Enhance Your Understanding of the Truth in Negotiations Act (TINA)

Size: px
Start display at page:

Download "Enhance Your Understanding of the Truth in Negotiations Act (TINA)"

Transcription

1

2 Enhance Your Understanding of the Truth in Negotiations Act (TINA) Breakout Session # B10 Janie L Maddox, Lecturer, U.S. Naval Postgraduate School Brent Calhoon, Partner, Baker Tilly Samantha Schwellenbach, Faculty Associate, U.S. Naval Postgraduate School Date July Time 2:30 3:45

3 Discussion Topics Basis in Law / Evolution TINA s Purpose Misperceptions of TINA Implementation of TINA TINA Thresholds Applicability & Exceptions How Offerors can Challenge Applicability What is Certified Cost Or Pricing Data? Judgment vs. Facts What is Data Other Than Certified Cost Or Pricing Data Certification of Cost or Pricing Data Defective Pricing- What is it? TINA Sweeps-What are they? Government Reliance Compliance Best Practices How can COs make TINA work Defective Pricing Liability Burden of Proof in Defective Pricing Possible Contractor Defenses 2

4 Basis in Law / Evolution Prior to 1962, businesses (offerors) submitting bids to the government were not held to any substantial requirement for disclosing all relevant cost or pricing information prior to conclusion of negotiations In 1962, the Truth-in-Negotiations Act (PL ; 10 U.S.C. 2306(a)), often referred to as TINA, was enacted to place DOD on equal footing in negotiating contract prices with commercial organizations In the mid-1980s the Government started treating defective pricing as an indication of criminal fraud In 1994, FASA extended TINA to civilian executive branch departments In 1995, FARA broadened exceptions to include commercial items In 2010, distinction added between certified cost or pricing data and data other than certified cost or pricing data, threshold -$700,000 In 2012, TINA turned 50 3

5 TINA s Purpose - Key Points TINA is intended to protect the Government when an offeror s cost is a significant factor in negotiating contract price In the absence of some objective indication of price reasonableness e.g., competition the government needs a mechanism to ensure it pays a fair and reasonable price TINA supports this need and seeks to level the negotiation playing field by placing the Government in the same position as offerors So, Government negotiators have access to the same cost or pricing data as the offeror s negotiators and recourse when its not submitted However, TINA does not create an equal position between the Government and the offeror There is no corresponding obligation on the part of the Government to disclose anything to the offeror 4

6 Misperceptions of TINA After all this time, considerable confusion remains: What is cost or pricing data? - Judgment vs. Facts? What must be done with it? (Contractors and Government) Under what circumstances can the Government request cost or pricing data and when and how much must a contractor provide it? What do terms like reliance, meaningful disclosure and sweep mean? When must contractors certify their cost or pricing data? Do contractors certify their proposal? What is data other than certified cost or pricing data? - How is it different from "certified cost or pricing data? What risks do contractors face when certification is required and when it isn t, but data is nevertheless requested by the Government? 5

7 TINA Implemented thru FAR subpart 15.4 Describes the contracting officer s responsibility to purchase supplies and services at fair and reasonable prices Establishes requirements for the submission of cost or pricing data (whether or not certified ) Establishes the circumstances under which a offeror must certify the accuracy, completeness and currency of cost or pricing data If certified cost or pricing data is required, establishes: - What the contracting officer must do with that data - How to document the extent to which the contracting officer relied on the offeror s certified data to negotiate the contract price Provides right of Government to examine offeror records (audit) Applicable Clauses FAR and Specifies proposal format (FAR Table 15-2 Instructions for Submitting Cost/Price Proposals) 6

8 TINA Thresholds $100,000 for contracts awarded before December 1, 1990 $500,000 for contracts awarded on or after December 1, 1990 $550,000 for contracts awarded on or after October 11, 2000 $650,000 for contracts awarded on or after September 28, 2006 $700,000 for contracts awarded on or after October 1, 2010 Note: CO s can request cost or pricing data for contract awards between the Simplified Acquisition Threshold and the cost or pricing data threshold with HCA approval 7 7

9 Applicability of TINA Negotiated prime contracts > $700,000 Prime contract modification or changes >$700,000 Aggregate absolute value of related modifications Negotiated subcontracts, modifications or changes > $700,000 at any tier, if prime contract and higher-tier subcontractor(s) were required to provide certified cost or pricing data 8

10 Applicability (cont.) Contract Modifications Applicability One must consider both price adjustment increases and decreases in terms of absolute values to determine if the adjustment requires the submittal of cost or pricing data. For example A price reduction of $500,000 and a price increase of $300,000 result in a net reduction of $200,000. However, if the sum of the absolute values exceeds the current TINA threshold cost or pricing data must be submitted. Price Reduction $ (500,000) $ 500,000 Price Increase 300,000 $ 300,000 Net Price Reduction $ (200,000) $ 800,

11 Applicability (cont.) Prime must obtain cost or pricing data for any TINA covered subcontract greater than $700,000, but only if prime is covered also Prime must submit (or cause submission of) the sub s data to the Government on a covered subcontract with a value that is either - $12.5 million dollars or more, or - $700,000 and more than 10% of the prime s proposed price The exercise of an option with previously agreed pricing is not a contract pricing action subject to TINA requirements 10

12 Exceptions from TINA Adequate Price Competition Prices Set by Law or Regulation Commercial Items Pricing Actions Less Than $700,000 Exceptional Cases Waiver by Head of Contracting Activity Modifications of Commercial Items-limited by standards 11

13 How Offerors Can Challenge and/or Avoid Applicability COs are not to insist on certified cost or pricing data where competition gives adequate assurances of price reasonableness Therefore Offerors should actively challenge demands by the Government or prime offerors for data/certification where price competition exists Get the exemption in writing. At least document your understanding that the exemption applies **Note: Ultimately the law gives COs discretion to require data in any appropriate circumstance, even where there is indication of price competition. o Offerors should emphasize the FAR policy statement that is not in the Government s best interest to unnecessarily require submission of data 12

14 What is Certified Cost or Pricing Data? All facts that, as of the date of price agreement, or, if applicable, an earlier date agreed upon by the parties that is as close as practicable to the date of price agreement, prudent buyers and sellers would reasonably expect to affect price negotiations significantly The concept of significant affect is not defined in the FAR and often ignored by Government auditors; almost every dollar is considered significant no amount is too small to pursue But, the DCAA Audit manual states that TINA price adjustments of up to 5% of the contract value or $50,000, whichever is less, normally should be considered immaterial 13

15 Certified Cost or Pricing Data (cont.) What are facts? Objective, verifiable information Cannot be determined based solely on the type of document. You must consider the nature of the information in the context of the particular negotiation in question. Each disclosure situation should be separately analyzed. Some things as a matter of common sense should be considered data. Other cases are much more difficult to assess Judgments and pure estimates are not cost or pricing data This has always been the law and this was affirmed in 1986 amendments to TINA and in the Texas Instruments case 14

16 Certified Cost or Pricing Data (cont.) Cost or pricing data includes more than just historical accounting data; they are all facts reasonably relevant to evaluate estimates of future costs and to the validity of costs already incurred. This may include, but is not limited to: - Vendor quotes; - Nonrecurring costs; - Information on changes in production methods and in production or purchasing volume; - Data supporting projections of business prospects and objectives and related operations costs; - Unit-cost trends such as yield rates and labor efficiency; - Make-or-buy decisions; - Estimated resources to attain business goals; and - Some information on significant management decisions 15

17 Judgment vs. Facts Offerors must disclose all facts necessary for the Government to evaluate - Judgmental forecasts of future business is not a fact - Bids outstanding or in the process are facts - Your bottom line for negotiations is not a fact (cost or pricing data) There may be a duty to disclose information that is a mix of fact and judgment, if judgment is necessary to understand the facts The fact that a management judgment has been made may be disclosable - e.g., a decision to invest in new equipment, a decision on make vs. buy Offerors are not liable for the accuracy of any judgmental estimate but must disclose all underlying factual data relating to those judgments, even if such data was not actually used in preparing estimates, - e.g., Estimates that essentially are verifiable, mathematical calculations rather than the result of applied judgment - It s the facts by which the future is estimated that s certified cost or pricing data 16

18 What is Data Other Than Certified Cost Or Pricing Data? Definition:.Such data may include the identical types of data as certified cost or pricing data, consistent with Table 15-2 of , but without the certification FAR Government will request with the expectation the contractor will provide But what exactly is it? Data to the extent necessary for the CO to determine a fair and reasonable price, such as: - Cost Data to determine the cost realism of competing offerors; and/or evaluate competing approaches - Price Data related to prices for commercial items t e.g., established catalog or market prices, sales to non-governmental and governmental entities Note: A contractor or subcontractor who fails to submit requested data is ineligible for award. FAR (a)(4) 17

19 Certification of Cost or Pricing Data Certification states that, to the best of the signatory s knowledge and belief that the cost or pricing data are accurate, complete, and current - Accurate: Cost or pricing data is free of error or misstatement - Current: The most recent data available up to the date of agreement, or other agreed to date, is submitted or disclosed - Complete: All reasonably available data relevant to the pricing action is submitted or disclosed The obligation to provide certified cost or priding data creates potential defective pricing liability and increased risk of fraud and false claims allegations for non-compliance 18

20 Certificate of Current Cost or Pricing Data (FAR ) This is to certify that, to the best of my knowledge and belief, the cost or pricing data (as defined in Section of the Federal Acquisition Regulation (FAR) and required under FAR subsection ) submitted, either actually or by specific identification in writing, to the Contracting officer or to the Contracting Officer s representative in support of * are accurate, complete, and current as of **. This certification includes the cost or pricing data supporting any advance agreements and forward pricing rate agreements between the offeror and the Government that are part of the proposal. Firm Signature Name Title Date of execution** *Identify the proposal, request for price adjustment or other submission involved, in giving the appropriate identify number (e.g., RFP No.). **Insert the day, month, and year when price negotiations were concluded and price agreement was reached, or, if applicable, an earlier data agreed upon between the parties that is as close as practicable to the date of agreement on price. 19

21 Defective Pricing - What is it? Defective pricing occurs when a contractor does not submit or disclose to the Government certified cost or pricing data that is accurate, complete, and current prior to reaching a price agreement. Defective pricing generally discovered during post-award audits during which records and data are examined and analyzed. Generally, Fixed Price contracts rather than Cost Reimbursable The objective of a post-award audit is to determine if the negotiated contract price was increased by a significant amount because the contractor did not submit or disclose accurate, complete, and current cost or pricing data. Penalties are assessed against payments made to Contractor to include offsets of higher costs by Contractor as long as the defective pricing is not considered intentional

22 TINA Sweeps What are they? Offeror s Obligation to Update Data Process whereby contractor reviews its records to determine if more current cost or pricing data exists and needs to be disclosed Offerors perform sweeps - After initial proposal submission and subsequent to proposal revisions - Prior to negotiations and before signing certificate - Generally occurs after negotiations (hand shake) but before contract award A sweep is not specifically required by regulations; it is a best practice internal control designed to improve TINA compliance Sweeps focus on new factual data that may significantly affect price negotiations 21

23 Government Reliance Occurs when Government negotiators directly or indirectly use or establish a price (or objective) wholly or partly based upon or derived from cost or pricing data the contractor submitted When an offeror is required to disclose and certify its cost or pricing data, the Government is required to Document in the PNM the extent to which the contracting officer (i) Relied on the certified cost or pricing data submitted and used them in negotiating the price; (ii) Recognized as inaccurate, incomplete, or noncurrent any certified cost or pricing data submitted; the action taken by the contracting officer and the contractor as a result; Possession of a Certificate of Current Cost or Pricing Data is not a substitute for examining and analyzing the offeror s proposal (FAR (d)) 22

24 Compliance Best Practices Challenge/avoid Applicability Offerors should pursue earlier cut-off date agreements allowed by regulations. Not often used, but a good solution for both sides Multiple Certifications (Pre-agreement, Post-agreement) No certifications in blank specify what data (facts) are being certified Prepare for Proposal submission, TINA sweeps, and Certificate submission. Submit proposal IAW FAR Table 15-2 and DFARS Proposal Adequacy Checklist Knowledge/education of senior leadership and establish clear roles for certificate signatory(s) 23

25 How Can COs Make TINA Work? Making sure the solicitation specifies: - Whether certified cost or pricing data are required; - And the offeror may submit a request for exception - Whether data other than certified cost or pricing data are required - The necessary pre-award or post-award access to the offeror s records; - Format required for submission of data Don t require the submission of cost or pricing data when adequate competition is anticipated Start negotiations as soon as possible after receipt of proposal Don t delay negotiations once initiated so limited updates are necessary Negotiations should be directed toward the offeror s submitted data, with revisions made in that data iaw the audit results and technical analyses Attempts at offering to settle at a total price figure, without defining how the total was derived from the data, could result in rendering TINA useless PNM Documentation of reliance of offerors data or lack thereof 24

26 Defective Pricing Liability Government gets price reduction for relying, to its detriment, on defective cost or pricing data. Currently, the Government also may: - Collect interest from the date of overpayment, and - Assess penalties for knowing submission of defective data Liability is statutory. A prime contractor may be liable regardless of whether data was submitted or a certificate was signed. While the law applies to subcontractors, there is no direct liability from subcontractors to the Government The Government may audit subcontractors and assess price reductions but against primes A prime contractor s ability to pass price reductions on to subcontractors depends on whether there are effective flowdowns and indemnities in the subcontract 25

27 Burden Of Proof In Defective Pricing Government must prove that: Data meets the definition of cost or pricing data; Data existed and was reasonably available before the date of agreement on price; Data submitted was not accurate, current, or complete; Undisclosed data was the type that prudent buyers or sellers would have reasonably expected to have a significant effect upon price negotiations; Government relied on the defective data; and Government s reliance on the defective data caused an increase in the contract price. 26

28 Possible Contractor Defenses Show: - TINA does not apply, not certifiable cost or pricing data - data at issue is not factual, is only judgmental(guesstimate) - there was adequate disclosure of facts - the Government actually knew the facts, even if you didn t disclose (asserting a government should have known is not a defense) - there was no Govt. reliance on the defective data - there would have been no impact on price if data were disclosed Challenge: - DCAA s use of data in calculating recommended reductions - DCAA sampling techniques Double-check DCAA s math and assumptions for consistency with your own or those established in negotiations Insist on use of negotiated, overheads and profits rates to calculate refunds, rather than proposal rates. Consistent with DCAA Audit Manual Substantiate that the price was a floor - would not have gone lower 27

29 Possible Contractor Defenses (cont.) Establish Offsets No affirmative recovery; just offsets Do your own reverse audits; look for undisclosed, higher data Can only offset for defective facts; not mistaken judgments Data must have been reasonably available at handshake date No offsets for intentional decisions not to use/disclosure higher priced data No offsets for bottom-line reductions May have offsets for negotiation reductions that are attributed e.g., to labor, material, overhead rates May offset cross category e.g., offset materials costs with labor costs No cross-contract offsets; but possible arguments regarding multiple orders handle via single bottom line negotiation. 28

30 Questions, Comments & Banter? Janie L Maddox Lecturer U.S. Naval Postgraduate School jlmaddox@nps.edu Brent Calhoon, CPA Partner Baker Tilly brent.calhoon@bakertilly.com Samantha Schwellenbach Faculty Associate U.S. Naval Postgraduate School slschwel@nps.edu 29

Truth in Negotiations Act (TINA) Essentials

Truth in Negotiations Act (TINA) Essentials Truth in Negotiations Act (TINA) Essentials Breakout Session #: F03 Presented by: Brent Calhoon, Partner, Baker Tilly Shingai Mavengere, Senior Manager, Baker Tilly Date: Tuesday, July 23 Time: 4:00pm-5:15pm

More information

PCI s Trending Cost & Pricing Series 2017 Defective Pricing Hazards and Defenses December 21, government contracting

PCI s Trending Cost & Pricing Series 2017 Defective Pricing Hazards and Defenses December 21, government contracting PCI s Trending Cost & Pricing Series 2017 Defective Pricing Hazards and Defenses December 21, 2017 1 Your hosts Bill Walter Executive Director Government Contract Advisory Services Dixon Hughes Goodman

More information

Cost Estimating and Truthful Cost or Pricing Data Requirements

Cost Estimating and Truthful Cost or Pricing Data Requirements Cost Estimating and Truthful Cost or Pricing Data Requirements Steven M. Masiello Jeremiah J. McIntyre Agenda Cost Estimating FAR cost estimating DFARS cost estimating system rule Government Proposal Analysis

More information

International Cost Estimating & Analysis Association. Supplier Cost/Price Analyses June 20, 2013

International Cost Estimating & Analysis Association. Supplier Cost/Price Analyses June 20, 2013 International Cost Estimating & Analysis Association Supplier Cost/Price Analyses June 20, 2013 David Eck and Todd W. Bishop Dixon Hughes Goodman LLP Government Contract Consulting Services Group Agenda

More information

Student Guide CON 170. Fundamentals of Cost and Price Analysis. Unit 1, Lesson 2 Truth In Negotiations Act

Student Guide CON 170. Fundamentals of Cost and Price Analysis. Unit 1, Lesson 2 Truth In Negotiations Act Student Guide CON 170 Fundamentals of Cost and Price Analysis Unit 1, Lesson 2 Truth In Negotiations Act October 2015 Notes Page 2 CON 170, Unit 1, Lesson 2, The Truth in Negotiations Act Lesson Presentation

More information

MG-3 - Supplier Cost Price Analyses Best Practices for Evaluating Supplier Proposals and Quotes

MG-3 - Supplier Cost Price Analyses Best Practices for Evaluating Supplier Proposals and Quotes International Cost Estimating & Analysis Association - Supplier Cost / Price Analyses June 10-13, 2014 Presented By: David Eck, CPA Director Mike Mardesich, CPA Manager Dixon Hughes Goodman Government

More information

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 1, Lesson 2 Truth In Negotiations Act

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 1, Lesson 2 Truth In Negotiations Act STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 1, Lesson 2 Truth In Negotiations Act October 2016 STUDENT PREPARATION Required Student Preparation Read TINA Language, FAR Part 15, DFARS

More information

TINA Sweeps and Defective Pricing (Part 1 of 2) Written by Nick Sanders

TINA Sweeps and Defective Pricing (Part 1 of 2) Written by Nick Sanders Many government contract compliance practitioners are aware of the Truth-in-Negotiations Act (or Truthful Cost or Pricing Data) or whatever the kids are calling it these days (I m calling it TINA). Whatever

More information

Adequacy of Proposals for. Global Supply Chain

Adequacy of Proposals for. Global Supply Chain Adequacy of Proposals for Global Supply Chain 1 Adequacy of Proposals Objectives This resource document covers the following: An overview of the proposal process, including applicable FAR (Federal Acquisition

More information

UNCLASSIFIED. ACC-Warren Industry Engagement Session #2 27 January Certified Cost or Pricing Data. Chief, Pricing Division

UNCLASSIFIED. ACC-Warren Industry Engagement Session #2 27 January Certified Cost or Pricing Data. Chief, Pricing Division ACC-Warren Industry Engagement g Session #2 27 January 2015 Certified Cost or Pricing Data Rich Kulczycki Chief, Pricing Division Agile Proficient Trusted UNCLASSIFIED Certified Cost or Pricing Data: Agenda

More information

Proposal Pricing Instructions Page 1 of 7 Supplier Proposal Adequacy Checklist Instructions

Proposal Pricing Instructions Page 1 of 7 Supplier Proposal Adequacy Checklist Instructions Proposal Pricing Instructions Page 1 of 7 Supplier Proposal Adequacy Checklist Instructions Unless a valid exemption applies, Cost or Pricing Data is required to support proposals exceeding $750,000. Contractors

More information

Government Contracts Pricing Strategies and Rate Structures

Government Contracts Pricing Strategies and Rate Structures Government Contracts Pricing Strategies and Rate Structures Presented By: Brandon Smith bsmith@anglincpa.com Jon Levin jlevin@maynardcooper.com Provisional Billing Rates Provisional, Target, Budget, Billing,

More information

New to Cost Reimbursement Contracts? Meet Your New Friends

New to Cost Reimbursement Contracts? Meet Your New Friends New to Cost Reimbursement Contracts? Meet Your New Friends Breakout Session #: G07 Brent Calhoon Partner Baker Tilly Shingai Mavengere Director, Government Accounting UnitedHealthcare Military & Veterans

More information

TITLE 70: DEPARTMENT OF FINANCE SUBCHAPTER COST AND PRICE ANALYSIS REGULATIONS

TITLE 70: DEPARTMENT OF FINANCE SUBCHAPTER COST AND PRICE ANALYSIS REGULATIONS SUBCHAPTER 70-30.1 COST AND PRICE ANALYSIS REGULATIONS Part 001 General Provisions 70-30.1-001 Overview and Summary 70-30.1-005 Scope 70-30.1-010 Definitions Part 100 Policy; Cost or Pricing Data 70-30.1-101

More information

Monitoring Subcontracts

Monitoring Subcontracts Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Page 1 Subcontracts What should a contractor know about subcontracting:

More information

ANNUAL SUPPLIER REPRESENTATIONS AND CERTIFICATIONS

ANNUAL SUPPLIER REPRESENTATIONS AND CERTIFICATIONS Page: 1 of 10 Date: 12AP16 ANNUAL SUPPLIER REPRESENTATIONS AND CERTIFICATIONS If Offeror has completed the annual representations and certifications electronically, via the System for Award Management

More information

Pricing Subcontracts to Win Work and Make a Profit

Pricing Subcontracts to Win Work and Make a Profit Pricing Subcontracts to Win Work and Make a Profit Breakout Session C02 Rita L. Wells, PhD Senior Acquisition Executive, Suntiva Deidre A. Lee Consultant Date: Thursday, March 17, 2016 Time: 3:45pm 5:00pm

More information

DEFENSE ACQUISITION UNIVERSITY CON Negotiation and Administration of Supply Contracts

DEFENSE ACQUISITION UNIVERSITY CON Negotiation and Administration of Supply Contracts 1 Given a complex fiscal law issue, and working in a team environment, generate a strategy which will resolve that issue. Interpret the major fiscal law statutes and regulations governing Federal contracting.

More information

VSRA Contract Compliance Seminar August 23, 2011

VSRA Contract Compliance Seminar August 23, 2011 VSRA Contract Compliance Seminar August 23, 2011 Topics Overview What s new? Defense Federal Acquisition Regulation Supplement; Business Systems Definition and Administration (DFARS Case 2009-D038) Reporting

More information

BAE Systems Electronic Systems Supplier COPD Overview

BAE Systems Electronic Systems Supplier COPD Overview 1 BAE Systems Electronic Systems Supplier COPD Overview Operations Proposal Group This presentation serves as guidance only and is not meant to be a definitive set of requirements or assurance to meet

More information

Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions

Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions General Terms and Conditions of Purchase Supplement 1 Federal Acquisition Regulation (FAR) Government Contract Provisions 1. When the products or services furnished are for use in connection with a U.S.

More information

National Contract Management Association of Boston 57th Annual March Workshop

National Contract Management Association of Boston 57th Annual March Workshop National Contract Management Association of Boston 57th Annual March Workshop Pricing and estimating March 7, 2018 Agenda Introductions Overview and background of the pricing and estimating process Certified

More information

Review of CON 110, 111 & 112. Preparation for CON 120

Review of CON 110, 111 & 112. Preparation for CON 120 Review of CON 110, 111 & 112 Preparation for CON 120 CON 110 Review Mission Support Planning Key Concepts What s a Best Value Procurement? Means the expected outcome of an acquisition that, in the Government

More information

Proposal Adequacy Checklist

Proposal Adequacy Checklist The offeror shall complete the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror s checklist,

More information

COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION

COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION Introduction The Prime Contract under which this solicitation is issued requires that APL determine the applicability of Cost Accounting Standards Board

More information

Challenges of Contracting with the Federal Government November 19 th, 2015

Challenges of Contracting with the Federal Government November 19 th, 2015 Challenges of Contracting with the Federal Government November 19 th, 2015 The Fundamentals of Government Contracting Webinar Series 1 Your Presenters David King Dixon Hughes Goodman, LLP 703.970.0433

More information

PSP A/ August 26, PSP-020(R)

PSP A/ August 26, PSP-020(R) DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.5.1.A/2013-009 August 26, 2013 13-PSP-020(R) MEMORANDUM FOR

More information

Subcontract Pricing Deficiencies. Next Slide

Subcontract Pricing Deficiencies. Next Slide Subcontract Pricing Deficiencies Table of Contents Risk Assessment Research and Planning Risk Assessment Review of Contract and Price Negotiation Memorandum (PNM) Risk Assessment Overrun/Underrun Analysis

More information

REPRESENTATIONS AND CERTIFICATIONS SAVANNAH RIVER REMEDIATION LLC

REPRESENTATIONS AND CERTIFICATIONS SAVANNAH RIVER REMEDIATION LLC REPRESENTATIONS AND CERTIFICATIONS SAVANNAH RIVER REMEDIATION LLC SRR-PPS-2009-00012, Rev 2 SECTION A, APPLICABLE TO ALL OFFERS... 2 1. Certification and Agreement... 2 2. Authorized Negotiators... 2 3.

More information

Cost Accounting Standards

Cost Accounting Standards Cost Accounting Standards Bill Walter Partner - Government Contract Consulting McLean, Virginia (703) 970-0509 bill.walter@dhgllp.com 1 Agenda Session I Administration: CAS Overview Applicability Types

More information

FAR GOVERNMENT CONTRACT PROVISIONS

FAR GOVERNMENT CONTRACT PROVISIONS PAGE 1 OF 10 INCORPORATION OF FAR CLAUSES The following terms and conditions apply for purchase orders, subcontracts, or other applicable agreements issued in support of a US Government contract, in addition

More information

Topics for Discussion

Topics for Discussion Government Contracting Update September 2010 Presentation By: James W. Thomas LLP PwC New and Proposed Regulations - Cost or Pricing Data - Acquisition Thresholds - Business Systems - Pensions - Security

More information

Mission Support Planning

Mission Support Planning CON 110 Review Mission Support Planning Key Concepts What s a Best Value Procurement? Means the expected outcome of an acquisition that, in the Government s estimation, provides the greatest overall benefit

More information

RFP Representations and Certifications Noncommercial Items for Government Programs (FAR/DFARS)

RFP Representations and Certifications Noncommercial Items for Government Programs (FAR/DFARS) RFP Representations and Certifications Noncommercial Items for Government Programs (FAR/DFARS) 1. FAR 52.215-6 PLACE OF PERFORMANCE a. The Offeror or Respondent, in the performance of any contract resulting

More information

Limitations on Pass-Through Charges. Government Contracts Update Volume 2, Nov. 2011

Limitations on Pass-Through Charges. Government Contracts Update Volume 2, Nov. 2011 Limitations on Pass-Through Charges Government Contracts Update Volume 2, Nov. 2011 11/22/2011 Vol. 2, Nov 2011 Page 1 of 4 Limitations on Pass-Through Charges Two new clauses were added to the FAR effective

More information

SOLICITATION INSTRUCTIONS Bidder will comply with these instructions when responding to this solicitation.

SOLICITATION INSTRUCTIONS Bidder will comply with these instructions when responding to this solicitation. Page : 1 of 4 SOLICITATION INSTRUCTIONS Bidder will comply with these instructions when responding to this solicitation. 1. Responses to this solicitation received after the specified "Bid Close Date"

More information

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 3, Lesson 2 Contract Financing

STUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 3, Lesson 2 Contract Financing STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 3, Lesson 2 Contract Financing October 2017 CON170, Unit 3 Lesson 2 Contract Financing - Page 1 STUDENT PREPARATION Required Student Preparation

More information

PROCUREMENT INTEGRITY ACT RESTRICTIONS

PROCUREMENT INTEGRITY ACT RESTRICTIONS PROCUREMENT INTEGRITY ACT RESTRICTIONS (RULES WHEN YOU ARE LOOKING FOR A NEW JOB and RULES AFFECTING YOUR NEW JOB AFTER LEAVING DOD) IMPORTANT NOTICE: This information was prepared to assist Department

More information

U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS

U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS I. DEFINITIONS A. Agreement means the agreement between City and Contractor to

More information

SUBPART FIXED-PRICE CONTRACTS (Revised January 15, 1999) Fixed-price contracts with economic price adjustment.

SUBPART FIXED-PRICE CONTRACTS (Revised January 15, 1999) Fixed-price contracts with economic price adjustment. SUBPART 216.2--FIXED-PRICE CONTRACTS (Revised January 15, 1999) 216.203 Fixed-price contracts with economic price adjustment. 216.203-4 Contract clauses. (a) Adjustment based on established prices--standard

More information

REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS OR QUOTERS

REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS OR QUOTERS REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS OR QUOTERS The offeror represents and certifies as part of the offer that: (Check or complete all applicable boxes or blocks.) 1. TYPE

More information

LOCKHEED MARTIN CORPORATION CORPDOC 2B

LOCKHEED MARTIN CORPORATION CORPDOC 2B LOCKHEED MARTIN CORPORATION CORPDOC 2B FEDERAL ACQUISITION REGULATION (FAR) AND NATIONAL AERONAUTICS AND SPACE ADMINISTRATION FAR SUPPLEMENT (NASA FARS) FLOWDOWN PROVISIONS FOR SUBCONTRACTS/PURCHASE ORDERS

More information

Arcata Purchasing Policies Summarized for Vendors. March 12, Arcata Associates, Inc Fire Mesa Street, Suite 110 Las Vegas, NV 89128

Arcata Purchasing Policies Summarized for Vendors. March 12, Arcata Associates, Inc Fire Mesa Street, Suite 110 Las Vegas, NV 89128 Arcata Purchasing Policies Summarized for Vendors March 12, 2008 Arcata Associates, Inc. 5288 Fire Mesa Street, Suite 110 Las Vegas, NV 89128 Page 1 of 6 03/12/2008 Selection and Evaluation of Subcontractors...

More information

Allowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management

Allowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management Allowability of Subcontractor/ Consultant Costs and the Challenges Presented for Procurement System Management Breakout Session #: B11 Presented by: Melanie Burgess and Phillip Seckman Date: July 22, 2013

More information

SUBCONTRACTOR EXPECTATIONS IN FEDERAL CONTRACTING

SUBCONTRACTOR EXPECTATIONS IN FEDERAL CONTRACTING SUBCONTRACTOR EXPECTATIONS IN FEDERAL CONTRACTING Reducing Risk & Meeting Requirements as Government Subcontractor AGENDA ointroduction othe Process oproposal Phase onegotiations ocompliance and Accountability

More information

ESSENTIALS OF COMPLIANT SUBCONTRACTING

ESSENTIALS OF COMPLIANT SUBCONTRACTING ESSENTIALS OF COMPLIANT SUBCONTRACTING Reducing Risk & Meeting Requirements as a Prime Contractor AGENDA ointroduction othe Process othe Solicitation othe Agreement oconsent opolicy and Procedure odocumentation

More information

SUMMARY: NASA is proposing to amend the NASA FAR Supplement (NFS) to incorporate a

SUMMARY: NASA is proposing to amend the NASA FAR Supplement (NFS) to incorporate a This document is scheduled to be published in the Federal Register on 10/29/2013 and available online at http://federalregister.gov/a/2013-25287, and on FDsys.gov NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

More information

THE RISKS AND EXTRA COSTS OF FEDERAL GOVERNMENT CONTRACTING. Richard J. Bednar Crowell & Moring, LLP (202) ;

THE RISKS AND EXTRA COSTS OF FEDERAL GOVERNMENT CONTRACTING. Richard J. Bednar Crowell & Moring, LLP (202) ; THE RISKS AND EXTRA COSTS OF FEDERAL GOVERNMENT CONTRACTING Richard J. Bednar Crowell & Moring, LLP (202) 624-2916; rbednar@crowell.com J. Catherine Kunz Crowell & Moring, LLP (202) 624-2957; ckunz@crowell.com

More information

Click to edit Master title style

Click to edit Master title style Third level Click Price to and edit Master Cost title style Analysis: Document your Contract Files and Impress Click to edit Auditors Master text styles Breakout Third Session level #D14 Jo Cunningham

More information

Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective

Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective Breakout Session #: C16 Presented by: Philip R. Seckman Christopher W. Myers Date: July 22, 2013 Time: 4:00-5:15 Agenda

More information

2. Bidder shall notify Buyer if a former employee of Buyer is representing Bidder in connection with its proposal or any resulting order.

2. Bidder shall notify Buyer if a former employee of Buyer is representing Bidder in connection with its proposal or any resulting order. Page: 1 of 5 General Instructions to Bidder 1. Bidder will carefully review all documents cited in Buyer's solicitation to ensure the following: a. All information required to properly respond to this

More information

Sequestration and Terminations for Convenience

Sequestration and Terminations for Convenience Sequestration and Terminations for Convenience J. Clark Pendergrass Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 jcp@lanierford.com www.lanierford.com

More information

REQUEST FOR QUOTES for FOSTER SUCCESS CONFERENCE RELEASE DATE: JUNE 18, 2018

REQUEST FOR QUOTES for FOSTER SUCCESS CONFERENCE RELEASE DATE: JUNE 18, 2018 REQUEST FOR QUOTES for FOSTER SUCCESS CONFERENCE RELEASE DATE: JUNE 18, 2018 Equal Opportunity Employer/Program Auxiliary Aids and service are available upon request to individuals with disabilities Relay:

More information

FAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS. FAR Number Title Latest Update MATERIAL REQUIREMENTS AUG 2000

FAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS. FAR Number Title Latest Update MATERIAL REQUIREMENTS AUG 2000 FAR FLOWDOWN PROVISIONS FOR NON-COMMERCIAL ITEMS 1. The following FAR clauses apply to all non-commercial orders: 52.211-5 MATERIAL REQUIREMENTS AUG 2000 52.215-20 REQUIREMENTS FOR COST OR PRICING DATA

More information

Defective Pricing Selective Disclosure. Next Slide

Defective Pricing Selective Disclosure. Next Slide Defective Pricing Selective Disclosure Table of Contents Risk Assessment Research and Planning Risk Assessment Review of Pricing Action Information Preliminary Analytical Procedures Meeting with Contractor

More information

Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts.

Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts. Page 1 of 11 Modification Details Purpose: The purpose of this modification is to incorporate updates to all Seaport e Contracts. 1. Make the following Changes in Section G: a. ADD HQ G-2-0005 Payment

More information

Webinar: Making the Right Choices in Government Contracting Part 3

Webinar: Making the Right Choices in Government Contracting Part 3 Public Contracting Institute LLC Webinar: Making the Right Choices in Government Contracting Part 3 Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com. Email rliebermanconsultant@gmail.com.

More information

This form will be made a part of any resultant purchase order or subcontract SECTION I

This form will be made a part of any resultant purchase order or subcontract SECTION I Procurement of material, services and supplies for a United States Government contract requires that prime contractors, subcontractors and suppliers comply with socioeconomic programs enacted into public

More information

FEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS

FEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS FEDERAL EMERGENCY MANAGEMENT AGENCY S GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS I. DEFINITIONS A. Agreement means the agreement between City and Contractor to which this document (Federal Emergency

More information

SOLICITATION FOR CONTINUING SERVICES CS PLUMBING SUPPLIES

SOLICITATION FOR CONTINUING SERVICES CS PLUMBING SUPPLIES SOLICITATION FOR CONTINUING SERVICES CS 19-601 PLUMBING SUPPLIES INTRODUCTION Polk County, a political subdivision of the State of Florida, seeks the submittal of information from vendors interested in

More information

IMMEDIATE POLICY CHANGE

IMMEDIATE POLICY CHANGE DEPARTMENT OF DEFENSE Defense Contract Management Agency IMMEDIATE POLICY CHANGE Pricing and Negotiation Contracts Directorate DCMA-INST 120 (IPC-1) OPR: DCMA-AQ March 22, 2016 1. POLICY. This Immediate

More information

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER

LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER FYOC III C-130 Program Contract FA8625-06-C-6456 Generated

More information

Meeting the challenge

Meeting the challenge Government Contract Services Meeting the challenge Ernst & Young LLP s Government Contract Services (GCS) can help you meet the challenges of government contracting. As the largest buyer of goods and services

More information

SUPPLEMENTAL PURCHASE ORDER PROVISIONS UNDER U.S. GOVERNMENT CONTRACTS

SUPPLEMENTAL PURCHASE ORDER PROVISIONS UNDER U.S. GOVERNMENT CONTRACTS SUPPLEMENTAL PURCHASE ORDER PROVISIONS UNDER U.S. GOVERNMENT CONTRACTS ADDITIONAL GOVERNMENT PROVISIONS. If the face of this order indicates that it is placed under a Government prime or higher-tier subcontract

More information

National Contract Management Association of Boston 58th Annual March Workshop

National Contract Management Association of Boston 58th Annual March Workshop National Contract Management Association of Boston 58th Annual March Workshop Pricing and estimating March 13, 2019 Introductions Overview and background of the pricing and estimating process Certified

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS International Republican Institute 1225 Eye St. NW, Suite 700 Washington, DC 20005 (202) 408-9450 (202) 408-9462 fax www.iri.org @IRIGlobal Procurement Number: ASIA2016IND09o Open

More information

A',M SMOP PT, DO sue ftetrt 0_

A',M SMOP PT, DO sue ftetrt 0_ A',M SMOP PT, ag DO sue ftetrt 0_0 93-29519 GAOUnited States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-253626 October 25, 1993 The Honorable

More information

Presented by CohnReznick s Government Contracting Industry Practice. Kristen Soles, CPA, Partner & Kiran Pinto, CPA, Senior Manager

Presented by CohnReznick s Government Contracting Industry Practice. Kristen Soles, CPA, Partner & Kiran Pinto, CPA, Senior Manager A u d i t R e a d y : A n I n s i d e r s G u i d e t o G o v e r n m e n t C o n t r a c t A u d i t s & C o m p l i a n c e Presented by CohnReznick s Government Contracting Industry Practice Kristen

More information

Agencies shall require prime contractors. to the maximum extent practicable, commercial items in all goods and services supplied to the government.

Agencies shall require prime contractors. to the maximum extent practicable, commercial items in all goods and services supplied to the government. 38 Contract Management October 2017 Contract Management October 2017 39 he Federal Acquisition Streamlining Act (FASA), enacted in October of 1994, codified the government s preference for purchasing commercial

More information

Master Document Audit Program. Version 4.21, dated March 2018 B-1 Planning Considerations

Master Document Audit Program. Version 4.21, dated March 2018 B-1 Planning Considerations Activity Code 17200 B-1 Planning Considerations Claim Audit, Other Type of Service - Attestation Examination Engagement Audit Specific Independence Determination Members of the audit team and internal

More information

Growing Pains: The Art of Subcontract Management for Small Business

Growing Pains: The Art of Subcontract Management for Small Business Growing Pains: The Art of Subcontract Management for Small Business Breakout Session # B02 Jeffery A. White, C.P.M, President/CEO J.A. White & Associates, Inc. Date: March 17, 2016 Time: 2:00pm 3:15pm

More information

Recent Developments in Contract Costs and Accounting. Terry L. Albertson J. Catherine Kunz Linda S. Bruggeman

Recent Developments in Contract Costs and Accounting. Terry L. Albertson J. Catherine Kunz Linda S. Bruggeman Recent Developments in Contract Costs and Accounting Terry L. Albertson J. Catherine Kunz Linda S. Bruggeman CAS: Affected Contracts On CAS-covered contracts, Govt is entitled to price adjustments to reflect

More information

e-cfr data is current as of March 23, 2018

e-cfr data is current as of March 23, 2018 ELECTRONIC CODE OF FEDERAL REGULATIONS e-cfr data is current as of March 23, 2018 Title 48 Chapter 1 Subchapter G Part 48 Title 48: Federal Acquisition Regulations System PART 48 VALUE ENGINEERING Contents

More information

Supplemental Government Terms and Conditions

Supplemental Government Terms and Conditions Supplemental Government Terms and Conditions 1. GENERAL: The terms and conditions herein are in addition to Aerojet Terms and Conditions for Purchase Orders, and are incorporated by reference into individual

More information

PROPOSAL DEADLINE: NOVEMBER 26, 2018 by 12PM

PROPOSAL DEADLINE: NOVEMBER 26, 2018 by 12PM LOWER RIO GRANDE VALLEY DEVELOPMENT COUNCIL REQUEST FOR PROPOSAL Vinyl Bus Wrap Production and Installation Services No: 2018-06 VINYL BUS WRAP PRODUCTION AND INSTALLATION SERVICES ON PUBLIC TRANSPORTATION

More information

TABLE OF CONTENTS CHAPTER 1 PROCUREMENT THRESHOLDS AND PROCEDURES...

TABLE OF CONTENTS CHAPTER 1 PROCUREMENT THRESHOLDS AND PROCEDURES... TABLE OF CONTENTS CHAPTER 1 THRESHOLDS AND PROCEDURES... 2 SECTION 1.1 OVERVIEW... 2 SECTION 1.2 METHODS OF... 2 Subsection 1.2.a Micro-purchases... 2 Subsection 1.2.b Small Purchase Procedures... 3 Subsection

More information

Chapter 12. Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims

Chapter 12. Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims Chapter 12 Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims Table of Contents 12-000 Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment

More information

COMPENSATION & PAYMENT PROVISIONS (COST REIMBURSABLE)

COMPENSATION & PAYMENT PROVISIONS (COST REIMBURSABLE) COMPENSATION & PAYMENT PROVISIONS (COST REIMBURSABLE) 1 Note: Articles flagged with an asterisk (*) are Flow-down requirements as defined in Article SUBCONTRACTORS AND SUPPLIERS in Contract Document GENERAL

More information

KERN HEALTH SYSTEMS REQUEST FOR PROPOSAL SUBMISSION CHECKLIST

KERN HEALTH SYSTEMS REQUEST FOR PROPOSAL SUBMISSION CHECKLIST KERN HEALTH SYSTEMS REQUEST FOR PROPOSAL SUBMISSION CHECKLIST Kern Health Systems (KHS) is a government agency dedicated to running a fair bidding program to foster high quality business relationships.

More information

BAA Process. DARPA Contracts Management Office Christopher L. Glista Contracting Officer. SubT Proposers Day January 18, 2018

BAA Process. DARPA Contracts Management Office Christopher L. Glista Contracting Officer. SubT Proposers Day January 18, 2018 DARPA Contracts Management Office Christopher L. Glista Contracting Officer SubT Proposers Day January 18, 2018 1/25/2018 1 Approved for Public Release; Distribution Unlimited What is a BAA? Solicitation

More information

DCMA Manual Terminations. Implements: DCMA-INST 2501, Contract Maintenance, August 15, October 10, 2014

DCMA Manual Terminations. Implements: DCMA-INST 2501, Contract Maintenance, August 15, October 10, 2014 DCMA Manual 2501-06 Terminations Office of Primary Responsibility Contract Maintenance Effective: October 2, 2018 Releasability: Cleared for public release Implements: DCMA-INST 2501, Contract Maintenance,

More information

Part V in a Series: Cost Analysis and Cost Realism and Their Expanding Roles in Contract Pricing. government contracting

Part V in a Series: Cost Analysis and Cost Realism and Their Expanding Roles in Contract Pricing. government contracting Part V in a Series: Cost Analysis and Cost Realism and Their Expanding Roles in Contract Pricing 1 Your instructor... Bill Walter, CPA Managing Director DHG GovCon Advisory Bill.Walter@dhgllp.com 1410

More information

Attached to this modification is a conformed Section C containing this change.

Attached to this modification is a conformed Section C containing this change. Page 2 of 9 Pages a. Section C, Clause C-4 Statement of Work, paragraph (d) (4) as reads: Laboratory Facilities. The Contractor shall manage and maintain Government-owned facilities, both provided and

More information

NEW CASTLE COUNTY Purchasing Division New Castle County Government Center 87 Read s Way New Castle, DE (302)

NEW CASTLE COUNTY Purchasing Division New Castle County Government Center 87 Read s Way New Castle, DE (302) Sealed proposals for:, Bid #17SA-319 Interested parties must submit a priced proposal, in writing with one (1) original and three (3) copies to the,,, New Castle, DE 19720 (302/395-5250) by 2:00 p.m. Wednesday,

More information

LOCKHEED MARTIN CORPORATION CORPDOC 2A

LOCKHEED MARTIN CORPORATION CORPDOC 2A LOCKHEED MARTIN CORPORATION CORPDOC 2A FEDERAL ACQUISITION REGULATION (FAR) AND DEFENSE FEDERAL ACQUISITION REGULATION SUPPLEMENT (DFARS) FLOWDOWN PROVISIONS FOR SUBCONTRACTS/PURCHASE ORDERS FOR COMMERCIAL

More information

THE FOLLOWING PROVISIONS APPLY: Applies to orders of any amount

THE FOLLOWING PROVISIONS APPLY: Applies to orders of any amount Attachment 32c Federal Provisions Applicable When Subcontractor (Commercial Entity) is in Possession of Government Property Government Subcontract Providsions Incorporated in All Subcontracts/Purchase

More information

PRIME CONTRACT F C-2018 Supplement to Appendix A 27 th Series 15 OCTOBER 2003

PRIME CONTRACT F C-2018 Supplement to Appendix A 27 th Series 15 OCTOBER 2003 LOCKHEED MARTIN CORPORATION PRIME SUPPLEMENTAL FLOWDOWN DOCUMENT (PSFD) ADDITIONAL TERMS AND CONDITIONS FOR SUBCONTRACTS/PURCHASE ORDERS UNDER PRIME CONTRACT F33657-03-C-2018 Supplement to Appendix A 27

More information

North Carolina Department of Health and Human Services Women's and Children's Health Nutrition Services Branch Special Nutrition Programs

North Carolina Department of Health and Human Services Women's and Children's Health Nutrition Services Branch Special Nutrition Programs North Carolina Department of Health and Human Services Women's and Children's Health Branch Special Nutrition Programs AGREEMENT BETWEEN SPONSORING ORGANIZATION AND DAY CARE HOME (DCH) PROVIDER Instructions:

More information

D EFENSE FEDERAL ACQUISITION REGULATION SUPPLEMENT (DFARS) FLOWDOWN PROVISIONS FOR

D EFENSE FEDERAL ACQUISITION REGULATION SUPPLEMENT (DFARS) FLOWDOWN PROVISIONS FOR LOCKHEED MARTIN CORPORATION CORPDOC 3A Modified for F-35 JSF LRIP 2 Contract on May 12, 2008 D EFENSE FEDERAL ACQUISITION REGULATION SUPPLEMENT (DFARS) FLOWDOWN PROVISIONS FOR SUBCONTRACTS/PURCHASE ORDERS

More information

A. Update to TC-001 (04/13), GENERAL TERMS AND CONDITIONS OF PURCHASE

A. Update to TC-001 (04/13), GENERAL TERMS AND CONDITIONS OF PURCHASE TC-UPDATE (11/14) The following updates reflect changes to various provisions and clauses of U.S. Government acquisition regulations, including the Federal Acquisition Regulations (FAR) and the Department

More information

2014 NEW JERSEY SUPPLEMENTAL NUTRITION ASSISTANCE PROGRAM EMPLOYMENT AND TRAINING PROVIDER (NJ SNAP ETP) PROJECT

2014 NEW JERSEY SUPPLEMENTAL NUTRITION ASSISTANCE PROGRAM EMPLOYMENT AND TRAINING PROVIDER (NJ SNAP ETP) PROJECT 2014 NEW JERSEY SUPPLEMENTAL NUTRITION ASSISTANCE PROGRAM EMPLOYMENT AND TRAINING PROVIDER (NJ SNAP ETP) PROJECT REQUEST FOR PROPOSALS LIST OF ATTACHMENTS ATTACHMENT A ATTACHMENT B ATTACHMENT C ATTACHMENTS

More information

USAID GHSC PSM. Annex 2: Required Certifications

USAID GHSC PSM. Annex 2: Required Certifications Annex 2: Required Certifications The following Representations and Certifications must be completed and submitted with the proposal Part 2 along with the detailed requirements for Part 2 indicated in the

More information

Cost Recovery Issues After A Termination For Convenience

Cost Recovery Issues After A Termination For Convenience Cost Recovery Issues After A Termination For Convenience Breakout Session # C15 Leslie Anderson, Program Manager, BAE Systems Greg Bingham, Vice President, The Kenrich Group Chelsea Taylor, Manager, The

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS International Republican Institute 1225 Eye St. NW, Suite 700 Washington, DC 20005 (202) 408-9450 (202) 408-9462 fax www.iri.org @IRIGlobal Procurement Number: AFRICA2016TZ12o Open

More information

DCAA Update and Limitation on Subcontracting

DCAA Update and Limitation on Subcontracting DCAA Update and Limitation on Subcontracting Bristol Bay Native Corporation 2016 Annual Compliance Conference Stephen D. Knight Smith Pachter McWhorter PLC Scope of Government Audit Rights FAR 52.215-2,

More information

From the Federal Register Online via the Government Printing Office [

From the Federal Register Online via the Government Printing Office [ Federal Register, Volume 70 Issue 67 (Friday, April 8, 2005) [Federal Register Volume 70, Number 67 (Friday, April 8, 2005)] [Proposed Rules] [Pages 17945-17949] From the Federal Register Online via the

More information

SUBPART CONTRACT PRICING (Revised November 24, 2008)

SUBPART CONTRACT PRICING (Revised November 24, 2008) SUBPART 215.4--CONTRACT PRICING (Revised November 24, 2008) 215.402 Pricing policy. Follow the procedures at PGI 215.402 when conducting cost or price analysis, particularly with regard to acquisitions

More information

COUNCIL OF DEFENSE AND SPACE INDUSTRY ASSOCIATIONS 4401 Wilson Boulevard, Suite 1110 Arlington, Virginia

COUNCIL OF DEFENSE AND SPACE INDUSTRY ASSOCIATIONS 4401 Wilson Boulevard, Suite 1110 Arlington, Virginia COUNCIL OF DEFENSE AND SPACE INDUSTRY ASSOCIATIONS 4401 Wilson Boulevard, Suite 1110 Arlington, Virginia 2203 703-875-8059 February 3, 2012 Defense Acquisition Regulations Systems ATTN: Dustin Pitsch Room

More information

REPRESENTATIONS AND CERTIFICATIONS

REPRESENTATIONS AND CERTIFICATIONS REPRESENTATIONS AND CERTIFICATIONS The Offeror identified below certifies to the following facts. The full text of the representations and certifications made below (and referenced to the right of each

More information

SUBPART OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised December 31, 2012)

SUBPART OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised December 31, 2012) SUBPART 225.8--OTHER INTERNATIONAL AGREEMENTS AND COORDINATION (Revised December 31, 2012) 225.802 Procedures. (b) Information on memoranda of understanding and other international agreements is available

More information