1 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai Tel. No /65/69 Fax Website: / Case No. 47 of 2018 In the matter of Petition of Jawaharlal Nehru Port Trust (JNPT) for taking on record its deemed Distribution Licensee status and for specifying the applicable Specific Conditions of its Distribution Licence CORAM Shri. Anand B. Kulkarni, Chairperson Shri. Mukesh Khullar, Member Jawaharlal Nehru Port Trust (JNPT) Petitioner Appearance For Petitioner Shri. Varun Sethi (Rep.) Shri. Arvind Pradhan (Rep.) ORDER Date: 14 June, Jawaharlal Nehru Port Trust (JNPT), Admin Building, Sheva, Uran, Navi Mumbai , has filed a Petition on 12 January, 2018 under Sections 14, 16 and 181 of Electricity Act, 2003 (EA, 2003) for taking on record its deemed Distribution Licensee status for the SEZ being developed at Village Sheva, Navi Mumbai and for issuing the Specific Conditions of Distribution Licence applicable to it. 2. JNPT s prayers are as follows: i) To take on record the Deemed Distribution Licensee status of the Petitioner, M/s. Jawaharlal Nehru Port Trust, under Section 14 of the Electricity Act, 2003 and Section 49 of SEZ Act, Order in Case No. 47 of 2018 Page 1 of 6
2 ii) To Issue Specific Conditions of Distribution License applicable to the Petitioner, M/s. Jawaharlal Nehru Port Trust. iii. To approve the provisional tariff equivalent to MSEDCL tariff for its area of supply. iv) To initiate the proceedings at the earliest to allow Petitioner to commence business operation from December 2018 onwards. v) Condone any inadvertent omissions/errors/shortcomings and permit the Petitioner to add/change/modify/alter this filing and make further submissions as may be required at a future date. vi).pass such orders as the Hon'ble Commission may deem fit as per the facts of the present case. 3. The Petition states that: 3.1 JNPT is a major port notified under Major Port Trusts Act, 1963 having its registered office at Jawaharlal Nehru Port Trust, Admin Building, Sheva, Uran, Navi Mumbai JNPT is developing a Port based multi product SEZ on Hectares of land at JNPT along the Panvel Uran Road connecting the cargo terminals to State highways. The focus of the SEZ is on collaborating upcoming sectors of India such as logistics, engineering goods, electronics, apparels and textiles and multi services sector among others. 3.3 JNPT has been notified as a Developer of said SEZ by the Ministry of Commerce and Industry, Government of India on 11 August, The SEZ is being developed over an area of Hectares situated in the villages of Savarkahar, Karal, Sonari and Jaskhar of Uran Taluka, Distt. Raigad of the Maharashtra. 3.4 Presently, JNPT SEZ is under various stages of development. Civil and electrical infrastructure work like development of internal distribution network and roads etc. has been allotted to EPC contractor through competitive bidding process and expected to be completed in December, The SEZ is expected to be operational by FY Vide Notification dated 3 March, 2010 under Section 49(1) (b) of the SEZ Act, 2005, the Ministry of Commerce and Industry (Department of Commerce), Government of India has specified that the developer of a SEZ is deemed to be a Distribution Licensee under the provisions of the EA, The SEZ has also received environmental clearance on 5 December, 2014 by State level Expert Appraisal Committee, Government of Maharashtra. 3.7 JNPT intends to expand its footprint by transforming itself into a global hub through creation of more value added services. The SEZ has been planned to be developed within the port area to ensure end-to-end facilities for export based industries including manufacturing, warehousing, assembly, packaging and finally shipment. The proposed SEZ is conceived to have all the integrated facilities. Order in Case No. 47 of 2018 Page 2 of 6
3 3.8 The proposed development is envisaged to be a port based multi product SEZ. The following sectors have been shortlisted for inclusion in the overall development plan based on their export potential and linkages to port: i. Engineering cluster ii. Textiles and apparel iii. Electronic manufacturing iv. Renewable energy v. Logistic Centre vi. Multi services/ ITES/Healthcare 3.9 The project area has been proposed to be developed with the optimal mix of export oriented sectors which will boost JNPT s overall objective of EXIM trade and a world class infrastructure To meet the obligations under Rule 5A of SEZ Rules, 2006 regarding providing 24X7 uninterrupted power supply within the area of supply, JNPT will have to undertake distribution activities under the provisions of the Electricity Act, The consumer base of a typical distribution licensee would be inclusive of diverse consumer categories i.e. residential, industrial, commercial, agriculture, public lighting, public works, railways etc. However, the SEZ at JNPT is unlikely to include the entire consumer mix of a typical distribution licensee and may be limited to residential, commercial, industrial and public services As per Sections 16 and 181 of the EA, 2003 and Regulation of the MERC (General Conditions of Distribution Licence) Regulations, 2006, the Commission is empowered to issue Specific Conditions of Licence to a Licensee or a class of Licensees, and these conditions shall be deemed to be the conditions of such Licence The Commission is requested to issue Specific Conditions of Distribution Licence applicable to JNPT SEZ. The notified SEZ area for JNPT may be specified as an area of supply in its Specific Conditions of Distribution Licence. Also, the term of Licence may be specified as 25 years from 11 August, 2014 i.e. the date of SEZ notification Regulation 5 of MERC (Multi Year Tariff) Regulations, 2015 allows the deemed Distribution Licensee whose Tariff is yet to be determined, to recover provisional Tariff in its area of supply as follows: Provided that, in case of a Deemed Distribution Licensee whose tariff is yet to be determined by the Commission till March 31, 2016, the Commission may relax the timelines for submission of the Multi-Year Tariff Petition, Midterm Review Petition and Truing-up Petitions, in case such specific relaxation is sought by such Distribution Licensee: Order in Case No. 47 of 2018 Page 3 of 6
4 Provided further that such Deemed Distribution Licensee may be permitted to first file a Petition for approval of a ceiling or other provisional tariff in its area of supply, followed by a Petition for approval of Power Purchase Agreement or arrangement, after which the Multi-Year Tariff Petition may be filed : 3.15 JNPT shall submit separate Petitions as per the above provisions of MYT Regulations, 2015 for approval of power procurement and determination of Tariff However, till filing the specific Petition for Tariff determination, JNPT requests the Commission to allow to charge provisional Tariff equivalent to the Tariff of MSEDCL in its area of supply for the first year and any difference in the revenue may be adjusted at the time of filing of the MYT Petition. 4. The hearing in the matter was held on 10 June, At the hearing, representative of JNPT reiterated its submission in the Petition and requested the Commission to take on record its deemed Distribution Licensee status. 5. Vide its submission dated 10 June, 2018, JNPT informed that it is in process of engaging M/s. PTC India Ltd. as a consultant for preparation of the power purchase plan and other relevant documents. PTC will be assisting JNPT in preparation of Network Roll-out Plan, Business Plan, Power Purchase Plan, Detailed Project Report including consumer related details, load profiling etc. With this approach, JNPT would be able to submit all the required documents and comprehensive reports of power distribution business. Commission s Ruling:- 6. The Commission notes that, vide Gazette Notification No. S.O. 2047(E) dated 11 August, 2014, the Ministry of Commerce and Industry (Department of Commerce), Government of India has notified JNPT as the developer for the SEZ on Hectares of land at JNPT along the Panvel Uran Road in the villages of Savarkahar, Karal, Soneri and Jaskhar, Taluka Uran, District Raigad in the State of Maharashtra. 7. The EA, 2003 was amended through Notification dated 3 March, 2010 to add a proviso to Section 14 (b): 14. Grant of Licence The Appropriate Commission may, on an application made to it under section 15, grant a licence to any person a. To transmit electricity as a transmission licensee: or b. To distribute electricity as a Distribution Licensee; or : Provided that the Developer of a Special Economic Zone notified under sub-section (1) of Section 4 of the Special Economic Zones Act, 2005, shall be deemed to be a licensee for the purpose of this clause, with effect from the date of notification of such Special Economic Zone; " Order in Case No. 47 of 2018 Page 4 of 6
5 8. JNPT has also submitted the map of the SEZ area, certified by the Office of the Development Commissioner, SEEPZ SEZ, Mumbai. 9. Considering the proviso introduced to Section 14(b) of the EA, 2003, the Commission hereby confirms the status of JNPT as the deemed Distribution Licensee for this SEZ area under Section 14 of the EA, As deemed Distribution Licensee, JNPT shall have to adhere to the following: (1) The relevant provisions of the EA, 2003 and the applicable Rules, Regulations and Orders issued thereunder; (2) Guidelines of the Commission for in-principle approval of its proposed capital investment schemes; (3) The provisions of the SEZ Act, 2005 and SEZ Rules, The Commission notes that JNPT has no Power Purchase Agreement (PPA) in place, for fulfilling its Universal Service Obligation. In order to do so in accordance with Section 43 of the EA, 2003, JNPT must make necessary filings for PPA approval and subsequent approval of its Aggregate Revenue Requirement (ARR) and Tariff to be paid by its consumers. JNPT has sought approval of a provisional Tariff to be levied to its consumers till the Petitions for PPA and ARR are filed by it and the respective approvals are in place. JNPT has sought the provisional Tariff for the first year equivalent to MSEDCL s Tariff for respective category of consumers. 12. Considering JNPT s proposal in this regard, the Commission is of the view that provisional Tariff may be allowed as an interim arrangement till the approval of ARR and Tariff are in place for JNPT. Licence area of JNPT overlaps with that of MSEDCL, which is the incumbent Distribution Licensee. The proviso to Section 62(1)(d) of the EA, 2003 provides that, in case of distribution of electricity in the same area by two or more Distribution Licensees, the Appropriate Commission may, for promoting competition among them, fix only the maximum ceiling of Tariff for retail sale of electricity. Accordingly, as an interim arrangement, the Commission allows JNPT to charge consumers in its Licence area the Tariff applicable to the respective categories of MSEDCL s consumers, as the ceiling Tariff. This provisional Tariff shall be valid for one year from the date of this Order. 13. JNPT has stated that it would submit a comprehensive report on its proposed distribution business. Same shall be submitted within 2 months of the Order. 14. JNPT is directed to submit its proposed timelines for further activities such as PPA filing, ARR filing, CGRF establishment etc. within fifteen days of the Order. 15. Under Section 16 of the EA, 2003, the Commission may specify general or specific conditions applicable to a Licensee, and these conditions shall be deemed to be conditions of its Licence. In view of the definition of the term specified in Order in Case No. 47 of 2018 Page 5 of 6
6 Section 2(62) of the Electricity Act, 2003, the specific conditions applicable to JNPT are required to be laid down by way of Regulations framed after previous publication, and the same cannot be stipulated through this Order. Accordingly, the Commission shall separately notify the Regulations specifying the specific conditions of Licence applicable to JNPT. Sd/- (Mukesh Khullar) Member Sd/- (Anand B. Kulkarni) Chairperson Order in Case No. 47 of 2018 Page 6 of 6
CASE No. 73 of hours for a period of six months from 1 April, 2019 to 30 September, Coram. I. M. Bohari, Member Mukesh Khullar, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCASE NO. 142 of Suo moto proceeding in the matter of Show-Cause Notice issued in Order dated 8 February, 2017 in Case No. 89 of 2015.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in
More informationCase No. 38 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in/mercindia@merc.gov.in
More informationCASE No. 103 of CASE No. 104 of 2016
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Maharashtra Electricity Regulatory Commission (Specific Conditions of Distribution Licence applicable to M/s. KRC Infrastructure and Projects Pvt. Ltd. for
More informationCASE No. 105 of Coram Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Transmission Co. Ltd.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/ 65/ 69 Fax No. 022 22163976 Email: mercindia@merc.gov.in
More informationCase No. 134 of CORAM Smt. Chandra Iyengar, Chairperson Shri. Azeez M. Khan, Member Shri. Deepak J. Lad, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationMERC (MULTI YEAR TARIFF) (FIRST AMENDMENT) REGULATIONS, 2017 STATEMENT OF REASONS
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Websites: www.mercindia.org.in
More informationCASE No. 150 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Vidarbha Industries Power Limited ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in
More informationCASE No. 107 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 125 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in
More informationCASE NO. 55 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. M/s Shah Promoters and Developers
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 170 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. I.M. Bohari, Member Shri Mukesh Khullar, Member ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre No. 1, 13 th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E mail: mercindia@merc.gov.in Website:
More informationCase No. 101 of Coram. Shri. Anand B. Kulkarni, Chairperson Shri. Mukesh Khullar, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCASE No. 113 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 56 of In the matter of Compliance of directives issued to MSEDCL under Order dated May 17, 2007 passed in Case No. 82 of 2006.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964-65-69 Fax 22163976 Email: mercindia@mercindia.org.in Website:
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationCase No. 24 of In the matter of Application of Reliance Infrastructure Ltd. for Amendment of Transmission Licence No.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 27 of In the matter of
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationTRANSMISSION LICENCE NO. 2 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 E-mail: mercindia@merc.gov.in Website:
More informationVidarbha Industries Power Limited - Transmission
Vidarbha Industries Power Limited - Transmission Revised Petition towards: Approval of Capital Cost and Determination of Aggregate Revenue Requirement ( ARR ) for the period FY 14-15 to FY 15-16 Filed
More informationShri Azeez M. Khan, Member Shri Deepak Lad, Member. The Tata Power Company Ltd. Maharashtra State Electricity Distribution Co. Ltd.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in
More informationCase No. 52 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationCase No. 129 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationCase No. 61 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationCase No. 52 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Mahati Hydro Power Projects Pvt. Ltd.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 19 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai- 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No. 1, 13th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/ 65/ 69; Fax 022 22163976 E-mail: mercindia@merc.gov.in
More informationGovernment of India Ministry of Commerce & Industry Department of Commerce Directorate General of Foreign Trade New Delhi
Export & Import Misc. Notification (Sl. No. 8) Government of India Ministry of Commerce & Industry Department of Commerce Directorate General of Foreign Trade New Delhi Dated 16th March, 2007 S.O. 393
More informationBefore the. Case No. 75 of 2007
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail: mercindia@mercindia.org.in
More informationCase No. 113 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in
More informationCASE No. 28 of Dr Pramod Deo, Chairman Shri A. Velayutham, Member ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005. Tel. 22163964 / 22163965, Fax No. 22163976 E-mail mercindia@mercindia.com
More informationCASE No. 2 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationMYT PETITION FOR JUBILANT INFRASTRUCTURE LTD
BEFORE THE HON BLE GUJARAT ELECTRICITY REGULATORY COMMISSION AHMEDABAD Filing No. Case No.. /2012 IN THE MATTER OF Filing of Petition under section 62 of the Electricity Act, 2003 for Aggregate Revenue
More informationTAMIL NADU ELECTRICITY REGULATORY COMMISSION (Constituted under section 82 (1) of the Electricity Act, 2003) (Central Act 36 of 2003)
TAMIL NADU ELECTRICITY REGULATORY COMMISSION (Constituted under section 82 (1) of the Electricity Act, 2003) (Central Act 36 of 2003) PRESENT: Thiru S.Akshayakumar Thiru G.Rajagopal Dr.T.Prabhakara Rao
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: mercindia@merc.gov.in Website:
More informationCASE No. 121 of and. M. A. No. 11 of 2015
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 3 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member. Reliance Infrastructure Ltd.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/ 65/ 69 Fax 022 22163976 Email: mercindia@mercindia.org.in
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017 ELECTRICITY ACT, 2003 No. MERC/Legal/2017/1771 - In exercise of
More informationCase No. 1 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationBEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL)
BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) REVISED PETITION FOR APPROVAL OF TRUE UP OF FY 2015-16 & FY 2016 17 AND PROVISIONAL TRUE UP of FY 2017-18
More informationDISTRIBUTION LICENCE NO. 1 OF 2011 LICENCE FOR DISTRIBUTION OF ELECTRICITY. Part I: General
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationMAHARASHTRA STATE POWER GENERATION COMPANY LIMITED (MSPGCL/MAHAGENCO)
MAHARASHTRA STATE POWER GENERATION COMPANY LIMITED (MSPGCL/MAHAGENCO) PETITION FOR CAPITAL COST AND TARIFF DETERMINATION FOR FY 2012-13 TO FY 2015-16 INCLUDING TRUE UP FOR FY 2012-13 &FY 2013-14 OF BHUSAWAL
More informationMERC Order on TPC-T s Petition for Truing up of ARR for FY and FY , and MTR for 3 rd Control Period. Before the
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in
More informationTRANSMISSION LICENCE NO. 1 OF 2009 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationCASE NO. 93 of Maharashtra State Electricity Distribution Co.Ltd. Maharashtra Energy Development Agency
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCASE No. 69 of In the matter of
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail: mercindia@merc.gov.in
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS,
Approach Paper for MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS, 2014 Issued By: Maharashtra Electricity Regulatory
More informationASSAM ELECTRICITY REGULATORY COMMISSION
ASSAM ELECTRICITY REGULATORY COMMISSION FILE NO. AERC. 511/2015 Petition No.: 14/2015 ORDER SHEET 21.12.2015 Before the Assam Electricity Regulatory Commission ASEB Campus, Dwarandhar, G. S. Road, Sixth
More informationThe Chief Engineer Maharashtra State Load Despatch Center Phone Fax Executive Summary MSLDC s Budget
Office of The Chief Engineer Maharashtra State Load Despatch Center Thane Belapur Road, Airoli, Navi Mumbai 400 708 (INDIA) (ISO 9001 2000 certified unit of Mahatransco) Phone (022) (O) 2760 1931 (P) 2760
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964/ 65/ 69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationGrievance No. K/E/953/1159/ ID No
Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph 2210707, Fax 2210707, E-mail : cgrfkalyan@mahadiscom.in No.EE/CGRF/Kalyan Zone/ Date
More informationORDER. Case No. 112 of 2008
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022-22163964/6569 Fax 022-22163976 Email: mercindia@mercindia.org.in
More informationIn the matter of Retrospective Recovery regarding IT/ITES Consumer
.(A Govt. of Maharashtra Undertaking) CIN: U40109MH2005SGC153645 PHONE NO. : 25664314/25664316 Consumer Grievance Redressal Forum FAX NO. 26470953 Vidyut Bhavan, Gr. Floor, Email: cgrfbhandupz@gmail.com
More informationTHE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY
THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY No. 419 9 Shrawan, 1932(s) Ranchi, Saturday 31th July, 2010 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION, RANCHI (RENEWABLE PURCHASE OBLIGATION
More informationCase No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationIN THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AT RANCHI. Case No. 12 of 2018, 13 of 2018, 14 of 2018 & 15 of 2018
IN THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AT RANCHI Case No. 12 of 2018, 13 of 2018, 14 of 2018 & 15 of 2018 Jharkhand Bijli Vitran Nigam Limited...... Petitioner CORAM: HON BLE MR. (DR)
More informationCase No. 30 of In the matter of Petition filed by MSETCL for approval of SLDC Budget for FY and FY
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationCASE No. 151 of 2017 CORAM. Shri Anand Kulkarni, Chairperson Shri Mukesh Khullar, Member. Maharashtra State Power Generation Co.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationPROCEEDINGS OF GOVERNMENT OF KARNATAKA
PROCEEDINGS OF GOVERNMENT OF KARNATAKA Preamble: Sub: State Policy for Special Economic Zones 2009 Ref: Govt. Order No. CI 252 SPI 2001 dated 25.2.2002. - - - The Government of India have announced the
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION, ITS COMPLIANCE AND IMPLEMENTATION OF RENEWABLE ENERGY CERTIFICATE FRAMEWORK)
More informationCASE No. 48 of In the matter of Appointment of Committee for study of subsidy, and related matters.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.com
More informationConsumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) Ph: & Ext: - 122
Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph: 2210707 & 2328283 Ext: - 122 IN THE MATTER OF GRIEVANCE NO. K/E/286/315 OF 09-10 OF
More informationExecutive Summary of Tata Power Generation True up Petition for FY as well as MYT Petition for FY to FY
Executive Summary of Tata Power Generation True up Petition for FY 2011-12 as well as MYT Petition for FY 2012-13 to FY 2015-16 Tata Power G Page 1 TABLE OF CONTENTS TABLE OF CONTENTS... 2 LIST OF TABLES...
More informationTariff order for Tata Steel for FY
Page 1 of 6 for Tata Steel for FY 2005-06 Jharkhand State Electricity Regulatory Commission (JSERC) SECTION 1: INTRODUCTION 1.1 About the Jharkhand State Electricity Regulatory Commission 1.1.1 The Jharkhand
More informationCase No. 66 of Smt. Chandra Iyengar, Chairperson Shri Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCASE NO. 196 OF In the matter of
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No. 1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022-22163964/65/69 Fax No. 022-22163976 Email: mercindia@merc.gov.in
More informationCASE No. 162 of In the matter of
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 206 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Company Limited
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR CASE NO: TP 59 / 13 14
ORDER OF THE WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR 2015 2016 IN CASE NO: TP 59 / 13 14 IN RE THE TARIFF APPLICATION OF THE WEST BENGAL POWER DEVELOPMENT CORPORATION LIMITED FOR THE
More informationCase No.39 of 2012 IN THE MATTER OF. Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail: mercindia@mercindia.org.in
More informationPower Purchase Obligation (Compliance by purchase of Renewable Energy/Renewable Energy Certificates) Regulations, 2012 (Regulation No. 1 of 2012).
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION RENEWABLE POWER PURCHASE OBLIGATION (COMPLIANCE BY PURCHASE OF RENEWABLE ENERGY/RENEWABLE ENERGY CERTIFICATES) REGULATIONS, 2012 Regulation No. 1 of 2012
More informationComments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018
Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018 S No. Existing provision/ Draft amended proposed Modified proposed
More informationCASE No. 24 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationCase No. 65 of In the matter of
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationBefore the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail: mercindia@mercindia.org.in
More information2011-TIOL-443-HC-MAD-CUS IN THE HIGH COURT OF MADRAS. C.M.A.No.3727 of 2004, W.P of 2011 and W.P of 1998 and CMP.No.
2011-TIOL-443-HC-MAD-CUS IN THE HIGH COURT OF MADRAS C.M.A.No.3727 of 2004, W.P.21054 of 2011 and W.P.12403 of 1998 and CMP.No.20013 of 2004 VETCARE ORGANIC PVT LTD Vs CESTAT, CHENNAI COMMISSIONER OF CUSTOMS,
More informationCase No. 26 of Shri. V. P. Raja, Chairman Shri. S. B. Kulkarni, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationBIHAR ELECTRICITY REGULATORY COMMISSION
BIHAR ELECTRICITY REGULATORY COMMISSION Bihar Electricity Regulatory Commission (Renewable Purchase Obligation, its Compliance and REC Framework Implementation) Regulations, 2010. NOTIFICATION The 16 th
More informationCase No. 158 of 2011 IN THE MATTER OF
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No. 1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in Case
More informationBefore the Appellate Tribunal for Electricity (Appellate Jurisdiction) Appeal no. 212 of 2013
Before the Appellate Tribunal for Electricity (Appellate Jurisdiction) Dated: 27 th October, 2014 Appeal no. 212 of 2013 Present: Hon ble Mr. Justice M. Karpaga Vinayagam, Chairperson Hon ble Mr. Rakesh
More information1 Grievance No. K/E/847/1035 of & No. K/E/848/1036 of
1 Grievance No. K/E/847/1035 of 2014-15 & Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph 2210707, Fax 2210707, E-mail : cgrfkalyan@mahadiscom.in
More informationGrievance No. K/E/1160/1381 of
Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph 2210707, Fax 2210707, E-mail : cgrfkalyan@mahadiscom.in No. K/E/1160/1381 of 2016-17
More informationMAHARASHTRA STATE POWER GENERATION COMPANY LIMITED Plot No. G-9, Prakashgad, Bandra (E), Mumbai Website:
MAHARASHTRA STATE POWER GENERATION COMPANY LIMITED Plot G-9, Prakashgad, Bandra (E), Mumbai 400051 Website: www.mahagenco.in PUBLIC NOTICE Inviting Suggestions/Objections on Maharashtra State Power Generation
More informationCase No. 62 of Shri. V. P. Raja, Chairman Shri. S. B. Kulkarni, Member Shri. V. L. Sonavane, Member ORDER
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationCase No. 62 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai - 400 005 Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in
More informationTRIPURA ELECTRICITY REGULATORY COMMISSION
TRIPURA ELECTRICITY REGULATORY COMMISSION No.F.25/TERC/2009/484 Dated, Agartala, the 9th November,2009 NOTIFICATION OF (RENEWABLE PURCHASE OBLIGATION AND ITS COMPLIANCE) REGULATIONS, 2009. In exercise
More informationM/S. ABHIMAAN MATERNITY & SURGICAL HOSPITAL THANE, MAHARASHTRA... (Hereinafter referred as Applicant)
PHONE NO. : 25664314/25664316 FAX NO. 26470953 Email: cgrfbhandupz@gmail.com.(a Govt. of Maharashtra Undertaking) CIN : U40109MH2005SGC153645 Consumer Grievance Redressal Forum Vidyut Bhavan, Gr. Floor,
More informationBRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST)
BRIHANMUMBAI ELECTRIC SUPPLY and TRANSPORT UNDERTAKING (BEST) EXECUTIVE SUMMARY OF Annual Performance Review for FY 2008-09 & ARR for FY 2009-10 along with Truing Up of Accounts for FY 2007-08 TO Maharashtra
More informationCase Nos. 157, 166 of 2016 and Case No 18 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. CASE No.
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:
More informationKandla Port Trust (KPT)
GUJARAT ELECTRICITY REGULATORY COMMISSION Tariff Order For Kandla Port Trust (KPT) Case No. 1474 of 2015 23 rd April, 2015 6 th Floor, GIFT ONE, Road 5C, GIFT City, Gandhinagar 382335 (Gujarat) India Phone:
More informationBIHAR STATE ELECTRICITY BOARD
BEFORE THE BIHAR ELECTRICITY REGULATORY COMMISSION PATNA CASE NO: Filing of the Review Petition for FY 2011-12 and Aggregate Revenue from Charges or Aggregate Revenue Requirement (ARR) & Tariff Petition
More informationMeghalaya State Electricity Regulatory Commission
Meghalaya State Electricity Regulatory Commission SHILLONG Notification Dated: 12 th March, 2015 No.MSERC/RPO/2015/02: In exercise of power conferred under section 61, 66, 86(1)(e) and 181 of the Electricity
More informationFILED BY MEGHALAYA POWER DISTRIBUTION CORPORATION LIMITED. Lum Jingshai, Short Round Road, Shillong
BEFORE MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION, SHILLONG PETITION FOR APPROVAL OF DISTRIBUTION OPEN ACCESS CHARGES FOR FY 2015-16 FILED BY MEGHALAYA POWER DISTRIBUTION CORPORATION LIMITED Lum
More informationMAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in Case No.
More informationGUIDELINES FOR DEVELOPMENT OF SPECIAL ECONOMIC ZONES (SEZs)
GUIDELINES FOR DEVELOPMENT OF SPECIAL ECONOMIC ZONES (SEZs) 1. BACKGROUND: India was one of the first in Asia to recognize the effectiveness of the Export Processing Zone (EPZ) model in promoting exports,
More informationMEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION
MEGHALAYA STATE ELECTRICITY REGULATORY COMMISSION Tariff Order For True up for FY 2014-15 And Annual Revenue Requirement & Transmission Tariff For FY 2017-18 MEGHALAYA POWER TRANSMISSION CORPORATION LIMITED
More informationMadhya Pradesh Poorv Ksthera Vidyut Vitaran Company Limited