IN THE COURT OF APPEAL OF NEW ZEALAND CA453/2012 [2013] NZCA 70. VIKRAM KUMAR AND NIRUPAMA KUMAR First Respondents

Size: px
Start display at page:

Download "IN THE COURT OF APPEAL OF NEW ZEALAND CA453/2012 [2013] NZCA 70. VIKRAM KUMAR AND NIRUPAMA KUMAR First Respondents"

Transcription

1 IN THE COURT OF APPEAL OF NEW ZEALAND CA453/2012 [2013] NZCA 70 BETWEEN AND AND AND STATION PROPERTIES LIMITED (IN RECEIVERSHIP AND LIQUIDATION) Appellant VIKRAM KUMAR AND NIRUPAMA KUMAR First Respondents ROBERT JAMES SELWYN Second Respondent MICHAEL DONALDSON AND PATRICIA BRONWYN DONALDSON Third Respondents Hearing: February 2013 Court: Counsel: Judgment: O'Regan P, Randerson and Asher JJ M J Tingey and S V East for Appellant R M Kelly and K J Jarvis for Respondents 20 March 2013 at 11:00am JUDGMENT OF THE COURT A B C D The appeal is allowed. It is declared that the appellant was entitled to cancel the transactions on the grounds of repudiation by the respondents. The case is remitted to the High Court for determination of the damages issue. The respondents jointly and severally must pay costs to the appellant as for a standard appeal on a Band A basis with usual disbursements. We certify for second counsel. STATION PROPERTIES LIMITED (IN RECEIVERSHIP AND LIQUIDATION) v KUMAR AND KUMAR COA CA453/2012 [20 March 2013]

2 REASONS (Given by Randerson J) Table of Contents Para No Introduction [1] Issues on appeal [15] The facts in more detail The terms of the side agreements [18] The Practical Completion Certificate (PCC) [25] Factual conclusion on practical completion [34] Events from July 2008 onward [38] Station s calls for settlement and the responses from the [44] respondents Mr and Mrs Kumar [45] Mr Selwyn [51] Mr and Mrs Donaldson [58] Was there any justification for the respondents repudiation of [67] the transactions? The PCC issue [68] The one per cent fee [71] The furniture package [73] The management agreements [75] The sunset clause [80] Was Station ready, willing and able to proceed with the [82] transactions? Conclusion on the contractual issues [86] Was there any basis for the Judge s conclusion in relation to [87] Mr Kumar s affirmative defence? Summary and disposition [94] Introduction [1] This appeal arises from a dispute over an apartment development in Queenstown known as Bowen View. The appellant Station Properties Ltd (Station) was one of a group of companies controlled by Mr Daniel McEwan and was responsible for the development, construction and sale of the apartments. [2] In May 2006 the respondents each entered agreements for sale and purchase (ASPs) to buy an apartment in the complex to be built in accordance with plans and

3 specifications identified in the ASPs. 1 The agreed sale prices were: First Respondents (Mr and Mrs Kumar) Second Respondent (Mr Selwyn) Third Respondents (Mr and Mrs Donaldson) $1,135, plus GST $1, plus GST $ 880, plus GST [3] Prior to the ASPs being signed, the respondents alleged that representations were made to them by or on behalf of Station about the terms of the proposed sales. They also asserted that certain additional terms were agreed to. These were not mentioned in the ASPs but, in summary were that Station would: Pay a fee of one per cent of the purchase price to each of the respondents in consideration of their signing the ASPs. Provide furniture for each apartment. Arrange a management agreement for all apartments in the complex. [4] Each of the respondents also alleged that they were told the ASPs were underwrite agreements and that they would not be required to settle the purchases since Station s intention was to sell the entire complex to a single purchaser upon completion of construction. The respondents alleged Mr McEwan (or others on his behalf) told them that the ASPs were required to enable Station to satisfy the requirements of the principal funder, Bank of Scotland International (Australia) Ltd (BOSI). [5] The ASPs contained a number of special conditions. Settlement was to occur five working days after the last of the following events: The date of issue of unit titles; The date of Practical Completion as defined; or The date of issue of code compliance certificates. 1 The complex was to comprise 25 apartments and 3 houses. A number of other apartments in the complex were sold but these sales are no longer in issue.

4 [6] The term Practical Completion was defined to mean: that stage of construction when the Works are substantially complete so that the property is capable of being used for the purposes for which it is intended without material inconvenience notwithstanding that there may be items of a comparatively minor nature that require finishing, alteration or remedial action. 2 [7] The ASPs contained two unusual terms described in the evidence as a sunset clause and a gazump clause: 26.0 Sunset clause 26.1 If the vendor is not ready, willing and able to settle this agreement on or before 20 December 2007, then either party may, by notice in writing at any time thereafter, cancel this agreement and the purchaser shall be entitled to the return of the deposit together with Net Interest accrued and neither party shall have any right of claim against the other Vendor s right to cancel ( Gazump clause) 37.1 Notwithstanding anything to the contrary herein, the vendor shall have the right to cancel this contract without notice at any time. In the event of such cancellation, the purchaser shall not have any right to compensation of any sort whatsoever. [8] The sunset clause was later varied by agreement to extend the date to 13 March 2009 (12 months after the estimated completion date of 13 March 2008). [9] Station separately contracted with Fletcher Construction for the construction of the apartments which commenced in September By mid-2008, construction was nearing completion. From July that year, Station began communicating with the respondents about settlement. Station acknowledged to the respondents that the property market had become depressed by that time and that its efforts to sell the completed development to others had been unsuccessful. As well, Station was experiencing financial difficulties. [10] The respondents each obtained valuations which revealed that the current values of the units were substantially lower than the prices agreed in the ASPs two 2 The Works were defined as meaning construction generally in accordance with the agreed plans and specifications.

5 years before. [11] From August 2008, Station s solicitors began calling on the respondents to settle the ASPs. There is no dispute that titles and code compliance certificates had been issued. Station relied upon a practical completion certificate (PCC) issued by the quantity surveyors for the project (Maltbys) rather than by the architect designated in the ASPs (Leuschke Group Architects Ltd). It was not until much later that an issue was raised about the validity of the Maltbys PCC but it was to become a central feature of the High Court judgment under appeal as we later discuss. [12] Despite attempts by Station to secure settlement over the period from August to October 2008, this did not occur. The Judge found that the respondents refused or were not prepared to settle the transactions. In consequence, Station issued summary judgment proceedings against the respondents and other purchasers seeking orders for specific performance of the ASPs. Associate Judge Robinson declined summary judgment in December He found that the respondents had an arguable defence based on pre-contractual misrepresentation under the Fair Trading Act [13] After Station issued its proceedings in the High Court, it was placed into receivership by BOSI on 20 April When the summary judgment application was dismissed in December of that year, Station s solicitors wrote to the respondents solicitors in February 2010 advising them that unless the respondents settled the ASPs, they would be treated as having repudiated the agreements. Settlement did not proceed and Station cancelled the ASPs on 6 April 2010, reserving the right to recover damages from the respondents. [14] The final step in this outline of the key facts is the judgment under appeal given by Toogood J on 29 June 2012 upon the substantive hearing of Station s proceedings. 4 The principal findings by the Judge were: The additional terms identified in [3] above were terms of the overall agreement between the parties. (We will call these additional terms the side agreements.) 3 4 Station Properties Ltd v Lever Action Ltd HC Auckland CIV , 17 December Station Properties Ltd (in rec) v Kumar [2012] NZHC 1527.

6 The gazump clause meant it could only be exercised if the vendor received an offer from a third party for the same price or a greater price with any profit being shared with the relevant respondents. 5 The time for settlement of the ASPs had never arrived because the Maltbys PCC did not comply with the contractual terms since the ASPs required the PCC be issued by Leuschke Group. Station had repudiated the ASPs by requiring the respondents to settle before the contractual settlement date. Station was never ready, willing and able to settle since it was unable to fulfil its obligations under the side agreements. Station s breach of the side agreements was material and substantial. Cancellation of the ASPs by the respondents was justifiable for breach by Station as well as on the grounds of repudiation by Station. Although not necessary to consider the affirmative defences raised by the respondents, the Judge said he would have granted remedies to Mr Kumar (but not to the Donaldsons or Mr Selwyn) under the Contractual Remedies Act 1979, based on pre-contractual representations by a Mr Charlett on behalf of Station. Issues on appeal [15] As is so often the case, the arguments in this Court have shifted somewhat from those focused upon in the High Court. It is no longer in dispute that: The side agreements did constitute contractual terms. The Maltbys PCC did not conform to that required by the ASPs. The time for settlement did not arrive before the ASPs were cancelled. 5 The Judge s interpretation of this clause is not challenged.

7 [16] Unlike the argument in the High Court, the focus of the argument before us was on the repudiatory conduct of the respondents. The essence of Mr Tingey s argument for Station is straightforward: By their conduct in the period July to October 2008 and thereafter, the respondents each repudiated the ASPs by demonstrating they did not intend to complete them (whether the time for settlement had arrived or not). The respondents had no justification for repudiating the ASPs since Station was not in material breach of the ASPs or the side agreements. The apartments were, as a matter of fact, practically completed by mid Station was, at relevant times, ready, willing and able to settle (or could have done if the validity of the PCC and the alleged breaches of the side agreements had been drawn to its attention or relied upon by the respondents at the time they were refusing to settle or to proceed with the ASPs). Station was entitled to cancel for repudiation by the respondents and to recover damages for its losses. There is no basis in law or fact for the Judge s conclusion in relation to Mr Kumar s affirmative defence arising from pre-contractual representations. [17] On behalf of the respondents Ms Kelly supported the High Court decision, substantially for the reasons the Judge gave. The facts in more detail The terms of the side agreements [18] We have already set out the key terms of the ASPs but it is necessary to discuss the terms of the side agreements by reference to relevant documentary

8 material. In an sent to the respondents on 20 September 2005 Station advised: The design has been altered to allow for a management arrangement to be run from House 3. This means the management rights will be sold to the highest bidder (around $25,000 per unit is the market rate) providing further income to the company. The sale and purchase contracts do not include a management agreement at this stage, however this will be made available during construction, along with the furniture package. (This will be past onto the company at cost plus 10% - we will fly to Italy and import the majority of these items.) [19] The same recorded that: As an incentive to purchase, the project will pay a 1% purchasers fee (of the unit price only), pre settlement. 6 [20] In a letter of 20 September 2005 accompanying the ASPs for signature, Station advised the respondents: The sale agreement needs to include the furniture package/airconditioning/heating package. Full lists of the contents of this item will be made available and as you are a shareholder will be at cost plus 10%. We have set a budget and will work to this. The public will pay a marked up price determined by a third party valuation (this is clearly more profit to the project). The vendor intends to arrange for the benefit of its shareholders as an option a serviced apartment management agreement. Decisions to be considered would be a number of weeks for personal usage, operator and brand, and weather [sic] the income would be pooled or tied to each unit. If pooled this would require a prospectus. [21] These issues were put slightly differently in instructions given to the respondents as to how to execute the ASPs: Prior to completion, an up to date furniture package arrangement, along with air-conditioning and heating, will be mandatory. A property management agreement will be offered pre settlement, we expect settlement to be approximately April [22] The intention to provide a furniture package was confirmed in a price list for the apartments as at September 2005 which described a furniture package as being mandatory. The price was to be available six months prior to completion. The 6 It is accepted that Mr Kumar s arrangement was slightly different. In his case, it was agreed that the one per cent purchasers fee would be paid upon the first construction drawdown under the Fletchers building contract.

9 price list added $30,000 for the furniture package to the price otherwise applicable to each apartment. [23] Mr Tingey pointed out that cl 28.2 of the ASPs provided that: The vendor may procure the body corporate to enter into a Building Manager s Agreement, in the same or similar form enclosed, with a professional building management company to be nominated by the vendor prior to settlement date. [24] We accept that the precise nature of any obligation on the part of Station to provide a management agreement is ambiguous and that it is reasonably arguable that the contractual term set out in the ASPs should override any other representations made prior to the execution of the ASPs. However, for reasons we later discuss, we do not think it matters whether there was a contractual obligation to provide a concluded management agreement at the time of settlement or whether (as Mr Tingey submitted) Station had the option of procuring a management agreement if it chose to do so. Nor do we think it matters whether Station s only obligation (at best) was to nominate a building management company prior to settlement. The Practical Completion Certificate (PCC) [25] On 29 and 30 May 2008 Mr Cocker of Leuschke Group inspected the apartments and prepared a lengthy list of items remaining to be completed. His evidence was that it would take at least three weeks to complete the list of outstanding matters. On 19 June 2008 another Leuschke employee (Mr Reeve) made a brief inspection of part of the site while on a visit to Queenstown for other purposes. In consequence of this inspection, Mr Cocker wrote on 24 June 2008 to Station s project manager (Insignis Ltd) and Mr Dawson of Maltby s: RE: BOWEN VIEW APARTMENTS PRACTICAL COMPLETION. Milton Reeve, from our office, carried out a brief inspection of part of the site on Thursday, 19 th June We have attached a list of some items observed on the 19 th June We have looked at the photographs he took on that day and note that there are still work items to be carried out (such as toilets not working) that we would consider need to be complete prior to the buildings being practically

10 complete. There is also evidence of further remedial work now being required as a result of completion work carried out since our previous visit. To be practically complete, the buildings should be suitable for occupation with only minor remedial work being required, and the remedial work should not be of a nature that would be disruptive to the occupation of the building. If the construction contract does not have provision for sectional practical completion, then the entire project has to be practically complete before you can issue your certificate. It appears to us that the works are still not at that stage. Yours faithfully LEUSHKE GROUP LIMITED. [26] The list attached referred to some outstanding matters noted by Mr Reeve on his 19 June visit. This did not purport to be a full inspection but covered one of the three houses and some of the apartments. We note however that, by the time of Mr Cocker s letter of 24 June 2008, more than three weeks had gone by since Mr Cocker s 29 and 30 May inspections. [27] Despite Mr Cocker s letter of 24 June, Mr Dawson of Maltby s wrote to Station and Fletcher Construction on 2 July 2008 stating: 7 This is to certify that in accordance with clause 10.4 of the conditions of the Contract, Practical Completion of 24 units and 3 houses was achieved on 3 June Outstanding defects are noted on the attached schedules and will need to be resolved within the 12 week period. This certificate does not warrant that the works have been completed as designed, marketed or in accordance with relevant laws or standards, but merely that the building is on the whole fit for occupation. Refer to attached Queenstown Lakes District Council Code Compliance Certificate for compliance with the Building Act [28] The code compliance certificates and the long list of outstanding matters prepared by Leuschke Group earlier and dated 30 May 2008 were attached to Mr Dawson s letter. 7 The reference to 24 units was a typographical error.

11 [29] In evidence, Mr Dawson readily accepted that his role was to keep an overview of the construction contract as the designated Engineer to the Contract. His qualifications were as a quantity surveyor of some 20 years experience. He readily accepted he was neither an engineer nor an architect by qualification and that he looked to Leuschke Group for advice as to the state of completion of the project for the purpose of the ASPs. As his letter stated, his PCC was for the purposes of cl 10.4 of the conditions of the building contract with Fletchers. [30] Mr Dawson was pressed in cross-examination about whether he had ticked off the defects listed following the 29 and 30 May inspections by Leuschke Group. He said he had done so after 19 June although he did not have with him any evidence to support a formal inspection. Nevertheless, he had visited the site once per week during this period. [31] He was asked about one of the matters Mr Reeve had found to be outstanding (toilets not working) and explained that the reason for that was that the water had been turned off to avoid the water freezing in the pipes during the Queenstown winter. There was some suggestion in the evidence that the failure of the toilets to operate might have been because of the absence of the operating button but, whatever the cause, this was clearly a matter which could have been quickly and easily remedied. [32] Mr Dawson was also asked about a missing handrail on an internal stairway. He accepted that this was the only item which was more than minor in his opinion. He was sure that he had contacted the builder to make sure it was installed. Other than this item, he regarded all the defects listed as minor and maintained his view that, at least for the purposes of the construction contract, the development was practically complete as he certified on 2 July. [33] Mr Cocker was called at trial for the respondents. He confirmed his view that, as at 24 June 2008, he did not consider the construction of the complex was practically complete in terms of the definition contained in the ASPs. He added that Leuschke Group had not undertaken any further complete inspections thereafter and

12 did not at any time issue a PCC. However, in cross-examination, Mr Cocker accepted that the bulk of the items on the list prepared at the time of the 29 and 30 May inspections were minor items capable of being remedied fairly quickly and easily. There was no structural work required. He mentioned an issue over a sheet of roofing material which had been more than minor but could not recall whether this was still at issue by the time of the preparation of the list on 30 May. Since Leuschke Group were based in Auckland, he had attended only two of the monthly project meetings during construction. These meetings took place in Queenstown and were chaired by Mr Dawson. He accepted that the local authority had issued code compliance certificates for the development on 1 July He also accepted it was likely the missing stair handrail had been attended to before the code compliance certificate was issued since it was a building code requirement. He agreed that the other issues identified by Mr Reeve in his 19 June visit were all minor items that could be fixed comparatively easily and quickly. He had no reason to suppose that they were not promptly attended to. Factual conclusion on practical completion [34] Because of the way the case developed in the High Court, the Judge did not make any factual finding as to whether, in substance, the construction of the apartments was complete in accordance with the plans and specifications appended to the ASPs. Rather, his focus was on the technical issue of whether the PCC conformed with the requirements of the ASPs. Since it was issued by Maltby s and not by the Leuschke Group as required, he found that it did not conform to the contract. In consequence, the settlement date did not arrive. [35] On our own review of the evidence, we find that the apartments were substantially complete no later than mid-july 2008 and probably earlier than that date. A full month had gone by since Mr Cocker s estimate that it would take at least three weeks to address the list of items outstanding from the inspections on 29 and 30 May; the local authority had issued its code compliance certificates on 1 July; Mr Dawson s clear evidence was, that at least for the purposes of the construction contract, he was satisfied the works were substantially complete when he issued his PCC on 2 July 2008; and despite the contrary view expressed by Mr Cocker in his

13 24 June letter, Mr Cocker accepted there was no reason to suppose that the matters outstanding at that date had not been attended to. [36] In any event, Mr Cocker accepted that all of the items identified from the inspections on 29 and 30 May and 19 June were minor matters, easily fixed. The only exceptions were the handrail and the functioning of the toilets. The handrail must, on the balance of probabilities, have been completed before the code compliance certificate was issued by the local authority on 1 July. The non-functioning of the toilets was explained either on the simple basis that the water was turned off or because of the absence of the relevant operating buttons. On any view, this was not a significant issue. [37] We consider we are entitled to place weight upon Mr Dawson s evidence in reaching our factual conclusions. Both Station and Fletcher Construction had sufficient confidence in his experience and ability to appoint him as the contract engineer for the purposes of the construction contract. He visited the site much more frequently than the representatives of the Leuschke Group and was in the best position to judge the state of completion of the project. We accept there were some slight differences in the definitions of practical completion for the purposes of the ASPs and the construction contract but our conclusion is one of substance rather than technical compliance with the strict definitions. Events from July 2008 onward [38] On 15 July 2008 Mr McEwan wrote to each of the respondents. He said: we have been advised by our contractors that we now have practical completion and Code Compliance for the apartments at Bowen View. Therefore we are only waiting on the Issue of titles before we are able to call for settlement. We expect that titles may be available by 31st July [39] The letter went on to set out the amount required for settlement and advised that Station might be in a position to call for settlement in approximately three weeks time. Mr McEwan recommended that the respondents make immediate arrangements for any finance required to settle the purchase and to advise their solicitors accordingly.

14 [40] On 22 July 2008, a solicitor employed by the McEwan Group (Ms Zamiri) wrote to the respondents advising, amongst other things: Management/Operator Select Hotels remain our operator of choice, however it is unlikely that any agreement will be reached before settlement is called for. The construction funder is not prepared to purchase furniture for the unsold units, which would leave the operator with insufficient units to run an efficient operation. In terms of obtaining mortgage finance, this means the units will not be managed at the time of settlement. Purchasers will thus be able to borrow a higher percentage against valuation, but GST is payable on the purchase price. GST is payable because this was always designed and consented to be a managed complex and as such attracts GST. If a management agreement is put in place in the future, GST registered owners can claim GST back. Furniture We are still negotiating with the funder regarding those purchasers whose contracts included furniture packages. Settlement Timing Those investors who have committed to the purchase of a unit via a Sale and Purchase agreement should be well down the path of organising finance by now, in anticipation of settlement around mid August. The Sale and Purchase agreement specifies a period of 5 working days after the issue of the latter of: title, code compliance or practical completion. Code Compliance and Practical Completion have been issued. Titles are currently being prepared expected first week of August. The vendor s solicitor will then call for settlement, with 5 days available to settle without incurring any penalty interest. Unless a magic bulk buyer is found very soon, the financier will require these investors to settle their obligations. [41] On 7 August 2008 Station s solicitor, Mr Jeremy Goodwin of Carter Atmore wrote to the solicitors for each of the respondents enclosing a copy of the title, copies of the code compliance certificates and the Maltby s PCC. The list of matters requiring attention as at 30 May prepared by Leuschke Group was not attached to the PCC. Mr Goodwin advised that the settlement date was 14 August 2008 and that a settlement statement would follow shortly. [42] On 13 August 2008, Ms Zamiri ed Ms Ruediger (the Associate Director, Corporate and Property Finance within BOSI):

15 Before settlement notices can be issued, several outstanding issues need to be resolved. These are: 1. Furniture packages to be provided or credited? 2. Body Corporate About Body Corporates is unable to accept our invitation to be the Body Corporate. We need to approach Strictly Body Corporates, however there needs to be an assurance that the Body Corporate levies will be forthcoming from the remaining unsold units. 3. Management agreement purchasers need to know if there will be an operator in place or not. In particular this relates directly to Unit 26 s agreement. 4. Underwrite fees will these be able to be credited on settlement? 5. 1% purchasers fees will these be able to be credited on settlement? I would be grateful if you could clarify any or all of these issues for me. My understanding has been that you have been liaising with Steve [Groves] on some of the above but I haven t been privy to any updates. [43] This drew a stern response from Ms Ruediger on 21 August 2008: BOS was not aware of any underwrite/purchaser fees nor was Tony Dawson who has confirmed that they were not included within the marketing & sales commissions budget. Furthermore, the S&P agreements do not detail such fee arrangements. Hence, no set off will be made at settlement. You should provide me with any side agreements (which agreements, you should note, will be in breach of BOS facility agreement given they were made without our prior consent) sooner rather than later I need to know what we are potentially dealing with here and report the situation to HBOSA Credit. Needless to say, Credit will not be forgiving in this regard and we will be pushing back on any set offs claimed, to the legal extent that we can. Station s calls for settlement and the responses from the respondents [44] Station s solicitors called for settlement by letters issued on 23 September 2008, 9 October 2008 and 10 October 2008 including the issue of settlement notices. Despite this, none of the respondents made any attempt to settle the transactions at any time, even after the appointment of receivers for Station.

16 Mr and Mrs Kumar [45] Much of Mr Kumar s evidence on behalf of himself and his wife focussed on the alleged pre-contractual representations and his understanding that he had signed an underwriting agreement which would not require him to settle the ASP. His evidence was that it was not until receiving Station s letter of 15 July 2008 advising that a call for settlement would be made about the end of that month, that he and his wife had any idea they were expected to settle the purchase of the apartment under the ASP. He and his wife decided that they should investigate whether it would be a viable option for us to settle the purchase of the apartment and on-sell it to a third party, rather than to fight the plaintiff [Station] over its change of position. They obtained a valuation on 13 August 2008, valuing the unit at $535,000, less than half the sale price under the ASP. Mr Kumar said that the valuation was so low that he and his wife realised that settling the purchase was not a viable option. [46] After Station s second call for settlement in September 2008, Mr Kumar sent an to Mr Groves of Station on 29 September 2008: Our solicitor has been asked by your (Station Properties) solicitors to settle on Unit 24, Bowen View Apartments, Queenstown. We had underwritten this apartment but note that Station Properties has made almost no effort to sell this apartment, particularly when the market was positive. Nevertheless, as an attempt to find a compromise solution, we are able to settle and pay for this unit based on the attached valuation, i.e. our offer is $535,000 inclusive of GST, furniture package, and all other payments whatsoever (including any penalties, interest, etc.) but excluding Body Corporate levy and rates. Please let me know if this is acceptable. [47] There does not appear to have been any direct response in writing to Mr Kumar s proposal but it was never accepted. This was made clear on 9 October 2008 when Mr Goodwin wrote to the solicitors for Mr and Mrs Kumar calling for settlement and later issuing a formal settlement notice. In evidence, Mr Kumar said the key factors of concern to him were the alleged pre-contractual representations regarding his obligations to settle an ASP, the lack of effort by Station to sell the

17 apartment at an earlier stage, the loss of value of the apartment and the fact that they could not afford to proceed. Although Mr Kumar made enquiries at earlier stages about the one per cent fee due to him, this did not feature in his written communication to Station. There was no reference to the furniture package or the management agreement and no suggestion the building work was incomplete. [48] Much later, on 2 June 2010 (after Station s letter of 6 April 2010 cancelling Mr Kumar s ASP), new solicitors representing Mr and Mrs Kumar wrote to Station s solicitors purporting to cancel the ASP for breach of the obligation to pay the one per cent fee (amounting to $11, and due upon the first construction drawdown under the building contract). By then, on our view of the matter, the ASP had already been validly cancelled by Station. [49] It is not in dispute that if a party to a contract repudiates it by making it clear by words or conduct that he or she does not intend to perform the obligations under it, the opposite party may cancel the contract. 8 [50] We accept Mr Tingey s submission that Mr and Mrs Kumar clearly repudiated the ASP by refusing to recognise any obligation to settle and by offering instead to buy the apartment at the much reduced figure of $535,000. In doing so, Mr and Mrs Kumar were plainly evincing an intention not to proceed with the ASP in accordance with its terms or at all. Our conclusion in this respect is subject to any question of justification on the part of Mr and Mrs Kumar which we discuss below. Mr Selwyn [51] Mr Selwyn s evidence at trial bears a remarkable resemblance of that of Mr Kumar s. He too dwelt at length on the alleged pre-contractual representations and expressed shock at being advised in Ms Zamiri s of 16 July 2008 that he would be expected to settle the purchase as soon as titles were available. This was, he said, the first time he had any reason to believe that Station expected him to settle the purchase of the apartment. 8 Section 7(2) Contractual Remedies Act 1979 and see the discussion in Burrows Finn & Todd Law of Contract in New Zealand (4th ed, LexisNexis, Wellington, 2012) at [18.2].

18 [52] After receiving Mr Goodwin s letter of 7 August 2008 calling for settlement, Mr Selwyn ed Ms Zamiri on 8 August 2008 enquiring about the status of the deposit paid under the ASP and payment of the one per cent fee. Ms Zamiri responded on 11 August advising Mr Selwyn of the amount of the deposit held by Station s solicitors and advising that, in respect of the one per cent fee, it is likely that it may be able to be credited on your settlement statement. Mr Selwyn replied on 13 August. He did not raise any issue about the suggestion that the one per cent fee be credited on settlement but asked that a detailed list of chattels (including the furniture package) be provided and put in place prior to settlement. There was no suggestion the works were not complete. [53] Mr Selwyn said he too decided to obtain a valuation to see whether it would be a viable option to settle the purchase and sell it to a third party rather than getting into a dispute with Station over what he described as its change in position. On 26 August 2008 Mr Selwyn obtained a valuation of the apartment at $615,000 (or about 60 per cent of the price under the ASP. [54] On 29 August 2008 Mr Selwyn ed Ms Zamiri stating: I regret to advise that based on extensive discussions with my legal advisor and banker, I will not be in a position to settle on the above property. I have obtained an independent valuation from Colliers International who value the property at $ including GST compared to the original price of $ incl GST. Of note in the valuation is the observation that a number of the units in the development were sold at significantly higher levels off the plans two years ago. We consider these transactions were above the market at that time. The original intent of the contract was to onsell the apartments to an operator and this has not been done. Indeed, I understand that half of the apartments remain unsold. Accordingly, because I believe that the developer has not complied with its obligations under the Contract, I now wish to rescind the contract. This is without prejudice to any remedies I may have against the developer. [55] Ms Zamiri responded on 10 September 2008 advising that Station did not accept the rescission and that a settlement statement would be forwarded as soon as Station was in a position to call for settlement.

19 [56] Mr Selwyn s solicitors confirmed by letters of 12 and 24 September 2008 that, by reason of alleged failure by Station to comply with its obligations under the ASP, Mr Selwyn considered the contract to be at an end. We note that no specific reference was made in Mr Selwyn s of 29 August or his solicitor s letters the following month to the non payment of the one per cent fee or issues relating to furniture or the management agreement. Rather, as in Mr Kumar s case, the focus was on the substantial drop in value of the apartments since the ASP was first signed and the failure by Station to on-sell the apartments to a third party. [57] Assuming the absence of any legal justification for his stance, we are satisfied that Mr Selwyn s communications in August and September 2008 amounted to a repudiation of the ASP. He was clearly unwilling to proceed to complete the transaction and purported to rescind the contract. Mr and Mrs Donaldson [58] Mrs Donaldson gave evidence on behalf of herself and her husband at trial. She said she became concerned after receiving the from Station on 6 June 2008 that said, contrary to her previous understanding, she and her husband might be required to settle the purchase of the apartment. She and her husband obtained a valuation dated 9 July 2008 valuing the apartment at $595,000, a figure substantially lower than the purchase price under the ASP. Mrs Donaldson said that the valuation was obtained for the same reasons mentioned by Mr Kumar and Mr Selwyn in their evidence, namely to see whether settling and on-selling the apartment would be a viable alternative rather than entering a dispute with Station. However, once the valuation was obtained, Mr and Mrs Donaldson accepted that settling and on-selling was not realistic. [59] Mrs Donaldson said she had several conversations with representatives of Station including Mr Groves and Ms Zamiri. In late June 2008, she said Mr Groves informed her that it did not seem likely that a third party would purchase the entire development and that she and her husband would be required to settle the purchase. Despite Mrs Donaldson protesting that they had not agreed to settle the purchase, Mr Groves informed her they would need to do so if called upon.

20 [60] Following this discussion and after receipt of the letter from Station of 15 July 2008 suggesting that settlement about the end of July 2008 was likely, Mrs Donaldson telephoned Ms Zamiri. She told Ms Zamiri that, as underwriters, they never agreed to settle the purchase of an apartment and could not afford to do so even if they had wanted to. She said Ms Zamiri told her that things were going crazy there, that we should sit tight, that we should not settle. Ms Zamiri confirmed in her evidence for the respondents at trial that matters were in disarray at Station during this period and that there were financial difficulties. It was for that reason that she told Mrs Donaldson to sit tight but she did not agree that she told her categorically not to settle. She accepted she might have told Mrs Donaldson not to settle at that particular time because settlement statements had not been issued and because of other difficulties over matters such as the furniture packages and the fees due to the respondents. [61] Mrs Donaldson accepted in cross-examination that Mr Groves had told her she had to settle and of course she knew she was being required to settle as soon as Station s solicitors began demanding settlement. [62] Mrs Donaldson said she also raised concerns with Mr Groves about the failure to pay the one per cent fee and the failure to arrange the promised furniture package. She also referred to errors in the settlement statement issued by Station s solicitors in September and October At one point, a deduction appeared to have been made from the price to allow for the value of the furniture/airconditioning package but, at a later stage, this was adjusted to reflect the full purchase price for the apartment. Like the other respondents, it was never suggested by the Donaldsons that the building work was incomplete. [63] Mrs Donaldson said that she and her husband did not wish to own an apartment in Queenstown. If they had wished to do so, they would have purchased an apartment outright rather than entering into an underwriting agreement which she understood would not require them to settle. They could not afford to purchase the apartment which, by the time of settlement, was valued at a significantly lower figure than the purchase price Station was asking them to pay.

21 [64] In cross-examination, Mrs Donaldson acknowledged that she and her husband had never made a written offer to settle at a price that made allowance for the one per cent fee and the failure to deliver the furniture and a management agreement. Although she said she had told Mr Groves she was willing to discuss the matter, that did not occur. Ultimately, Mrs Donaldson acknowledged in her evidence that even if Station had offered to settle at a discount to reflect the one per cent fee and a discount for the furniture, she and her husband would not have been willing or able to settle the purchase. She volunteered that she and her husband never had any intention of settling even if Station had offered a discount for those matters. [65] We are satisfied that Mr and Mrs Donaldson clearly demonstrated that they had no intention of completing the ASP even if some allowance had been made for their matters of complaint with regard to the one per cent fee and the furniture package. The factors of concern to them were undoubtedly their belief that they were not obliged to settle the ASP; their appreciation (late in the piece) that they were being required to settle; and the intervening significant drop in the market value of the property which meant it could not be on-sold and that they could not afford to buy it. These factors, combined with the continuing failure by the Donaldsons to respond to subsequent calls for settlement and the settlement notices issued by Station confirmed Mrs Donaldson s frank acknowledgement in her evidence at trial. [66] Subject to any issue of legal justification, we are satisfied the Donaldsons repudiated the transaction. Was there any justification for the respondents repudiation of the transactions? [67] In cases of repudiation of contract, it may be doubted that issues of justification are directly relevant 9 except to the extent they may bear upon whether the cancelling party was ready, willing and able to perform the contract and was not itself in material breach. 10 Ms Kelly advanced four matters on behalf of the respondents which she submitted justified the respondents refusal to proceed with the transaction Compare cancellation for breach where s 7(3) and (4) of the Contractual Remedies Act apply. The issue of materiality was recently discussed by this Court in Pimlico Properties Ltd v Driftwood Developments Ltd [2009] NZCA 523 at [31].

22 The PCC issue [68] The first is the PCC issue we have already discussed. It is clear that the lack of a PCC issued by Leuschke Group in conforming with the ASPs did not emerge until shortly before the trial in the High Court. Ms Kelly explained that it was not until after discovery that the Leuschke Group letter of 24 June 2008 was made available. The contract provided that someone else could be nominated to provide the PCC and she said it was not appreciated that this had not occurred. [69] However, we consider all this is beside the point. There was no suggestion during the time Station was calling for settlement in 2008 that, as a matter of fact, the apartments were not substantially completed in accordance with the plans and specifications. Even now, there is no evidence that any specific items remained to be completed. [70] Given our factual conclusion that the complex was in fact substantially complete by no later than mid-july 2008, there is no basis to suggest that Station had not completed its obligations under the ASP to construct the apartments generally in accordance with the plans and specifications appended to the contracts. While the date for settlement could only be triggered by the issue of the PCC, its absence does not have the significance attributed to it by the Judge. On our view of the matter, the respondents had repudiated the ASPs before the time for settlement had arrived. We have no doubt that if the respondents had been willing to settle and had raised the absence of a PCC that complied strictly with the technical terms of the contract, Station would have obtained the appropriate PCC and tendered it on settlement. The one per cent fee [71] The second matter relied upon by the respondents is the admitted failure by Station to pay or offer the one per cent fee. This payment was offered as an incentive to the respondents to enter the ASPs, but it was, in the scheme of things, a relatively minor matter. In dollar terms, the amount due to Mr and Mrs Kumar was $11,351; for Mr Selwyn it was $10,396; and it was $8,801 for the Donaldsons. We accept on the evidence that these amounts could not have been paid in cash by

23 Station and that it was very unlikely that BOSI would have been prepared to advance further cash to enable the payments to be made. However, we find it inconceivable in commercial terms that Station and BOSI would not have agreed to the relevant sums being credited against the purchase price at settlement as envisaged in cases such as the recent Supreme Court decision in Property Ventures Investments Ltd v Regalwood Holdings Ltd. 11 Station s receiver Mr Graham confirmed that, post-receivership, he would have readily agreed to give credit for items such as this if the respondents had been willing to proceed with the purchase. [72] Contrary to the view reached by the Judge, we are not persuaded that this issue was material or substantial. The furniture package [73] We reach a similar view with regard to the furniture. Mr Groves gave extensive evidence about the steps taken by him to secure furniture packages in accordance with Station s obligations. He accepted, however, that although the furniture was available, it was neither installed nor paid for. It could not have been acquired without funding by BOSI which he said would not be forthcoming. Mr Groves evidence was that it made no sense to acquire the furniture if the respondents were not willing to proceed with the ASPs. [74] Again, we are satisfied that, if the respondents had been ready, willing and able to settle the transaction, a deduction of $30,000 from the purchase price would have been the obvious and appropriate way to deal with this issue. We respectfully differ from the Judge on this issue. We are satisfied that this issue was not material or substantial. The management agreements [75] The final matter advanced by Ms Kelly was the failure to obtain the promised management agreements. Mr Groves gave evidence on this subject to the effect that 11 Property Ventures Investments Ltd v Regalwood Holdings Ltd [2010] NZSC 47, [2010] 3 NZLR 231 at [61] [69] of the majority judgment discussing equitable set-off in relation to an agreement for the sale and purchase of land.

24 management agreements were available but did not proceed for the same reasons as those he gave in respect of the furniture. We accept that Station had nominated a manager but the arrangement was not in place at the time settlement was called for or at any later time before Station cancelled for repudiation by the respondents. [76] Even assuming, contrary to Mr Tingey s submission, that the obligation was to actually have a management agreement in place, we find ourselves in disagreement with the view of the Judge that this was a material factor. We are satisfied on the evidence that, had the respondents been willing to proceed with the transactions, it would have been a simple matter for a management contract to have been put in place or for an appropriate allowance to have been made against the purchase price. [77] Ms Kelly submitted that the failure of Station to provide a management contract meant that the respondents became liable to pay GST on the purchase which they would not have had to pay if the apartments had been sold as a going concern. However, we accept Mr Tingey s submission that the purchasers were always obliged to pay GST on the purchase price. The ASPs provided expressly for the payment of GST in addition to the price. The purchase could not be zero-rated for GST in terms of s 11(1)(m) of the Goods and Services Act 1985 (the GST Act) since the respondents were not registered for GST purposes and the ASPs contained no agreement to sell as a going concern. [78] The only question therefore is whether the respondents could later recover the GST they were bound to pay on settlement. We accept Mr Tingey s submission that the respondents could have recovered the GST subsequently under s 20 of the GST Act if they had entered a management agreement under which the units were leased and if they had become registered for GST. This could have been achieved after settlement so long as they had intended to purchase the units for the principal purpose of leasing them thereby qualifying as a taxable activity in terms of s 6 of the GST Act. On the evidence, none of the respondents intended to personally occupy the units and all understood the apartments would be leased under a management agreement. The recovery of GST could have occurred promptly so that

25 any interest costs on borrowing to pay the GST would have been immaterial. 12 [79] We conclude that none of the matters relied upon as justifying the respondents refusal to proceed with the ASPs, whether taken singly or together, constituted a material or substantial breach which could have justified the respondents not proceeding with the transactions. The sunset clause [80] Ms Kelly submitted that the respondents were entitled to rely on the sunset clause at any time after 13 March 2009 and cancel the contract. She submitted the respondents had done so by giving notice in writing when they filed their notice of opposition to the summary judgment application on 9 June [81] We do not accept that submission. The notice of opposition pleaded breach of fiduciary duty by Station, unconscionable conduct, breach of s 9 of the Fair Trading Act and misrepresentation relying on the Contractual Remedies Act. The relief sought was for orders that the respondents were entitled to rescind their contracts or that Station was estopped from enforcing the contracts, a declaration that the contracts were void, and damages. The claim for damages was clearly inconsistent with any reliance on the sunset clause. It gave only a right to cancel the contract. We conclude that the notice of opposition did not purport to cancel the contracts or to rely on the sunset clause. And, as we next discuss, Station was ready, willing and able to proceed with its primary obligations. The sunset clause could not therefore be triggered. Was Station ready, willing and able to proceed with the transactions? [82] With the exception of the four matters we have just dealt with, there is no question that Station was ready, willing and able to complete the transactions from the time when the titles were issued shortly before Mr Goodwin s letter to the respondents of 7 August We accept that Station s actions from July 2008 onwards indicated that it was not intending to honour the side agreements. The 12 In terms of s 15 of the GST Act, the taxable period could have been as short as one month.

IN THE SUPREME COURT OF NEW ZEALAND SC 39/2013 [2014] NZSC 146

IN THE SUPREME COURT OF NEW ZEALAND SC 39/2013 [2014] NZSC 146 IN THE SUPREME COURT OF NEW ZEALAND SC 39/2013 [2014] NZSC 146 BETWEEN VIKRAM KUMAR AND NIRUPAMA KUMAR First Appellants ROBERT JAMES SELWYN Second Appellant MICHAEL DONALDSON AND PATRICIA BRONWYN DONALDSON

More information

Appellant. YANG WANG AND CHEN ZHANG Respondents

Appellant. YANG WANG AND CHEN ZHANG Respondents IN THE COURT OF APPEAL OF NEW ZEALAND CA58/2017 [2017] NZCA 280 BETWEEN AND Y&P NZ LIMITED Appellant YANG WANG AND CHEN ZHANG Respondents Hearing: 11 May 2017 Court: Counsel: Judgment: Cooper, Mallon and

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC MDS DEVELOPMENTS LIMITED Applicant

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC MDS DEVELOPMENTS LIMITED Applicant IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV-2015-404-1109 [2015] NZHC 2145 BETWEEN AND MDS DEVELOPMENTS LIMITED Applicant APPLEBY HOLDINGS LIMITED Respondent Hearing: 25 August 2015 Appearances:

More information

IN THE SUPREME COURT OF NEW ZEALAND SC 78/2014 [2014] NZSC 197. Appellant. Elias CJ, McGrath, William Young, Glazebrook and Arnold JJ

IN THE SUPREME COURT OF NEW ZEALAND SC 78/2014 [2014] NZSC 197. Appellant. Elias CJ, McGrath, William Young, Glazebrook and Arnold JJ NOTE: THE ORDER MADE BY THE HIGH COURT ON 28 MAY 2012 PROHIBITING PUBLICATION OF THE PARTIES' NAMES AND ANY PARTICULARS THAT WOULD IDENTIFY THE RESPONDENT (INCLUDING HER NAME, OCCUPATION, EMPLOYMENT HISTORY

More information

BRIAN MURRAY DAKEN Appellant. MURRAY EDWIN NIGEL WIIG Respondent JUDGMENT OF THE COURT REASONS OF THE COURT. (Given by Asher J)

BRIAN MURRAY DAKEN Appellant. MURRAY EDWIN NIGEL WIIG Respondent JUDGMENT OF THE COURT REASONS OF THE COURT. (Given by Asher J) IN THE COURT OF APPEAL OF NEW ZEALAND CA211/2016 [2016] NZCA 636 BETWEEN AND BRIAN MURRAY DAKEN Appellant MURRAY EDWIN NIGEL WIIG Respondent Hearing: 20 October 2016 Court: Counsel: Judgment: Asher, Heath

More information

REAL ESTATE COUNCIL OF ONTARIO DISCIPLINE DECISION

REAL ESTATE COUNCIL OF ONTARIO DISCIPLINE DECISION REAL ESTATE COUNCIL OF ONTARIO DISCIPLINE DECISION IN THE MATTER OF A DISCIPLINE HEARING HELD PURSUANT TO BY-LAW NO. 10 OF THE REAL ESTATE COUNCIL OF ONTARIO John Van Dyk Respondent This document also

More information

I TE KŌTI PĪRA O AOTEAROA CA416/2017 [2018] NZCA 239

I TE KŌTI PĪRA O AOTEAROA CA416/2017 [2018] NZCA 239 IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA CA416/2017 [2018] NZCA 239 BETWEEN AND QBE INSURANCE (INTERNATIONAL) LIMITED Appellant ALLIANZ AUSTRALIA INSURANCE LIMITED Respondent Hearing:

More information

C.J. PARKER CONSTRUCTION LIMITED (IN LIQUIDATION) Appellant. Winkelmann, Brewer and Toogood JJ

C.J. PARKER CONSTRUCTION LIMITED (IN LIQUIDATION) Appellant. Winkelmann, Brewer and Toogood JJ IN THE COURT OF APPEAL OF NEW ZEALAND CA637/2015 [2017] NZCA 3 BETWEEN AND C.J. PARKER CONSTRUCTION LIMITED (IN LIQUIDATION) Appellant WASIM SARWAR KETAN, FARKAH ROHI KETAN AND WASIM KETAN TRUSTEE COMPANY

More information

IN THE COURT OF APPEAL OF NEW ZEALAND CA327/2011 [2012] NZCA 481. POSTAL WORKERS UNION OF AOTEAROA INCORPORATED First Appellant

IN THE COURT OF APPEAL OF NEW ZEALAND CA327/2011 [2012] NZCA 481. POSTAL WORKERS UNION OF AOTEAROA INCORPORATED First Appellant IN THE COURT OF APPEAL OF NEW ZEALAND CA327/2011 [2012] NZCA 481 BETWEEN AND AND POSTAL WORKERS UNION OF AOTEAROA INCORPORATED First Appellant LINDA STREET Second Appellant NEW ZEALAND POST LIMITED Respondent

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC KIWIBANK LIMITED Defendant

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC KIWIBANK LIMITED Defendant IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV-2015-404-694 [2015] NZHC 1417 BETWEEN AND E-TRANS INTERNATIONAL FINANCE LIMITED Plaintiff KIWIBANK LIMITED Defendant Hearing: 23 April 2015 Appearances:

More information

Part II: Handling Conflicts of Interest between Insured and Insurer: The Lawyer s Dilemma

Part II: Handling Conflicts of Interest between Insured and Insurer: The Lawyer s Dilemma Handling Professional Indemnity Coverage Issues in Cases of Suspected Fraud Part II: Handling Conflicts of Interest between Insured and Insurer: The Lawyer s Dilemma Alison Padfield Devereux A. Introduction

More information

BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL. FRANK VOSPER AND VOSPER REALTY LIMITED Appellants

BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL. FRANK VOSPER AND VOSPER REALTY LIMITED Appellants BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL [2016] NZREADT 60 READT 081/15 IN THE MATTER OF BETWEEN AND AND an appeal under s111 of the Real Estate Agents Act 2008 FRANK VOSPER AND VOSPER REALTY

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV UNDER the Companies Act BLOSSOM WOOL LIMITED Applicant

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV UNDER the Companies Act BLOSSOM WOOL LIMITED Applicant IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2008-404-000161 UNDER the Companies Act 1993 BETWEEN AND BLOSSOM WOOL LIMITED Applicant JAMES WILLIAM PIPER Respondent AND UNDER the Companies Act

More information

IN THE EMPLOYMENT COURT AUCKLAND [2013] NZEmpC 15 ARC 84/12. VULCAN STEEL LIMITED Plaintiff. KIREAN WONNOCOTT Defendant

IN THE EMPLOYMENT COURT AUCKLAND [2013] NZEmpC 15 ARC 84/12. VULCAN STEEL LIMITED Plaintiff. KIREAN WONNOCOTT Defendant IN THE EMPLOYMENT COURT AUCKLAND [2013] NZEmpC 15 ARC 84/12 IN THE MATTER OF a challenge to a determination of the Employment Relations Authority BETWEEN AND VULCAN STEEL LIMITED Plaintiff KIREAN WONNOCOTT

More information

IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY CIV [2017] NZHC 367. IN THE MATTER the Insolvency Act 2006

IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY CIV [2017] NZHC 367. IN THE MATTER the Insolvency Act 2006 IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY CIV-2016-425-000117 [2017] NZHC 367 IN THE MATTER the Insolvency Act 2006 AND IN THE MATTER BETWEEN AND of the bankruptcy of ABRAHAM NICOLAAS VAN

More information

IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY CIV [2016] NZHC IN THE MATTER of the Insolvency Act 2006

IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY CIV [2016] NZHC IN THE MATTER of the Insolvency Act 2006 IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY CIV-2016-485-428 [2016] NZHC 3204 IN THE MATTER of the Insolvency Act 2006 AND IN THE MATTER BETWEEN AND of the Bankruptcy of Anthony Harry De Vries

More information

HEARING at Specialist Courts and Tribunals Centre, Chorus House, Auckland

HEARING at Specialist Courts and Tribunals Centre, Chorus House, Auckland NEW ZEALAND LAWYERS AND CONVEYANCERS DISCIPLINARY TRIBUNAL [2015] NZLCDT 29 LCDT 002/15 BETWEEN AUCKLAND STANDARDS COMMITTEE 4 Applicant AND ANTHONY BERNARD JOSEPH MORAHAN Respondent CHAIR Judge BJ Kendall

More information

THE IMMIGRATION ACTS. Promulgated On 17 th March 2015 On 23 rd March 2015 Prepared on 17 th March Before DEPUTY UPPER TRIBUNAL JUDGE WOODCRAFT

THE IMMIGRATION ACTS. Promulgated On 17 th March 2015 On 23 rd March 2015 Prepared on 17 th March Before DEPUTY UPPER TRIBUNAL JUDGE WOODCRAFT IAC-FH-AR/V1 Upper Tribunal (Immigration and Asylum Chamber) Appeal Number: IA/52919/2013 THE IMMIGRATION ACTS Heard at Field House Decision and Reasons Promulgated On 17 th March 2015 On 23 rd March 2015

More information

CONCERNING CONCERNING BETWEEN. The names and identifying details of the parties in this decision have been changed. DECISION

CONCERNING CONCERNING BETWEEN. The names and identifying details of the parties in this decision have been changed. DECISION LCRO 132/2014 CONCERNING an application for review pursuant to section 193 of the Lawyers and Conveyancers Act 2006 AND CONCERNING a determination of the [City] Standards Committee [X] BETWEEN WK Applicant

More information

FROM THE CIRCUIT COURT OF THE CITY OF RICHMOND Melvin R. Hughes, Jr., Judge. This appeal is from an order removing George B.

FROM THE CIRCUIT COURT OF THE CITY OF RICHMOND Melvin R. Hughes, Jr., Judge. This appeal is from an order removing George B. Present: All the Justices GEORGE B. LITTLE, TRUSTEE OPINION BY v. Record No. 941475 CHIEF JUSTICE HARRY L. CARRICO June 9, 1995 WILLIAM S. WARD, JR., ET AL. FROM THE CIRCUIT COURT OF THE CITY OF RICHMOND

More information

THE TAKEOVER PANEL HEARINGS COMMITTEE RANGERS INTERNATIONAL FOOTBALL CLUB PLC ( RANGERS ) AND MR DAVID CUNNINGHAM KING ( MR KING )

THE TAKEOVER PANEL HEARINGS COMMITTEE RANGERS INTERNATIONAL FOOTBALL CLUB PLC ( RANGERS ) AND MR DAVID CUNNINGHAM KING ( MR KING ) 2018/8 THE TAKEOVER PANEL HEARINGS COMMITTEE RANGERS INTERNATIONAL FOOTBALL CLUB PLC ( RANGERS ) AND MR DAVID CUNNINGHAM KING ( MR KING ) RULING OF THE CHAIRMAN OF THE HEARINGS COMMITTEE This Panel Statement

More information

IN THE COURT OF APPEAL OF NEW ZEALAND CA112/06 [2007] NZCA 479. Appellant. Hammond, Chambers and Arnold JJ. Judgment: 1 November 2007 at 11.

IN THE COURT OF APPEAL OF NEW ZEALAND CA112/06 [2007] NZCA 479. Appellant. Hammond, Chambers and Arnold JJ. Judgment: 1 November 2007 at 11. IN THE COURT OF APPEAL OF NEW ZEALAND CA112/06 [2007] NZCA 479 BETWEEN AND ROCHIS LIMITED Appellant ZACHERY ANDREW CHAMBERS, JULIAN DAVID CHAMBERS, JOCELYN ZELPHA CHAMBERS AND KIMBERLY FAITH CHAMBERS Respondents

More information

Mr S complains about Bar Mutual Indemnity Fund Limited s decision to withdraw funding for his claim.

Mr S complains about Bar Mutual Indemnity Fund Limited s decision to withdraw funding for his claim. complaint Mr S complains about Bar Mutual Indemnity Fund Limited s decision to withdraw funding for his claim. background I issued a provisional decision on this complaint in December 2015. An extract

More information

DECISION OF THE TRIBUNAL

DECISION OF THE TRIBUNAL BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL [2014] NZREADT 48 READT 006/14 IN THE MATTER OF BETWEEN an appeal under s.111 of the Real Estate Agents Act 2008 BARFOOT & THOMPSON LTD Appellant AND

More information

LAURA JANE GEORGE Applicant. AUCKLAND COUNCIL Respondent. Ellen France, Randerson and French JJ JUDGMENT OF THE COURT REASONS OF THE COURT

LAURA JANE GEORGE Applicant. AUCKLAND COUNCIL Respondent. Ellen France, Randerson and French JJ JUDGMENT OF THE COURT REASONS OF THE COURT IN THE COURT OF APPEAL OF NEW ZEALAND CA731/2013 [2014] NZCA 209 BETWEEN AND LAURA JANE GEORGE Applicant AUCKLAND COUNCIL Respondent Hearing: 12 May 2014 Court: Counsel: Judgment: Ellen France, Randerson

More information

IN THE EMPLOYMENT COURT AUCKLAND [2016] NZEmpC 68 EMPC 248/2015. MATTHEW PHILLIPS Defendant

IN THE EMPLOYMENT COURT AUCKLAND [2016] NZEmpC 68 EMPC 248/2015. MATTHEW PHILLIPS Defendant IN THE EMPLOYMENT COURT AUCKLAND IN THE MATTER OF BETWEEN AND [2016] NZEmpC 68 EMPC 248/2015 a challenge to a determination of the Employment Relations Authority MODERN TRANSPORT ENGINEERS (2002) LIMITED

More information

KENSINGTON DEVELOPMENTS LIMITED (IN RECEIVERSHIP) Appellant. COMMISSIONER OF INLAND REVENUE Respondent. Randerson, Winkelmann and Keane JJ

KENSINGTON DEVELOPMENTS LIMITED (IN RECEIVERSHIP) Appellant. COMMISSIONER OF INLAND REVENUE Respondent. Randerson, Winkelmann and Keane JJ IN THE COURT OF APPEAL OF NEW ZEALAND CA64/2014 [2015] NZCA 60 BETWEEN AND KENSINGTON DEVELOPMENTS LIMITED (IN RECEIVERSHIP) Appellant COMMISSIONER OF INLAND REVENUE Respondent Hearing: 16 February 2015

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV CLAVERDON DEVELOPMENTS LIMITED Defendant. P Chambers for Defendant

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV CLAVERDON DEVELOPMENTS LIMITED Defendant. P Chambers for Defendant IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV-2009-404-6292 BETWEEN AND HOUSING NEW ZEALAND LIMITED Plaintiff CLAVERDON DEVELOPMENTS LIMITED Defendant Hearing: 2 February 2010 Counsel: Judgment:

More information

Christiaan Hendrik Muller. Sharon Gail Yerman DECISION

Christiaan Hendrik Muller. Sharon Gail Yerman DECISION BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL Decision No: [2015] NZIACDT 77 Reference No: IACDT 045/14 IN THE MATTER of a referral under s 48 of the Immigration Advisers Licensing

More information

The names and identifying details of the parties in this decision have been changed.

The names and identifying details of the parties in this decision have been changed. LCRO 142/2014 & 160/2014 CONCERNING applications for review pursuant to section 193 of the Lawyers and Conveyancers Act 2006 AND CONCERNING a determination of Standards Committee BETWEEN VL Applicant (and

More information

ONTARIO SUPERIOR COURT OF JUSTICE DIVISIONAL COURT SACHS, WILTON-SIEGEL, MYERS JJ. ) ) ) Respondents )

ONTARIO SUPERIOR COURT OF JUSTICE DIVISIONAL COURT SACHS, WILTON-SIEGEL, MYERS JJ. ) ) ) Respondents ) CITATION: Papp v. Stokes 2018 ONSC 1598 DIVISIONAL COURT FILE NO.: DC-17-0000047-00 DATE: 20180309 ONTARIO SUPERIOR COURT OF JUSTICE DIVISIONAL COURT SACHS, WILTON-SIEGEL, MYERS JJ. BETWEEN: Adam Papp

More information

IN THE COURT OF APPEAL OF NEW ZEALAND CA256/05. ANTHONY ARBUTHNOT Respondent. William Young P, Arnold and Ellen France JJ

IN THE COURT OF APPEAL OF NEW ZEALAND CA256/05. ANTHONY ARBUTHNOT Respondent. William Young P, Arnold and Ellen France JJ IN THE COURT OF APPEAL OF NEW ZEALAND CA256/05 BETWEEN AND THE CHIEF EXECUTIVE OF THE DEPARTMENT OF WORK AND INCOME Appellant ANTHONY ARBUTHNOT Respondent Hearing: 24 August 2006 Court: Counsel: William

More information

IN THE EMPLOYMENT COURT AUCKLAND [2018] NZEmpC 33 ARC 98/13 ARC 22/14. LSG SKY CHEFS NEW ZEALAND LIMITED First Defendant

IN THE EMPLOYMENT COURT AUCKLAND [2018] NZEmpC 33 ARC 98/13 ARC 22/14. LSG SKY CHEFS NEW ZEALAND LIMITED First Defendant IN THE EMPLOYMENT COURT AUCKLAND IN THE MATTER OF AND IN THE MATTER BETWEEN AND AND AND [2018] NZEmpC 33 ARC 98/13 ARC 22/14 challenges to determinations of the Employment Relations Authority of an application

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2016] NZHC UNDER the Companies Act 1993

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2016] NZHC UNDER the Companies Act 1993 IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2013-404-003305 [2016] NZHC 2712 UNDER the Companies Act 1993 IN THE MATTER OF an application under sections 295 and 298 BETWEEN AND MARK HECTOR NORRIE

More information

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN Decision Ref: 2018-0130 Sector: Product / Service: Conduct(s) complained of: Banking Lending Application of interest rate Outcome: Substantially upheld LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES

More information

STATE OF MICHIGAN COURT OF APPEALS

STATE OF MICHIGAN COURT OF APPEALS STATE OF MICHIGAN COURT OF APPEALS POLARIS HOME FUNDING CORPORATION, Plaintiff-Appellee, UNPUBLISHED December 28, 2010 v No. 295069 Kent Circuit Court AMERA MORTGAGE CORPORATION, LC No. 08-009667-CK Defendant-Appellant.

More information

THE CHIEF EXECUTIVE OF THE MINISTRY OF SOCIAL DEVELOPMENT Respondent. J K Scragg and P H Higbee for Appellant U R Jagose and D L Harris for Respondent

THE CHIEF EXECUTIVE OF THE MINISTRY OF SOCIAL DEVELOPMENT Respondent. J K Scragg and P H Higbee for Appellant U R Jagose and D L Harris for Respondent DRAFT IN THE COURT OF APPEAL OF NEW ZEALAND CA122/2013 [2013] NZCA 410 BETWEEN AND GARY BRIDGFORD AS EXECUTOR OF THE ESTATE OF ELVA BRIDGFORD OF WHANGAREI Appellant THE CHIEF EXECUTIVE OF THE MINISTRY

More information

First Bowring Insurance Brokers (Pty) Limited DETERMINATION IN TERMS OF SECTION 30M OF THE PENSION FUNDS ACT OF 1956

First Bowring Insurance Brokers (Pty) Limited DETERMINATION IN TERMS OF SECTION 30M OF THE PENSION FUNDS ACT OF 1956 IN THE TRIBUNAL OF THE PENSION FUNDS ADJUDICATOR CASE NO. PFA/GA/387/98/LS IN THE COMPLAINT BETWEEN C G M Wilson Complainant AND First Bowring Staff Pension Fund First Bowring Insurance Brokers (Pty) Limited

More information

THE IMMIGRATION ACT. Heard at Field House Decision & Reasons Promulgated On 8 th February 2018 On 23 rd February Before

THE IMMIGRATION ACT. Heard at Field House Decision & Reasons Promulgated On 8 th February 2018 On 23 rd February Before Upper Tribunal (Immigration and Asylum Chamber) Appeal Number: THE IMMIGRATION ACT Heard at Field House Decision & Reasons Promulgated On 8 th February 2018 On 23 rd February 2018 Before DEPUTY UPPER TRIBUNAL

More information

DISCIPLINARY COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS

DISCIPLINARY COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS DISCIPLINARY COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS REASONS FOR DECISION In the matter of: Mr Martyn Gary Wheeler Heard on: 24 June 2015 Location: Committee: Legal Adviser: Chartered

More information

ANDREW DENNIS CHARLES HUTCHINSON JUDGMENT

ANDREW DENNIS CHARLES HUTCHINSON JUDGMENT 1 SAFLII Note: Certain personal/private details of parties or witnesses have been redacted from this document in compliance with the law and SAFLII Policy IN THE HIGH COURT OF SOUTH AFRICA EASTERN CAPE

More information

ERIC MESERVE HOUGHTON Appellant

ERIC MESERVE HOUGHTON Appellant IN THE COURT OF APPEALOF NEW ZEALAND CA578/2014 [2015] NZCA 141 BETWEEN AND ERIC MESERVE HOUGHTON Appellant TIMOTHY ERNEST CORBETT SAUNDERS, SAMUEL JOHN MAGILL, JOHN MICHAEL FEENEY, CRAIG EDGEWORTH HORROCKS,

More information

Conveyancing and property

Conveyancing and property Editor: Peter Butt STATUTORY WARFARE, ROUND 2: HAS THE HIGH COURT CONFUSED THE LAW OF ILLEGALITY? In an earlier note in this column ( Statutory warfare? What happens when retail lease legislation collides

More information

JANET ELSIE LOWE Respondent. J C Holden and M J R Conway for Appellants P Cranney and A McInally for Respondent JUDGMENT OF THE COURT

JANET ELSIE LOWE Respondent. J C Holden and M J R Conway for Appellants P Cranney and A McInally for Respondent JUDGMENT OF THE COURT - IN THE COURT OF APPEAL OF NEW ZEALAND CA169/2015 [2016] NZCA 369 BETWEEN DIRECTOR-GENERAL OF HEALTH, MINISTRY OF HEALTH First Appellant CHIEF EXECUTIVE, CAPITAL AND COAST DISTRICT HEALTH BOARD Second

More information

Ombudsman s Determination

Ombudsman s Determination Ombudsman s Determination Applicant Scheme Respondent Mrs S Canon (UK) Ltd Pension Scheme (the Scheme) Trustees of the Canon (UK) Retirement Benefit Scheme (the Trustees) Complaint Summary 1. Mrs S complaint

More information

IN THE HIGH COURT OF JUSTICE BETWEEN AND

IN THE HIGH COURT OF JUSTICE BETWEEN AND THE REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV2014-03058 BETWEEN RAVI NAGINA SUMATI BAKAY Claimants AND LARRY HAVEN SUSAN RAMLAL HAVEN Defendants Before The Hon. Madam Justice C. Gobin

More information

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY CIV [2016] NZHC 562. IN THE MATTER OF the Insolvency Act 2006

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY CIV [2016] NZHC 562. IN THE MATTER OF the Insolvency Act 2006 IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY CIV-2010-409-000559 [2016] NZHC 562 IN THE MATTER OF the Insolvency Act 2006 AND IN THE MATTER OF BETWEEN AND the bankruptcy of DAVID IAN HENDERSON

More information

The return of the taxpayer

The return of the taxpayer The return of the taxpayer 1 June 2016 Keith Gordon discusses the First-tier Tribunal s decision in Revell v HMRC and the broader implications of the case What is the issue? The First-tier Tribunal s decision

More information

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN Decision Ref: 2018-0103 Sector: Product / Service: Conduct(s) complained of: Outcome: Banking Personal Loan Application of interest rate Delayed or inadequate communication Substantially upheld LEGALLY

More information

Dip Chand and Sant Kumari. Richard Uday Prakash

Dip Chand and Sant Kumari. Richard Uday Prakash BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL Decision No: [2012] NZIACDT 60 Reference No: IACDT 006/11 IN THE MATTER BY of a referral under s 48 of the Immigration Advisers Licensing

More information

Ombudsman s Determination

Ombudsman s Determination Ombudsman s Determination Applicant Scheme Respondents Mr H Firefighters' Pension Scheme (the Scheme) Hereford & Worcester Fire Authority (the Authority) Worcestershire County Council (the Council) Outcome

More information

NOTE: PUBLICATION OF NAME OR IDENTIFYING PARTICULARS OF COMPLAINANT PROHIBITED BY S 139 OF THE CRIMINAL JUSTICE ACT 1985.

NOTE: PUBLICATION OF NAME OR IDENTIFYING PARTICULARS OF COMPLAINANT PROHIBITED BY S 139 OF THE CRIMINAL JUSTICE ACT 1985. NOTE: PUBLICATION OF NAME OR IDENTIFYING PARTICULARS OF COMPLAINANT PROHIBITED BY S 139 OF THE CRIMINAL JUSTICE ACT 1985. IN THE COURT OF APPEAL OF NEW ZEALAND CA82/2014 [2014] NZCA 304 BETWEEN AND TOESE

More information

TC05816 [2017] UKFTT 0339 (TC) Appeal number: TC/2013/07292

TC05816 [2017] UKFTT 0339 (TC) Appeal number: TC/2013/07292 [17] UKFTT 0339 (TC) TC0816 Appeal number: TC/13/07292 INCOME TAX penalties for not filing return on time whether penalty under para 4 Sch FA 09 valid after Donaldson: no whether reasonable excuse for

More information

DECISION OF THE TRIBUNAL

DECISION OF THE TRIBUNAL BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL [2014] NZREADT 53 READT 053/13 IN THE MATTER OF BETWEEN an appeal under s.111 of the Real Estate Agents Act 2008 PAUL C DAVIE of Auckland, Real Estate

More information

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY CRI [2013] NZHC Appellant. CHRISTCHURCH CITY COUNCIL Respondent

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY CRI [2013] NZHC Appellant. CHRISTCHURCH CITY COUNCIL Respondent IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY CRI-2013-409-000006 [2013] NZHC 2388 BETWEEN AND CIRCLE K LIMITED Appellant CHRISTCHURCH CITY COUNCIL Respondent Hearing: 11 September 2013 Appearances:

More information

IN THE EMPLOYMENT COURT CHRISTCHURCH [2010] NZEMPC 144 CRC 25/10. DEREK WAYNE GILBERT Applicant

IN THE EMPLOYMENT COURT CHRISTCHURCH [2010] NZEMPC 144 CRC 25/10. DEREK WAYNE GILBERT Applicant IN THE EMPLOYMENT COURT CHRISTCHURCH [2010] NZEMPC 144 CRC 25/10 IN THE MATTER OF BETWEEN AND application for leave to file challenge out of time DEREK WAYNE GILBERT Applicant TRANSFIELD SERVICES (NEW

More information

MJY and VYW DECISION. The names and identifying details of the parties in this decision have been changed.

MJY and VYW DECISION. The names and identifying details of the parties in this decision have been changed. LCRO 250/2016 LCRO 251/2016 CONCERNING applications for review pursuant to section 193 of the Lawyers and Conveyancers Act 2006 AND CONCERNING a determination by [Area] Standards Committee [X] BETWEEN

More information

STATE OF MICHIGAN COURT OF APPEALS

STATE OF MICHIGAN COURT OF APPEALS STATE OF MICHIGAN COURT OF APPEALS STATE TREASURER, Plaintiff/Counter-Defendant- Appellee, UNPUBLISHED November 18, 2010 v No. 294142 Muskegon Circuit Court HOMER LEE JOHNSON, LC No. 09-046457-CZ and Defendant/Counter-Defendant-

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV NAJDA COURT & ORS Respondent RESERVED JUDGMENT OF MILLER J

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV NAJDA COURT & ORS Respondent RESERVED JUDGMENT OF MILLER J IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 5284-03 BETWEEN AND MACLENNAN REALTY LIMITED Appellant NAJDA COURT & ORS Respondent Hearing: 18 February 2004 Appearances: J Waymouth for Appellant

More information

THE HUMAN RIGHTS REVIEW TRIBUNAL & ORS Respondents

THE HUMAN RIGHTS REVIEW TRIBUNAL & ORS Respondents NOTE: ORDER OF THE HUMAN RIGHTS REVIEW TRIBUNAL AND OF THE HIGH COURT PROHIBITING PUBLICATION OF NAMES, ADDRESSES OR IDENTIFYING PARTICULARS OF THE SECOND, THIRD AND FOURTH RESPONDENTS AND THE SECOND RESPONDENT'S

More information

COMMISSIONER OF INLAND REVENUE Appellant. PATTY TZU CHOU LIN Respondent. Harrison, Cooper and Asher JJ

COMMISSIONER OF INLAND REVENUE Appellant. PATTY TZU CHOU LIN Respondent. Harrison, Cooper and Asher JJ IN THE COURT OF APPEAL OF NEW ZEALAND CA308/2017 [2018] NZCA 38 BETWEEN AND COMMISSIONER OF INLAND REVENUE Appellant PATTY TZU CHOU LIN Respondent Hearing: 7 February 2018 Court: Counsel: Judgment: Harrison,

More information

SHABEENA SHAREEN NISHA Applicant. LSG SKY CHEFS NZ LIMITED Respondent. D J Goddard QC for Applicant C M Meechan QC for Respondent

SHABEENA SHAREEN NISHA Applicant. LSG SKY CHEFS NZ LIMITED Respondent. D J Goddard QC for Applicant C M Meechan QC for Respondent IN THE COURT OF APPEAL OF NEW ZEALAND CA616/2015 [2016] NZCA 21 BETWEEN AND SHABEENA SHAREEN NISHA Applicant LSG SKY CHEFS NZ LIMITED Respondent Hearing: 15 February 2016 Court: Counsel: Judgment: Wild,

More information

EASTEND HOMES LIMITED. - and - (1) AFTAJAN BIBI (2) MAHANARA BEGUM JUDGMENT. Dates: 24 August 2017

EASTEND HOMES LIMITED. - and - (1) AFTAJAN BIBI (2) MAHANARA BEGUM JUDGMENT. Dates: 24 August 2017 Claim No. B00EC907 In the County Court at Central London On Appeal from District Judge Sterlini Sitting at Clerkenwell & Shoreditch His Honour Judge Parfitt EASTEND HOMES LIMITED Appellant - and - (1)

More information

WESLEY BORK JR. And THE TAMARIND CLUB II LIMITED

WESLEY BORK JR. And THE TAMARIND CLUB II LIMITED BRITISH VIRGIN ISLANDS EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE CLAIM NO: BVIHCV 245/2009 IN THE MATTER OF THE INSOLVENCY ACT 2003 AND IN THE MATTER OF THE TAMARIND CLUB II LIMITED

More information

GOVERNMENT EMPLOYEES PENSION FUND

GOVERNMENT EMPLOYEES PENSION FUND IN THE HIGH COURT OF SOUTH AFRICA EASTERN CAPE LOCAL DIVISION, PORT ELIZABETH CASE NO: 228/2015 Date heard: 30 July 2015 Date delivered: 4 August 2015 In the matter between NOMALUNGISA MPOFU Applicant

More information

Arbitration and Conciliation Act

Arbitration and Conciliation Act 1 of 31 20-11-2012 21:02 Constitution of Nigeria Court of Appeal High Courts Home Page Law Reporting Laws of the Federation of Nigeria Legal Education Q&A Supreme Court Jobs at Nigeria-law Arbitration

More information

CONCERNING CONCERNING BETWEEN. DECISION The names and identifying details of the parties in this decision have been changed.

CONCERNING CONCERNING BETWEEN. DECISION The names and identifying details of the parties in this decision have been changed. LCRO 30/2015 CONCERNING an application for review pursuant to section 193 of the Lawyers and Conveyancers Act 2006 AND CONCERNING BETWEEN a determination of the [Area] Standards Committee [X] GN Applicant

More information

IN THE COURT OF APPEAL BETWEEN. ALAN DICK AND COMPANY LIMITED [Improperly sued as Alan Dick and Company] AND FAST FREIGHT FORWARDERS LIMITED AND

IN THE COURT OF APPEAL BETWEEN. ALAN DICK AND COMPANY LIMITED [Improperly sued as Alan Dick and Company] AND FAST FREIGHT FORWARDERS LIMITED AND REPUBLIC OF TRINIDAD AND TOBAGO IN THE COURT OF APPEAL CIVIL APPEAL No. 214 of 2010 BETWEEN ALAN DICK AND COMPANY LIMITED [Improperly sued as Alan Dick and Company] APPELLANT AND FAST FREIGHT FORWARDERS

More information

I TE KŌTI PĪRA O AOTEAROA CA35/2018 [2018] NZCA 240. OMV NEW ZEALAND LIMITED Appellant

I TE KŌTI PĪRA O AOTEAROA CA35/2018 [2018] NZCA 240. OMV NEW ZEALAND LIMITED Appellant IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA CA35/2018 [2018] NZCA 240 BETWEEN AND OMV NEW ZEALAND LIMITED Appellant PRECINCT PROPERTIES HOLDINGS LIMITED Respondent Hearing: 24 May 2018

More information

THE STATE OF NEW HAMPSHIRE SUPREME COURT

THE STATE OF NEW HAMPSHIRE SUPREME COURT THE STATE OF NEW HAMPSHIRE SUPREME COURT In Case No. 2017-0487, In re Simone Garczynski Irrevocable Trust, the court on July 26, 2018, issued the following order: The appellant, Michael Garczynski (Michael),

More information

IMMIGRATION APPEAL TRIBUNAL

IMMIGRATION APPEAL TRIBUNAL Ar Heard at Field House On: 17 November 2004 Dictated 17 November 2004 Notified: 18 January 2005 [IS IS (Concession made by rep representative) Sierra Leone [2005] UKI UKIAT 00009 IMMIGRATION APPEAL TRIBUNAL

More information

DECISION OF THE BOARD OF APPEAL OF THE EUROPEAN CHEMICALS AGENCY. 7 March 2018

DECISION OF THE BOARD OF APPEAL OF THE EUROPEAN CHEMICALS AGENCY. 7 March 2018 A-014-2016 1(11) DECISION OF THE BOARD OF APPEAL OF THE EUROPEAN CHEMICALS AGENCY 7 March 2018 (Biocidal products Data sharing dispute Every effort Permission to refer Chemical similarity Contractual freedom)

More information

COURT OF APPEAL FOR BRITISH COLUMBIA

COURT OF APPEAL FOR BRITISH COLUMBIA COURT OF APPEAL FOR BRITISH COLUMBIA Citation: Between: And Before: Hik v. Redlick, 2013 BCCA 392 John Hik and Jennie Annette Hik Larry Redlick and Larry Redlick, doing business as Larry Redlick Enterprises

More information

Lim Kitt Ping Lynnette v People s Insurance Co Ltd and another

Lim Kitt Ping Lynnette v People s Insurance Co Ltd and another 914 SINGAPORE LAW REPORTS (REISSUE) [1997] 1 SLR(R) Lim Kitt Ping Lynnette v People s Insurance Co Ltd and another [1997] SGHC 122 High Court Suit No 2235 of 1992 Kan Ting Chiu J 11, 12 February; 12 May

More information

BETWEEN DECISION. The names and identifying details of the parties in this decision have been changed.

BETWEEN DECISION. The names and identifying details of the parties in this decision have been changed. LCRO 2/2014 CONCERNING an application for review pursuant to section 193 of the Lawyers and Conveyancers Act 2006 AND CONCERNING a determination of [Area] Standards Committee [X] BETWEEN JB Applicant AND

More information

NEW ZEALAND LAWYERS AND CONVEYANCERS DISCIPLINARY TRIBUNAL. Decision No. [2009] NZLCDT 9 LCDT 08/2009. IN THE MATTER of the Law Practitioners Act 1982

NEW ZEALAND LAWYERS AND CONVEYANCERS DISCIPLINARY TRIBUNAL. Decision No. [2009] NZLCDT 9 LCDT 08/2009. IN THE MATTER of the Law Practitioners Act 1982 NEW ZEALAND LAWYERS AND CONVEYANCERS DISCIPLINARY TRIBUNAL Decision No. [2009] NZLCDT 9 LCDT 08/2009 IN THE MATTER of the Law Practitioners Act 1982 BETWEEN CANTERBURY DISTRICT LAW SOCIETY AND DAVID ALAN

More information

SOLICITORS DISCIPLINARY TRIBUNAL. IN THE MATTER OF THE SOLICITORS ACT 1974 Case No

SOLICITORS DISCIPLINARY TRIBUNAL. IN THE MATTER OF THE SOLICITORS ACT 1974 Case No SOLICITORS DISCIPLINARY TRIBUNAL IN THE MATTER OF THE SOLICITORS ACT 1974 Case No. 10922-2012 On 28 June 2013, Mr Moseley appealed against the Tribunal s decision on sanction. The appeal was dismissed

More information

FINAL NOTICE. 1. For the reasons given in this notice, and pursuant to section 56 of the Act, the FSA has decided to:

FINAL NOTICE. 1. For the reasons given in this notice, and pursuant to section 56 of the Act, the FSA has decided to: FINAL NOTICE To: Mr Colin Jackson To: Baronworth (Investment Services) Limited (in liquidation) FSA FRN: 115284 Reference Number: CPJ00002 Date: 19 December 2012 ACTION 1. For the reasons given in this

More information

TERMS AND CONDITIONS OF SALE

TERMS AND CONDITIONS OF SALE 1/6 TERMS AND CONDITIONS OF SALE 1 - SCOPE 1.1 In accordance with Article L 441-6 of the French Commercial Code, our General Terms and Conditions of Sale form the sole basis of all commercial negotiations.

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Dawson v Jewiss; Thompson v Jewiss [2004] QCA 374 PARTIES: STUART BEVAN DAWSON (plaintiff/respondent) v HENRY WILLIAM JEWISS also known as HARRY JEWISS (defendant/appellant)

More information

IAN CHARLES SCHULER First Appellant. Harrison, White and Venning JJ. D G Hayes for Appellants C W Grenfell and B J Norling for Respondent

IAN CHARLES SCHULER First Appellant. Harrison, White and Venning JJ. D G Hayes for Appellants C W Grenfell and B J Norling for Respondent IN THE COURT OF APPEAL OF NEW ZEALAND CA27/2013 [2014] NZCA 91 BETWEEN IAN CHARLES SCHULER First Appellant INDEPENDENT LIVESTOCK 2010 LIMITED (IN LIQUIDATION) Second Appellant AND DAMIEN GRANT AND STEVEN

More information

6 February Dear Complainant,

6 February Dear Complainant, Dear Complainant, 6 February 2017 Complaint against the Financial Conduct Authority Reference Number: Thank you for your correspondence about your complaint against the Financial Conduct Authority (FCA).

More information

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN Decision Ref: 2018-0087 Sector: Product / Service: Conduct(s) complained of: Insurance Household Buildings Rejection of claim - fire Outcome: Rejected LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES

More information

BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL. Appellant. THE REAL ESTATE AGENTS AUTHORITY Respondent

BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL. Appellant. THE REAL ESTATE AGENTS AUTHORITY Respondent FURTHER DRAFT BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL Decision no: [2013] NZREADT 4 Ref No: NZREADT 115/11 IN THE MATTER OF BETWEEN AND an appeal under s 111 of the Real Estate Agents Act 2008

More information

Ombudsman s Determination

Ombudsman s Determination Ombudsman s Determination Applicant Scheme Respondent Mr L NHS Pension Scheme (the Scheme) NHS Pensions (as a service provided by NHS Business Services Authority (NHS BSA) Complaint Summary Mr L has complained

More information

- and - TRATHENS TRAVEL SERVICES LIMITED

- and - TRATHENS TRAVEL SERVICES LIMITED Case No: 9PF00857 IN THE LEEDS COUNTY COURT Leeds Combined Court The Courthouse 1 Oxford Row Leeds LS1 3BG Date: 9 th July 2010 Before : HIS HONOUR JUDGE S P GRENFELL Between : LEROY MAKUWATSINE - and

More information

1 January 2010 (as amended 1 January 2015) Table of contents

1 January 2010 (as amended 1 January 2015) Table of contents Terms of Reference 1 January 2010 (as amended 1 January 2015) Table of contents Section A: Preliminary Matters 1. Introduction 1.1 Purpose of the Service 1.2 Principles that underpin FOS operations and

More information

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN

LEGALLY BINDING DECISION OF THE FINANCIAL SERVICES AND PENSIONS OMBUDSMAN Decision Ref: 2018-0105 Sector: Product / Service: Conduct(s) complained of: Outcome: Banking Variable Mortgage Delayed or inadequate communication Dissatisfaction with customer service Failure to process

More information

IN THE EMPLOYMENT COURT AUCKLAND [2012] NZEmpC 34 ARC 73/11. Plaintiff. VINCENT SINGH Defendant

IN THE EMPLOYMENT COURT AUCKLAND [2012] NZEmpC 34 ARC 73/11. Plaintiff. VINCENT SINGH Defendant IN THE EMPLOYMENT COURT AUCKLAND [2012] NZEmpC 34 ARC 73/11 IN THE MATTER OF an application for compliance order BETWEEN AND NOEL COVENTRY Plaintiff VINCENT SINGH Defendant Hearing: 23 February 2012 (Heard

More information

Ahmed Muhsen Ikbarieh. Osama (Sam) Hammadieh

Ahmed Muhsen Ikbarieh. Osama (Sam) Hammadieh BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL Decision No: [2014] NZIACDT 49 Reference No: IACDT 0048/12 IN THE MATTER of a referral under s 48 of the Immigration Advisers Licensing

More information

Upper Tribunal (Immigration and Asylum Chamber) PA/08153/2017 THE IMMIGRATION ACTS

Upper Tribunal (Immigration and Asylum Chamber) PA/08153/2017 THE IMMIGRATION ACTS Upper Tribunal (Immigration and Asylum Chamber) PA/08153/2017 Appeal Number: THE IMMIGRATION ACTS Heard at Field House Decision & Reasons Promulgated On 15 March 2018 On 11 May 2018 Before DEPUTY UPPER

More information

Ontario Ltd. (c.o.b. Castle Auto Collision & Mechanical Service) v. Certas Insurance, [2016] O.J. No. 264

Ontario Ltd. (c.o.b. Castle Auto Collision & Mechanical Service) v. Certas Insurance, [2016] O.J. No. 264 1218897 Ontario Ltd. (c.o.b. Castle Auto Collision & Mechanical Service) v. Certas Insurance, [2016] O.J. No. Ontario Judgments [2016] O.J. No. 2016 ONSC 354 Ontario Superior Court of Justice Divisional

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: HBU Properties Pty Ltd & Ors v Australia and New Zealand Banking Group Limited [2015] QCA 95 HBU PROPERTIES PTY LTD AS TRUSTEE FOR THE SHANE MUNDEY FAMILY

More information

THE IMMIGRATION ACTS. Heard at Field House Decision & Reasons Promulgated On 4 th April 2018 On 17 th April Before

THE IMMIGRATION ACTS. Heard at Field House Decision & Reasons Promulgated On 4 th April 2018 On 17 th April Before Upper Tribunal (Immigration and Asylum Chamber) Appeal Number: HU/18141/2016 THE IMMIGRATION ACTS Heard at Field House Decision & Reasons Promulgated On 4 th April 2018 On 17 th April 2018 Before DEPUTY

More information

DISCIPLINARY COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS REASONS FOR DECISION. Heard on: 23 October and 5 December 2014

DISCIPLINARY COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS REASONS FOR DECISION. Heard on: 23 October and 5 December 2014 DISCIPLINARY COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS REASONS FOR DECISION In the matter of: Mrs Ajda D jelal Heard on: 23 October and 5 December 2014 Location: ACCA Offices, 29

More information

EDITORIAL NOTE: NO SUPPRESSION APPLIED. IN THE DISTRICT COURT AT QUEENSTOWN CIV [2016] NZDC 2055

EDITORIAL NOTE: NO SUPPRESSION APPLIED. IN THE DISTRICT COURT AT QUEENSTOWN CIV [2016] NZDC 2055 EDITORIAL NOTE: NO SUPPRESSION APPLIED. IN THE DISTRICT COURT AT QUEENSTOWN CIV-2014-059-000156 [2016] NZDC 2055 BETWEEN AND JAMES VELASCO BUENAVENTURA Plaintiff ROWENA GONZALES BURGESS Defendant Hearing:

More information

Category Scottish Further and Higher Education: Higher Education/Plagiarism and Intellectual Property

Category Scottish Further and Higher Education: Higher Education/Plagiarism and Intellectual Property Scottish Parliament Region: Mid Scotland and Fife Case 201002095: University of Stirling Summary of Investigation Category Scottish Further and Higher Education: Higher Education/Plagiarism and Intellectual

More information

IN THE SUPREME COURT OF NEW ZEALAND SC 124/2011 [2012] NZSC 69. SERVICE AND FOOD WORKERS UNION NGA RINGA TOTA INC First Appellant

IN THE SUPREME COURT OF NEW ZEALAND SC 124/2011 [2012] NZSC 69. SERVICE AND FOOD WORKERS UNION NGA RINGA TOTA INC First Appellant IN THE SUPREME COURT OF NEW ZEALAND SC 124/2011 [2012] NZSC 69 BETWEEN AND AND SERVICE AND FOOD WORKERS UNION NGA RINGA TOTA INC First Appellant THE PERSONS LISTED IN SCHEDULE A OF THE APPLICATION (THE

More information

CARL KIATIKA NGAWHIKA Appellant. THE QUEEN Respondent. J U Mooney for Appellant JEL Carruthers for Respondent JUDGMENT OF THE COURT

CARL KIATIKA NGAWHIKA Appellant. THE QUEEN Respondent. J U Mooney for Appellant JEL Carruthers for Respondent JUDGMENT OF THE COURT IN THE COURT OF APPEAL OF NEW ZEALAND CA297/2017 [2017] NZCA 535 BETWEEN AND CARL KIATIKA NGAWHIKA Appellant THE QUEEN Respondent Hearing: 15 November 2017 Court: Counsel: Judgment: Harrison, Lang and

More information

SOLICITORS DISCIPLINARY TRIBUNAL SOLICITORS ACT IN THE MATTER OF BLESSING RINGWEDE ODATUWA, solicitor (the Respondent)

SOLICITORS DISCIPLINARY TRIBUNAL SOLICITORS ACT IN THE MATTER OF BLESSING RINGWEDE ODATUWA, solicitor (the Respondent) No. 10323-2009 SOLICITORS DISCIPLINARY TRIBUNAL SOLICITORS ACT 1974 IN THE MATTER OF BLESSING RINGWEDE ODATUWA, solicitor (the Respondent) Upon the application of Peter Cadman on behalf of the Solicitors

More information