What amounts to good faith conduct or repudiation on construction projects?

Size: px
Start display at page:

Download "What amounts to good faith conduct or repudiation on construction projects?"

Transcription

1 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 1 What amounts to good faith conduct or repudiation on construction projects? When is a building contract a joint venture and what amounts to good faith conduct or repudiation on construction projects? A recent decision of the Prince Edward Island Court of Appeal in WCI Waste Conversion Inc. v. ADI International In. involving a joint venture project raised a number of important issues including: a. whether a contractor and subcontractor were actually in a joint venture relationship b. when do parties to a construction project owe duties of good faith or fiduciary duties to each other? c. and what misconduct on a construction project will be considered to be sufficiently serious that it amounts to repudiation entitling the other party to terminate the contract? The Background In June 2000, a PEI Crown Corporation, Island Waste Management Corporation ( IWMC ), issued a Request for Proposals for the design, construction and operation of a central composting facility to serve the province of Prince Edward Island. WCI approached ADI about making a proposal together. The two companies submitted a Pre-Qualification Submission which was expressly made by those companies in association and as a team. The ultimate Proposal was submitted in March 2001 by ADI and it stated that it was prepared by both companies. In July 2001, IWMC awarded the contract to ADI, with WCI which was shown as a subcontractor. In May 2001, ADI and WCI entered into a Memorandum of Understanding ( MOU ). They entered into a further MOU in August 2001 after the contract had been awarded by IWMC to ADI. The key provision of the August MOU stated as follows: It is agreed that ADI will be the prime contracting party, with WCI engaged as a sub-contractor. ADI will provide the bonding and insurances as stipulated by the RFP. However, it is agreed that the actual working THOMAS HEINTZMAN O.C., Q.C. AUTHOR PROFILE Thomas Heintzman specializes in the field of alternative dispute resolution (ADR) and has been senior counsel in actions and arbitrations across Canada, and at all levels of appellate courts including numerous appearances in the Supreme Court of Canada. His practice specializes in litigation, arbitration and mediation relating to corporate disputes, shareholder s rights, securities law, broadcasting/ telecommunications and class actions.

2 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 2 relationship will be based on the general principles of a joint venture agreement as summarized below. In their correspondence with each other, ACI and WCI frequently referred to the bid as being joint and to the relationship as being a joint venture, but ADI insisted throughout that it was the prime contractor and carried the associated rights and risks. Construction of the project was substantially completed by October During the construction, the relationship between ADI and WCI deteriorated and ADI terminated the contract with WCI. The Sub-Contract or Joint Venture Issue A difficult issue that may arise between contractors and subcontractors is the nature of their contractual relationship. Are they: independent contractors; or partners; or joint venturers; or employees one of the other? The PEI Court of Appeal considered whether a contractor and subcontractor were actually in a joint venture relationship. The decision is an important one as the majority and minority of the court approached the issue in a different way. The trial judge found that the contract between the parties included the two MOUs and the correspondence between the parties, at least so far as determining the relationship between the parties. He held that, for the purposes of the relationship with IWMC, the parties were in a contractor-subcontractor relationship, but between themselves they were parties to a joint venture relationship. A difficult issue that may arise between contractors and subcontractors is the nature of their contractual relationship. A re they: independent contractors; or partners; or joint venturers; or employees one of the other? The majority of the PEI Court of Appeal affirmed this finding. A number of features of its reasoning are important. First, the majority held that ADI could not rely on evidence outside the MOU to contradict the statement in the MOU that the relationship between the parties was a joint venture. Second, the majority held that it was not necessary that WCI have an

3 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 3 expectation of profit from the prime contract with IWMC for there to be a joint venture between the parties. Even though WCI was only entitled to a fixed payment from ADI, and ADI was entitled to all the upside and subject to the downside of that prime contract, the parties were still entitled to call their agreement a joint venture agreement and thereby impose duties upon themselves consistent with a joint venture. Third, the majority held that contractors and subcontractors are entitled to contract between themselves as joint venturers, and to contract with the owner on the basis that only one of them is the contractor and the other is a subcontractor. The majority distinguished the case of Design Services v. R, [2008] 1SCR 737 in which a subcontractor asserted that it was in a contractual relationship with the owner based upon it really being part of a joint venture with the contractor. The majority of the PEI Court of Appeal said that, in Design Services, the owner had issued no contract at all to the contractor but had issued the contract to another bidder: Canada awarded no construction contract to the contractor, Olympic. Olympic didn t enter into a subcontract with Design Services. In the present case, WCI s claim is between the contracting parties, inter se, where terms have been agreed and expressed by the parties. The minority judge disagreed. As to the clause in the MOU stating the parties relationship, the minority judge held that there was an inconsistency between the first and third sentences and that the court was obligated to find an interpretation which would give meaning to both provisions that create the inconsistency. The majority held that contractors and subcontractors are entitled to contract between themselves as joint venturers, and to contract with the owner on the basis that only one of them is the contractor and the other is a subcontractor. The minority judge then turned to the actual responsibilities and the actual entitlements to payment and profits to determine whether the relationship was really one of joint venture or one of contractor-subcontractor. He found that ADI entered into a fixed price contract with IWMC in which WCI had no entitlement to profit, and that WCI entered into a fixed price contract for WCI to be paid a fixed price. There was no sharing in profits under either arrangement. ADI and WCI had separate activities for which they were responsible. Each party entered into separate sub-contracts. Neither party was vulnerable to the other. In short, all the ingredients of the relationship

4 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 4 indicated that there was no joint venture and that the parties were independent contractors. According to the minority judge, the statement about a joint venture in the MOU: meant they would work in close cooperation with each other to carry out their specialized duties as contractor and subcontractor. Reliance on joint venture was for purposes of facilitating the proper functioning of their working relationship as contractor and subcontractor there is nothing in their contractual arrangements which would indicate they agreed to enter into a joint venture.the statement standing by itself in the contract did not make their legal relationship that of parties to a joint venture. This disagreement between the majority and minority reveals a fundamentally different approach to determining the legal relationship between the parties. The majority held that, if the parties state in their agreement that they are joint venturers, then the court will hold them to that statement. The minority held that the court may go behind that statement, at least if the parties also state that they have a contractor-subcontractor relationship so far as the owner is concerned; and the court may determine if the relationship between the parties is really one of joint venture and if it is not, then the parties statement about joint venture may be over-ridden. The majority held that, if the parties state in their agreement that they are joint venturers, then the court will hold them to that statement. This difference in opinion raises a number of questions: First, if the parties wish to have a joint venture relationship between themselves, but also wish one of them to be the prime contractor and the other to be the subcontractor, can they legally do so? If they can, how do they do so to ensure that the relationship is not disputed later? The wording used by the parties in the key provision of the MOU seems as clear as possible, namely, that the parties wanted a joint venture arrangement between them, but recognized that one of them would be contractor and the other sub-contractor so far as the owner was concerned. How could they have more clearly stated that intention? Would

5 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 5 it have been better to leave out reference to the actual working relationship being based on a joint venture agreement, and instead say that the real legal relationship between the parties is that of joint venture? Or with this judicial precedent, can we now proceed on the basis that the words in this contract are sufficient in the future to create a joint venture between a contractor and subcontractor? Second, which approach is better? Should courts accept the parties statement as it is? Or should they inquire into the actual relationship to see if it is one of joint venture? In the employment setting, courts often determine whether the relationship is really one of employment or one of independent contractors, but there are real public policy reasons for doing so. When the parties say that they are partners, should the court go behind that statement to see if they really are? If they say that they have entered into a joint venture agreement, are there good public policy reasons for the court to go behind that statement? What amounts to good faith conduct or repudiation on construction projects? What misconduct on a construction project will be considered to be sufficiently serious that it amounts to repudiation entitling the other party to terminate the contract? What misconduct on a construction project will be considered to be sufficiently serious that it amounts to repudiation entitling the other party to terminate the contract? Under ADI s contract with IWMC, ADI was to enter into a five year operating contract with IWMC, and under the MOU, ADI was to enter into a five year subcontract with WCI under which WCI was to be the operator. In its Substantial Performance letter dated October 7, 2001, IWMC accepted ADI s application for Substantial Performance effective October 1, In accepting Substantial Performance, IWMC stated that its concerns about throughput performance were to be addressed by the date of Total Performance, which was to occur on February 1, As a result, both ADI and WCI had until February 1, 2003 to demonstrate throughput performance. Moreover, the majority of the Court of Appeal concluded that, based upon its conduct leading up to the Substantial Performance letter, ADI effectively viewed WCI s performance with respect to throughput

6 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 6 performance as being a deficiency, and not conduct which repudiated WCI s obligations under the contract. On November 26, 2002, ADI gave notice to WCI that it was in default of its obligations and gave a five day cure notice to WCI. By letter dated November 29, 2001, WCI denied that it was in default and restated its commitment to improve the throughput performance of the project. By letter dated December 4, 2002, ADI terminated the contractual relationship between the parties. Repudiation and Termination The trial judge held that, as of the date of ADI s termination of the contract, WCI had not repudiated the contract, and therefore ADI s termination was unlawful. This finding was upheld by the majority of the Court of Appeal. There are several aspects of its conclusions that are important. First, the majority of the Court of Appeal held that the cure notice could not be given by ADI if WCI was not then in default. Since WCI had until February 2003 to ensure that throughput performance was met, WCI was not in breach of any obligations as of November 26, 2002 when ADI delivered its cure notice, and December 4, 2002 when it terminated the contract. The Court of Appeal stated its affirmation of the trial judge s conclusion as follows: The trial judge was entitled to find, as he did that WCI did not by its words or conduct repudiate; that, in any event, the time for correction of the deficiencies in question was not exhausted; and, in the circumstances of the status of the deficiencies, ADI did not show that WCI was incapable of performing its part of the contract. This is a very useful check list for a contractor contemplating termination of a subcontractor, particularly when deciding to give or act upon a cure notice. First, by its words or conduct, has the subcontractor really repudiated its obligations? Second, has the time for performance of the obligations in question really been exhausted? And third, is the subcontractor really incapable of performing its contract? And for good measure, can I prove all these elements at a trial? This is a very useful check list for a contractor contemplating termination of a subcontractor... First, by its words or conduct, has the subcontractor really repudiated its obligations? Second, has the time for performance of the obligations in question really been exhausted? An d third, is the subcontractor really incapable of performing its contract? And for good measure, can I prove all these elements at a trial?

7 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 7 The second important aspect of the Court of Appeal s decision is its affirmation of the principle that when a contract provides a time within which the contract work must be completed, the contractor is entitled to the whole of that time for doing the work relying on Goldsmith and Heintzman on Canadian Building Contracts (4th ed) at chapter 5, part 1(d). Third, the trial judge and majority judgment in the Court of Appeal applied the principle of good faith performance of contractual obligations. The trial judge held that ADI did not act in good faith in seeking approval of Substantial Completion on the basis of throughput performance being achieved by February 2003 and then turning around and terminating the contract with WCI based upon its deficiencies in relation to throughput performance before February The Court of Appeal held that a contract must be performed in good faith, that this obligation involves performance within the reasonable expectations established by the contract, and that the trial judge was entitled to find that ADI s tactics and motivations were inconsistent with a good faith exercise of its obligations and contractual duties to WCI. Fourth, in examining the conduct and rights of ADI and WCI, the trial judge and Court of Appeal looked to the conduct and rights as between the owner, IWMC, and ADI. Thus, IWMC had delivered no cure notice or termination notice to ADI in relation to throughput performance. Why was ADI delivering such a notice to WCI? At ADI s request, IWMC had agreed that throughput performance would be established by the date of Total Performance. Why was ADI not agreeing with WCI to the same date for performance? Clearly, ADI s inconsistent conduct or attitude was of crucial concern to the trial judge, and the Court of Appeal upheld the trial judge s findings based on those concerns. The Court of Appeal held that a contract must be performed in good faith, that this obligation involves performance within the reasonable expectations established by the contract, and that the trial judge was entitled to find that ADI s tactics and motivations were inconsistent with a good faith exercise of its obligations and contractual duties to WCI. The minority judge agreed with this conclusion but would have directed a new trial related to the entitlement of ADI to terminate the operating contract with WCI at its sole discretion and whether it had done so in good faith. All the judges of the Court of Appeal were firmly of the view that the issue of whether or not WCI had repudiated the contract and whether or not ADI had

8 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 8 the right to terminate the contract based on repudiation, was to be determined on an objective basis. The majority held that repudiating is not lightly to be inferred from a party s conduct, and that, as the terminating party, ADI had the obligation to prove WCI s repudiation and its entitlement to terminate. Accordingly, there was no element of discretion or deference to be accorded to ADI s decision to terminate. In all respects, this decision of the PEI Court of Appeal provides a very useful survey of the issues which must be addressed by contractors and subcontractors when termination for repudiation is contemplated under a construction contract, particularly when a cure notice is involved. Good Faith and Fiduciary Duties The trial judge concluded that, by reason of the joint venture between them, the parties owed fiduciary duties to each other. Both the majority and the minority of the Court of Appeal disagreed. The majority held that a joint venture, unlike a partnership, does not necessarily give rise to fiduciary duties. Without deciding if fiduciary duties did arise in this joint venture, the majority held that the material findings of the trial judge about the conduct of the parties and the legal consequences of that conduct could be supported without reference to fiduciary duties. The minority judge found that it was unlikely that, in the circumstances of this case, fiduciary duties would arise. The minority judge then considered whether the parties had an obligation to exercise their rights under the contract in good faith. He concluded that there was no such obligation in relation to any of the provisions of the contract which did not involve discretion, and that there was in relation to those provisions that did involve discretion. He then concluded that under the cure notice provision of the MOU, if AWI properly followed the notice provisions and WCI did not cure, then the MOU could be terminated without regard to issues of good faith. However, he held that AWI s right to terminate the operating agreement was unilateral and could be exercised in its sole discretion, provided it gave the required notice and paid the required termination fees. In this circumstance, the minority judge concluded that AWI was required to act in good faith in giving a notice to terminate the operating In all respects, this decision of the PEI Court of Appeal provides a very useful survey of the issues which must be addressed by contractors and subcontractors when termination for repudiation is contemplated under a construction contract, particularly when a cure notice is involved.

9 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 9 agreement. The concepts of a fiduciary duty and a duty of good faith are very different. A fiduciary duty is a duty to act in the utmost good faith and in the other party s best interest. An obligation of good faith is not a fiduciary duty. It is not the obligation to act in the utmost good faith and in other party s best interest. It is the obligation to act in accordance with the purpose of the contract and not to undermine its performance. It is highly doubtful that a true fiduciary duty will arise during a construction project unless the parties call themselves partners. The commercial setting for the project is not consistent with such an obligation. On the other hand, it is hard to see why an obligation to act in good faith should not arise. After all, that obligation simply requires a party not to act in bad faith, not to act for an ulterior motive, that is, a motive which is outside the purpose of the contract. Making an obligation of good faith dependent upon the existence of discretion, as the minority judge did, is highly problematic. The element of discretion is usually relevant to determining whether the duty is a fiduciary duty, not whether a duty of good faith exists. If a cure notice is given properly on its face, but is given for an ulterior motive having nothing to do with the proper completion of the construction project, why should that sort of conduct be valid? Why is the right to terminate the operating contract any more unilateral than the right to give a cure notice? And if a party has a right to terminate in its sole discretion, then surely the real issue is whether that right is exercised for bona fide reasons consistent with the purpose of the contract. In all these circumstances, good faith appears to be applicable to most of the obligations on a construction project. In all these circumstances, good faith appears to be applicable to most of the obligations on a construction project. REFERENCE: WCI v. ADI, 2011 PECA 14 (CanLII) For a copy of the judgment see the International Court Decisions page on the Building Disputes Tribunal website under RESOURCES:

10 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 10 Letters to the Editor We welcome letters to the editor If you would like to submit a letter for possible publication please... a MS Word copy of your letter as an attachment to editor@buildingdisputestribunal.co.nz with Letter to the Editor as the subject Include you full name and contact details Keep your letter short, concise and to the point Avoid personal attacks (even if you perceive you are responding to a personal attack).

11 BuildLaw - Good Faith Conduct or Repudiation on Construction Projects 11 CONTRIBUTIONS: Contributions to BuildLaw are welcome. BuildLaw is published four times a year in March, June, September and December. Readers are invited to submit material to be considered for publication by to the editor at editor@buildingdisputestribunal.co.nz. Contributions may consist of articles, case notes, book reviews, news of forthcoming events and other matters of interest to readers. Contributors are entirely responsible for the accuracy of case names and citations, quotations and other references, spelling etc. All contributions should be in final form and in word format. DISCLAIMER: BuildLaw is published by Building Disputes Tribunal. BuildLaw is a newsletter and does not purport to provide a comprehensive analysis of the subjects covered or to constitute legal advice. BuildLaw is intended to promote and engender discussion, debate, and consideration of all matters in relation to the development and application of construction law, the resolution of building and construction disputes, and the processes that are used for the resolution of those disputes. Articles, commentaries and opinions are intended to raise questions rather than to be emphatic statements on the subjects covered and the views expressed are the views of the author and are not necessarily those of the directors, servants and agents of the Tribunal. Information published is not guaranteed to be correct, current or comprehensive and the Tribunal accepts no responsibility for the accuracy of any information published in BuildLaw and no person should act in reliance on any statement or information contained in BuildLaw. Readers are specifically advised that specialist legal advice should be sought in relation to all matters in relation to, or in connection with, the subjects covered and articles published in BuildLaw. COPYRIGHT: This issue of BuildLaw and all material and information contained herein are subject to the full protection given by the Copyright Act In many cases the copyright of individual articles remains the property of the author and articles and commentaries should not be reproduced without first obtaining the express authorisation of the relevant third party copyright owner concerned. If you are in any doubt as to whether a proposed use is covered by this licence please consult the Editor. Building Disputes Tribunal (NZ) Limited. All rights reserved BuildLaw : Reaches you first with the construction law news you need to know Gives you access to important judgments when they are delivered Gives you expert commentary and analysis of key legal developments and issues affecting your business Explains complex issues clearly and simply

GLOBAL CLAIMS. BuildLaw - Issue No 16 December Jeremy Glover JEREMY GLOVER

GLOBAL CLAIMS. BuildLaw - Issue No 16 December Jeremy Glover JEREMY GLOVER BuildLaw - Issue No 16 December 2012 1 GLOBAL CLAIMS - Jeremy Glover Global claims were defined by Byrne J in the Australian case John Holland Construction v Kvaerner RJ Brown as being a claim where: the

More information

Citation: ADI v. WCI & WCI v. ADI & IWMC Date: PESCTD 89 Docket: S1-GS Registry: Charlottetown

Citation: ADI v. WCI & WCI v. ADI & IWMC Date: PESCTD 89 Docket: S1-GS Registry: Charlottetown Citation: ADI v. WCI & WCI v. ADI & IWMC Date: 20021231 2002 PESCTD 89 Docket: S1-GS-19514 Registry: Charlottetown PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - TRIAL DIVISION BETWEEN: AND BETWEEN:

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

Trusts & Equity Law 463 Fall Term 2018 LECTURE NOTES NO. 1

Trusts & Equity Law 463 Fall Term 2018 LECTURE NOTES NO. 1 Trusts & Equity Law 463 Fall Term 2018 LECTURE NOTES NO. 1 THE FIDUCIARY PRINCIPLE Fiduciary duties are a special category of obligations that sound in equity rather than common law. Breaching such a duty

More information

UNITED STATES BANKRUPTCY COURT DISTRICT OF MASSACHUSETTS EASTERN DIVISION

UNITED STATES BANKRUPTCY COURT DISTRICT OF MASSACHUSETTS EASTERN DIVISION UNITED STATES BANKRUPTCY COURT DISTRICT OF MASSACHUSETTS EASTERN DIVISION In re CHARLES STREET AFRICAN METHODIST EPISCOPAL CHURCH OF BOSTON, Chapter 11 Case No. 12 12292 FJB Debtor MEMORANDUM OF DECISION

More information

Ledcor Construction Ltd. v. Northbridge Indemnity Insurance Co., 2016 SCC 37

Ledcor Construction Ltd. v. Northbridge Indemnity Insurance Co., 2016 SCC 37 PUBLICATION Ledcor Construction Ltd. v. Northbridge Indemnity Insurance Co., 2016 SCC 37 Date: September 15, 2016 Co-Authors: David Mackenzie, Dominic Clarke, Zack Garcia Original Newsletter(s) this article

More information

Pass-Through Claims and Liquidation Agreements

Pass-Through Claims and Liquidation Agreements Pass-Through Claims and Liquidation Agreements by Gregory J. Dukellis, Senior Partner Watt, Tieder, Hoffar & Fitzgerald, L.L.P.* On construction projects, it is not uncommon that a party is damaged during

More information

ASYLUM AND IMMIGRATION TRIBUNAL

ASYLUM AND IMMIGRATION TRIBUNAL RS and SS (Exclusion of appellant from hearing) Pakistan [2008] UKAIT 00012 ASYLUM AND IMMIGRATION TRIBUNAL THE IMMIGRATION ACTS Heard at: Field House Date of Hearing: 18 December 2007 Before: Mr C M G

More information

CITATION: Lucas-Logan v. Certas Direct Insurance Company, 2017 ONSC 828 COURT FILE NO.: CV DATE: ONTARIO SUPERIOR COURT OF JUSTICE

CITATION: Lucas-Logan v. Certas Direct Insurance Company, 2017 ONSC 828 COURT FILE NO.: CV DATE: ONTARIO SUPERIOR COURT OF JUSTICE CITATION: Lucas-Logan v. Certas Direct Insurance Company, 2017 ONSC 828 COURT FILE NO.: CV-15-21829 DATE: 20170202 ONTARIO SUPERIOR COURT OF JUSTICE BETWEEN: Eunice Lucas-Logan Plaintiff and Certas Direct

More information

Recent Franchise Case Law Developments. CFA Law Day, January 28, 2016

Recent Franchise Case Law Developments. CFA Law Day, January 28, 2016 Recent Franchise Case Law Developments CFA Law Day, January 28, 2016 Jean-Marc Leclerc, Sotos LLP and Chris Horkins, Cassels Brock and Blackwell LLP 1 (a) Class Actions and Group Actions Trillium Motors

More information

Managing design professional risks arising out of the Prime/Subcontractor relationship

Managing design professional risks arising out of the Prime/Subcontractor relationship Managing design professional risks arising out of the Prime/Subcontractor relationship June 22, 2017 Gail S. Kelley P.E., Esq., LEED AP J. Kent Holland, J.D. ConstructionRisk, LLC Copyright Information

More information

Introduction to Arbitration and Dispute Resolution under FIDIC. Dr. Asanga Gunawansa Attorney-at-Law

Introduction to Arbitration and Dispute Resolution under FIDIC. Dr. Asanga Gunawansa Attorney-at-Law Introduction to Arbitration and Dispute Resolution under FIDIC Dr. Asanga Gunawansa Attorney-at-Law PART 1 ARBITRATION Arbitration Arbitration is a procedure in which a dispute is submitted, by agreement

More information

THE HUMAN RIGHTS REVIEW TRIBUNAL & ORS Respondents

THE HUMAN RIGHTS REVIEW TRIBUNAL & ORS Respondents NOTE: ORDER OF THE HUMAN RIGHTS REVIEW TRIBUNAL AND OF THE HIGH COURT PROHIBITING PUBLICATION OF NAMES, ADDRESSES OR IDENTIFYING PARTICULARS OF THE SECOND, THIRD AND FOURTH RESPONDENTS AND THE SECOND RESPONDENT'S

More information

REPUBLIC OF SOUTH AFRICA IN THE LABOUR APPEAL COURT OF SOUTH AFRICA, DURBAN THANDA ROYAL ZULU FOOTBALL CLUB

REPUBLIC OF SOUTH AFRICA IN THE LABOUR APPEAL COURT OF SOUTH AFRICA, DURBAN THANDA ROYAL ZULU FOOTBALL CLUB * REPUBLIC OF SOUTH AFRICA Not Reportable IN THE LABOUR APPEAL COURT OF SOUTH AFRICA, DURBAN Case no: DA 8/14 In the matter between: THANDA ROYAL ZULU FOOTBALL CLUB Appellant and LESTER, S N.O. First Respondent

More information

FLEMMING & SON CONSTRUCTION (WEST MIDLANDS) LIMITED. -and- THE COMMISSIONERS FOR HER MAJESTY S REVENUE AND CUSTOMS JUDGE KEVIN POOLE BEVERLEY TANNER

FLEMMING & SON CONSTRUCTION (WEST MIDLANDS) LIMITED. -and- THE COMMISSIONERS FOR HER MAJESTY S REVENUE AND CUSTOMS JUDGE KEVIN POOLE BEVERLEY TANNER [12] UKFTT (TC) TC01900 Appeal numbers: TC/11/01493 TC/11/08678 Income tax construction industry scheme deductions from payments to subcontractors sums representing materials cost not to be subject to

More information

ORDER PO Appeal PA Peterborough Regional Health Centre. June 30, 2016

ORDER PO Appeal PA Peterborough Regional Health Centre. June 30, 2016 ORDER PO-3627 Appeal PA15-399 Peterborough Regional Health Centre June 30, 2016 Summary: The appellant, a journalist, sought records relating to the termination of the employment of several employees of

More information

UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA. Plaintiff, COMPLAINT. Preliminary Statement

UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA. Plaintiff, COMPLAINT. Preliminary Statement CASE 0:13-cv-00923-RHK-JSM Document 1 Filed 04/22/13 Page 1 of 14 UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA C.S. McCrossan Construction, Inc., No. v. Plaintiff, COMPLAINT Minnesota Department

More information

EFFECTIVE EXCLUSION CLAUSES

EFFECTIVE EXCLUSION CLAUSES EFFECTIVE EXCLUSION CLAUSES An exclusion (sometimes called a limitation or exemption clause) clause is one which attempts to exclude or limit a party s liability, or to exclude or limit the other party

More information

401(k) Fee Litigation Update

401(k) Fee Litigation Update October 6, 2008 401(k) Fee Litigation Update Courts Divide on Fiduciary Status of 401(k) Service Providers Introduction As the 401(k) fee lawsuits progress, the federal district courts continue to grapple

More information

Promote the entry of competitive Alberta technology-oriented SMEs into the global market;

Promote the entry of competitive Alberta technology-oriented SMEs into the global market; INTRODUCTION The Micro-Voucher Program, Voucher Program and Product Demonstration Program (collectively, the Programs ) have been designed to support innovation and creative problem solving in the Alberta

More information

FEDERAL CONSTRUCTION PROJECT MANAGER S BULLETIN Devoted exclusively to problems encountered while performing Government construction contracts

FEDERAL CONSTRUCTION PROJECT MANAGER S BULLETIN Devoted exclusively to problems encountered while performing Government construction contracts FEDERAL CONSTRUCTION PROJECT MANAGER S BULLETIN Devoted exclusively to problems encountered while performing Government construction contracts Volume II Number 21 ENFORCEABILITY OF CONTRACTS Readers of

More information

FEDERAL COURT OF APPEAL. - and - RESPONDENT S MEMORANDUM OF FACT AND LAW

FEDERAL COURT OF APPEAL. - and - RESPONDENT S MEMORANDUM OF FACT AND LAW Court File No. A-000-09 FEDERAL COURT OF APPEAL BETWEEN: ERNEST HEMINGWAY Appellant - and - COUNT LEV NIKOLAYEVICH TOLSTOY Respondent RESPONDENT S MEMORANDUM OF FACT AND LAW Torys LLP Suite 3000 79 Wellington

More information

National Insurance Company Ltd. Vs. Hindustan Safety Glass Works Ltd.

National Insurance Company Ltd. Vs. Hindustan Safety Glass Works Ltd. National Insurance Company Ltd. Vs. Hindustan Safety Glass Works Ltd. ((2009) 5 SCC 121) Madan B. Lokur, J. 1. The question arising in the first appeal directed against the judgment and order dated 23rd

More information

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT July Term 2013

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT July Term 2013 MAY, J. DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT July Term 2013 PALM BEACH POLO HOLDINGS, INC., a Florida corporation, Appellant, v. STEWART TITLE GUARANTY COMPANY, a Texas corporation,

More information

IN THE COMMONWEALTH COURT OF PENNSYLVANIA. Appellant :

IN THE COMMONWEALTH COURT OF PENNSYLVANIA. Appellant : IN THE COMMONWEALTH COURT OF PENNSYLVANIA Northeast Bradford School District, : : Appellant : : v. : No. 2007 C.D. 2016 : Argued: June 5, 2017 Northeast Bradford Education : Association, PSEA/NEA : BEFORE:

More information

In the Supreme Court of Florida

In the Supreme Court of Florida In the Supreme Court of Florida CASE NO.: SC09-401 STATE FARM FLORIDA INSURANCE COMPANY, Petitioner, v. CHAD GOFF and CAROL GOFF, Respondents. ON DISCRETIONARY REVIEW FROM THE SECOND DISTRICT COURT OF

More information

Blueprint. for Design Professionals September 2011 Volume 2 Issue 2. What do you do when served with a lawsuit?

Blueprint. for Design Professionals September 2011 Volume 2 Issue 2. What do you do when served with a lawsuit? Blueprint for Design Professionals September 2011 Volume 2 Issue 2 Welcome to our third edition of Blueprint For Deisgn Professionals. The articles for this issue provide a primer for the litigation process

More information

Yugraneft v. Rexx Management: Limitation periods under the New York Convention A Case Comment by Paul M. Lalonde & Mark Hines*

Yugraneft v. Rexx Management: Limitation periods under the New York Convention A Case Comment by Paul M. Lalonde & Mark Hines* Yugraneft v. Rexx Management: Limitation periods under the New York Convention A Case Comment by Paul M. Lalonde & Mark Hines* Prepared for the Canadian Bar Association National Section on International

More information

ONTARIO TRIAL LAWYERS ASSOCIATION (OTLA) OTLA s Submission to the Review of FSCO s Dispute Resolution Services

ONTARIO TRIAL LAWYERS ASSOCIATION (OTLA) OTLA s Submission to the Review of FSCO s Dispute Resolution Services ONTARIO TRIAL LAWYERS ASSOCIATION (OTLA) OTLA s Submission to the Review of FSCO s Dispute Resolution Services 9/20/2013 The Ontario Trial Lawyers Association (OTLA) was formed in 1991 by lawyers acting

More information

AGREEMENT FOR PROFESSIONAL CONSULTANT SERVICES CITY OF SAN MATEO PUBLIC WORKS DEPARTMENT

AGREEMENT FOR PROFESSIONAL CONSULTANT SERVICES CITY OF SAN MATEO PUBLIC WORKS DEPARTMENT AGREEMENT FOR PROFESSIONAL CONSULTANT SERVICES CITY OF SAN MATEO PUBLIC WORKS DEPARTMENT Sanitary Sewer Rehabilitation Design Services [name of consultant] This agreement, made and entered into this day

More information

Finnish Arbitration Act (23 October 1992/967)

Finnish Arbitration Act (23 October 1992/967) Finnish Arbitration Act (23 October 1992/967) Comments of the Secretariat of the United Nations Commission on International Trade Law (UNCITRAL) on the basis of the unofficial translation from Finnish

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS. Appeal of -- ) ) The Swanson Group, Inc. ) ASBCA No ) Under Contract No. N C-9509 )

ARMED SERVICES BOARD OF CONTRACT APPEALS. Appeal of -- ) ) The Swanson Group, Inc. ) ASBCA No ) Under Contract No. N C-9509 ) ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) The Swanson Group, Inc. ) ASBCA No. 54863 ) Under Contract No. N68711-91-C-9509 ) APPEARANCE FOR THE APPELLANT: APPEARANCES FOR THE GOVERNMENT:

More information

Agreement for Advisors Providing Services to Interactive Brokers Customers

Agreement for Advisors Providing Services to Interactive Brokers Customers 6101 03/10/2015 Agreement for Advisors Providing Services to Interactive Brokers Customers This Agreement is entered into between Interactive Brokers ("IB") and the undersigned Advisor. WHEREAS, IB provides

More information

I. Introduction. Appeals this year was Fisher v. State Farm Mutual Automobile Insurance Company, 2015 COA

I. Introduction. Appeals this year was Fisher v. State Farm Mutual Automobile Insurance Company, 2015 COA Fisher v. State Farm: A Case Analysis September 2015 By David S. Canter I. Introduction One of the most important opinions to be handed down from the Colorado Court of Appeals this year was Fisher v. State

More information

IN THE COURT OF APPEAL BETWEEN BISSONDAYE SAMAROO AND

IN THE COURT OF APPEAL BETWEEN BISSONDAYE SAMAROO AND TRINIDAD AND TOBAGO IN THE COURT OF APPEAL Civil Appeal No: 164 of 2008 BETWEEN BISSONDAYE SAMAROO Appellant AND 1. AZIZOOL MOHAMMED 2. KHALIED MOHAMMED ALSO CALLED KHALID MOHAMMED 3. FAZILA MOHAMMED 4.

More information

WHEN CAN YOU STOP WORK FOR NONPAYMENT?

WHEN CAN YOU STOP WORK FOR NONPAYMENT? WHEN CAN YOU STOP WORK FOR NONPAYMENT? PLANNING AHEAD When an owner or general contractor has not paid a roofing contractor the sums it is owed under the contract, the roofing contractor is faced with

More information

IN THE LABOUR COURT OF SOUTH AFRICA JOHANNESBURG ESKOM HOLDINGS SOC LIMITED

IN THE LABOUR COURT OF SOUTH AFRICA JOHANNESBURG ESKOM HOLDINGS SOC LIMITED IN THE LABOUR COURT OF SOUTH AFRICA JOHANNESBURG Reportable/Not Reportable Case no: JR538/14 In the matter between: ESKOM HOLDINGS SOC LIMITED Applicant and NATIONAL UNION OF MINEWORKERS First Respondent

More information

A Guide to Canadian Standard Form of Agreement Between Client and Architect Abbreviated Version Document Seven

A Guide to Canadian Standard Form of Agreement Between Client and Architect Abbreviated Version Document Seven A Guide to Canadian Standard Form of Agreement Between Client and Architect Abbreviated Version Document Seven Background This guide is written to assist both the Client and Architect in completing the

More information

Before : LORD JUSTICE GOLDRING LORD JUSTICE AIKENS and LORD JUSTICE McCOMBE Between :

Before : LORD JUSTICE GOLDRING LORD JUSTICE AIKENS and LORD JUSTICE McCOMBE Between : Neutral Citation Number: [2013] EWCA Civ 585 Case No: C1/2012/1950 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM QUEEN S BENCH (ADMINISTRATIVE COURT) MR JUSTICE HOLMAN [2012] EWHC 1303 (Admin)

More information

Fiduciary Best Practices Helped NYU Win ERISA Class Action

Fiduciary Best Practices Helped NYU Win ERISA Class Action Portfolio Media. Inc. 111 West 19 th Street, 5th Floor New York, NY 10011 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Fiduciary Best Practices Helped NYU Win ERISA

More information

Understanding the Risks of Construction Management (CM)

Understanding the Risks of Construction Management (CM) PROFESSIONAL LIABILITY UPDATE A Loss Prevention Newsletter for the Design Profession MSP PL 07/02: Understanding the Risks of Construction Management (CM) July, 2002 Understanding the Risks of Construction

More information

Czech Republic. Contributor: Alena Bányaiová. Editor: Philip Britton

Czech Republic. Contributor: Alena Bányaiová. Editor: Philip Britton CZ Czech Republic Contributor: Alena Bányaiová Editor: Philip Britton Czech Republic General questions 769 Topics 773 1 General obligations of the employer 773 1.1 Traditional procurement 773 1.2 Design

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS

ARMED SERVICES BOARD OF CONTRACT APPEALS ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) International Computers ) & Telecommunications, Inc. ) ASBCA No. 51725 ) Under Contract No. DAHC77-96-C-0004 ) APPEARANCE FOR THE APPELLANT: APPEARANCES

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION REPORTABLE CIVIL APPEAL NO.9048 OF 2014 (Arising out of Special Leave Petition (Civil) No.10849 of 2013) Swan Gold Mining Ltd. Appellant (s) Versus

More information

To Go to Arbitration or Litigation in Subrogation Cases?

To Go to Arbitration or Litigation in Subrogation Cases? To Go to Arbitration or Litigation in Subrogation Cases? Dr. Zhan Hao, managing partner of AnJie Law Firm (zhanhao@anjielaw.com) One of the questions in China is whether an insurer should go to arbitration

More information

DOUKPSC04 Rev Feb 2013

DOUKPSC04 Rev Feb 2013 DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby

More information

In every contract over $10,000, the provisions in A. and B. below apply: A. During the performance of this contract, the vendor agrees as follows:

In every contract over $10,000, the provisions in A. and B. below apply: A. During the performance of this contract, the vendor agrees as follows: The following Terms and Conditions are MANDATORY and shall be incorporated verbatim in any contract award: 1. APPLICABLE LAWS AND COURTS: This solicitation and any contract resulting from this solicitation

More information

Reese J. Henderson, Jr., Esq., B.C.S

Reese J. Henderson, Jr., Esq., B.C.S Altman Contractors, Inc. v. Crum & Forster Specialty Ins. Co.: Balancing the Interests Surrounding Potential Insurance Coverage for Chapter 558 Notices of Claim February 23, 2018 Reese J. Henderson, Jr.,

More information

STANDARD FORM OF AGREEMENT BETWEEN DESIGN CONSULTANT AND DESIGN SUB-CONSULTANT

STANDARD FORM OF AGREEMENT BETWEEN DESIGN CONSULTANT AND DESIGN SUB-CONSULTANT STANDARD FORM OF AGREEMENT BETWEEN DESIGN CONSULTANT AND DESIGN SUB-CONSULTANT Document No. 575 First Edition, 2012 Design-Build Institute of America Washington, DC Design-Build Institute of America Contract

More information

Rush University Case: Impact on Self-Settled Trusts. By Gideon Rothschild, Esq. and Martin M. Shenkman, Esq.

Rush University Case: Impact on Self-Settled Trusts. By Gideon Rothschild, Esq. and Martin M. Shenkman, Esq. Rush University Case: Impact on Self-Settled Trusts By Gideon Rothschild, Esq. and Martin M. Shenkman, Esq. A recent Illinois case that ruled unfavorably on the use of self-settled trusts, Rush Univ. Med.

More information

ADMISSIONS AND LICENSING COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS

ADMISSIONS AND LICENSING COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS ADMISSIONS AND LICENSING COMMITTEE OF THE ASSOCIATION OF CHARTERED CERTIFIED ACCOUNTANTS REASONS FOR DECISION In the matter of: Mr Abdus Salam Heard on: Monday, 4 December 2017 Location: Committee: Legal

More information

DO NOT PUBLISH STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

DO NOT PUBLISH STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT DO NOT PUBLISH STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT 08-110 LOCAL NUMBER 144, PROFESSIONAL FIREFIGHTER S ASSOCIATION, ET AL VERSUS CITY OF CROWLEY ********** APPEAL FROM THE FIFTEENTH JUDICIAL

More information

Presentation Overview

Presentation Overview Conflicts Essentials Webinar Practice Advisors: Nancy Carruthers and Elizabeth Aspinall September 21, 2017 Presentation Overview Discuss how to recognize and manage conflicts of interest Introduce the

More information

Aviva plc. General Accident plc GOODWILL PAYMENT SCHEME IN RESPECT OF PREFERENCE SHARES. Scheme Terms and Conditions

Aviva plc. General Accident plc GOODWILL PAYMENT SCHEME IN RESPECT OF PREFERENCE SHARES. Scheme Terms and Conditions 31 May 2018 Aviva plc General Accident plc GOODWILL PAYMENT SCHEME IN RESPECT OF PREFERENCE SHARES Scheme Terms and Conditions Definitions 1.1 In this Scheme, the following words and expressions have the

More information

FROM ISDS TO ICS: A LEOPARD CAN T CHANGE ITS SPOTS

FROM ISDS TO ICS: A LEOPARD CAN T CHANGE ITS SPOTS FROM ISDS TO ICS: A LEOPARD CAN T CHANGE ITS SPOTS Brussels, 11 February 2016 POSITION PAPER ON THE COMMISSION PROPOSAL FOR AN INVESTMENT COURT SYSTEM IN TTIP This position paper illustrates Greenpeace

More information

CHARITY LAW BULLETIN NO. 49

CHARITY LAW BULLETIN NO. 49 CHARITY LAW BULLETIN NO. 49 JULY 30, 2004 REVISED NOVEMBER 2, 2004 Editor: Terrance S. Carter ONTARIO SUPERIOR COURT OF JUSTICE REAFFIRMS UNENFORCEABILITY OF PLEDGES By Terrance S. Carter, B.A., LL.B.,

More information

Lawrence Ochulor 1. Introduction

Lawrence Ochulor 1. Introduction THE DIALECTICS OF THE COURT OF APPEAL PRONOUNCEMENTS ON NON- ARBITRABILITY OF TAX DISPUTES IN NIGERIA: DRAWING A DISTINCTION BETWEEN TAX AND CONTRACTUAL DISPUTES IN NIGERIA Introduction Lawrence Ochulor

More information

Tribes Need More Than Just The Sovereign Immunity Defense

Tribes Need More Than Just The Sovereign Immunity Defense Portfolio Media. Inc. 111 West 19 th Street, 5th Floor New York, NY 10011 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Tribes Need More Than Just The Sovereign

More information

CITY OF LOS ANGELES, Plaintiff and Appellant, v. CENTEX TELEMANAGEMENT, INC., Defendant and Respondent.

CITY OF LOS ANGELES, Plaintiff and Appellant, v. CENTEX TELEMANAGEMENT, INC., Defendant and Respondent. 29 Cal. App. 4th 1384, *; 1994 Cal. App. LEXIS 1113, **; 34 Cal. Rptr. 2d 782, ***; 94 Cal. Daily Op. Service 8396 CITY OF LOS ANGELES, Plaintiff and Appellant, v. CENTEX TELEMANAGEMENT, INC., Defendant

More information

the imposition of a duty of fair dealing on all parties to the franchise agreement; and

the imposition of a duty of fair dealing on all parties to the franchise agreement; and Lawyers, Patent & Trade-mark Agents 150 York Street, Suite 800 Toronto ON M5H 3S5 Tel: 416.364.1553 Fax: 416.364.1453 Canadian Franchise Legislation: An Overview 1 A. Introduction David Kornhauser dkornhauser@msmlaw.ca

More information

2014 Thomson Reuters. No claim to original U.S. Government Works. 1

2014 Thomson Reuters. No claim to original U.S. Government Works. 1 2010 WL 1600562 Only the Westlaw citation is currently available. NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. s 2-102(E).

More information

a guide to the use of CCDC stipulated price contract

a guide to the use of CCDC stipulated price contract 20 20 a guide to the use of CCDC 2-2008 stipulated price contract 2 0 0 8 The Canadian Construction Documents Committee (CCDC) is a national joint committee responsible for the development, production

More information

Esso Standard (Inter-America) Inc. v. J. W. Enterprises et al., [1963] S.C.R. 144

Esso Standard (Inter-America) Inc. v. J. W. Enterprises et al., [1963] S.C.R. 144 Osgoode Hall Law Journal Volume 3, Number 2 (April 1965) Article 10 Esso Standard (Inter-America) Inc. v. J. W. Enterprises et al., [1963] S.C.R. 144 M. L. D. Follow this and additional works at: http://digitalcommons.osgoode.yorku.ca/ohlj

More information

-and- THE COMMISSIONERS FOR HER MAJESTY S REVENUE & CUSTOMS JUDGE KEVIN POOLE RICHARD CORKE FCA

-and- THE COMMISSIONERS FOR HER MAJESTY S REVENUE & CUSTOMS JUDGE KEVIN POOLE RICHARD CORKE FCA [13] UKFTT 042 (TC) TC02462 Appeal number: TC/11/0972 INCOME TAX construction industry scheme deductions from payments to subcontractors travel and other expenses included in subcontractor invoices obligation

More information

ConsensusDocs Guidebook

ConsensusDocs Guidebook ConsensusDocs Guidebook ConsensusDocs 410 Agreement and General Conditions Between Owner and Design-Builder (Cost of the Work Plus Fee with GMP) August 2013 Edition Page 1 of 10 Copyright 2013 by ConsensusDocs

More information

Here s a Bonus: You re Fired!

Here s a Bonus: You re Fired! EMPLOYMENT LAW CONFERENCE 2017 PAPER 7.1 Here s a Bonus: You re Fired! If you enjoyed this Practice Point, you can access all CLEBC course materials by subscribing to the Online Course Materials Library

More information

Telecom Decision CRTC

Telecom Decision CRTC Telecom Decision CRTC 2014-601 PDF version Ottawa, 20 November 2014 File number: 8690-E17-201401455 Bragg Communications Incorporated, operating as Eastlink - Dispute over billed charges for Bell Aliant

More information

INVITATION TO TENDER TENDER FORM

INVITATION TO TENDER TENDER FORM INVITATION TO TENDER 09-07-2025 TENDER FORM Submitted by: To: (hereinafter referred to as the Bidder ) Workers Compensation Board Registration Number: CAMOSUN COLLEGE (hereinafter called the Owner ) Purchasing

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV ORAL JUDGMENT OF VENNING J

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV ORAL JUDGMENT OF VENNING J IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2005-404-006984 BETWEEN AND STELLAR PROJECTS LIMITED Appellant NICK GJAJA PLUMBING LIIMITED Respondent Hearing: 10 April 2006 Appearances: Mr J C

More information

EASTEND HOMES LIMITED. - and - (1) AFTAJAN BIBI (2) MAHANARA BEGUM JUDGMENT. Dates: 24 August 2017

EASTEND HOMES LIMITED. - and - (1) AFTAJAN BIBI (2) MAHANARA BEGUM JUDGMENT. Dates: 24 August 2017 Claim No. B00EC907 In the County Court at Central London On Appeal from District Judge Sterlini Sitting at Clerkenwell & Shoreditch His Honour Judge Parfitt EASTEND HOMES LIMITED Appellant - and - (1)

More information

Bulletin Litigation/Mergers & Acquisitions

Bulletin Litigation/Mergers & Acquisitions Blake, Cassels & Graydon LLP December 2008 jeff galway AND michael gans While the decision has been known for months, the Canadian business and legal communities have eagerly awaited the Supreme Court

More information

Comparison of 2007 and 2017 AIA contract documents

Comparison of 2007 and 2017 AIA contract documents Construction & Design Risk Briefing Winter 2017 Comparison of 2007 and 2017 AIA contract documents Architects should consider switching over to the 2017 edition sooner rather than later. As with all form

More information

Best Practices in Pension Plan Governance

Best Practices in Pension Plan Governance Best Practices in Pension Plan Governance Randy Bauslaugh Partner McCarthy Tétrault Toronto, Ontario The opinions expressed in this presentation are those of the speaker. The International Society and

More information

Third District Court of Appeal State of Florida

Third District Court of Appeal State of Florida Third District Court of Appeal State of Florida Opinion filed February 21, 2018. Not final until disposition of timely filed motion for rehearing. No. 3D16-1881 Lower Tribunal No. 15-9465 Liork, LLC and

More information

INSURANCE LAW BULLETIN

INSURANCE LAW BULLETIN INSURANCE LAW BULLETIN April 1, 2013 Rose Bilash & Caroline Theriault NON-EARNER BENEFITS: ASSESSING ENTITLEMENT FOLLOWING THE COURT OF APPEAL RULING IN GALDAMEZ [The information below is provided as a

More information

Steptoe & so on. The facts of the case. What is the issue? What does it mean to me? What can I take away? 1 November 2015

Steptoe & so on. The facts of the case. What is the issue? What does it mean to me? What can I take away? 1 November 2015 Steptoe & so on 1 November 2015 Keith Gordon reviews the First-tier s decision in Barrett v HMRC [2015] UKFTT 0329 (TC) What is the issue? Mr Barrett, a jobbing builder, took on casual labour on a subcontract

More information

LANDMARK CASE BCE INC. V DEBENTUREHOLDERS

LANDMARK CASE BCE INC. V DEBENTUREHOLDERS BCE INC. V. 1976 DEBENTUREHOLDERS CURRICULUM LINKS: Canadian and International Law, Grade 12, University Preparation (CLN4U) Understanding Canadian Law, Grade 11, University/College Preparation (CLU3M)

More information

Trends and Developments in Public Works Law and Practice

Trends and Developments in Public Works Law and Practice Trends and Developments in Public Works Law and Practice APWA Public Works Conference 2015 Presented by: Arne B. Sandberg, Lozano Smith Ron Bernal, City of Antioch INTRODUCTION New ADR Requirements for

More information

NORTHWEST INSURANCE LAW

NORTHWEST INSURANCE LAW NORTHWEST INSURANCE LAW QUARTERLY NEWSLETTER WINTER 2018 Williams Kastner has been serving clients in the Pacific Nor thwest since our Seattle office opened in 1929. With more than 60 attorneys in offices

More information

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - APPEAL DIVISION

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - APPEAL DIVISION Page: 1 PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - APPEAL DIVISION Citation: Trigen v. IBEW & Ano. 2002 PESCAD 16 Date: 20020906 Docket: S1-AD-0930 Registry: Charlottetown BETWEEN: AND: TRIGEN

More information

Designing an Effective Arbitration Clause

Designing an Effective Arbitration Clause Designing an Effective Arbitration Clause Claims and disputes arising from construction projects are often costly and time consuming to resolve. While it is best to avoid construction claims and disputes

More information

Heads of Terms of the Design Agreement for the Moscow Kazan Section of the Moscow Kazan Ekaterinburg High-Speed Railway Line

Heads of Terms of the Design Agreement for the Moscow Kazan Section of the Moscow Kazan Ekaterinburg High-Speed Railway Line Heads of Terms of the Design Agreement for the Moscow Kazan Section of the Moscow Kazan Ekaterinburg High-Speed Railway Line October 2013 Moscow Key Information These heads of terms (the Heads of Terms)

More information

Contract No BO0. A. Definitions. As used in this Contract the terms are defined as follows:

Contract No BO0. A. Definitions. As used in this Contract the terms are defined as follows: A. Definitions Contract No. 13139BO0 As used in this Contract the terms are defined as follows: 1. County and/or Owner shall mean the Board of County Supervisors of Prince William County, Virginia, or

More information

WCI Communities, Inc., and certain related Debtors FORM OF CHINESE DRYWALL PROPERTY DAMAGE AND PERSONAL INJURY SETTLEMENT TRUST AGREEMENT

WCI Communities, Inc., and certain related Debtors FORM OF CHINESE DRYWALL PROPERTY DAMAGE AND PERSONAL INJURY SETTLEMENT TRUST AGREEMENT WCI Communities, Inc., and certain related Debtors FORM OF CHINESE DRYWALL PROPERTY DAMAGE AND PERSONAL INJURY SETTLEMENT TRUST AGREEMENT WCI Communities, Inc., and certain related Debtors CHINESE DRYWALL

More information

IN THE LABOUR COURT OF SOUTH AFRICA HELD AT JOHANNESBURG

IN THE LABOUR COURT OF SOUTH AFRICA HELD AT JOHANNESBURG IN THE LABOUR COURT OF SOUTH AFRICA HELD AT JOHANNESBURG Case Nos: JR1061-2007 In the matter between: SAMANCOR LIMITED Applicant and NUM obo MARIFI JOHANNES MALOMA First Respondent TAXING MASTER, LABOUR

More information

DECISION APPLICATION FOR STAY OR ADJOURNMENT

DECISION APPLICATION FOR STAY OR ADJOURNMENT IN THE MATTER OF THE NATURAL PRODUCTS MARKETING (BC) ACT AND APPEALS FROM DECISIONS OF THE BRITISH COLUMBIA MUSHROOM MARKETING BOARD CONCERNING THE MARKETING OF PRODUCT BETWEEN: THANH BINH LAM AND TRANG

More information

Retaining a Chartered Business Valuator:

Retaining a Chartered Business Valuator: THE MNP VALUATION GUIDANCE SERIES Retaining a Chartered Business Valuator: A Guide for Lawyers, Accountants and their Clients The MNP Valuation Guidance Series MNP LLP s Chartered Business Valuators provide

More information

Case Note September 2007

Case Note September 2007 Case Note September 2007 CGU Limited v AMP Financial Planning Pty Ltd On Wednesday 29 August 2007 Chief Justice Gleeson and Justices Kirby, Callinan, Heydon and Crennan handed down the judgement of the

More information

AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME

AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME WORKING NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP VERSION 1 APPROVED

More information

IAASB CAG REFERENCE PAPER IAASB CAG Agenda (December 2005) Agenda Item I.2 Accounting Estimates October 2005 IAASB Agenda Item 2-B

IAASB CAG REFERENCE PAPER IAASB CAG Agenda (December 2005) Agenda Item I.2 Accounting Estimates October 2005 IAASB Agenda Item 2-B PROPOSED INTERNATIONAL STANDARD ON AUDITING 540 (REVISED) (Clean) AUDITING ACCOUNTING ESTIMATES AND RELATED DISCLOSURES (OTHER THAN THOSE INVOLVING FAIR VALUE MEASUREMENTS AND DISCLOSURES) (Effective for

More information

2018 PA Super 45. Appeal from the Order entered March 29, 2017 In the Court of Common Pleas of Chester County Civil Division at No: CT

2018 PA Super 45. Appeal from the Order entered March 29, 2017 In the Court of Common Pleas of Chester County Civil Division at No: CT 2018 PA Super 45 WILLIAM SMITH SR. AND EVERGREEN MANAGEMENT GROUP, INC. IN THE SUPERIOR COURT OF PENNSYLVANIA v. BRIAN HEMPHILL AND COMMERCIAL SNOW + ICE, LLC APPEAL OF BARRY M. ROTHMAN, ESQUIRE No. 1351

More information

Ethical Contract Negotiation

Ethical Contract Negotiation Ethical Contract Negotiation Texas Society of Professional Engineers May 16, 2006 Brian W. Erikson Quilling, Selander, Cummiskey & Lownds, P.C. 2001 Bryan Street, Suite 1800 Dallas, Texas 75201 (214) 880-1844

More information

Learning When to Waive Good-Bye. DPLE 195 September 19, 2018

Learning When to Waive Good-Bye. DPLE 195 September 19, 2018 Learning When to Waive Good-Bye DPLE 195 September 19, 2018 1 RLI Design Professionals is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on

More information

BANKS AND FINANCIAL INSTITUTION APPEAL BOARD BETWEEN: THE BELIZE BANK LTD APPELLANT THE CENTRAL BANK OF

BANKS AND FINANCIAL INSTITUTION APPEAL BOARD BETWEEN: THE BELIZE BANK LTD APPELLANT THE CENTRAL BANK OF BANKS AND FINANCIAL INSTITUTION APPEAL BOARD APPEAL NO. 1 OF 2008 BETWEEN: THE BELIZE BANK LTD APPELLANT AND THE CENTRAL BANK OF BELIZE RESPONDENT Mr. A. Marshalleck and Ms. Naima Badillo for the appellant.

More information

United States Small Business Administration Office of Hearings and Appeals

United States Small Business Administration Office of Hearings and Appeals Cite as: Size Appeal of Henderson Group Unlimited, Inc., SBA No. SIZ-5034 (2009) United States Small Business Administration Office of Hearings and Appeals SIZE APPEAL OF: Henderson Group Unlimited, Inc.

More information

CONSTRUCTIVE DISMISSAL AND THE DUTY TO MITIGATE

CONSTRUCTIVE DISMISSAL AND THE DUTY TO MITIGATE CONSTRUCTIVE DISMISSAL AND THE DUTY TO MITIGATE In 1997, in a case called Farber v. Royal Trust Co. 1, the Supreme Court of Canada discussed the nature of constructive dismissal in Canada and the rights

More information

IN THE SUPREME COURT OF SOUTH AFRICA (APPELLATE DIVISION) COMMISSIONER FOR INLAND REVENUE SOUTHERN LIFE ASSOCIATION LIMITED

IN THE SUPREME COURT OF SOUTH AFRICA (APPELLATE DIVISION) COMMISSIONER FOR INLAND REVENUE SOUTHERN LIFE ASSOCIATION LIMITED IN THE SUPREME COURT OF SOUTH AFRICA (APPELLATE DIVISION) CASE NO 665/92 In the matter between COMMISSIONER FOR INLAND REVENUE Appellant versus SOUTHERN LIFE ASSOCIATION LIMITED Respondent CORAM: HOEXTER,

More information

Jaff (s.120 notice; statement of additional grounds ) [2012] UKUT 00396(IAC) THE IMMIGRATION ACTS. Before UPPER TRIBUNAL JUDGE GRUBB.

Jaff (s.120 notice; statement of additional grounds ) [2012] UKUT 00396(IAC) THE IMMIGRATION ACTS. Before UPPER TRIBUNAL JUDGE GRUBB. Upper Tribunal (Immigration and Asylum Chamber) Jaff (s.120 notice; statement of additional grounds ) [2012] UKUT 00396(IAC) THE IMMIGRATION ACTS Heard at Field House On 21 August 2012 Determination Promulgated

More information

Small Business Enterprise (SBE) Subcontracting Program. Policies and Procedures Manual

Small Business Enterprise (SBE) Subcontracting Program. Policies and Procedures Manual Small Business Enterprise (SBE) Subcontracting Program Policies and Procedures Manual February, 2010 Article TABLE OF CONTENTS Page No. 1. Definitions 2 2. The Office of Contract Compliance 3 3. Eligibility

More information

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND PRINCE EDWARD ISLAND COURT OF APPEAL

Page: 1 PROVINCE OF PRINCE EDWARD ISLAND PRINCE EDWARD ISLAND COURT OF APPEAL Page: 1 PROVINCE OF PRINCE EDWARD ISLAND PRINCE EDWARD ISLAND COURT OF APPEAL Citation: Doiron v. Island Regulatory and Appeals Commission 2011 PECA 9 Date: 20110603 Docket: S1-CA-1205 Registry: Charlottetown

More information