Click Here for POWER POINT SLIDES

Size: px
Start display at page:

Download "Click Here for POWER POINT SLIDES"

Transcription

1 Mechanic s Liens: Preserve and Perfect Your Lien Rights While Avoiding Fatal Defects James T. Dixon Brouse McDowell LPA 600 Superior Ave., East Suite 1600 Cleveland, Ohio jdixon@brouse.com Click Here for POWER POINT SLIDES

2 Table of Contents I. Mechanic s Liens on Private Projects... 3 A. What is a Mechanic s Lien?... 3 B. Who Has the Right to Lien a Project?... 3 C. How Can Property Owners, Lenders, and Prime Contractors Protect Themselves?... 4 D. How Do Claimants Preserve and Perfect Their Lien Rights?... 8 E. How Can Owners and Contractors Respond to Liens? F. What is Required to Initiate a Foreclosure Lawsuit? G. How Are Lien Claimants Paid in a Foreclosure Action? H. Differences for Residential and Oil and Gas Projects I. Release of Liens II. Mechanic s Liens on Public Projects III. Contract Terms Relating to Liens A. Advance Lien Waivers B. Lien Indemnification C. Bonding Requirements D. Lien Waiver Contingencies (Payment) E. Statutory Protections of The Fairness in Contracting Act IV. Terms of Progress and Final Lien Waivers Ohio Mechanic s Liens Cheat Sheet Exhibit A - ORIGINAL NOTICE OF COMMENCEMENT Exhibit B - Notice of Furnishing Exhibit C - Affidavit To Obtain A Mechanic's Lien Exhibit D - Notice of Furnishing Exhibit E - Affidavit of Lien DISCLAIMER: The following materials and accompanying Access MCLE, LLC audio program are for instructional purposes only. Nothing herein constitutes, is intended to constitute, or should be relied on as, legal advice. The author expressly disclaims any responsibility for any direct or consequential damages related in any way to anything contained in the materials or program, which are provided on an as-is basis and should be independently verified by experienced counsel before being applied to actual matter. By proceeding further you expressly accept and agree to Author s absolute and unqualified disclaimer of liability.

3 I. Mechanic s Liens on Private Projects A. What is a Mechanic s Lien? To paraphrase the definition published by Merriam-Webster, a lien is a charge upon real property that arises by operation of statute in order to satisfy a debt. And, the phrase also relies upon that dictionary s broad definition of the term mechanic, which is generally a manual worker. As the definition indictes, a lien arises by operation of statute. In this case, the statutes are set forth in crtain sections of the Ohio Revised Code ( ORC ). Arising from this is one of the touchstones of the Ohio common law that has developed from these statutory rights. Because liens are a creature of statute, they are considered to be rights provided in derogation of the common law. As such, they are construed strictly when it comes to perfecting the right. See, e.g., Manpower, Inc. v. Phillips, 177 Ohio St. 45 (1962). A liberal rule of construction is provided by ORC , but that only applies to issues that arise once the lien attaches. Furthermore, the lien is not always against the ownership interest in the real property. Complications arise when it is a tenant that is contracting for the work. In that case, the lien only attaches to the improvements and the lessee s leasehold interest, not to the owner s interest in the property (which is also called the fee interest ). ORC ; Construction One, Inc. v. Shore Thing, Inc., Eighth Dist. No , 2003-Ohio-1339, at 22, 24. And, as you will see below, liens on public construction projects are secured not by real property but by public funds. B. Who Has the Right to Lien a Project? Every person who performed work or labor upon or furnishes material in furtherance of any improvement... to real estate through a contract with an owner, part owner or lessee (or their agent), and every person who as a subcontractor, laborer, or material supplier carried forward that work through an agreement with an original contractor or subcontractor, has a lien to secure payment therefor upon the improvement and all the interests... in the land or leasehold. ORC Suppliers obtain lien rights through various provisions relating to materials used on construction projects. A lien can include the value of the materials delivered to the project (even if then moved to another project), the value of rented equipment, and, to an extent, the value of purchased equipment. ORC (A)(1)-(4), (B), (C)(2). The term original contractor is defined to include a construction manager tasked with supervision only. ORC (F). And, ORC (J) defines the term improvement quite broadly. Page 3

4 This diagram illustrates lien entitlement in relation to the lines of contractual privity, which are often refered to as tiers. Private Project Lien Diagram Owner A L L T I E R S Original Contractor Subcontractor* Laborer Materialman* Subcontractor Laborer Materialman Subcontrator Laborer Materialman *Notice of Furnishing required from all subcontractors and suppliers. C. How Can Property Owners, Lenders, and Prime Contractors Protect Themselves? The Ohio statutory framework gives project owners an important tool that they must use to protect themselves from hidden liens. Key to the lien law framework is the idea of notice. In sum, the law gives laborers, suppliers, and subcontractors a lien right, but it also obliges them to provide notice so owners can protect themselves. The only way owners can make certain that they receive notice from all companies performing work on or providing materials to a project is through the Notice of Commencement. If an owner properly uses this tool, it can escape liability for the claims of subcontractors and suppliers that did not properly notify the owner of their contributions to the project. The Notice of Commencement also sets priorities to such an extent Page 4

5 that, in practice, lenders prepare and record the Notice of Commencement. The Notice of Commencement also helps subcontractors and suppliers by providing essential project information needed for their lien documents. If the owner, part owner or lessee fails to record the Notice of Commencement, the lender or original contractor may prepare and record the Notice of Commencement on behalf of the owner, part owner or lessee. ORC (N)(1). A contractor can only record the Notice of Commencement if the owner fails to record it within the latter of ten days after work starts or three days after the original contractor demands it. The owner, part owner or lessee also will be liable for all expenses incurred by the lender or original contractor in obtaining the information and in preparing and recording the Notice of Commencement. ORC (N)(2). If a lender or original contractor prepares and records the Notice of Commencement, then the Notice of Commencement must reflect this fact on its face. ORC (N)(4). The lender or original contractor will not be liable to the owner for any errors in the Notice of Commencement unless it was required by contract to file the Notice of Commencement on behalf of the owner, part owner or lessee. ORC (N)(3). The Notice of Commencement must be recorded for all projects with the exception of: (a) home construction contracts, (b) projects relating the oil and gas wells, or (c) projects where utility companies are owners, part owners or lessees. ORC (O), (C)(1), and (Q). 1. Required Contents of the Notice of Commencement Section (B) provides that the Notice of Commencement must contain all of the following information: (1) a complete legal description of the property subject to the improvement, which would be sufficient for purposes of conveyance; (2) a description of the improvement sufficient to allow lien claimants to identify the project; (3) the name, address, and capacity of the person or entity contracting for the improvement; (4) the name and address(es) of the fee owner(s) if the contracting party is a lessee or a land contract vendee; (5) the name and address of the owner s or lessee s designee for the project; (6) the names and address(es) of all original contractor(s); (7) the date the owner, part owner or lessee first executed a contract with each original contractor; (8) the name and address of all lenders providing financing for the improvements; (9) the names and addresses of all sureties on any bond guaranteeing payment of the original contractor s obligations under the contract for the improvements; and (10) the following statement: To Lien Claimants and Subsequent Purchasers: Take notice that labor or work is about to begin on or materials are about to be furnished for an improvement to the real property described in this instrument. A person having a mechanics' lien may preserve the lien by providing a notice of furnishing to the above-named designee and the above-named designee's original contractor, if any, and by timely recording an affidavit pursuant to section of the Revised Code. Page 5

6 A copy of this notice may be obtained upon making a written request by certified mail to the above-named owner, part owner, lessee, designee, or the person with whom you have contracted. ORC (B)(10). In addition, the Notice of Commencement must contain the name and address of the person preparing it and the owners, part owner or lessee (or their agent) must verify it in affidavit form. ORC (B)(11)-(12). A sample Notice of Commencement for a Private Project is provided as Exhibit A. 2. Errors in and Amendments to the Notice of Commencement An owner, part owner or lessee that includes incorrect information in the Notice of Commencement is liable to lien claimants for any resulting loss of lien rights or the actual expenses of preserving those rights, including attorney s fees, if the loss directly resulted from the claimant s reliance on the incorrect information. ORC (C). If a lien has incorrect information due to an error in the Notice of Commencement, then the lien claimant has the right to amend its lien. Id. If the error results in a material deviation from the statute s requirements, then the lien claimant will be relieved from the requirement of serving a Notice of Furnishing. See Clinton Electrical & Plumbing Supply, Inc. v. Airline Professionals Ass n, Twelfth Dist. No. CA , 2006-Ohio-1274, 8 (addressing a Notice of Commencement listing the owner as APA Teamsters Local 1224 when the actual owners was Airline Professionals Association, Teamsters Local 1224 ). Owners, part owners and lessees may amend a previously recorded Notice of Commencement in order to correct or add information. In addition, the owner, part owner or lessee has a duty to amend the Notice of Commencement to reflect the names of new original contactors, lenders or sureties not named in the original Notice of Commencement. ORC (A)(2). The amendment relates back to the recording date of the original Notice of Commencement. Id. Only one Notice of Commencement must be filed for each project. ORC (A)(2). If more than one Notice of Commencement is filed for the same project, then the latter Notice of Commencement is deemed to be an amendment to the original. Id. The effective date of an amendment to the original Notice of Commencement relates back to the original filing. Id. 3. Time and Manner of Recording the Notice of Commencement The Notice must be recorded by the office of the County Recorder in the county where the property subject to the improvement is situated, prior to performance of any labor or work or the furnishing of any material for the improvement. ORC (A)(1). Page 6

7 4. Effect of Failure to Record a Notice of Commencement A failure to record the Notice of Commencement has several adverse consequences for the owner, part owner or lessee. First, it suspends the requirement that all subcontractors and suppliers must serve a Notice of Furnishing, thereby increasing the risk of hidden liens. ORC (I). Second, it affects the determination of priorities of mechanic s liens on the project. ORC Third, it renders the owner, part owner or lessee potentially liable to lien claimants for actual costs and expenses incurred in gathering the information necessary to perfect a mechanic's lien claim on the project. ORC (K). Fourth, the owner, part owner or lessee is liable for the costs and expenses incurred by the original contractor or lender who exercise their statutory right to file a Notice of Commencement. ORC (N)(2). Fifth, the owner, part owner or lessee is liable to the original contractor for all expenses relating to a mechanic s lien claim that otherwise could have been avoided through proper payment if the Notice of Commencement had been filed. ORC (M)(1). 5. Posting the Notice of Commencement The owner, part owner, lessee or designee must post and maintain a copy of the Notice of Commencement in a conspicuous place on the project throughout the entire period of physical construction or improvement. ORC (G)(1). This does not apply to an improvement that is the subject of a home purchase contract. ORC (G)(2). If the owner fails to post the Notice of Commencement, then the original contractor has the right to make a written demand for posting. ORC (M)(1). The owner s failure to comply with the demand within ten days creates liability for all damages, costs and expenses relating to the filing of mechanic's liens which otherwise could have been avoided through proper payment. Id. An owner, part owner or lessee that fails to post the Notice of Commencement also is liable to any subcontractors, material suppliers or laborers for all actual expenses incurred by the lien claimant to gather the information otherwise provided by the Notice of Commencement. ORC (K). 6. Service of the Notice of Commencement The owner, part owner or lessee must serve a copy of the Notice of Commencement on all original contractors for the project. ORC (H). The owner, part owner or lessee also must serve a copy of the Notice of Commencement on all subcontractors and suppliers that serve a written demand for a copy of the Notice within ten days of receipt of the demand. The subcontractor s or supplier s request should be made by certified mail, return receipt requested. If anyone required to serve a Notice of Furnishing makes a request in writing on the owner or the owner s designee for a copy of the Notice of Commencement, the owner or owner s designee shall serve a copy of the Notice of Commencement within ten days. ORC (D). If the owner or owner s designee fails to serve the Notice of Commencement within ten days, the time within which the person must serve the Notice of Furnishing is extended until twenty-one days after the Notice of Commencement actually is served. ORC (J). Thus, even if there is no Notice of Commencement on a project when a person starts Page 7

8 to perform work, he should serve a written request for the Notice of Commencement to the owner or owner s designee. Then, the person will not have to continually search to see if the Notice of Commencement is subsequently filed in order to preserve lien rights for work performed after the Notice of Commencement is recorded. If the written request for the Notice of Commencement is directed to the contractor, it does not toll the time for serving the Notice of Furnishing, but the contractor is liable for all costs incurred to obtain the information contained in the Notice of Commencement. ORC (L). D. How Do Claimants Preserve and Perfect Their Lien Rights? 1. Obtain the Notice of Commencement All project participants who have the right to obtain a lien must obtain a copy of the Notice of Commencement if they are going to properly perfect their rights. This is because, as will be shown, the Notice of Commencement provides information that must be included in the Notice of Furnishing. A first-tier subcontractor or supplier may serve a written request for a copy of the Notice of Commencement to the original contractor, to the owner, part owner, lessee, or to the designee of the owner, part owner, or lessee. Lower-tier subcontractors and suppliers may serve a written request on the subcontractor with whom they are in privity of contract. ORC (E)-(F). If the original contractor or subcontractor fails to respond to the request in a timely manner, then it is liable to the requesting party for the actual expenses incurred as a result of having to obtain the information contained in the Notice of Commencement. ORC (L). If anyone required to serve a Notice of Furnishing makes a request in writing on the owner or the owner s designee for a copy of the Notice of Commencement, the owner or owner s designee shall serve a copy of the Notice of Commencement within 10 days. ORC (D). If the owner or owner s designee fails to serve the Notice of Commencement within 10 days, the time within which the person must serve the Notice of Furnishing is extended until 21 days after the Notice of Commencement actually is served. ORC (J). If the written request for the Notice of Commencement is directed to the contractor, it does not toll the time for serving the Notice of Furnishing, but the contractor is liable for all costs incurred to obtain the information contained in the Notice of Commencement. ORC (L). 2. Prepare the Notice of Furnishing a. Who Must Do So? If there is a Notice of Commencement, everyone except for the original contractor and laborers must serve a Notice of Furnishing if someone has recorded a Notice of Commencement. Page 8

9 ORC , (G)(exempting laborers) On the table above, those who must provide a Notice of Furnishing are identified in boxes with a double-lined frame. b. Required Contents Pursuant to section , the Notice of Furnishing must include: (a) the name and address of the owner, part owner or lessee or the named designee; (b) the name and address of the original contractor; (c) the name and address of the person or entity with whom the person supplying the Notice of Furnishing is in direct privity of contract; (d) a legal description sufficient to reasonably identify the property subject to the improvement; (e) the name and address of the person or entity supplying the Notice of Furnishing; (f) the name, capacity and address of the person executing the Notice on behalf of the lien claimant; (g) the date the Notice is executed; and (h) a verbatim, conspicuous recitation of the following statutory warning: WARNING TO OWNER: THIS NOTICE IS REQUIRED BY THE OHIO MECHANICS' LIEN LAW. IF YOU HAVE ANY QUESTIONS ABOUT YOUR RIGHTS AND DUTIES UNDER THESE STATUTES YOU SHOULD SEEK LEGAL ASSISTANCE TO PROTECT YOU FROM THE POSSIBILITY OF PAYING TWICE FOR THE IMPROVEMENTS TO YOUR PROPERTY. The Notice of Furnishing need not be in the form of a sworn affidavit, but it must substantially comply with the statutory form set forth in Section Exhibit B is a Notice of Furnishing taken from the statute. c. Time for Service of the Notice of Furnishing If a Notice of Commencement is filed prior to commencement of construction on the project, then the subcontractors and suppliers must serve their individual Notice of Furnishing within twenty-one (21) days after performing their first labor or work or furnishing of materials (or within the 21-days after the Notice of Commencement is served on them by the owner or owner s designee, if not served within 10 days of written request to owner or owner s designee, as discussed above) in order to preserve their lien rights for the entire value of their work and material. ORC (A). If a subcontractor or supplier serves a Notice of Furnishing more than twenty-one (21) days after they first begin work or furnish materials, the Notice of Furnishing will relate back twenty-one (21) days from the date of service. The late Notice of Furnishing will preserve the lien claim only for the value of work and materials provided during the relation back period and later. ORC (D)(2). If the Notice of Commencement is filed after construction commences, then subcontractors and suppliers can preserve their entire lien claim by serving their Notice of Furnishing within twenty-one (21) days after the Notice of Commencement is filed with the county recorder. ORC (I) and (A). Even if the subcontractors or suppliers fail to serve an Notice of Furnishing after the Notice of Commencement is recorded, the subcontractors and suppliers still have the right to a lien for work performed or materials Page 9

10 furnished before the Notice of Commencement was recorded (even without any service of a Notice of Furnishing). ORC (I). d. Manner of Service of the Notice of Furnishing What we call first tier subcontractors, meaning those subcontractors or suppliers that have a contract with an original contractor, are only required to serve their Notice of Furnishing on the owner, part owner or lessee, or its designee if there is one. ORC (A). Subcontractors or suppliers involved at any tier other than the first tier (i.e. their contract is with a subcontractor) must also serve their Notice of Furnishing on the original contractor. Id. ORC provides the methods of service for any document required to be served under Chapter 1311, including: (1) by the sheriff of the county in which the person to be served resides or maintains his or its principal place of business; (2) by certified or registered mail, overnight delivery, hand delivery, or any other method that includes written evidence of receipt ; and (3) by service on the Secretary of State, if the person to be served is a corporation. ORC (A). Service by certified mail is complete upon the date of mailing. ORC (B). If service is sent to an address listed in the Notice of Commencement, but is returned unclaimed or refused, service is complete when first attempted. Id. In addition, a notice is considered served (and service is complete on the date the notice is received) regardless of whether it was sent by the methods specified in Section (A) if the person acknowledges receipt or it can be proved by a preponderance of the evidence that the person actually received the notice. ORC (C). The notice is presumed to have been received three days after mailing, unless written acknowledgement provides proof to the contrary. Id. 3. Prepare, Record and Serve the Affidavit of Lien To perfect a lien on most private commercial projects, anyone in direct contractual privity with the owner, part owner or lessee generally only needs to record an Affidavit for Mechanic s Lien within 75 days of his last work on the project, and serve the owner s designee (or the owner, part owner or lessee, if no designee) with the lien within 30 days after it is recorded. ORC (B)(3) & The lien is valid for 6 years. ORC (C). a. Required Contents The Affidavit For Mechanic's Lien must contain the following information: (a) The amount due, over and above legal set-offs; 1 (b) a full legal description of the improved property subject to the lien; (c) the name and address of the person or entity with whom the lien claimant was in direct privity of contract; (d) the name of the owner, part owner or lessee, if known; (e) the name and address of the lien claimant; and (f) the first and last dates the lien claimant performed any labor or work or furnished materials to the project. The information must be verified 1 The affidavit need not state the amount of the set-off itself. Warne v. Bamfield, Fifth Dist. No CA-33, 2006-Ohio-850, at 19. Page 10

11 before a notary by the lien claimant or the claimant s agent. ORC (A). Exhibit C is a sample. The description of the property contained in the Affidavit must be in a form sufficient to describe the real property for purposes of conveyance, or contained in the instrument by which the owner, part owner or lessee took title.... ORC (B)(1) and (D). One Affidavit may be filed for unpaid wages on behalf of a group of laborers provided, however, that the claim of each individual laborer is itemized in the Affidavit. ORC (F). 2 b. Time for Recording and Service On commercial projects, the Affidavit for Mechanic s Lien must be recorded with the county recorder within 75 days of the lien claimant s last work on the project and served on the owner s designee (or the owner, part owner or lessee, if no designee) within 30 days after it is recorded. ORC (B)(3), If the Affidavit cannot be served as provided in , the lien claimant shall serve it by posting a copy in a conspicuous place on the premises of the improved property within 10 days after the expiration of the 30 days typically allowed for service. Id. On residential projects, the time for recording the lien is reduced to 60 days. ORC (B)(1). For oil and gas projects, the lien must be recorded within 120 days. ORC (B)(2). The work must be within the original contract scope of work (including punch-list work). Warranty work or additional work or materials provided under a separate contract will not extend the time for recording the lien on either commercial or residential projects. See Swim Rite Pool Co. v. Strausbaugh, Sixth Dist. No. S , 2006-Ohio-3612, at 21 (purchase of pool cover and reel was separate contract from installation and mechanic s lien was filed beyond 60-day limit and was invalid). Whether work performed or materials furnished are necessary to properly complete the contract scope of work (or an improper attempt to extend the time for filing the affidavit) is a question of fact. Id. at 13; Gilson v. Windows and Doors Showcase, LLC, Sixth Dist. Nos. F & F-05-24, 2006-Ohio-2921, at (later delivery of screens was pursuant to original contract that they would be stored for $20 charge and delivered at end of project, so lien was timely filed within 60 days of delivery of screens). c. A Note on the Computation of Time Under ORC 1.14, the time within which an act is required to be done excludes the first day and includes the last day. When the last day falls on Sunday or a legal holiday, the action may be done on the next succeeding day that is not Sunday or a legal holiday. Note that 1.14 does not provide an extension of time when the last day falls on a Saturday. Thus when the last 2 Wages is defined to include basic hourly rate of pay and all other contractually owed benefits. ORC (K). Page 11

12 day for filing or service of a lien falls on a Saturday, it should be filed or served on the preceding Friday. ORC 5.30 provides that, Every Saturday afternoon is a legal holiday, beginning at twelve noon and ending at twelve midnight. Thus, an argument can be made that, when the last day falls on a Saturday, which is by definition a legal holiday, a lien claimant is entitled to file on the next succeeding day that is not a Sunday or legal holiday. d. Amending the Affidavit The lien claimant has the right to amend the Affidavit to correct errors within 6 years from the date of filing it with the county recorder, but only if the error resulted from incorporating incorrect information from the Notice of Commencement. See ORC (C). Of course, a lien claimant always can file an amended lien if it is still within the statutory period for recording of the original Affidavit. E. How Can Owners and Contractors Respond to Liens? An owner, part owner or lessee has a right to make direct payment to any subcontractor or supplier that serves a Notice of Furnishing and may pay the claim of any laborer. ORC (B)(1). If the owner, part owner, or lessee pays the claimant, then there is a statutory right to a set-off or credit against the original contractor or subcontractor who employed the lien claimant. Id. The set-off or credit is in an amount equal to what was actually paid to the claimant. Id. An original contractor or subcontractor has a right to make direct payment to any subcontractor or supplier that serves a Notice of Furnishing and may pay the claim of any laborer. ORC (B)(2). If the original contractor or subcontractor pays the claimant, then there is a statutory right to a set-off or credit against the subcontractor who employed the lien claimant for the amount equal to what was actually paid to the claimant. Id. F. What is Required to Initiate a Foreclosure Lawsuit? ORC provides that any person holding a mechanic s lien pay proceed by petition against the owner and all other persons interested, either as lienholders or otherwise, in the land and obtain such judgment for the rent or sale thereof as justice and equity require. The court may allow reasonable attorney s fees to the prevailing party to be paid out of the fund realized for lien claimants. ORC Mechanic s liens are effective for 6 years from the date of recording the Affidavit for Mechanic's Lien with the county recorder. ORC (C). If an action is brought to enforce the lien within that time, then the lien continues in full force and effect until final adjudication. Id. If no action is taken to enforce the lien within the 6 year period, then the lien will be rendered void and title to the property will be cleared of the encumbrance. Page 12

13 G. How Are Lien Claimants Paid in a Foreclosure Action? 1. General Rules of Priority Three are three basic rules of priority for mechanic s liens. The first rule applies if no Notice of Commencement is recorded or if the lien claimant provided all of its work or materials before the recording of the Notice of Commencement. Under these circumstances, the lien claim will relate back to the date the first visible work or labor is performed or materials are furnished by the original contractor, subcontractor, supplier or laborer at the site of the improvement. ORC (A)(1). The second rule applies if the Notice of Commencement is filed prior to commencement of visible construction or if the lien claimant provides all of its work or materials after the filing of the Notice of Commencement. In these situations, the lien claim will relate back to the date of recording of the Notice of Commencement. ORC (A)(2). The third rule applies if a lien claimant provided work or materials both before and after the recording of the Notice of Commencement. In such circumstances, the lien has two effective dates. The work performed before recording the Notice of Commencement is effective as of the first visible work, the work performed after the Notice of Commencement is recorded is effective as of the recording of the Notice of Commencement. ORC (B)(1). In general, mechanic s liens on a project that have the same effective date (e.g., date of first visible work or date Notice of Commencement is recorded) have no priority among themselves. The mechanic's lien claimants share pro-rata in any revenue generated from the sale of the property to the extent that there is not enough proceeds to satisfy all lien claims in full. 2. Super Priority for Laborers If visible work commences prior to the recording of the Notice of Commencement and any liens are recorded with an effective date relating back to the first visible work, then the effective date for any laborer s lien is the date of first visible work. ORC (B)(3). Moreover, laborers liens have priority over all other mechanic s liens relating to the same improvement, regardless of whether the work was performed before or after the recording of the Notice of Commencement. ORC (D)(2). Laborer s liens for work performed both before and after the Notice of Commencement is recorded have priority as of the first visible work. ORC (B)(2). The lien claims of laborers, supplier and subcontractors to an original contactor or subcontractor are superior to any lien (already taken or to be taken) by such original contactor or subcontractor indebted to them for such labor, work or material. ORC (A). Page 13

14 3. Priority for Mortgages The rules of priority set forth above clearly require construction lenders and other mortgagees to record their interests in the property subject to the improvement (1) prior to the recording of the Notice of Commencement and (2) prior to the commencement of any visible work on the project if they want their mortgage interest to prime all mechanic s liens on the project. A construction mortgage or any other mortgage interest that is recorded after the Notice of Commencement generally will be subordinate to all mechanic's liens arising out of the construction project. 3 H. Differences for Residential and Oil and Gas Projects 1. Residential Distinctions Most of the requirements to perfect a lien on commercial projects apply to residential projects (one- or two-family dwelling or residential unit of a condominium that is used or intended to be used as a personal residence by the owner, part owner or lessee), with two notable exceptions. First, owners of existing residential property contracting for improvements to it are not required to record a Notice of Commencement. ORC (O). Second, the Affidavit for Mechanic s Lien must be recorded within 60 days of the last work on the project by the person claiming the lien. ORC (B)(1). In addition, as discussed in more detail below, residential owners can defeat any lien rights of contactors, subcontractors, suppliers or laborers by paying the original contractor in full, if the payment was made before the owner received a copy of the mechanic s lien. ORC (B)(1). A contactor, subcontractor, supplier, laborer or lower-tier subcontractor may claim a lien for work or labor performed or material furnished under a home construction, improvement or purchase contract, but the lien claim is limited to the remaining amount the owner owes the original contractor at the time the lien is filed. ORC (B)(2). The amount due is the unpaid balance under the home construction or home purchase contact, minus the cost to complete the contract according to its terms and conditions, including any warranty or repair work. ORC (B)(2). If the residential owner already paid the original contractor in full before a mechanic s lien is filed, then the owner may avoid the lien completely by filing an affidavit with the county recorder that states that the original contractor had been paid in full. ORC (B)(1). Before making any payments to an original contactor on a residential project, lenders are required to obtain an affidavit from the original contractor that the original contractor has paid in full for all labor and work performed and for all materials furnished by the original contractor, 3 There is an exception to this general rule for construction mortgages that strictly comply with the requirements of ORC Page 14

15 all subcontractors, suppliers, and laborers prior to the date of closing of the purchase or during and prior to the payment period, except unpaid claims specifically set forth by the original contactor and identified as to claimant and amount, and that no other claims exist. ORC (B)(4). In the event of a payment dispute between the original contractor and a subcontractor, supplier or laborer, the lender is required to pay to the original contractor the amount withheld when the time for filing a lien by the subcontractor, supplier or laborer has expired without a lien being recorded (or when the claim has been paid, bonded or released). ORC (B)(8). 2. Oil and Gas Distinctions Typically, the same parties who are entitled to a commercial or residential lien may also assert a lien on an oil and gas project. ORC (A). Activities include digging, drilling, boring, operating, completing or repairing a well or injection well, or altering, repairing, or constructing any oil derrick, oil tank, or leasehold production pipeline. Id. A Notice of Commencement is not required. ORC (C)(1). Nor is a Notice of Furnishing. ORC (C)(2). Claimants have 120 days to record their lien. ORC (B)(2). Owners can request an affidavit from the contractor that identifies subcontractors and suppliers. If the contractor fails to comply, it will lose its lien rights. The owner can then insist upon receipt of a lien waiver or pay direct otherwise and exercise a right of set-off. ORC (C)(5). The subcontractor or supplier may serve the owner with a notice in writing that includes certain information. Doing so gives the owner the right to pay direct. ORC (C)(6)(c). The lien can attach to the oil or gas lease or the mineral estate, the oil and gas produced, the proceeds from their sale, or the materials located on the project and used in connection with the work. ORC (B). I. Release of Liens ORC provides damages for neglect or refusal to release a mechanic's lien within 30 days after it is satisfied. If the lienholder fails to release the lien, he is liable to the owner, part owner or lessee for all resulting damages, not exceeding the amount of the lien and costs. II. Mechanic s Liens on Public Projects A. Scope of this Section The principal remedy available to a claimant on a public project is a mechanic s lien, referred to by some as an attested account claim. This latter reference is historic and nature, and Page 15

16 comes from the pre-1991 version of the statute that required claimants to itemize their claim in the form of an account. This section focuses on the procedure for enforcing mechanic s lien rights on a public project from the claimant s perspective, with discussion of other parties responsibilities to the extent that they impact that procedure. Public-project lien statutes are interpreted separately from private project lien statutes. In re William Cargile Contractor, Inc. (Bankr. S.D. Ohio 1993), 151 B.R A claimant may also have a claim against a payment bond, but that remedy is discussed elsewhere in these materials. B. What is a Lien? In the context of public projects, the term lien is somewhat of a misnomer. While the statutes governing public project liens are in a section of the code discussing mechanic s liens, the right created by those statutes is not a lien right. Traditionally, lien rights relate to real property, and describe a right to property that is not voluntarily granted by the project owner. For examples, think of tax liens, judgment liens, and private-project mechanic s liens. On a public project, the lien granted is against the public funds held in the treasury of the public authority for the purpose of compensating the principal contractor. Ohio Revised Code ( ORC ) The realty owned by the public authority cannot be made subject to a lien. While this seems like less security, keep in mind that public authorities are required to have sufficient funds to pay the value of the contract, and are required to specifically earmark those funds for that project. Thus, so long as the fund has not been fully disbursed, the code provides for security in a fund that will be in place. However, contractors should be aware that if the public authority has already disbursed all of the funds before the Affidavit of Lien is filed, there is no claim. L.E. Myers Co., High Voltage Systems Div. v. Jordano Elec. Co. (1998) 47 Ohio App.3d 132, 547 N.E.2d 1014, motion to certify overruled, motion overruled 38 Ohio St. 3d 717, 533 N.E.2d 787. Thus, potential claimants whose work concludes near the end of a project should move quickly to protect their rights. The law s general purpose is to protect those whose claims accumulate daily and who have no other means to protect themselves. Lee Turzillo Contracting Co. v. Cincinnati Metropolitan Housing Authority (1967) 10 Ohio St. 2d 5, 225 N.E. 2d 255. C. What is a Public Project? Under ORC , a public improvement is: [A]ny construction, reconstruction, improvement, enlargement, alteration, demolition, or repair of a building, highway, drainage system, water system, road, street, alley, sewer, ditch, sewage disposal plant, water works, and any other structure or work of any nature by a public authority. And, under the same statute, a public authority is: Page 16

17 [T]he state, and a county, township, municipal corporation, school district, or other political subdivision of the state, and any public agency, authority, board, commission, instrumentality, or special district of or in the state or a county, township, municipal corporation, school district, or other political subdivision of the state, and any officer or agent thereof. Even with these straightforward definitions, it is not always easy to tell when a project is public or private. For example, when the City of Cincinnati wanted to redevelop housing in its Over-the-Rhine district, it transferred ownership of eight parcels to a developer, who in turn agreed to improve the homes on the land through a loan from the City. The City retained contractual oversight, imposed its quality standards, and had the right to a share of the potential profits. When a subcontractor was not paid, it pursued a public-project lien claim under ORC Ohio s Tenth District Court of Appeals determined that even though the City did not own the property, it was a public project because the developer was working as the City s agent under the definition cited above. City of Cincinnati v. Scheer & Scheer Dev., 2006 Ohio 1221, P27, 2006 Ohio App. LEXIS 1142 (Ohio App. 10 Dist., 2006). D. Who is Vested with Public Project Lien Rights? The Code vests the following parties with public project lien rights: Any subcontractor, supplier, or laborer who is performing or has performed labor or work or is furnishing or has furnished material for any public improvement provided for in a contract between the public authority and a principal contractor, and under a contract between the subcontractor, supplier, or laborer and a principal contractor or subcontractor.... ORC A principal contractor is any person who undertakes to construct, alter, erect, improve, repair, demolish, remove, dig, or drill any part of any public improvement under a contract with a public authority. ORC (F) (emphasis added). Thus, a subcontractor, supplier or laborer has lien rights if it has provided its services on a public improvement through a contract with the principal contractor or one of the project s subcontractors. Thus, the code provides lien rights for every tier of subcontractor, laborer or supplier. However, the principal contractor does not have the right to a lien on a public project. Material suppliers are only entitled to a lien on a public project if the materials they supplied were intended to be used in the course of the public improvement at issue, were incorporated into the public improvement or consumed to construct that improvement, were fabricated specifically for that improvement and are not readily resalable, were used for the improvement or the operation of machinery for the improvement, or were tools or equipment used on the improvement. ORC Page 17

18 Public Project Lien Diagram Public Authority Principal Contractor A L L T I E R S Subcontractor Laborer Materialman Subcontractor* Laborer Materialman* Subcontrator Laborer Materialman *Notice of Furnishing Required from Second or Lower Tier Subcontractors and Suppliers E. How Does a Claimant Perfect its Lien Rights? 1. Gather Initial Data: The Notice of Commencement and Bond Information Before commencing work, the claimant should obtain a copy of the Notice of Commencement. The Notice of Commencement is to be prepared by the public authority and must contain information that is essential to the lien claimant, including identification of the project, the public entity and its representative, the principal contractor, the principal contractor s surety, and the date of the prime contract. ORC If information in the Notice of Commencement is inaccurate or the entity does not provide a copy, the claimant s rights will not be prejudiced. ORC (C), (D). The public entity is required to prepare this document prior to commencement and make this document available to the public upon request. ORC (A). Unlike the owner of a Page 18

19 private project, a public authority is not required to record or post the Notice of Commencement. Principal contractors and their subcontractors are also required to provide the identity of the public authority and the principal contractor when they enter into contracts, and if they fail to do so they are liable for the resulting damages. ORC (C)-(E). The claimant should also obtain a copy of the payment bond for all contractors above it in the contractual lines of privity. A best practice is to collect all of this information on a project data sheet for later use. Also, one person at the company should be responsible for recording the deadlines discussed below that arise in relation to the first day of work and the last day of work. Make sure these very important dates and deadlines are given a prime location on your project data sheet and on your calendars. Even with this information in hand, a potential claimant should take additional steps to protect its interests. Payment bond and mechanic s lien claims are remedial in nature they protect the subcontractor and supplier only after there has been a problem with payment. The best course of action is to fully investigate the company with whom you will be contracting to guard against the risk of insolvency and to fully review the contract to be sure that your interests are protected. 2. Prepare and Serve the Notice of Furnishing For those claimants who are in the designated class, service of a Notice of Furnishing is mandatory. ORC (A)(1). Furthermore, the statutory requirements will be strictly enforced. Lee Turzillo, 10 Ohio St. 2d 5. Unless a subcontractor or supplier has a contract directly with the principal contractor, that subcontractor or supplier is required to prepare and serve a Notice of Furnishing within twenty-one (21) days of the first day it provided labor or materials. ORC (A)(1). Note that a laborer is not subject to this requirement. ORC (F). If the Notice of Furnishing is served after more than twenty-one (21) days from the first work, it is not invalid; instead, the claim is limited to the value of work the claimant provided in the preceding twenty-one days. ORC (A)(2). Section (B) provides that the Notice of Furnishing substantially follow the form set out in that provision, which is set forth in Exhibit D to these materials. The Notice of Furnishing is to be served on the principal contractor whose contract with the public authority is the contract under which the subcontractor or supplier is performing labor or work or furnishing materials. ORC (A)(1). Since proof of such service is so important, the claimant should serve the Notice of Furnishing by certified mail. The Notice of Furnishing should be served on the principal contractor at the addresses listed in the Notice of Commencement or in the pertinent subcontract. Be sure to save the green card the post office gives you upon sending the notice and the green card you receive in the mail proving that recipient received the notice. Page 19

20 Make absolutely sure that your certified letter is post-marked on or before the twentyfirst day. If you are close to the deadline, take it to the post office in person and ask them to stamp it in front of you. If the Notice of Furnishing does not provide the information required by the statute, is not served on the proper party, or is not served within twenty-one days of any work, the notice will be invalid and the claimant will lose its lien rights. While the claimant will still have contractual rights against the contractor with whom it has an agreement, these rights are not secured by a source of payment. If the contractor is not paying, the risk that the contractor will be uncollectible is distinct. 3. Prepare and Serve the Affidavit of Lien and Affidavit of Service of the Notice of Furnishing. To perfect its lien rights, a claimant must properly prepare and serve an Affidavit of Lien. If that party is also required to prepare and serve a Notice of Furnishing, the Affidavit of Lien must include an Affidavit of Service of the Notice of Furnishing. ORC A properly composed Affidavit of Lien must be served within 120 days of the date the claimant last provided work, materials, or labor to the project. ORC This deadline is mandatory. The Affidavit of Lien must contain the amount due and unpaid, the last date the claimant provided work, materials, or labor to the project, a statement of all credits or offsets, and the address of the claimant. ORC A sample Affidavit of Lien is attached as Exhibit E. It is written to include an Affidavit of Service. Laborers may use an agent to prepare an Affidavit of Lien, and that lien may include a claim from a number of laborers so long as the affidavit is itemized. ORC The Affidavit of Lien and, if required, the Affidavit of Service, must be served upon the representative of the public authority at the address set forth in the Notice of Commencement. ORC Again, since proof of service of the Affidavit of Lien and Affidavit of Service are conditions precedent to enforcement, these documents should be served via certified mail, with care taken to ensure that the date of mailing is compliant and that the evidence of mailing and receipt are preserved for trial, which can be months or years later. Claimants who worked under a first-tier subcontractor, must, within twenty (20) days of service on the owner, provide that subcontractor with a copy of the lien affidavit. ORC Otherwise, the lien is invalid. Id. To keep things simple, the second-tier claimant should just serve the first-tier subcontractor at the same time and in the same manner as the public authority. 4. Record the Affidavit of Lien Page 20

Texas Lien & Bond Law Booklet

Texas Lien & Bond Law Booklet Texas Lien & Bond Law Booklet Presented by: Jason C. Spencer Telephone: (512) 900-3032 Facsimile: (512) 900-3082 jspencer@andrewsmyers.com www.andrewsmyers.com AUTHOR BIO Jason C. Spencer is a shareholder

More information

TEXAS OTHER NOTICES. Not Required OTHER NOTICES. Written notice to owner or. later date of (1) 1 year after the with prime contractor)

TEXAS OTHER NOTICES. Not Required OTHER NOTICES. Written notice to owner or. later date of (1) 1 year after the with prime contractor) PRIVATE WORKS RIGHTS AVAILABLE: Mechanic's Lien 5/13 Pub Date Page 1 of 8 Texas Property Code Title 5; Chapter 53 (liens) TPC 36.25.010 et seq. Original Contractor Lien Affidavit: Record Residential Construction:

More information

CONNECTICUT MECHANIC S LIEN LAW

CONNECTICUT MECHANIC S LIEN LAW CONNECTICUT MECHANIC S LIEN LAW 2018-2019 Go to: Connecticut Mechanic s Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How

More information

A G & R ABDULAZIZ, GROSSBART & RUDMAN

A G & R ABDULAZIZ, GROSSBART & RUDMAN A G & R ABDULAZIZ, GROSSBART & RUDMAN PRIVATE WORKS MECHANIC S LIEN, STOP NOTICE AND BOND CHECKLIST I. WHAT IS A MECHANIC S LIEN?: A. A Mechanic s Lien is a lien on real estate that has been improved.

More information

(a) Mailing the notice by certified or registered mail to the owner or reputed owner; or

(a) Mailing the notice by certified or registered mail to the owner or reputed owner; or RCW 60.04.031 Notices -- Exceptions. (1) Except as otherwise provided in this section, every person furnishing professional services, materials, or equipment for the improvement of real property shall

More information

GENERAL: WITNESSETH: That the said Contractor and the said District, for consideration hereinafter named agree as follows: DESCRIPTION OF WORK:

GENERAL: WITNESSETH: That the said Contractor and the said District, for consideration hereinafter named agree as follows: DESCRIPTION OF WORK: GENERAL: This Contract made and entered into this day of, 2013, by and between the Sundown Sanitary Sewer District, hereinafter called "District", and, hereinafter called "Contractor", duly authorized

More information

AC SUPPLY COMPANY, INC. TEXAS COMMERCIAL LIEN SEMINAR. Subcontractor and Sub-Subcontractor Forms. Private Commercial Construction Projects

AC SUPPLY COMPANY, INC. TEXAS COMMERCIAL LIEN SEMINAR. Subcontractor and Sub-Subcontractor Forms. Private Commercial Construction Projects AC SUPPLY COMPANY, INC. TEXAS COMMERCIAL LIEN SEMINAR Subcontractor and Sub-Subcontractor Forms Private Commercial Construction Projects Presented by: Bradley H. Rice DECKER, JONES P.C. 2000 Burnett Plaza

More information

VERMONT MECHANIC S LIEN LAW

VERMONT MECHANIC S LIEN LAW VERMONT MECHANIC S LIEN LAW 2018-2019 Go to: Vermont Mechanics Lien Forms More Info: www.nationallienlaw.com Section Contents Vermont Mechanic s Lien Who is Entitled to a Lien? When to File/Record Where

More information

The Construction Lien Act Liens, Trusts and Rights to Information

The Construction Lien Act Liens, Trusts and Rights to Information The Construction Lien Act Liens, Trusts and Rights to Information Michael Swartz WeirFoulds LLP Ontario Association of Architects 2017 Admission Course May 26, 2017 Overview What we ll cover The Construction

More information

NEW HAMPSHIRE MECHANIC S LIEN LAW 2017

NEW HAMPSHIRE MECHANIC S LIEN LAW 2017 NEW HAMPSHIRE MECHANIC S LIEN LAW 2017 Go to: New Hampshire Mechanic s Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How

More information

REVOLVING CREDIT MORTGAGE

REVOLVING CREDIT MORTGAGE REVOLVING CREDIT MORTGAGE WHEN RECORDED, MAIL TO: 1 2 3 PARCEL ID NUMBER: 4 SPACE ABOVE THIS LINE FOR RECORDER'S USE THIS MORTGAGE CONTAINS A DUE-ON-SALE PROVISION AND SECURES INDEBTEDNESS UNDER A CREDIT

More information

WEST VIRGINIA MECHANIC S LIEN LAW 2017

WEST VIRGINIA MECHANIC S LIEN LAW 2017 WEST VIRGINIA MECHANIC S LIEN LAW 2017 Go to: West Virginia Mechanics Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How

More information

CONSTRUCTION CONTRACT RIDER

CONSTRUCTION CONTRACT RIDER CONSTRUCTION CONTRACT RIDER In connection with the work at, Massachusetts (the Development ) to be performed by (the Contractor ) pursuant to the Construction Contract dated, 20 between the Contractor

More information

Enforcing a Mechanics Lien in Nevada

Enforcing a Mechanics Lien in Nevada Prepared by John E. Bragonje Lewis Roca Rothgerber Christie LLP 3993 Howard Hughes Parkway, Suite 600 Las Vegas, Nevada 89169 jbragonje@lrrc.com (702) 474-2625 Enforcing a Mechanics Lien in Nevada This

More information

1 Exam Prep Business Procedures Florida Lien Law Practice Test

1 Exam Prep Business Procedures Florida Lien Law Practice Test 1 Exam Prep Business Procedures Florida Lien Law Practice Test Part 1 1. Furnished material as covered by the Construction Lien Law includes. A. Supplied materials included in the improvement, excluding

More information

Washington University in St. Louis

Washington University in St. Louis Washington University in St. Louis Construction Terms and Conditions A. AGREEMENT. The Purchase Order, these Terms and Conditions, any special conditions, Owner s Policies, Design Standards and Insurance

More information

Utah Preconstruction and Construction Lien Law

Utah Preconstruction and Construction Lien Law Utah Preconstruction and Construction Lien Law Chapter Survey What is a Lien? Who is Entitled to a Lien? State Construction Registry Program Notice of Retention Notice of Commencement Preliminary Notice

More information

Title 33: PROPERTY. Chapter 9: MORTGAGES OF REAL PROPERTY. Table of Contents

Title 33: PROPERTY. Chapter 9: MORTGAGES OF REAL PROPERTY. Table of Contents Title 33: PROPERTY Chapter 9: MORTGAGES OF REAL PROPERTY Table of Contents Subchapter 1. GENERAL PROVISIONS... 3 Section 501. FORMS... 3 Section 501-A. "POWER OF SALE"... 3 Section 502. ENTRY BY MORTGAGEE...

More information

SUMMARY OF MECHANICS LIEN LAW FOR NEW HAMPSHIRE. Section Contents Pre-lien Notice(s)

SUMMARY OF MECHANICS LIEN LAW FOR NEW HAMPSHIRE. Section Contents Pre-lien Notice(s) SUMMARY OF MECHANICS LIEN LAW FOR NEW HAMPSHIRE Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic s Lien Who

More information

A Guide To Construction Liens In New Jersey

A Guide To Construction Liens In New Jersey Portfolio Media. Inc. 111 West 19th Street, 5th floor New York, NY 10011 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com A Guide To Construction Liens In New Jersey

More information

Louisiana Mechanics Lien Law

Louisiana Mechanics Lien Law Louisiana Mechanics Lien Law Chapter Survey What is a Lien? Who is Entitled to a Lien? Notice of Contract Priority Notice of Termination of the Work Statement of Claim or Privilege Time in Which to Foreclose

More information

SUMMARY OF MECHANICS LIEN LAW FOR MICHIGAN. With Changes for Name of Notice Who Must Use This Notice When How to Serve Verified or notarized?

SUMMARY OF MECHANICS LIEN LAW FOR MICHIGAN. With Changes for Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? SUMMARY OF MECHANICS LIEN LAW FOR MICHIGAN With Changes for 2013 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic

More information

Deed of Trust. a resident of the Commonwealth of Virginia, whose full residence or business address is

Deed of Trust. a resident of the Commonwealth of Virginia, whose full residence or business address is "THIS DEED OF TRUST SHALL NOT, WITHOUT THE CONSENT OF THE SECURED PARTY HEREUNDER, BE SUBORDINATED UPON THE REFINANCING OF ANY PRIOR MORTGAGE." Return To: Tax Map Reference #: RPC/Parcel ID #: Prepared

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

CDBG/HOME CONTRACT DOCUMENTS NEW HOUSING CONSTRUCTION

CDBG/HOME CONTRACT DOCUMENTS NEW HOUSING CONSTRUCTION CDBG/HOME CONTRACT DOCUMENTS NEW HOUSING CONSTRUCTION 2013 CDBG/HOME HOUSING NEW CONSTRUCTION CONTRACT THIS CONSTRUCTION CONTRACT is made and entered into this day of 2013, by and between, (marital status),

More information

SUMMARY OF MECHANICS LIEN LAW FOR IDAHO. Reviewed Through Section Contents Mechanic s Lien

SUMMARY OF MECHANICS LIEN LAW FOR IDAHO. Reviewed Through Section Contents Mechanic s Lien SUMMARY OF MECHANICS LIEN LAW FOR IDAHO Reviewed Through 2011 Section Contents Mechanic s Lien Who is Entitled to a Lien? When to File/Record Where to File/Record How to Serve Amount of Lien Property Subject

More information

Construction Law: Greensboro Builders Association Remodelers Counsel

Construction Law: Greensboro Builders Association Remodelers Counsel Construction Law: Greensboro Builders Association Remodelers Counsel February 25, 2010 J. Patrick Haywood Carruthers & Roth, P.A. 235 N. Edgeworth Street Greensboro, NC 27401 Direct Line: (336) 478-1177

More information

CONSTRUCTION CLAIMS DISCLOSURE (NRS )

CONSTRUCTION CLAIMS DISCLOSURE (NRS ) CONSTRUCTION CLAIMS DISCLOSURE (NRS 113.135) This Construction Claims Disclosure is made as required by NRS 113.135 in contemplation of a Purchase and Sale Agreement (the "Agreement") which may be entered

More information

The following set of additional terms and conditions form part of Canadian Imperial Bank of Commerce. Contents

The following set of additional terms and conditions form part of Canadian Imperial Bank of Commerce. Contents Page 1 of 23 Consumer General Collateral Mortgage Additional Terms and Conditions The following set of additional terms and conditions form part of Canadian Imperial Bank of Commerce. Contents 1. Definitions...

More information

American Land Title Association Revised 10/17/92 Section II-1 POLICY OF TITLE INSURANCE. Issued by BLANK TITLE INSURANCE COMPANY

American Land Title Association Revised 10/17/92 Section II-1 POLICY OF TITLE INSURANCE. Issued by BLANK TITLE INSURANCE COMPANY POLICY OF TITLE INSURANCE Issued by BLANK TITLE INSURANCE COMPANY SUBJECT TO THE EXCLUSIONS FROM COVERAGE, THE EXCEPTIONS FROM COVERAGE CONTAINED IN SCHEDULE B AND THE CONDITIONS AND STIPULATIONS, BLANK

More information

Consumer General Collateral Mortgage Standard Charge Terms Land Registration Reform Act

Consumer General Collateral Mortgage Standard Charge Terms Land Registration Reform Act Page 1 of 20 Consumer General Collateral Mortgage Standard Charge Terms Land Registration Reform Act Filed By: Canadian Imperial Bank of Commerce Filing Number: 200816 Filing Date: August 8, 2008 The following

More information

PROPERTY MANAGEMENT AGREEMENT Sundial Real Estate 263 West 3 rd Place Mesa, AZ (480) Office (480) Fax

PROPERTY MANAGEMENT AGREEMENT Sundial Real Estate 263 West 3 rd Place Mesa, AZ (480) Office (480) Fax PROPERTY MANAGEMENT AGREEMENT Sundial Real Estate 263 West 3 rd Place Mesa, AZ 85201 (480)966-2170 Office (480)969-4006 Fax THIS AGREEMENT is made as of the day of, 20 between (hereinafter called Owner

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor City, Zip Work Phone Number: Cell Phone Number: Fax Number: Email

More information

NORTH CAROLINA SUPERIOR COURT JUDGES FALL CONFERENCE. October 20, 2010 CONSTRUCTION LIEN AND BOND LAW BASICS FOR THE TRIAL JUDGE

NORTH CAROLINA SUPERIOR COURT JUDGES FALL CONFERENCE. October 20, 2010 CONSTRUCTION LIEN AND BOND LAW BASICS FOR THE TRIAL JUDGE NORTH CAROLINA SUPERIOR COURT JUDGES FALL CONFERENCE October 20, 2010 CONSTRUCTION LIEN AND BOND LAW BASICS FOR THE TRIAL JUDGE R. Harper Heckman hheckman@nexsenpruet.com Nexsen Pruet, PLLC 701 Green Valley

More information

WHO'S ON FIRST? NOTHING FUNNY ABOUT LIENS FOR LENDERS

WHO'S ON FIRST? NOTHING FUNNY ABOUT LIENS FOR LENDERS WHO'S ON FIRST? NOTHING FUNNY ABOUT LIENS FOR LENDERS Banking, Bankruptcy & Creditors' Rights Law Practice Group June 7, 2017 Author: Joseph M. Ammar Direct: (269) 226-8845 jammar@plunkettcooney.com Unlike

More information

DEED OF TRUST. a resident of the Commonwealth of Virginia, whose full residence or business address is. , and

DEED OF TRUST. a resident of the Commonwealth of Virginia, whose full residence or business address is. , and "THIS DEED OF TRUST SHALL NOT WITHOUT THE CONSENT OF THE SECURED PARTY HEREUNDER BE SUBORDINATED UPON THE REFINANCING OF ANY PRIOR MORTGAGE." Return To: Tax Map Reference #: Prepared by: RPC/Parcel ID

More information

Mechanic s Liens in Practice (Subcontractor Rights) (NC)

Mechanic s Liens in Practice (Subcontractor Rights) (NC) Resource ID: w-016-4869 Mechanic s Liens in Practice (Subcontractor Rights) (NC) NEALE T. JOHNSON AND MICHAEL D. JEFFERSON, FOX ROTHSCHILD LLP, WITH PRACTICAL LAW REAL ESTATE Search the Resource ID numbers

More information

Montana Construction Lien Laws JANUARY 14 TH :00 1:00PM MBIA ONLINE CLASSROOM WEBINAR

Montana Construction Lien Laws JANUARY 14 TH :00 1:00PM MBIA ONLINE CLASSROOM WEBINAR Montana Construction Lien Laws JANUARY 14 TH 2010 12:00 1:00PM MBIA ONLINE CLASSROOM WEBINAR Instructor Bruce Spencer, Shareholder, Smith Law Firm J.D. University of Oregon 1992 Areas of practice include:

More information

Form 3928 ( ) LAND TITLES ACT (ALBERTA) SET OF STANDARD FORM MORTGAGE TERMS COLLATERAL MORTGAGE (PERSONAL LENDING)

Form 3928 ( ) LAND TITLES ACT (ALBERTA) SET OF STANDARD FORM MORTGAGE TERMS COLLATERAL MORTGAGE (PERSONAL LENDING) LAND TITLES ACT (ALBERTA) SET OF STANDARD FORM MORTGAGE TERMS COLLATERAL MORTGAGE (PERSONAL LENDING) TABLE OF CONTENTS SECTION 1 TERMS YOU NEED TO KNOW...1 SECTION 2 - HOW THE MORTGAGE WORKS...4 SECTION

More information

HAWAII MECHANIC S LIEN LAW

HAWAII MECHANIC S LIEN LAW HAWAII MECHANIC S LIEN LAW 2018-2019 Go to: Hawaii Mechanic s Lien Forms More Info: www.nationallienlaw.com Section Contents Hawaii Mechanic s Lien Who is Entitled to a Lien? When to File/Record Where

More information

American Land Title Association Revised 10/17/92 Section II-2

American Land Title Association Revised 10/17/92 Section II-2 POLICY OF TITLE INSURANCE Issued by BLANK TITLE INSURANCE COMPANY SUBJECT TO THE EXCLUSIONS FROM COVERAGE, THE EXCEPTIONS FROM COVERAGE CONTAINED IN SCHEDULE B AND THE CONDITIONS AND STIPULATIONS, BLANK

More information

STANDARD MORTGAGE TERMS. Filed By: CMLS Financial Ltd. Filing Date: February 8, Filing Number: MT121004

STANDARD MORTGAGE TERMS. Filed By: CMLS Financial Ltd. Filing Date: February 8, Filing Number: MT121004 STANDARD MORTGAGE TERMS Filed By: CMLS Financial Ltd. Filing Date: February 8, 2013 Filing Number: MT121004 These STANDARD MORTGAGE TERMS shall be deemed to be included in every Mortgage which incorporates

More information

Land Registration Reform Act. Filing No filed by CMLS Financial Ltd. STANDARD CHARGE TERMS

Land Registration Reform Act. Filing No filed by CMLS Financial Ltd. STANDARD CHARGE TERMS Land Registration Reform Act Filing No. 201304 filed by CMLS Financial Ltd. STANDARD CHARGE TERMS These STANDARD CHARGE TERMS shall be deemed to be included in every Charge/Mortgage which refers to them

More information

SUBCONTRACT CONSTRUCTION AGREEMENT

SUBCONTRACT CONSTRUCTION AGREEMENT SUBCONTRACT CONSTRUCTION AGREEMENT THIS SUBCONTRACT CONSTRUCTION AGREEMENT, made and executed this day of, 20, by and between SHERWOOD CONSTRUCTION, INC (hereinafter referred to as "Contractor"), and (hereinafter

More information

Land Registration Reform Act

Land Registration Reform Act Page 1 Land Registration Reform Act Set of Standard Charge Terms Variable Rate Page 2 TABLE OF CONTENTS Land Registration Reform Act...1 TABLE OF CONTENTS...2 SECTION 1 TERMS YOU NEED TO KNOW...4 SECTION

More information

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT This Equipment Purchase Agreement ( Agreement ) is entered into this day of, 20, by and between the Western Riverside Council of Governments,

More information

OHIO MECHANIC S LIEN LAW Reviewed Thru Section Contents Pre-lien Notice(s)

OHIO MECHANIC S LIEN LAW Reviewed Thru Section Contents Pre-lien Notice(s) OHIO MECHANIC S LIEN LAW Reviewed Thru 2012 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic s Lien Who is

More information

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor Assumes Risk of Owner Payment) The original text

More information

DEVELOPER EXTENSION AGREEMENT

DEVELOPER EXTENSION AGREEMENT DEVELOPER EXTENSION AGREEMENT SILVER LAKE WATER DISTRICT APPLICATION AND AGREEMENT TO CONSTRUCT EXTENSION TO DISTRICT SYSTEM Project: Developer: The undersigned, Developer (also referred to as Owner )

More information

SUMMARY OF MECHANICS LIEN LAW FOR KANSAS. with Changes in 2011

SUMMARY OF MECHANICS LIEN LAW FOR KANSAS. with Changes in 2011 SUMMARY OF MECHANICS LIEN LAW FOR KANSAS with Changes in 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic

More information

TABLE OF CONTENTS. A. Introduction: The Nature of a Lien B. The Advantages of a Lien C. Only One Set of Lien Laws... 9

TABLE OF CONTENTS. A. Introduction: The Nature of a Lien B. The Advantages of a Lien C. Only One Set of Lien Laws... 9 TABLE OF CONTENTS Preparing and Filing a Lien... 1 A. Introduction: The Nature of a Lien... 1 B. The Advantages of a Lien... 5 C. Only One Set of Lien Laws... 9 D. Establishing Your Right to Lien... 13

More information

OHIO. Breach of Contract. Breach of Contract

OHIO. Breach of Contract. Breach of Contract Big 10 Construction & Surety Law CLE OHIO Construction Contracting Without Borders Peter W. Hahn Dinsmore & Shohl, LLP Columbus, Ohio Breach of Contract Claims by Contractor Standard No different from

More information

CONTRACTOR AND SUBCONTRACTOR PAYMENT ACT Act of Feb. 17, 1994, as amended May 21, 2018 AN ACT

CONTRACTOR AND SUBCONTRACTOR PAYMENT ACT Act of Feb. 17, 1994, as amended May 21, 2018 AN ACT CONTRACTOR AND SUBCONTRACTOR PAYMENT ACT Act of Feb. 17, 1994, as amended May 21, 2018 AN ACT Requiring timely payment to certain contractors and subcontractors; and providing remedies to contractors and

More information

DEED OF TRUST (Assumable Not Due on Transfer)

DEED OF TRUST (Assumable Not Due on Transfer) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 The printed portions of this form, except

More information

Blueprint. for Design Professionals September 2011 Volume 2 Issue 2. What do you do when served with a lawsuit?

Blueprint. for Design Professionals September 2011 Volume 2 Issue 2. What do you do when served with a lawsuit? Blueprint for Design Professionals September 2011 Volume 2 Issue 2 Welcome to our third edition of Blueprint For Deisgn Professionals. The articles for this issue provide a primer for the litigation process

More information

NC General Statutes - Chapter 45 Article 9 1

NC General Statutes - Chapter 45 Article 9 1 Article 9. Instruments to Secure Equity Lines of Credit. 45-81. Definitions. The following definitions apply in this Article: (1) Authorized person. Any borrower; the legal representative of any borrower;

More information

CHAPTER 244 FORECLOSURE AND REDEMPTION OF MORTGAGES*

CHAPTER 244 FORECLOSURE AND REDEMPTION OF MORTGAGES* CHAPTER 244 FORECLOSURE AND REDEMPTION OF MORTGAGES* *selected sections relating to foreclosures by sale Section 1 Foreclosure by entry or action; continued possession Section 1. A mortgagee may, after

More information

LOAN SERVICING AND EQUITY INTEREST AGREEMENT

LOAN SERVICING AND EQUITY INTEREST AGREEMENT LOAN SERVICING AND EQUITY INTEREST AGREEMENT THIS LOAN SERVICING AND EQUITY INTEREST AGREEMENT ( Agreement ) is made as of, 20 by and among Blackburne & Sons Realty Capital Corporation, a California corporation

More information

Basics of Alabama Lien Law

Basics of Alabama Lien Law Basics of Alabama Lien Law Charles A. Ray, IV Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 CAR@LanierFord.com www.lanierford.com 2014 1 Agenda Types

More information

_, 20 Between : Home Improvement Contract. This AGREEMENT is made as of the day of. Owner s Name : Owner s Street Address : City, State and Zip :

_, 20 Between : Home Improvement Contract. This AGREEMENT is made as of the day of. Owner s Name : Owner s Street Address : City, State and Zip : This AGREEMENT is made as of the day of, 20 Between : Alpha Roofing, Inc 1517 Thermal Ave San Diego, CA 92154 Phone: (619) 386-5574 carlos@alpharoofingcontractor.com www.alpharoofingcontractor.com Lic

More information

Senate Bill No. 818 CHAPTER 404

Senate Bill No. 818 CHAPTER 404 Senate Bill No. 818 CHAPTER 404 An act to amend Section 2924 of, to amend and repeal Sections 2923.4, 2923.5, 2923.6, 2923.7, 2924.12, 2924.15, and 2924.17 of, to add Sections 2923.55, 2924.9, 2924.10,

More information

Payment Act Comparison NJ/DE/PA/MD/NY

Payment Act Comparison NJ/DE/PA/MD/NY Payment Act Comparison NJ/DE/PA/MD/NY Many Remedies Exist for Non- Payment or Untimely Payment: Mechanics Liens Payment Bond Claims Trust Fund Claims Prompt Payment Act Claims Litigation/Arbitration/Mediation

More information

Land Titles Act (Alberta) Set of Standard Form Mortgage Terms - Residential

Land Titles Act (Alberta) Set of Standard Form Mortgage Terms - Residential Variable Rate Land Titles Act (Alberta) Set of Standard Form Mortgage Terms - Residential TABLE OF CONTENTS SECTION 1 TERMS YOU NEED TO KNOW...1 SECTION 2 HOW THE MORTGAGE WORKS...3 SECTION 3 INTEREST...4

More information

Registration Number: Date: February 4, 2016

Registration Number: Date: February 4, 2016 Filed By: Canadian Imperial Bank of Commerce 6213-2016/03 Page 1 of 17 Consumer General Collateral Mortgage Standard Mortgage Terms Registration Number: 161036262 Date: February 4, 2016 The following set

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,

More information

INTERIM WAIVER AND RELEASE UPON PAYMENT

INTERIM WAIVER AND RELEASE UPON PAYMENT EXHIBIT F STATE OF GEORGIA COUNTY OF INTERIM WAIVER AND RELEASE UPON PAYMENT THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN, HAS BEEN EMPLOYED BY TO FURNISH FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS WHICH

More information

MORTGAGE. This Mortgage is made this day of, Legal Description: Property Address:

MORTGAGE. This Mortgage is made this day of, Legal Description: Property Address: Return To: FOLIO # MORTGAGE This Mortgage is made this day of, between ( Borrower ) residing at and, a ( Lender ), located at. In this Mortgage, the words I, me and mine mean the Borrower and the words

More information

OWNER S INFORMATION SHEET

OWNER S INFORMATION SHEET HOMEOWNER S POLICY OF TITLE INSURANCE For a one-to-four family residence Issued By BLANK TITLE INSURANCE COMPANY OWNER S INFORMATION SHEET Your Title Insurance Policy is a legal contract between You and

More information

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Shoshana E. Rothman BrigliaMcLaughlin, PLLC April 2017 Seminar Goals: 1. Understand key contract clauses

More information

Real Estate Finance: Massachusetts

Real Estate Finance: Massachusetts Resource ID: 7-500-3877 Real Estate Finance: Massachusetts Paul Jakubowski and Stephen M. Edwards, WilmerHale, with Practical Law Real Estate Search the Resource ID numbers in blue on Westlaw for more.

More information

Shutting Down the Construction Project

Shutting Down the Construction Project White Paper Real Estate August 2012 Shutting Down the Construction Project by Robert A. James, Amy L. Pierce and Noa L. Clark Article originally appeared in Perspectives on Real Estate, Spring 2010 edition.

More information

The Construction Lien Act & Contract Administration

The Construction Lien Act & Contract Administration The Construction Lien Act & Contract Administration Liens, Trusts, Rights to Information and New Amendments Glenn W. Ackerley 4100-66 Wellington Street West TD Bank Tower Toronto, ON M5K 1B7 416-947-5024

More information

CMLS FINANCIAL LTD. Alberta Land Titles Act STANDARD MORTGAGE TERMS. Registration No

CMLS FINANCIAL LTD. Alberta Land Titles Act STANDARD MORTGAGE TERMS. Registration No CMLS FINANCIAL LTD. Alberta Land Titles Act STANDARD MORTGAGE TERMS Registration No. 131037998 These STANDARD MORTGAGE TERMS shall be deemed to be included in every Mortgage which incorporates and refers

More information

INDIANA MECHANIC S LIEN LAW 2017

INDIANA MECHANIC S LIEN LAW 2017 INDIANA MECHANIC S LIEN LAW 2017 Go to: Indiana Mechanic s Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified

More information

AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES

AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES AN ANALYSIS OF ARIZONA PROMPT PAYMENT STATUTES GUY W. BLUFF, ESQ. I. ARIZONA S PROMPT PAYMENT STATUTES 3 A. The General Rule 4 B. Objections Must be In Writing and Specific 6 II. SUMMARY OF STATUTORY AND

More information

IN THE COURT OF APPEALS OF INDIANA

IN THE COURT OF APPEALS OF INDIANA Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of establishing the defense of res judicata, collateral

More information

CUSTOMER S ACCEPTANCE OF

CUSTOMER S ACCEPTANCE OF Force Vector Master Contract for Equipment Rental and Services 1) FVI s Business. (a) Force Vector, Inc., an Illinois corporation, ( FVI ) rents various types of industrial equipment ( Rented Equipment

More information

TEXAS MECHANIC S LIEN LAW

TEXAS MECHANIC S LIEN LAW TEXAS MECHANIC S LIEN LAW 2018-2019 Go to: Texas Mechanics Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified

More information

DEED OF TRUST WITH REQUEST FOR NOTICE

DEED OF TRUST WITH REQUEST FOR NOTICE RECORDING REQUESTED BY: When Recorded Mail Document To: APN: SPACE ABOVE THIS LINE IS FOR RECORDER S USE DEED OF TRUST WITH REQUEST FOR NOTICE HIS DEED OF TRUST is made this day of among the Trustor, (herein

More information

Standard Mortgage Terms

Standard Mortgage Terms These mortgage terms shall be deemed to be included and form part of every mortgage. The terms of this set of standard mortgage terms may be modified by additions, amendments or deletions in the schedule

More information

Construction Lien Law

Construction Lien Law Construction Lien Law Lee A. Weintraub Becker One East Broward Blvd., Ste. 1800 Ft. Lauderdale, Florida 33301 (954) 985-4147 lweintraub@beckerlawyers.com PROPERTY INTERESTS SUBJECT TO LIEN Where the property

More information

Consumer General Collateral Mortgage Standard Mortgage Terms

Consumer General Collateral Mortgage Standard Mortgage Terms Consumer General Collateral Mortgage Standard Mortgage Terms Filed By: Canadian Imperial Bank of Commerce Filing Number: MT080113 Filing Date: August 1, 2008 The following set of standard mortgage terms

More information

REAL PROPERTY ACT (P.E.I.)

REAL PROPERTY ACT (P.E.I.) REAL PROPERTY ACT (P.E.I.) ROYAL BANK OF CANADA (PERSONAL LENDING) (Fixed Rate) COLLATERAL MORTGAGE TABLE OF CONTENTS SECTION 1 AMOUNTS SECURED BY THE MORTGAGE AND INTEREST RATE...2 SECTION 2 - TERMS YOU

More information

* gat *OLD REPUBLIC * National Title Insurance Company l -r-.

* gat *OLD REPUBLIC * National Title Insurance Company l -r-. ,711e Inqtran,,e South' 55401. * -I( * gat *OLD REPUBLIC * National Title Insurance Company l -r-. 4` Commitment To Insure Issued through the Office of ORDOCS COMM TO INSURE ORT FORM 3229CA MF01138 COMMITMENT

More information

2017 Construction Law Seminar

2017 Construction Law Seminar 2017 Construction Law Seminar Mechanic's Liens in Iowa Under the New Rules 2:20 p.m. - 3:05 p.m. Presented by Brian Rickert Brown Winick 666 Grand Avenue, Suite 2000 Des Moines, IA 50309-2510 Phone: 515-242-2457

More information

CHAPTER 14 RESPONSIBLE UTILITY CUSTOMER PROTECTION

CHAPTER 14 RESPONSIBLE UTILITY CUSTOMER PROTECTION CHAPTER 14 RESPONSIBLE UTILITY CUSTOMER PROTECTION PENNSYLVANIA CONSOLIDATED STATUTES TITLE 66 Sec. 1401. Scope of chapter. 1402. Declaration of policy. 1403. Definitions. 1404. Cash deposits and household

More information

Form 3927 ( ) REAL PROPERTY ACT (MANITOBA) SET OF STANDARD CHARGE MORTGAGE TERMS COLLATERAL MORTGAGE (PERSONAL LENDING)

Form 3927 ( ) REAL PROPERTY ACT (MANITOBA) SET OF STANDARD CHARGE MORTGAGE TERMS COLLATERAL MORTGAGE (PERSONAL LENDING) REAL PROPERTY ACT (MANITOBA) SET OF STANDARD CHARGE MORTGAGE TERMS COLLATERAL MORTGAGE (PERSONAL LENDING) A C K N O W L E D G M E N T The undersigned, the Mortgagor(s) named in a Mortgage of Land to Royal

More information

NOW THEREFORE BE IT ORDAINED

NOW THEREFORE BE IT ORDAINED ORDINANCE OF THE CITY OF BAYONNE, COUNTY OF HUDSON, NEW JERSEY AUTHORIZING FIVE (5) YEAR TAX EXEMPTION ON THE ASSESSED VALUE OF NEW IMPROVEMENTS ONLY FOR NEWLY CONSTRUCTED RESIDENTIAL UNITS WITH RESPECT

More information

American Land Title Association Adopted OWNER S POLICY OF TITLE INSURANCE Issued by [TITLE INSURANCE COMPANY]

American Land Title Association Adopted OWNER S POLICY OF TITLE INSURANCE Issued by [TITLE INSURANCE COMPANY] OWNER S POLICY OF TITLE INSURANCE Issued by [TITLE INSURANCE COMPANY] Any notice of claim and any other notice or statement in writing required to be given to the Company under this Policy must be given

More information

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office and

More information

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties.

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties. SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office

More information

TD DEED OF TRUST

TD DEED OF TRUST 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 forfeiture

More information

SUMMARY OF MECHANICS LIEN LAW FOR TEXAS. With Changes for 2012

SUMMARY OF MECHANICS LIEN LAW FOR TEXAS. With Changes for 2012 SUMMARY OF MECHANICS LIEN LAW FOR TEXAS With Changes for 2012 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic

More information

OPTIONAL MORTGAGE COVENANTS STANDARD RESIDENTIAL MORTGAGE TERMS AND CONDITIONS TABLE OF CONTENTS

OPTIONAL MORTGAGE COVENANTS STANDARD RESIDENTIAL MORTGAGE TERMS AND CONDITIONS TABLE OF CONTENTS Form 3973 (11-2005) OPTIONAL MORTGAGE COVENANTS STANDARD RESIDENTIAL MORTGAGE TERMS AND CONDITIONS TABLE OF CONTENTS SECTION 1 TERMS YOU NEED TO KNOW...1 SECTION 2 HOW THE MORTGAGE WORKS...3 SECTION 3

More information

M E M B E R S H I P Associated Subcontractors of Massachusetts

M E M B E R S H I P Associated Subcontractors of Massachusetts M E M B E R S H I P GETTING PAID in Massachusetts Provided as a courtesy to ASM Members Associated Subcontractors Associated Subcontractors of Massachusetts of Massachusetts 31 State Street 4th Floor Boston,

More information

ConsensusDocs 750 vs. AIA A : Which is Best For You?

ConsensusDocs 750 vs. AIA A : Which is Best For You? ConsensusDocs 750 vs. AIA A401 2007: Which is Best For You? Presented for the AGC NE Building Chapter by Kory George and Brian Koerwitz Woods & Aitken LLP Omaha, Lincoln, Denver, Washington D.C. kgeorge@woodsaitken.com

More information

ARKANSAS MECHANIC S LIEN LAW

ARKANSAS MECHANIC S LIEN LAW ARKANSAS MECHANIC S LIEN LAW 2018-2019 Go to: Arkansas Mechanic s Lien Forms More Info: www.nationallienlaw.com Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve

More information

CONCURRENT SESSION LIEN & BOND ISSUES. Update on 2013 Lien Law Changes. By: Caroline Trautman Anderson Jones, PLLC

CONCURRENT SESSION LIEN & BOND ISSUES. Update on 2013 Lien Law Changes. By: Caroline Trautman Anderson Jones, PLLC CONCURRENT SESSION LIEN & BOND ISSUES Update on 2013 Lien Law Changes By: Caroline Trautman Anderson Jones, PLLC Carolina Lindsey Trautman Native of: Reidsville, NC College and Year Graduated: UNC-Chapel

More information

Speedy Now USER AGREEMENT IMPORTANT TERMS AND CONDITIONS - PLEASE READ CAREFULLY

Speedy Now USER AGREEMENT IMPORTANT TERMS AND CONDITIONS - PLEASE READ CAREFULLY Speedy Now USER AGREEMENT IMPORTANT TERMS AND CONDITIONS - PLEASE READ CAREFULLY 1. Terms and Conditions. These terms and conditions outlines the terms and conditions, governing your use of the Speedy

More information

DEED OF TRUST AND ASSIGNMENT OF RENTS SAN FRANCISCO POLICE IN THE COMMUNITY LOAN PROGRAM (PIC)

DEED OF TRUST AND ASSIGNMENT OF RENTS SAN FRANCISCO POLICE IN THE COMMUNITY LOAN PROGRAM (PIC) Free Recording Requested Pursuant to Government Code Section 27383 When recorded, mail to: Mayor's Office of Housing AND Community Development of the City and County of San Francisco One South Van Ness

More information