1 30 January 2013 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By ELodgement REPORT FOR THE QUARTER ENDED 31 DECEMBER 2012 Level St Kilda Road Melbourne, VIC, 3004 PO Box 6315 St Kilda Road Central Melbourne, VIC, 8008 Telephone: Directors Mr Joseph Gutnick Executive Chairman and Chief Executive Officer Mr Henry Herzog NonExecutive Director Dr David S Tyrwhitt NonExecutive Director Mr Craig Michael NonExecutive Director Senior Management Mr Peter Lee CFO & Company Secretary Mr Mike Kammermann Exploration Manager Mr Eric Magee Merlin Mine Operations Manager Merlin Mine Commencing Mining Operations Merlin Diamonds and Jet Mining have executed an agreement for Jet Mining to commence borehole mining operations at the Merlin Diamond Mine. The mining is expected to commence in the second quarter 2013 for trial operations aimed at optimising production. Full commercial mining operations will commence in the third quarter The Company has appointed Eric Magee as Operations Manager for the Merlin Diamond Mine. Work package tenders have been released for outsourcing processing plant operations and camp support services. Merlin Reserves and Resources Ore Classification Probable Ore Reserves Indicated & Inferred Mineral Resources Material (Mt) Average Grade (ct per tonne) Carats (Mcts) TOTAL The above Ore Reserves are additional to the Mineral Resources and are estimated on open pit and underground mining assumptions. A Reserve for alternative mining methods has not yet been estimated. Corporate Placement of 43 million ordinary shares at a price of 21 cents per share raising $9,030,000 of which 18 million shares have been issued with the balance to be issued by early March $8 million convertible note to international investor convertible at 21 cents per share., December 2012 Quarterly Report Page 1

2 Merlin Diamond Mine Trial Production Jet Mining Pty Ltd, an affiliate of USA based Kinley Exploration, has defined the technical and economic parameters for hydraulic ore cutting at Merlin. When implemented, this technology will enable the direct extraction of ore at Merlin without the need for capital intensive underground development or overburden removal. Jet Mining and Merlin Diamonds have executed the contract to begin mining operations at the Merlin Diamond Mine. The Company expects the borehole mining equipment and drilling rig to be commissioned during the second quarter The commissioning phase will be conducted on a single shift basis, mining kimberlite ore from the PalSac pipe. Subsequent to the successful commissioning of the borehole mining rig, double shift operations will commence at the higher grade Ywain kimberlite pipe. During the trial period, factors affecting ore extraction rates will be studied and the engineering processes optimised. Also, integration of mining and ore processing will be undertaken to establish the production levels for the Mine. Once a steady rate of diamond production is achieved, the Company expects mining and processing to continue uninterrupted. At that time, the Company will examine its options for increasing production which may include additional borehole mining rigs and/or plant upgrades. The Company s aim is to be producing at a minimum rate of 250,000 carats per year by the second half of 2014 with anticipated cash costs of less than US$150 per carat or less than US$60 per tonne of ore mined. The Company will initially outsource the operational and support activities at the Mine. Tenders for mining, haulage, processing and camp management have been released and the Company is evaluating the options. This strategy will allow the operation to commence production without the obligations and potential delays involved in Merlin employing and training staff inhouse. In the near term, Merlin management will focus on integrating and optimising site operations. Once production processes are in place, and the mine is operating in a steady state, the Company intends to move into a cost effective owner operated business model. Merlin Diamonds has appointed Eric Magee as Operations Manager for the Merlin Diamond Mine. Mr Magee is a qualified engineer with post graduate studies in Mining Engineering. He has over 25 years experience in the mining industry in South Africa and Australia. Between 2008 and 2012, he worked for Kimberley Diamond Company, with his final role being General Manager Operations. The Company has prepared tenders for key areas of the mines operation. Site visits by short listed companies have been concluded and the Company is awaiting proposals for two out of the three work packages., December 2012 Quarterly Report Page 2

3 Work Package 1: Mining Jet Mining has been awarded the tender for the provision of specialised borehole mining equipment, engineering and project management services to commence kimberlite ore extraction in the second quarter The work package specifies management of inpit operations and the engagement of a third party drilling contractor. All mining activity and ore haulage will be managed by Jet Mining. Work Package 2: Ore Processing The processing tender calls for suitable engineers to operate, maintain and possibly upgrade the Merlin processing plant. DRA Group has conducted a site visit and are preparing a proposal. DRA Group has an established history with the Merlin Mine. DRA designed the Merlin plant for Ashton Mining in the early days of the project. Work Package 3: Camp Facilities The camp facilities tender calls for suitable remote catering suppliers to supply catering and camp management services for the Merlin mine camp. Cater Care Group has conducted a site visit and is preparing a proposal. Cater Care Group are an industrial catering and accommodation company with experience in mining, offshore and remote sites. Merlin Exploration Program Since the early 1990 s a total of 11 kimberlite pipes have been discovered on the Merlin Mine Lease. The Mine s previous owners conducted extensive geochemical sampling and followed up with a drilling program resulting in the discovery of a lens shaped kimberlite body 100m south of Bedevere. The Company holds a significant historical database and data derived from sampling and drilling programs. The Company believes that the area covered by and near the Merlin Mine Lease has the potential to host undiscovered kimberlites. During 2012, a review of the exploration data has been commissioned and an exploration program designed with the goal of targeting unresolved geophysical, geochemical and structural anomalies. An exploration program drilling 42 targets was conducted at the Merlin Diamond Mine. The drilling program drilled 128 holes for a total of 3,568 metres. No kimberlites were intersected, however two drillholes intercepted anomalous geology in the sandstone cover. Samples from a fissure and a possible brecciated pipe discovered during the drilling program have been taken for indicator mineral analysis. No geochemical or heavy mineral results will be available until the next quarter. Numerous untested kimberlite targets remain to be drilled within the Merlin Mine Lease. Borroloola Alluvial Diamond Project An application was lodged in 2004 (Exploration Licence Application 24512) for an area of 289 blocks (approximately 230,000 acres), 10 kilometres south of the township of Borroloola. The Northern Land Council s Full Council ratified the Borroloola traditional owners decision to consent to the grant of the licence. On 29 August 2011, Exploration Licence was granted to the Company for a period of six years. The Borroloola alluvial gravels are exposed at surface in an area covering 5km 2. However, the total area which could potentially host alluvial gravel deposits on the Company s tenements is yet to be, December 2012 Quarterly Report Page 3

4 explored and is in the order of 300km 2. This significantly increases the opportunity to identify a large volume, high value alluvial diamond deposit. Following the grant of the exploration licence for the Borroloola Alluvial Diamond Project (EL24512) in August 2011, the Company immediately commenced the excavation of 5,000 tonnes of alluvial material from known diamond bearing gravel deposits. The purpose of the tests was to commence the assessment of the economic potential of the gravels by determining diamond quality, quantity and distribution in the alluvial material. The bulk sampling program focused on an area of outcropping gravel. Material from three costeans, 3,000 tonnes in total, has been processed at the Merlin Mine, yielding 22 stones with a total weight of 1.09 carats. Thirteen of the recovered diamonds are white in colour including the largest two at 0.19 and 0.25 carats. High water levels in rivers leading to the Merlin Diamond Mine prevented 2,000 tonnes of gravel from two costeans being transported during the wet season. This material will be processed in due course and further exploration work aimed at understanding the fluvial architecture of the gravels will be planned. The Borroloola Alluvial Diamond Project represents a significant and unique opportunity to explore for a large volume, high value, alluvial diamond deposit. Lancelot Prospect At the Lancelot Prospect (EL25676), in the Merlin Orbit tenements, an analysis of airborne gravity and magnetic data acquired in 2004, in conjunction with geochemical sampling has highlighted overlapping geophysical anomalies in proximity to geochemical anomalies. A Mine Management Plan has been submitted and accepted by the Department of Mines and Energy in the Northern Territory for an exploration costeaning program. The costeaning program was completed in November 2012 and targeted 30 sites. Fifty eight costeans were excavated and 91 samples comprising 20 to 80 kg each were collected for indicator mineral analysis. The results of this analysis are pending. In addition to testing the coincidental geophysical anomalies for the potential to be primary kimberlite, the program was designed to map and sample buried alluvial channels, known as palaeochannels, which may carry kimberlite indicator minerals. These palaeochannels were identified in drilling and costeaning during 2009 and The 2012 sampling will establish the distribution of chromites and micro diamonds in this alluvial material. This information will be used as vectors in future exploration programs to identify locations of primary kimberlite sources. Arnhem Land Exploration In October 2012 the Company collected 47 diamond exploration samples totalling 1,920kg over tenements EL331, EL3337, EL10233 and EL330. To date results from 28 samples have been received from the laboratory. Chromites were recovered in seven samples but are considered to be worn,, December 2012 Quarterly Report Page 4

5 weathered and of nonkimberlitic origin. A cube shaped microdiamond recovered in one sample is also considered to be of nonkimberlitic origin. Merlin Diamond Mine Project Background The Merlin Diamond Mine Project is located some 100km south of the settlement of Borroloola and comprises 14 kimberlite pipes. Since 1998, 9 of the Merlin pipes have been subject to openpit mining over a 5 year period. These previous mining operations produced 507,000 carats of diamonds. This included Australia s largest diamond at cts. In 2004, Merlin Diamonds acquired the project from the Rio Tinto parties. Mining Operations The Company s aim is to commence production in the third quarter of To meet this aim, capital items and personnel are currently being sourced. Resource Estimate Mining studies have enabled some of the Indicated Resources to be upgraded to Probable Ore Reserves. This resource estimate makes the Merlin Diamond Mine Project the second largest combined diamond resource and reserve in Australia. The combined Mineral Resource and Ore Reserve for all of the diamond pipes at Merlin is 30.1 million tonnes representing a total contained 7.2 million carats. A Reserve for alternative mining methods has not yet been estimated. Probable Ore Reserve The combined Probable Ore Reserve for all diamond pipes at Merlin is 11.1 million tonnes for an average grade of 26 carats per hundred tonnes ( cpht ) representing a total contained 2.89 million carats. Southern Cluster Probable Ore Reserve (Mt) Grade (cpht) Carats (Mcts) PalSac SubTotal Central Cluster Gawain Ywain SubTotal Northern Cluster Kaye Ector SubTotal TOTAL , December 2012 Quarterly Report Page 5

6 1 Resource grade based on previous mining operation recovery using a mm slotted bottom screen and a +0.95mm cutoff. 2 Resource grade based on bulk sample test work using a mm slotted bottom screen and a +1mm cutoff. The above Ore Reserves are additional to the Mineral Resources and are estimated on open pit and underground mining assumptions. A Reserve for alternative mining methods has not yet been estimated. Inferred and Indicated Resources The combined Indicated and Inferred Mineral Resource for all diamond pipes at Merlin is million tonnes for an average grade of 24 carats cpht representing a total contained 4.31 million carats. Southern Cluster Indicated Mineral Resource (Mt) Inferred Mineral Resource (Mt) Total (Mt) Grade (cpht) Carats (Mcts) PalSac Launfal Excalibur Tristram SubTotal Central Cluster Gawain Ywain SubTotal Northern Cluster Gareth Kaye Ector Bedevere SubTotal TOTAL Resource grade based on previous mining operation recovery using a mm slotted bottom screen and a +0.95mm cutoff. 2 Resource grade based on bulk sample test work using a mm slotted bottom screen and a +1mm cutoff. The above Mineral Resources are additional to the Ore Reserve and are estimated on open pit and underground mining assumptions. A Reserve for alternative mining methods has not yet been estimated., December 2012 Quarterly Report Page 6

7 DIAMOND EXPLORATION OVERVIEW Merlin Orbit Projects, Northern Territory The Merlin Orbit Project comprises an area of some 2,000km 2, and encompasses numerous known unresolved occurrences of indicator minerals and diamonds. Arnhem Land Projects, Northern Territory In 2009, the Company purchased all rights and title to tenements held by De Beers Exploration Australia Limited within Arnhem Land. These tenements are considered to have potential for diamonds and other minerals. The total Arnhem Land project area now encompasses some 20,000km 2. North Australian Diamonds Tenements Swancove and Red River Resources Joint Venture Agreement Merlin Diamonds Earning 80% Merlin Diamonds has a contractual right to obtain an 80% interest in two tenements covering some 2,000km² of land in the prospective western region of Arnhem Land. The Company s right to acquire an 80% interest in the two tenements is conditional on the grant of these tenements which are currently at the application stage. KIMBERLEY PROJECTS North Kimberley Within the Company s North Kimberley project area, the Company had previously identified a total inferred resource of 1.57M carats, contained within the Ashmore and Seppelt 1 and 2 pipes. The Company holds these resources under mining leases, as they continue to retain commercial potential. CORPORATE On 14 December 2012, the Company announced that it has entered into Application for Shares Agreements with four international investors to place 43 million fully paid ordinary shares at a price of 21 cents each raising $9,030,000. Since that announcement, the Company has issued 18 million shares ($3,780,000) and the balance of 25 million shares is due to settle by 4 March At the same time, the Company announced that that it has entered into an $8 million convertible note agreement with an international investor. The convertible note is for 1 year and bears interest at 6.5%. Interest is payable quarterly. The convertible notes can be converted into fully paid ordinary shares at any time during the 1 year period at a conversion price of 22 cents. The convertible notes are unsecured. The issue of the convertible note was subject to shareholder approval, which was obtained on 25 January The funds raised by the placements and convertible note are to provide financing towards the recommencement of mining operations at the Merlin diamond mine in Northern Territory, and for working capital., December 2012 Quarterly Report Page 7

8 The information in this report that relates to exploration results is based on information compiled by Dr DS Tyrwhitt who is a Fellow of the Australasian Institute of Mining and Metallurgy. Dr DS Tyrwhitt is a consulting geologist employed by DS Tyrwhitt & Associates Pty Ltd. Dr DS Tyrwhitt has 50 years experience in the industry and has more than 5 years experience which is relevant to the style of mineralisation being reported upon to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code of Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr Tyrwhitt consents to the inclusion in the report of the matters based on the information in the form and context to which it appears. Attached is a copy of the Company s Mining Exploration Entity Quarterly Report in accordance with Listing Rule 5.3. J I GUTNICK Chief Executive Officer 30 January 2013, December 2012 Quarterly Report Page 8

9 Figure 1 Merlin Diamond Mine and Surrounds Seppelt Ashmore Argyle Merlin Ellendale Western Australia Northern Territory Australian Diamond Pipes kilom etres 100 Scale 1:5,000,000, December 2012 Quarterly Report Page 9

10 Figure 2 Merlin Diamond Mine and Surrounding Areas, December 2012 Quarterly Report Page 10

11 Figure 3 Merlin Diamond Mine Area, December 2012 Quarterly Report Page 11

12 Figure 4 Arnhem Land Project Locations, December 2012 Quarterly Report Page 12

13 Appendix 5B Mining exploration entity quarterly report Appendix 5B Rule 5.3 Mining exploration entity quarterly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity MERLIN DIAMONDS LIMITED ABN Quarter ended ( current quarter ) DECEMBER 2012 Consolidated statement of cash flows Cash flows related to operating activities 1.1 Receipts from product sales and related debtors Current quarter $A 000 Year to date (6 months) $A Payments for (a) exploration & evaluation (b) development (c) production (d) administration (840) (497) (1,414) (1,370) 1.3 Dividends received 1.4 Interest and other items of a similar nature received Interest and other costs of finance paid (2) (3) 1.6 Income taxes paid 1.7 Other (GST & Fuel tax credits, R&D refund) Net Operating Cash Flows (1,262) (2,611) Cash flows related to investing activities 1.8 Payment for purchases of: (a) prospects (b) equity investments (c) other fixed assets 1.9 Proceeds from sale of: (a) prospects (b) equity investments (c) other fixed assets 1.10 Loans to other entities (339) 1.11 Loans repaid by other entities 1.12 Other (Security Deposits) (8) 1 Net investing cash flows (11) (344) 1.13 Total operating and investing cash flows (carried forward) (1,273) (2,955) (3) (6) + See chapter 19 for defined terms. 17/12/2010 Appendix 5B Page 1

14 Appendix 5B Mining exploration entity quarterly report 1.13 Total operating and investing cash flows (brought forward) (1,273 (2,955) Cash flows related to financing activities 1.14 Proceeds from issues of shares, options, etc. 1,890 1, Proceeds from sale of forfeited shares 1.16 Proceeds from borrowings 1.17 Repayment of borrowings 1.18 Dividends paid 1.19 Other (Finance leases, fees for share consolidation) (18) (36) Net financing cash flows 1,872 1,854 Net increase (decrease) in cash held 599 (1,101) 1.20 Cash at beginning of quarter/year to date 1,225 2, Exchange rate adjustments to item Cash at end of quarter 1,824 1,824 Payments to directors of the entity and associates of the directors Payments to related entities of the entity and associates of the related entities Current quarter $A' Aggregate amount of payments to the parties included in item Aggregate amount of loans to the parties included in item Explanation necessary for an understanding of the transactions Noncash financing and investing activities 2.1 Details of financing and investing transactions which have had a material effect on consolidated assets and liabilities but did not involve cash flows 2.2 Details of outlays made by other entities to establish or increase their share in projects in which the reporting entity has an interest + See chapter 19 for defined terms. Appendix 5B Page 2 17/12/2010

15 Appendix 5B Mining exploration entity quarterly report Financing facilities available Add notes as necessary for an understanding of the position. Amount available Amount used $A 000 $A Loan facilities 8,000 8, Credit standby arrangements Estimated cash outflows for next quarter $A Exploration and evaluation 1, Development 6, Production 4.4 Administration 1,200 Total 9,200 Reconciliation of cash Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts is as follows. Current quarter $A 000 Previous quarter $A Cash on hand and at bank 1,824 1, Deposits at call 5.3 Bank overdraft 5.4 Other (provide details) Total: cash at end of quarter (item 1.22) 1,824 1,224 Changes in interests in mining tenements 6.1 Interests in mining tenements relinquished, reduced or lapsed 6.2 Interests in mining tenements acquired or increased Tenement reference Nature of interest (note (2)) Interest at beginning of quarter EL27756 Partial Relinquishment 15 Bl 4 Bl Interest at end of quarter + See chapter 19 for defined terms. 17/12/2010 Appendix 5B Page 3

16 Appendix 5B Mining exploration entity quarterly report Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates. 7.1 Preference + securities (description) Total number Number quoted Issue price per security (see note 3) (cents) NIL 7.2 Changes during quarter (a) Increases through issues (b) Decreases through returns of capital, buybacks, redemptions Ordinary securities 141,783, ,783,427 Amount paid up per security (see note 3) (cents) 7.4 Changes during quarter (a) Increases through issues 9,000,000 (b) Decreases through returns of capital, buybacks Convertible debt NIL securities (description) 7.6 Changes during quarter (a) Increases through issues (b) Decreases through securities matured, converted 7.7 Options (description and conversion factor) 7.8 Issued during quarter 9,000, Exercised during quarter 7.10 Expired during quarter 7.11 Debentures NIL (totals only) 7.12 Unsecured notes NIL (totals only) Exercise price Expiry date + See chapter 19 for defined terms. Appendix 5B Page 4 17/12/2010

17 Appendix 5B Mining exploration entity quarterly report Compliance statement 1 This statement has been prepared under accounting policies which comply with accounting standards as defined in the Corporations Act or other standards acceptable to ASX (see note 5). 2 This statement does give a true and fair view of the matters disclosed. Sign here:... Date: 30 JANUARY 2013 (Director/Company Secretary) Print name: PETER LEE Notes 1 The quarterly report provides a basis for informing the market how the entity s activities have been financed for the past quarter and the effect on its cash position. An entity wanting to disclose additional information is encouraged to do so, in a note or notes attached to this report. 2 The Nature of interest (items 6.1 and 6.2) includes options in respect of interests in mining tenements acquired, exercised or lapsed during the reporting period. If the entity is involved in a joint venture agreement and there are conditions precedent which will change its percentage interest in a mining tenement, it should disclose the change of percentage interest and conditions precedent in the list required for items 6.1 and Issued and quoted securities The issue price and amount paid up is not required in items 7.1 and 7.3 for fully paid securities. 4 The definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. 5 Accounting Standards ASX will accept, for example, the use of International Financial Reporting Standards for foreign entities. If the standards used do not address a topic, the Australian standard on that topic (if any) must be complied with. == == == == == + See chapter 19 for defined terms. 17/12/2010 Appendix 5B Page 5

Merlin Diamonds Limited

Merlin Diamonds Limited 31 July2013 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By ELodgement REPORT FOR THE QUARTER ENDED 30 JUNE 2013 Merlin Diamonds Limited Level 8 580 St Kilda

More information

Merlin Diamonds Limited ACN INTERIM FINANCIAL REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2012

Merlin Diamonds Limited ACN INTERIM FINANCIAL REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2012 Merlin Diamonds Limited INTERIM FINANCIAL REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2012 Table of Contents Page Chairman s Report 2 Directors Report 9 Auditor s Independence Declaration 10 Consolidated

More information

For personal use only

For personal use only Top End Minerals Ltd 31 January 2013 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By ELodgement REPORT FOR THE QUARTER ENDED 31 DECEMBER 2012 Top End Minerals

More information

For personal use only

For personal use only 30 October 2015 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By ELodgement REPORT FOR THE QUARTER ENDED 30 SEPTEMBER 2015 Top End Minerals Limited Level 8

More information

Merlin Diamonds Limited

Merlin Diamonds Limited 31 July 2017 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By E-Lodgement REPORT FOR THE QUARTER ENDED 30 JUNE 2017 Merlin s Limited Level 1A 42 Moray Street

More information

Merlin Diamonds Limited

Merlin Diamonds Limited Merlin s Limited 24 October 2017 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By E-Lodgement REPORT FOR THE QUARTER ENDED 30 SEPTEMBER 2017 Merlin s Limited

More information

Merlin Diamonds Limited

Merlin Diamonds Limited Merlin s Limited 30 April 2018 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By E-Lodgement REPORT FOR THE QUARTER ENDED 31 MARCH 2018 Merlin s Limited Level

More information

NORTH AUSTRALIAN DIAMONDS LTD. Annual General Meeting The Sebel Albert Park, Melbourne - 25 November 2010

NORTH AUSTRALIAN DIAMONDS LTD. Annual General Meeting The Sebel Albert Park, Melbourne - 25 November 2010 NORTH AUSTRALIAN DIAMONDS LTD Annual General Meeting The Sebel Albert Park, Melbourne - 25 November 2010 1 DISCLAIMER Forward Looking Statement This presentation contains forward looking statements. Such

More information

For personal use only

For personal use only Quarterly Report & Appendix 5B Exalt Resources Ltd 31 December 2014 Exploration General The Company has continued to explore opportunities for the quarter ended 31 December 2014. In particular, the Company

More information

Appendix 5B. Quarter ended ( current quarter ) December Receipts from product sales and related debtors - -

Appendix 5B. Quarter ended ( current quarter ) December Receipts from product sales and related debtors - - Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10, 17/12/10. Name of entity

More information

For personal use only

For personal use only ASX ANNOUNCEMENT ASX: IVG Date: 29 July 2011 Number: 013/290711 JUNE 2011 QUARTERLY REPORT SUMMARY Market Cap A$3.78 m ($0.105 p/s) Issued Capital 36,000,006 First pass and infill soil geochemistry surveys

More information

QUARTERLY ACTIVITIES REPORT For the period ended 31 March 2015

QUARTERLY ACTIVITIES REPORT For the period ended 31 March 2015 30 April 2015 QUARTERLY ACTIVITIES REPORT For the period ended 31 March 2015 COMPANY OVERVIEW Regalpoint Resources Limited was formed to use the best available science to explore the Australian continent

More information

Merlin Diamonds Limited ACN INTERIM FINANCIAL REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2017

Merlin Diamonds Limited ACN INTERIM FINANCIAL REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2017 ACN 009 153 119 INTERIM FINANCIAL REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2017 Table of Contents Page Chairman s Report 2 Directors Report 4 Auditor s Independence Declaration 5 Consolidated Statement

More information

Appendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report

Appendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8

More information

Mining exploration entity quarterly report

Mining exploration entity quarterly report Appendix 5B Mining exploration entity quarterly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity Predictive Discovery Ltd ABN 11 127

More information

Appendix 5B. Quarter ended ( current quarter ) September Receipts from product sales and related debtors - -

Appendix 5B. Quarter ended ( current quarter ) September Receipts from product sales and related debtors - - Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity REGALPOINT

More information

Appendix 5B. Brazilian Metals Group Limited. Quarter ended ( current quarter ) March 2011

Appendix 5B. Brazilian Metals Group Limited. Quarter ended ( current quarter ) March 2011 Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity Brazilian

More information

June 2016 Quarterly Activity Report. Makabingui Gold Project Permit Update. Moura Permit Konkoutou Gold Project. Corporate

June 2016 Quarterly Activity Report. Makabingui Gold Project Permit Update. Moura Permit Konkoutou Gold Project. Corporate Bassari Resources Limited is an Australian ASXlisted company focused on discovering and developing multimillion ounce gold deposits in the Birimian Gold Belt, Senegal, West Africa. FAST FACTS ASX Code

More information

Axiom Mining Limited. Cash Flow Report Appendix 5B. For the Quarter Ended 30 June 2010

Axiom Mining Limited. Cash Flow Report Appendix 5B. For the Quarter Ended 30 June 2010 Axiom Mining Limited Cash Flow Report Appendix 5B For the Quarter Ended 30 June 2010 Axiom Mining Limited ( Axiom ASX:AVQ) hereby releases it s Appendix 5B in accordance with the ASX Listing Rules. This

More information

Appendix 5B. Mining exploration entity and oil and gas exploration entity

Appendix 5B. Mining exploration entity and oil and gas exploration entity Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8

More information

Quarterly Report for the Period Ended 31 December 2013

Quarterly Report for the Period Ended 31 December 2013 ABN 63 124 706 449 Address: Postal: Phone: Fax: Email: Level 1, 95 Canning Highway South Perth, WA 6151, Australia PO Box 6731, East Perth WA 6892, Australia 61 8 9221 6813 61 8 9474 9304 admin@nexmetals.com

More information

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) December 2011

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) December 2011 Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity BERKELEY RESOURCES

More information

Marmota Energy. QUARTERLY REPORT Quarter ending 30 September Significant large oil-bearing carbonaceous shale body discovered on Ambrosia.

Marmota Energy. QUARTERLY REPORT Quarter ending 30 September Significant large oil-bearing carbonaceous shale body discovered on Ambrosia. QUARTERLY REPORT Quarter ending 30 September 2008 Marmota Energy Highlights Three and a half month targeted 4,375 metre drilling program completed on Ambrosia and Mulgathing. Positive uranium results returned

More information

Appendix 5B. Mining exploration entity quarterly report

Appendix 5B. Mining exploration entity quarterly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 1/6/10, 17/12/10 Rule 5.3 SOUTHERN CROSS EXPLORATION N.L. QUARTER ENDED ("Current Quarter") : 31st MARCH 2016 Consolidated Statement

More information

Quarterly Activities Report

Quarterly Activities Report ASX: CYL Quarterly Activities Report Quarter ended 30 September 2013 SUMMARY Data review confirms shallow gold potential beneath Hayanmi and Boyd s Dam Prospects at Four Eagles Gold Project 2014 drilling

More information

Appendix 5B. Quarter ended ( current quarter ) June 2011

Appendix 5B. Quarter ended ( current quarter ) June 2011 Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity AusNiCo Limited

More information

Quarterly activities report For Qtr ended 30 June 2013 OPERATIONS

Quarterly activities report For Qtr ended 30 June 2013 OPERATIONS Quarterly activities report For Qtr ended 30 June 2013 ASX:AWV Anova Metals Limited ABN 20 147 678 779 OPERATIONS 26 July 2013 Directors Jon Parker Chairman & NED Tim Dobson Managing Director Bill Fry

More information

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B

Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8

More information

Argent Minerals Limited

Argent Minerals Limited ASX ANNOUNCEMENT 28 January 2010 QUARTERLY ACTIVITIES REPORT FOR QUARTER ENDED 31 st DECEMBER 2009 HIGHLIGHTS Kempfield Scoping Study The Scoping Study into the Kempfield silver project is expected to

More information

For personal use only

For personal use only Mining exploration entity ly report Rule 5.3 Mining exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity Australian

More information

Appendix 5B. Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 COALBANK LIMITED

Appendix 5B. Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 COALBANK LIMITED Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity COALBANK LIMITED ABN Quarter ended ( current ) 20 075 877 075 31 December

More information

THE HOME OF LARGE HIGH QUALITY DIAMONDS MERLIN DIAMONDS LIMITED SEPTEMBER 2017 PRESENTATION

THE HOME OF LARGE HIGH QUALITY DIAMONDS MERLIN DIAMONDS LIMITED SEPTEMBER 2017 PRESENTATION THE HOME OF LARGE HIGH QUALITY DIAMONDS MERLIN DIAMONDS LIMITED SEPTEMBER 2017 PRESENTATION Merlin Diamonds Limited - August 2017 1 AUSTRALIA S LARGEST DIAMOND AT 104.73 CARATS WAS MINED AT MERLIN Merlin

More information

For personal use only

For personal use only ABN 93 104 757 904 Suite 4, 213 Balcatta Road, BALCATTA WA 6021 PO Box 572, BALCATTA WA 6914 T: 61 8 9240 4111 F: 61 8 9240 4054 W: www.australasiaconsolidated.com.au E: admin@australasiaconsolidated.com.au

More information

Mining exploration entity and oil and gas exploration entity quarterly report

Mining exploration entity and oil and gas exploration entity quarterly report Rule 5.5 Appendix 5B Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name

More information

QUARTERLY ACTIVITIES REPORT For the period ended 30 September 2015

QUARTERLY ACTIVITIES REPORT For the period ended 30 September 2015 30 October 2015 QUARTERLY ACTIVITIES REPORT For the period ended 30 September 2015 COMPANY OVERVIEW Regalpoint Resources Limited was formed to use the best available science to explore the Australian continent

More information

Bankable feasibility study on the Coburn project continued broadly on schedule with completion due in late March 2004.

Bankable feasibility study on the Coburn project continued broadly on schedule with completion due in late March 2004. QUARTERLY REPORT TO END OF DECEMBER 2003 GUNSON RESOURCES LIMITED QUARTERLY REPORT FOR THE PERIOD ENDED 31 st DECEMBER 2003 HIGHLIGHTS A significant increase in the Amy Zone resource at the Coburn heavy

More information

For personal use only

For personal use only Newfield Resources Limited 79 Broadway Nedlands WA 6009 Telephone: +61 8 6389 2688 Facsimile: +61 8 6389 2588 Email: info@newfieldresources.com.au Website: www.newfieldresources.com.au Quarterly Report

More information

Mining exploration entity and oil and gas exploration entity quarterly report

Mining exploration entity and oil and gas exploration entity quarterly report Rule 5.5 Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10, 17/12/10, 01/05/2013

More information

Mining exploration entity quarterly report. Quarter ended ( current quarter ) December 2012

Mining exploration entity quarterly report. Quarter ended ( current quarter ) December 2012 Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity ASCOT RESOURCES LIMITED ABN Quarter ended ( current ) 85 146 530 378 31

More information

Haoma Mining NL A.B.N

Haoma Mining NL A.B.N Haoma Mining NL A.B.N 12 008 676 177 Registered Office & Head Office: 411 Collins Street, Melbourne, Vic., 3000, GPO Box 2282U, Melbourne, Vic., 3001. Telephone (03) 9629 6888, Facsimile (03) 9629 1250

More information

Quarterly Activities Report

Quarterly Activities Report ASX: CYL Quarterly Activities Report Quarter ended 30 June 2012 SUMMARY High grade gold intersected in aircore drilling programme at Four Eagles Gold Project. Very high grade gold mineralisation in diamond

More information

For personal use only

For personal use only Mount Magnet South NL ABN 93 096 635 246 Quarterly Activities & Cashflow Report 30 September 2011 Summary Upgraded Mineral Resource Estimate at Kirkalocka finalised increasing Indicated category by 13%

More information

TRAKA RESOURCES LTD (A.B.N )

TRAKA RESOURCES LTD (A.B.N ) TRAKA RESOURCES LTD (A.B.N. 63 103 323 173) Quarterly Activity Report for the three months ended 30 th June 2008 Suite 2 Ground floor, 43 Ventnor Avenue, West Perth Western Australia 6005 Telephone: (+61)

More information

For personal use only

For personal use only Rule 5.5 Mining exploration entity and oil and gas exploration entity quarterly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name of

More information

Quarterly Activities Report For the quarter ended 30 June 2007

Quarterly Activities Report For the quarter ended 30 June 2007 ASX Release ASX Codes 26 July 2007 DMA, DMAO Quarterly Activities Report For the ended 30 June 2007 Issued Capital 33.5M shares 21.8M options Cash at 30 June 2007 A$4.1M Board of Directors David McSweeney

More information

Appendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report

Appendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name of entity

More information

Quarterly Activities Report

Quarterly Activities Report ASX: CYL Quarterly Activities Report Quarter ended 31 December 2015 SUMMARY January 2016 drilling and gravity geophysical programme finalised for Four Eagles Joint Venture Up to 24,000 metres of Aircore

More information

For personal use only

For personal use only MARCH 2011 QUARTERLY REPORT Equatorial Resources Limited ( Equatorial or the Company ) is pleased to present its quarterly report for the period ended 31 March 2011. HIGHLIGHTS Drilling commenced at the

More information

Appendix 5B. Mining exploration entity quarterly report

Appendix 5B. Mining exploration entity quarterly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 1/6/10, 17/12/10 Rule 5.3 SOUTHERN CROSS EXPLORATION N.L. QUARTER ENDED ("Current Quarter") : 30th September 2015 Consolidated

More information

ASX Release ASX Code: RLC

ASX Release ASX Code: RLC Reedy Lagoon Corporation Limited ABN 41 006 639 514 ASX Release ASX Code: RLC 29 January 2016 Quarterly Report for the period ended 31 December 2015 HIGHLIGHTS Cassilis gold project assessment for acquisition

More information

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) June 2014

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) June 2014 Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity NIUMINCO GROUP LIMITED ABN 44 009 163 919 30 June 2014 Quarter ended ( current ) Consolidated statement

More information

For personal use only

For personal use only 31st March 2013 Quarterly Report March 2012 Forte Energy NL ( Forte Energy or the Company ) (ASX/AIM: FTE) is an emerging international uranium company focused on the exploration and development of a portfolio

More information

Quarterly Activities Report

Quarterly Activities Report ASX: CYL Quarterly Activities Report Quarter ended 30 September 2011 SUMMARY Drilling due to commence on Four Eagles Gold Project before the end of October 2011 after no drilling activity during the September

More information

Scoping study (assuming toll milling) estimates $A24M (US$17M) operating surplus

Scoping study (assuming toll milling) estimates $A24M (US$17M) operating surplus 30 th April 2009 March December 2009 Quarterly Quarterly Report Report 2008 Highlights Akoko Project 76,000 ounce Indicated and Inferred Mineral Resource estimated for Akoko North gold deposit Pit optimisation

More information

WOOLGAR GOLD PROJECT QUEENSLAND

WOOLGAR GOLD PROJECT QUEENSLAND ACN 008 901 380 ABN 35 008 901 380 Level 1 460 Roberts Road Subiaco, Western Australia 6008 29th OCTOBER 2007 ANNOUNCEMENTS AUSTRALIAN STOCK EXCHANGE ASX ONLINE SYDNEY NSW P.O. Box 66 Floreat Forum WA

More information

Appendix 5B. Mining exploration entity and oil and gas exploration entity

Appendix 5B. Mining exploration entity and oil and gas exploration entity Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8

More information

Appendix 5B. Mindax Limited. Quarter ended ( current quarter ) June 2012

Appendix 5B. Mindax Limited. Quarter ended ( current quarter ) June 2012 Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity Mindax Limited

More information

For personal use only

For personal use only ACN 072 692 365 Report for September Quarter 26 October 2016 ASX Code: HEG, HEGOA CORPORATE A subscription agreement was signed with Bao Industry Pty Ltd (01.08.2016) for a number of placements to raise

More information

RECOMMENDATION Strong BUY Short Term target A$0.10 Long Term target A$0.48

RECOMMENDATION Strong BUY Short Term target A$0.10 Long Term target A$0.48 Diamond Joe in a comeback The AGE, December, 24, 2008 North Australian Diamonds Limited (NAD) as at 10 th November 2009 A$0.059 RECOMMENDATION Strong BUY Short Term target A$0.10 Long Term target A$0.48

More information

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) March 2009

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) March 2009 Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity Axiom Mining Ltd ARBN

More information

For personal use only

For personal use only 29 July 2016 QUARTERLY REPORT For the Period Ending 30 June 2016 Redstone Resources Limited (ASX Code: RDS) ( Redstone or the Company ) presents its quarterly report for the period ending 30 June 2016

More information

For personal use only

For personal use only QUARTERLY REPORT TO 30 SEPTEMBER 2013 HIGHLIGHTS Acquisition of the Bullendale Gold Project, New Zealand Siburan has acquired EP 52889 which contains historic underground mine workings located near Arrowtown

More information

For personal use only

For personal use only 31 January 2011 ASX Code: KAS DECEMBER QUARTERLY REPORT BOARD & MANAGEMENT Mike Spratt Non Executive Chairman Rod Marston Non Executive Director Rob Weinberg Non Executive Director Wayne Bramwell Managing

More information

For personal use only

For personal use only ASX: GBM Quarterly Report for the period ended 31 December 2013 Summary GBM Gold Ltd (ASX: GBM) ( GBM or Company ) completed the part sale of Inglewood Mining Company Pty Ltd ( INGMCo ) to Wilshire Asset

More information

Strengthening of board with the appointment of Dr Allan Trench as a Non-executive Director

Strengthening of board with the appointment of Dr Allan Trench as a Non-executive Director Highlights Corporate Strengthening of board with the appointment of Dr Allan Trench as a Non-executive Director Land Acquisition Substantial increase to Productora uranium-copper-gold project with the

More information

RED RIVER RESOURCES LIMITED (RVR) QUARTERLY REPORT (Fourth Quarter) APRIL-JUNE 2010

RED RIVER RESOURCES LIMITED (RVR) QUARTERLY REPORT (Fourth Quarter) APRIL-JUNE 2010 29 July 2010 Company Announcements Office Australian Stock Exchange Limited 20 Bridge Street SYDNEY NSW 2000 RED RIVER RESOURCES LIMITED (RVR) QUARTERLY REPORT (Fourth Quarter) APRIL-JUNE 2010 Activities

More information

For personal use only

For personal use only Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name of entity

More information

QUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2009 HIGHLIGHTS

QUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2009 HIGHLIGHTS 45 Ventnor Avenue, West Perth WA 6005 PO Box 829, West Perth WA 6872 (08) 9389 4450 Fax: (08) 9389 4400 0418 928 180 wayne@eagleeyemetals.com ABN 11 113 931 105 30 October 2009 The Company Announcements

More information

RE: QUARTERLY ACTIVITIES REPORT FOR THE QUARTER ENDED 30 SEPTEMBER

RE: QUARTERLY ACTIVITIES REPORT FOR THE QUARTER ENDED 30 SEPTEMBER Activities Report Quarter Ended 30 September 2010 21 October 2010 Company Announcements Office ASX Limited RE: QUARTERLY ACTIVITIES REPORT FOR THE QUARTER ENDED 30 SEPTEMBER 2010 As part of its expansion

More information

For personal use only

For personal use only Mining exploration entity and oil and gas exploration entity ly report Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97,

More information

Mining exploration entity quarterly report. Quarter ended ( current quarter ) March 2013

Mining exploration entity quarterly report. Quarter ended ( current quarter ) March 2013 Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity ASCOT RESOURCES LIMITED ABN Quarter ended ( current ) 85 146 530 378 31

More information

For personal use only

For personal use only Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name of entity

More information

QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2011

QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2011 26 OCTOBER 2011 QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2011 St George Mining Limited (ASX: SGQ) ( St George Mining ), a gold and nickel focused exploration company, presents its

More information

For personal use only

For personal use only Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity International Coal Limited ABN Quarter ended ( current ) 65 149 197 651 31 March 2015

More information

Quarterly Cash Flow Report

Quarterly Cash Flow Report Quarterly Cash Flow Report 30 April 2012 Company Announcements Office Australian Securities Exchange Limited Quarterly Cash Flow Report The Company s Appendix 5B Quarterly Cash Flow Statement for the Quarter

More information

Appendix 5B. Mining exploration entity quarterly report. Consolidated statement of cash flows. Current quarter $A 000

Appendix 5B. Mining exploration entity quarterly report. Consolidated statement of cash flows. Current quarter $A 000 Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity ATTILA RESOURCES LIMITED ABN Quarter ended ( current ) 53 142 165 080

More information

For personal use only

For personal use only Quarterly Report FOR PERIOD ENDING 30 SEPTEMBER 2013 ASX Code: FAS Contact Details Unit 3, 136 Main Street, Osborne Park WA 6017 PO Box 1520 Osborne Park WA 6916 T: 08 9242 5111 F: 08 9242 5677 E: admin@fairstarresources.com

More information

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) MARCH 2010

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) MARCH 2010 Mining exploration entity ly report Appendix 5B (Rule 5.3) Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity PO VALLEY ENERGY

More information

QUARTERLY ACTIVITIES REPORT For the period ended 31 March 2016

QUARTERLY ACTIVITIES REPORT For the period ended 31 March 2016 29 April 2016 QUARTERLY ACTIVITIES REPORT For the period ended 31 March 2016 COMPANY OVERVIEW Regalpoint Resources Limited (Company or ASX:RGU) currently holds projects in Queensland and Northern Territory,

More information

For personal use only

For personal use only Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity HARANGA RESOURCES LIMITED ABN Quarter ended ( current ) 83 141 128 841 31 December 2010 Consolidated

More information

For personal use only

For personal use only ASX: CYL Quarterly Activities Report Quarter ended 31 March 2015 SUMMARY Catalyst secures up to $4.2 million private funding for Four Eagles Gold Project Four Eagles Gold Project tenement EL4525 renewed

More information

For personal use only

For personal use only www.kentorgold.com.au Quarterly Activities Report Period Ended 31 March 2013 Corporate Administrators appointed to the subsidiary company operating the Murchison gold mine after a finance facility to fund

More information

Quarterly Report Period to 31 March 2014

Quarterly Report Period to 31 March 2014 ASX Release 30 April 2014 HIGHLIGHTS Quarterly Report Period to 31 March 2014 New Madagascar Prime Minister, Mr Roger Kolo. Submission process of the ESIA started. Environmental Social Impact Assessment

More information

For personal use only

For personal use only ABN QUARTERLY ACTIVITIES REPORT MARCH 2013 SUMMARY Drilling to commence at Mayfield and Porters Mount The Company announced to the ASX on 23 April 2013 proposed drilling and exploration programs for the

More information

For personal use only

For personal use only Redbank Copper ASX: RCP ASX Announcement 31 October 2016 Shares on Issue 2,339,430,263 Current Share Price A$ 0.002 Market Capitalisation $4.67M (based on A$0.002) Cash at 30/9/16 A$0.05 million Board

More information

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) JUNE 2013

Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) JUNE 2013 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10, 17/12/10. Name of entity SUN RESOURCES NL ABN Quarter ended ( current ) 69 009 196 810 30 JUNE 2013 Consolidated statement

More information

For personal use only

For personal use only FOR THE PERIOD ENDED 31/12/11 ASX Code: Issued Shares: Market Capitalisation: AAL 250m $3.5m Cash: $16,000 Review of Operations Coal Concession The outcome of the Judicial Review adjudicated by the Administrative

More information

For personal use only

For personal use only Redbank Copper ASX: RCP ASX Announcement 31 January 2017 Shares on Issue 2,339,430,263 Current Share Price A$ 0.002 Market Capitalisation $4.68M (based on A$0.002) Cash at 30/12/16 A$2,000 Board of Directors

More information

Consolidated Tin Mines Limited

Consolidated Tin Mines Limited Snapshot: Registered Office: 395 Lake Street, Cairns North, QLD, 4870 Ph: (07) 4032 3319 Current CSD Share Price: $0.08 Current LME Tin Price: $28,775 Detailed information at www.csdtin.com.au JUNE QUARTER

More information

ASX RELEASE 30 January 2018 ASX Code: POZ. QUARTERLY REPORT Period Ending 31 December Summary:

ASX RELEASE 30 January 2018 ASX Code: POZ. QUARTERLY REPORT Period Ending 31 December Summary: 30 January 2018 ASX Code: POZ QUARTERLY REPORT Period Ending 31 December 2017 Summary: Blina Diamond Project (100% POZ) Granting of all four Mining Leases and Agreements with Traditional Owners paves the

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 29 April 2013 Perpetual Resources Limited Quarterly Cash Flow and Activity Statement For Quarter Ended March 2013. Perpetual Resources Limited ( Perpetual ) during the was admitted to

More information

For personal use only

For personal use only Exalt Resources Ltd ACN: 145 327 617 Level 5, 56 Pitt Street, Sydney NSW 2000 P: +61 2 8651 7800 QUARTERLY REPORT FOR THE PERIOD ENDING 31 ST DECEMBER 2011 ASX RELEASE Exalt s Projects Exalt owns 100%

More information

For personal use only

For personal use only Suite 1502, Tower B, 799 Pacific Highway, Chatswood NSW 2067 Tel. (02) 9411 6033 Fax (02) 9411 6066 www.malachite.com.au Mining exploration entity quarterly report Introduced 1/7/96. Origin: Appendix 8.

More information

For personal use only

For personal use only Mining exploration entity and oil and gas exploration entity ly report Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97,

More information

QUARTERLY ACTIVITIES REPORT For the Quarter ended 31 March 2012

QUARTERLY ACTIVITIES REPORT For the Quarter ended 31 March 2012 QUARTERLY ACTIVITIES REPORT For the Quarter ended 31 March 2012 Liontown Resources Limited ABN 39 118 153 825 HIGHLIGHTS Jubilee Reef Joint Venture Project (Northern Tanzania) 7,000 metre drilling program

More information

For personal use only

For personal use only Quarterly Activities Report - period ending April 2012 Havilah Resources (ASX: HAV) Havilah Resources NL aims to become a significant new producer of copper, gold, cobalt and molybdenum from its 100% owned

More information

QUARTERLY ACTIVITIES REPORT SEPTEMBER QUARTER 2014

QUARTERLY ACTIVITIES REPORT SEPTEMBER QUARTER 2014 Marmota Energy Limited (ASX: MEU) ASX ANNOUNCEMENT 31 October 2014 QUARTERLY ACTIVITIES REPORT SEPTEMBER QUARTER 2014 HIGHLIGHTS: Marmota was given consent by NSW Government to apply for an exploration

More information

For personal use only

For personal use only Mining exploration entity and oil and gas exploration entity ly report Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97,

More information

For personal use only

For personal use only QUARTERLY OPERATIONS REPORT TO 30 JUNE 2016 OPERATIONS SRI LANKAN MINERAL SANDS PROJECT Windimurra Vanadium Ltd (the Company ) has exercised an option to acquire 100% of the issued capital of Srinel Holdings

More information

For personal use only

For personal use only (Formerly Fission Energy Ltd) ACN 119 057 457 ASX QUARTERLY REPORT FOR PERIOD ENDED 30 TH JUNE 2013 Mt Thirsty Cobalt Nickel Oxide Project positive results continue Highlights Further metallurgical test