible. Nonetheless, inadvertent errors can occur, and applicable laws, rules and regulations may change. The Development Bank of Southern Africa makes its documentation available without warranty of any kind and accepts no responsibility for its accuracy or for any consequences of its use. Series Editor: Andrew Paterson Series Publication Coordinator: Lyn Sumners ISBN: Page 2

3 Contents 1. Introduction Overview Purpose of the guidelines Scope of the guidelines 6 2. Environmental appraisal The role of environmental appraisal Principles of environmental assessment Environmental appraisal and sustainable development 8 3. Overarching environmental issues DBSA policies for the environmental appraisal module The DBSA investment process Integration with other appraisal modules Information required for environmental appraisals Responsibility for environmental appraisals Risk categorisation of projects Environmental appraisal in SADC Public disclosure and participation Environmental appraisal guidelines Overview Initial screening Site visits Environmental risk appraisal of projects Environmental risk appraisal of programmes Financial intermediaries Agency agreements Other DBSA investment products Loan conditions Loan negotiations Project implementation Review process Review procedures Responsibilities 26 Page 3

4 6. References 26 Appendix 1: Extract from the National Environmental Management Act No. 107 of Appendix 2: Criteria for assessing institutional capacity for environmental management 30 Appendix 3: Format for environmental assessment of existing infrastructure projects 31 Appendix 4: Categories of project risk 33 Category 1: High risk 33 Category 2: Medium risk 34 Category 3: Low risk 34 Category 4: Financial intermediary 35 Appendix 5: Project, programme and consolidated reports Project reports Programme reports Consolidated project and programme reports 38 Appendix 6: Contents of EIA reports 39 Appendix 7: Guidance note for EIA reviews 41 Appendix 8: Terms of reference for consultants 52 Appendix 9: Sensitive geographic areas and environmental sites 53 Appendix 10: Environmental requirements for financial intermediaries 54 Tables 55 Abbreviations 55 Terms and definitions 55 Page 4

5 1. Introduction 1.1 Overview The Development Bank of Southern Africa (DBSA) is a development finance institution that finances the creation of infrastructure in South Africa and the southern African region. Although wholly owned by the government of South Africa, the DBSA serves all of the member countries of the Southern African Development Community (SADC). The Development Bank of Southern Africa Act, No. 13 of 1997, defines the primary purpose of the Bank as promoting economic development and growth, human resource development and institutional capacity building by mobilising financial and other resources from the national and international private and public sectors for sustainable developmental programmes and projects. This requires it, among other objectives, to do the following: z Appraise, plan and monitor the implementation of development programmes and projects. z Fund or mobilise funding, in line with the regulations to the Act, for initiatives aimed at minimising or mitigating the environmental impact of development programmes or projects. In terms of these provisions, the DBSA is committed to promoting sustainable development and building the institutional capacity of its borrowers. It recognises that the integrated and sustainable management of the environment, now and in the future, is the basis for sustainable development in all areas of human activity. In terms of this commitment, the DBSA developed a policy framework for environmental appraisal, which comprises the environmental policy of the DBSA Group and the procedural framework outlined in this document. All programmes and projects proposed for DBSA support must undergo environmental appraisals based on the guidelines outlined in this document. These guidelines are intended to guide and assist environmental analysts and specialists in producing consistent and high-quality environmental appraisals to enhance the DBSA s decision-making and, hence, sustainable development. For ease of use, in the rest of this document, references to projects should be understood to include programmes, unless otherwise indicated. Also, the terms environmental analyst and environmental specialist are used interchangeably, unless otherwise specified. 1.2 Purpose of the guidelines The purpose of these environmental appraisal guidelines is to facilitate the application of the DBSA s internal environmental appraisal process; they are designed to ensure the easy and consistent application of the environmental appraisal module. The guidelines allow the early, systematic and Page 5

6 structured consideration of environmental issues in proposed projects, thereby ensuring that they are environmentally sound and in line with the Bank s mandate and policies. In addition, the guidelines will contribute to building the capacity of environmental specialists in the Bank and in financial intermediaries supported by the DBSA. 1.3 Scope of the guidelines The environmental appraisal guidelines in this document cover all projects supported by the Bank, whether directly, through financial intermediaries or in terms of agency agreements. This document also includes specific appraisal requirements for operations outside South Africa. Technical assistance grants for studies or projects that do not involve the provision of infrastructure are excluded, particularly as these have no impact on the environment. However, the responsible environmental analyst must still carefully review the scope or terms of reference of all projects to ensure alignment with the Bank s mandate and compliance with its principles and environmental policy. 2. Environmental appraisal 2.1 The role of environmental appraisal The overarching purpose of the environmental appraisal module is to: z Ensure that projects supported by the DBSA are environmentally sound and sustainable. z Identify and evaluate the environmental risks associated with them. z Ensure that the borrowers implement appropriate mitigation measures to address such risks. The DBSA follows a lifecycle approach to projects by assisting borrowers in designing an appropriate system for environmental management and helping to build their capacity to fulfil their environmental obligations. The DBSA does not, however, manage the environmental concerns associated with any project on behalf of the borrower. The borrower remains completely responsible for managing these and, in its ongoing interaction with borrowers, the DBSA avoids creating any dependency by the borrower in this regard. In the appraisal process, the DBSA aims to achieve the following: z Identify opportunities to maximise the developmental and environmental benefits of projects and promote sustainable development. z Assist management in deciding whether to support a project, based on its environmental risks. z Minimise the environmental risks and liabilities of both the project and the DBSA. Page 6

7 z Assist the borrower in obtaining any legislated environmental authorisations that may be necessary. z Assist borrowers in building their environmental capacity. z Identify ways to prevent, minimise, mitigate or compensate for the environmental risks and/or impact associated with projects. z Assist in the development of conditions to be included in the loan agreement with borrowers. The environmental appraisal module at the Bank is, therefore, a decision-making tool that supports the DBSA in managing its business risks and increasing its developmental impact. 2.2 Principles of environmental assessment The principles underpinning an environmental assessment, whether a strategic or environmental impact assessment (EIA), are set out in section 2 of the National Environmental Management Act (NEMA), No. 107 of 1998, and reproduced in Appendix 1. Section 2(3) of the Act specifically requires development to be socially, environmentally and economically sustainable. The DBSA, as an organ of the state, is bound by the principles established in this statute. It uses the definition of the environment provided in section 1 of the Act, which reads as follows: Environment means the surroundings within which humans exist and that are made up of: (i) (ii) (iii) (iv) the land, water and atmosphere of the earth micro-organisms, plant and animal life any part or combination of the (i) and (ii) and the interrelationships among and between them the physical, chemical, aesthetic and cultural properties and conditions of the foregoing that influence human health and well-being. This definition is also in line with the national standard on the environmental assessment of sites and organisations, SANS 14015:2003/ISO 14015:2001, which defines the environment as surroundings in which an organisation operates, including air, water, land, natural resources, flora, fauna, humans, and their interrelation. Although the NEMA and SANS definitions include people as part of the environment, the DBSA appraises the socio-economic impact of its projects in the social appraisal module. This inevitably results in overlaps between the social and environmental appraisal modules, and the results of these modules must be integrated before the findings of all six of the appraisal modules (the other four being technical, economic, financial and institutional) are consolidated. Page 7

8 2.3 Environmental appraisal and sustainable development The guiding principle of the appraisal process is to ensure that Bank-supported interventions are economically, socially and environmentally sustainable, in accordance with the principles of sustainable development outlined in the NEMA. Integral to these principles, particularly the precautionary principle, is the requirement that the environmental risk of a proposed project must be properly assessed and managed. Four sources of environmental risk must be considered in environmental appraisals. These are: z Environmental impact: Risks emerging from the nature and impact of the project could include, for example, the potential of a waste disposal site to pollute groundwater, or of road fill contaminated with heavy metals to lead to toxic runoff. z Legal requirements: Non-compliance with the legislative regime is a significant source of risk. Legal risks can include siting requirements such as planning authorisation and EIA approvals, operating requirements such as water permits, and environmental liability regimes that link the proponents of a project to any existing or future contamination. z Institutional capacity: Any limitations of the capacity of an institution to fulfil environmental requirements during the implementation, operation and maintenance of a project can present a significant risk. z Public and political concerns: Environmental issues have a high potential for reputational risk and even conflict owing to public and political concerns. Environmental assessments are not limited to risks the Bank also appraises the environmental benefits of projects. In line with the Bank s policy and the sustainability principles, the appraisal process actively considers ways to improve environmental benefits, for instance by exploring alternatives that may have a larger positive impact on the environment. Appraisals of projects within South Africa are based on the NEMA principles. Appraisals of private sector projects outside of South Africa, especially those with a high environmental risk, must use international good practice on social and environmental assessment, particularly the Performance standards on social and environmental sustainability of the International Finance Corporation (2006). 3. Overarching environmental issues 3.1 DBSA policies for the environmental appraisal module The DBSA Board approved the current environmental policy in 2005 (see the DBSA website). This policy requires all Bank operations to be carried out in an environmentally and socially responsible manner, deriving the maximum environmental and social benefits. The policy is in line with the DBSA s commitments in terms of the UNEP Finance Initiative (in 2004, the DBSA became Page 8

9 a signatory to this initiative between the UNEP and the financial sector). The Initiative recognises that sustainable development depends on a positive interaction between socio-economic development and environmental protection, which balances the interests of the current and future generations. It views sustainable development as a collective responsibility of government, business and individuals, and requires financial institutions to adopt best practice in environmental management. In line with this commitment, projects can only qualify for DBSA support if they fully comply with the Bank s environmental policy and adhere to the procedural framework outlined in this document. The environmental policy outlines three fundamental principles of the appraisal process, namely: z Compliance with national and regional policies, legislative and regulatory requirements related to the environment, as well as any relevant international obligations z Stewardship of environmental products and services both within and outside the Bank z An environmental management system (EMS) that assists in improving the environmental performance of the Bank s investment portfolio In implementing these appraisal guidelines in line with the environmental policy, the following internal policies apply: z All projects being considered for support are subject to an environmental appraisal; this must be submitted to the project manager, in writing, according to the format outlined in this document. z The appraisal must be conducted by an environmental analyst, and such an analyst must therefore be on every project team that does appraisals. z All documentation and communication used and decisions taken in the appraisal must be clearly referenced and justified in the appraisal report. z The environmental specialist in the Advisory Unit must review all appraisal reports for high-risk and SADC programmes and projects, to provide input and share knowledge with other members of the Environmental CoP. z All projects in the high-risk category must have environmental management plans (EMPs) in line with the EIA process. z No environmental appraisal report can be changed without consultation with the relevant environmental analyst. z No funds can be disbursed without the appropriate authorisations from the regulatory authority; consequently, any requirement for an environmental authorisation or permit will be a suspensive condition in the loan agreement. z The DBSA will not fund a project if the environmental risk assessment remains high after mitigation. z Any conditionality pertaining to credit lines on projects must be identified and addressed in the appraisal. Page 9

10 3.2 The DBSA investment process The process flow for investment applications can broadly be divided into the following seven steps: 1. Process the application 2. Mobilise project resources and information 3. Recommend an investment proposition 4. Process the investment decision 5. Conclude the contract 6. Deliver implementation assistance 7. Project implementation completion The process is sequential and follows the phases of the lifecycle of the project. The length of this process depends on the nature and type of project and the institutional capacity of the client for environmental management. The primary elements of the investment process flow are described below: 1. Process the application: In this step, development needs are identified, a development intervention is conceptualised and an application is made to the DBSA for funding. After registering the application, the project manager screens it against the mandate of the Bank and requests a project team, including an environmental analyst, to be assigned. Using the available information, the environmental analyst determines the environmental risk category of the project and issues a request for any additional information required. 2. Mobilise project resources and information: Once established, the project team assists the borrower in the design and preparation of the project, if necessary. The environmental analyst assesses the adequacy of the information provided by the client and, where appropriate, assists the client in fulfilling the requirements outlined in this document. 3. Recommend an investment proposition: When all of the required information has been obtained, the project team undertakes a detailed appraisal of the sustainability of the proposed project, according to the appraisal guidelines for the six modules. At this stage, additional environmental information is analysed, particularly for medium- to high-risk projects (as per Appendix 4). The team s findings and recommendations provide the basis for a decision about providing investment assistance, as well as the terms and conditions for any investment loan. 4. Process the investment decision: After the completion of the appraisal, DBSA management reviews the investment appraisal report and its recommendations. Depending on the type and value of the project, the proposal serves at the Development Intervention Committee, Corporate Credit Committee or Board Investment Committee, where a decision is taken about support for the project. Page 10

11 5. Conclude the contract: Following the approval of the proposal by the relevant investment review committee, the contract is concluded with the client. This involves the negotiation and agreement on the primary terms and conditions of the loan agreement. Any environmental requirements suggested in the appraisal report will be part of the negotiations and, once agreed upon, included in the loan agreement as either suspensive or further terms and conditions. 6. Deliver implementation assistance: This process entails disbursing funding and monitoring the implementation of the project, according to the terms and conditions in the loan agreement. The DBSA monitors all projects under implementation to ensure full compliance with these terms and conditions, including environmental conditions. 7. Project implementation completion: Project completion reports review the results of the implementation, generate lessons learnt, and recommend surveillance or monitoring arrangements. The Bank continues to monitor the project for the duration of the loan term. The completion report includes a section on environmental performance, which reflects environmental compliance. Section 4 of this document details the procedural requirements for each of these steps. In view of the importance of the evaluation function, a separate and independent unit has been established to conduct evaluations. These studies compare the actual impact of the project, including on the environment, with the impact anticipated in the appraisal process, and assess the effectiveness of any mitigation measures. 3.3 Integration with other appraisal modules Unit managers, in conjunction with project managers, appoint members of the project team, generally from the same region. (In the Equity and Investment Banking and the Project Finance Units, however, the project manager selects the analysts.) Every project team must include an environmental analyst, as noted above, to conduct the environmental appraisal. To be effective, the environmental appraisal must be integrated with the full appraisal report and its findings aligned with those of the other appraisal modules. The environmental analyst should interact closely with the technical, institutional and social analysts. 3.4 Information required for environmental appraisals To expedite the environmental appraisal, the borrower should be informed as soon as possible about the information that the DBSA requires. The nature of the required information depends on the type of project and its initial risk categorisation. In some cases, the borrower may need advice about legal procedures for obtaining permits and other environmental authorisations. When assisting clients in this regard, the environmental analyst must Page 11

12 bear in mind the issue of environmental liability. The analyst may not recommend specific consultants to the borrower, intervene, or take steps to obtain permits on its behalf. Guidance may be given only on procedural requirements. The DBSA reserves the right to request additional information about the project at any time. Technical assistance may be offered to assist clients in obtaining all the information needed for the environmental appraisal. 3.5 Responsibility for environmental appraisals z The borrower: The borrower is responsible for environmental management of the project and, accordingly, for all the costs associated with the environmental assessment. The borrower must also provide adequate information in good time to allow the environmental analyst (and the team) to conduct a proper appraisal to facilitate decision-making. This information includes relevant environmental study reports, environmental permits or authorisations, and any other records deemed necessary for the appraisal. In addition, the borrower must allow reasonable access to the project site. It is imperative for the borrower to take the responsibility and ensure that the environmental appraisal leads to environmentally sound projects. z The DBSA: The Bank establishes a project appraisal team for every registered project application; in line with these guidelines, this team will include an environmental analyst. The specific tasks of this analyst include the following: Assess the early review report in conjunction with the project manager, screen the project and provide an initial risk categorisation. Inform the borrower about the environmental information required for the appraisal, based on the risk categorisation of the project. Conduct the environmental appraisal of the project in accordance with these procedural requirements. The environmental analyst may, at the request of the borrower, offer advice on the preparation of terms of reference for EIAs, legal procedures for obtaining permits, and the environmental management of the project. Further, the analyst may be requested to draw up terms of reference for external consultants to review, for example, an EIA or other technical reports. A proposed framework for such terms of reference is presented in Appendix 8. As noted, the analyst may not recommend specific consultants to the borrower, intervene, or obtain the relevant permits on its behalf. 3.6 Risk categorisation of projects Proposed projects are classified into four categories based on the type, location, sensitivity and size of the project, as well as the nature and intensity (or magnitude) of the environmental impact associated with the project. The purpose of this classification is to assist in decision-making during the appraisal process, and indicate what information or permits and authorisations may be required. Page 12

13 The categories are: Category 1: High risk A project in Category 1 is likely to have a significant and irreversible adverse impact on the environment, and could lead to significant changes in land use and in the social and biophysical environment. The DBSA requires an EIA for any project in this category, regardless of legislative or regulatory requirements. Note that South African law requires an EIA for all activities identified under section 21 of the Environment Conservation Act, No. 73 of 1989, and section 24(5) of the NEMA. In addition, the Bank requires all projects in this category to have an EMP in line with the EIA to ensure that environmental risks are properly mitigated. An EMP is a recognised tool that can provide assurance that the project proponent has made adequate provision for the mitigation of its environmental impacts. The Integrated Environmental Management (IEM) Information Series, No. 12 (DEAT, 2004a) reflects on methods and procedures for mitigating and monitoring environmental impact. It may assist DBSA staff in reviewing EIAs and related documents (including EMPs), as well as clients developing and implementing the EMP. Category 2: Medium risk A project in Category 2 has a potentially adverse impact on the environment, but less so than Category 1 projects. In this category, the country s legislative and regulatory requirements for EIAs apply. If the project is not a regulated activity, the requirements of the environmental assessment apply. However, the responsible analyst must still indicate the level of environmental assessment required. This may be an assessment of the site (facility) or organisation, a basic EIA or a full EIA, depending on the type of project or a combination of other factors, such as the sensitivity of the geographic area or natural environment. Category 3: Low risk A project in Category 3 is unlikely to have a significant adverse impact on the environment. Since these projects have no adverse impact on the natural environment, they are readily appraised with limited environmental information. However, they remain subject to a screening process similar to projects in the previous categories, in order to identify potential issues for further investigation. Page 13

14 Category 4: Financial intermediaries This category entails Bank investments through financial intermediaries. The funding is lent in turn to subprojects, some of which may have a significant adverse impact on the environment (see Appendix 10). The environmental analyst remains responsible for categorising all projects, regardless of category, and must also determine what environmental information is required for the appraisal. This must be appropriately motivated in the appraisal report. As a minimum requirement, the project must adhere to the legislative and regulatory requirements of the country where it will be implemented. To facilitate categorisation, an illustrative list of projects under each category is provided in Appendix 4; note that the list is not exhaustive. Finally, where a project involves the refinancing of existing infrastructure projects, the Bank requires a comprehensive assessment of the environmental performance of the organisation and the facility concerned for all Category 1 and 2 projects, even where these are not affected by the legislative and regulatory requirements for EIAs. The proposed approach to and format for assessment of existing infrastructure projects is presented in Appendix 3. An international standard for the environmental assessment of an organisation, SANS 14050:2003, provides additional guidance on the planning, implementation and reporting of such an assessment. 3.7 Environmental appraisal in SADC As noted, these environmental appraisal guidelines apply to all DBSA-supported projects, including in the rest of the SADC region. In the region, different countries have different approaches depending on their legislative regimes, and a project should be assessed against the legislative and regulatory requirements of the country concerned (Walmsely & Tshipala, 2007). If there is no enabling legislation for environmental assessment or effective regulations for implementing the provisions of the enabling legislation, the borrower will be required to implement a process based on the framework outlined in this document. The review process should be aligned to internationally recognised standards for environmental assessment. As indicated earlier, it is strongly recommended that all high-risk private sector projects outside South Africa be reviewed against the standards of the International Finance Corporation (2006). The standards cover the following issues: social and environmental assessment and management systems; labour and working conditions; pollution prevention and abatement; community health, safety and security; land acquisition and involuntary resettlement; biodiversity conservation and sustainable natural resource management; indigenous people; and cultural heritage. Page 14

15 The Bank will likewise apply international standards for environmental quality to projects in countries that lack legislative requirements to this effect. The main standard used is the Environmental, health, and safety (EHS) guidelines of the World Bank (2007), which provides technical guidance on good industry practice. Should borrowers argue for a different standard, a recommendation to this effect must to be based on specialist investigations, comprehensively documented in the EIA or environmental due diligence (EDD). To assist the analyst with a review of the EIA, particularly for projects in the SADC region, the main components of an EIA report and guidance notes are provided in Appendices 6 and 7 respectively. The DBSA reserves the right to apply standards, in terms of both procedural requirements and environmental quality standards, that go beyond legislative and regulatory requirements. 3.8 Public disclosure and participation In compliance with Principle 10 of the Rio Declaration on Environment and Development (UNEP, 1992), South African legislation and regulations on activities that must have EIAs also set out requirements for public participation. These requirements enable interested and affected parties to engage with the authorities and project sponsors on any proposed development project. The DBSA, as a development finance institution, views public participation as a critical component of the EIA process, as it enhances collective decision-making and project ownership and helps to broaden development impact. Therefore, the DBSA requires public consultation on all Category 1 projects and any Category 2 projects that must have an EIA, in line with the DBSA Act and the Bank s policy on environmental sustainability. In addition, as part of the appraisal and ongoing monitoring, the environmental analyst must, where feasible and appropriate, engage with all relevant stakeholders, including local communities and environmental or other interest groups. Such engagement will fulfil the public consultation requirements for projects under Category 3, for which a formal EIA process is not required. The IEM Information Series No. 3 (DEAT, 2004c) reflects on approaches to stakeholder engagement (broadly defined to include public participation and consultation) and techniques to facilitate environmental appraisal. It may be useful to both DBSA staff and clients. 4. Environmental appraisal guidelines 4.1 Overview This section provides further details on the risk assessment methodologies used in environmental appraisal in the Bank. It outlines the main steps in conducting an appraisal and then reflects procedural requirements for the assessment and management of environmental risk. The environmental appraisal, being primarily qualitative, involves planning the process, gathering and validating information, Page 15

16 evaluating the information, and reporting on the appraisal. As outlined below, the process comprises three main steps, namely project screening, a site visit and the environmental appraisal. 4.2 Initial screening The major task in implementing the environmental appraisal guidelines is the initial screening of the project to determine, among others, the appropriate risk category. The screening commences after a project has been accepted into the pipeline based on its fit with the DBSA s mandate, policies and priorities. The DBSA requires an environmental screening of all projects, regardless of their potential environmental risks. This screening or project categorisation is based on the early review report prepared by the project manager, the borrower s project proposal, and any other baseline information available to the environmental analyst. The environmental analyst assigns the proposed development project or credit line to one of the following four categories (see section 3.6): z Category 1: High risk z Category 2: Medium risk z Category 3: Low risk z Category 4: Financial intermediary The analyst has the discretion to impose requirements that differ from those of the above categories. Any such deviation must be motivated in the project appraisal report for discussion with the project manager and team. The analyst may also call on other professionals, whether internal or external, to assist in the initial screening decisions. Once a risk category has been assigned, the analyst outlines the information needed, including legislative and regulatory requirements, and communicates this to the borrower in conjunction with the project manager. At this stage, all existing environmental investigations, audits and EIAs are verified. Any alternative opportunities that may yield additional environmental benefits are also identified for consideration in the proposed project. However, since project planning is often at an advanced stage when borrowers approach the Bank for funding, opportunities for influencing the project in this way may be limited. 4.3 Site visits The environmental specialist undertakes at least one site visit before the appraisal, to inform the risk categorisation and to assess the types of risks that are likely to be encountered before and after mitigation. During the field visit, the analyst does the following: Page 16

17 z Assess the sensitivity of the site, the potential environmental risks from project activities, and the potential for intervention to promote alternative designs. z Assess the institutional capacity of the borrower for environmental management. z Establish relationships with, among other important contacts, project designers, engineers and interested and affected parties. A site visit is particularly important when no EIA or scoping report has been submitted or when they are incomplete, as it enables the analyst to identify the potential environmental impact of the project and develop a risk table for the appraisal report. Also, when the DBSA has previously financed projects as part of an ongoing programme with a borrower, the site visit allows the analyst to assess the environmental performance of both the borrower and the projects. 4.4 Environmental risk appraisal of projects The environmental analyst uses all the relevant documentation, including EIA or environmental due diligence reports, information from site visits, discussions with regulatory authorities and interested and affected parties, and the relevant guidelines to identify the environmental risks of the project and the phases in which they are likely to occur. In some cases, the documentation supplied by the borrower may be inadequate. The environmental analyst will then consult with the project manager to, for example, redo all or part of the EIA, obtain other documents, or request expert reporting on sectoral issues and a review of the EIA, for which additional funding may be needed. An appraisal cannot be comprehensive and sound without an adequate information base. The Bank therefore requires the analyst to report on the adequacy and source of the information. Appendix 5 outlines further requirements for documenting the quality and adequacy of the information reviewed for the appraisal report. The methodology for the review of an EIA is given in Appendix 7; see also DEAT (2004b). The Bank also requires an environmental risk table for all projects. The broad methodology for constructing the table is outlined in the rest of this section. For each risk identified, the magnitude of its consequences (or impact) is assessed and given a rating of low, medium or high. The criteria for the rating could include the following: z Nature of the impact z Sensitivity of the environment z Extent of the impact z Intensity or severity of the impact z Duration of the impact z Potential for cumulative effects Page 17

18 z Potential for non-compliance with regulatory requirements z Impact on endangered species z Potential for lender liability z Potential for reputational risk This list is not definitive, and analysts are encouraged to identify criteria that may be more appropriate for a particular project. Any criteria used in the rating should be documented in the appraisal report. When projects form part of a programme that has already been assessed, the norms and criteria identified in the programme appraisal report should be used. The table below identifies possible ways of deciding on the rating. Table 1: Qualitative measures of magnitude Criteria Rating Low Medium High Scale of impact Localised On site Fairly extensive Regional National International Sensitivity of the environment Not in a sensitive environment In a sensitive environment, but impact localised and reversible Mitigation measures easily prescribed Project situated in sensitive areas specified in Appendix 9 Potential for cumulative impact Non-compliance with regulatory requirements None Limited Extensive Full compliance Applications in place Non-compliance Impact on endangered species Little or none Unlikely to be adverse Some, but mostly reversible Significant loss of species Irreversible Diverse and comprehensive negative effects Potential for lender liability Potential for reputational risk Little or none Some Significant Little or none Some Significant Page 18

19 The probability of the risk event occurring is then assessed, as per Table 2. Table 2: Qualitative measures of probability Descriptor High Medium Low Description The event is likely to occur in most circumstances The event may sometimes occur The event may only occur in exceptional circumstances Table 3 combines the magnitude of the impact of each risk and the probability of the risk event occurring, to yield an overall rating for each risk. Table 3: Qualitative risk assessment matrix Probability Magnitude of consequence (impact) Low Medium High A (High) High/low High/medium High B (Medium) Medium/low Medium Medium/high C (Low) Low Low/medium Low/high The ratings in Table 3 are interpreted as follows: High/low: High/medium: High: Medium/low: Medium: Medium/high: Low: Low/medium: Low/high: The chance of the event occurring is very high but the potential impact is low. The chance of the event occurring is high but the potential impact is moderate. The chance of the event occurring and the potential impact are both high. The chance of the event occurring is moderate and the potential impact limited. The chance of the event occurring and the potential impact are both moderate. The chance of the event occurring is moderate and the potential impact high. The chance of the event occurring and the potential impact are both low. The chance of the event occurring is low and the potential impact moderate. The chance of the event occurring is low and the potential impact high. The initial risk assessment is done before mitigation measures are in place. Once these measures have been identified, the magnitude, probability and overall risk are reassessed, based on the expected effects of the mitigation measures. Note that the proposed mitigation measures must be practical and involve concrete actions in the EMP, as well as adequate financial provision. General statements of intent, with a limited capacity to implement the required actions, must not be used to reduce the impact ratings, as the risk will remain high. Page 19

20 The analyst should also explicitly consider the effect of the borrower s institutional capacity on the magnitude and probability of each of the identified environmental risks. The results of the risk assessment are detailed in the environmental appraisal report and summarised as per Table 4 below. Table 4: Summary risk assessment of a project Environmental risk Specify environmental risk Magnitude Probability Risk rating (without mitigation) Proposed mitigation measures H, M, L H, M, L H/M, etc. Detail mitigation measures Magnitude Probability Risk rating (with mitigation) H, M, L H, M, L H/L, etc. An overall risk rating for the project should also be given before and after the mitigation. This is done as follows: as part of the initial screening, a project is classified into one of the categories identified earlier, based on its nature, the magnitude of potential adverse effects and the sensitivity of the project site, among other criteria. Individual risks are then assigned risk ratings in terms of their probability and magnitude profile. Once mitigation measures are in place, the ratings of individual risks are reassessed, as per Table 4, and the whole project is then reassessed according to where it lies in the broad category. For example, if the broad category is medium, the project may be medium/ high, medium or medium/low. This gives the allocation of the overall risk category. In the loan risk spread provided by the Risk Management Unit, environmental risk is allocated 20 points. Table 5 proposes a method for allocating these 20 points, after the borrower has agreed to the mitigation measures. Table 5: Application of the loan risk spread Overall environmental risk rating Risk-rating points allocated (from loan risk spread summary) Risk spread Risk-rating class High 0 Unacceptable High/medium 3 Doubtful High High/low 5 Weak Medium/high 9 Vulnerable Medium 11 Acceptable Medium Medium/low 13 Satisfactory Low/high 15 Good Low/medium 17 Very good Low Low 20 Excellent Page 20

21 4.5 Environmental risk appraisal of programmes As noted, the DBSA also funds investment programmes that involve several different projects. The Bank requires all of the projects in a programme to be appraised individually. In some programmes, the individual projects are listed or even described upfront. In this case, the analyst must try to obtain enough information to identify the nature and type of the projects, and determine the project category. The analyst can use the information obtained by the borrower when the projects were identified and also request additional baseline information, especially for projects with significant environmental risks. The institutional rating and the risk categorisation of individual projects are then used to assign an overall risk rating to the programme. In other cases, information on the projects may not be available at the time of the appraisal. Under these circumstances, the emphasis is on the risk profile of the programme and the institutional capacity of the borrower for environmental management. Appendix 2 lists criteria for assessing institutional capacity; other criteria can be motivated where required. On the basis of these criteria, the borrower risk will be evaluated as high, medium or low. The institutional rating and the risk profile of the programme are then used to assign an overall risk rating to the programme. The rest of the process to apply the loan risk spread is the same as for projects, and the results are presented as per Table 6 below. Table 6: Summary risk assessment of a programme Projects, project types and/or sectors (Infrastructure programme) Risk classification Institutional capacity risk rating Overall risk rating Electricity reticulation High, medium, low High, medium, low Based on the risk of the project and the risk rating from the institutional capacity assessment Sanitation reticulation As above As above As above 4.6 Financial intermediaries The DBSA s support to financial intermediaries presents special considerations in the appraisal process. As is the case with some programmes, the environmental analyst may have very little information on the projects that will be supported through the on-lending of funds, other than perhaps the sectors under consideration. Page 21

22 In general, the analyst follows the same approach as for the appraisal of programmes. The emphasis is on the overall risk category of the projects being considered for funding and the financial intermediary s institutional capacity for environmental management. However, the DBSA s environmental requirements for on-lending projects may differ from those for directly financed programmes, as outlined in Appendix 10. The DBSA requires projects funded by financial intermediaries to be environmentally sound and sustainable. Therefore, if they do not already have the appropriate policies, financial intermediaries must establish an environmental appraisal policy and procedural framework as part of their overall credit review policy. The existence and/or adequacy of the borrower s environmental appraisal policy framework is assessed as part of the appraisal of the credit line. The analyst, in conjunction with the project manager, should inform the financial intermediary of the requirements outlined in Appendix 10 as early as possible in the appraisal process. 4.7 Agency agreements The DBSA s investment portfolio also includes projects supported through credit lines that the Bank has with other development finance institutions. Most of these institutions have attached environmental conditionalities to their lines of credit. When appraising projects, the environmental analyst should ensure that any environmental conditionalities are included in the environmental appraisal and, more importantly, that the ultimate borrower (or financial intermediary) adheres to them. Where the agencies have not such procedural requirements or conditionalities to their support, the environmental guidelines set out in this document apply, with due regard for international good practice. 4.8 Other DBSA investment products In addition to traditional loans, the DBSA provides a range of innovative products, such as equity investments, bids and bonds. The environmental appraisal of these products faces special challenges stemming from the diversity of the implementing institutions and their varied capacity for environmental management. In most cases, Bank lending through these products is not targeted at specific projects. Therefore, the focus of the environmental appraisal is on the institutional capacity for environmental management and the profile of the projects to be funded by such products. In addition, to ensure that these financial products result in projects or operations that are environmentally sound and sustainable, adherence to the DBSA s internal policies and environmental requirements as outlined in these guidelines is strictly monitored. Page 22

23 Therefore, the environmental analyst must ensure that the loan agreement includes clauses for compliance with all of the relevant environmental legislative and regulatory requirements, as well as the requirements for monitoring and reporting environmental risks. Where feasible, the analyst and the project team must monitor these conditions for each individual project financed by such products. In line with the DBSA s focus on ensuring that the projects supported by these financial products are environmentally sound and sustainable, it is committed to strengthening the environmental management capacity of the borrowers. In the assessment, the environmental analyst must identify any limitations or inadequacies in this capacity for possible support through technical assistance. The assessment should use the criteria in Appendix 2 and preferably also the national standard for the environmental appraisal of sites and organisations (SANS 14015). 4.9 Loan conditions The DBSA ensures compliance with its mandate, policy and guidelines on environmental management by incorporating appropriate conditionalities in the legal agreements with its borrowers. The two main types of conditionalities are suspensive conditions and further terms and conditions. z Suspensive conditions: The acquisition of an environmental authorisation or permit, where required, is always a suspensive condition the DBSA requires proof that the authorisation or permit has been obtained before any funds can be disbursed to the project. Where non-compliance with certain requirements would affect the environmental risks of a project to such an extent that the DBSA could suffer significant liability, such requirements must also be made suspensive conditions. z Further terms and conditions: These aim to ensure that the borrower complies with the environmental conditions identified in the loan agreement. They may include, for example, requirements for preparing and reporting on an environmental mitigation and management plan. The environmental analyst, in conjunction with the project manager, must clearly indicate the issues to be included in the legal agreement with the borrower. The legal advisor will assist in drafting such environmental conditions; they should be precise and indicate exactly what is required. Before the borrower signs loan agreement, the analyst must verify that these environmental conditions have been included in the agreement. The main mitigation measures to lower the environmental risks of the project should form part of the loan agreement and be drawn through to the contract documents, tender documents and the bill of quantities. As part of the monitoring during the implementation phase, the environmental analyst should verify that the borrower adheres to the relevant clauses in the loan agreement. Page 23

Earth is our Business

Earth is our Business Earth is our Business changing the rules of the game POLLY HIGGINS SHEPHEARD-WALWYN (PUBLISHERS) LTD 2012 Polly Higgins Some rights reserved. [license_3.0] This work is licensed under a Creative Commons

More information

OPERATIONS MANUAL BANK POLICIES (BP)

OPERATIONS MANUAL BANK POLICIES (BP) BANK POLICIES (BP) OM Section F1/BP Page 1 of 2 These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. SAFEGUARD POLICY STATEMENT 1. The Asian Development

More information

UPDATE. Financial Intermediary Lending and Environmental Assessment. Environmental Assessment

UPDATE. Financial Intermediary Lending and Environmental Assessment. Environmental Assessment Environmental Assessment S o u r c e b o o k UPDATE Environment Department June 2002 The World Bank Number 27 Financial Intermediary Lending and Environmental Assessment The World Bank supports economic

More information

International Finance Corporation s Policy on Social & Environmental Sustainability

International Finance Corporation s Policy on Social & Environmental Sustainability International Finance Corporation s Policy on Social & Environmental Sustainability Section 1: Purpose of this Policy 1. International Finance Corporation (IFC) strives for positive development outcomes

More information

Environmental Assessment

Environmental Assessment OP 4.01 January 1999 These policies were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. Environmental Assessment (Archived August 2004) Note: OP and BP

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section F1/BP Page 1 of 3 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ENVIRONMENTAL

More information

DRAFT FOR CONSULTATION OCTOBER 7, 2014

DRAFT FOR CONSULTATION OCTOBER 7, 2014 DRAFT FOR CONSULTATION OCTOBER 7, 2014 Information Note 1: Environmental and Social Risk Classification The Board has requested the release of this document for consultation purposes to seek feedback on

More information

DBN ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT APPRAISAL AND MONITORING PROCEDURES

DBN ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT APPRAISAL AND MONITORING PROCEDURES DBN ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT APPRAISAL AND MONITORING PROCEDURES 1 Table of Contents 1. Introduction... 4 2. Commitments and Responsibilities... 5 2.1. Systematic risk and impact assessment...

More information

Basel Committee on Banking Supervision. Consultative Document. Pillar 2 (Supervisory Review Process)

Basel Committee on Banking Supervision. Consultative Document. Pillar 2 (Supervisory Review Process) Basel Committee on Banking Supervision Consultative Document Pillar 2 (Supervisory Review Process) Supporting Document to the New Basel Capital Accord Issued for comment by 31 May 2001 January 2001 Table

More information

World Bank Environmental. and Social Policy for Investment Project Financing

World Bank Environmental. and Social Policy for Investment Project Financing World Bank Environmental and Social Policy for Investment Project Financing Purpose 1. This Environmental and Social Policy for Investment Project Financing 1 sets out the mandatory requirements of the

More information

PART A: THE PALESTINIAN ENVIRONMENTAL ASSESSMENT POLICY. A policy to establish an environmental assessment process in Palestine

PART A: THE PALESTINIAN ENVIRONMENTAL ASSESSMENT POLICY. A policy to establish an environmental assessment process in Palestine PART A: THE PALESTINIAN ENVIRONMENTAL ASSESSMENT POLICY A policy to establish an environmental assessment process in Palestine WHEREAS the Palestinian National Authority seeks to achieve sustainable development

More information

4. Clarification of the requirement for documents indicating compliance of timber with applicable legislation

4. Clarification of the requirement for documents indicating compliance of timber with applicable legislation 4. Clarification of the requirement for documents indicating compliance of timber with applicable legislation Relevant legislation: EU Timber Regulation Article 2 [ ] (f) 'legally harvested' means harvested

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.6 INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES OCTOBER 2007 This document was prepared

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.x INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES DRAFT, MARCH 2008 This document was prepared

More information

(13 July 2018 to date) NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998

(13 July 2018 to date) NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998 (13 July 2018 to date) NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998 (Gazette No. 19519, Notice No. 1540. Commencement date: 29 January 1999 [Proc. No. 8, Gazette No. 19703]) ENVIRONMENTAL IMPACT ASSESSMENT

More information

Proposed Revision to the UK Stewardship Code Annex A - Revised UK Stewardship Code

Proposed Revision to the UK Stewardship Code Annex A - Revised UK Stewardship Code Consultation Financial Reporting Council January 2019 Proposed Revision to the UK Stewardship Code Annex A - Revised UK Stewardship Code The FRC s mission is to promote transparency and integrity in business

More information

EBRD s Environmental & Social (E&S) Risk Management Procedures for Leasing Activities

EBRD s Environmental & Social (E&S) Risk Management Procedures for Leasing Activities EBRD s Environmental & Social (E&S) Risk Management Procedures for Leasing Activities Any EBRD partner Financial Intermediary (FI) must have clearly defined environmental and social management systems

More information

Recommendation of the Council on Good Practices for Public Environmental Expenditure Management

Recommendation of the Council on Good Practices for Public Environmental Expenditure Management Recommendation of the Council on for Public Environmental Expenditure Management ENVIRONMENT 8 June 2006 - C(2006)84 THE COUNCIL, Having regard to Article 5 b) of the Convention on the Organisation for

More information

OPERATING POLICIES AND PROCEDURES Chapter 12 Due Diligence Policy and Procedures. Effective from 28 November 2016

OPERATING POLICIES AND PROCEDURES Chapter 12 Due Diligence Policy and Procedures. Effective from 28 November 2016 OPERATING POLICIES AND PROCEDURES Chapter 12 Due Diligence Policy and Procedures Effective from 28 November 2016 1 Contents 1. Policy Statement... 3 2. When to conduct due diligence... 5 3. New Business

More information

Recommendations on President s Aid to Negotiations Environmental Impact Assessments

Recommendations on President s Aid to Negotiations Environmental Impact Assessments Recommendations on President s Aid to Negotiations Environmental Impact Assessments ISSUE Relevant text from PRESIDENT S AID TO NEGOTIATIONS (PAN) PROPOSED EDITS RATIONALE SUPPORT (where applicable) 1.

More information

EBRD s s Experience in CEE Environmental Risks and Opportunities. Dr. Dariusz Prasek Head of Operational Support

EBRD s s Experience in CEE Environmental Risks and Opportunities. Dr. Dariusz Prasek Head of Operational Support EBRD s s Experience in CEE Environmental Risks and Opportunities Dr. Dariusz Prasek Head of Operational Support Environment Department European Bank for Reconstruction and Development Presentation Structure

More information

Step 07. Closure. Summary of Step 7: Closure. Plan for Closure and Post-Closure in an Integrated Manner

Step 07. Closure. Summary of Step 7: Closure. Plan for Closure and Post-Closure in an Integrated Manner 1 2 3 4 5 6 7 8 1 Regulations, Extracting good practices Feasibility Development Institutions Planning Exploration Production Closure Post-closure & Licensing & Construction & Rule of Law Step 07 Closure

More information

Can we have a Global Standard on Environmental, and Social Governance?

Can we have a Global Standard on Environmental, and Social Governance? Can we have a Global Standard on Environmental, and Social Governance? Prasad Modak, Rahul Datar, Lucille Andrade 1 Preamble Environmental and Social Governance (ESG) is critical for sustainable development.

More information

Environmental and Social Management System Arrangement. Sri Lanka: Small and Medium-Sized Enterprises Line of Credit Project

Environmental and Social Management System Arrangement. Sri Lanka: Small and Medium-Sized Enterprises Line of Credit Project Environmental and Social Management System Arrangement February 2017 Sri Lanka: Small and Medium-Sized Enterprises Line of Credit Project Prepared by Sampath Bank PLC for the Asian Development Bank. The

More information

OVERSIGHT EXPECTATIONS FOR LINKS BETWEEN RETAIL PAYMENT SYSTEMS

OVERSIGHT EXPECTATIONS FOR LINKS BETWEEN RETAIL PAYMENT SYSTEMS OVERSIGHT EXPECTATIONS FOR LINKS BETWEEN RETAIL PAYMENT SYSTEMS Introduction Oversight of payment systems, which aims to ensure the smooth functioning of payment systems and to contribute to financial

More information

BERMUDA MONETARY AUTHORITY THE INSURANCE CODE OF CONDUCT FEBRUARY 2010

BERMUDA MONETARY AUTHORITY THE INSURANCE CODE OF CONDUCT FEBRUARY 2010 Table of Contents 0. Introduction..2 1. Preliminary...3 2. Proportionality principle...3 3. Corporate governance...4 4. Risk management..9 5. Governance mechanism..17 6. Outsourcing...21 7. Market discipline

More information

Environmental and Social Directive for Investment Project Financing. Bank Access to Information Policy Designation Public

Environmental and Social Directive for Investment Project Financing. Bank Access to Information Policy Designation Public Bank Directive Environmental and Social Directive for Investment Project Financing Bank Access to Information Policy Designation Public Catalogue Number OPS5.03-DIR.111 Issued October 3, 2018 Effective

More information

PILLAR III DISCLOSURES

PILLAR III DISCLOSURES PILLAR III DISCLOSURES 2014 PILLAR III Disclosures - 2014 Page 1 of 21 TABLE OF CONTENT 1 SCOPE OF APPLICATION... 4 1.1 PILLAR I MINIMUM CAPITAL REQUIREMENTS... 4 1.2 PILLAR II INTERNAL CAPITAL ADEQUACY

More information

REVIEW PRACTICE GUIDANCE

REVIEW PRACTICE GUIDANCE Biennial Reports and National Communications: Review Challenges and Practice REVIEW PRACTICE GUIDANCE Biennial Reports and National Communications: Review Challenges and Practice Background Paper for the

More information

XII. CGIF Environmental and Social Safeguards Policy and Framework 1

XII. CGIF Environmental and Social Safeguards Policy and Framework 1 A. Policy XII. CGIF Environmental and Social Safeguards Policy and Framework 1 1. Credit Guarantee and Investment Facility (CGIF), a trust fund of the Asian Development Bank (ADB) was established to promote

More information

Risk Management Framework

Risk Management Framework Risk Management Framework Anglican Church, Diocese of Perth November 2015 Final ( Table of Contents Introduction... 1 Risk Management Policy... 2 Purpose... 2 Policy... 2 Definitions (from AS/NZS ISO 31000:2009)...

More information

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia Phase 3 Consultation in Indonesia January 26-28, 2016 Objective Illustrate

More information

Auckland Transport HS03-01 Risk and Hazard Management

Auckland Transport HS03-01 Risk and Hazard Management Auckland Transport HS03-01 Risk and Hazard Management (Procedure uncontrolled when printing) Relating to Standard: HS03 Risk and Hazard Management Standard December 2016 Health and Safety-Procedure-HS03-01

More information

Armenia German-Armenian Fund GAF Loan Programme for the Promotion of Micro and Small Private Enterprises

Armenia German-Armenian Fund GAF Loan Programme for the Promotion of Micro and Small Private Enterprises Armenia German-Armenian Fund GAF Loan Programme for the Promotion of Micro and Small Private Enterprises Ex post evaluation OECD sector BMZ project ID Project-executing agency Consultant 24030 Financial

More information

What is the prudent maximum exposure to any one investment manager for my fund?

What is the prudent maximum exposure to any one investment manager for my fund? What is the prudent maximum exposure to any one investment manager for my fund? Vanguard commentary May 2010 Executive summary. Trustees of investment funds, who bear a fiduciary duty to protect the interests

More information

ENVIRONMENTAL SOCIAL GOVERNANCE (ESG) POLICY INTRODUCTION

ENVIRONMENTAL SOCIAL GOVERNANCE (ESG) POLICY INTRODUCTION ENVIRONMENTAL SOCIAL GOVERNANCE (ESG) POLICY INTRODUCTION As long-term stewards of our clients capital, Coronation is focussed on the long-term prospects of the assets in which we invest on our clients

More information

28 July May October 2016

28 July May October 2016 Policy Name Risk Management Policy & Procedure Related Policies and Legislation AISWA Guidelines Risk Management Policy Category Planning & Management Relevant Audience Date of Issue / Last Revision All

More information

THE ROLE OF NATIONAL REGULATOR FOR COMPULSORY SPECIFICATIONS (NCRS) IN TERMS OF CONFORMITY ASSESSMENT. Speaker / Author: T Scriven Principal-author

THE ROLE OF NATIONAL REGULATOR FOR COMPULSORY SPECIFICATIONS (NCRS) IN TERMS OF CONFORMITY ASSESSMENT. Speaker / Author: T Scriven Principal-author THE ROLE OF NATIONAL REGULATOR FOR COMPULSORY SPECIFICATIONS (NCRS) IN TERMS OF CONFORMITY ASSESSMENT Speaker / Author: T Scriven Principal-author Company National Regulator for Compulsory Specifications

More information

Rating Methodology Government Related Entities

Rating Methodology Government Related Entities Rating Methodology 13 July 2018 Contacts Jakob Suwalski Alvise Lennkh Giacomo Barisone Associate Director Director Managing Director Public Finance Public Finance Public Finance +49 69 6677 389 45 +49

More information

MANAGING RISK IN EMERGING MARKETS OUR CORE BUSINESS FISCAL YEAR 2013

MANAGING RISK IN EMERGING MARKETS OUR CORE BUSINESS FISCAL YEAR 2013 MANAGING RISK IN EMERGING MARKETS OUR CORE BUSINESS FISCAL YEAR 2013 PROVEN TRACK RECORD 2 IFC IN NUMBERS 57 $63.2bn $49.6bn $13.6bn $24.9bn $18.3bn $6.5bn $1bn Years of profitable investments in emerging

More information

ESG AND RESPONSIBLE INVESTMENT PHILOSOPHY

ESG AND RESPONSIBLE INVESTMENT PHILOSOPHY ESG AND RESPONSIBLE INVESTMENT PHILOSOPHY February 2017 AMP CAPITAL ESG AND RESPONSIBLE INVESTMENT PHILOSOPHY 1 AMP Capital is one of Asia Pacific s largest investment managers. We have a single goal in

More information

PILLAR III DISCLOSURES

PILLAR III DISCLOSURES PILLAR III DISCLOSURES 6102 PILLAR III Disclosures - 6102 Page 1 of 21 TABLE OF CONTENT 1 SCOPE OF APPLICATION... 4 1.1 PILLAR I MINIMUM CAPITAL REQUIREMENTS... 4 1.2 PILLAR II INTERNAL CAPITAL ADEQUACY

More information

CENTRAL GOVERNMENT ACCOUNTING STANDARDS

CENTRAL GOVERNMENT ACCOUNTING STANDARDS CENTRAL GOVERNMENT ACCOUNTING STANDARDS APRIL 2018 CONTENTS Updates 2 Introduction 6 Conceptual Framework for Central Government Accounting 7 Standard 1 Financial Statements 24 Standard 2 Expenses 39 Standard

More information

CENTRAL GOVERNMENT ACCOUNTING STANDARDS

CENTRAL GOVERNMENT ACCOUNTING STANDARDS CENTRAL GOVERNMENT ACCOUNTING STANDARDS March 2015 CENTRAL GOVERNMENT ACCOUNTING STANDARDS FRANCE Updates Public Sector Accounting Standards Council Date of Central Government Accounting Standards Opinion

More information

Prudential Standard GOI 3 Risk Management and Internal Controls for Insurers

Prudential Standard GOI 3 Risk Management and Internal Controls for Insurers Prudential Standard GOI 3 Risk Management and Internal Controls for Insurers Objectives and Key Requirements of this Prudential Standard Effective risk management is fundamental to the prudent management

More information

Evaluation and future development of the EIA system in Jordan

Evaluation and future development of the EIA system in Jordan MEDITERRANEAN ENVIRONMENTAL TECHNICAL ASSISTANCE PROGRAM Evaluation and future development of the EIA system in Jordan A report prepared under the METAP EIA Institutional Strengthening Project December

More information

FIDANTE PARTNERS EUROPE LIMITED. Pillar III Disclosure. 30 June 2017

FIDANTE PARTNERS EUROPE LIMITED. Pillar III Disclosure. 30 June 2017 FIDANTE PARTNERS EUROPE LIMITED Pillar III Disclosure 30 June 2017 Fidante Partners Europe LimitedPillar III Disclosure 30 June 2017 Fidante Partners Europe Limited ( Fidante Partners Europe or the Firm

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY AMTEK AUTO LIMITED RISK MANAGEMENT POLICY Introduction Oxford Dictionary defines the term risk as a chance or possibility of danger, loss, injury or other adverse consequences Risk management attempts

More information

FRAMEWORK FOR SUPERVISORY INFORMATION

FRAMEWORK FOR SUPERVISORY INFORMATION FRAMEWORK FOR SUPERVISORY INFORMATION ABOUT THE DERIVATIVES ACTIVITIES OF BANKS AND SECURITIES FIRMS (Joint report issued in conjunction with the Technical Committee of IOSCO) (May 1995) I. Introduction

More information

GENERAL RISK CONTROL AND MANAGEMENT POLICY

GENERAL RISK CONTROL AND MANAGEMENT POLICY GENERAL RISK CONTROL AND MANAGEMENT POLICY Translation originally issued in Spanish and prepared in accordance with the regulatory applicable to the Group. In the event of a discrepancy, the Spanishlanguage

More information

Contents. Ulkoministeriö Utrikesministeriet Ministry for Foreign Affairs of Finland

Contents. Ulkoministeriö Utrikesministeriet Ministry for Foreign Affairs of Finland 1 Contents 1. Introduction 2. Project Developer Responsibilities 3. Milestone Reporting 4. Monitoring and Site Visits 5. Disbursement of Funds 6. Repayable Grant 7. Procurement 8. Project Audit Report

More information

Consultation Paper. FSB Principles for Sound Residential Mortgage. Underwriting Practices

Consultation Paper. FSB Principles for Sound Residential Mortgage. Underwriting Practices Consultation Paper FSB Principles for Sound Residential Mortgage Underwriting Practices 26 October 2011 Table of Contents Page Definitions... i I. Introduction... 1 II. Principles... 2 1. Effective verification

More information

OLD MUTUAL INVESTMENT GROUP RESPONSIBLE OWNERSHIP GUIDELINES

OLD MUTUAL INVESTMENT GROUP RESPONSIBLE OWNERSHIP GUIDELINES RESPONSIBLE INVESTMENT POSITIVE FUTURES OLD MUTUAL INVESTMENT GROUP RESPONSIBLE OWNERSHIP GUIDELINES First published: JULY 2012 Latest update: JANUARY 2016 1 TABLE OF CONTENTS 1. INTRODUCTION 1 2. OLD

More information

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS July 13, 2015 Office of the Compliance Advisor Ombudsman (CAO) COMPLIANCE APPRAISAL: SUMMARY OF RESULTS IFC Investment in Bilt Paper B.V., Malaysia Project #34602 Complaint 01 Ballarpur International Graphic

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

EPWP INCENTIVE GRANT MANUAL

EPWP INCENTIVE GRANT MANUAL EPWP Incentive Grant Manual 2009/10 EPWP INCENTIVE GRANT MANUAL FROM THE NATIONAL DEPARTMENT OF PUBLIC WORKS FOR THE IMPLEMENTATION OF THE EPWP INCENTIVE GRANT BY IMPLEMENTING PUBLIC BODIES Version 1 May

More information

Risk Management Plan PURPOSE: SCOPE:

Risk Management Plan PURPOSE: SCOPE: Management Plan Authority Source: Vice-Chancellor Approval Date: 16/05/2018 Publication Date: 17/05/2018 Review Date: 17/05/2021 Effective Date: 16/05/2018 Custodian: General Counsel and University Secretary

More information

Risk Management Strategy

Risk Management Strategy Resources Risk Management Strategy Successful organisations are not afraid to take risks; Unsuccessful organisations take risks without understanding them. Issue: Version 3 - November 2011 Group: Resources

More information

Guidelines for Transboundary Environmental Impact Assessment in the Lower Mekong Basin

Guidelines for Transboundary Environmental Impact Assessment in the Lower Mekong Basin Summary note Guidelines for Transboundary Environmental Impact Assessment in the Lower Mekong Basin Final draft In an effort to communicate openly with broader stakeholders of the Mekong River Commission

More information

Review and Update of the World Bank s Environmental and Social Safeguard Policies Phase 3 Feedback Summary

Review and Update of the World Bank s Environmental and Social Safeguard Policies Phase 3 Feedback Summary Review and Update of the World Bank s Environmental and Social Safeguard Policies Phase 3 Feedback Summary Date: February 16 and 17, 2016 Location (City, Country): Dar es Salaam, Tanzania Audience: Government

More information

Order Execution Policy. January 2018 v1

Order Execution Policy. January 2018 v1 Order Execution Policy January 2018 v1 Table of Contents Introduction... 2 Scope... 2 Background... 3 Legislation Reference... 3 Business Model... 3 Client Category... 4 Authorised Personnel... 4 Best

More information

Report to G7 Finance Ministers and Central Bank Governors on International Accounting Standards

Report to G7 Finance Ministers and Central Bank Governors on International Accounting Standards Report to G7 Finance Ministers and Central Bank Governors on International Accounting Standards Basel Committee on Banking Supervision Basel April 2000 Table of Contents Executive Summary...1 I. Introduction...4

More information

Responsible Investment Policy

Responsible Investment Policy Responsible Investment Policy This Responsible Investment Policy details the approach that BCPP will follow in fulfilling its commitment to the partner funds in the delegation of RI and stewardship responsibilities.

More information

TRAINING CATALOGUE ON IMPACT INSURANCE Building practitioner skills in providing valuable and viable insurance products

TRAINING CATALOGUE ON IMPACT INSURANCE Building practitioner skills in providing valuable and viable insurance products TRAINING CATALOGUE ON IMPACT INSURANCE Building practitioner skills in providing valuable and viable insurance products 2017 Contents of the training catalogue The ILO s Impact Insurance Facility... 3

More information

Corporate responsibility. Mitigating environmental, social and governance (ESG) risks in underwriting and investment management

Corporate responsibility. Mitigating environmental, social and governance (ESG) risks in underwriting and investment management Corporate responsibility Mitigating environmental, social and governance (ESG) risks in underwriting and investment management 2 Corporate responsibility Version 1.0 Corporate responsibility Version 1.0

More information

A Discussion Document on Assurance of Social and Environmental Valuations

A Discussion Document on Assurance of Social and Environmental Valuations A Discussion Document on Assurance of Social and Environmental Valuations Social Value UK Winslow House, Rumford Court, Liverpool, L3 9DG +44 (0)151 703 9229 This document is not intended to be an assurance

More information

PRI Reporting Framework Main definitions 2018

PRI Reporting Framework Main definitions 2018 PRI Reporting Framework Main definitions 2018 November 2017 reporting@unpri.org +44 (0) 20 3714 3187 Table of Contents Introduction 2 ESG issues 3 Active/ Passive investments 4 ESG incorporation 5 Active

More information

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS1 Assessment and Management of Environmental and Social Risks and Impacts

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS1 Assessment and Management of Environmental and Social Risks and Impacts The Guidance Notes provide guidance for the Borrower on the application of the Environmental and Social Standards (ESSs), which form part of the World Bank s 2016 Environmental and Social Framework. The

More information

ASIC s Regulatory Guide 247 Effective Disclosure in an Operating and Financial Review and the International Integrated Reporting Framework

ASIC s Regulatory Guide 247 Effective Disclosure in an Operating and Financial Review and the International Integrated Reporting Framework companydirectors.com.au Comparison guide July 2014 ASIC s Regulatory Guide 247 Effective Disclosure in an Operating and and the International Integrated Reporting Framework Important Notices The Material

More information

Interpretation Note on Environmental and Social Categorization

Interpretation Note on Environmental and Social Categorization Introduction IN1. This Interpretation Note (IN) explains IFC s approach to environmental and social (E&S) categorization of proposed investments, and becomes effective on. IN1 This IN also contrasts the

More information

PE-CONS 3619/3/01 REV 3

PE-CONS 3619/3/01 REV 3 on the assessment of the effects of certain plans and programmes on the environment THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION, Having regard to the Treaty establishing the European

More information

Debentures improving disclosure for retail investors

Debentures improving disclosure for retail investors REGULATORY GUIDE 69 Debentures improving disclosure for retail investors August 2008 About this guide This guide is for issuers and others involved with the issue of debentures. It sets out guidelines

More information

D6.2 Risk Assessment Plan

D6.2 Risk Assessment Plan D6.2 Risk Assessment Plan Project number: 730830 Project acronym: Project title: Safe4RAIL Start date of the project: 1 st of October, 2016 Duration: Programme: Safe4RAIL: SAFE architecture for Robust

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

IOSCO CONSULTATION FINANCIAL BENCHMARKS PUBLIC COMMENT ON FINANCIAL BENCHMARKS

IOSCO CONSULTATION FINANCIAL BENCHMARKS PUBLIC COMMENT ON FINANCIAL BENCHMARKS IOSCO CONSULTATION FINANCIAL BENCHMARKS PUBLIC COMMENT ON FINANCIAL BENCHMARKS General Comments: Standard Chartered Bank welcomes the opportunity to participate in and provide comments to this consultation.

More information

Financial Management (FM) Syllabus and study guide

Financial Management (FM) Syllabus and study guide September 2018 to June 2019 Financial Management (FM) Syllabus and study guide Guide to structure of the syllabus and study guide Overall aim of the syllabus This explains briefly the overall objective

More information

IIC Environmental and Social Guidance Document

IIC Environmental and Social Guidance Document IIC Environmental and Social Guidance Document Acronyms and Abbreviations DFI DIAS E & S EIA ESDD ESIA ESAP ESMP ESMS FI IIC IDB IFC ILO ISO PS SME TA XASR Development Finance Institution Development

More information

STRATEGIC PLANNING PROCESS (2017) 1.1 The Association s strategic planning framework consists of the preparation of the following documents;

STRATEGIC PLANNING PROCESS (2017) 1.1 The Association s strategic planning framework consists of the preparation of the following documents; 1.0 INTRODUCTION STRATEGIC PLANNING PROCESS (2017) 1.1 The Association s strategic planning framework consists of the preparation of the following documents; Corporate Management Plan Departmental Service

More information

Fidelity International and the Taiwan Stewardship Principles for Institutional Investors

Fidelity International and the Taiwan Stewardship Principles for Institutional Investors Fidelity International and the Taiwan Stewardship Principles for Institutional Investors FIL Securities Investment Trust Co. (Taiwan) Limited s ( SITE ) main business is to manage and offer securities

More information

Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION

Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION 1.1 OVERVIEW Preamble 1.1.1 The African Development Bank is the premier financial development institution in Africa dedicated to combating poverty and

More information

SINDICATUM RENEWABLE ENERGY COMPANY GREEN BOND

SINDICATUM RENEWABLE ENERGY COMPANY GREEN BOND SINDICATUM RENEWABLE ENERGY COMPANY GREEN BOND SECOND OPINION BY SUSTAINALYTICS November 13, 2017 www.sustainalytics.com Ankita Shukla (Toronto) Senior Advisor, Advisory Services ankita.shukla@sustainalytics.com

More information

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY NHS Education for Scotland RISK MANAGEMENT STRATEGY January 2016 1 Contents 1. NES STATEMENT ON RISK MANAGEMENT 2 RISK MANAGEMENT STRATEGY 3 RISK MANAGEMENT STRUCTURES 4 RISK MANAGEMENT PROCESSES 5 RISK

More information

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects Seminar on African Electrical Interconnection Module 6 - Financing Interconnection Projects Module 6 - Financing Interconnection Projects Contents 1) Major Financing Features 2) Basic Financing Approaches

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID AND CIVIL PROTECTION - ECHO

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID AND CIVIL PROTECTION - ECHO EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HUMANITARIAN AID AND CIVIL PROTECTION - ECHO FRAMEWORK PARTNERSHIP AGREEMENT WITH INTERNATIONAL ORGANISATIONS PREAMBLE 1 The European Union's humanitarian action

More information

May 2018 Legal & General Investment Management - Conflicts of Interest. Corporate Governance Conflicts of Interest Policy

May 2018 Legal & General Investment Management - Conflicts of Interest. Corporate Governance Conflicts of Interest Policy Corporate Governance Conflicts of Interest Policy Introduction The Legal & General Investment Management (LGIM) Corporate Governance team has responsibility for engaging and voting with listed companies

More information

Financial Management (F9) June & December 2013

Financial Management (F9) June & December 2013 Financial Management (F9) June & December 2013 This syllabus and study guide is designed to help with planning study and to provide detailed information on what could be assessed in any examination session.

More information

INTERNATIONAL AUDITING PRACTICE STATEMENT 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS

INTERNATIONAL AUDITING PRACTICE STATEMENT 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS INTERNATIONAL AUDITING PRACTICE STATEMENT 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS (This Statement is effective) CONTENTS Paragraph Introduction... 1 12 Guidance

More information

Risk Management Framework. Metallica Minerals Ltd

Risk Management Framework. Metallica Minerals Ltd Risk Management Framework Metallica Minerals Ltd Risk Management Framework 23 March 2012 Table of Contents Contents 1. Introduction... 3 2. Risk Management Approach... 3 3. Roles and Responsibilities...

More information

VOLTA RIVER AUTHORITY

VOLTA RIVER AUTHORITY VOLTA RIVER AUTHORITY Capital Expenditure Guidelines November 2012 TABLE OF CONTENTS PAGE 1.0 Purpose and Scope of Guidelines...3 2.0 Projects Guidelines Apply To....4 3.0 Exemptions from Guidelines...4

More information

The EU Reference Budgets Network pilot project

The EU Reference Budgets Network pilot project The EU Reference Budgets Network pilot project Towards a method for comparable reference budgets for EU purposes Summary We develop reference budgets that represent the minimum resources that persons need

More information

Infrastructure ESG policy guidelines

Infrastructure ESG policy guidelines Infrastructure policy guidelines At AMP Capital Investors Limited (AMP Capital), we recognise that environmental, social and governance () issues can impact the long-term performance of our investment

More information

GOOD PRACTICES FOR GOVERNANCE OF PENSION SUPERVISORY AUTHORITIES

GOOD PRACTICES FOR GOVERNANCE OF PENSION SUPERVISORY AUTHORITIES . GOOD PRACTICES FOR GOVERNANCE OF PENSION SUPERVISORY AUTHORITIES November 2013 GOOD PRACTICES FOR GOVERNANCE OF PENSION SUPERVISORY AUTHORITIES Introduction 1. Promoting good governance has been at the

More information

RISK MANAGEMENT POLICY October 2015

RISK MANAGEMENT POLICY October 2015 RISK MANAGEMENT POLICY October 2015 1. INTRODUCTION 1.1 The primary objective of risk management is to ensure that the risks facing the business are appropriately managed. 1.2 Paringa Resources Limited

More information

Official Journal of the European Union. (Legislative acts) DIRECTIVES

Official Journal of the European Union. (Legislative acts) DIRECTIVES 25.4.2014 L 124/1 I (Legislative acts) DIRECTIVES DIRECTIVE 2014/52/EU OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL of 16 April 2014 amending Directive 2011/92/EU on the assessment of the effects of certain

More information

«Your bridge to the world of private assets.» Principles of Responsible Investing

«Your bridge to the world of private assets.» Principles of Responsible Investing «Your bridge to the world of private assets.» Principles of Responsible Investing October 2013 1. Introduction The purpose of the Principles of Responsible Investing ( the Principles ) is to introduce

More information

Risk Management. Policy No. 14. Document uncontrolled when printed DOCUMENT CONTROL. SSAA Vic

Risk Management. Policy No. 14. Document uncontrolled when printed DOCUMENT CONTROL. SSAA Vic Document uncontrolled when printed Policy No. 14 Risk Management DOCUMENT CONTROL Version: Date approved by Board: On behalf of Board: Jack Wegman 17 March 2015 26 March 2015 Denis Moroney President Next

More information

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Consultant s Report Project Number: 49166-001 People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Public Private Partnerships: Management

More information

ENVIRONMENTAL, SOCIAL AND GOVERNANCE POLICY

ENVIRONMENTAL, SOCIAL AND GOVERNANCE POLICY 1.0 ESG Philosophy Manulife Asset Management(Manulife AM) provides comprehensive asset management solutions for clients across a wide range of asset classes and investment objectives, all sharing the common

More information

B.29[17d] Medium-term planning in government departments: Four-year plans

B.29[17d] Medium-term planning in government departments: Four-year plans B.29[17d] Medium-term planning in government departments: Four-year plans Photo acknowledgement: mychillybin.co.nz Phil Armitage B.29[17d] Medium-term planning in government departments: Four-year plans

More information

Report on Internal Control

Report on Internal Control Annex to letter from the General Secretary of the Autorité de contrôle prudentiel to the Director General of the French Association of Credit Institutions and Investment Firms Report on Internal Control

More information