The Navigators Group, Inc.
|
|
- Joanna Williams
- 6 years ago
- Views:
Transcription
1 The Navigators Group, Inc. The Opportunity and Challenges of Underwriting Construction Risks in the Energy and Infrastructure Sectors 2 nd Seminar of Lloyd s in Brazil Stephen Coward President Navigators Technical Risk 20th July /18/2010 1
2 Agenda Introduction What is the subject matter? A quick guide to construction project insurance Construction loss illustrations to give context What are the challenges? Key project information and its worth Essential attributes of a construction (re) insurer The opportunity: What does Lloyd s offer on Brazilian construction projects? The Navigators Group, Inc. 2
3 Planned spending under PAC Clockwise: The Navigators Group, Inc. 3
4 What is the subject matter? An introductory look at construction project insurance Erection all risks (EAR) = Electrical/mechanical projects (nuts & bolts) e.g. power stations, oil refineries, gas processing, industrial plants, pipelines, water /waste treatment and offshore exploration and production installations All risks of physical loss/damage to the contract works Covering all parties associated with project site (Employer, Financiers, Contractors, sub contractors, etc.) Main exposures = fire, explosion, collapse, mechanical breakdown, human error The Navigators Group, Inc. 4
5 What is the subject matter? An introductory look at construction project insurance (2) Contractors all risks (CAR) = dwellings, commercial buildings, roads, bridges, tunnels, dams, sea defences All risks of physical loss/damage to the contract works Covering all parties associated with project site (Employer, Financiers, Contractors, sub contractors, etc.) Main exposures= fire, collapse, landslide, faulty design or materials, storm, flood, human error
6 What is the subject matter? An introductory look at construction project insurance (3) Delay start up insurance (DSU) also known as ALoP Loss of anticipated profit/loan interest repayment (and/or ICOW) arising from an insured delay to the commencement of the business Employer (and financiers) insured, but not contractors Third party liability All insured parties protected against liabilities to others for bodily injury or damage arising out of the execution of project works Let s see what can go wrong some claims examples
7 Run of river hydroelectric scheme inundation of workings Central America
8 Blow down tank for steam turbine under construction vacuum induced collapse
9 Crane collapse at construction site in USA jib falling on site camp caused fatalities
10 Generator Step-Up transformer explosion and fire
11 Deep excavation in Dubai
12 Retaining wall showing signs failure
13 Major failure of retaining wall
14 We wanted a basement car park not a swimming pool!!!!
15 Gas fired power plant nearing completion in USA
16 Gas explosion during pipeline purging widespread damage and loss of life
17 Extensive damage and project delayed several months
18 What are the challenges? Cont/.. Many projects in the infrastructure and energy sectors are highly complex risks, with distinctly individual characteristics Insurance is required for the whole of the project period Complex contractual arrangements Various separate entities working together; sometimes conflicts arise during the life of the project Building sites are inherently dangerous places Profit margins are slim in the construction industry; aggressive tendering process in public and private sectors; cash flow is an important consideration for contractors Insurance risk assessment is often required at tender/pre-bid stage before full plans and specifications have been developed or suppliers identified. Getting relevant information can prove difficult.
19 Cont/ What are the challenges? At the commencement of the insurance many projects elements are yet to be determined even the basics are only estimates e.g. estimated Contract Value, estimated period of construction Risk monitoring and loss prevention is a key part of a successful project. Loss mitigation is also an important element. What went wrong and how to fix it? How to prevent a recurrence on this and other similar projects around the world? Non-renewable business directly impacted by economic cycles. Environmental and political influences are becoming key drivers too. Increasingly ambitious projects lead to greater exposure. Technological and environmental boundaries are being taken to new limits Substantial (re) insurance capacity is required; this capacity has to be sustainable in the long term Underwriting results take several years to develop The Navigators Group, Inc. 19
20 Development of results - an illustration of EAR exposure over time The Navigators Group, Inc. 20
21 Key project information and its worth Underwriting information required What is it? - project features, technical characteristics Who is involved? the parties to the project and their past experience Where is it? location of site, ground conditions, proximity to water How much is it going to cost? the make up of the contract value between its key constituent parts How long will it take to complete? seasonal exposures, length of testing/commissioning phase, lead time for items on the critical path (DSU) And more ? Why it makes a difference? No two projects are the same Premium and deductibles need to be commensurate with expected risk Tailoring coverage to match the exposure Better utilization of capacity. Realistic PML needs to be assessed Loss prevention strategies can be developed with clients The Navigators Group, Inc. 21
22 Essential attributes of a construction (re) insurer Since these are long term policies, the market needs underwriters who provide: A continuing appetite for the risk throughout the project period Adequate engineering resources to provide after sales services; progress monitoring A positive attitude to change after policy inception; project alterations are likely (project plan vs actual activity) A willingness to extend the period of insurance, perhaps long into the future An ability to accept future increases in insured values and the additional exposure ~ Variation orders ~ Unforeseen rise in construction costs, which can be significant ~ Long-term inflation Claims handling capability ~ Technical understanding what went wrong and how to fix it Claims paying ability ~ staged payments, recognising the liquidity of insured parties, long term financial security The Navigators Group, Inc. 22
23 The opportunity: What does Lloyd s offer on Brazilian construction projects? Technical expertise across a range of project types Wide experience drawn from all parts of the world (direct insurance and reinsurance) Reinsurance leadership, including risk management/loss prevention and claim handling capabilities Meaningful facultative capacity from several individual syndicates Competitive pricing Policy/Product innovation: coverage developed from international experience (an alternative to standard Munich Re forms) When the works are completed, the possibility of a smooth transition into operational (re)insurances i.e. property, business interruption Lloyd s unique financial security The Navigators Group, Inc. 23
The Navigators Group, Inc.
The Navigators Group, Inc. Willis 2012 Latin American Energy Conference The Underwriting of Construction Project Risks in the Latin American Energy/Power Generation Sector Stephen Coward President Navigators
More informationInsurance for the construction industry an overview of core products, coverage and claims
Insurance for the construction industry an overview of core products, coverage and claims ZF Summit Construction 29 May 2014 James Grindley, CEO CertAsig Who is CertAsig? CertAsig is a niche, non-life
More informationTopics of IMIA Working Group Papers
Topics of IMIA Working Group Papers 1984-2018 2018 Singapore (WGP 106 111) Construction in Mountainous Areas Offshore Oil & Gas Platforms Construction and Operation of Scientific Instruments Electric Failuresnot
More informationEVALUATING CDM PROJECT RISKS: AN INSURER'S PERSPECTIVE. Johannesburg, November Jonathan Young Underwriter, Carbon Risks
EVALUATING CDM PROJECT RISKS: AN INSURER'S PERSPECTIVE Johannesburg, Jonathan Young Underwriter, Carbon Risks http://www.nasa.gov/audience/foreducators/topnav/materials/listbytype/apollo.17.view.of.earth.html
More informationEngineering Insurance Premium and Loss Statistics
The International Association of Engineering Insurers TM Engineering Insurance Premium and Loss Statistics 29-211 Presented by Allianz Global Corporate & Specialty 22 26 September 212 Rio de Janeiro, Brazil
More information(b) goods or assets situated in Uganda;
Page 2 No person, other than a person licensed as an insurer under this Act, shall issue any insurance policy on (a) persons who at the time of effecting a contract are residents of Uganda; (b) goods or
More informationIMIA Engineering Underwriting Training Course
11 15 March 2013 in Berlin Course Time Schedule Stand 09/12 Course Programme Details Session 1 - Monday 14.00-15.30h - Introduction to Engineering Insurance Utz Groetschel Introduction of participants
More informationConstruction Insurance
Construction Insurance Construction Insurance on a Global Scale The rate of global construction is likely to increase by nearly double the amount from 2014 through 2025. This sector is one of the most
More informationConstruction Insurance
Construction Insurance Product overview All construction, erection and installation work contain an element of risk, whether created by the nature of the work to be carried out, by the contractual liability
More informationChubb Technical lines
Chubb Technical lines Companies today are looking for an insurer who can cater for their whole range of technical or engineering insurance requirements. These broad and varied needs include everything
More informationRisk Control and Claims Handling on Advanced Loss of Profits Insurance (ALOP) (WGP63 (2009))
Risk Control and Claims Handling on Advanced Loss of Profits Insurance (ALOP) (WGP63 (2009)) IMIA Conference Istanbul 2009 Project Group Neil Clutterbuck, Allianz Engineering (Chairman) Eric Brault, AXA
More informationIMIA 9-28 (93) E NEW ASPECTS OF PML ESTIMATION IN CAR AND EAR INSURANCE
IMIA 9-28 (93) E NEW ASPECTS OF PML ESTIMATION IN CAR AND EAR INSURANCE Hans-Berndt Schittek 1993 PML-Estimation for CAR/EAR Risks 1. Introduction Under the impression of recent large claims in the fields
More informationMarine, Energy & Construction
Marine, Energy & Construction Overview We aim to maintain our position as a globally-recognised market leader providing specialty products and services for the oil, gas, petrochemical, chemical, pharmaceutical,
More informationThe International Association of Engineering Insurers TM. Engineering Insurance Statistics
IMIA The International Association of Engineering Insurers TM Engineering Insurance Statistics 23-25 Presented by Allianz Global Corporate & Specialty in September 26 at the IMIA Conference in Boston Development
More informationAXA Africa Specialty Risks
AXA AFRICA SPECIALTY RISKS Political Risk and Trade Credit Growing a business in an emerging market can come with a wide range of issues. That s why offers tailor-made coverage that s designed to help
More informationNatural Resources. We can show you more.
Natural Resources We can show you more. CNA Hardy Natural Resources We partner with customers to help protect assets and operations in the best possible way; a partner with cross class expertise that understands
More informationRisk of Hydro Power Sector in Nepal. Mahesh Guragain, FCA Chairman, NepalRe (
Risk of Hydro Power Sector in Nepal Mahesh Guragain, FCA Chairman, NepalRe (www.nepalre.com.np) INTRODUCTION Contractors All Risk Insurance (C.A.R. also known as Contract Works Insurance) is an insurance
More informationTradesmen Policy This is a summary of your policy, giving important information about the cover provided so you can check that it is right for you.
POLICY SUMMARY Tradesmen Policy This is a summary of your policy, giving important information about the cover provided so you can check that it is right for you. Arista Insurance Tradesmen Policy Summary
More informationTerraz. Engineering. Specialist Products. Engineering
o underwrites on behalf of the Absa Insurance Company Limited, providing engineering solutions to a wide range of industrial and commercial customers, helping them protect both their assets and their profitability.
More informationQuestionnaire and Proposal for Erection All Risks Insurance
Questionnaire and Proposal for Erection All Risks Insurance 1. Title of Contract (if Project consists of several section(s) to be insured) 2. Location of Erection Site Country City, Town, Village 3. Proposer
More informationQuestionnaire and Proposal for Contractor s All Risk Insurance
Questionnaire and Proposal for Contractor s All Risk Insurance 1. Title of contract (If project consists of Several sections, specify Section(s) to be insured.). Site Country/Province/District City/Town/Village
More informationGlobal Risk Consulting
Allianz Global Corporate & Specialty Global Risk Consulting Tailored worldwide risk management services from Allianz Risk Consulting 1 What we do? Allianz Risk Consulting (ARC) applies a consultative approach
More informationSingle Project Proposal Form IMPORTANT NOTES
Single Project Proposal Form IMPORTANT NOTES PRIVACY STATEMENT This notice sets out how MECON and AIG collect, use and disclose personal information about: you, if an individual; and other individuals
More informationMarine, Energy & Construction
Marine, Energy & Construction Overview We aim to maintain our position as a globally-recognised market leader providing specialty products and services for the oil, gas, petrochemical, chemical, pharmaceutical,
More informationCOMMERCIAL GENERAL LIABILITY APPLICATION
COMMERCIAL GENERAL LIABILITY APPLICATION IF SPACE IS INSUFFICIENT FOR ANSWER, PLEASE USE SEPARATE SHEETS INSURANCE COMPANY NEW POLICY EXISTING POLICY NO OF LOCATIONS NO OF ATTACHMENTS 1. APPLICANT S NAME
More informationCash Flows Included. Darryl Wagner, FSA, MAAA. Insurance IFRS Seminar December 1, 2016 Darryl Wagner. Session 11
Cash Flows Included Insurance IFRS Seminar December 1, 2016 Darryl Wagner Darryl Wagner, FSA, MAAA Session 11 Agenda Cash flows included Cash flows excluded Scenario requirements 2 Which cash flows are
More informationQuestionnaire and proposal for contractors all risks insurance No.
Questionnaire and proposal for contractors all risks insurance No. 1. Title of contract (If project consists of several sections, specify section(s) to be insured.) 2. Site County/Province/District City/Town/Village
More informationGlobal Corporate & Commercial Engineering
Global Corporate & Commercial Engineering What s keeping you awake at night? It s a question we ask our clients every day Natural disasters Globalization has expanded your opportunities, but unknown territories
More informationProposal Form Erection All Risks Insurance
Proposal Form Erection All Risks Insurance This proposal is to be completed by the Proposer or an Authorized Representative of the proposer. As the answers will form the basis of any insured issued, they
More informationProfessional Indemnity Insurance. Single Project Proposal Form
Professional Indemnity Insurance Single Project Proposal Form LIABILITY OF THE COMPANY DOES NOT COMMENCE UNTIL THE PROPOSAL HAS BEEN ACCEPTED AND THE PREMIUM HAS BEEN RECEIVED IN A ACCORDANCE WITH THE
More informationA&E A&E. ProSurance TM. Application Form INSURANCE FOR ARCHITECTS & ENGINEERS
A&E INSURANCE FOR ARCHITECTS & ENGINEERS ProSurance TM A&E Application Form This is an application for an errors and omissions package policy designed specifically for architects and engineers. As well
More informationThe International Association of Engineering Insurers
The International Association of Engineering Insurers About us Photo: IMIA 2014 Photo Competition Road bridge near Jerusalem by Alon Eisenberg, Engineers, Surveyors & Loss Adjusters IMIA is a network of
More informationCatastrophe Risk Engineering Solutions
Catastrophe Risk Engineering Solutions Catastrophes, whether natural or man-made, can damage structures, disrupt process flows and supply chains, devastate a workforce, and financially cripple a company
More informationAGCS: YOUR PARTNER IN A CHANGING ENERGY LANDSCAPE
Allianz Global Corporate & Specialty SE AGCS: YOUR PARTNER IN A CHANGING ENERGY LANDSCAPE Chris van Gend Munich, 02 November 2017 CONTENTS 01 AGCS AT A GLANCE 04 RANGE OF PRODUCTS AND SERVICES FROM AGCS
More informationNatural Resources. We can show you more.
Natural Resources We can show you more. CNA Hardy Natural Resources We partner with customers to help protect assets and operations in the best possible way; a partner with cross class expertise that understands
More informationPIONEER RENEWABLE ENERGY
PIONEER RENEWABLE ENERGY We want to work with you Warren Diogo Head of Renewable Energy +44 20 7480 0257 warren.diogo@pioneeruw.com Jack O Sullivan Assistant Underwriter +44 20 7480 4352 jack.o sullivan@pioneeruw.com
More informationCONTRACTING OPERATIONS INFORMATION
t m CONTRACTOR S SUPPLEMENTAL QUESTIONNAIRE Note: Throughout this questionnaire the words you and your include all entities seeking coverage. BASIC INFORMATION Name(s) of Applicant: License Number: Years
More informationREPORT OF MEETING DATE SAND DUNES RE-MODELLING AT NORTH BEACH CAR PARK / SUMMERFIELDS
DECISION ITEM REPORT OF MEETING DATE DEVELOPMENT SERVICES DIRECTORATE PUBLIC ITEM TOURISM AND LEISURE COMMITTEE 12 JANUARY 2017 5 SAND DUNES RE-MODELLING AT NORTH BEACH CAR PARK / SUMMERFIELDS This item
More informationDelivering Public Private Partnerships in PNG
Port Moresby Chamber of Commerce-INA Public Private Partnership Seminar Pt Moresby, 22 nd February, 2012 1.4 Delivering Public Private Partnerships in PNG Michael Regan Professor of Infrastructure Institute
More informationAn Approach for the Assessment of the Maximum Probable Loss for Insurance Purposes
1. INTRODUCTION An Approach for the Assessment of the Maximum Probable Loss for Insurance Purposes During the last decades, the financing of the construction and maintenance of new motorways in various
More informationREQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS
REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS Contact: Sarah Merriman Town Clerk/Select Board Assistant Town of Middlesex 5 Church Street Middlesex,
More informationSingle Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy
Single Project Professional Indemnity Insurance Proposal Form Note: This is a proposal form for a claims made policy Please provide any necessary explanations or additional details by attaching separate
More informationDelay In Start-Up Insurance. A Primer Based on Lessons Learned Houston Marine Insurance Seminar September 21, 2015
Delay In Start-Up Insurance A Primer Based on Lessons Learned Houston Marine Insurance Seminar September 21, 2015 What is DSU? DSU on the Rise Number of policies involving DSU cover DOUBLED over the last
More informationSUPPLEMENTAL QUESTIONNAIRE Artisan Contractors
SUPPLEMENTAL QUESTIONNAIRE Artisan Contractors GENERAL INFORMATION Applicant Name: Mailing Address: Location Address (if different from above): Website Address: Date Business Started Has applicant changed
More informationThe basics of verification. Richard Nott Lloyd s Register EMEA
The basics of verification Richard Nott Lloyd s Register EMEA Introductions Richard Nott Manager, Compliance and Engineering Services Lloyd s Register EMEA Agenda The Offshore Installation (Safety Case)
More informationMANAGING RISK CONSTRUCTION INSURANCE
IMIA WGP3(99)E MANAGING RISK CONSTRUCTION INSURANCE Report Objektive Prologue Introduction Definition of risk management Definition of risk Risk Management Resources Risk Identification, Appraisal and
More information1.1 Name and address of main Proposer : Contract Awarded?
PROPOSAL FORM FOR SINGLE PROJECT PROFESSIONAL INDEMNITY NOTE: THIS IS A PROPOSAL FOR A CLAIMS MADE POLICY Note : Please provide any necessary explanations or additional details by attachment to this Proposal
More informationCB Treasurers Conference Insurance Presentation
CB Treasurers Conference Insurance Presentation 19 th January, 2014 Nick Rolfe, Jeremy Goodacre Sheraton Heathrow Hotel Agenda Introduction to Marsh Team Background to Club Insurances Current Insurance
More informationSINGAPORE. aspen-insurance.com
SINGAPORE aspen-insurance.com ASPEN GROUP Founded in 2002, and listed on the New York Stock Exchange in 2003, Aspen is a leading provider of insurance and reinsurance to clients. We operate through whollyowned
More informationWHAT S IT WORTH TO YOU?
WHAT S IT WORTH TO YOU? IMUA Annual Conference Atlanta, GA May 21, 2013 Rick Lunt Technical Director, Business Resilience Phil Moretti Executive General Adjuster Property valuation Business interruption/ee
More informationELECTRONIC EQUIPMENT INSURANCE (EEI)
ELECTRONIC EQUIPMENT INSURANCE (EEI) The term electronic equipment is used for all systems which generally require very low voltage and power. These equipments are generally quiet in their operation. EEI
More informationArchitects. Proposal Form
Architects Proposal Form Architects Proposal Form IMPORTANT INFORMATION REGARDING COMPLETION OF THIS FORM Method of Completion This proposal form may be completed in ink or electronically and signed and
More informationQuestionnaire and Proposal for Erection All Risks Insurance No
Questionnaire and Proposal for Erection All Risks Insurance No 1 Title of contract (if project consists of several sections, specify section(s) to be insured) 2 Location of erection site Country City,
More informationBroadform General & Products Liability 2017/06 Proposal. about Broadform General and Products Liability 2016/05 Proposal
About Broadform General & Products Liability 2017/06 Proposal about Broadform General and Products Liability 2016/05 Proposal Page 1 of 12 IMPORTANT INFORMATION: PLEASE READ THE FOLLOWING INFORMATION BEFORE
More informationDesign Clauses in Engineering Contracts Industry Standard Wordings in Comparison
Design Clauses in Engineering Contracts Industry Standard Wordings in Comparison In large-scale engineering projects, millions of dollars in potential losses hinge on the integrity of each and every constituent
More informationConstruction E & O Application
1550 Bedford Highway, Suite 815 Bedford, NS B4A 1E6 t: 1-877-343-8224 f: 1-877-432-9822 e: accounts@agileuw.ca agileuw.ca Construction E & O Application Whoever fills out the form must be a principal,
More informationSubmission Type: New Renewal Conversion BROKER INFORMATION
Proposed Effective Date Expiration Date of Current GL Policy ADMITTED ARTISAN CONTRACTOR PROGRAM APPLICATION 5/24/2017 5/24/2017 Submission Number: Submission Type: New Renewal Conversion BROKER INFORMATION
More informationThe International Association of Engineering Insurers. Access Bridge - Ceneri Tunnel, Gero Stenzel, Partner Re
The International Association of Engineering Insurers About us Access Bridge - Ceneri Tunnel, Gero Stenzel, Partner Re IMIA Mission and Focus IMIA is a network of experts in Engineering Insurance from
More informationA&E. Inter-Pacific Insurance Brokers, Inc. APPLICATION FORM INSURANCE FOR ARCHITECTS & ENGINEERS
A&E INSURANCE FOR ARCHITECTS & ENGINEERS APPLICATION FORM INTRODUCTION The purpose of this application form is for us to find out who you are and to obtain information relevant to the cover provided by
More informationNon traditional Insurance Solutions for Renewables. Corporate Insurance Partner Special Enterprise Risks (SER) - Green Tech Solutions (GTS)J
Non traditional Insurance Solutions for Renewables Corporate Insurance Partner Special Enterprise Risks (SER) - Green Tech Solutions (GTS)J Special Enterprise Risks (SER): Full support for your individual
More informationWorking Group 104 Inconsistent Insurance and Reinsurance IMIA Conference Munich, Germany 2017
Working Group 104 Inconsistent Insurance and Reinsurance IMIA Conference Munich, Germany 2017 By Pascal Lüthi Sompo International Reinsurance September 2017 The Working Group Max Benz (Sponsor) Underwriting
More informationCOMMERCIAL INSURANCE WHEN THE UNBELIEVABLE HAPPENS ELMO INSURANCE. elmoinsurance.com
COMMERCIAL INSURANCE WHEN THE UNBELIEVABLE HAPPENS ELMO INSURANCE elmoinsurance.com BECAUSE WE BELIEVE LITTLE THINGS MAKE A BIG DIFFERENCE Elmo Insurance is a respected company linked to global and financially
More informationA&E. Application Form INSURANCE FOR ARCHITECTS & ENGINEERS
A&E INSURANCE FOR ARCHITECTS & ENGINEERS Application Form This is an application for an errors and omissions package policy designed specifically for architects and engineers. As well as errors and omissions
More informationSINGAPORE 360 THINKING. aspen-insurance.com
SINGAPORE 360 THINKING aspen-insurance.com ASPEN GROUP Founded in 2002, and listed on the New York Stock Exchange in 2003, Aspen is a leading provider of insurance and reinsurance to clients. We operate
More informationBUILDERS RISK POLICIES: ALL RISK PROTECTION OR BLACK HOLES IN WHICH TO DROP YOUR PREMIUMS?
BUILDERS RISK POLICIES: ALL RISK PROTECTION OR BLACK HOLES IN WHICH TO DROP YOUR PREMIUMS? Builders Risk Policies: All Risk Protection or Black Holes in Which to Drop Your Premiums? PANELISTS Moderator
More informationSection II: Vulnerability Assessment and Mitigation
Section II: Vulnerability Assessment and Mitigation 1. Hazard Vulnerability Analysis (facility name) should conduct a thorough Hazard Vulnerability Analysis to help determine what events or incidents may
More informationCombined Liability Proposal Form
Combined Liability Proposal Form 1. Full name of the Insured (including the name of all subsidiary companies): 2. Date Business established: 3. Period of Insurance 4. Business Address (if more than one
More informationSINGLE PROJECT FACT FIND. This application is intended for contracts with a value in excess of 500,000
SINGLE PROJECT FACT FIND This application is intended for contracts with a value in excess of 500,000 SINGLE PROJECT FACT FIND underwriting Definitions to assist you in completing this application Contract
More informationPROPOSAL FORM FOR INSURANCE AGAINST ERECTION ALL RISKS 1. FULL NAME OF PROPOSER ADDRESS...TELEPHONE NO TRADE OR BUSINESS...FAX NO...
SIC INSURANCE COMPANY LIMITED P.O. Box 2363, Accra Ghana HEAD OFFICE: NYEMITEI HOUSE 28/29 Ring Road East. Tel (030) 2-280600-9 Fax (030) 2-780615 Ring Road West: (030) 2-228926/ 228922/228962/228987/
More informationSummary of Cover If you wish to make a claim please call for advice and guidance
Summary of Cover If you wish to make a claim please call 0345 266 9660 for advice and guidance Policy Summary Insurer Protector Insurance Policy number 708596 Policyholder Plus Dane Housing Ltd Period
More informationP art B 4 NATURAL HAZARDS. Natural Hazards ISSUE 1. River Flooding
4 NATURAL HAZARDS ISSUE 1 River Flooding A large part of the plains within the Timaru District is subject to some degree of flooding risk. At least part of all of the main settlements in the District and
More informationIMIA INDEX SURVEY 2017
IMIA INDEX SURVEY 2017 September 2017 Stephan Lämmle Agenda 1. IMIA Mission 2. Introduction to the IMIA Engineering Index Survey 3. Presentation of the IMIA Engineering Index Survey Format 4. Presentation
More informationCONSTRUCTION RISK PARTNERS LLC, A JLT GROUP COMPANY AMERICAN GAS ASSOCIATION JULY, 2017
CONSTRUCTION RISK PARTNERS LLC, A JLT GROUP COMPANY AMERICAN GAS ASSOCIATION JULY, 2017 AGENDA Market Review Casualty Market Property Market Emerging Risk Forecast 2 Construction Risk Partners Established
More informationRail Owner Controlled Insurance Program Manual
Rail Owner Controlled Insurance Program Manual Addendum No. 4 to June 2013 Edition (Updated 08-21-17) Update to Section 5 Enrolled and Excluded Contractor Required Coverage for Package P Contract Section
More informationLANDLORD S INSURANCE POLICY SUMMARY
LANDLORD S INSURANCE POLICY SUMMARY www.modusunderwriting.com LANDLORD S INSURANCE POLICY SUMMARY This document consists of your policy summary and other key information you need to know about the insurance.
More informationTokyo, October 1st to 3rd
Presentation of IMIA at the 2007 Conference Tokyo, October 1st to 3rd History / general remarks Aim and role of IMIA Memberships / organisation Annual conference Statistics IMIA website 1 History / general
More informationRoofers and Scaffolders Enquiry Form
Broker: Address inc Pcode: Contact Name: Telephone No: Proposer Details Name of Client: Full Address: Post Code: Website: Current Insurer: Current Broker: Expiring Premium: + Insurance Premium Tax Work
More informationS L tr lo a y t d egy s Cyber -Attack
Lloyd s Cyber-Attack Strategy 02 Introduction The focus of this paper is on insurance losses arising from malicious electronic acts, referred to throughout as cyber-attack. The malicious act is the proximate
More informationLloyd s Minimum Standards MS7 Reinsurance Management and Control
Lloyd s Minimum Standards MS7 Reinsurance Management and Control January 2019 2 Contents MS7 Reinsurance Management & Control 3 Minimum Standards and Requirements 3 Management guidance 3 Definitions 3
More informationRisk & Insurance. Alex Rimmer Chief Operating Officer. A Member of the Global Alliance Group of Companies
Risk & Insurance Alex Rimmer Chief Operating Officer A Member of the Global Alliance Group of Companies Company Background Global Alliance Group was founded in 2001 Represented in 6 Countries Worldwide
More informationRenewable Energy Insurance. The Leader in Renewable Energy Insurance Our Knowledge, Your Power
Renewable Energy Insurance The Leader in Renewable Energy Insurance Our Knowledge, Your Power History of Leadership With over 20 years of experience, we have become the industry leader, insuring over 30,000MW
More informationNo. 19. Offshore Wind Energy in Europe Fresh Wind for Insurers, Too? A Berkshire Hathaway Company. Topics No. 19
No. 19 Topics No. 19 Offshore Wind Energy in Europe Fresh Wind for Insurers, Too? A Berkshire Hathaway Company 10 Offshore Wind Energy in Europe Fresh Wind for Insurers, Too? Oliver Stein Oliver Stein
More informationLift Engineers. Proposal Form
Lift Engineers Proposal Form CONTENTS SECTION PAGE 1. IMPORTANT INFORMATION & DATA PROTECTION 3 2. CONTACT INFORMATION 5 3. PROPOSER DETAILS 6 4. BUSINESS ACTIVITIES 7 5. GENERAL QUESTIONS 8 6. PREMISES
More informationSPAIO Conference Sept 21, 2018 OCIP v CCIP
SPAIO Conference Sept 21, 2018 OCIP v CCIP April Pittendreigh, VP Claims, Gallagher Canada Scott Hamilton, Partner, Loopstra Nixon Arthur J. Gallagher Canada Limited ajgcanada.com Agenda 1. Introduction:
More informationEBRD s Environmental & Social (E&S) Risk Management Procedures for Insurance
EBRD s Environmental & Social (E&S) Risk Management Procedures for Insurance Any EBRD partner Financial Intermediary (FI) must have clearly defined environmental and social management systems in place,
More informationConstruction Risks. US Construction Practice
US Construction Practice Willis' US Construction Practice provides innovative products and delivers risk management services through its specialist building services teams, addressing the unique needs
More informationBuilder s Risk. Introduction and Coverages. March 9, 2018
Builder s Risk Introduction and Coverages March 9, 2018 Why Builder s Risk? Purpose: First Party Coverage to protect Insureds against damage & resulting loss to work in Course of Construction, before delivered
More informationLessons Learned with Offshore Windfarms and Converter Stations Claims Property & Engineering Petrus Knollmueller Munich,
Lessons Learned with Offshore Windfarms and Converter Stations Claims Property & Engineering Petrus Knollmueller Munich, 03.11.2017 Agenda Petrus Knollmüller Claims Property & Engineering Lessons learned
More informationMUNICIPAL BONDING AN INTRODUCTION FOR LOCAL LEADERS
MUNICIPAL BONDING AN INTRODUCTION FOR LOCAL LEADERS INTRODUCTION The world of municipal bonding can be confusing and challenging to navigate. However, gaining a basic understanding of the key principles
More informationPROPERTY RISK ENGINEERING IN THE CHEMICAL SECTOR. August 2016
PROPERTY RISK ENGINEERING IN THE CHEMICAL SECTOR August 2016 PROPERTY RISK ENGINEERING IN THE CHEMICAL SECTOR When chemical sector professionals in Europe think of chemical site safety, they normally think
More informationNURTURING ASIA S BEST PROGRAMME CALENDAR
ASIA S NURTURING BEST PROGRAMME CALENDAR 2019 02 January Risk Management 21, 22, 24, 25 & 28 January Mon, Tue, Thu, Fri & Mon Intermediate It aims to provide candidates with the knowledge of the application
More informationMITIGATION OF HYDRO PROJECT DEVELOPMENT RISK - INSURANCE NEED
MITIGATION OF HYDRO PROJECT DEVELOPMENT RISK - INSURANCE NEED Alok Choubey, GM- Hydro Projects ABSTRACT Development of Infrastructure projects including Hydro Power Projects are becoming riskier due to
More informationFREQUENTLY ASKED QUESTION ABOUT FLOODPLAINS Michigan Department of Environmental Quality
FREQUENTLY ASKED QUESTION ABOUT FLOODPLAINS Michigan Department of Environmental Quality WHAT IS A FLOOD? The National Flood Insurance Program defines a flood as a general and temporary condition of partial
More informationPUBLIC LIABILITY INSURANCE
PROPOSAL FORM PUBLIC LIABILITY INSURANCE Important tice 1. Statement pursuant to Section 25(5) of the Insurance Act (Cap 142) or any amendments thereof: you are to disclose in the application, fully and
More informationCOMMERCIAL PACKAGE POLICY COVERAGES WITH CONTRACTOR SHIELDSM
contractor shield sm COMMERCIAL PACKAGE POLICY COVERAGES WITH IMPACT CONTRACTOR SHIELDSM For decades, Federated insurance products have been designed specifically for contractors to manage the risks and
More informationFit for a game change
Image: Getty Images Baden-Baden, Hermann Pohlchristoph Agenda 1. Munich Re strategy Continually stretching our business model 4. Data driven Holistic risk management approach 2. Traditional reinsurance
More informationProfessional Indemnity for Engineers Proposal Form
Professional Indemnity for Engineers Proposal Form 4767 03/06 PROFESSIONAL INDEMNITY FOR ENGINEERS Your business activity 1. Name of all companies/firms to be insured: Name Date established 2. Address
More informationCL-3: Catastrophe Modeling for Commercial Lines
CL-3: Catastrophe Modeling for Commercial Lines David Lalonde, FCAS, FCIA, MAAA Casualty Actuarial Society, Ratemaking and Product Management Seminar March 12-13, 2013 Huntington Beach, CA 2013 AIR WORLDWIDE
More informationFINANCIAL STATEMENTS EPM GROUP Quarter
FINANCIAL STATEMENTS EPM GROUP Quarter 3-2011 1 Disclaimer 2 EPM prepared this document to provide stakeholders with information on the company s financial status. This document may include discussions
More informationIFRS Seminar for Regulators Accounting and Regulatory Issues Insurance Sector
REPARIS A REGIONAL PROGRAM IFRS Seminar for Regulators Accounting and Regulatory Issues Insurance Sector Session 2: Implications for regulators of IFRS4 Phase I versus Phase II Teddy Nyahasha May 31, 2011
More information