PROJECT RISK REGISTER Guidance Notes

Size: px
Start display at page:

Download "PROJECT RISK REGISTER Guidance Notes"

Transcription

1 PROJECT RISK REGISTER Guidance Notes The Risk Register is a tool to assist Project Managers in identifying likely sources of risk and the impact they may have on achieving Objective 2 target expenditure. It seeks to build upon more general risk assessment guidance that has been provided by other regeneration programmes. Even early guidance provided for the SRB Challenge Fund (Guidance Note No. 3 Project Appraisal and Approval Dec 1995) acknowledged the need to identify and consider each component of risk. Later guidance (New Deal for Communities and Single Regeneration Budget Approval and Appraisal Oct 2000) went on to identify two main levels of risk firstly, risks that might prevent an option delivering anticipated results or outputs on the ground and, secondly, risks that might prevent outputs and results from being translated into long-term outcomes. Risk management is now seen as an integral part of good project and programme management and a robust assessment of risk needs to be undertaken to ensure that target spend (or claim) is achieved together with successful project implementation. The following Guidance Notes set out a recommended approach to risk assessment and a guide to the completion of the Risk Register. It is appreciated that a number of APPs already have risk management procedures in place. This Guidance is designed primarily to help other APPs in establishing their own systems, but it should also be used to ensure that any existing system is sufficient to meet GONW s expectations. Effective risk management will be part of GO s audit remit when looking at project management, in EPS six monthly monitoring visits, for example. The Guidance is structured around completing a risk register, in accordance with the process set out in the slides which accompanied the APP workshops held on 24 th /25 th February. It assumes a project-by-project approach but APPs may wish to deal with similar projects in groups. A proforma risk register is included at Annex A.

2 RISK IDENTIFICATION WORKSHOP The first recommended step is to convene a workshop involving the project manager, project team members and, if possible, key stakeholders. Ideally, an APP representative should also attend to input any programme level risks, provide guidance and ensure consistency of approach between projects. For the purposes of the risk form, focus should be on risks to claim value and timing, rather than on risks to outcomes and outputs. Outcome/output risks should however be considered as part of good risk management practice. Brainstorming Session After a brief introduction as to the process to be followed, the risk workshop opens with a brainstorming session, identifying any risks which could affect the project. Some categories of risks are suggested at Annex B, to help structure the process. The first list comprises generic risks, potentially applicable to all projects, whilst the second contains additional risks specific to Prioirty 3 (or physical) projects. An APP or project may identify other categories for consideration: these lists are not exhaustive. It is important that the risks identified by workshop participants are clearly defined rather than described in general terms, so that the precise nature of the risk is understood and can be actioned. Risks identified should be logged on a risk register. You may find it useful to give each a unique identification number: this is useful in tracking risks and can help to group them by type if an alphanumeric code is used (eg F3: funding risk no 3). For Priority 3 projects you should note to which claim element the risk relates. The timing of the risk in terms of which phase of the project is likely to be impacted should be considered. In order to comply with the Risk Form input requirements, the pro forma Risk Register suggests that risks be noted as possible to occur in the next quarter by year end (Dec 2003), or later in the project life PROJECT NAME ID Risk Claim element Stage next 1/4 Dec-03 whole life F3 Title concerns delay sale Acquisition X

3 Risk Impact Assessment The impact of the risk, should it occur, needs to be considered in time, cost and quality terms, as follows: Time: the impact on project programme (and particularly the timing of a claim) think in days/weeks/months Cost: the impact on claim value think in s Quality: the impact on outcomes or outputs think in terms of m 2 office space, no of jobs, etc. For each impact type, rate and score the likely effect as being Very low 1 Low 2 Medium 3 High 4 Very high 5 You may wish to set some parameters to define what you mean by each of these terms if different workshop participants are likely to have differing views on impact severity. The parameters might % impact or absolute (eg 5-10% of total cost or 2,500-5,000). Generally, zero or insignificant impact will score 1, whilst project-critical impact (ie so severe that it threatens to stop the project) will score 5 across one or more dimensions. You can then get a total impact score by simply adding up the values in the time, cost and quality columns. The Impact score will be a value between 3 and 15. PROJECT NAME ID Risk Time (T) Cost (C) Quality (Q) Impact (I) T+C+Q F3 Title concerns delay sale

4 Risk Probability Assessment This considers the likelihood of the risk occurring and is rated in terms of percentage chance. Again, a five-point scoring system is used. Very low 1 Low 2 Medium 3 High 4 Very high 5 A score of 1 would imply that the risk is very unlikely to happen, a medium score might imply a 50/50 chance, and a score of 5 would apply to a risk which is very likely to be realised. Risk Severity and Ranking The combined effect of impact and probability needs to be assessed to rate the overall severity of each risk. This is done by simply multiplying the Impact and Probability scores. The higher the resulting figure, the more significant the risk, and so risks can be prioritised and ranked accordingly PROJECT NAME ID Risk T C Q Impact (I) Probability (P) Severity Ranking T+C+Q 1-5 I x P F3 Title concerns delay sale C1 Weather delays construction M4 Initial estimates too low

5 RISK MANAGEMENT AND RISK REVIEW The Risk Register has an important role to play in ongoing management of risk and should be used not only to identify risks but also to actively work to reduce them and review progress regularly. Using the risk ranking, prioritise risks so that the most severe are tackled first. Then decide what mitigating action can be taken to alleviate the risk. The mitigation may Reduce the severity of the impact should the risk occur, and/or Reduce the likelihood of the risk occurring Some risks may have more than one mitigating action. The nominated risk owner is responsible for ensuring that action is taken and reviewed by the agreed date. Ranking Mitigation Owner Deadline 1 Transfer weather risks to contractor J Bloggs 23/04/ Engage lawyer early A N Other 28/02/ Get QS to review estimates P Manager 14/03/2003 Maintenance of the risk register should be the responsibility of the Project Manager. Regular reviews should ensure that any new risks are captured and that mitigating actions are undertaken to address risks which remain current. Consideration should be given to reassessing the impact and probability scores for risks as the project progresses and as mitigating actions are completed: they are likely to change over time and risks should be re-ranked accordingly. Management effort can then be redirected to always focus on the most important risks at any point in time.

6 ANNEX A RISK REGISTER pro-forma

7 ANNEX B CATEGORY GENERIC RISKS (ALL PROJECTS) SUB-CATEGORY Funding - Number of match funding sources - Type of match funding sources - Extent of commitment Political Risk/Approvals APP or Project Management Capacity and Capability to Deliver Accommodation and Equipment Cost Escalation & Over-run - Partner approval or support - State Aid approval - Statutory approval (such as planning and highways) - Funding approval - Management capability - Staffing capacity - Failure to submit or process claims - Obtaining suitable accommodation or equipment - Maintaining accommodation or equipment - Poor initial cost estimates - Inflationary cost increases Market Risk - Insufficient demand for product or service Other Risks (please specify) - 3 rd Party actions leading to delay - Under-spend - Under-claim - No claim - Weather delays - Costs associated with transfer of control to the private sector

8 ADDITIONAL RISKS TO PRIORITY 3 & PHYSICAL PROJECTS CATEGORY SUB_CATEGORY Land Acquisition - Delay in completion of acquisition - Failure to acquire - Cost increases Unanticipated Site Issues - Poor ground conditions - Contamination - Pollution Legal Risk - Poor title - Wayleaves/3 rd party rights - Liabilities (such as environmental) Contractual Risk - Failure of contractors - Under-performance of contractors - Transfer of control and risk to private sector

Risk Management Strategy

Risk Management Strategy Resources Risk Management Strategy Successful organisations are not afraid to take risks; Unsuccessful organisations take risks without understanding them. Issue: Version 3 - November 2011 Group: Resources

More information

Kidsafe NSW Risk Management Plan. August 2014

Kidsafe NSW Risk Management Plan. August 2014 Kidsafe NSW Risk Management Plan August 2014 Document Control Document Approval Name & Position Signature Date Document Version Control Version Status Date Prepared By Comments Document Reviewers Name

More information

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY NHS Education for Scotland RISK MANAGEMENT STRATEGY January 2016 1 Contents 1. NES STATEMENT ON RISK MANAGEMENT 2 RISK MANAGEMENT STRATEGY 3 RISK MANAGEMENT STRUCTURES 4 RISK MANAGEMENT PROCESSES 5 RISK

More information

Risk management procedures

Risk management procedures Purpose and scope In accordance with the BizOps Enterprises risk management policy, these procedures describe the organisation s standard process for risk management, including: 1. Risk identification

More information

APPENDIX 1. Transport for the North. Risk Management Strategy

APPENDIX 1. Transport for the North. Risk Management Strategy APPENDIX 1 Transport for the North Risk Management Strategy Document Details Document Reference: Version: 1.4 Issue Date: 21 st March 2017 Review Date: 27 TH March 2017 Document Author: Haddy Njie TfN

More information

Version: th November 2010 RISK MANAGEMENT POLICY

Version: th November 2010 RISK MANAGEMENT POLICY Version: 1.2-25th November 2010 RISK MANAGEMENT POLICY Document History Document Location To be completed. Revision History Date of this revision: 17/09/2010 Date of next revision: N/A Revision Number

More information

Risk Management Policy and Framework

Risk Management Policy and Framework Risk Management Policy and Framework Risk Management Policy Statement ALS recognises that the effective management of risks is a fundamental component of good corporate governance and is vital for the

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

SECTION II.7 MANAGING PROJECT RISKS

SECTION II.7 MANAGING PROJECT RISKS SECTION II.7 MANAGING PROJECT RISKS 1. WHAT ARE RISK ANALYSIS AND RISK MANAGEMENT? Any uncertainty in the scope of the Project, the cost of delivery and time scale for delivery, will present either a risk

More information

Risk Management Framework. Group Risk Management Version 2

Risk Management Framework. Group Risk Management Version 2 Group Risk Management Version 2 RISK MANAGEMENT FRAMEWORK Purpose The purpose of this document is to summarise the framework which Service Stream adopts to manage risk throughout the Group. Overview The

More information

NHS HIGHLAND STRATEGIC RISK REGISTER ADULT SOCIAL CARE SERVICES AND CHILDREN S SERVICES

NHS HIGHLAND STRATEGIC RISK REGISTER ADULT SOCIAL CARE SERVICES AND CHILDREN S SERVICES Highland NHS Board 14 August Item 4.3 NHS HIGHLAND STRATEGIC RISK REGISTER ADULT SOCIAL CARE SERVICES AND CHILDREN S SERVICES Report by Jan Baird, Care and Lesley Anne Smith, Quality on behalf of Elaine

More information

Nagement. Revenue Scotland. Risk Management Framework. Revised [ ]February Table of Contents Nagement... 0

Nagement. Revenue Scotland. Risk Management Framework. Revised [ ]February Table of Contents Nagement... 0 Nagement Revenue Scotland Risk Management Framework Revised [ ]February 2016 Table of Contents Nagement... 0 1. Introduction... 2 1.2 Overview of risk management... 2 2. Policy Statement... 3 3. Risk Management

More information

Integrated Risk Management Framework Sept Page 1 of 17

Integrated Risk Management Framework Sept Page 1 of 17 Integrated Risk Management Framework 2017-2018 Sept 2017 Page 1 of 17 Reference: Title: Author/Nominated Lead: Approval Date: Approving Committee: Review Date: Target Audience: Circulation List: Cross

More information

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management 0470_022817_03_chap01.fm Page 11 Wednesday, September 8, 2004 3:29 PM Part I The basics of project risk management 0470_022817_03_chap01.fm Page 12 Wednesday, September 8, 2004 3:29 PM 0470_022817_03_chap01.fm

More information

NHS North Somerset Clinical Commissioning Group Risk Management Strategy and Framework

NHS North Somerset Clinical Commissioning Group Risk Management Strategy and Framework NHS North Somerset Clinical Commissioning Group Risk Management Strategy and Framework An Integrated Risk Management Framework Clinical Risk Management Financial Risk Management Corporate Risk Management

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

Executive Board Annual Session Rome, May 2015 POLICY ISSUES ENTERPRISE RISK For approval MANAGEMENT POLICY WFP/EB.A/2015/5-B

Executive Board Annual Session Rome, May 2015 POLICY ISSUES ENTERPRISE RISK For approval MANAGEMENT POLICY WFP/EB.A/2015/5-B Executive Board Annual Session Rome, 25 28 May 2015 POLICY ISSUES Agenda item 5 For approval ENTERPRISE RISK MANAGEMENT POLICY E Distribution: GENERAL WFP/EB.A/2015/5-B 10 April 2015 ORIGINAL: ENGLISH

More information

RISK AND BUSINESS CONTINUITY MANAGEMENT

RISK AND BUSINESS CONTINUITY MANAGEMENT RISK AND BUSINESS CONTINUITY MANAGEMENT EFFECTIVE: 18 MAY 2010 VERSION: 1.4 FINAL Last updated date: 29 September 2015 Uncontrolled when printed 2 Effective: 18 May 2010 CONTENTS 1 POLICY STATEMENT...

More information

STRATEGIC PLANNING PROCESS (2017) 1.1 The Association s strategic planning framework consists of the preparation of the following documents;

STRATEGIC PLANNING PROCESS (2017) 1.1 The Association s strategic planning framework consists of the preparation of the following documents; 1.0 INTRODUCTION STRATEGIC PLANNING PROCESS (2017) 1.1 The Association s strategic planning framework consists of the preparation of the following documents; Corporate Management Plan Departmental Service

More information

RISK AND OPPORTUNITY ASSESSMENT GUIDE RISK CRITERIA

RISK AND OPPORTUNITY ASSESSMENT GUIDE RISK CRITERIA RISK AND OPPORTUNITY ASSESSMENT GUIDE RISK ASSESSMENT GUIDE TABLE OF CONTENTS 1. PURPOSE... 3 2. SCOPE... 3 3. RELATED DOCUMENTS... 3 4. PROCEDURE... 3 5. RISK MANAGEMENT PROCESS... 3 6. STEP 1 RISK ANALYSIS...

More information

A Second Runway for Gatwick Appendix. A21 Programme Risk Management

A Second Runway for Gatwick Appendix. A21 Programme Risk Management A Second Runway for Gatwick Appendix A21 Programme Risk Management London Gatwick Airport Expansion Airport Commission Programme Risk Management Report Turner & Townsend 7 Savoy Court London WC2R 0EX

More information

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6.1 In appraisals, there is always likely to be some difference between what is expected and what eventually happens, because of biases unwittingly

More information

PRINCE2-PRINCE2-Foundation.150q

PRINCE2-PRINCE2-Foundation.150q PRINCE2-PRINCE2-Foundation.150q Number: PRINCE2-Foundation Passing Score: 800 Time Limit: 120 min File Version: 6.0 Exam PRINCE2-Foundation Version: 6.0 Exam A QUESTION 1 What process ensures focus on

More information

Integrated Planning, Monitoring and Reporting

Integrated Planning, Monitoring and Reporting 1. Purpose This procedure describes the integrated planning, monitoring and ing cycle of the European Chemicals Agency, including the preparation of the Single Programming Document (SPD). This procedure

More information

Risk Management Plan PURPOSE: SCOPE:

Risk Management Plan PURPOSE: SCOPE: Management Plan Authority Source: Vice-Chancellor Approval Date: 16/05/2018 Publication Date: 17/05/2018 Review Date: 17/05/2021 Effective Date: 16/05/2018 Custodian: General Counsel and University Secretary

More information

Trust Board Meeting 01 October 2015

Trust Board Meeting 01 October 2015 Trust Board Meeting 01 October 2015 Title of the paper: Risk Management Update including Corporate Risk Register Agenda Item: 19/30 Lead : Author: Trust objective: Purpose: Helen Brown, Director of Strategy

More information

Tariff Risk Management Plan

Tariff Risk Management Plan Tariff Risk Management Plan June 2012 Table of Contents EXECUTIVE SUMMARY... PRINCIPLES OF THE TARIFF...2 SUCCESS OF THE TARIFF...4 LEGAL REQUIREMENTS FOR DELIVERY...7 CURRENT HEADLINE TARIFF POSITION...7

More information

Nagement. Revenue Scotland. Risk Management Framework

Nagement. Revenue Scotland. Risk Management Framework Nagement Revenue Scotland Risk Management Framework Table of Contents 1. Introduction... 2 1.2 Overview of risk management... 2 2. Policy statement... 3 3. Risk management approach... 4 3.1 Risk management

More information

TONGA NATIONAL QUALIFICATIONS AND ACCREDITATION BOARD

TONGA NATIONAL QUALIFICATIONS AND ACCREDITATION BOARD TONGA NATIONAL QUALIFICATIONS AND ACCREDITATION BOARD RISK MANAGEMENT FRAMEWORK 2017 Overview Tonga National Qualifications and Accreditation Board (TNQAB) was established in 2004, after the Tonga National

More information

Risk Management Strategy Highland Council Pension Fund

Risk Management Strategy Highland Council Pension Fund Risk Management Strategy Highland Council Pension Fund Approved Pensions Committee 9 August 2018 3 1. Introduction 1.1 Risk management is a key element of Corporate Governance and the Highland Council

More information

Braindumps.PRINCE2-Foundation.150.QA

Braindumps.PRINCE2-Foundation.150.QA Braindumps.PRINCE2-Foundation.150.QA Number: PRINCE2-Foundation Passing Score: 800 Time Limit: 120 min File Version: 29.1 http://www.gratisexam.com/ I was a little apprehensive at first about an online

More information

INTEGRATED RISK MANAGEMENT FRAMEWORK (STRATEGY AND POLICY)

INTEGRATED RISK MANAGEMENT FRAMEWORK (STRATEGY AND POLICY) INTEGRATED RISK MANAGEMENT FRAMEWORK (STRATEGY AND POLICY) Version 1.5 (DRAFT) RATIFIED DATE BY WHOM Fylde and Wyre CCG Governing Body Fylde and Wyre CCG (F&W CCG) is committed to ensuring that, as far

More information

Risk Management Methodology. City Project Management. City Project Management

Risk Management Methodology. City Project Management. City Project Management Risk Management Methodology City Project Management City Project Management 2011 www.cityprojectmanagement.com Why bother with Risk management Introduction & objectives Project plans are often developed

More information

Risk Management Policy and Procedures.

Risk Management Policy and Procedures. Risk Management Policy and Procedures. Rev Date Purpose of Issue/Description of Change Date 1. June 2006 Initial Issue 2. November 2009 Revised and updated 6 th November 2009 3. September 2010 Revised

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY TABLE OF CONTENTS PAGE 1. BACKGROUND 3 2. MATERIAL BUSINESS RISK 3 3. RISK TOLERANCE 4 4. OUTLINE OF ARTEMIS RESOURCE LIMITED S RISK MANAGEMENT POLICY 5 5. RISK MANAGEMENT ROLES

More information

Risk Management Policies and Procedures

Risk Management Policies and Procedures Risk Management Policies and Procedures As at May 5 2017 Masters Swimming Australia ABN 24 694 633 156 Level 2, Sports House, 375 Albert Road, Albert Park 3206 t: (03) 9682 5666 e: gm@mastersswimming.org.au

More information

BARNSLEY METROPOLITAN BOROUGH COUNCIL

BARNSLEY METROPOLITAN BOROUGH COUNCIL BARNSLEY METROPOLITAN BOROUGH COUNCIL This matter is a Key Decision within the Council s definition and has been included in the relevant Forward Plan. 1. Purpose of Report Report of the Executive Director

More information

M_o_R (2011) Foundation EN exam prep questions

M_o_R (2011) Foundation EN exam prep questions M_o_R (2011) Foundation EN exam prep questions 1. It is a responsibility of Senior Team: a) Ensures that appropriate governance and internal controls are in place b) Monitors and acts on escalated risks

More information

PFI PROJECTS: THEIR SCOPE FOR DELIVERING VFM

PFI PROJECTS: THEIR SCOPE FOR DELIVERING VFM PFI PROJECTS: THEIR SCOPE FOR DELIVERING VFM David Rutter and Kassim Gidado School of The Environment, University of Brighton, Brighton, BN24GJ One of the key initial requirements for Private Finance Initiative

More information

Risk Management Strategy

Risk Management Strategy Risk Management Strategy Document Reference MLCSU CA_WL_V3 Version 3 Authors: Donna Bamber, Midlands & Lancashire Commissioning Support Unit Senior Risk Officer Smita Shetty, Service Redesign Manager,

More information

Flood Risk Management Planning in Scotland: Arrangements for February 2012

Flood Risk Management Planning in Scotland: Arrangements for February 2012 Flood Risk Management Planning in Scotland: Arrangements for 2012 2016 February 2012 Flood Risk Management (Scotland) Act 2009 1 Contents Forewords 1. Introduction to this document... 5 2. Sustainable

More information

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration. Project Risk Management Tutorial Presented to: Eastern Idaho Chapter Project Management Institute Presented by: Carl Lovell, PMP Contract and Technical Integration March 2009 Project Risk Definition An

More information

Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation)

Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation) EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Integrated Sustainable Urban Development (Article 7 ERDF Regulation) p10 addition of 3 bullet points for specific

More information

Risk Management Framework. Metallica Minerals Ltd

Risk Management Framework. Metallica Minerals Ltd Risk Management Framework Metallica Minerals Ltd Risk Management Framework 23 March 2012 Table of Contents Contents 1. Introduction... 3 2. Risk Management Approach... 3 3. Roles and Responsibilities...

More information

RISK REGISTER POLICY AND PROCEDURE

RISK REGISTER POLICY AND PROCEDURE RISK REGISTER POLICY AND PROCEDURE Lead Manager: Head of Clinical Governance Responsible Director: Board Medical Director Approved by: Date Approved: Date for Review: Feb 2012 Replaces Version: 1.0 Page

More information

Actualtests.PRINCE2Foundation.120questions

Actualtests.PRINCE2Foundation.120questions Actualtests.PRINCE2Foundation.120questions Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PRINCE2 Foundation PRINCE2 Foundation written Exam 1. Dump

More information

BOARD ASSURANCE FRAMEWORK & SIGNIFICANT RISK REGISTER Trust Board in public

BOARD ASSURANCE FRAMEWORK & SIGNIFICANT RISK REGISTER Trust Board in public BOARD ASSURANCE FRAMEWORK & SIGNIFICANT RISK REGISTER Trust Board in public Date: 22 February 2018 Agenda item: 1.7 Executive sponsor Report author(s) Report discussed previously: (name of sub-committee/group

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK RISK MANAGEMENT FRAMEWORK Approving authority Approval date University Council 5 August 2013 (3/2013 meeting) Advisor Vice President (Corporate Services) vpcorporateservices@griffith.edu.au (07) 373 57343

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

Scouting Ireland Risk Management Framework

Scouting Ireland Risk Management Framework No. SID 124A/15 Gasóga na héireann/scouting Ireland Issued Amended 20 th June 2015 Deleted Source: National Management Committee Scouting Ireland Risk Management Framework Revision Date Description # 20/06/2015

More information

Perpetual s Risk Management Framework

Perpetual s Risk Management Framework Perpetual s Risk Management Framework Perpetual s Risk Management Framework Context Perpetual Limited (Perpetual) is a diversified financial services firm, listed on the Australian Securities Exchange.

More information

UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK

UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK 1 TABLE OF CONTENTS FIGURES AND TABLES... 3 1. INTRODUCTION... 4 2. KEY TERMS AND DEFINITIONS... 5 2.1 Risk... 5 2.2 Risk Management... 5 2.3 Risk Management

More information

Main Sections. Corporate Risk Policy Statement and Procedures AR-RMD-CR01. Executive Summary. Anglia Ruskin University Risk Management

Main Sections. Corporate Risk Policy Statement and Procedures AR-RMD-CR01. Executive Summary. Anglia Ruskin University Risk Management Corporate Risk Policy Statement and Procedures AR-RMD-CR01 Executive Summary This document is intended to assist Anglia Ruskin University, its subsidiaries and Joint Ventures in controlling business risks,

More information

IRAS SUPPLEMENTARY CIRCULAR SUPPLEMENTARY ADMINISTRATIVE GUIDANCE ON ADVANCE PRICING ARRANGEMENTS

IRAS SUPPLEMENTARY CIRCULAR SUPPLEMENTARY ADMINISTRATIVE GUIDANCE ON ADVANCE PRICING ARRANGEMENTS IRAS SUPPLEMENTARY CIRCULAR SUPPLEMENTARY ADMINISTRATIVE GUIDANCE ON ADVANCE PRICING ARRANGEMENTS Published by Inland Revenue Authority of Singapore Published on 20 October 2008 Inland Revenue Authority

More information

RISK MANAGEMENT POLICY. Head of Corporate Development and Change. Policy owners

RISK MANAGEMENT POLICY. Head of Corporate Development and Change. Policy owners POLICY RISK MANAGEMENT Policy owners Policy holder Author Head of Corporate Development and Change Risk and Policy Manager Head of Corporate Development and Change/ Programme Manager/ Risk and Policy Manager

More information

Chapter 8: Lifecycle Planning

Chapter 8: Lifecycle Planning Chapter 8: Lifecycle Planning Objectives of lifecycle planning Identify long-term investment for highway infrastructure assets and develop an appropriate maintenance strategy Predict future performance

More information

CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL

CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL Dr Suwarna Torgal Assistatnt Professor, IET, DAVV, Indore ( M P ) ABSTRACT There are many risks events that adversely affect the

More information

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011 Topic RISK MANAGEMENT Procedure 07.01 Category Risk Management Updated 07/2011 RELATED POLICIES, PROCEDURES AND FORMS Policies Procedures Forms Risk Management Policy Code of Conduct Public Interest Disclosure

More information

Risk Management Strategy

Risk Management Strategy Risk Management Strategy 2016 2019 Version: 6 Policy Lead/Author & Deputy Director of Quality position: Ward / Department: Nursing Directorate Replacing Document: Version 5 Approving Committee Quality

More information

Risk Management Framework

Risk Management Framework Risk Management Framework Introduction The outgoing Corporate Strategy 2013-18 and incoming University Strategy 2018-23 continues on a trajectory towards Vision 2025 in an increasingly competitive Higher

More information

The Water Industry Commission for Scotland Scottish Water Scottish Water

The Water Industry Commission for Scotland Scottish Water Scottish Water The Water Industry Commission for Scotland Scottish Water Scottish Water Reporter s Report SR10 2 nd Draft Business Plan Appendix C Investment and Outputs Plan April 2009 SCOTTISH WATER REPORTER S REPORT

More information

Assets, Regeneration and Growth Committee 1 st June 2015

Assets, Regeneration and Growth Committee 1 st June 2015 Assets, Regeneration and Growth Committee 1 st June 2015 Title Community Asset Strategy Report of Chief Operating Officer Wards All Status Public Enclosures Appendix 1: Draft Community Asset Strategy Officer

More information

Strategic flood risk management

Strategic flood risk management Report by the Comptroller and Auditor General Department for Environment, Food & Rural Affairs and Environment Agency Strategic flood risk management HC 780 SESSION 2014-15 5 NOVEMBER 2014 4 Key facts

More information

LONDON BOROUGH OF ENFIELD RISK MANAGEMENT STRATEGY

LONDON BOROUGH OF ENFIELD RISK MANAGEMENT STRATEGY LONDON BOROUGH OF ENFIELD RISK MANAGEMENT STRATEGY JANUARY 2013 1 Version Control Reference Comments Approval date 05 09 12 19 11 12 10 01 13 2 FOREWORD Welcome to the Council s Risk Management Strategy.

More information

Risk Registers. Providing evidence, if required, that the Trust is compliant with the Management of Health and Safety Regulations 1999;

Risk Registers. Providing evidence, if required, that the Trust is compliant with the Management of Health and Safety Regulations 1999; Risk Registers Appendix 1 What is a Risk Register? A Risk Register is a log of risks of all kinds that threaten the delivery of objectives and the delivery of services. It should be a live document which

More information

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales The PRINCE2 Practitioner Examination Sample Paper TR Answers and rationales For exam paper: EN_P2_PRAC_2017_SampleTR_QuestionBk_v1.0 Qu Correct Syll Rationale answer topic 1 A 1.1a a) Correct. PRINCE2

More information

A new approach to public private partnerships: PF2. OECD Annual Meeting of Senior PPP Officials

A new approach to public private partnerships: PF2. OECD Annual Meeting of Senior PPP Officials A new approach to public private partnerships: PF2 OECD Annual Meeting of Senior PPP Officials 15 April 2013 Concerns with the Private Finance Initiative In some cases the returns to equity investors in

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK Risk Management Framework RISK MANAGEMENT FRAMEWORK Purpose This Risk Management Framework introduces St. Michael s College s approach to risk management. It includes a definition of risk, a summary of

More information

Railway Housing Association. Value for Money Strategy

Railway Housing Association. Value for Money Strategy Railway Housing Association Value for Money Strategy 2016-21 1 Executive Summary 1.1 Railway Housing Association (RHA) recognises that Value for Money (VFM) is a fundamental consideration for all housing

More information

Risk Management Strategy. February 2016 February 2019 Risk management, risk Assurance Plan SOP

Risk Management Strategy. February 2016 February 2019 Risk management, risk Assurance Plan SOP Corporate Risk Register: Standard Operating Procedure Document Control Summary Status: Version: Author/Title: Owner/Title: Approved by: Ratified: Related Trust Strategy and/or Strategic Aims Implementation

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.x INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES DRAFT, MARCH 2008 This document was prepared

More information

Annex 8. Project Assurance Recommendations

Annex 8. Project Assurance Recommendations Annex 8 Project Assurance Recommendations Contents 1. Project Review Report 2. Recommendations and actions Taken 3. Project Board Roles and Responsibilities This page is intentionally blank BRT North -

More information

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework MEMORANDUM To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 Re: ERM Policy and Framework Executive Summary Attached are the draft Enterprise Risk Management

More information

HSC Business Services Organisation Board

HSC Business Services Organisation Board Paper BSO 25/2009 HSC Business Services Organisation Board Risk Management 1. Purpose of this report The purpose of this report is to brief the Board on the BSO Risk Management process. 2. Background HSC

More information

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36 Risk Management User Guide Prepared By: Neville Turbit Version 1.0 1 Feb 09 22/01/2009 Risk Management User Guide Page 1 of 36 Table of Contents Document Origin...2 Change History...2 Risk Guidelines...

More information

SOL PLAATJE MUNICIPALITY

SOL PLAATJE MUNICIPALITY RISK MANAGEMENT AND INTERNAL CONTROL Approved As Per Resolution CR 500 dd 17-11-05 INDEX 1. INTRODUCTION 2. PURPOSE AND SCOPE 3. OBJECTIVE OF THE RISK POLICY 4. RISK MANAGEMENT FRAMEWORK 5. ACCOUNTABILTY

More information

NATIONAL RISK MANAGEMENT SYSTEM

NATIONAL RISK MANAGEMENT SYSTEM Scouts Australia NATIONAL RISK MANAGEMENT SYSTEM 2003 First Published 2003 Reviewed August 2006 in consideration of AS/NZS 4360-2004 and Organisational Performance Since First Published. Amendment by Chair

More information

Risk Management Framework

Risk Management Framework Risk Management Framework Anglican Church, Diocese of Perth November 2015 Final ( Table of Contents Introduction... 1 Risk Management Policy... 2 Purpose... 2 Policy... 2 Definitions (from AS/NZS ISO 31000:2009)...

More information

Risk Management Plan Project Name: Version 1.0 Date: dd/mm/yyyy

Risk Management Plan Project Name: Version 1.0 Date: dd/mm/yyyy Risk Management Plan Project Name: Version 1.0 Date: dd/mm/yyyy Contents DOCUMENT OVERVIEW... 3 RISK METHODOLOGY... 3 RISK IDENTIFICATION... 3 Risk Categories... 3 RISK ANALYSIS... 4 RISK RESPONSE PLANNING...

More information

Recommendation of the Council on Good Practices for Public Environmental Expenditure Management

Recommendation of the Council on Good Practices for Public Environmental Expenditure Management Recommendation of the Council on for Public Environmental Expenditure Management ENVIRONMENT 8 June 2006 - C(2006)84 THE COUNCIL, Having regard to Article 5 b) of the Convention on the Organisation for

More information

Construction projects: manage risk to achieve success

Construction projects: manage risk to achieve success Construction projects: manage risk to achieve success By: Gareth Byatt, Principal Consultant Risk Insight Consulting Date: 12 th August 2017 Summary: This Paper discusses risk management on construction

More information

Risk Management Strategy

Risk Management Strategy Risk Management Strategy Job title of lead contact: Corporate Services Manager Version number: Version 1 Group responsible for approving Executive Team / Governing Body the document: Date of final approval:

More information

Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS ESTABLISH GOALS AND CONTEXT IDENTIFY THE RISKS...8

Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS ESTABLISH GOALS AND CONTEXT IDENTIFY THE RISKS...8 Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS...4 1. ESTABLISH GOALS AND CONTEXT...5 2. IDENTIFY THE RISKS...8 Identifying the risks... 8 Identify the sources of the risks... 8 Identify the impact

More information

RISK MANAGEMENT POLICY October 2015

RISK MANAGEMENT POLICY October 2015 RISK MANAGEMENT POLICY October 2015 1. INTRODUCTION 1.1 The primary objective of risk management is to ensure that the risks facing the business are appropriately managed. 1.2 Paringa Resources Limited

More information

Lloyd s Minimum Standards MS6 Exposure Management

Lloyd s Minimum Standards MS6 Exposure Management Lloyd s Minimum Standards MS6 Exposure Management January 2019 2 Contents 3 Minimum Standards and Requirements 3 Guidance 3 Definitions 3 5 UW 6.1 Exposure Management System and Controls Framework 5 UW6.2

More information

Outline Capital Investment Strategy

Outline Capital Investment Strategy Outline Capital Investment Strategy INDEX FOREWORD 1. INTRODUCTION 2. PURPOSE 3. SUMMARY 4. INFLUENCES ON CAPITAL INVESTMENT 5. CURRENT CAPITAL EXPENDITURE 6. COMMERCIAL PROPERTY INVESTMENT STRATEGY 7.

More information

Bournemouth Primary MAT Risk Management Policy

Bournemouth Primary MAT Risk Management Policy Bournemouth Primary MAT Risk Management Policy 1. Introduction The Bournemouth Primary Multi-Academy Trust (the Trust) operates a risk management system in order to identify and manage key exposures and

More information

Job Safety Analysis Preparation And Risk Assessment

Job Safety Analysis Preparation And Risk Assessment Job Safety Analysis Preparation And Risk Assessment Sample Only Reference CPL_PCR_JSA_Risk_Assessment Revision Number SAMPLE ONLY Document Owner Sample Date 2015 File Location Procedure Revision Date Major

More information

Senior Director, Fire Life Safety & Risk Management

Senior Director, Fire Life Safety & Risk Management Page 1 of 3 Enterprise Risk Management Policy Item 4 November 15, 2018 Building Investment, Finance and Audit Committee Report: To: From: BIFAC:2018-66 Building Investment, Finance and Audit Committee

More information

PUBLIC INQUIRY DOCUMENT

PUBLIC INQUIRY DOCUMENT M4 Corridor around Newport PUBLIC INQUIRY DOCUMENT REFERENCE NO. : ID/184 RAISED BY: The Inspectors DATE: 17/01/2018 RESPONDED BY: Matthew Jones DATE: 02/02/2018 SUBJECT: Project Costs, Risk and Optimism

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK RISK MANAGEMENT FRAMEWORK UNIQUE REF NUMBER: GB/AC/001/V2.1 DOCUMENT STATUS: Approved by Audit & Governance Committee 18 October 2018 DATE ISSUED: November 2018 DATE TO BE REVIEWED: November 2021 1 AMENDMENT

More information

RISK M A N A G E M E N T P L A N

RISK M A N A G E M E N T P L A N CONTENTS LEARNING OUTCOMES... 2 INTRODUCTION... 3 RISK DEFINITION OVERVIEW... 3 RISK MANAGEMENT ROLES AND RESPONSIBILITIES... 3 RISK MANAGEMENT APPROACH... 4 RISK IDENTIFICATION... 4 RISK QUALIFICATION

More information

Planning Construction Procurement. A guide to risk and value management

Planning Construction Procurement. A guide to risk and value management Planning Construction Procurement A guide to risk and value management ISBN: 978-1-98-851708-7 (online) First published October 2015 Revised October 2016 New Zealand Government Procurement PO Box 1473

More information

Travel Risk Assessment Operation Manual

Travel Risk Assessment Operation Manual Travel Risk Assessment Operation Manual This document contains information on how to use the travel risk assessment system. Overview Any member of staff who is planning to travel overseas on official University

More information

Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management

Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management Jeff Hollingdale DQS South Africa jeffh@dqs.co.za PAS 55 Risk Management The guideline states: (4.4.7);

More information

Solvency II Detailed guidance notes for dry run process. March 2010

Solvency II Detailed guidance notes for dry run process. March 2010 Solvency II Detailed guidance notes for dry run process March 2010 Introduction The successful implementation of Solvency II at Lloyd s is critical to maintain the competitive position and capital advantages

More information

Implementation processes for the Flood Risk Management (Scotland) Act 2009

Implementation processes for the Flood Risk Management (Scotland) Act 2009 Implementation processes for the Flood Risk Management (Scotland) Act 2009 Final Report 30/05/2012 Page 0 Published by The James Hutton Institute on behalf of CREW Scotland s Centre of Expertise for Waters

More information

Policy. Safety risk assessment. 1 Why use risk assessment?

Policy. Safety risk assessment. 1 Why use risk assessment? Safety risk assessment V E R S I O N 1. 1 M A R C H 2 0 0 5 1 Why use risk assessment? 1.1 The principle reason for conducting risk assessments is to comply with our legal duty. The Management of Health

More information

PST Board Assurance Framework

PST Board Assurance Framework PST Board Assurance Framework 14 th January 2016 PST Board Assurance Framework Registered Address (No: IP030872) Fratton Park Frogmore Road Portsmouth PO4 8RA Prepared by Dr Mark Farwell PST Secretary

More information