EVOLUTIONARY OPTIMIZATION OF RESOURCE ALLOCATION IN REPETITIVE CONSTRUCTION SCHEDULES

Size: px
Start display at page:

Download "EVOLUTIONARY OPTIMIZATION OF RESOURCE ALLOCATION IN REPETITIVE CONSTRUCTION SCHEDULES"

Transcription

1 EVOLUTIONARY OPTIMIZATION OF RESOURCE ALLOCATION IN REPETITIVE CONSTRUCTION SCHEDULES SUBMITTED: October 2003 REVISED: September 2004 ACCEPTED: September 2005 at EDITOR: C. Anumba Khaled Nassar, Assoc Professor Unversty of Maryland Eastern Shore, Prncess Ann, USA emal: SUMMARY: Repettve constructon projects are common n a number of dfferent stuatons such as hghway constructon and housng projects. Several approaches and models have been presented for modelng repettve constructon projects as well as for optmzng resource allocaton for these types of projects. Ths paper presents a model that uses genetc algorthms to optmally assgn resources to repettve actvtes n order to mnmze the overall project duraton as well as the number of nterrupton days. The model presented n ths paper s a straghtforward formulaton that can be easly modfed and expanded for any problem through ts spreadsheet mplementaton, whch reduces the modelng tme for typcal problems extensvely. The model outperforms other models n terms of fndng a soluton wth less nterrupton days. In addton, users of the proposed model can nteractvely examne tradeoffs between the number of nterrupton days and the overall project duraton. KEYWORDS: optmzaton, repettve constructon schedules, resource allocaton problem 1. INTRODUCTION Repettve actvtes are common n a number of constructon projects. Repettve constructon s commonly found for example, n hgh-rse buldngs, housng projects, hghways, ppelne networks, brdges, etc. Several approaches and models have been presented for modelng repettve constructon projects, startng wth the tradtonal network technques such as Crtcal Path Method (CPM). A number of researchers however, recognzed early on the problems of usng conventonal network technques for schedule such projects. The man draw back of conventonal network technques s ther nablty to mantan crew work contnuty (Brrell 1980; Selnger 1980; Kavanagh 1985; Reda 1990; Russell and Wong 1993). In order to rectfy ths problem, a number of schedulng technques have been proposed for repettve constructon projects (Selnger 1980; Johnston 1981; Ardt and Albulak 1986; Charzanowsk and Johnston 1986; Russell and Caselton 1988; Al Sarraj 1990; El-Rayes and Moselh 1998). Dynamc programmng, for example, has also been extensvely used to optmze the schedulng of repettve projects, (Moselh and El- Rayes 1993; Eldn and Senouc 1994, Selnger 1980; Russell and Caselton 1988). These formulatons consder the overall project duraton (Selnger 1980; Moselh and El-Rayes 1993) or both the overall project duraton and the number of nterrupton days (Russell and Caselton 1988; Eldn and Senouc 1994; and El-Rayes and Moselh 2001). Mantanng crew work contnuty leads to maxmzng the learnng curve effect and mnmzng the dle tme of each crew (Ashley 1980; Brrell 1980). On the other hand, mantanng crew work contnuty mght result n longer project duraton. Selnger (1980) for nstance, suggested that ncreasng crew work nterruptons up to a specfc amount for some of the actvtes mght reduce the overall project duraton. Therefore, the tradeoff between the overall project duraton and the number of nterrupton days s a crucal factor n assgnng resources n repettve projects. In ths paper, an alternatve model that uses Genetc Algorthm (GA) to optmally assgn resources for repettve constructon projects. The model provdes an optmum duraton for repettve constructon projects whle applyng the mnmum crew work nterrupton days to the repettve constructon actvtes. The model proposed here s straghtforward n that t can be mplemented easly on any spreadsheet software and modfed and expanded for any problem. Furthermore, usng the proposed genetc algorthms optmzaton, the model acheves solutons that can be better than those acheved usng other models. ITcon Vol. 10 (2005), Nassar, pg. 265

2 2. RESOURCE ASSIGNMENT IN REPETITIVE CONSTRUCTION SCHEDULES In order to explan the problem of resource assgnment n repettve constructon schedules, consder the concrete brdge example whch was frst presented n (Selnger 1980). Russell and Caselton (1988), and Moselh and EL-Rayes (1993 & 2001) also analyzed ths same example. In the secton 4 of ths paper, the results from the model presented n ths paper are compared to the solutons from these studes. The project conssts of four smlar sectons or unts, and each ncludes the followng repettve actvtes n sequence: Excavatons, Foundatons, Columns, Beams, and Slabs. Each repettve actvty s performed by a crew that progresses from the frst to the fourth secton sequentally. The job logc (.e., relatonshps) among succeedng actvtes, for the project selected here, s fnsh to start wth no lag tme. The same technque however can also work wth other knds of relatonshps (start-to-fnsh, start-to-start, etc ). TABLE 1: Sample Problem (from Selnger 1980) Actvty Unt j Excavaton Foundaton Columns Beams Slabs Opton opton opton opton opton opton opton opton opton opton opton opton opton # 1 # 1 # 2 # 3 # 1 # 2 # 3 # 1 # 2 # 3 # 4 # 1 # Dfferent crew formatons optons are avalable for each actvty as lsted n Table 1 (excavaton for example has only 1 crew opton, whle the beams actvty has 4 crew optons). Each crew formaton has ts own producton rate. In addton to determnng the optmum crew assgnment that mnmzes the overall project duraton, one also needs to determne the best nterrupton vector assocated wth ths assgnment. Prevous researchers have defned the nterrupton vector s the number of days that the assgned crews wll be nterrupted between the dfferent work unts (Caselton 1988, Moselh and EL-Rayes 1993, 2001). Allowng crew work nterruptons for some of the actvtes mght reduce the overall project duraton. The resource assgnment problem n repettve constructon schedules therefore s to determne the optmum crew formaton and nterrupton vector that wll reduce the overall project duraton. In prevous formulatons, some of them utlze an arbtrary set of nterrupton vectors prepared pror to schedulng (Russell and Caselton 1988; Eldn and Senouc 1994). El-rayes and Moselh 2001 appled an nterrupton to ther model that automatcally generates a set of calculated nterrupton vectors durng schedulng to make the nterrupton more feasble and bounded. In the model presented n ths paper however, ths s not requred, as wll be presented n the next secton. 3. THE DEVELOPED MODEL 3.1 Model descrpton The developed model s a two-state varable model because t consders mnmzng the total overall duraton of the project as well as mnmzng the number of nterrupton days (n the nterrupton vector). The model s presented n a way that s smlar to tradtonal CPM calculatons and therefore can be easly developed for any project. In addton, the model s developed n a table format whch facltates ts mplementaton n any spreadsheet software as well as utlzng the already developed optmzaton routnes found n such software, such as the genetc algorthm solver n excel, whch s utlzed n ths case. Table 2 presents the calculatons for the sample problem descrbed above. The calculatons are dvded nto three man parts: Frstly, part one calculates the earlest start date for each of the actvtes. Secondly part 2 calculates the latest start date. Fnally, the thrd part s used to determne when to actually schedule the start of each actvty to mnmze the overall duraton and also mnmze the nterruptons. The Interrupton Vector ITcon Vol. 10 (2005), Nassar, pg. 266

3 column (column 13) shows the number of days that each actvty s delayed, and the fnsh day of the last actvty s the overall total duraton of the project (106.8 days). TABLE 2.: Table used n the Proposed Model The nputs to the problem presented here are shown n TABLE 1, whch shows the dfferent crew duratons for the dfferent actvtes. The crew duraton s the amount of tme that each crew n would take to fnsh each unt j of actvty. 3.2 Model Explanaton Part One of the Model Now, consder part 1 of the model n TABLE 2. Column 1 contans the earlest possble start date accordng to crew avalablty, SCA. For the frst actvty n the frst unt (no succeedng actvty) ths s equal to zero. For the next unt, SCA s equal to the early fnsh date of the precedng unt of the same actvty. It s determned usng the followng formula: SCA = Early Fnsh Date n ( j 1) (column7) (1) The early fnsh date for a unt j of an actvty s based on the crew n selected. The crew used for each actvty s shown n column (column 5). For example, the earlest possble tme that the thrd unt of the foundaton actvty can start (40.1) s determned from the earlest fnsh date of the second unt. Note that snce crew number 1 s used (as shown n the no column, number 5) for the foundaton actvty, the duraton, D, for any of the unts of the actvty consdered s actually the crew duraton (shown n Table 1). If a dfferent crew were selected then the duraton (column 4) for the unts would reflect the new crew selected n column 5. ITcon Vol. 10 (2005), Nassar, pg. 267

4 Column number 2, on the other hand, contans the earlest possble start date accordng to job logc, SJL. Ths represents the earlest date the actvty could start f there were no constrants due to the crew duraton. Ths s calculated based on the scheduled fnsh date or the same unt of the precedng actvty, and s gven by: 1 1 SJL = Scheduled Fnsh date (Column12) (2) Snce an actvty can not start untl ts predecessor has fnshed or untl the crew workng on the actvty s avalable, the earlest start date (column 6) for each actvty would have to be the latest of the (SJL or SCA). Ths s calculated accordng to the followng formula: Early Start Date = MAX( SJL, SCA ) For any gven actvty, f the earlest start date accordng to job logc, SJL, were later than the earlest start due to crew avalablty, SCA, then ths would mean that the actvty could start mmedately snce the crew would also be avalable to work mmedately. In ths case, there s no dle tme for the actvty. On the other hand, f the start earlest start date accordng to job logc, SJL, were earler than the earlest start due to crew avalablty, SCA, then the actvty would have to st dle untl the crew has fnshed workng on the precedng unt. The tme the actvty sts dle n that case s the dfference between the SJL and the SCA. Idle tme s shown n column 3 and s calculated accordng to for the followng formula: Idle 0,f ( SJL SCA ) 0 = SJL SCA,f( SJL SCA ) > 0 Fnally, the early fnsh date (column 7) for any unt n an actvty s smply the sum of the early start date and the duraton. Ths s gven by the followng formula: Early Fnsh Date (column7) = Early Start Date (column6) + D (column 4) Ths concludes the frst part of the model, whch determnes the early starts and early fnsh dates, as well as the amount of dle tme for any unts of an actvty due to lack of resources (because the crews would be stll workng on the prevous unt of the actvty) Part Two of the Model In the second part of the model the late start and late fnsh dates are calculated. The dea here s that snce some of the unts n an actvty would have to st dle anyways (due to the crew avalablty), one could shft the start of precedng unts accordngly. The amount that each unt could be delayed wthout delayng the overall project fnsh date s called the shft. The shft (column 8) s equal to the sum of all the dle tmes of the precedng unts n an actvty and s gven by the followng formula: shft = Idle j j+ 1 Snce the shft determnes the amount that each unt could be delayed wthout delayng the overall project fnsh date, the late start date (column 9) would smply equal the early start plus the shft, and the late fnsh s equal to the late start plus the duraton: Late Start Date (column 9) = Early Start Date (column 6) + shft (column 8) (3) (4) (5) (6) (7) Late Fnsh Date Part Three of the Model (column 10) = Late Start Date (column 9) + D (column Now that the late and early start dates for each unt have been calculated, the thrd part of the model s used to determne the overall fnsh date of the project gven specfc nterruptons (or shfts) for each unt of the actvtes. The work on specfc unts can be nterrupted for a number of days wthout ncreasng the overall project duraton. The number of days that each actvty can be nterrupted s shown n the Interrupton column 4) (8) ITcon Vol. 10 (2005), Nassar, pg. 268

5 (column 13). In fact by varyng the number of nterrupton days (.e. the nterrupton vector) and the crews, a reducton n the overall project duraton can be acheved. The scheduled start date of any unt n the project would equal the late start date mnus those nterrupton days. Although the scheduled start date can also be determned as the earlest start plus the nterrupton days, the way the spreadsheet s setup makes t more readable to use the late start mnus the nterrupton days. The scheduled start and fnsh dates are therefore defned as: Scheduled Start Date Scheduled Fnsh Date (column 11) = Late Start Date (column 12) = Scheduled Start Date (column 9) j j+ 1 Inter (column 11) + D (column 13) (9) (column 4) (10) TABLE 3: Comparson between the results of the proposed model and other smlar models for the same problem Actvty Unt J Excavaton Foundaton Columns Beams Slabs Inter S Inter S Inter S Inter S Inter S One-state varable formulaton (Selnger 1980) Fnsh Optmum Formaton Two-state varable formulaton (Russel and Cselton 1988) Fnsh Optmum Formaton Two-state varable formulaton (El-Rayes and Moselh 2001) Fnsh Optmum Formaton Proposed Two-state varable formulaton Fnsh Optmum Formaton ITcon Vol. 10 (2005), Nassar, pg. 269

6 The values used n the Interrupton Vector column (column 13), as well as those n the column (column 5), whch specfy whch of the dfferent crews wll be used for each actvty, wll determne the overall project duraton. These values were determned through an optmzaton routne as descrbed n the next secton. The spreadsheet cells n the Interrupton Vector column (column 13) were used as the varables n the optmzaton problem, whch was used to mnmze the overall project duraton Computerzed Solutons usng Evolutonary Add-n One of the advantages of the formulaton descrbed above s that t can be easly developed for any sze problem on any commercal spreadsheet applcaton. Spreadsheets provde a transparent way of modelng the problem, gvng the user a complete understandng and control of the dfferent varables and constrants n the problem. For the majorty of constructon problems, whose sze usually ranges from small to medum, spreadsheet solutons would be the most effcent and economcal method to solve the problem. Most contractors already use spreadsheets extensvely. Furthermore, the model can be easly modfed and expanded for any problem by smple formula draggng whch reduces the modelng tme for typcal problems extensvely. The developed spreadsheet uses standard spreadsheet formulae to model the problem. For example, an HLOOKUP functon s used to look up duraton of each unt based on the crew used. Spreadsheet, such as Excel, provdes a solver add-n, whch can be used for optmzng problems lke the one presented here. However, tradtonal solvers can not be used to optmze ths problem, because the spreadsheet nvolves dscontnuous and non-smooth functons such as the MAX() and LOOKUP() functons. Fortunately, a number of commercal genetc solver add-ns are avalable for excel that can maxmze the speed and robustness for solvng optmzaton problems such as the one presented above, e.g. Evolver and the Premum Solver whch s used here. The Premum Solver Platform works wth exstng Excel Solver models to solve much larger problems up to hundreds of tmes faster. Ths evolutonary solver uses the powerful optmzaton capabltes of generc algorthm (GA) technques. GA technques are nspred by bologcal systems that mprove ftness through evoluton. Ths s done through mmckng Darwnan prncples of natural selecton by creatng an envronment where hundreds of possble solutons to a problem can compete wth one another and only the "fttest" survve. Just as n bologcal evoluton, each soluton can pass along ts good "genes" through "offsprng" solutons so that the entre populaton of solutons wll contnue to evolve better solutons. In terms of our applcaton, good genes would represent the schedule wth the least duraton and wth the least nterrupton days. The objectve of the model presented here s to determne the optmum crew work formaton and nterrupton vector that wll mnmze the overall project duraton, whle also keepng the number of nterrupton days to a mnmum. Therefore the objectve functon s set as the overall project duraton plus the sum of the nterrupton days. The crew work formaton type and work nterrupton for each unt were set as the changng varables. It s a requrement when usng evolutonary solver that ndependent varable must have an upper and lower lmt. Therefore upper lmt and lower lmt constrants were specfed for all varables. For example, the upper lmt on the crew varable was set as 3 for the foundatons, 3 for the columns, 4 for the beams and 2 for the slabs. Another constrant to satsfy s that the actvty n each repettve unt cannot start at an earler date than that establshed n part 1 of the model because of the job logc and crew avalablty constrants. After runnng the optmzaton, the optmum overall project duraton was determned as wth assocated total nterrupton of 14 days. 4. COMPARISON TO EXISTING MODELS The same problem was analyzed by usng dynamc programmng formulatons. The ntal problem formulaton by Slnger (1980) Russell and Caselton (1988) dd not consder nterrupton as a second state varable and resulted n a mnmum duraton of days. Russel and Caselton (1988), whch expanded the formulaton allowng 16 nterrupton days, provded an mprovement by mnmzng the overall duraton days to days. The last formulaton (El-Rayes and Moselh (2001) provded an addtonal mprovement by reducng the overall project duraton to days, and nterruptng the crew work contnuty by a total of 15 days, as shown n Table 4.2. ITcon Vol. 10 (2005), Nassar, pg. 270

7 Optmum Project Duraton Total Project Durato, days Selnger (1980) Russell & El-Rayes & Caselton (1988) Moselh (2001) Proposed EV Model FIG. 1: Comparson of optmum project duraton Total Interrupton Total Project Iterruptons, days Russell & Caselton (1988) 15 El-Rayes & Moselh (2001) 14 Proposed EV Model FIG. 2: Comparson of total nterruptons (days) TABLE 4: Optmum Project Duraton & Interrupton Formulaton Model Total Duraton Interrupton (days) (days) Selnger (1980) Russell & Caselton (1988) El-Rayes & Moselh (2001) Proposed GA Model The results obtaned usng dynamc formulatons (Selnger 1980; Russell and Caselton 1988; El-Rayes and Moselh 2001) are compared to those provded by the spreadsheet model as shown n Table 3, Fg 1, Fg 2 and Table 4, confrm that the GA model provdes a more effcent soluton than those obtaned by others, the mnmum overall duraton s the same as that of (El-Ryes and Moselh 2001), but wth less nterruptng days for crew work contnuty. In addton, one of the advantages of the model descrbed here s the ablty to nteractvely modfy the varable n the model, such as the nterrupton vector, and observe the effects on the overall duraton. For example, by ncreasng the nterrupton days for the fourth unt n the foundaton actvty from 5 to 7, the overall duraton of the project can stll be further reduced to 105.5, whle ncreasng the nterrupton days by those two days. Ths allows users to examne tradeoffs between the number of nterrupton days and the overall project duraton. 5. DISCUSSIONS AND CONCLUSIONS In ths paper a model for resource allocaton n repettve constructon schedules was descrbed. Usng the proposed spreadsheet GA mplementaton, users can mnmze the overall project duraton whle keepng the nterruptons as low as possble. Whle most optmzers keep only the best soluton found durng ts search, the ITcon Vol. 10 (2005), Nassar, pg. 271

8 evolutonary optmzer keeps a large set of results, called a populaton of canddate soluton. The populaton s used to help create new startng soluton ponts not necessarly n the neghborhood of the current best soluton, and thus helpng to avod Evolutonary Solver gettng trapped at a local optmum. Therefore, the model users can experment wth the dfferent varables n the model to perform a senstvty analyss on the model. Whle the model presented here can easly be mplemented for any smlar problem as has been found to outperform smlar models n terms of mnmzng nterrupton days, a number of ponts need to be ponted out. The model s non-determnstc as t reles n part on randomly determned startng pont, ths may yeld dfferent solutons for dfferent runs. The model also has the same restrctons as smlar models n the lterature: Labor requrement and feasble crew sze are determned n advance. Each crew formaton has a unque daly output and assocated duraton for completng the actvty as well as the assumpton that work nterruptons may reduce total constructon tme, and so general expenses. 6. REFERENCES Al Sarraj, Z. M. (1990). Formal development of-lne Balance Technque. J. Constr. Engrg. and Mgmt., ASCE, 116(4), Ardt, D., and Albulak, M. Z. (1986). Lne of-balance Schedulng n Pavement Constructon. J. Constr. Engrg. and Mgmt., ASCE, 112(3), Ashley, D. B. (1980). Smulaton of Repettve-Unt Constructon. J. Constr. Engrg. and Mgmt., ASCE, 106(2), Beans, J. C. (1994). Genetc Algorthms and Random Keys for Sequencng and Optmzaton. ORSA J. on Comp., 6(2), Brrell, G. S. (1980). Constructon Plannng - Beyond the Crtcal Path. J. Constr. Engrg. and Mgmt., ASCE, 106(3), Chrzanowsk, E. N. Jr., and Johnston, D. W (1986). Applcaton of Lnear Schedulng. J. Constr. Engrg. and Mgmt., ASCE, 112(4), Eldn, N. N., and Senouc, A. B. (1994). Schedulng and Control of Lnear Projects. Can. J. Cv. Engrg., Ottawa, 21, El-Rayes, K., and Moselh, O. (1998). Resource-Drven Schedulng of Repettve Actvtes on Constructon Projects. J. Constr. Engrg. and Mgmt., ASCE, 107(2), El-Rayes, K., and Moselh, O. (2001). Optmzng Resource Utlzaton for Repettve Projects. J. Constr. Engrg. and Mgmt., ASCE, 16(4), Frontlne System Inc., developers of Spreadsheet Solver/Optmzer n Mcrosoft Excel, Constructon Goldberg, D. E. (1989). Genetc Algorthm n Search, Optmzaton, and Machne Learnng, Addson- Wesley, Readng, Mass. Johnston, D. W. (1981). Lnear Schedulng Method for Hghway Constructon. J. Constr.Dv., ASCE, 107(2), Kavanagh, D. P. (1985). SIREN: A Repettve Constructon Smulaton Model. J. Constr.Dv., ASCE, 111(3), O Bren, J. J., Kretzberg, F. C., and Mkes, W. F. (1985). Network Schedulng Varatons for Repettve work. J. Constr. Engrg. and Mgmt., ASCE, 111(2), Reda, R. M. (1990). RPM: Repettve Project Modelng. J. Constr. Engrg. and Mgmt., ASCE, 116(2), Russell, A. D., and Caselton, W. F. (1988). Extensons to Lnear Schedulng Optmzaton. J. Constr. Dv., ASCE, 114(1), ITcon Vol. 10 (2005), Nassar, pg. 272

9 Russell, A. D., and Wong, W. C. M. (1993). New Generaton of Plannng Structures. J. Constr. Dv., ASCE, 119(2), Senouc, A., and Eldn, N. (1996). A Tme-Cost Trade-Off Algorthm for Nonseral Lnear Projecrs. Can. J. Cv. Engrg., Ottawa, 23, ITcon Vol. 10 (2005), Nassar, pg. 273

AC : THE DIAGRAMMATIC AND MATHEMATICAL APPROACH OF PROJECT TIME-COST TRADEOFFS

AC : THE DIAGRAMMATIC AND MATHEMATICAL APPROACH OF PROJECT TIME-COST TRADEOFFS AC 2008-1635: THE DIAGRAMMATIC AND MATHEMATICAL APPROACH OF PROJECT TIME-COST TRADEOFFS Kun-jung Hsu, Leader Unversty Amercan Socety for Engneerng Educaton, 2008 Page 13.1217.1 Ttle of the Paper: The Dagrammatc

More information

Optimization model for resource assignment problems of linear construction projects

Optimization model for resource assignment problems of linear construction projects Automaton n Constructon 16 (2007) 460 473 www.elsever.com/locate/autcon Optmzaton model for resource assgnment problems of lnear constructon projects Shu-Shun Lu a,, Chang-Jung Wang b,1 a Department of

More information

Quiz on Deterministic part of course October 22, 2002

Quiz on Deterministic part of course October 22, 2002 Engneerng ystems Analyss for Desgn Quz on Determnstc part of course October 22, 2002 Ths s a closed book exercse. You may use calculators Grade Tables There are 90 ponts possble for the regular test, or

More information

A New Uniform-based Resource Constrained Total Project Float Measure (U-RCTPF) Roni Levi. Research & Engineering, Haifa, Israel

A New Uniform-based Resource Constrained Total Project Float Measure (U-RCTPF) Roni Levi. Research & Engineering, Haifa, Israel Management Studes, August 2014, Vol. 2, No. 8, 533-540 do: 10.17265/2328-2185/2014.08.005 D DAVID PUBLISHING A New Unform-based Resource Constraned Total Project Float Measure (U-RCTPF) Ron Lev Research

More information

Tests for Two Correlations

Tests for Two Correlations PASS Sample Sze Software Chapter 805 Tests for Two Correlatons Introducton The correlaton coeffcent (or correlaton), ρ, s a popular parameter for descrbng the strength of the assocaton between two varables.

More information

CS 286r: Matching and Market Design Lecture 2 Combinatorial Markets, Walrasian Equilibrium, Tâtonnement

CS 286r: Matching and Market Design Lecture 2 Combinatorial Markets, Walrasian Equilibrium, Tâtonnement CS 286r: Matchng and Market Desgn Lecture 2 Combnatoral Markets, Walrasan Equlbrum, Tâtonnement Matchng and Money Recall: Last tme we descrbed the Hungaran Method for computng a maxmumweght bpartte matchng.

More information

A DUAL EXTERIOR POINT SIMPLEX TYPE ALGORITHM FOR THE MINIMUM COST NETWORK FLOW PROBLEM

A DUAL EXTERIOR POINT SIMPLEX TYPE ALGORITHM FOR THE MINIMUM COST NETWORK FLOW PROBLEM Yugoslav Journal of Operatons Research Vol 19 (2009), Number 1, 157-170 DOI:10.2298/YUJOR0901157G A DUAL EXTERIOR POINT SIMPLEX TYPE ALGORITHM FOR THE MINIMUM COST NETWORK FLOW PROBLEM George GERANIS Konstantnos

More information

Cyclic Scheduling in a Job shop with Multiple Assembly Firms

Cyclic Scheduling in a Job shop with Multiple Assembly Firms Proceedngs of the 0 Internatonal Conference on Industral Engneerng and Operatons Management Kuala Lumpur, Malaysa, January 4, 0 Cyclc Schedulng n a Job shop wth Multple Assembly Frms Tetsuya Kana and Koch

More information

Tree-based and GA tools for optimal sampling design

Tree-based and GA tools for optimal sampling design Tree-based and GA tools for optmal samplng desgn The R User Conference 2008 August 2-4, Technsche Unverstät Dortmund, Germany Marco Balln, Gulo Barcarol Isttuto Nazonale d Statstca (ISTAT) Defnton of the

More information

15-451/651: Design & Analysis of Algorithms January 22, 2019 Lecture #3: Amortized Analysis last changed: January 18, 2019

15-451/651: Design & Analysis of Algorithms January 22, 2019 Lecture #3: Amortized Analysis last changed: January 18, 2019 5-45/65: Desgn & Analyss of Algorthms January, 09 Lecture #3: Amortzed Analyss last changed: January 8, 09 Introducton In ths lecture we dscuss a useful form of analyss, called amortzed analyss, for problems

More information

Finance 402: Problem Set 1 Solutions

Finance 402: Problem Set 1 Solutions Fnance 402: Problem Set 1 Solutons Note: Where approprate, the fnal answer for each problem s gven n bold talcs for those not nterested n the dscusson of the soluton. 1. The annual coupon rate s 6%. A

More information

OPERATIONS RESEARCH. Game Theory

OPERATIONS RESEARCH. Game Theory OPERATIONS RESEARCH Chapter 2 Game Theory Prof. Bbhas C. Gr Department of Mathematcs Jadavpur Unversty Kolkata, Inda Emal: bcgr.umath@gmal.com 1.0 Introducton Game theory was developed for decson makng

More information

Price and Quantity Competition Revisited. Abstract

Price and Quantity Competition Revisited. Abstract rce and uantty Competton Revsted X. Henry Wang Unversty of Mssour - Columba Abstract By enlargng the parameter space orgnally consdered by Sngh and Vves (984 to allow for a wder range of cost asymmetry,

More information

Solution of periodic review inventory model with general constrains

Solution of periodic review inventory model with general constrains Soluton of perodc revew nventory model wth general constrans Soluton of perodc revew nventory model wth general constrans Prof Dr J Benkő SZIU Gödöllő Summary Reasons for presence of nventory (stock of

More information

Elton, Gruber, Brown, and Goetzmann. Modern Portfolio Theory and Investment Analysis, 7th Edition. Solutions to Text Problems: Chapter 9

Elton, Gruber, Brown, and Goetzmann. Modern Portfolio Theory and Investment Analysis, 7th Edition. Solutions to Text Problems: Chapter 9 Elton, Gruber, Brown, and Goetzmann Modern Portfolo Theory and Investment Analyss, 7th Edton Solutons to Text Problems: Chapter 9 Chapter 9: Problem In the table below, gven that the rskless rate equals

More information

Creating a zero coupon curve by bootstrapping with cubic splines.

Creating a zero coupon curve by bootstrapping with cubic splines. MMA 708 Analytcal Fnance II Creatng a zero coupon curve by bootstrappng wth cubc splnes. erg Gryshkevych Professor: Jan R. M. Röman 0.2.200 Dvson of Appled Mathematcs chool of Educaton, Culture and Communcaton

More information

Economic Design of Short-Run CSP-1 Plan Under Linear Inspection Cost

Economic Design of Short-Run CSP-1 Plan Under Linear Inspection Cost Tamkang Journal of Scence and Engneerng, Vol. 9, No 1, pp. 19 23 (2006) 19 Economc Desgn of Short-Run CSP-1 Plan Under Lnear Inspecton Cost Chung-Ho Chen 1 * and Chao-Yu Chou 2 1 Department of Industral

More information

Tests for Two Ordered Categorical Variables

Tests for Two Ordered Categorical Variables Chapter 253 Tests for Two Ordered Categorcal Varables Introducton Ths module computes power and sample sze for tests of ordered categorcal data such as Lkert scale data. Assumng proportonal odds, such

More information

An Application of Alternative Weighting Matrix Collapsing Approaches for Improving Sample Estimates

An Application of Alternative Weighting Matrix Collapsing Approaches for Improving Sample Estimates Secton on Survey Research Methods An Applcaton of Alternatve Weghtng Matrx Collapsng Approaches for Improvng Sample Estmates Lnda Tompkns 1, Jay J. Km 2 1 Centers for Dsease Control and Preventon, atonal

More information

RESOURCE ALLOCATION IN REPETITIVE CONSTRUCTION SCHEDULES USING ANT COLONY OPTIMIZATION

RESOURCE ALLOCATION IN REPETITIVE CONSTRUCTION SCHEDULES USING ANT COLONY OPTIMIZATION RESOURCE ALLOCATION IN REPETITIVE CONSTRUCTION SCHEDULES USING ANT COLONY OPTIMIZATION Mohamed A. El-Gafy, Ph.D., M.A.I. 1, Amne Ghanem 2 mgafy@lstu.edu 1, ghaneam@eng.fsu.edu 2 Constructon management

More information

/ Computational Genomics. Normalization

/ Computational Genomics. Normalization 0-80 /02-70 Computatonal Genomcs Normalzaton Gene Expresson Analyss Model Computatonal nformaton fuson Bologcal regulatory networks Pattern Recognton Data Analyss clusterng, classfcaton normalzaton, mss.

More information

A MODEL OF COMPETITION AMONG TELECOMMUNICATION SERVICE PROVIDERS BASED ON REPEATED GAME

A MODEL OF COMPETITION AMONG TELECOMMUNICATION SERVICE PROVIDERS BASED ON REPEATED GAME A MODEL OF COMPETITION AMONG TELECOMMUNICATION SERVICE PROVIDERS BASED ON REPEATED GAME Vesna Radonć Đogatovć, Valentna Radočć Unversty of Belgrade Faculty of Transport and Traffc Engneerng Belgrade, Serba

More information

COS 511: Theoretical Machine Learning. Lecturer: Rob Schapire Lecture #21 Scribe: Lawrence Diao April 23, 2013

COS 511: Theoretical Machine Learning. Lecturer: Rob Schapire Lecture #21 Scribe: Lawrence Diao April 23, 2013 COS 511: Theoretcal Machne Learnng Lecturer: Rob Schapre Lecture #21 Scrbe: Lawrence Dao Aprl 23, 2013 1 On-Lne Log Loss To recap the end of the last lecture, we have the followng on-lne problem wth N

More information

USING A MULTICRITERIA INTERACTIVE APPROACH IN SCHEDULING NON-CRITICAL ACTIVITIES

USING A MULTICRITERIA INTERACTIVE APPROACH IN SCHEDULING NON-CRITICAL ACTIVITIES OPERATIONS RESEARCH AND DECISIONS No. 1 2018 DOI: 10.5277/ord180103 Mace NOWAK 1 Krzysztof S. TARGIEL 1 USING A MULTICRITERIA INTERACTIVE APPROACH IN SCHEDULING NON-CRITICAL ACTIVITIES A typcal proect

More information

Elements of Economic Analysis II Lecture VI: Industry Supply

Elements of Economic Analysis II Lecture VI: Industry Supply Elements of Economc Analyss II Lecture VI: Industry Supply Ka Hao Yang 10/12/2017 In the prevous lecture, we analyzed the frm s supply decson usng a set of smple graphcal analyses. In fact, the dscusson

More information

Applications of Myerson s Lemma

Applications of Myerson s Lemma Applcatons of Myerson s Lemma Professor Greenwald 28-2-7 We apply Myerson s lemma to solve the sngle-good aucton, and the generalzaton n whch there are k dentcal copes of the good. Our objectve s welfare

More information

ISyE 2030 Summer Semester 2004 June 30, 2004

ISyE 2030 Summer Semester 2004 June 30, 2004 ISyE 030 Summer Semester 004 June 30, 004 1. Every day I must feed my 130 pound dog some combnaton of dry dog food and canned dog food. The cost for the dry dog food s $0.50 per cup, and the cost of a

More information

Multiobjective De Novo Linear Programming *

Multiobjective De Novo Linear Programming * Acta Unv. Palack. Olomuc., Fac. rer. nat., Mathematca 50, 2 (2011) 29 36 Multobjectve De Novo Lnear Programmng * Petr FIALA Unversty of Economcs, W. Churchll Sq. 4, Prague 3, Czech Republc e-mal: pfala@vse.cz

More information

Scribe: Chris Berlind Date: Feb 1, 2010

Scribe: Chris Berlind Date: Feb 1, 2010 CS/CNS/EE 253: Advanced Topcs n Machne Learnng Topc: Dealng wth Partal Feedback #2 Lecturer: Danel Golovn Scrbe: Chrs Berlnd Date: Feb 1, 2010 8.1 Revew In the prevous lecture we began lookng at algorthms

More information

Lecture Note 2 Time Value of Money

Lecture Note 2 Time Value of Money Seg250 Management Prncples for Engneerng Managers Lecture ote 2 Tme Value of Money Department of Systems Engneerng and Engneerng Management The Chnese Unversty of Hong Kong Interest: The Cost of Money

More information

- contrast so-called first-best outcome of Lindahl equilibrium with case of private provision through voluntary contributions of households

- contrast so-called first-best outcome of Lindahl equilibrium with case of private provision through voluntary contributions of households Prvate Provson - contrast so-called frst-best outcome of Lndahl equlbrum wth case of prvate provson through voluntary contrbutons of households - need to make an assumpton about how each household expects

More information

The Integration of the Israel Labour Force Survey with the National Insurance File

The Integration of the Israel Labour Force Survey with the National Insurance File The Integraton of the Israel Labour Force Survey wth the Natonal Insurance Fle Natale SHLOMO Central Bureau of Statstcs Kanfey Nesharm St. 66, corner of Bach Street, Jerusalem Natales@cbs.gov.l Abstact:

More information

Least Cost Strategies for Complying with New NOx Emissions Limits

Least Cost Strategies for Complying with New NOx Emissions Limits Least Cost Strateges for Complyng wth New NOx Emssons Lmts Internatonal Assocaton for Energy Economcs New England Chapter Presented by Assef A. Zoban Tabors Caramans & Assocates Cambrdge, MA 02138 January

More information

A Case Study for Optimal Dynamic Simulation Allocation in Ordinal Optimization 1

A Case Study for Optimal Dynamic Simulation Allocation in Ordinal Optimization 1 A Case Study for Optmal Dynamc Smulaton Allocaton n Ordnal Optmzaton Chun-Hung Chen, Dongha He, and Mchael Fu 4 Abstract Ordnal Optmzaton has emerged as an effcent technque for smulaton and optmzaton.

More information

An Efficient Heuristic Algorithm for m- Machine No-Wait Flow Shops

An Efficient Heuristic Algorithm for m- Machine No-Wait Flow Shops An Effcent Algorthm for m- Machne No-Wat Flow Shops Dpak Laha and Sagar U. Sapkal Abstract We propose a constructve heurstc for the well known NP-hard of no-wat flow shop schedulng. It s based on the assumpton

More information

Time Planning and Control. Precedence Diagram

Time Planning and Control. Precedence Diagram Tme Plannng and ontrol Precedence agram Precedence agrammng S ctvty I LS T L n mportant extenson to the orgnal actvty-on-node concept appeared around 14. The sole relatonshp used n PRT/PM network s fnsh

More information

A HEURISTIC SOLUTION OF MULTI-ITEM SINGLE LEVEL CAPACITATED DYNAMIC LOT-SIZING PROBLEM

A HEURISTIC SOLUTION OF MULTI-ITEM SINGLE LEVEL CAPACITATED DYNAMIC LOT-SIZING PROBLEM A eurstc Soluton of Mult-Item Sngle Level Capactated Dynamc Lot-Szng Problem A EUISTIC SOLUTIO OF MULTI-ITEM SIGLE LEVEL CAPACITATED DYAMIC LOT-SIZIG POBLEM Sultana Parveen Department of Industral and

More information

Stochastic job-shop scheduling: A hybrid approach combining pseudo particle swarm optimization and the Monte Carlo method

Stochastic job-shop scheduling: A hybrid approach combining pseudo particle swarm optimization and the Monte Carlo method 123456789 Bulletn of the JSME Journal of Advanced Mechancal Desgn, Systems, and Manufacturng Vol.10, No.3, 2016 Stochastc job-shop schedulng: A hybrd approach combnng pseudo partcle swarm optmzaton and

More information

Parallel Prefix addition

Parallel Prefix addition Marcelo Kryger Sudent ID 015629850 Parallel Prefx addton The parallel prefx adder presented next, performs the addton of two bnary numbers n tme of complexty O(log n) and lnear cost O(n). Lets notce the

More information

UNIVERSITY OF NOTTINGHAM

UNIVERSITY OF NOTTINGHAM UNIVERSITY OF NOTTINGHAM SCHOOL OF ECONOMICS DISCUSSION PAPER 99/28 Welfare Analyss n a Cournot Game wth a Publc Good by Indraneel Dasgupta School of Economcs, Unversty of Nottngham, Nottngham NG7 2RD,

More information

Stochastic ALM models - General Methodology

Stochastic ALM models - General Methodology Stochastc ALM models - General Methodology Stochastc ALM models are generally mplemented wthn separate modules: A stochastc scenaros generator (ESG) A cash-flow projecton tool (or ALM projecton) For projectng

More information

Optimal Service-Based Procurement with Heterogeneous Suppliers

Optimal Service-Based Procurement with Heterogeneous Suppliers Optmal Servce-Based Procurement wth Heterogeneous Supplers Ehsan Elah 1 Saf Benjaafar 2 Karen L. Donohue 3 1 College of Management, Unversty of Massachusetts, Boston, MA 02125 2 Industral & Systems Engneerng,

More information

ASIAN JOURNAL OF CIVIL ENGINEERING (BUILDING AND HOUSING) VOL. 12, NO. 4 (2011) PAGES

ASIAN JOURNAL OF CIVIL ENGINEERING (BUILDING AND HOUSING) VOL. 12, NO. 4 (2011) PAGES ASIAN JOURNAL OF CIVIL ENGINEERING (BUILDING AND HOUSING) VOL. 12, NO. 4 (2011) PAGES 511-522 DISCOUNTED CASH FLOW TIME-COST TRADE-OFF PROBLEM OPTIMIZATION; ACO APPROACH K. Aladn, A. Afshar and E. Kalhor

More information

Heuristic optimization of complex constrained portfolio sets with short sales

Heuristic optimization of complex constrained portfolio sets with short sales Heurstc optmzaton of complex constraned portfolo sets wth short sales G A Vjayalakshm Pa Dept of Math. & Computer Applns. PSG College of Technology Combatore, INDIA pagav@mca.psgtech.ac.n Therry Mchel

More information

Algorithm For The Techno-Economic Optimization Applied In Projects Of Wind Parks Of Latin America.

Algorithm For The Techno-Economic Optimization Applied In Projects Of Wind Parks Of Latin America. IOSR Journal of Mechancal and Cvl Engneerng (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 13, Issue 4 Ver. VI (Jul. - Aug. 2016), PP 60-65 www.osrjournals.org Algorthm For The Techno-Economc

More information

Note on Cubic Spline Valuation Methodology

Note on Cubic Spline Valuation Methodology Note on Cubc Splne Valuaton Methodology Regd. Offce: The Internatonal, 2 nd Floor THE CUBIC SPLINE METHODOLOGY A model for yeld curve takes traded yelds for avalable tenors as nput and generates the curve

More information

Equilibrium in Prediction Markets with Buyers and Sellers

Equilibrium in Prediction Markets with Buyers and Sellers Equlbrum n Predcton Markets wth Buyers and Sellers Shpra Agrawal Nmrod Megddo Benamn Armbruster Abstract Predcton markets wth buyers and sellers of contracts on multple outcomes are shown to have unque

More information

MgtOp 215 Chapter 13 Dr. Ahn

MgtOp 215 Chapter 13 Dr. Ahn MgtOp 5 Chapter 3 Dr Ahn Consder two random varables X and Y wth,,, In order to study the relatonshp between the two random varables, we need a numercal measure that descrbes the relatonshp The covarance

More information

ISE High Income Index Methodology

ISE High Income Index Methodology ISE Hgh Income Index Methodology Index Descrpton The ISE Hgh Income Index s desgned to track the returns and ncome of the top 30 U.S lsted Closed-End Funds. Index Calculaton The ISE Hgh Income Index s

More information

We consider the problem of scheduling trains and containers (or trucks and pallets)

We consider the problem of scheduling trains and containers (or trucks and pallets) Schedulng Trans and ontaners wth Due Dates and Dynamc Arrvals andace A. Yano Alexandra M. Newman Department of Industral Engneerng and Operatons Research, Unversty of alforna, Berkeley, alforna 94720-1777

More information

II. Random Variables. Variable Types. Variables Map Outcomes to Numbers

II. Random Variables. Variable Types. Variables Map Outcomes to Numbers II. Random Varables Random varables operate n much the same way as the outcomes or events n some arbtrary sample space the dstncton s that random varables are smply outcomes that are represented numercally.

More information

Linear Combinations of Random Variables and Sampling (100 points)

Linear Combinations of Random Variables and Sampling (100 points) Economcs 30330: Statstcs for Economcs Problem Set 6 Unversty of Notre Dame Instructor: Julo Garín Sprng 2012 Lnear Combnatons of Random Varables and Samplng 100 ponts 1. Four-part problem. Go get some

More information

Available online at ScienceDirect. Procedia Computer Science 24 (2013 ) 9 14

Available online at   ScienceDirect. Procedia Computer Science 24 (2013 ) 9 14 Avalable onlne at www.scencedrect.com ScenceDrect Proceda Computer Scence 24 (2013 ) 9 14 17th Asa Pacfc Symposum on Intellgent and Evolutonary Systems, IES2013 A Proposal of Real-Tme Schedulng Algorthm

More information

A Single-Product Inventory Model for Multiple Demand Classes 1

A Single-Product Inventory Model for Multiple Demand Classes 1 A Sngle-Product Inventory Model for Multple Demand Classes Hasan Arslan, 2 Stephen C. Graves, 3 and Thomas Roemer 4 March 5, 2005 Abstract We consder a sngle-product nventory system that serves multple

More information

Evaluating Performance

Evaluating Performance 5 Chapter Evaluatng Performance In Ths Chapter Dollar-Weghted Rate of Return Tme-Weghted Rate of Return Income Rate of Return Prncpal Rate of Return Daly Returns MPT Statstcs 5- Measurng Rates of Return

More information

Pivot Points for CQG - Overview

Pivot Points for CQG - Overview Pvot Ponts for CQG - Overvew By Bran Bell Introducton Pvot ponts are a well-known technque used by floor traders to calculate ntraday support and resstance levels. Ths technque has been around for decades,

More information

EDC Introduction

EDC Introduction .0 Introducton EDC3 In the last set of notes (EDC), we saw how to use penalty factors n solvng the EDC problem wth losses. In ths set of notes, we want to address two closely related ssues. What are, exactly,

More information

Clock Tree Construction based on Arrival Time Constraints

Clock Tree Construction based on Arrival Time Constraints Clock Tree Constructon based on Arrval Tme Constrants Rckard Ewetz and Cheng-Kok Koh Department of Electrcal and Computer Engneerng, Unversty of Central Florda, Orlando, US School of Electrcal and Computer

More information

ECE 586GT: Problem Set 2: Problems and Solutions Uniqueness of Nash equilibria, zero sum games, evolutionary dynamics

ECE 586GT: Problem Set 2: Problems and Solutions Uniqueness of Nash equilibria, zero sum games, evolutionary dynamics Unversty of Illnos Fall 08 ECE 586GT: Problem Set : Problems and Solutons Unqueness of Nash equlbra, zero sum games, evolutonary dynamcs Due: Tuesday, Sept. 5, at begnnng of class Readng: Course notes,

More information

Genetic Algorithms for Optimization of Resource Allocation in Large Scale Construction Project Management

Genetic Algorithms for Optimization of Resource Allocation in Large Scale Construction Project Management 1916 JOURNAL OF COMPUTERS, VOL. 5, NO. 12, DECEMBER 2010 Genetc Algorthms for Optmzaton of Resource Allocaton n Large Scale Constructon Project Management Jan-wen Huang* College of Hydraulc & Envronmental

More information

University of Toronto November 9, 2006 ECO 209Y MACROECONOMIC THEORY. Term Test #1 L0101 L0201 L0401 L5101 MW MW 1-2 MW 2-3 W 6-8

University of Toronto November 9, 2006 ECO 209Y MACROECONOMIC THEORY. Term Test #1 L0101 L0201 L0401 L5101 MW MW 1-2 MW 2-3 W 6-8 Department of Economcs Prof. Gustavo Indart Unversty of Toronto November 9, 2006 SOLUTION ECO 209Y MACROECONOMIC THEORY Term Test #1 A LAST NAME FIRST NAME STUDENT NUMBER Crcle your secton of the course:

More information

University of Toronto November 9, 2006 ECO 209Y MACROECONOMIC THEORY. Term Test #1 L0101 L0201 L0401 L5101 MW MW 1-2 MW 2-3 W 6-8

University of Toronto November 9, 2006 ECO 209Y MACROECONOMIC THEORY. Term Test #1 L0101 L0201 L0401 L5101 MW MW 1-2 MW 2-3 W 6-8 Department of Economcs Prof. Gustavo Indart Unversty of Toronto November 9, 2006 SOLUTION ECO 209Y MACROECONOMIC THEORY Term Test #1 C LAST NAME FIRST NAME STUDENT NUMBER Crcle your secton of the course:

More information

Project Management Project Phases the S curve

Project Management Project Phases the S curve Project lfe cycle and resource usage Phases Project Management Project Phases the S curve Eng. Gorgo Locatell RATE OF RESOURCE ES Conceptual Defnton Realzaton Release TIME Cumulated resource usage and

More information

Problem Set 6 Finance 1,

Problem Set 6 Finance 1, Carnege Mellon Unversty Graduate School of Industral Admnstraton Chrs Telmer Wnter 2006 Problem Set 6 Fnance, 47-720. (representatve agent constructon) Consder the followng two-perod, two-agent economy.

More information

Optimising a general repair kit problem with a service constraint

Optimising a general repair kit problem with a service constraint Optmsng a general repar kt problem wth a servce constrant Marco Bjvank 1, Ger Koole Department of Mathematcs, VU Unversty Amsterdam, De Boelelaan 1081a, 1081 HV Amsterdam, The Netherlands Irs F.A. Vs Department

More information

Mode is the value which occurs most frequency. The mode may not exist, and even if it does, it may not be unique.

Mode is the value which occurs most frequency. The mode may not exist, and even if it does, it may not be unique. 1.7.4 Mode Mode s the value whch occurs most frequency. The mode may not exst, and even f t does, t may not be unque. For ungrouped data, we smply count the largest frequency of the gven value. If all

More information

Topics on the Border of Economics and Computation November 6, Lecture 2

Topics on the Border of Economics and Computation November 6, Lecture 2 Topcs on the Border of Economcs and Computaton November 6, 2005 Lecturer: Noam Nsan Lecture 2 Scrbe: Arel Procacca 1 Introducton Last week we dscussed the bascs of zero-sum games n strategc form. We characterzed

More information

Survey of Math: Chapter 22: Consumer Finance Borrowing Page 1

Survey of Math: Chapter 22: Consumer Finance Borrowing Page 1 Survey of Math: Chapter 22: Consumer Fnance Borrowng Page 1 APR and EAR Borrowng s savng looked at from a dfferent perspectve. The dea of smple nterest and compound nterest stll apply. A new term s the

More information

Capability Analysis. Chapter 255. Introduction. Capability Analysis

Capability Analysis. Chapter 255. Introduction. Capability Analysis Chapter 55 Introducton Ths procedure summarzes the performance of a process based on user-specfed specfcaton lmts. The observed performance as well as the performance relatve to the Normal dstrbuton are

More information

Advisory. Category: Capital

Advisory. Category: Capital Advsory Category: Captal NOTICE* Subject: Alternatve Method for Insurance Companes that Determne the Segregated Fund Guarantee Captal Requrement Usng Prescrbed Factors Date: Ths Advsory descrbes an alternatve

More information

Instituto de Engenharia de Sistemas e Computadores de Coimbra Institute of Systems Engineering and Computers INESC - Coimbra

Instituto de Engenharia de Sistemas e Computadores de Coimbra Institute of Systems Engineering and Computers INESC - Coimbra Insttuto de Engenhara de Sstemas e Computadores de Combra Insttute of Systems Engneerng and Computers INESC - Combra Joana Das Can we really gnore tme n Smple Plant Locaton Problems? No. 7 2015 ISSN: 1645-2631

More information

Petroleum replenishment and routing problem with variable demands and time windows

Petroleum replenishment and routing problem with variable demands and time windows Petroleum replenshment and routng problem wth varable demands and tme wndows Yan Cheng Hsu Jose L. Walteros Rajan Batta Department of Industral and Systems Engneerng, Unversty at Buffalo (SUNY) 34 Bell

More information

Macroeconomic Theory and Policy

Macroeconomic Theory and Policy ECO 209 Macroeconomc Theory and Polcy Lecture 7: The Open Economy wth Fxed Exchange Rates Gustavo Indart Slde 1 Open Economy under Fxed Exchange Rates Let s consder an open economy wth no captal moblty

More information

-~~?.~~.!.i.':':'.~.~-~-~~~~':':'.~~~.::.~~~~~~~--~-~-~~.::."!}.~!.~.. ~.~~-~...

-~~?.~~.!.i.':':'.~.~-~-~~~~':':'.~~~.::.~~~~~~~--~-~-~~.::.!}.~!.~.. ~.~~-~... -~~?.~~.!..':':'.~.~-~-~~~~':':'.~~~.::.~~~~~~~--~-~-~~.::."!}.~!.~.. ~.~~-~.... Part 1: Defnng schedules (10 Descrbe the followng terms as used n schedulng projects. 1.1 Crtcal path 1.2 Slack tme or float

More information

c slope = -(1+i)/(1+π 2 ) MRS (between consumption in consecutive time periods) price ratio (across consecutive time periods)

c slope = -(1+i)/(1+π 2 ) MRS (between consumption in consecutive time periods) price ratio (across consecutive time periods) CONSUMPTION-SAVINGS FRAMEWORK (CONTINUED) SEPTEMBER 24, 2013 The Graphcs of the Consumpton-Savngs Model CONSUMER OPTIMIZATION Consumer s decson problem: maxmze lfetme utlty subject to lfetme budget constrant

More information

ISE Cloud Computing Index Methodology

ISE Cloud Computing Index Methodology ISE Cloud Computng Index Methodology Index Descrpton The ISE Cloud Computng Index s desgned to track the performance of companes nvolved n the cloud computng ndustry. Index Calculaton The ISE Cloud Computng

More information

Single-Item Auctions. CS 234r: Markets for Networks and Crowds Lecture 4 Auctions, Mechanisms, and Welfare Maximization

Single-Item Auctions. CS 234r: Markets for Networks and Crowds Lecture 4 Auctions, Mechanisms, and Welfare Maximization CS 234r: Markets for Networks and Crowds Lecture 4 Auctons, Mechansms, and Welfare Maxmzaton Sngle-Item Auctons Suppose we have one or more tems to sell and a pool of potental buyers. How should we decde

More information

Appendix - Normally Distributed Admissible Choices are Optimal

Appendix - Normally Distributed Admissible Choices are Optimal Appendx - Normally Dstrbuted Admssble Choces are Optmal James N. Bodurtha, Jr. McDonough School of Busness Georgetown Unversty and Q Shen Stafford Partners Aprl 994 latest revson September 00 Abstract

More information

Pay for Performance Regulation. Draft Final Proposal Addendum

Pay for Performance Regulation. Draft Final Proposal Addendum Pay for Performance Regulaton Draft Fnal Proposal Addendum February 22, 2012 Pay for Performance Regulaton Draft Fnal Proposal Table of Contents 1 Introducton... 3 2 Plan for Stakeholder Engagement...

More information

Developing a quadratic programming model for time-cost trading off in construction projects under probabilistic constraint

Developing a quadratic programming model for time-cost trading off in construction projects under probabilistic constraint Proceedngs of the Internatonal Conference on Industral Engneerng and Operatons Management Rabat, Morocco, Aprl 11-13, 2017 Developng a quadratc programmng model for tme-cost tradng off n constructon projects

More information

Chapter 5 Student Lecture Notes 5-1

Chapter 5 Student Lecture Notes 5-1 Chapter 5 Student Lecture Notes 5-1 Basc Busness Statstcs (9 th Edton) Chapter 5 Some Important Dscrete Probablty Dstrbutons 004 Prentce-Hall, Inc. Chap 5-1 Chapter Topcs The Probablty Dstrbuton of a Dscrete

More information

m-inductive Properties of Logic Circuits Hamid Savoj, Alan Mishchenko, and Robert Brayton University of California, Berkeley

m-inductive Properties of Logic Circuits Hamid Savoj, Alan Mishchenko, and Robert Brayton University of California, Berkeley m-inductve Propertes of Logc Crcuts Hamd Savoj, lan Mshcheno, and Robert Brayton Unversty of Calforna, Bereley bstract Ths paper ntroduces the concept of m-nductveness over a set of sgnals S n a sequental

More information

Optimizing Merchant Revenue with Rebates

Optimizing Merchant Revenue with Rebates Optmzng Merchant Revenue wth Rebates Rakesh Agrawal Search Labs Mcrosoft Research rakesha@mcrosoft.com Samuel Ieong Search Labs Mcrosoft Research saeong@mcrosoft.com Raja Velu School of Management Syracuse

More information

Economics 1410 Fall Section 7 Notes 1. Define the tax in a flexible way using T (z), where z is the income reported by the agent.

Economics 1410 Fall Section 7 Notes 1. Define the tax in a flexible way using T (z), where z is the income reported by the agent. Economcs 1410 Fall 2017 Harvard Unversty Yaan Al-Karableh Secton 7 Notes 1 I. The ncome taxaton problem Defne the tax n a flexble way usng T (), where s the ncome reported by the agent. Retenton functon:

More information

Discrete Dynamic Shortest Path Problems in Transportation Applications

Discrete Dynamic Shortest Path Problems in Transportation Applications 17 Paper No. 98-115 TRANSPORTATION RESEARCH RECORD 1645 Dscrete Dynamc Shortest Path Problems n Transportaton Applcatons Complexty and Algorthms wth Optmal Run Tme ISMAIL CHABINI A soluton s provded for

More information

STUDY GUIDE FOR TOPIC 1: FUNDAMENTAL CONCEPTS OF FINANCIAL MATHEMATICS. Learning objectives

STUDY GUIDE FOR TOPIC 1: FUNDAMENTAL CONCEPTS OF FINANCIAL MATHEMATICS. Learning objectives Study Gude for Topc 1 1 STUDY GUIDE FOR TOPIC 1: FUNDAMENTAL CONCEPTS OF FINANCIAL MATHEMATICS Learnng objectves After studyng ths topc you should be able to: apprecate the ever-changng envronment n whch

More information

A Distributed Algorithm for Constrained Multi-Robot Task Assignment for Grouped Tasks

A Distributed Algorithm for Constrained Multi-Robot Task Assignment for Grouped Tasks A Dstrbuted Algorthm for Constraned Mult-Robot Tas Assgnment for Grouped Tass Lngzh Luo Robotcs Insttute Carnege Mellon Unversty Pttsburgh, PA 15213 lngzhl@cs.cmu.edu Nlanjan Charaborty Robotcs Insttute

More information

Global sensitivity analysis of credit risk portfolios

Global sensitivity analysis of credit risk portfolios Global senstvty analyss of credt rsk portfolos D. Baur, J. Carbon & F. Campolongo European Commsson, Jont Research Centre, Italy Abstract Ths paper proposes the use of global senstvty analyss to evaluate

More information

COST OPTIMAL ALLOCATION AND RATIONING IN SUPPLY CHAINS

COST OPTIMAL ALLOCATION AND RATIONING IN SUPPLY CHAINS COST OPTIMAL ALLOCATIO AD RATIOIG I SUPPLY CHAIS V..A. akan a & Chrstopher C. Yang b a Department of Industral Engneerng & management Indan Insttute of Technology, Kharagpur, Inda b Department of Systems

More information

Financial mathematics

Financial mathematics Fnancal mathematcs Jean-Luc Bouchot jean-luc.bouchot@drexel.edu February 19, 2013 Warnng Ths s a work n progress. I can not ensure t to be mstake free at the moment. It s also lackng some nformaton. But

More information

Construction Rules for Morningstar Canada Dividend Target 30 Index TM

Construction Rules for Morningstar Canada Dividend Target 30 Index TM Constructon Rules for Mornngstar Canada Dvdend Target 0 Index TM Mornngstar Methodology Paper January 2012 2011 Mornngstar, Inc. All rghts reserved. The nformaton n ths document s the property of Mornngstar,

More information

Teaching Note on Factor Model with a View --- A tutorial. This version: May 15, Prepared by Zhi Da *

Teaching Note on Factor Model with a View --- A tutorial. This version: May 15, Prepared by Zhi Da * Copyrght by Zh Da and Rav Jagannathan Teachng Note on For Model th a Ve --- A tutoral Ths verson: May 5, 2005 Prepared by Zh Da * Ths tutoral demonstrates ho to ncorporate economc ves n optmal asset allocaton

More information

New Distance Measures on Dual Hesitant Fuzzy Sets and Their Application in Pattern Recognition

New Distance Measures on Dual Hesitant Fuzzy Sets and Their Application in Pattern Recognition Journal of Artfcal Intellgence Practce (206) : 8-3 Clausus Scentfc Press, Canada New Dstance Measures on Dual Hestant Fuzzy Sets and Ther Applcaton n Pattern Recognton L Xn a, Zhang Xaohong* b College

More information

S yi a bx i cx yi a bx i cx 2 i =0. yi a bx i cx 2 i xi =0. yi a bx i cx 2 i x

S yi a bx i cx yi a bx i cx 2 i =0. yi a bx i cx 2 i xi =0. yi a bx i cx 2 i x LEAST-SQUARES FIT (Chapter 8) Ft the best straght lne (parabola, etc.) to a gven set of ponts. Ths wll be done by mnmzng the sum of squares of the vertcal dstances (called resduals) from the ponts to the

More information

The evaluation method of HVAC system s operation performance based on exergy flow analysis and DEA method

The evaluation method of HVAC system s operation performance based on exergy flow analysis and DEA method The evaluaton method of HVAC system s operaton performance based on exergy flow analyss and DEA method Xng Fang, Xnqao Jn, Yonghua Zhu, Bo Fan Shangha Jao Tong Unversty, Chna Overvew 1. Introducton 2.

More information

Hedging Greeks for a portfolio of options using linear and quadratic programming

Hedging Greeks for a portfolio of options using linear and quadratic programming MPRA Munch Personal RePEc Archve Hedgng reeks for a of otons usng lnear and quadratc rogrammng Panka Snha and Archt Johar Faculty of Management Studes, Unversty of elh, elh 5. February 200 Onlne at htt://mra.ub.un-muenchen.de/20834/

More information

Finite Math - Fall Section Future Value of an Annuity; Sinking Funds

Finite Math - Fall Section Future Value of an Annuity; Sinking Funds Fnte Math - Fall 2016 Lecture Notes - 9/19/2016 Secton 3.3 - Future Value of an Annuty; Snkng Funds Snkng Funds. We can turn the annutes pcture around and ask how much we would need to depost nto an account

More information

ECO 209Y MACROECONOMIC THEORY AND POLICY LECTURE 8: THE OPEN ECONOMY WITH FIXED EXCHANGE RATES

ECO 209Y MACROECONOMIC THEORY AND POLICY LECTURE 8: THE OPEN ECONOMY WITH FIXED EXCHANGE RATES ECO 209 MACROECONOMIC THEOR AND POLIC LECTURE 8: THE OPEN ECONOM WITH FIXED EXCHANGE RATES Gustavo Indart Slde 1 OPEN ECONOM UNDER FIXED EXCHANGE RATES Let s consder an open economy wth no captal moblty

More information

Strategic Planning and Project Selection for IT Portfolio Management

Strategic Planning and Project Selection for IT Portfolio Management Assocaton for Informaton Systems AIS Electronc Lbrary (AISeL) Internatonal Research Workshop on IT Project Management 2009 Internatonal Research Workshop on IT Project Management (IRWITPM) 12-14-2009 Strategc

More information