CSP Project Power Purchase Agreements: The Landscape and Key Deal Points To Obtain A Financeable PPA

Size: px
Start display at page:

Download "CSP Project Power Purchase Agreements: The Landscape and Key Deal Points To Obtain A Financeable PPA"

Transcription

1 CSP Project Power Purchase Agreements: The Landscape and Key Deal Points To Obtain A Financeable PPA Presented to the 4 th Annual Concentrated Solar Power Summit USA 24 June 2010 Todd Glass Wilson Sonsini Goodrich & Rosati, PC

2 An Overview Key Elements of CSP Project Deals A Common CSP Project Structure A Few Observations about Utilities, RFOs/RFPs, Form PPAs, the RPS Markets, and Results to Date Key PPA Deal Points to Make Your PPA: Practically feasible Commercially viable Approvable, and Financeable

3 Key Elements of CSP Project Deals - 1 Allocating the benefits... the energy output (amount and price) environmental attributes (i.e., renewable energy credits (RECs)) tax credits, accelerated depreciation, and other benefits ancillary services residual value utility credits and other potential goodies buy-out potential at the end of the contract* * NOT LESS THAN FAIR MARKET VALUE

4 Key Elements of CSP Project Deals and the risks and costs: Construction Performance Insolation Creditworthiness/security Diminution of environmental attributes Scheduling/Imbalances Equipment failure/ warranties O&M Removal costs/site restoration Change in law risk Other key deal points: Ownership Term Site/Location/Security Financing terms Conditions precedent Regulatory status Property and other taxes Insurance O&M duties and costs ULTIMATE QUESTION: Is the project financeable?

5 A Basis PPA Structure Utility Buys Energy and RECs Utility Energy + RECs PPA $$$ $$$ EPC Contractor EPC Contract Owner/ Project Company Engineering, Procurement, Construction Services $$$ Debt Debt Payments Typical Project Finance Documents ROI $$$ Lease $$$ Equity (tax benefits) Landowner

6 A Few Observations about Utilities, RFOs/RFPs, Form PPAs, the RPS Markets, and Results to Date Utilities have signed hundreds of PPAs to comply with RPS requirements; more than 50 utility scale solar PPAs in the US Yet very few utility-scale solar projects have been financed (< 5) Utilities now seem to be focusing on utilityowned and distributed generation PV projects and financing schemes What are independent evaluators doing? See CPUC updated table of RPS projects: A02EAAD2-7C72-4C3D-B4E5-92DEC /0/ RPS_Project_Status_Table_2010_June.XLS. CPUC RPS Quarterly Report on June 22, which is available here:

7 A Few Observations about Utilities, RFOs/RFPs, Form PPAs, the RPS Markets, and Results to Date Using significant market power (oligopsony), utilities are creating RPS RFO/RFP programs that are onerous and difficult for CSP and other utility scale solar developers Form PPAs (and utility negotiators) are pushing more and more risk onto developers (e.g., SCE s Buyer Curtailment, PG&E s CAISO availability standards) From Chinese PV manufacturers to unsophisticated new developers willing to sign anything, competition is driving PPA contract prices down significantly -- to the point of slim or even negligible returns The results: Fewer PPAs Unfinancable PPAs RPS compliance penalties?

8 Key PPA Deal Points Conditions Precedent None, except for PUC approval and perhaps ITC availability (placed in service after 2016) 2. Development Schedule Key Milestones Only: CSD, GCSD, COD and GCOD Progress Reporting: fine, but pass thru to EPC Contractor Extensions: Force Majeure, transmission upgrades (outside control) 3. Development Security/Delivery Term Security/Counterparty Credit Development Security: ~$30-50/kW of installed capacity Delivery Term Security: ~$ /kW of contract capacity Know thy seller/buyer (do you have a European bank?) 4. Interconnection; Point of Delivery Utility scale issues relating to schedule, cost, who pays POD should be a physical location, not some ephemeral, potentially moving point on the CAISO system (e.g., P-Node)

9 Key PPA Deal Points Term 20 year is typical; 25 years is better for utility scale projects No termination rights, except for default, long-term FM events Buy-out options (FMV, valuation, terms of buyout can be difficult) 6. Energy Product Parameters Energy ($/MWh) TOD Factors/Seasonal Pricing Storage, Shaping and Capacity Payments (utilities say that energy price usually includes capacity/resource adequacy attributes) Test power/initial operating period No separate price for capacity... yet 7. COD vs Placed in Service PPAs generally define and use commercial operation date, but IRS s placed-in-service date does not equal commercial operation date in all cases (IRS follows a 5-factor test); define COD equal to PIS Caution: Provision in PPA which provide that the COD is deemed to be a certain number of days after notice/testing/etc.

10 Key PPA Deal Points Performance Guarantees Insolation Risk & Production Guarantees: Bottom line: 24 month rolling, 70-80%, excluding FM, curtailments, and forced outages Capacity Guarantees are coming in the form of CAISO s New Availability Requirements 9. RECs, Environmental Attributes, GHG Emission Reductions Lots of possibilities, but usually sold as part of the energy Note: compliance risk and costs borne by Seller CPUC s recent TREC Decision is wreaking havoc on CA market and fundamental understanding of RECs 10. Governmental Charges/Taxes Buyer should bear federal, state, local sales, use, real property, personal property taxes, duties, assessments, public benefit charges, etc. (but not income taxes), but utilities do not usually do so

11 Key PPA Deal Points Good Industry Practice, Force Majeure, and Destruction of System Good Industry Practice, NOT Good Utility Practice FM: expressly include volcanic eruption, require actual notice of FM event, and allow for contributing factors leading to a FM event If project is completely destroyed, Seller should have option of whether to rebuild; if Seller does not rebuild, PPA is terminated; ROFO perhaps, but no ROFR 11. Assignment/Financing Consents, Cooperation and Assurances Buyer must agree to not unreasonably withhold, condition, or delay consents, estoppels, certificates, opinions of counsel, provided the foregoing does not materially change rights, benefits, or burdens.

12 Key PPA Deal Points Change in Law; Costs of Compliance Change in law should not be a FM event Price and whole PPA must be fixed regardless of change in law Costs of Compliance: Seller must bear the following burdens/costs for term of PPA: WREGIS requirements, GHG Emissions reporting requirements, Green Attributes requirements, Resource Adequacy benefits, and PIRP/EIRP costs. Most of these laws and programs are still under development and are subject to change; what if it becomes costly or impossible to comply? Answer: meaningful, financeable compliance caps and no default for commercially reasonable efforts to comply New Buyer Curtailment Provisions demonstrate how utility imposed openended commitments can make projects unfinanceable.

13 PUC Nevada Solution - 1 On March 22, 2007, the PUC of Nevada resolved this question of risk correctly and thereby enabled Nellis AFB Solar Project to be financed by MMA Renewable Ventures:

14 PUC Nevada Solution - 2 Application of Nevada Power Company..., Docket No (PUC Nevada Order, March 22, 2007)

15 The California PUC Solution STC [Standard Term and Condition] 1: CPUC Approval CPUC Approval means a final and non-appealable order of the CPUC, without conditions or modifications unacceptable to the Parties, or either of them, which contains the following terms: (a) approves this Agreement in its entirety, including payments to be made by the Buyer, subject to CPUC review of the Buyer s administration of the Agreement; and (b) finds that any procurement pursuant to this Agreement is procurement from an eligible renewable energy resource for purposes of determining Buyer s compliance with any obligation that it may have to procure eligible renewable energy resources pursuant to the California Renewables Portfolio Standard (Public Utilities Code Section et seq.), Decision , or other applicable law.

16 The California PUC Solution STC 6: Eligibility Seller, and, if applicable, its successors, represents and warrants that throughout the Delivery Term of this Agreement that: (i) the Project qualifies and is certified by the CEC as an Eligible Renewable Energy Resource ( ERR ) as such term is defined in Public Utilities Code Section or Section ; and (ii) the Project s output delivered to Buyer qualifies under the requirements of the California Renewables Portfolio Standard. To the extent a change in law occurs after execution of this Agreement that causes this representation and warranty to be materially false or misleading, it shall not be an Event of Default if Seller has used commercially reasonable efforts to comply with such change in law. Order Instituting Rulemaking to Implement the California Renewables Portfolio Standard Program, CPUC Docket , Decision (November 16, 2007)

17 Todd Glass Wilson Sonsini Goodrich & Rosati, PC

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT [This contract has been approved by the California Public Utilities Commission in Decision 13-05-034. Modification of the terms and conditions of this contract will result in the need to obtain additional

More information

Geothermal Energy and Its Value

Geothermal Energy and Its Value Geothermal Energy and Its Value Imperial Valley Renewable Energy Summit March16, 2016 Rahm Orenstein VP, Business Development Heber Geothermal Complex, CA, USA Green energy you can rely on Disclaimer Information

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON THIRD REVISED POWER PURCHASE AGREEMENT

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CLEAN COALITION COMMENTS ON THIRD REVISED POWER PURCHASE AGREEMENT BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program. Rulemaking

More information

POWER PURCHASE AND SALE AGREEMENT. between [BUYER S NAME] and [SELLER S NAME] (ID #[Number])

POWER PURCHASE AND SALE AGREEMENT. between [BUYER S NAME] and [SELLER S NAME] (ID #[Number]) POWER PURCHASE AND SALE AGREEMENT between [BUYER S NAME] and [SELLER S NAME] (ID #[Number]) Standard Contract for Qualifying Facilities with a Power Rating that is Less than or Equal to 20MW TERMS THAT

More information

August 25, Advice Letter 4677-E

August 25, Advice Letter 4677-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor August 25, 2015 Erik Jacobson Director, Regulatory Relations Pacific Gas and

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 62411-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 60693-E Sheet 1 BIOENERGY MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT

More information

BIOENERGY MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT

BIOENERGY MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT [This contract has been approved by the California Public Utilities Commission in Decision 15-09-004. Modification of the terms and conditions of this contract will result in the need to obtain additional

More information

ELECTRIC SCHEDULE E-CHPSA Sheet 1 (N) COMBINED HEAT AND POWER SIMPLIFIED UNDER 500 KW PPA

ELECTRIC SCHEDULE E-CHPSA Sheet 1 (N) COMBINED HEAT AND POWER SIMPLIFIED UNDER 500 KW PPA Original 30825-E ELECTRC SCHEDULE E-CHPSA Sheet 1 COMBNED HEAT AND POWER SMPLFED UNDER 500 KW PPA APPLCABLTY : This Schedule provides a power purchase agreement (PPA) for combined heat and power systems

More information

2013 RPS Solicitation Request for Proposals Conference. January 13, 2014

2013 RPS Solicitation Request for Proposals Conference. January 13, 2014 2013 RPS Solicitation Request for Proposals Conference January 13, 2014 Overview of the Conference Introduction Safety Moment Words from Senior Management Overview Elements of the Bidder s Conference Meet

More information

Marin Clean Energy 2016 Open Season Procurement Process Procedural Overview & Instructions

Marin Clean Energy 2016 Open Season Procurement Process Procedural Overview & Instructions 1) Introduction: Marin Clean Energy ( MCE ) has made a commitment to procuring increasing amounts of renewable and carbon-free energy for its customers. In fact, MCE s default retail service option, Light

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Request for Modifications to SCE s Renewable Auction Mechanism ( RAM ) Program Pursuant to Decision 10-12-048 Rulemaking 11-05-005 (Filed

More information

VALLEY CLEAN ENERGY ALLIANCE. Staff Report Item 12. Mitch Sears, Interim General Manager Gary Lawson, Sacramento Municipal Utility District (SMUD)

VALLEY CLEAN ENERGY ALLIANCE. Staff Report Item 12. Mitch Sears, Interim General Manager Gary Lawson, Sacramento Municipal Utility District (SMUD) VALLEY CLEAN ENERGY ALLIANCE Staff Report Item 12 TO: FROM: SUBJECT: Valley Clean Energy Alliance Board Mitch Sears, Interim General Manager Gary Lawson, Sacramento Municipal Utility District (SMUD) Procurement

More information

SCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS

SCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS SCHEDULE C ELECTRICITY PURCHASE AGREEMENT TERM SHEET TRANSMISSION AND LARGE DISTRIBUTION CONNECTED PROJECTS The following is a summary of the key terms and conditions of the proposed standard form electricity

More information

Southern California Edison s Renewable Auction Mechanism (RAM) Program. June 6, 2014 EPRG Workshop on Distributed Generation and Smart Connections

Southern California Edison s Renewable Auction Mechanism (RAM) Program. June 6, 2014 EPRG Workshop on Distributed Generation and Smart Connections Southern California Edison s Renewable Auction Mechanism (RAM) Program June 6, 2014 EPRG Workshop on Distributed Generation and Smart Connections The RAM Contracting Tool In D.10-12-048 ( the RAM Decision

More information

Prototype Wind PPA Term Sheet

Prototype Wind PPA Term Sheet Prototype Wind PPA Term Sheet Background: This Prototype Wind PPA Term Sheet ( Term Sheet ) sets forth the current requirements that PSE wants the Respondent to address or incorporate into any proposal

More information

June 13, Advice Letter 3884-E

June 13, Advice Letter 3884-E STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 13, 2012 Brian K. Cherry Vice President, Regulation and Rates Pacific

More information

FEED-IN TARIFF STANDARD FORM POWER PURCHASE AGREEMENT BETWEEN SACRAMENTO MUNICIPAL UTILITY DISTRICT AND

FEED-IN TARIFF STANDARD FORM POWER PURCHASE AGREEMENT BETWEEN SACRAMENTO MUNICIPAL UTILITY DISTRICT AND FEED-IN TARIFF STANDARD FORM POWER PURCHASE AGREEMENT BETWEEN SACRAMENTO MUNICIPAL UTILITY DISTRICT AND This POWER PURCHASE AGREEMENT (the Agreement ) for an Eligible Renewable Energy Resource ( Facility

More information

Schedule GTSR-CR Sheet 1 GREEN TARIFF SHARED RENEWABLES COMMUNITY RENEWABLES

Schedule GTSR-CR Sheet 1 GREEN TARIFF SHARED RENEWABLES COMMUNITY RENEWABLES Southern California Edison Revised Cal. PUC Sheet No. 59541-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 56740-E Schedule GTSR-CR Sheet 1 APPLICABILITY This Schedule is applicable

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA FILED 12/01/17 04:59 PM Order Instituting Rulemaking to Continue Implementation and Administration, and Consider Further Development of,

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 58812-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 55706-E Sheet 1 NET ENERGY METERING Form 14-935 (To be inserted by utility)

More information

UNIQUE ATTRIBUTES OF RENEWABLE POWER PURCHASE AGREEMENTS

UNIQUE ATTRIBUTES OF RENEWABLE POWER PURCHASE AGREEMENTS 11.11.2009 UNIQUE ATTRIBUTES OF RENEWABLE POWER PURCHASE AGREEMENTS Power Purchase Agreements ( PPA ) are highly negotiated long term agreements through which power producers (often referred to as sellers)

More information

ELECTRIC SCHEDULE E-CHP Sheet 1 (N) COMBINED HEAT AND POWER PPA

ELECTRIC SCHEDULE E-CHP Sheet 1 (N) COMBINED HEAT AND POWER PPA Original 30809-E ELECTRC SCHEDULE E-CHP Sheet 1 COMBNED HEAT AND POWER PPA APPLCABLTY: TERRTORY: RATES: This Schedule provides a power purchase agreement (PPA) for combined heat and power systems with

More information

D Los Angeles ""VV Department of

D Los Angeles VV Department of D Los Angeles ""VV Department of... P.Water & Power RESOLUTION NO.-------- BOARDLETTERAPPROVAL Senior Assistant General Manager Power System MARCIE L. EDWARDS General Manager DATE: May 13, 2015 SUBJECT:

More information

MARIN ENERGY AUTHORITY REQUEST FOR PROPOSALS

MARIN ENERGY AUTHORITY REQUEST FOR PROPOSALS MARIN ENERGY AUTHORITY REQUEST FOR PROPOSALS FOR LOCAL RENEWABLE ENERGY PROJECTS RFP RELEASE DATE: DECEMBER 3, 2010 RESPONSE DEADLINE: FEBRUARY 4, 2011 BY 2:00 P.M. TABLE OF CONTENTS Overview... 3 Background...

More information

1. FORWARD A. Tax Equity Due Diligence Summary FINANCING STRUCTURES OVERVIEW... 6

1. FORWARD A. Tax Equity Due Diligence Summary FINANCING STRUCTURES OVERVIEW... 6 C&I Solar Due Diligence Review Manual for Tax Equity Transactions A comprehensive guide to reviewing Commercial & Industrial or Distributed Generation Solar project documents for Partnership/Flip and Sale/Leaseback

More information

SCHEDULE C ELECTRICITY PURCHASE AGREEMENT - TERM SHEET SMALL PROJECTS

SCHEDULE C ELECTRICITY PURCHASE AGREEMENT - TERM SHEET SMALL PROJECTS SCHEDULE C ELECTRICITY PURCHASE AGREEMENT - TERM SHEET SMALL PROJECTS The following is a summary of the key terms and conditions of the proposed standard form electricity purchase agreement ( EPA ) for

More information

RENEWABLE FINANCING CONSIDERATIONS. Bond Buyer 2011 CA Public Finance Renewable Panel

RENEWABLE FINANCING CONSIDERATIONS. Bond Buyer 2011 CA Public Finance Renewable Panel RENEWABLE FINANCING CONSIDERATIONS Panel Federal and State Proposals and Regulations Issue Background and Status Effects Clean Water Act (CWA) Section 316(b) requires that the location, design, construction

More information

PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR ELECTRIC GENERATING FACILITES Customer Owned Generation-Distribution Rate (Schedule G-1)

PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR ELECTRIC GENERATING FACILITES Customer Owned Generation-Distribution Rate (Schedule G-1) PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR ELECTRIC GENERATING FACILITES Customer Owned Generation-Distribution Rate (Schedule G-1) This Agreement is entered into on by and between the City of Lompoc,

More information

PUBLIC SERVICE COMPANY OF NEW MEXICO AGREEMENT NO.

PUBLIC SERVICE COMPANY OF NEW MEXICO AGREEMENT NO. PUBLIC SERVICE COMPANY OF NEW MEXICO AGREEMENT NO. STANDARD LARGE SOLAR RENEWABLE ENERGY CERTIFICATE PURCHASE AGREEMENT FOR THIRD-PARTY OWNER PARTICIPATION IN PNM S SOLAR REC INCENTIVE PROGRAM SYSTEMS

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 63569-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 63569-E 61960-E Sheet 1 VIRTUAL NET METERING FOR MULTIFAMILY AFFORDABLE

More information

Corporate Renewable Energy Procurement

Corporate Renewable Energy Procurement Corporate Renewable Energy Procurement Legal Considerations & Market Trends 8/17/2016 Presented by Ann A. Hawkins / Nike O. Opadiran / Ethan M. Schultz Beijing / Boston / Brussels / Chicago / Frankfurt

More information

COM/MP1/avs DRAFT Agenda ID #9721 (Rev.6) Ratesetting 1/13/11 Item 44 Decision PROPOSED DECISION OF COMMISSIONER PEEVEY (Mailed 8/25/2010)

COM/MP1/avs DRAFT Agenda ID #9721 (Rev.6) Ratesetting 1/13/11 Item 44 Decision PROPOSED DECISION OF COMMISSIONER PEEVEY (Mailed 8/25/2010) COM/MP1/avs DRAFT Agenda ID #9721 (Rev.6) Ratesetting 1/13/11 Item 44 Decision PROPOSED DECISION OF COMMISSIONER PEEVEY (Mailed 8/25/2010) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No E.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No E. Southern California Edison Revised Cal. PUC Sheet No. 60051-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58818-E Sheet 1 VIRTUAL NET ENERGY METERING FOR GENERATING FACILITIES

More information

July 31, The Many Values of. Renewable Energy. Prepared For

July 31, The Many Values of. Renewable Energy. Prepared For The Many Values of Renewable Energy Prepared For About Duff & Phelps Duff & Phelps is the global advisor that protects, restores and maximizes value for clients in the areas of valuation, corporate finance,

More information

SUBJECT: Submission of the Tule Wind Contract for Procurement of Renewable Energy from SCEs 2014 Renewables Portfolio Standard Solicitation

SUBJECT: Submission of the Tule Wind Contract for Procurement of Renewable Energy from SCEs 2014 Renewables Portfolio Standard Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 May 25, 2016 Advice Letters 3287-E and 3287-E-A Russell G. Worden Director,

More information

Smart Grid Compressed Air Energy Storage Demonstration Project Request for Offers

Smart Grid Compressed Air Energy Storage Demonstration Project Request for Offers Smart Grid Compressed Air Energy Storage Demonstration Project Request for Offers (CAES RFO) 2015 PARTICIPANTS WEBINAR October 29, 2015 Q&A / Audio Replay PG&E will take questions via email only during

More information

SUBJECT: Submission of the Garland Contract for Procurement of Renewable Energy from SCE's 2014 RPS Solicitation

SUBJECT: Submission of the Garland Contract for Procurement of Renewable Energy from SCE's 2014 RPS Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 December 7, 2015 Advice Letters: 3273-E Russell G. Worden Director, State

More information

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 April 28, 2015 Advice Letter 3119-E Russell G. Worden Director, State Regulatory

More information

GENERATING FACILITY INTERCONNECTION AGREEMENT FOR MULTIPLE TARIFFS USING A NEM-ST GENERATING FACILITY SIZED GREATER THAN ONE MEGAWATT.

GENERATING FACILITY INTERCONNECTION AGREEMENT FOR MULTIPLE TARIFFS USING A NEM-ST GENERATING FACILITY SIZED GREATER THAN ONE MEGAWATT. Southern California Edison Revised Cal. PUC Sheet No. 60050-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58817-E Sheet 1 GENERATING FACILITY INTERCONNECTION AGREEMENT FOR MULTIPLE

More information

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION

Portland General Electric Company Sheet No SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION Portland General Electric Company Sheet No. 201-1 PURPOSE SCHEDULE 201 QUALIFYING FACILITY 10 MW or LESS AVOIDED COST POWER PURCHASE INFORMATION To provide information about Standard Avoided Costs and

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation ) ) ) Docket No. ER13-872-000 MOTION TO INTERVENE AND COMMENTS OF SOUTHERN CALIFORNIA

More information

Alignment of Key Infrastructure Planning Processes by CPUC, CEC and CAISO Staff December 23, 2014

Alignment of Key Infrastructure Planning Processes by CPUC, CEC and CAISO Staff December 23, 2014 Introduction and Summary Alignment of Key Infrastructure Planning Processes Since the restructuring of California s electric industry in the late 1990s pursuant to AB 1890, electric infrastructure planning

More information

PG&E s Bidders Webinar

PG&E s Bidders Webinar PG&E s Bidders Webinar PG&E s Request for Offers: Renewable Auction Mechanism, and Green Tariff Shared Renewables/Community Solar Choice July 14, 2015 Agenda Topics Introduction Solicitation Overview Eligibility

More information

CCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer

CCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer CCA 101: Policy and Governance Dawn Weisz, MCE Chief Executive Officer Presentation Overview Growth of CCA Core Policy Issues Exit Fees and Non-Bypassable Charges Future of California s Energy Policies

More information

REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS

REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS Issuance Date: July 1, 2013 The Narragansett Electric Company d/b/a National Grid i Table of Contents I. Introduction and Overview...1

More information

INTERCONNECTION & NET ENERGY METERING AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC GENERATING FACILITIES

INTERCONNECTION & NET ENERGY METERING AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC GENERATING FACILITIES D ECLARATIONS R EV 0 7. 21.2017 P G.1 CITY OF HEALDSBURG, ELECTRIC DEPARTMENT INTERCONNECTION & NET ENERGY METERING AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC GENERATING FACILITIES DECLARATIONS

More information

NET-ENERGY METER AGGREGATION INTERCONNECTION AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC CUSTOMERS

NET-ENERGY METER AGGREGATION INTERCONNECTION AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC CUSTOMERS CITY OF HEALDSBURG, ELECTRIC DEPARTMENT NET-ENERGY METER AGGREGATION INTERCONNECTION AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC CUSTOMERS DECLARATIONS ( Customer ) and the City of Healdsburg ( City

More information

Schedule GTSR-GR Sheet 1 GREEN TARIFF SHARED RENEWABLES GREEN RATE

Schedule GTSR-GR Sheet 1 GREEN TARIFF SHARED RENEWABLES GREEN RATE Southern California Edison Revised Cal. PUC Sheet No. 59547-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 56750-E Schedule GTSR-GR Sheet 1 APPLICABILITY This Schedule is applicable

More information

Structuring Solar PV Agreements: Negotiating Real Estate Entitlements and Offtake Agreements

Structuring Solar PV Agreements: Negotiating Real Estate Entitlements and Offtake Agreements Presenting a live 90-minute webinar with interactive Q&A Structuring Solar PV Agreements: Negotiating Real Estate Entitlements and Offtake Agreements THURSDAY, APRIL 30, 2015 1pm Eastern 12pm Central 11am

More information

Appendix B-2. Term Sheet for Tolling Agreements. for For

Appendix B-2. Term Sheet for Tolling Agreements. for For Appendix B-2 Term Sheet for Tolling Agreements for For 2015 Request For Proposals For Long-Term Developmental Combined-Cycle Gas Turbineand Existing Capacity and Energy Resources in WOTAB DRAFT Entergy

More information

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Nancy Saracino, Vice President, General Counsel & Chief Administrative Officer Date: September 7, 2012 Re:

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 61965-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58811-E Sheet 1 SOUTHERN CALIFORNIA EDISON COMPANY 10 KILOWATT OR LESS

More information

2. IDENTITY AND LOCATION OF GC

2. IDENTITY AND LOCATION OF GC INTERCONNECTION AND NET ENERGY METERING AGREEMENT FOR LARGE COMMERCIAL CUSTOMERS OF A SOLAR, WIND OR HYBRID OF BOTH GENERATING FACILITY HAVING A CAPACITY OF 30 KW TO 1,000 KW DECLARATIONS This Interconnection

More information

Request for Proposals. Renewable Resources (2016R RFP) ISSUED: Monday, April 11, DUE DATE: Friday, May 20, :00 PM PPT

Request for Proposals. Renewable Resources (2016R RFP) ISSUED: Monday, April 11, DUE DATE: Friday, May 20, :00 PM PPT Request for Proposals Renewable Resources (2016R RFP) ISSUED: Monday, April 11, 2016 DUE DATE: Friday, May 20, 2016 5:00 PM PPT 2016R RFP Responses: PacifiCorp RFP 2016R Attention: Origination 825 NE Multnomah,

More information

RMR and CPM Enhancements Stakeholder Conference Call December 20, 2018

RMR and CPM Enhancements Stakeholder Conference Call December 20, 2018 RMR and CPM Enhancements Stakeholder Conference Call December 20, 2018 Keith Johnson Infrastructure & Regulatory Policy Manager Agenda Time Item Presenter 10:00-10:15 1. Stakeholder process and general

More information

INVITATION FOR EXPRESSIONS OF INTEREST

INVITATION FOR EXPRESSIONS OF INTEREST INVITATION FOR EXPRESSIONS OF INTEREST DMS # 3292795 v2 TABLE OF CONTENTS 1. DISCLAIMER... 1 2. GLOSSARY... 2 3. INTRODUCTION... 4 3.1 Purpose of this Invitation... 4 3.2 Western Australian renewable energy

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA REPLY COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA REPLY COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop an Electricity Integrated Resource Planning Framework and to Coordinate and Refine Long-Term Procurement

More information

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 August 21, 2015 Advice Letter 3120-E Russell G. Worden Director, State Regulatory

More information

Joint Development Agreements in Renewable Energy Projects

Joint Development Agreements in Renewable Energy Projects Presenting a live 90-minute webinar with interactive Q&A Joint Development Agreements in Renewable Energy Projects Selection of Partner, Agreement Structure, Planning for Involuntary Early Endings, Avoiding

More information

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: SCE Utility Number/Type: U 338-E Advice Letter Number(s): 3660-E Date AL(s) Filed: September 25, 2017 Utility Contact Person: Darrah Morgan

More information

Business Practice Manual For. Generator Management. Version 8

Business Practice Manual For. Generator Management. Version 8 Business Practice Manual For Generator Management Version 8 Revision Date: June 30, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine BPM Owner s Title:

More information

INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS

INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS TABLE OF CONTENTS SECTION TITLE PAGE 1. CUSTOMER-GENERATOR RENEWABLE ELECTRICAL GENERATING

More information

Going Green What Every College or University President Needs to Know about Renewable Energy Renewable Energy on Campus

Going Green What Every College or University President Needs to Know about Renewable Energy Renewable Energy on Campus Going Green What Every College or University President Needs to Know about Renewable Energy By Lee Goodwin, Richard Cogen, and Michael Cooney Cambridge, Palo Alto, the Research Triangle... academic institutions

More information

SUBJECT: Submission of the Sun Streams Contract for Procurement of Renewable Energy from SCEs 2014 Renewables Portfolio Standard Solicitation

SUBJECT: Submission of the Sun Streams Contract for Procurement of Renewable Energy from SCEs 2014 Renewables Portfolio Standard Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 20, 2016 Advice Letters: 3333-E & 3333-E-A Russell G. Worden Managing

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator ) Docket No. ER14-2824-000 Corporation ) ) MOTION TO INTERVENE, LIMITED PROTEST AND COMMENTS

More information

2011 All Source RFP Exhibit I

2011 All Source RFP Exhibit I Prototype Natural Gas Tolling Agreement Term Sheet Background: This Prototype Natural Gas Tolling Agreement Term Sheet ( Term Sheet ) sets forth the current requirements that PSE wants the Respondent to

More information

Due Diligence checklist for [insert project name]

Due Diligence checklist for [insert project name] Due Diligence checklist for [insert project name] Draft February 2016 PricewaterhouseCoopers, ABN 52 780 433 757 Darling Park Tower 2, 201 Sussex Street, GPO BOX 2650, SYDNEY NSW 1171 T: +61 2 8266 0000,

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 61962-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 61237-E Sheet 1 GENERATING FACILITY INTERCONNECTION AGREEMENT Form (Continued)

More information

Solar Power Purchase Agreement

Solar Power Purchase Agreement Solar Power Purchase Agreement This Solar Power Purchase Agreement (this Agreement ) is dated as of [ ] (the Effective Date ), and is witnessed, acknowledged, and executed by authorized representatives

More information

Clean Coalition comments on Proposed CREST PPA

Clean Coalition comments on Proposed CREST PPA Southern California Edison CREST Reform Clean Coalition comments on Proposed CREST PPA Tam Hunt, Attorney and Policy Advisor for the Clean Coalition June 22, 2011 1 Clean Coalition Comments on Proposed

More information

Direct Purchasing and PPAs 101

Direct Purchasing and PPAs 101 Direct Purchasing and PPAs 101 PPA Fundamentals Kevin Rackstraw Vice President, Customer Solutions REM Conference October 19, 2015 CFR is a Different Kind of Supplier: A Renewable Energy Integrator Our

More information

Solar*Rewards REC Purchase Contract Customer-Owned PV Systems Greater than 25 kw DC nameplate capacity

Solar*Rewards REC Purchase Contract Customer-Owned PV Systems Greater than 25 kw DC nameplate capacity Application ID: {Opportunity ID} Solar*Rewards REC Purchase Contract Customer-Owned PV Systems Greater than 25 kw DC nameplate capacity This Contract is made and entered into {Todays Date}, by and between

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 61967-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58820-E Sheet 1 SOUTHERN CALIFORNIA EDISON COMPANY FACILITY INTERCONNECTION

More information

Solar: Wind: Total: (AC Nameplate Rating) x (720 hrs/mo) x (0.15 = solar/ 0.10 = wind) Date(s) of Parallel Operation Rebate Expiration

Solar: Wind: Total: (AC Nameplate Rating) x (720 hrs/mo) x (0.15 = solar/ 0.10 = wind) Date(s) of Parallel Operation Rebate Expiration APPLICATION FOR THE INTERCONNECTION OF A SOLAR OR WIND POWERED ELECTRICAL GENERATING FACILITY TO BE USED FOR NET ENERGY METERING SERVICE APPLICABILITY This application is for the interconnection of a solar,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ALJ/BWM/sid Mailed 7/27/2007 Decision 07-07-027 July 26, 2007 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration

More information

January 26, /14/2011http://docs.cpuc.ca.gov/WORD_PDF/FINAL_DECISION/ pdf.

January 26, /14/2011http://docs.cpuc.ca.gov/WORD_PDF/FINAL_DECISION/ pdf. Bruce A. Measure Chair Montana Rhonda Whiting Montana W. Bill Booth Idaho James A. Yost Idaho Dick Wallace Vice-Chair Washington Tom Karier Washington Bill Bradbury Oregon Joan M. Dukes Oregon January

More information

SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) 2011 RENEWABLES PORTFOLIO STANDARD PROCUREMENT PLAN VOLUME 1

SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) 2011 RENEWABLES PORTFOLIO STANDARD PROCUREMENT PLAN VOLUME 1 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program. ) ) ) )

More information

ASSET MANAGEMENT WEBINAR SERIES

ASSET MANAGEMENT WEBINAR SERIES ASSET MANAGEMENT WEBINAR SERIES Rick Brown, PhD President TerraVerde Energy rick.brown@terraverde.energy David Burdick VP Asset Management TerraVerde Energy david@terraverde.energy INTRODUCTIONS TerraVerde

More information

SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) AMENDED 2011 RENEWABLES PORTFOLIO STANDARD PROCUREMENT PLAN VOLUME 1

SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) AMENDED 2011 RENEWABLES PORTFOLIO STANDARD PROCUREMENT PLAN VOLUME 1 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program. ) ) ) )

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59895-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57290-E GENERATING FACILITY INTERCONNECTION AGREEMENT (Non-Exporting)

More information

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

FEED-IN TARIFF CONTRACT (FIT CONTRACT) FEED-IN TARIFF CONTRACT (FIT CONTRACT) Version 1.5.1 (July 15, 2011) CONTRACT IDENTIFICATION # FIT REFERENCE # FIT- FIT- CONTRACT DATE SUPPLIER SUPPLIER S ADDRESS SUPPLIER INFORMATION GROSS NAMEPLATE CAPACITY

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop an Electricity Integrated Resource Planning Framework and to Coordinate and Refine Long-Term Procurement

More information

Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating)

Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating) Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating) This Up Front Incentive Renewable Energy Credit Purchase Agreement ( Agreement ) is hereby made and entered

More information

We Energies. Request for Proposal Renewable Energy Supply 2014

We Energies. Request for Proposal Renewable Energy Supply 2014 We Energies Request for Proposal Renewable Energy Supply 2014 Page 2 of 12 I. Introduction A. Summary of Request for Proposals Wisconsin Electric Power Company (We Energies) requests proposals (Proposals)

More information

ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT

ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT THIS STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT ( Agreement ) is made and entered

More information

Financing Utility Scale Solar

Financing Utility Scale Solar Financing Utility Scale Solar Matt Handel Vice President Solar, Distributed Generation & Storage August 25, 2016 Headquartered in Juno Beach, FL, NextEra Energy, Inc. has operations in 27 states, Canada,

More information

Solar*Rewards REC Purchase Contract Customer-Site PV Systems For Third Party PV Developers

Solar*Rewards REC Purchase Contract Customer-Site PV Systems For Third Party PV Developers Application ID: 1. 2. 3. 4. Solar*Rewards REC Purchase Contract Customer-Site PV Systems For Third Party PV Developers This Contract is made and entered into, by and between Public Service Company of Colorado

More information

Solar Power in Small Municipalities

Solar Power in Small Municipalities Solar Power in Small Municipalities March 30, 2011 Agenda Why Solar? Regulatory Environment & Incentives Technologies Selecting a Site Financing Structures Why Solar? Costs are Coming Down Federal and

More information

SCHEDULE VNM-A-ST Sheet 1

SCHEDULE VNM-A-ST Sheet 1 Original Cal. P.U.C. Sheet o. 27707-E San Diego, California Canceling Cal. P.U.C. Sheet o. SCHEDULE VM-A-ST Sheet 1 VIRTUAL ET EERGY METERIG FOR MULTIFAMILY AFFORDABLE HOUSIG SUCCESOR APPLICABILITY Optionally

More information

Form No. 23 DECLARATIONS

Form No. 23 DECLARATIONS GOLDEN STATE WATER COMPANY Revised Cal. P.U.C. Sheet No. 1579-E SAN DIMAS, CALIFORNIA 91773-9016 Canceling Original Cal. P.U.C. Sheet No. 1506-E DECLARATIONS Page 1 This Interconnection Agreement ("Agreement")

More information

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 March 19, 2015 Advice Letters: 3124-E Russell G. Worden Director, State Regulatory

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration, and Consider Further Development of, California Renewables

More information

Community Choice Aggregation

Community Choice Aggregation Community Choice Aggregation Base Case Feasibility Evaluation County of Marin Prepared By Navigant Consulting, Inc March 2005 2 EXECUTIVE SUMMARY This report offers Navigant Consulting, Inc. s (NCI) evaluation

More information

SolarCurrents Program Agreement

SolarCurrents Program Agreement SolarCurrents Program Agreement This SolarCurrents Agreement, including all exhibits hereto ( Agreement ) is made by and between DTE Electric Company ( DTE ), a Michigan corporation, whose address is One

More information

PENINSULA CLEAN ENERGY JPA Board Correspondence

PENINSULA CLEAN ENERGY JPA Board Correspondence Item No. 10 PENINSULA CLEAN ENERGY JPA Board Correspondence DATE: June 16, 2017 BOARD MEETING DATE: June 22, 2017 SPECIAL NOTICE/HEARING: None VOTE REQUIRED: None TO: FROM: SUBJECT: Honorable Peninsula

More information

Please Refer to Attached Sample Form

Please Refer to Attached Sample Form Revised Cal. P.U.C. Sheet No. 41131-E Cancelling Revised Cal. P.U.C. Sheet No. 41004-E* U 39 San Francisco, California Electric Sample Sheet 1 Interconnection Agreement for Net Metering for a Renewable

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Review, Revise, and Consider Alternatives to the Power Charge Indifference Adjustment. Rulemaking 17-06-026

More information

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY SMART PROVISION

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY SMART PROVISION Page 1 of 15 1.0 Purpose The operation of the SMART Provision is pursuant to the Solar Massachusetts Renewable Target ( SMART ) Program regulations at 225 CMR 20.00 promulgated pursuant to Chapter 75 of

More information

Please Refer to Attached Sample Form

Please Refer to Attached Sample Form Revised Cal. P.U.C. Sheet No. 41124-E Cancelling Revised Cal. P.U.C. Sheet No. 40736-E U 39 San Francisco, California Electric Sample Form No. 79-1069 Sheet 1 Generating Facility Interconnection Agreement

More information

SUBJECT: Submission of the Maverick Solar, LLC Contract for Procurement of Renewable Energy from SCE's 2015 RPS Solicitation

SUBJECT: Submission of the Maverick Solar, LLC Contract for Procurement of Renewable Energy from SCE's 2015 RPS Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 July 6, 2017 Advice Letter 3562-E Russell G. Worden Director, State Regulatory

More information