1 APPLICATION FORM Under the Future Energy Jobs Act, ComEd retail customers taking service under the provisions of Rider POGCS Parallel Operation of Retail Customer Generating Facilities Community Supply (CS), or such retail customers assignee, are eligible to apply for a rebate. This rebate offer is also available to nonresidential retail customers taking service under Rider POGNM - Parallel Operation of Retail Customer Generating Facilities with Net Metering, or such nonresidential retail customers assignee. Please follow the steps below to ensure eligibility to receive a rebate from the ComEd Renewable Energy Distributed Generation Rebate Program. How to Apply 1. Verify eligibility Ensure your project meets the eligibility requirements as stated in the terms and conditions section of this form. Eligible renewable generating facilities installed after June 1, 2017, must be interconnected to the Company s distribution system by means of a smart inverter (see the California Energy Commission list of approved smart inverters at GoSolarCalifornia.org/equipment/inverters.php) Eligible renewable generating facilities with a nameplate or rated capacity of no more than 2,000 kw measured as nominal AC power output of such project. For a CS Beneficiary or CS Subscriber taking service under Rider POGCS, check with the CS Project developer/owner/operator to determine rebate eligibility. (NOTE: a rebate may have already been provided to the developer/owner/operator of the CS Project.) 2. Install equipment (Net Metering or Community Supply Project) For Rider POGNM qualified projects, install the eligible renewable generating facilities equipment in accordance with ComEd s interconnection requirements and the Illinois Administrative Codes. For Rider POGCS qualified community supply projects, install the eligible renewable generating facilities equipment in accordance with ComEd s interconnection requirements and the Illinois Administrative Codes. 3. Complete application Visit ComEd.com/DGRebate to apply online or to download the PDF application. 4. Submit application Submit your completed application, material invoices, specification sheets, and W Receive incentive payment ComEd will pay a rebate within 60 days of receipt of all required paperwork for a qualifying installation. Applications should be submitted by ONE of the following methods We strongly recommend completing the application process online, as ComEd is making an effort to reduce paper use and streamline the application process. However, printable, mailable options are available. ComEd.DGRebate@dnvgl.com (10MB file size limit; submit multiple s if necessary) Mail: ComEd DG Rebate, 700 Commerce Drive, Suite 330, Oak Brook, IL Questions? ComEd.DGRebate@dnvgl.com or call
2 APPLICATION FORM Directions: Please save a copy of this form to your computer by selecting File/Save As before entering text and numbers. Then fill in your information electronically and select Save. Note that this form requires Adobe Reader version 11.0 to function properly. Download the most recent version of Adobe Acrobat Reader DC at Pre-Approval Application (OPTIONAL) Final Application ESTIMATED PROJECT COST TOTAL PROJECT COST TOTAL INCENTIVE REQUESTED (TOTAL FROM PAGE 4 WORKSHEET) TOTAL INCENTIVE REQUESTED (TOTAL FROM PAGE 4 WORKSHEET) ESTIMATED COMPLETION DATE ACTUAL COMPLETION DATE Application Checklist Pre-approval is optional. If the installation has been completed, please skip to FINAL checklist. PRE FINAL ATTACH THE FOLLOWING (Incomplete applications will not be processed and applicants will be notified) 1. Completed application checklist (page 2 of this application) 2. Completed applicant and contractor information (page 3 of this application) N/A 3. Dated and itemized invoices listing the type and quantity of installed equipment, including final invoices 4. Specification sheets for all proposed / installed equipment 5. Rebate worksheet (page 4 of this application) N/A N/A 6. Customer W-9 form; third party W-9 form (if applicable) 7. Third party payment authorization (page 5 of this application, if applicable) Project Type (select one) Non-Residential Net Metering Customer (skip to Customer Information, page 3) Community Supply Project Developer (skip to Customer Information, page 3) Community Supply Subscriber/Beneficiary COMMUNITY SUPPLY SUBSCRIBER/BENEFICIARY ONLY PROJECT NAME (REQUIRED) EFFECTIVE DATE OF COMMUNITY SUPPLY SUBSCRIPTION TOTAL kw SUBSCRIBED Please fill in the Customer Information section at the top of page 3. This will complete your application as a CS Subscriber/Beneficiary. 2
3 CUSTOMER INFORMATION APPLICANT INFORMATION CUSTOMER NAME TAXPAYER ID: FEIN (NOTE: MUST ATTACH W-9 FORM, REV OCT 2018) ComEd ACCOUNT NUMBER NAME AS IT APPEARS ON YOUR ENERGY BILL CUSTOMER CONTACT NAME TITLE PHONE ADDRESS WHERE MEASURES INSTALLED CITY STATE ZIP MAILING ADDRESS, IF DIFFERENT THAN ABOVE CITY STATE ZIP CONTRACTOR INFORMATION (Primary point of contact for your project) CONTRACTING COMPANY CONTACT NAME TITLE PHONE ADDRESS CITY STATE ZIP 3
4 Energy Generation Source WORKSHEET Non-residential Net Metering and Community Supply customers are eligible for a $250/kW rebate on qualified distributed generation installations. Please see the Terms and Conditions for further details regarding eligibility and qualified equipment. * Specification sheets required for all model numbers listed below. Product / Type Model Number * DC Rating (kw) Qty Rebate (kw x Qty x $250) TOTAL REBATE $ Smart Inverter Information (required if installed after June 1, 2017) Manufacturer Model Number AC Rating (max 2000 kw) Voltage Qty Customer Signature Required at Pre-Application and Final Application I certify that the information provided in this application is true and correct. I have read and understand the program requirements and terms and conditions set forth in this application and agree to abide by these requirements. I verify by my signature hereto that I have authority to submit this application. ComEd CUSTOMER AUTHORIZED SIGNATURE SIGNATURE TITLE AND/OR RELATIONSHIP TO COMPANY PRINTED NAME DATE 4
5 OPTIONAL THIRD-PARTY PAYMENT AUTHORIZATION Payment Preference ComEd offers the option to assign your project s rebate payment to a third party. Please complete the third party payment authorization and submit it with your final application if you are interested in this option. OPTIONAL THIRD PARTY PAYMENT AUTHORIZATION (Please skip if check will be made payable to ComEd customer) COMPANY NAME TAXPAYER ID: FEIN (NOTE: MUST ATTACH W-9 FORM, REV NOV 2017) TAX STATUS (CHECK ONE) Individual / Sole Proprietor Partnership LLC Corporation Exempt CONTACT NAME PHONE MAILING ADDRESS CITY STATE ZIP Customer Signature Required When Assigning Rebate to a Third Party I am authorizing the payment of the rebate to the third party named below and I understand that I will not be receiving the rebate payment from ComEd. I also understand that my release of the payment to a third party does not exempt me from the program requirements outlines in the measure specifications and terms and conditions. ComEd CUSTOMER AUTHORIZED SIGNATURE SIGNATURE TITLE AND/OR RELATIONSHIP TO COMPANY PRINTED NAME DATE 5
6 TERMS AND CONDITIONS The Rider DG REBATE Renewable Energy Distributed Generation Rebate ( Rider DG REBATE ) program, offers qualifying retail customers a $250 rebate per kilowatt ( kw ) of nameplate generating capacity for an eligible project. The DG Rebate Program serves ComEd s non-residential customers that take service under the provisions of ComEd s Rider POGNM - Parallel Operation of Retail Customer Generating Facilities with Net Metering. The DG Rebate Program is also available to retail customers taking service under Rider POGCS Parallel Operation of Retail Customer Generating Facilities Community Supply as a CS Project, CS Beneficiary or CS Subscriber. Service under the DG Rebate Program is not restricted to retail customers that obtain electric power and energy supply from ComEd. Residential customers taking service under POGCS as a CS Subscriber or CS Beneficiary are not eligible for the DG Rebate Program if the CS Project owner or operator collected the rebate amount for the CS Project in whole. Residential customers taking service under POGCS as a CS Subscriber or CS Beneficiary are not eligible for the DG Rebate Program if the CS Project owner or operator collected the rebate amount for the CS Project in whole. Check with your CS Project administrator regarding your Rider DG Rebate eligibility prior to submitting this application. Additional Rider DG Rebate program qualification information regarding the size, location, and renewable generation requirements can be found in the Terms & Conditions of this DG Rebate Application Form. A qualified distributed generation facility includes; For a retail customer taking service under Rider POGNM - the retail customer must own or operate solar, wind, or other electric generating facilities powered by solar electric energy, wind, dedicated crops grown for electricity generation, agricultural residues, untreated and unadulterated wood waste, landscape trimmings, livestock manure, anaerobic digestion of livestock or food processing waste, fuel cells or microturbines powered by renewable fuels, or hydroelectric energy, provided such generating facilities;. (a) have a total rated capacity that does not exceed 2,000 kw,. (b) are located on the retail customer s premises, and. (c) are intended to offset the retail customer s electric power and energy requirements. For a retail customer taking service under Rider POGCS a retail customer that owns or operates a renewable generating facility;. (a) with a nameplate or rated capacity that does not exceed 2,000 kilowatts (kws),. (b) that is located in the Company s service territory and interconnected to the Company s distribution system under rules adopted by the Illinois Commerce Commission (ICC), and. (c) is powered by solar energy, wind, dedicated crops grown for electricity generation, agricultural residues, untreated and unadulterated wood waste, landscape trimmings, livestock manure, anaerobic digestion of livestock or food processing waste, fuel cells or microturbines powered by renewable fuels, or hydroelectric energy, provided such hydroelectric energy does not involve construction or significant expansion of hydropower dams. Retail customers who begin taking service under Rider POGNM or Rider POGCS after June 1, 2017 must have a smart inverter associated with the distributed generation facility in order to be eligible for a rebate. Nonresidential retail customers taking service under Rider POGNM prior to June 1, 2017 must be interconnected to ComEd s distribution service. Such retail customers are not required to have a smart inverter installed to qualify for the rebate. A retail customer taking service under Rider POGCS that is a CS Beneficiary, CS Project or a CS Subscriber, as those terms are defined in the Definitions section of the rider, are eligible for a DG Rebate as follows; a CS Beneficiary is a retail customer, residential or nonresidential, that has an interest in the electric power and energy produced by a CS Project that is not a community renewable generation project, as defined in Section 1-10 of the Illinois Power Agency (IPA) Act, with such interest expressed as a portion of the total nameplate or rated capacity of the CS Project and sized primarily to offset part or all of such retail customer s electric power and energy requirements. NOTE: Such CS Beneficiary is NOT eligible for a DG Rebate whenever the owner or operator of the CS Project that the CS Beneficiary has an interest in previously applied for and received a DG Rebate for the CS Project. a CS Project is a renewable generating facility that is a nonresidential retail customer that includes. (a) properties owned or leased by multiple retail customers that contribute to the operation of a renewable generating facility through an ownership or leasehold interest of at least 200 watts in such facility, such as a 6
7 TERMS AND CONDITIONS community-owned wind project, a community-owned biomass project, a community owned solar project, or a community methane digester processing livestock waste from multiple sources, provided that the facility is also located within the utility s service territory;. (b) individual units, apartments, or properties located in a single building that are owned or leased by multiple retail customers and collectively served by a common renewable generating facility, such as an office or apartment building, a shopping center or strip mall served by photovoltaic panels on the roof; or. (c) a community renewable generation project as defined in Section 1-10 of the IPA Act. a CS Subscriber is a retail customer, residential or nonresidential, that has an interest in the electric power and energy produced by a CS Project that is a community renewable generation project, as defined in Section 1-10 of the IPA Act, with such interest expressed as a portion of total nameplate or rated capacity of the CS Project and sized primarily to offset part or all of such retail customer s electric power and energy requirements. NOTE: Such CS Subscriber is NOT eligible for a DG Rebate whenever the owner or operator of the CS Project that the CS Subscriber has an interest in previously applied for and received a DG Rebate for the CS Project. Equipment must be installed in compliance with state codes. You must be a current ComEd delivery service customer. Commonwealth Edison Company (ComEd) is offering a distributed generation rebate (DG Rebate) under the ComEd RIDER DG REBATE tariff in accordance with the provisions of the Public Utilities Act, Section The DG Rebate is available to: 1) nonresidential retail customers taking service under ComEd s net metering tariff, Rider POGNM Parallel Operation of Retail Customer Generating Facilities with Net Metering, or 2) retail customers taking service as a Community Supply (CS) Project, CS Beneficiary or a CS Subscriber under ComEd s Community Supply tariff, Rider POGCS - Parallel Operation of Retail Customer Generating Facilities Community Supply. NOTE: CS Beneficiary and CS Subscriber customers may not be eligible for the DG Rebate under circumstances where the CS Project they have entered into an agreement with has already received the DG Rebate. Check with your CS Project administrator regarding your DG Rebate eligibility prior to submitting this application. Service is not restricted to retail customers that obtain electric power and energy supply from ComEd. Retail customers obtaining electric power and energy supply from alternative retail electric suppliers are also eligible. The DG Rebate is not available to residential retail customers receiving net metering service under ComEd s Rider POGNM. The applicant warrants that it 1) has not assigned any rights associated with the rebate and 2) has the right to allow the Company to operate and control and Smart Inverter(s) associated with such distributed electric renewable generating facility for purposes of contributing to grid support during excursions from normal operating conditions, including, but not limited to, voltage and frequency, operating conditions utilizing the Smart Inverter functionality and conforming to the requirements in the DG Rebate Required Smart Inverter Settings Informational Sheets of the Company s Schedule of Rates, as applicable. PROGRAM EFFECTIVE DATES DG Rebates are offered in accordance with ComEd s tariffs, RIDER DG REBATE RENEWABLE ENERGY and RIDER DG REBATE ADJUSTMENT RENEWABLE ENERGY ADJUSTMENT. The effective date of the DG Rebate is December 12, 2018 and will continue to be available as provided for in RIDER DG REBATE. In the event of a conflict between the tariffs and the information provided herein, the tariffs prevail. PROGRAM AND PROJECT ELIGIBILITY Project requirements under the ComEd DG Rebate program include the following: Equipment must be installed in a property owned by the applicant, or the applicant must receive permission from the property owner to install the equipment. Submission of an application indicates that the tenant has obtained this permission. PARTICIPATION RELEASE If receiving a DG Rebate from ComEd, the customer authorizes the release of any application data, including customer name and address, to any contractor or other vendor providing services or support under this program. 7
8 TERMS AND CONDITIONS APPLICATION PROCESS Completed and customer-signed applications must be accompanied by an itemized contractor invoice(s) or proof of purchase receipt(s), which contains all of the required information as listed on page 1 of the application. Failure to complete the rebate application in full and provide the required supporting documentation will either delay the payment process or result in the application being denied. INSTANT REBATE REQUIREMENTS If the customer is releasing payment of the rebate to the installing contractor for an instant rebate, the contractor must submit a customer-signed copy of the customer job order/invoice showing the full and correct rebate amount deducted from the total purchase price and labeled as a ComEd rebate. It is the installing contractor s sole responsibility to verify customer, equipment and installation eligibility prior to providing an instant rebate. Contractor assumes all liability by providing the instant rebate. LANDLORD APPLICATION REQUIREMENTS A landlord with a tenant who holds the property s ComEd account may receive a DG Rebate payment for a qualifying installation paid for by the landlord and completed in a property owned by the landlord. The customer may release payment of the DG Rebate to the landlord in the application and include a copy of the contractor invoice signed by the purchaser (i.e. the landlord). INSPECTIONS ComEd reserves the right to inspect all rebated equipment to verify compliance with program rules and the accuracy of project documentation. This may include post-installation inspections or participant interviews. Upon reasonable notice by ComEd, the customer must allow access to project documents and the installed equipment for a period of one year after receipt of a DG Rebate payment by ComEd. Customer also agrees that by receiving a DG Rebate, he or she may be contacted by an evaluator to complete a customer survey. Replaced equipment must be permanently removed and disposed of in accordance with local codes and ordinances. Resale of replaced equipment is expressly forbidden. Resale equipment, new parts installed in existing equipment, or equipment that is leased, rebuilt, rented, received from insurance claims, received from a warranty, received with rewards points or won as a prize do not qualify. TAX LIABILITY Rebates may be taxable under federal and state tax codes and, if more than $600, will be reported to the IRS unless the customer provides acceptable proof that it is exempt from payment of such applicable taxes. In any event, ComEd is not responsible for any taxes that may be imposed as a result of your receipt of a DG Rebate, or for providing legal or accounting advice regarding such. Customer should consult with its tax accountant or advisor regarding potential tax liability. DISPUTES/GOVERNING LAW This application shall be exclusively governed by and interpreted in accordance with the laws of the State of Illinois. Any litigation between the parties shall be prosecuted only in the state or federal courts located in Cook County, Illinois. TOXIC MATERIALS Neither ComEd, nor its consultants, contractors and/or subcontractors, shall have any responsibility for the discovery, presence, handling, removal, disposal of, or exposure to hazardous materials of any kind in connection with customer s home or business, including, without limitation, asbestos, asbestos products, PCBs or any other toxic substances. LIMITATIONS OF LIABILITY The customer shall independently evaluate any advice or information offered by ComEd related to estimates of electricity savings or program costs and is solely responsible for the selection and installation of generation equipment. Each party hereby agrees to defend, indemnify and hold harmless the other party, its consultants, contractors and 8
9 TERMS AND CONDITIONS subcontractors, and their respective officers, employees, agents, assigns, and successors-in-interest ( Indemnified Parties ) from and against any third-party claims, damages, losses, liability, costs (including attorney s fees and expenses) for bodily injury to any person (including death resulting therefrom) and property damage arising out of or in connection with the program, except to the extent such claims, damages, losses, liability and costs are caused by the negligence or willful misconduct of the other party. DISCLAIMER ComEd does not guarantee that certain energy savings will be achieved and does not make any warranties associated with the generation facilities eligible for rebates under this program. ComEd has no obligations regarding, and does not endorse or guarantee, any claims, promises, representations, or work made or performed, or equipment furnished or installed by any contractors, subcontractors, or vendors that sell or install distributed generation facilities. The customer shall be entitled to the energy cost savings realized by the customer that result from the installation of distributed generation at the customer s site. RELEASE OF LIABILITY ComEd program administrators and implementers disclaim any and all liability, loss or damage and make no guarantees related to: Participation in the program, including use or installation of the equipment. Loss or delay of rebate check in the mail. Terms and conditions apply. Commonwealth Edison Company,
STANDARD AND CUSTOM INCENTIVES PRE-APPROVAL AND FINAL APPLICATION FORM
PRE-APPROVAL AND FINAL APPLICATION FORM The ComEd Energy Efficiency Program offers incentives to help facilities save money by improving the efficiency of their equipment. Receive standard cash incentives
More informationENERGY STAR SMART THERMOSTAT REBATE APPLICATION
ENERGY STAR SMART THERMOSTAT Smart thermostat must be purchased and installed by December 31, 2018. Application must be submitted within 60 days of purchase or by February 28, 2019, whichever comes first.
More informationNEW CONSTRUCTION PARTICIPATION CHECKLIST
NEW CONSTRUCTION PARTICIPATION CHECKLIST June 1, 2017 through December 31, 2017 DIRECTIONS: Please save a copy of this form to your computer by selecting FILE/SAVE AS before entering text and numbers.
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 61967-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58820-E Sheet 1 SOUTHERN CALIFORNIA EDISON COMPANY FACILITY INTERCONNECTION
More informationCITY OF UKIAH PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR NET ENERGY METERING FROM SOLAR ELECTRIC GENERATING FACILITIES OF 1 KW (KILOWATT) TO 100 KW
CITY OF UKIAH PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR NET ENERGY METERING FROM SOLAR ELECTRIC GENERATING FACILITIES OF 1 KW (KILOWATT) TO 100 KW DECLARATIONS ( Customer-Generator ), and the City of
More informationPolicy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620
Policy Bulletin No. 25 Net Metering Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Interconnection Agreement For Net Energy Metering With Customer Solar, Wind,
More informationSolar: Wind: Total: (AC Nameplate Rating) x (720 hrs/mo) x (0.15 = solar/ 0.10 = wind) Date(s) of Parallel Operation Rebate Expiration
APPLICATION FOR THE INTERCONNECTION OF A SOLAR OR WIND POWERED ELECTRICAL GENERATING FACILITY TO BE USED FOR NET ENERGY METERING SERVICE APPLICABILITY This application is for the interconnection of a solar,
More informationPEPCO CUSTOMER NET ENERGY METERING CONTRACT. Qualifying facility of 1000 KW or less
PEPCO CUSTOMER NET ENERGY METERING CONTRACT Qualifying facility of 1000 KW or less Customer Name: Customer Pepco Acct. #: Customer Address: Customer Telephone Number: Customer E-Mail Address: Generator
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 61965-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58811-E Sheet 1 SOUTHERN CALIFORNIA EDISON COMPANY 10 KILOWATT OR LESS
More informationMason County PUD No. 1. Net Energy Metering Interconnection Agreement
Mason County PUD No. 1 Net Energy Metering Interconnection Agreement Customer Owned Fuel Cell, Solar, Wind, Biogas, Combined Heat and Power or Hydropower Electric Generating Facilities of 100 Kilowatts
More informationRESERVATION REQUEST FORM INSTRUCTIONS
Form 1 Side 1 RESERVATION REQUEST FORM INSTRUCTIONS TO BE COMPLETED BY THE LADWP CUSTOMER AND PV RETAILER / DISTRIBUTOR / MANUFACTURER OR PV CONTRACTOR / INSTALLER 1. Reservations are good for twelve months,
More informationNET METERING CUSTOMER SITED RENEWABLE GENERATION FACILITIES POLICY
A CUSTOMER OWNED UTILITY Serving Our Community Since 1894 NET METERING CUSTOMER SITED RENEWABLE GENERATION FACILITIES POLICY APPROVED BY THE BOARD OF ELECTRIC COMMISSIONERS: June 28 th, 2016 Previously
More informationApplication for Interconnection and Net Metering Level 1
Application for Interconnection and Net Metering Level 1 Use this Application only for: 1.) a generating facility that is inverter based and certified by a nationally recognized testing laboratory to meet
More informationEASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 27. SUBJECT: Interconnection and Parallel Operation of Distribution Generation
EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 27 SUBJECT: Interconnection and Parallel Operation of Distribution Generation OBJECTIVE: To establish safety, reliability and economic standards for interconnection
More informationRECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:
LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 10 KW AC AND LESS THAN OR EQUAL TO 100 KW AC TIER 2 This Interconnection
More informationCustom Incentive Application for Business Customers
2019 Custom Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the Terms and Conditions
More information7 th Revision of Sheet No. 150 Canceling 6 th Revision WN U-60 of Sheet No. 150
7 th Revision of Sheet No. 150 Canceling 6 th Revision WN U-60 of Sheet No. 150 TABLE OF CONTENTS Overview Sheet 150-A Availability Sheet 150-A Definitions Sheet 150-B Monthly Rates Sheet 150-D Terms And
More informationRECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:
LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 10 KW AND LESS THAN OR EQUAL TO 100 KW TIER 2 This Interconnection Agreement
More informationInterconnection of Electric Generators
Interconnection of Electric Generators (GENERATING CAPACITY OF NOT MORE THAN 25 KILOWATTS) Public Utility #1 of Ferry County Republic Washington November 15, 2007 Table of Contents Chapter 1 Purpose and
More informationCustom Incentive Application for Business Customers
2019 Custom Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the Terms and Conditions
More informationTier 1 Net Metering and Renewable Resource Interconnection Agreement. Grantee: Abbreviated Legal Description: Assessor s Tax Parcel Number(s):
Return to: Inland Power & Light Co. PO Box A Spokane, WA 99219-5000 Reference numbers of related documents: N/A Tier 1 Net Metering and Renewable Resource Interconnection Agreement Grantor: Inland Power
More informationInterconnection Request Application Form for Interconnecting a Certified Inverter-Based Generating Facility No Larger than 20 kw
Attachment 6 Interconnection Request Application Form for Interconnecting a Certified Inverter-Based Generating Facility No Larger than 20 kw This Interconnection Request Application Form is considered
More informationPlease Refer to Attached Sample Form
Revised Cal. P.U.C. Sheet No. 41131-E Cancelling Revised Cal. P.U.C. Sheet No. 41004-E* U 39 San Francisco, California Electric Sample Sheet 1 Interconnection Agreement for Net Metering for a Renewable
More informationName: City: State: Zip Code: Is the applicant the property owner at the system address? Yes No. City: State: Zip Code: City: State: Zip Code:
Maryland Level 1 Interconnection Request Application Form and Conditional Agreement to Interconnect (Lab Certified Inverter-based Small Generator Facilities Less than 10 kw) Interconnection Applicant Contact
More informationInterconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW
Interconnection Application and Compliance Form For Photovoltaic Systems Up to 2 MW A. APPLICANT INFORMATION *Person/Company Name: *OUC Account No.: *Mailing Address: *City, State & Zip: Street Address
More informationINTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS
INTERCONNECTION AGREEMENT FOR NET BILLING FOR RENEWABLE ELECTRICAL GENERATING FACILITIES OF ONE MEGAWATT OR LESS TABLE OF CONTENTS SECTION TITLE PAGE 1. CUSTOMER-GENERATOR RENEWABLE ELECTRICAL GENERATING
More informationAN APPLICATION FEE OF $50.00 MUST BE SUBMITTED WITH THE APPLICATION. Interconnection Applicant Contact Information. Name: Address:
Illinois Standard Distributed Generation Interconnection Level 1 Interconnection Request Application Form and Conditional Agreement to Interconnect (Lab-Certified Inverter-Based Distributed Generation
More informationINTERCONNECTION GENERATION AND NET METERING POLICY
INTERCONNECTION GENERATION AND NET METERING POLICY Manual for Member Owned Interconnection Generation Facilities Equal to 100 kw or Less Revised: May 11, 2015 Approved: August 25, 2014 Effective: August
More informationSuperseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 RULE NO. 18. Net Energy Metering
Superseding REVISED Sheet No. 38 REVISED SHEET NO. 38 Effective March 20, 2008 Effective February 6, 2014 A. ELIGIBLE CUSTOMER-GENERATOR RULE NO. 18 Net Energy Metering Net energy metering is available
More informationStandard Interconnection Agreement for Customer-Owned Renewable Generation System
Standard Interconnection Agreement for Customer-Owned Renewable Generation System This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at in,
More informationRenewable Generation (Category 1-20 kw and less):
Renewable Generation (Category 1-20 kw and less): Net Metering Program Interconnection Program Application Parallel Operating Agreement Net Metering Program What is net metering? Net metering is a tool
More informationSTANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM
STANDARD INTERCONNECTION AGREEMENT FOR RENEWABLE GENERATION SYSTEM This Agreement is made and entered into this day of, 20, by and between, (hereinafter RGS Owner ), located at in, Florida, and Utility
More informationSmall Generator Interconnection Application
Small Generator Interconnection Application Eligibility: All Interconnection Customers must submit a completed copy of this application to Holy Cross Energy s Power Supply Department. HCE s review process
More informationRenewable Generation (Category 1 20 kw and less):
Renewable Generation (Category 1 20 kw and less): Net Metering Program Interconnection Program Application Parallel Operating Agreement Net Metering Program What is net metering? Net metering is a tool
More informationTier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System
CITY OF MOUNT DORA, FLORIDA FIRST REVISED SHEET NO. 15.0 CANCELS ORIGINAL SHEET NO. 15.0 Tier 1 Standard Interconnection Agreement Customer-Owned Renewable Generation System This Agreement is made and
More informationA. CUSTOMER INFORMATION Customer. B. PROJECT INFORMATION Project. C. CONTRACTOR INFORMATION Contractor D. INCENTIVE PAYMENT RELEASE
Eugene Water & Electric Board Energy Management Services 500 E 4 th Avenue / PO Box 10148 Eugene, OR 97440 541-685-7000 www.eweb.org EWEB Solar Electric Program 2018 Power Purchase Agreement ( Agreement
More informationRESIDENTIAL REWARDS PROGRAM SOLAR ELECTRIC (PV) APPLICATION
SECTION 1: CUSTOMER INFORMATION RESIDENTIAL REWARDS PROGRAM SOLAR ELECTRIC (PV) APPLICATION This application covers products purchased and installed between January 1, 2013 and December 31, 2013 that received
More informationINTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS
INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS This Interconnection Agreement for Customer-Owned Renewable Generation Systems ( Interconnection Agreement ) is made this day of
More informationExhibit A Simplified Process Interconnection Application
Exhibit A Simplified Process Interconnection Application Instructions (please do not submit this page) General Information: If you, the Interconnecting Customer, wish to submit an application to interconnect
More informationPlease Refer to Attached Sample Form
Revised Cal. P.U.C. Sheet No. 41147-E Cancelling Revised Cal. P.U.C. Sheet No. 40751-E U 39 San Francisco, California ELECTRIC SAMPLE FORM NO. 79-978 Sheet 1 Interconnection Agreement for Net Energy Metering
More informationPlease Refer to Attached Sample Form
Revised Cal. P.U.C. Sheet No. 41148-E* Cancelling Revised Cal. P.U.C. Sheet No. 41015-E U 39 San Francisco, California Electric Sample Form No. 79-978-02 Sheet 1 Interconnection Agreement for Net Energy
More information2. IDENTITY AND LOCATION OF GC
INTERCONNECTION AND NET ENERGY METERING AGREEMENT FOR LARGE COMMERCIAL CUSTOMERS OF A SOLAR, WIND OR HYBRID OF BOTH GENERATING FACILITY HAVING A CAPACITY OF 30 KW TO 1,000 KW DECLARATIONS This Interconnection
More informationNHEC s 2014 Residential Solar Photovoltaic Incentive Program
NHEC s 2014 Residential Solar Photovoltaic Incentive Program Dear Member: Thank you for inquiring about your New Hampshire Electric Cooperative s (NHEC) Residential Solar Photovoltaic (PV) Incentive Program.
More informationSPECIAL RULES GOVERNING THE APPLICATION OF RATE RIDER RGB
1 of 5 1. A Customer shall not operate electric generating equipment in parallel with the Company's electric system unless specifically authorized in writing by the Company, consistent with the rules and
More informationEASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 27. SUBJECT: Interconnection and Parallel Operation of Distribution Generation
EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 27 SUBJECT: Interconnection and Parallel Operation of Distribution Generation OBJECTIVE: To establish safety, reliability and economic standards for interconnection
More informationROCK ENERGY COOPERATIVE INTERCONNECTION POLICY Policy M Board Policy Interconnection and Parallel Operation of Distributed Generation
ROCK ENERGY COOPERATIVE INTERCONNECTION POLICY Policy M25-08 SUBJECT: Board Policy Interconnection and Parallel Operation of Distributed Generation OBJECTIVE: To establish safety, reliability and economic
More informationDISTRICT OF COLUMBIA COMMUNITY RENEWABLE ENERGY FACILITY (CREF) APPLICATION and CONTRACT
l pepco. An Exelon Company ISTRICT OF COLUMBIA COMMUNITY RENEWABLE ENERGY FACILITY (CREF) APPLICATION and CONTRACT Send applications via Email or Mail to: The Green Power Connection Team Pepco An Exelon
More informationLEVEL 1: STANDARD APPLICATION FORM AND INTERCONNECTION AGREEMENT
LEVEL 1: STANDARD APPLICATION FORM AND INTERCONNECTION AGREEMENT Interconnection Request Application Form and Conditional Agreement to Interconnect (For Lab-Certified Inverter-Based Distributed Generation
More informationI. Members Applying for New Interconnection/Submission of Plans/Specifications.
PLATTE-CLAY ELECTRIC COOPERATIVE APPLICATION AND AGREEMENT FOR INTERCONNECTION AND NET METERING OF RENEWABLE ENERGY SYSTEMS WITH CAPACITY OF 100 kw OR LESS PROCEDURES: I. Members Applying for New Interconnection/Submission
More informationSTANDARD INTERCONNECTION AGREEMENT FOR TIER 1 RENEWABLE GENERATOR SYSTEMS
STANDARD INTERCONNECTION AGREEMENT FOR TIER 1 RENEWABLE GENERATOR SYSTEMS This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at in, Florida
More informationENTERGY NEW ORLEANS, INC. STANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES LOCATED IN ORLEANS PARISH
INSTRUCTIONS: Enter information in the empty fields below and send this form to Entergy. This Standard Interconnection Agreement shall be completed, submitted and approved before the net metering facility
More informationENTERGY MISSISSIPPI, INC. STANDARD INTERCONNECTION APPLICATION AND AGREEMENT FOR NON-RESIDENTIAL NET METERING FACILITIES (for kw systems)
INSTRUCTIONS: Enter information in the empty fields below and send this form to Entergy Mississippi, Inc. ( Entergy or the Company ). This Standard Interconnection Application and Agreement shall be completed,
More informationENTERGY LOUISIANA, LLC STANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES
INSTRUCTIONS Enter information in the empty fields below and send this form to Entergy. This Standard Interconnection Agreement shall be completed, submitted and approved before the net metering facility
More informationTown of Highlands Board Approved as of May 17, 2012
TOWN OF HIGHLANDS INTERCONNECTION AGREEMENT FOR SMALL PHOTOVOLTAIC GENERATION FACILITY OF 10 kw OR LESS This PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR SMALL GENERATION 10 kw or less (the Agreement ),
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 63569-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 63569-E 61960-E Sheet 1 VIRTUAL NET METERING FOR MULTIFAMILY AFFORDABLE
More informationNET-ENERGY METER AGGREGATION INTERCONNECTION AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC CUSTOMERS
CITY OF HEALDSBURG, ELECTRIC DEPARTMENT NET-ENERGY METER AGGREGATION INTERCONNECTION AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC CUSTOMERS DECLARATIONS ( Customer ) and the City of Healdsburg ( City
More informationSTANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES
STANDARD INTERCONNECTION AGREEMENT FOR NET METERING FACILITIES I. STANDARD INFORMATION Section 1. Customer Information Name: _Customer Name Here Mailing Address(Box#/Street): 2300 Jackson St. (City/State/Zip):_Conway,
More informationNHEC s 2016 Residential Solar Photovoltaic Incentive Program
Dear NHEC Member: NHEC s 2016 Residential Solar Photovoltaic Incentive Program Thank you for inquiring about your New Hampshire Electric Cooperative s (NHEC) Residential Solar Photovoltaic (PV) Incentive
More informationParkland Light & Water Company Park Ave Tacoma, WA 98444
Parkland Light & Water Company 12918 Park Ave Tacoma, WA 98444 Interconnection Requirements of Member Owned Renewable Electric Generating Facilities of 100 Kilowatts or Less (REVISED 8/29/2015) Table of
More informationJefferson Energy Cooperative Policy 124 DISTRIBUTED GENERATION POLICY
DISTRIBUTED GENERATION POLICY I. OBJECTIVE This document establishes the terms and conditions for the interconnection of distributed generation facilities and for providing net energy metering services
More informationSURPLUS ENERGY PURCHASE AGREEMENT PARALLEL CUSTOMER GENERATION CGS 8 WISCONSIN AGGREGATE RENEWABLE CAPACITY OF 20 KILOWATTS OR LESS
SURPLUS ENERGY PURCHASE AGREEMENT PARALLEL CUSTOMER GENERATION CGS 8 WISCONSIN AGGREGATE RENEWABLE CAPACITY OF 20 KILOWATTS OR LESS This Agreement made this day of, by and between Wisconsin Electric Power
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No E.
Southern California Edison Revised Cal. PUC Sheet No. 60051-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 58818-E Sheet 1 VIRTUAL NET ENERGY METERING FOR GENERATING FACILITIES
More informationUp Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating)
Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating) This Up Front Incentive Renewable Energy Credit Purchase Agreement ( Agreement ) is hereby made and entered
More informationIllinois Adjustable Block Program PV System Purchase Disclosure Form
Illinois Adjustable Block Program PV System Purchase Disclosure Form Draft for Stakeholder Comments Released October 3, 2018 Comments Due October 26, 2018 This form gives consumers who are considering
More informationSouthern California Edison Company FERC Electric Tariff, Second Revised Volume No. 5. APPENDIX 10 to GIP
APPENDIX 10 to GIP Application, Procedures, and Terms and Conditions for Interconnecting a Certified Inverter-Based Small Generating Facility No Larger than 10 kw ("10 kw Inverter Process") 1.0 The Interconnection
More informationSTANDARD INTERCONNECTION AGREEMENT FOR TIER 2 RENEWABLE GENERATOR SYSTEMS
STANDARD INTERCONNECTION AGREEMENT FOR TIER 2 RENEWABLE GENERATOR SYSTEMS This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at in, Florida
More informationINTERCONNECTION & NET ENERGY METERING AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC GENERATING FACILITIES
D ECLARATIONS R EV 0 7. 21.2017 P G.1 CITY OF HEALDSBURG, ELECTRIC DEPARTMENT INTERCONNECTION & NET ENERGY METERING AGREEMENT FOR RESIDENTIAL AND COMMERCIAL ELECTRIC GENERATING FACILITIES DECLARATIONS
More informationLane Electric Cooperative, Inc. Eugene, Oregon Policy 311 (Net-Metering Services)
October 2018 Lane Electric Cooperative, Inc. Eugene, Oregon Policy 311 (Net-Metering Services) I. Objective A. This Policy is offered in compliance with ORS 757.300, as amended by House Bill 3219, dated
More informationApplication Terms & Conditions and Final Payment Agreement
Prescriptive, Self-Direct Custom Program & Self-Direct Application Terms & Conditions and Final Payment Agreement Version: January 1, 2015 January 2017 TERMS AND CONDITIONS AEP Ohio offers Efficient Products
More informationTRI-COUNTY ELECTRIC COOPERATIVE APPLICATION AND AGREEMENT FOR INTERCONNECTION AND NET METERING OF SYSTEMS WITH CAPACITY OF 100 kw OR LESS
TRI-COUNTY ELECTRIC COOPERATIVE APPLICATION AND AGREEMENT FOR INTERCONNECTION AND NET METERING OF SYSTEMS WITH CAPACITY OF 100 kw OR LESS PROCEDURES: I. Members Applying for New Interconnection/Submission
More informationGARLAND POWER & LIGHT. GP&L s Solar Generation Installation Requirements 2018
GARLAND POWER & LIGHT GP&L s Solar Generation Installation Requirements 2018 All GP&L Customers who plan to install Solar Photovoltaic Panels must meet minimum requirements. Please direct any questions
More informationResidential and Small Scale Air Source Heat Pump Program System Owner s Agreement
Residential and Small Scale Air Source Heat Pump Program System Owner s Agreement Updated: August 10, 2016 The following Participant s Agreement (the Agreement ) is issued by the Massachusetts Clean Energy
More informationClark Public Utilities
Electric Generating Facilities of 100 Kilowatts or Less This ( Agreement ) is entered into by the undersigned customer ("Customer"), and, ( Utility ). Both parties, who may be herein further referred to
More informationPHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR ELECTRIC GENERATING FACILITES Customer Owned Generation-Distribution Rate (Schedule G-1)
PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR ELECTRIC GENERATING FACILITES Customer Owned Generation-Distribution Rate (Schedule G-1) This Agreement is entered into on by and between the City of Lompoc,
More informationNET ENERGY METERING AND INTERCONNECTION AGREEMENT
NET ENERGY METERING AND INTERCONNECTION AGREEMENT This Net Energy Metering and Interconnection Agreement (the Agreement ), dated,, (the Effective Date ), is entered into by and between the CITY OF PALO
More informationTaunton Municipal Lighting Plant. This INTERCONNECTION & NET METERING AGREEMENT 1. CUSTOMER ELECTRIC GENERATING SYSTEM
Taunton Municipal Lighting Plant INTERCONNECTION & NET METERING AGREEMENT For Customer-Owned, Grid-Connected Electric Generating Systems of 60kW or Less This INTERCONNECTION & NET METERING AGREEMENT (
More informationMASTER DISTRIBUTED GENERATION RENEWABLE ENERGY CERTIFICATE PURCHASE AND SALE AGREEMENT COVER SHEET
MASTER DISTRIBUTED GENERATION RENEWABLE ENERGY CERTIFICATE PURCHASE AND SALE AGREEMENT COVER SHEET This Master Distributed Generation Renewable Energy Certificate Purchase and Sale Agreement (this Agreement
More informationPOWER PURCHASE and INTERCONNECTION AGREEMENT FOR SNAP GENERATION
POWER PURCHASE and INTERCONNECTION AGREEMENT FOR SNAP GENERATION This Agreement, effective the day of, 20 by and between PUBLIC UTILITY DISTRICT NO. 1 OF Chelan COUNTY, WASHINGTON, herein referred to as
More informationSOLAR PV INSTALLATION AT USC BASEBALL STADIUM
AMENDMENT NO. 7 TO SOLICITATION TO: ALL VENDORS FROM: Charles Johnson, Procurement Manager SUBJECT: SOLICITATION NUMBER: USC-RFP-1761-CJ SOLAR PV INSTALLATION AT USC BASEBALL STADIUM DATE: June 30, 2010
More informationStandard Interconnection Agreement for Customer-Owned Renewable Generation System kw
Standard Interconnection Agreement for Customer-Owned Renewable Generation System kw This Agreement is made and entered into this day of, 20, by and between, (hereinafter called "Customer"), located at
More informationPublic Utility District No. 1 Of Jefferson County
Public Utility District No. 1 Of Jefferson County INTERCONNECTION & NET METERING AGREEMENT For Customer-Owned, Grid Connected Electric Generating Systems of 100kW or Less This INTERCONNECTION & NET METERING
More informationResidential Equipment Rebates Application Instructions
ENERGY EFFICIENCY REBATE PROGRAM Residential Equipment s Application Instructions A new 07 Equipment Application will be available soon. In the meantime, please submit this 06 Equipment Application until
More informationSTANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission
STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission This STANDARD INTERCONNECTION AGREEMENT, (the Agreement ), is entered into this day of, 20 by and between, hereinafter called Customer
More informationENERGY EFFICIENCY CONTRACTOR AGREEMENT
ENERGY EFFICIENCY CONTRACTOR AGREEMENT 2208 Rev. 2/1/13 THIS IS AN AGREEMENT by and between PUBLIC UTILITY DISTRICT NO. 1 OF SNOHOMISH COUNTY (the District ) and a contractor registered with the State
More informationCustomer account name Phone ( Installation address City State Mailing address City State
If you conserve, you can save. UTAH ThermWise Custom Business Rebates Simplified Analysis Pre-Installation Report (PIR) Application Application Instructions IMPORTANT: Please read this application carefully.
More informationSTANDARD INTERCONNECTION APPLICATION FOR NET METERING FACILITIES
STANDARD INTERCONNECTION APPLICATION FOR NET METERING FACILITIES This application and interconnection agreement is for grid connected, customer owned generating facilities using certified inverters that
More informationHOLY CROSS ENERGY November 3, 2015 GENERATOR INTERCONNECT POLICY
GENERATOR INTERCONNECT POLICY GENERATOR INTERCONNECT (PROCEDURE) GENERATOR INTERCONNECT (GUIDELINES) Page 1 of 50 TABLE OF CONTENTS GENERATOR INTERCONNECT (PROCEDURE)... 4 I. GENERAL OVERVIEW... 5 A. Applicability...
More informationENTERGY MISSISSIPPI, INC. STANDARD INTERCONNECTION APPLICATION AND AGREEMENT FOR RESIDENTIAL NET METERING FACILITIES (for systems 20 kw or less)
INSTRUCTIONS: Enter information in the empty fields below and send this form to Entergy Mississippi, Inc. ( Entergy or the Company ). This Standard Interconnection Application and Agreement shall be completed,
More informationRECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:
LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 100 KW AND LESS THAN OR EQUAL TO 1 MW TIER 3 This Interconnection Agreement
More informationLighting New Construction Incentive Application for Business Customers
0 22018 Lighting New Construction Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer
More informationRENEWABLE ENERGY INCENTIVE PROGRAM Step 1, Section 1 Uniform Credit Purchase Program Application
RENEWABLE ENERGY INCENTIVE PROGRAM Step 1, Section 1 Uniform Credit Purchase Program Application For residential and commercial systems, the combined generation capacity at the location is limited to a
More informationCustomer Information Packet on Net(B) Metering SYSTEM MUST BE OWNED AND OPERATED BY CUSTOMERS OF WAKEFIELD MUNICIPAL GAS AND LIGHT DEPARTMENT
Net(B) Metering Customer Information Packet on Net(B) Metering SYSTEM MUST BE OWNED AND OPERATED BY CUSTOMERS OF WAKEFIELD MUNICIPAL GAS AND LIGHT DEPARTMENT 1. Cover Letter to Customers 2. What is Net(B)
More informationSolarCurrents Program Agreement
SolarCurrents Program Agreement This SolarCurrents Agreement, including all exhibits hereto ( Agreement ) is made by and between DTE Electric Company ( DTE ), a Michigan corporation, whose address is One
More informationForm No. 23 DECLARATIONS
GOLDEN STATE WATER COMPANY Revised Cal. P.U.C. Sheet No. 1579-E SAN DIMAS, CALIFORNIA 91773-9016 Canceling Original Cal. P.U.C. Sheet No. 1506-E DECLARATIONS Page 1 This Interconnection Agreement ("Agreement")
More information2018 Residential Program Geothermal Heat Pump Rebate Application
MEMBER INFORMATION SEND REBATE CHECK HERE Residential Member Name Mailing Address City State ZIP Phone Electric Cooperative/REMC Name Electric Cooperative/REMC Account Number INSTALLATION SITE INFORMATION
More informationCboe Global Markets Subscriber Agreement
Cboe Global Markets Subscriber Agreement Vendor may not modify or waive any term of this Agreement. Any attempt to modify this Agreement, except by Cboe Data Services, LLC ( CDS ) or its affiliates, is
More informationVFD and Pump Incentive Application for Business Customers
VFD and Pump Incentive Application for Business Customers 20188 A Cash Incentive Energy Efficiency Program brought to you by: Instructions for Use: For complete instructions, please refer to the Terms
More informationResidential and Small-Scale Biomass Heating Program Participant s Agreement
Residential and Small-Scale Biomass Heating Program Participant s Agreement Updated: July 18, 2016 The following Participant s Agreement (the Agreement ) is issued by the Massachusetts Clean Energy Technology
More informationALAMEDA MUNICIPAL POWER INTERCONNECTION AGREEMENT GENERAL CONDITIONS
ALAMEDA MUNICIPAL POWER INTERCONNECTION AGREEMENT GENERAL CONDITIONS For Residential, Commercial, Municipal, or Federal Agency Eligible Renewable Electrical Generation Facilities These General Conditions
More informationWEST OREGON ELECTRIC COOPERATIVE, INC. VERNONIA, OREGON POLICY 311 NET METERING SERVICE
September, 2016 WEST OREGON ELECTRIC COOPERATIVE, INC. VERNONIA, OREGON POLICY 311 NET METERING SERVICE I. Objective Net-Metering service is available, on an equal basis, to members who own and operate
More information