Xantrex Complete Charge Controller Supplemental Owner s Manual Rev 1.0 Copyright 2012

Size: px
Start display at page:

Download "Xantrex Complete Charge Controller Supplemental Owner s Manual Rev 1.0 Copyright 2012"

Transcription

1 Xantrex Complete Charge Controller Supplemental Owner s Manual Rev 1.0 Copyright

2 Table of Contents Introduction 3 Main Components of the Xantrex Complete Charge Controller 3 Mounting the Xantrex Complete Charge Controller...4 Connecting the Wind Turbine to the Xantrex Complete Charge Controller 4 Setting the Voltage and Operating Mode Jumpers for the Xantrex C- Series Charge Controller 5 Adjusting the Voltage Settings of the Xantrex C- Series Charge Controller 5 Grounding the Xantrex Complete Charge Controller 5 Wiring the Xantrex Complete Charge Controller to the Renewable Energy (RE) System 5-6 Trouble Shooting the Xantrex Complete Charge Controller 6 2

3 Introduction Thank you for your purchase of the Windy Nation s Xantrex Complete Charge Controller. This Supplemental Owner s Manual is to be used as a supplemental guide to the Xantrex C- Series Charge Controller Owner Manual which is also included with your purchase. This supplemental manual in no way replaces the instructions in the Xantrex C- Series Charge Controller Owner s Manual. Before you begin to install Windy Nation s Xantrex Complete Charge Controller, you must completely read and understand the Xantrex C- Series Charge Controller Owner s Manual. Failure to read and understand the Xantrex C- Series Charge Controller Owner s Manual could result in property damage, serious injury and death. Main Components of the Xantrex Complete Charge Controller The Xantrex Complete Charge Controller consists of four main components: 1. The Xantrex C- Series Charge Controller (C35, C40 or C60): The Xantrex C- Series Charge Controller serves the purpose of monitoring the voltage of the battery bank. The charge controller regulates when power should be diverted to the dump loads to prevent overcharging of the battery bank. 2. An 80 amp 3- phase bridge rectifier: The 80 amp 3- phase bridge rectifier converts the 3- phase AC electricity of the wind turbine or renewable energy source to DC electricity. 3. Wire wound resistors (dump loads or diversion loads): The wire wound resistors act as dump loads and consume power from the battery bank to prevent the battery bank from being overcharged by the renewable energy source(s) (e.g. wind turbine, hydro, and solar). 4. Electrical wire: The electrical wire is used to make electrical connections between the charge controller, dump load(s), 3- phase bridge rectifier, and battery bank. Figure 1: Main components of Xantrex Complete Charge Controller. 3

4 Mounting the Xantrex Complete Charge Controller Use the four mounting holes at the base of the Xantrex Complete Charge Controller to mount the unit to a wall. The controller is designed for indoor mounting. Care should be taken in selecting a location and when mounting the enclosure. Avoid mounting it in direct sun light to prevent heating of the enclosure. The enclosure should be mounted vertically on a wall. In outdoor installations, the C- Series controller must be installed in a rainproof enclosure to eliminate exposure to rain, mist or water- spray. Connecting the Wind Turbine to the Xantrex Complete Charge Controller The three AC wires from the 3- phase AC wind turbine or renewable energy source need to be connected to the three AC terminals on the 3- phase AC bridge rectifier. Depending on (a) the length of the wire run between the wind turbine and the Xantrex Complete Charge Controller and (b) the power that the wind turbine produces, the three wires traveling from the wind turbine to the 3- phase bridge rectifier should be 8, 10 or 12 AWG stranded, outdoor rated wire. There is one unused cable gland on the face of the Xantrex Complete Charge Controller which is to be used to run these three wires into the enclosure. See photo and instructions below in Figure 2. Figure 2: Run the three AC wires coming from the wind turbine or renewable energy source (yellow wires) through the unused cable gland. Then connect these three wires to the three empty terminals on the 3- phase bridge rectifier. Make sure the your firmly tighten the cable gland after you have installed the three wires. 4

5 Setting the Voltage and Operating Mode Jumpers for the Xantrex C- Series Charge Controller Windy Nation configured the Voltage Jumper for the Xantrex C- Series Charge Controller at the factory. (e.g. 12 volt Xantrex Complete Charge Controllers have been set for 12 volt battery bank operation, 24 volt Xantrex Complete Charge Controllers have been set for 24 volt battery bank operation, and 48 volt Xantrex Complete Charge Controllers have been set for 48 volt battery bank operation.) WindyNation has also configured the Operating Mode Jumper at the factory. It has been set to Charge Control Mode Jumper which is the appropriate setting for operating the controller in Diversion Mode. Refer to page 20 of the Xantrex C- Series Owner s Manual for an explanation of how the Xantrex C- Series Voltage and Operating Mode Jumpers are configured to operate correctly. Adjusting the Voltage Settings of the Xantrex C- Series Charge Controller WindyNation has NOT set the bulk and float voltage trip points on the Xantrex C- Series Charge Controller. The reason this is NOT done by Windy Nation is because different battery types (e.g. automotive batteries, maintenance free batteries, deep cycle batteries, sealed batteries, etc.) require different charging /discharging voltage levels. Refer to pages of the Xantrex C- Series Owner s Manual and contact the company that sold you the batteries or the manufacturer of the batteries to find out the appropriate voltage settings (bulk and float) for your particular batteries. Once you determine the appropriate charging (bulk and float) voltage settings for your batteries, refer to pages 4-5 and pages in the Xantrex Owner s Manual for directions on how to set the bulk and float voltage settings on the Xantrex C- Series Charge Controller. Grounding the Xantrex Complete Charge Controller Refer to page 37 of the Xantrex Owner s Manual for instructions on how to properly ground the Xantrex C- Series Charge Controller. Wiring the Xantrex Complete Charge Controller to the Renewable Energy (RE) System For detailed instructions on wiring the Xantrex Charge Controller, refer to pages and The Windy Nation Xantrex Complete Charge Controller has been wired in Diversion Mode at the factory. Refer to pages of the Xantrex Owner s Manual for a detailed description of the Diversion Mode wiring schematics. After reviewing pages of the Xantrex Owner s Manual, you will see that there are additional wiring steps that must be completed to safely and properly connect the Xantrex Complete Charge Controller to your RE system. These steps are listed below and can be referred to on pages of the Xantrex C- Series Owner s Manual: 5

6 1. Connect your DC current source (PV, wind, hydro, etc.) directly to the RE disconnect. This is the red wire marked 1 in Figure 3 below. 2. Connect another cable from the other side of the RE disconnect to the battery positive terminal. 3. Run a negative wire from the DC current source (PV, wind, hydro, etc.) to the battery negative terminal. This is the black wire marked 3 in Figure 3 below. 4. Connect a cable from the Xantrex controller terminal marked BAT POS to the battery disconnect. This is the red wire marked 4 in Figure 3 below. 5. Connect a cable from the battery disconnect to the positive terminal of the battery. 6. Connect a cable from the negative battery terminal to one of the terminals marked COMMON NEGATIVES on the controller s circuit board. This is the black wire marked 6 in Figure 3 below. 7. Connect a cable from the controller s other terminal marked COMMON NEGATIVES to the negative terminal of your DC diversion load. This is the black wire marked 7 in Figure 3 below. 8. Connect a cable from the controller s terminal marked PV+/LOAD+ to the positive terminal of the DC diversion load. This is the red wire marked 8 in Figure 3 below. Figure 3: Labeled wires inside the Xantrex Complete Charge Controller Trouble Shooting the Xantrex Complete Charge Controller Refer to pages of the Xantrex C- Series Owner s Manual for trouble shooting solutions to common set- up and operating issues. 6

Xantrex XW Power System Xantrex XW / Xantrex XW / Xantrex XW /240 60

Xantrex XW Power System Xantrex XW / Xantrex XW / Xantrex XW /240 60 Xantrex XW Power System Xantrex XW4024 120/240 60 Xantrex XW4548 120/240 60 Xantrex XW6048 120/240 60 Installation Guide www.schneider-electric.com Xantrex XW Power System Installation Guide www.schneider-electric.com

More information

Application for Interconnection and Net Metering Level 1

Application for Interconnection and Net Metering Level 1 Application for Interconnection and Net Metering Level 1 Use this Application only for: 1.) a generating facility that is inverter based and certified by a nationally recognized testing laboratory to meet

More information

Xantrex XW Hybrid Inverter/Charger

Xantrex XW Hybrid Inverter/Charger Xantrex XW Hybrid Inverter/Charger Xantrex XW4024 230 50 Xantrex XW4548 230 50 Xantrex XW6048 230 50 Installation Guide www.schneider-electric.com YOUR SCHNEIDER ELECTRIC DISTRIBUTOR SOLIGENT 800-967-6917

More information

Interconnection Process and Guide for Small Power Generation Systems

Interconnection Process and Guide for Small Power Generation Systems Interconnection Process and Guide for Small Power Generation Systems As Adopted by the Board of Directors South Central Indiana REMC July 2014 Amended 05-25-2017 South Central Indiana REMC 300 Morton Avenue

More information

SS-10 ELECTRONIC INTERFACE INSTALLATION GUIDE

SS-10 ELECTRONIC INTERFACE INSTALLATION GUIDE SS-10 ELECTRONIC INTERFACE INSTALLATION GUIDE OVERVIEW The SS10 is designed to work with most vehicles that are equipped with non-mechanical transmission sensors (no speedometer cable). This interface

More information

MH Corbin SS-10 Electronic Interface Installation Guide Version 2.0

MH Corbin SS-10 Electronic Interface Installation Guide Version 2.0 MH Corbin SS-10 Electronic Interface Installation Guide Version 2.0 OVERVIEW The SS-10 is designed to work with most vehicles that are equipped with nonmechanical transmission sensors (no speedometer cable).

More information

Interconnection of Electric Generators

Interconnection of Electric Generators Interconnection of Electric Generators (GENERATING CAPACITY OF NOT MORE THAN 25 KILOWATTS) Public Utility #1 of Ferry County Republic Washington November 15, 2007 Table of Contents Chapter 1 Purpose and

More information

DC Power Adapter 120 VAC

DC Power Adapter 120 VAC DC Power Adapter 120 VAC The DC Power Adapter 120 VAC is within an enclosure for indoor use and must be connected to a 120 VAC standard outlet. It supplies power to analog and digital circuits through

More information

Name: City: State: Zip Code: Is the applicant the property owner at the system address? Yes No. City: State: Zip Code: City: State: Zip Code:

Name: City: State: Zip Code: Is the applicant the property owner at the system address? Yes No. City: State: Zip Code: City: State: Zip Code: Maryland Level 1 Interconnection Request Application Form and Conditional Agreement to Interconnect (Lab Certified Inverter-based Small Generator Facilities Less than 10 kw) Interconnection Applicant Contact

More information

TMCC Operating Track Controller (OTC) /02

TMCC Operating Track Controller (OTC) /02 TMCC Operating Track Controller (OTC) 71-4185-250 11/02 Congratulations Congratulations on your purchase of the TMCC Operating Track Controller (OTC)! The incredible OTC unit is capable of controlling

More information

MODEL STANDING OFFER TERMS & CONDITIONS FOR BASIC CONNECTION SERVICES FOR RETAIL CUSTOMERS WHO ARE SMALL GENERATORS 3602

MODEL STANDING OFFER TERMS & CONDITIONS FOR BASIC CONNECTION SERVICES FOR RETAIL CUSTOMERS WHO ARE SMALL GENERATORS 3602 MODEL STANDING OFFER TERMS & CONDITIONS FOR BASIC CONNECTION SERVICES FOR RETAIL CUSTOMERS WHO ARE SMALL GENERATORS 3602 SA Power Networks www.sapowernetworks.com.au 3602 - MSO T_C's for BCS for Retail

More information

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment B to Schedule 150, Page 1

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment B to Schedule 150, Page 1 WN U-60 Attachment B to Schedule 150, Page 1 FUEL CELL, SOLAR, WIND, BIOGAS, COMBINED HEAT AND POWER, OR HYDROPOWER ELECTRIC GENERATING FACILITIES OF 100 KILOWATTS OR LESS Application and Agreement for

More information

Steps/Process. <COOPERATIVE NAME> 10 kw INVERTER PROCESS Page 1

Steps/Process. <COOPERATIVE NAME> 10 kw INVERTER PROCESS Page 1 10 kw INVERTER PROCESS Page 1 Application, Procedures, and Terms and Conditions for Interconnecting a Certified Inverter-Based Generation Facility No Larger than 10 kw ("10 kw Inverter Process") Steps/Process

More information

INTERCONNECTION GENERATION AND NET METERING POLICY

INTERCONNECTION GENERATION AND NET METERING POLICY INTERCONNECTION GENERATION AND NET METERING POLICY Manual for Member Owned Interconnection Generation Facilities Equal to 100 kw or Less Revised: May 11, 2015 Approved: August 25, 2014 Effective: August

More information

P.O. BOX 1521 POLSON, MT REV D, RELEASED 10/10/2003, QUALITY MANAGER

P.O. BOX 1521 POLSON, MT REV D, RELEASED 10/10/2003, QUALITY MANAGER HELLROARING TECHNOLOGIES, INC. P.O. BOX 1521 POLSON, MT 59860 406 883-3801 HTTP://WWW.HELLROARING.COM SUPPORT@HELLROARING.COM REV D, RELEASED 10/10/2003, QUALITY MANAGER BCM-240CC-24VRG The BCM-240CC-24VRG

More information

Net Metering Interconnections Standards

Net Metering Interconnections Standards Net Metering Interconnections Standards FOR Interconnection of Electric Generators (GENERATING CAPACITY OF NOT MORE THAN 100 KILOWATTS) PUBLIC UTILITY DISTRICT # 1 OF SKAMANIA COUNTY My Documents / Electric

More information

ENTERGY LOUISIANA, LLC STANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES

ENTERGY LOUISIANA, LLC STANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES INSTRUCTIONS Enter information in the empty fields below and send this form to Entergy. This Standard Interconnection Agreement shall be completed, submitted and approved before the net metering facility

More information

Parkland Light & Water Company Park Ave Tacoma, WA 98444

Parkland Light & Water Company Park Ave Tacoma, WA 98444 Parkland Light & Water Company 12918 Park Ave Tacoma, WA 98444 Interconnection Requirements of Member Owned Renewable Electric Generating Facilities of 100 Kilowatts or Less (REVISED 8/29/2015) Table of

More information

Superseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 RULE NO. 18. Net Energy Metering

Superseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 RULE NO. 18. Net Energy Metering Superseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 A. ELIGIBLE CUSTOMER-GENERATOR RULE NO. 18 Net Energy Metering Net energy metering is available

More information

ELECTRICAL FEE SCHEDULE. Effective October 1, 2013 Revision June 2018

ELECTRICAL FEE SCHEDULE. Effective October 1, 2013 Revision June 2018 ELECTRICAL FEE SCHEDULE Effective October 1, 2013 Revision June 2018 ELECTRICAL FEE SCHEDULE EFFECTIVE OCTOBER 1, 2013 Table 1 CONTRACTOR FLAT RATE PERMIT FEES Work of Electrical Installation Fee ($) 1.

More information

Interconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW

Interconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW Interconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW A. APPLICANT INFORMATION *Person/Company Name: *OUC Account No.: *Mailing Address: *City, State & Zip: Street Address

More information

Interconnection Request Application Form for Interconnecting a Certified Inverter-Based Generating Facility No Larger than 20 kw

Interconnection Request Application Form for Interconnecting a Certified Inverter-Based Generating Facility No Larger than 20 kw Attachment 6 Interconnection Request Application Form for Interconnecting a Certified Inverter-Based Generating Facility No Larger than 20 kw This Interconnection Request Application Form is considered

More information

QM35. Cover. Output. A = Line Driver B = Line Driver (ABZ) /Open Collector (UVW) C = Dual Votage Line Driver (ABZ)/ Open Collector (UVW)

QM35. Cover. Output. A = Line Driver B = Line Driver (ABZ) /Open Collector (UVW) C = Dual Votage Line Driver (ABZ)/ Open Collector (UVW) QM35 DESIGN FEATURES Bearingless modular design Low profile assembled height Resolutions up to 8192 lines per revolution 4, 6, 8 or 10 pole commutation Easy lock-n-twist assembly feature Through shaft

More information

ENTERGY NEW ORLEANS, INC. STANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES LOCATED IN ORLEANS PARISH

ENTERGY NEW ORLEANS, INC. STANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES LOCATED IN ORLEANS PARISH INSTRUCTIONS: Enter information in the empty fields below and send this form to Entergy. This Standard Interconnection Agreement shall be completed, submitted and approved before the net metering facility

More information

QML35. Cover. Voltage A = 5V (+/- 5%) B = 3.3V (+/- 5%)

QML35. Cover. Voltage A = 5V (+/- 5%) B = 3.3V (+/- 5%) QML35 DESIGN FEATURES Bearingless modular design Low profile assembled height Resolutions up to 8192 lines per revolution 4, 6, 8 or 10 pole commutation Easy lock-n-twist assembly feature Through shaft

More information

CAPTIVUE SPORTS MESSAGE CENTER INSTRUCTION MANUAL REVISION DATE: PART#:

CAPTIVUE SPORTS MESSAGE CENTER INSTRUCTION MANUAL REVISION DATE: PART#: CAPTIVUE SPORTS MESSAGE CENTER INSTRUCTION MANUAL REVISION DATE: 08-21-07 PART#: 98-0019-42 SERVICE & CUSTOMER INFORMATION CUSTOMER MUST HAVE PART NUMBER WHEN ORDERING ITEMS THROUGH THE SERVICE DEPARTMENT.

More information

33000 Module Installation Guide

33000 Module Installation Guide 33000 Module Installation Guide 1996-2004 ECMs DDEC iii & DDECiv 12.7L & 14.0l Detroit Engines Up to 30% HP Gain 10-20% Fuel Savings AgDieselSolutions.com Power +12 volts (Red) & Ground (Black) Adjustable

More information

Public Utility District Number 1 of Klickitat County POLICY BULLETIN 21. Customer Service Policy Electric

Public Utility District Number 1 of Klickitat County POLICY BULLETIN 21. Customer Service Policy Electric Public Utility District Number 1 of Klickitat County POLICY BULLETIN 21 Customer Service Policy Electric I. Definition of Terms A. Applicant - The person(s) applying for electric service. B. Customer -

More information

Cinelabs Sanyo EZ-20 Flyback Installation Guide

Cinelabs Sanyo EZ-20 Flyback Installation Guide Cinelabs Sanyo EZ-20 Flyback Installation Guide WARNING: CRT display monitors can produce lethal voltages. Refer servicing to qualified service personnel. PLEASE NOTE: This product is intended to be installed

More information

HOLY CROSS ENERGY November 3, 2015 GENERATOR INTERCONNECT POLICY

HOLY CROSS ENERGY November 3, 2015 GENERATOR INTERCONNECT POLICY GENERATOR INTERCONNECT POLICY GENERATOR INTERCONNECT (PROCEDURE) GENERATOR INTERCONNECT (GUIDELINES) Page 1 of 50 TABLE OF CONTENTS GENERATOR INTERCONNECT (PROCEDURE)... 4 I. GENERAL OVERVIEW... 5 A. Applicability...

More information

I. Members Applying for New Interconnection/Submission of Plans/Specifications.

I. Members Applying for New Interconnection/Submission of Plans/Specifications. PLATTE-CLAY ELECTRIC COOPERATIVE APPLICATION AND AGREEMENT FOR INTERCONNECTION AND NET METERING OF RENEWABLE ENERGY SYSTEMS WITH CAPACITY OF 100 kw OR LESS PROCEDURES: I. Members Applying for New Interconnection/Submission

More information

Interconnection Process for Customer-Owned Generation (QFs)

Interconnection Process for Customer-Owned Generation (QFs) Interconnection Process for Customer-Owned Generation (QFs) Member-consumer makes Co-op letter explaining process & providing information (including co-op Application Member reviews information Member

More information

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows: LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 100 KW AND LESS THAN OR EQUAL TO 1 MW TIER 3 This Interconnection Agreement

More information

STANDARD INTERCONNECTION AGREEMENT FOR INTERCONNECTED CUSTOMER-OWNED BATTERY SUBSYSTEMS 1 KW OR MORE

STANDARD INTERCONNECTION AGREEMENT FOR INTERCONNECTED CUSTOMER-OWNED BATTERY SUBSYSTEMS 1 KW OR MORE STANDARD INTERCONNECTION AGREEMENT FOR INTERCONNECTED CUSTOMER-OWNED BATTERY SUBSYSTEMS 1 KW OR MORE This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"),

More information

User Manual. Plenum DVI Dual Link Male/Male Cable ATP-14009

User Manual. Plenum DVI Dual Link Male/Male Cable ATP-14009 User Manual Plenum DVI Dual Link Male/Male Cable ATP-14009 www.atlona.com DESCRIPTION Rated Voltage (V) - Rated Temperature ( C) 75 Product Standard Certification CL2P Flame test NFPA 262/UL910 Application

More information

Small Generator Interconnection Application

Small Generator Interconnection Application Small Generator Interconnection Application Eligibility: All Interconnection Customers must submit a completed copy of this application to Holy Cross Energy s Power Supply Department. HCE s review process

More information

BOARD POLICY NUMBER 38 NET METERING AND COOPERATIVE PURCHASE OF EXCESS MEMBER OWNED GENERATION CAPACITY

BOARD POLICY NUMBER 38 NET METERING AND COOPERATIVE PURCHASE OF EXCESS MEMBER OWNED GENERATION CAPACITY I. OBJECTIVE BOARD POLICY NUMBER 38 NET METERING AND COOPERATIVE PURCHASE OF EXCESS MEMBER OWNED GENERATION CAPACITY To encourage member investment in renewable energy resources, comply with the Public

More information

CAPE HATTERAS ELECTRIC COOPERATIVE

CAPE HATTERAS ELECTRIC COOPERATIVE CAPE HATTERAS ELECTRIC COOPERATIVE INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities

More information

ARKANSAS PUBLIC SERVICE COMMISSION

ARKANSAS PUBLIC SERVICE COMMISSION 2 nd Revised Sheet No. 61.0.1 Schedule Sheet 1 of 18 Replacing: 1 st Revised Sheet No. 61.0.1 61.0. TARIFF GOVERNING THE INSTALLATION OF ELECTRIC UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS AND UNDERGROUND

More information

HP9015 Module Installation Guide

HP9015 Module Installation Guide Up to 30% More Horsepower 10-20% Fuel Savings Cummins 15.0L Final Tier IV Engines HP9015 Module Installation Guide AgDieselSolutions.com Male ECM Connector Power and Ground connections Female ECM Connector

More information

TRI-COUNTY ELECTRIC COOPERATIVE APPLICATION AND AGREEMENT FOR INTERCONNECTION AND NET METERING OF SYSTEMS WITH CAPACITY OF 100 kw OR LESS

TRI-COUNTY ELECTRIC COOPERATIVE APPLICATION AND AGREEMENT FOR INTERCONNECTION AND NET METERING OF SYSTEMS WITH CAPACITY OF 100 kw OR LESS TRI-COUNTY ELECTRIC COOPERATIVE APPLICATION AND AGREEMENT FOR INTERCONNECTION AND NET METERING OF SYSTEMS WITH CAPACITY OF 100 kw OR LESS PROCEDURES: I. Members Applying for New Interconnection/Submission

More information

Cummins 6.7L Tier IV CUCR3004 INSTALLATION INSTRUCTIONS

Cummins 6.7L Tier IV CUCR3004 INSTALLATION INSTRUCTIONS Cummins 6.7L Tier IV CUCR3004 INSTALLATION INSTRUCTIONS For 6.7L Cummins Tier IV Engines CUCR3004_revB 6.7L Cummins Tier IV Engine Instructions Power +12 volts (Red wire) & Ground (Black wire) Injector

More information

Rail Clamps Type BSZ. PINTSCH BUBENZER is certified according to DIN EN ISO 9001:2008. Safe Tried and Trusted High Performance Robust Easy Maintenance

Rail Clamps Type BSZ. PINTSCH BUBENZER is certified according to DIN EN ISO 9001:2008. Safe Tried and Trusted High Performance Robust Easy Maintenance Rail Clamps Type BSZ PINTSCH BUBENZER is certified according to DIN EN ISO 0:0 Safe Tried and Trusted High Performance Robust Easy Maintenance H Description BSZ Main Features Rail clamp spring applied

More information

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows: LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 10 KW AC AND LESS THAN OR EQUAL TO 100 KW AC TIER 2 This Interconnection

More information

OKTOBERFEST IN JULY FOOD VENDOR APPLICATION

OKTOBERFEST IN JULY FOOD VENDOR APPLICATION WHERE: OKTOBERFEST IN JULY FOOD VENDOR APPLICATION Shawnee Mountain Ski Area 401 Hollow Road, East Stroudsburg, PA 18301 WHEN: Saturday, July 14 & Sunday, July 15, 2018 11:00 am to 5:00 pm both days SET-UP:

More information

STANDARD INTERCONNECTION APPLICATION FOR NET METERING FACILITIES

STANDARD INTERCONNECTION APPLICATION FOR NET METERING FACILITIES STANDARD INTERCONNECTION APPLICATION FOR NET METERING FACILITIES This application and interconnection agreement is for grid connected, customer owned generating facilities using certified inverters that

More information

Welcome to Home Wiring Repair Essential. No-cost, no hassle home wiring repairs.

Welcome to Home Wiring Repair Essential. No-cost, no hassle home wiring repairs. Welcome to Home Wiring Repair Essential. No-cost, no hassle home wiring repairs. Important program terms and conditions are inside. Please file for future reference. 2015 Duke Energy Corporation 151299-hw

More information

Renewable Generation (Category 2 20 kw to 150 kw)

Renewable Generation (Category 2 20 kw to 150 kw) Renewable Generation (Category 2 20 kw to 150 kw) Net Metering Program Generator Interconnection Application Interconnection & Parallel Operating Agreement 01/13 Net Metering Program What is net metering?

More information

Accessories and Spare Parts

Accessories and Spare Parts For T Contactors and Contactor Relays Accessories for TB, TC, TF, TG, TK contactors Size Type kg Solid-state compatible auxiliary switch blocks with screw terminals 5TY7 561-1. 14 2 and 4 TF68 For mounting

More information

ENTERGY MISSISSIPPI, INC. STANDARD INTERCONNECTION APPLICATION AND AGREEMENT FOR NON-RESIDENTIAL NET METERING FACILITIES (for kw systems)

ENTERGY MISSISSIPPI, INC. STANDARD INTERCONNECTION APPLICATION AND AGREEMENT FOR NON-RESIDENTIAL NET METERING FACILITIES (for kw systems) INSTRUCTIONS: Enter information in the empty fields below and send this form to Entergy Mississippi, Inc. ( Entergy or the Company ). This Standard Interconnection Application and Agreement shall be completed,

More information

DIN ISO 9001 : 2000 QA-Nr.: Safe Tried and Trusted High Performance Robust Easy Maintenance

DIN ISO 9001 : 2000 QA-Nr.: Safe Tried and Trusted High Performance Robust Easy Maintenance Rail Clamps Type BSZ DIN ISO 0 : 00 QA-Nr.: 0400 924 BUBENZER BREMSEN is certified according to DIN EN ISO 0:00 Safe Tried and Trusted igh Performance Robust Easy Maintenance Description BSZ Main Features

More information

Users Guide for Ac-MINI

Users Guide for Ac-MINI Problem solved. Users Guide for Ac-MINI Thank you for choosing Anywhere Cart! The AC-MINI is designed to charge and store 1-12 Chromebooks, tablets, and laptops. The AC-MINI-16 is designed to charge and

More information

INVITATION FOR QUOTATION. TEQIP-III/2018/uceo/Shopping/19

INVITATION FOR QUOTATION. TEQIP-III/2018/uceo/Shopping/19 INVITATION FOR QUOTATION TEQIP-III/2018/uceo/Shopping/19 09-May-2018 To, tion for Quotations for supply of Goods Sub: Invita Dear Sir, 1. You are invited to submit your most competitive quotation for the

More information

Southern California Edison Company FERC Electric Tariff, Second Revised Volume No. 5. APPENDIX 10 to GIP

Southern California Edison Company FERC Electric Tariff, Second Revised Volume No. 5. APPENDIX 10 to GIP APPENDIX 10 to GIP Application, Procedures, and Terms and Conditions for Interconnecting a Certified Inverter-Based Small Generating Facility No Larger than 10 kw ("10 kw Inverter Process") 1.0 The Interconnection

More information

Customer Information Packet on Net(B) Metering SYSTEM MUST BE OWNED AND OPERATED BY CUSTOMERS OF WAKEFIELD MUNICIPAL GAS AND LIGHT DEPARTMENT

Customer Information Packet on Net(B) Metering SYSTEM MUST BE OWNED AND OPERATED BY CUSTOMERS OF WAKEFIELD MUNICIPAL GAS AND LIGHT DEPARTMENT Net(B) Metering Customer Information Packet on Net(B) Metering SYSTEM MUST BE OWNED AND OPERATED BY CUSTOMERS OF WAKEFIELD MUNICIPAL GAS AND LIGHT DEPARTMENT 1. Cover Letter to Customers 2. What is Net(B)

More information

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) This Standard contains the requirements, in addition to applicable

More information

Exhibit A Simplified Process Interconnection Application

Exhibit A Simplified Process Interconnection Application Exhibit A Simplified Process Interconnection Application Instructions (please do not submit this page) General Information: If you, the Interconnecting Customer, wish to submit an application to interconnect

More information

ENTERGY MISSISSIPPI, INC. STANDARD INTERCONNECTION APPLICATION AND AGREEMENT FOR RESIDENTIAL NET METERING FACILITIES (for systems 20 kw or less)

ENTERGY MISSISSIPPI, INC. STANDARD INTERCONNECTION APPLICATION AND AGREEMENT FOR RESIDENTIAL NET METERING FACILITIES (for systems 20 kw or less) INSTRUCTIONS: Enter information in the empty fields below and send this form to Entergy Mississippi, Inc. ( Entergy or the Company ). This Standard Interconnection Application and Agreement shall be completed,

More information

Making Power Cool. of residential appliances.

Making Power Cool. of residential appliances. Making Power Cool Richard Gaudet, vice president of Xantrex, a Schneider Electric company Schneider Electric is Xantrex s parent company. Xantrex VP Richard Gaudet says having Schneider as a parent means

More information

13. Manufacturer's warranty Marking 6 W A R N I N G!

13. Manufacturer's warranty Marking 6 W A R N I N G! CONTENT 1. Manufacturer 1 2. General safety informations 1 3. Purpose 2 4. Product compliance 2 5. Degree of protection and technical data 2 6. Type 3 7. Mounting and instalation 3 8. Dimensions 5 9. Inspection,

More information

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 63 SOUTH CAROLINA Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition

More information

Big Country Electric Cooperative, Inc. Big Country Development Corporation

Big Country Electric Cooperative, Inc. Big Country Development Corporation Big Country Electric Cooperative, Inc. Big Country Development Corporation Dear Member, We look forward to working with you and being of service as your residential scale memberowned generation project

More information

LEVEL 1: STANDARD APPLICATION FORM AND INTERCONNECTION AGREEMENT

LEVEL 1: STANDARD APPLICATION FORM AND INTERCONNECTION AGREEMENT LEVEL 1: STANDARD APPLICATION FORM AND INTERCONNECTION AGREEMENT Interconnection Request Application Form and Conditional Agreement to Interconnect (For Lab-Certified Inverter-Based Distributed Generation

More information

Issued by authority of an Order of the Public Service Commission of Kentucky Executive in Director Case No , Dated January 8,2009.

Issued by authority of an Order of the Public Service Commission of Kentucky Executive in Director Case No , Dated January 8,2009. Nalin RECC Elizabethtown, KY 42701-6767 Original Sheet No. 78.1 CANCELING PSC ICY NO. RATES SCHEDULE NM-NET METERING AVAILABILITY OF NET METERING SERVICE Net Metering is available to eligible member-generators

More information

Indexed as: BCSSAB 21 (1) IN THE MATTER OF THE SAFETY STANDARDS ACT SBS 2003, Chapter 39

Indexed as: BCSSAB 21 (1) IN THE MATTER OF THE SAFETY STANDARDS ACT SBS 2003, Chapter 39 Date Issued: July 12, 2010 File: SSAB 21-10 Indexed as: BCSSAB 21 (1) 2010 IN THE MATTER OF THE SAFETY STANDARDS ACT SBS 2003, Chapter 39 AND IN THE MATTER OF an appeal to the British Columbia Safety Standard

More information

RENEWABLE ENERGY INCENTIVE PROGRAM Step 1, Section 1 Uniform Credit Purchase Program Application

RENEWABLE ENERGY INCENTIVE PROGRAM Step 1, Section 1 Uniform Credit Purchase Program Application RENEWABLE ENERGY INCENTIVE PROGRAM Step 1, Section 1 Uniform Credit Purchase Program Application For residential and commercial systems, the combined generation capacity at the location is limited to a

More information

AN APPLICATION FEE OF $50.00 MUST BE SUBMITTED WITH THE APPLICATION. Interconnection Applicant Contact Information. Name: Address:

AN APPLICATION FEE OF $50.00 MUST BE SUBMITTED WITH THE APPLICATION. Interconnection Applicant Contact Information. Name:  Address: Illinois Standard Distributed Generation Interconnection Level 1 Interconnection Request Application Form and Conditional Agreement to Interconnect (Lab-Certified Inverter-Based Distributed Generation

More information

CLINTON COUNTY ELECTRIC COOPERATIVE, INC. BREESE, ILLINOIS INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION

CLINTON COUNTY ELECTRIC COOPERATIVE, INC. BREESE, ILLINOIS INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION CLINTON COUNTY ELECTRIC COOPERATIVE, INC. BREESE, ILLINOIS MEMBERS: POLICY NO. 126 SUBJECT: INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION I. OBJECTIVE To establish safety, reliability

More information

delma,va power A PHI Company DELAWARE LEVEL 1 INTERCONNECTION APPLICATION/AGREEMENT

delma,va power A PHI Company DELAWARE LEVEL 1 INTERCONNECTION APPLICATION/AGREEMENT delma,va power A PHI Company ELAWARE LEVEL 1 INTERCONNECTION APPLICATION/AGREEMENT With Terms and Conditions for Interconnection (Lab Certified Inverter-Based Small Generator Facilities Less than or Equal

More information

Solid-Electrolyte TANTALEX Capacitors, Hermetically-Sealed, Axial-Lead

Solid-Electrolyte TANTALEX Capacitors, Hermetically-Sealed, Axial-Lead Solid-Electrolyte TANTALEX Capacitors, Hermetically-Sealed, Axial-Lead PERFORMANCE CHARACTERISTICS Operating Temperature: -55 C to +125 C (above 85 C, voltage derating is required) Capacitance Tolerance:

More information

Jefferson Energy Cooperative Policy 124 DISTRIBUTED GENERATION POLICY

Jefferson Energy Cooperative Policy 124 DISTRIBUTED GENERATION POLICY DISTRIBUTED GENERATION POLICY I. OBJECTIVE This document establishes the terms and conditions for the interconnection of distributed generation facilities and for providing net energy metering services

More information

RETAIL ELECTRIC SERVICE TARIFF P.S.C. Md. No. 3 OPTIONAL METER CONNECTION EQUIPMENT RIDER OMCE Sheet 125

RETAIL ELECTRIC SERVICE TARIFF P.S.C. Md. No. 3 OPTIONAL METER CONNECTION EQUIPMENT RIDER OMCE Sheet 125 APPLICABILITY RETAIL ELECTRIC SERVICE TARIFF P.S.C. Md. No. 3 OPTIONAL METER CONNECTION EQUIPMENT RIDER OMCE Sheet 125 RIDER OMCE OPTIONAL METER CONNECTION EQUIPMENT RIDER This rider is applicable to Service

More information

South Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard)

South Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard) South Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition

More information

ROCKLAND ELECTRIC COMPANY B.P.U. NO. 3 - ELECTRICITY. 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 GENERAL INFORMATION

ROCKLAND ELECTRIC COMPANY B.P.U. NO. 3 - ELECTRICITY. 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 GENERAL INFORMATION 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 No. 15 IDENTIFICATION OF EMPLOYEES Company employees or agents authorized to enter upon its customers premises are provided with photo identification

More information

EMERA MAINE TERMS AND CONDITIONS OF SERVICE TABLE OF CONTENTS

EMERA MAINE TERMS AND CONDITIONS OF SERVICE TABLE OF CONTENTS EMERA MAINE TERMS AND CONDITIONS OF SERVICE TABLE OF CONTENTS Section Title Page No. Revision Effective Date 1 Classification of Service 1.1 Original January 1, 2014 1-A Residential Service 1.1 First August

More information

INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS

INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS TABLE OF CONTENTS SECTION TITLE PAGE 1. CUSTOMER-GENERATOR RENEWABLE ELECTRICAL GENERATING

More information

Bridgeville School District

Bridgeville School District Bridgeville School District Request for Quotes revised* Informal quotes for project with estimated value under $15,000 *Revised October 30, 2017 to correct installation complete date deletions shown in

More information

Standard Interconnection Agreement for Customer-Owned Renewable Generation System kw

Standard Interconnection Agreement for Customer-Owned Renewable Generation System kw Standard Interconnection Agreement for Customer-Owned Renewable Generation System kw This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at

More information

January 30, ABB to acquire Thomas & Betts Unlocking the North American Low- Voltage Market

January 30, ABB to acquire Thomas & Betts Unlocking the North American Low- Voltage Market January 30, 2012 ABB to acquire Thomas & Betts Unlocking the North American Low- Voltage Market Safe-harbor statement This presentation contains "forward-looking statements" relating to the proposed acquisition

More information

A/V PowerSaver 8 Quick Installation Guide

A/V PowerSaver 8 Quick Installation Guide A/V PowerSaver 8 Quick Installation Guide Introducing the A/V PowerSaver 8 The A/V PowerSaver 8 surge protector provides a great energy conservation solution that utilizes the Master- Power-Save control

More information

Net Metering Interconnection Standards

Net Metering Interconnection Standards Net Metering Interconnection Standards FOR Interconnection of Electric Generators (GENERATING CAPACITY OF NOT MORE THAN 100 KILOWATTS) Table of Contents Chapter 1 Purpose and Scope Pg 3 Chapter 2 Application

More information

LM6000PD/PF 3- and 5-DVP Cabinet. Product Manual (Revision A) Original Instructions. Single or Redundant DVP Power Input Versions

LM6000PD/PF 3- and 5-DVP Cabinet. Product Manual (Revision A) Original Instructions. Single or Redundant DVP Power Input Versions Product Manual 26574 (Revision A) Original Instructions LM6000PD/PF 3- and 5-DVP Cabinet Single or Redundant DVP Power Input Versions Installation Manual General Precautions Read this entire manual and

More information

GM 6.6L Duramax *L5P* Up to 90HP Gain 1-3 MPG Fuel Savings. AgDieselSolutions.com

GM 6.6L Duramax *L5P* Up to 90HP Gain 1-3 MPG Fuel Savings. AgDieselSolutions.com 2017-2018 GM 6.6L Duramax *L5P* Up to 90HP Gain 1-3 MPG Fuel Savings AgDieselSolutions.com Fuel Sensor Connector Fuel Sensor Connector Adjustable Switch 2017-2018 L5P Duramax Engine Installations Fuel

More information

Energy Storage Systems (ESS): Preparing to Deal with the Hazards

Energy Storage Systems (ESS): Preparing to Deal with the Hazards 2017 NFPA Conference & Expo Energy Storage Systems (ESS): Preparing to Deal with the Hazards Presented by: Skip Donnell Engineering Manager Liberty Mutual Insurance Legal Disclaimer: Course Focus & Limitations

More information

2017 FOOD VENDOR AGREEMENT

2017 FOOD VENDOR AGREEMENT 2017 FOOD VENDOR AGREEMENT Agreement made this day of, 2017 by and between Fall Fest and: Name: (Hereinafter referred to as Vendor) Address: Telephone: _Cell Phone E-MAIL # of Booths requested: (Max. 2)

More information

SOLAHART PV SYSTEM AND/OR BATTERY WARRANTY - AUSTRALIA ONLY

SOLAHART PV SYSTEM AND/OR BATTERY WARRANTY - AUSTRALIA ONLY SOLAHART PV SYSTEM AND/OR BATTERY WARRANTY - AUSTRALIA ONLY IMPORTANT NOTE: This Limited Warranty covers a range of systems, products and components. This Warranty only applies in respect of the specific

More information

Standard Interconnection Agreement for Customer-Owned Renewable Generation System

Standard Interconnection Agreement for Customer-Owned Renewable Generation System Standard Interconnection Agreement for Customer-Owned Renewable Generation System This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at in,

More information

CARRY STAINLESS STEEL SUBMERSIBLE TURBINE PUMP CP06 SERIES - 3 PHASE OWNERS MANUAL

CARRY STAINLESS STEEL SUBMERSIBLE TURBINE PUMP CP06 SERIES - 3 PHASE OWNERS MANUAL CARRY STAINLESS STEEL SUBMERSIBLE TURBINE PUMP CP06 SERIES - 3 PHASE OWNERS MANUAL CP06 SERIES - 3 PHASE HIGH VOLUME STAINLESS STEEL VERTICAL TURBINE SUBMERSIBLE PUMP MODEL NUMBER EXPLANATION 2019 MODEL

More information

SALT RIVER PROJECT SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW)

SALT RIVER PROJECT SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW) Improvement and Power District Original Sheet No. P-1 SALT RIVER PROJECT SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW) Approved by SRP Board of Directors:

More information

SOLAR PV INSTALLATION AT USC BASEBALL STADIUM

SOLAR PV INSTALLATION AT USC BASEBALL STADIUM AMENDMENT NO. 7 TO SOLICITATION TO: ALL VENDORS FROM: Charles Johnson, Procurement Manager SUBJECT: SOLICITATION NUMBER: USC-RFP-1761-CJ SOLAR PV INSTALLATION AT USC BASEBALL STADIUM DATE: June 30, 2010

More information

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows: LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 10 KW AND LESS THAN OR EQUAL TO 100 KW TIER 2 This Interconnection Agreement

More information

र य गक स थ न प द र क र ल NATIONAL INSTITUTE OF TECHNOLOGY PUDUCHERRY Karaikal Tender Document

र य गक स थ न प द र क र ल NATIONAL INSTITUTE OF TECHNOLOGY PUDUCHERRY Karaikal Tender Document र य गक स थ न प द र क र ल 609 609 NATIONAL INSTITUTE OF TECHNOLOGY PUDUCHERRY Karaikal 609 609 Tender Document For Supply of 1.5 & 2 Ton Split Type Air Conditioners (ACs) at National Institute of Technology

More information

Section 24 COGENERATION AND SMALL POWER PRODUCTION

Section 24 COGENERATION AND SMALL POWER PRODUCTION Section 24 COGENERATION AND SMALL POWER PRODUCTION Cooperative is a member of Corn Belt Power Cooperative and Northwest Iowa Power Cooperative, generation and transmission cooperatives ("G&T" or "Corn

More information

Caterpillar 3126 B & E models Edge EZ Module Installation Instructions & Manual OLD P/N: ECAT1000 NEW P/N: 50200

Caterpillar 3126 B & E models Edge EZ Module Installation Instructions & Manual OLD P/N: ECAT1000 NEW P/N: 50200 Caterpillar 3126 B & E models Edge EZ Module Installation Instructions & Manual OLD P/N: ECAT1000 NEW P/N: 50200 Table of Contents DISCLAIMER OF LIABILITY 3 LIMITATION OF WARRANTY 3 Installation Instructions

More information

STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM

STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM This Agreement is made and entered into this day of, 20, by and between, (hereinafter RGS Owner ), located at in, Florida, and Utility

More information

Model Standing Offer Basic Connection Service for Retail Customers (For Micro Embedded Generation)

Model Standing Offer Basic Connection Service for Retail Customers (For Micro Embedded Generation) Model Standing Offer Basic Connection Service for Retail Customers (For Micro Embedded Generation) 01.12.17 01.12.17 1 Part 1 Letter of Offer Customer Name: Customer Address: Offer Date: Application Reference

More information

Power. On Your Terms.

Power. On Your Terms. Power. On Your Terms. 10 YEAR LIMITED WARRANTY PHI2.6 TM PHI3.4 TM 1 SIMPLIPHI POWER, INC. REV081716 10 YEAR LIMITED WARRANTY: PHI2.6 TM, PHI3.4 TM PREAMBLE: AUSTRALIAN CONSUMER LAW The Simpliphi Power

More information

NET ENERGY METERING AND INTERCONNECTION AGREEMENT

NET ENERGY METERING AND INTERCONNECTION AGREEMENT NET ENERGY METERING AND INTERCONNECTION AGREEMENT This Net Energy Metering and Interconnection Agreement (the Agreement ), dated,, (the Effective Date ), is entered into by and between the CITY OF PALO

More information

Steuben Rural Electric Cooperative, Inc. Member-Owned Distributed Generation Interconnection Information Packet

Steuben Rural Electric Cooperative, Inc. Member-Owned Distributed Generation Interconnection Information Packet Steuben Rural Electric Cooperative, Inc. Member-Owned Distributed Generation Interconnection Information Packet Member-Owned Distributed Generation Application Procedures (For single-phase attachment of

More information

INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS

INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS This Interconnection Agreement for Customer-Owned Renewable Generation Systems ( Interconnection Agreement ) is made this day of

More information