No. MERC/National Tariff Policy/2003/0648 April 05, Subject: Formulation of Tariff Policy under the provisions of EA, 2003.

Size: px
Start display at page:

Download "No. MERC/National Tariff Policy/2003/0648 April 05, Subject: Formulation of Tariff Policy under the provisions of EA, 2003."

Transcription

1 No. MERC/National Tariff Policy/2003/0648 April 05, 2005 Shri R.V. Shahi, Secretary, Ministry of Power, Government of India, Shram Shakti Bhavan, New Delhi Subject: Formulation of Tariff Policy under the provisions of EA, Sir, I am directed to refer to Ministry of Power s letter No. 23/2/2005-R&R dated 16 th March, 2005 seeking comments on the enclosed draft Tariff Policy. The comments of the Maharashtra Electricity Regulatory Commission on the draft Policy are enclosed. With regards, Yours faithfully, Sd/- (A.M. Khan) Secretary, MERC Encl: Cc: Cc: Cc: Cc: as above. Shri Alok Kumar, Director, (R&R Cell), Ministry of Power, Government of India, Shram Shakti Bhavan, Rafi Marg, New Delhi Chairman, MERC Member (Shri Velayutham) Director MERC's Comments on Draft Tariff Policy.doc 1

2 COMMENTS OF MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (MERC) ON DRAFT TARIFF POLICY CIRCULATED UNDER MOP LETTER DATED General Comments: 1.1 At the outset, MERC would like to emphasize that these comments are informed by the unique participatory, consultative process through which it developed the various Regulations under the Electricity Act (EA), 2003 which cover many issues relevant to the draft Tariff Policy. The Regulations were notified after extensive interaction between consumer representatives and licensees, apart from the many comments received from other stakeholders and the general public to whom the outcome of these discussions were put in the form of draft Regulations. 1.2 Under EA, 2003, the SERCs are only to be guided by the Policy, and can depart from it if the circumstances of any given issue or case so require. Thus, the Policy can only be recommendatory and guiding in nature, and not prescriptive or binding. At many places, by the use of terms such as 'would', 'should', 'shall' and in other ways, prescriptive or mandatory dispensations have been set out which are not envisaged by the EA, The draft Policy needs general revision in this respect. 1.3 MERC and other State Commissions have already put in place certain dispensations in the form of Orders or other instruments which are not inconsistent with the provisions of EA, 2003 but which may differ in some respects from the Policy provisions now being introduced. These earlier dispensations by the various Commissions are in any case subject to judicial or quasi-judicial review. Where they are not inconsistent with the Act, a new element of regulatory uncertainty is not introduced and the process already set in motion is not disturbed. The Policy should make it clear that such dispensations are protected, leaving it to the respective Commissions to decide whether any modification is called for Unlike any other State, Maharashtra has 4 different types of distribution licensees with varying backgrounds, orientation and consumer mix, and who had also been operating under different legal dispensations, viz. two private entities, a local authority, a co-operative society, and the SEB. The draft Policy is silent as to the definition and treatment of equity in the case of such different types of entities and seems to take the meaning as given, which is not the case. This omission in the draft Policy needs to be rectified. 1.5 In the context of the diversity of existing distribution licensees in Maharashtra referred to above, MERC also notes that the Policy ignores the existence, even prior to EA, 2003 of parallel licenses and second licenses in the same area, as in Mumbai. Various issues arising out of this situation, particularly since one of the licensees has only a partial network, cannot be resolved through the mechanism of MERC's Comments on Draft Tariff Policy.doc 2

3 open access to the consumer from one licensee using the facilities of the other. Moreover, network expansion to meet the universal service obligation has implications for the optimum use of resources in terms of duplication, which cannot be ignored. 2. Specific Comments: Policy Objectives 2.1 Clause 4.0- The objectives of the Policy, particularly in view of the new legal framework and the evolving power scenario in the country, would depend on the time frame that is being considered, since the emphasis required today and the objectives that may be relevant at a future date are likely to be quite different. However, the draft Policy does not give any indication of the time horizon that has been kept in view before it is expected to be revisited. MERC also notes that the stated objectives do not mention several important aspects, viz. (a) efficiency, (b) competition and (c) transparency in utility governance. General Approach to Tariff 2.2 Clause 5.1-The draft Policy states that all power needs to be procured competitively, except where tariff-based bidding may not be cost effective from the consumers' point of view (such as in cases of project expansion or where there is an identified developer) and where norm-based tariff determination will be necessary. MERC is of the view that there are many pitfalls in this approach in the present circumstances. It is also not supported by the statutory provisions, which allow various alternative methodologies also while moving towards or simulating a more competitive situation. Thus, while competition needs to be encouraged, an appropriate regulated pricing regime may be necessary, as mandated under the Act, depending on the circumstances. Further, it is not merely a question that tariff based bidding may not be cost effective from the consumers' point of view in many situations. Indeed, the interest of direct consumers is only one among several factors that have to be taken into account by the regulators under the Act. Apart from the limited experience of competitive procurement in the country and the need for much higher levels of investment in generation as well as other segments, competitive bidding in the present circumstances may well work to the future disadvantage of consumers and of society at large, for instance, by arresting the technological development and investment in renewables. Moreover, there is a contradiction in the wording of the draft inasmuch as the competitive process can be by-passed merely on account of identifying a developer, i.e. in the MoU route. MERC's Comments on Draft Tariff Policy.doc 3

4 2.3 Clause 5.2-Similarly, the statement that "multiple players will enhance the quality of service through competition" is simplistic and misleading inasmuch as, apart from the possibility of collusion, it does not take into account the mandate to utilize resources optimally, and may also lead to unhealthy duplication of infrastructure with adverse implications for longer term economic and financial costs. 2.4 Clause 5.3(a)-The draft Policy states that the rate of return on equity for generation and transmission notified by CERC shall be followed by the SERCs also. As mentioned earlier, the Act does not mandate the use of the term 'shall' in this respect. At most, the SERCs might be asked to consider such notified RoR on equity. Moreover, it appears that the draft Policy has at the back of its mind the conventional thermal and hydro projects to the exclusion of others. As pointed out at para 1.4, what constitutes 'equity' in respect of different types of entities also has to be elucidated. Further, Clause 5.3 (a) states that the RoR notified by the CERC for transmission would be adopted by the State Commissions for distribution also. The MERC is of the view that EA, 2003 clearly segregates transmission from distribution, and to automatically apply the RoR of one to the other is therefore not warranted. Moreover, on many considerations such as losses, consumer mix, power purchase, etc., distribution generally entails a greater risk than transmission, which may have to be compensated through a higher RoR for the former. The Explanation to Clause 5.3(a) clarifies the return on equity. MERC is of the view that, in the context of this Explanation, Accounting Standards should be developed for this purpose, and that the draft Policy should incorporate a commitment to do so. 2.5 Clause 5.3(c)- Clause 5.3(c) states that the depreciation rate notified by the CERC for transmission assets would also be applicable for distribution. Apart from the earlier comment that the dispensation with regard to transmission cannot be applied mutatis mutandis to distribution, this prescription does not take into account the fact that the life of assets in these two segments is likely to be vastly different and cannot, therefore, be subject to the same depreciation rate. Moreover, considering the accounting depreciation of 5 to 7% governed by the provisions of the Companies Act for different classes of assets matching the loan repayment to this duration (14 to 20 years) does not appear practicable. It may merely be stated that, for the purposes of tariff determination, the depreciation could be linked to a suitable loan repayment period. 2.6 Clause 5.3(d)- It is highly unlikely that lenders would generally agree to provide for re-fixation of interest rates every 3 years to reduce the interest rate risk on the project developer. MERC's Comments on Draft Tariff Policy.doc 4

5 2.7 Clause 5.3(e)- MERC is of the view, that in the case of RoR on foreigndenominated equity, it is necessary to move away from the concept of dollar or other foreign-denominated returns. MERC notes that in the competitive bidding guidelines, this has been considered only in rupee terms. This needs to be made clear in the Policy. 2.8 Clause 5.3(f)- The draft Policy states that "operating norms" for distribution networks would be notified by the SERCs. This provision needs to be reworded so as to make the meaning of the term 'operating norms' clear. It implies that a Distribution Code, akin to the Grid Code, is envisaged, which does not seem to be the case and is also not practicable in the present stage of development. Perhaps what is envisaged is efficiency or performance norms. In any case, this needs clarification so that there is a clear understanding of what is expected over and above the State Grid Code, Supply Code and Standards of Performance required to be specified under the Act by the State Commissions. 2.9 Clause 5.3(g)- The Policy states that appropriate capital costs should be assessed after thorough scrutiny "including public hearing". Such assessment of capital costs, both through the tariff determination process and otherwise, and pre and post investment, is done by the Commission in accordance with the requirements of these processes. Apart from the provisions in the relevant Regulations, MERC has also issued Guidelines for pre-investment, in-principle clearance of capital projects and schemes. It is not for the Policy to prescribe the procedure by which this is to be done, which is guided by the relevant Regulations, particularly relating to its Conduct of Business, which may or may not require public hearing depending on the stage and circumstances of the process. The reference to the requirement of public hearing should, therefore, be removed Clause 5.3(h)(3)-According to the draft Policy, uncontrollable costs should preferably be recovered within the financial year itself (typically on a quarterly basis). Further, such uncontrollable costs would include fuel costs, inflation, statutory levies, variations in power purchase unit costs, etc. While MERC appreciates the rationale for this provision and, indeed, had in the past mandated a pass-through formula for the SEB that took some of these factors into account, with the coming into force of the EA, 2003, no such dispensation is possible (unless there is a contrary legal interpretation of the clear terms of Section 62(4) ). Under Section 62(4), no tariff or part of tariff can ordinarily be amended more than once a year. The exception to this general rule is only in respect of any changes permitted "under the terms of any fuel surcharge formula" that is specified. Thus, regular variations in tariff have been limited by the Act to cover only variations in the fuel cost, and cannot take into account changes in other costs. Therefore, this provision of the draft Policy violates Section 62(4) Clause 5.4-This clause mentions that user charges which are to be paid by the consumers also include duties, cess levied by the State Govt. As a matter of clarification, MERC would like to point out that not all such statutory levies by MERC's Comments on Draft Tariff Policy.doc 5

6 the State Govt. have a one to one incidence on consumers. Whereas the incidence of certain levies, such as Electricity Duty, is directly on the respective consumers, there are other levies, such as Tax on Sale of Electricity, which are to the account of the licensees, and are reflected in the consumer tariff along with other components of the ARR as and when it is determined. Generation 2.12 Clause 6.2(1) and (2)- The MERC notes that what is suggested is implementation of a UI mechanism as a balancing market modality. The MERC also notes that as per Clause 5.7.1(b) of the National Electricity Policy, State Commissions are required to introduce ABT regime at the State level. However, the detailed scope, pricing methodology, exclusion of some participants and other matters have to be left to the discretion of the respective Commissions. The intra-state ABT mechanism need not necessarily mean a UI mechanism with frequency linked pricing as is applicable at the regional level. While it is necessary to develop a mechanism for power transfer exchange pricing, balancing and settlement at the State level, its emphasis and objectives and, therefore, its modalities are likely to differ significantly from the existing inter-state ABT framework. Indeed, the National Task Force had also opined "that the principles for inter-state flows may not be readily replicable for the State networks due to peculiarities and complications involved." The MERC notes that various pricing options are available for introduction of a balancing market mechanism at the State level, including (a) regulated pricing (including frequency-linked pricing mechanism specified by CERC), (b) cost based pricing, and (c) market based pricing. The mechanism suitable for a particular State would have to be determined by the concerned Commission. The primary objective of introduction of frequency linked UI price based ABT regime at the regional level has been to encourage grid discipline amongst pool participants, which is not the primary focus intra-state. Moreover, the UI mechanism is not suitable for trading as variability of prices is the key to success of any market, and the underlying assumption of the UI mechanism is to maintain the frequency at close to 50 Hz. However, with a frequency-linked balancing mechanism, it is either possible to maintain frequency or to manage trading, and not both. Further, ABT mechanism with frequency linked UI pricing was introduced at a time when most of the State participants were structured as integrated/ bundled entities. Thus, the response of State participants at the regional level has been a reflection of their system operations (scheduling and dispatch) by managing their load as well as the generating stations at their disposal. Moreover, the system is highly vulnerable to manipulation and 'gaming'. It is also important to appreciate the implications of the change in role envisaged for various participants, including the SLDC, upon un-bundling/ restructuring of the SEBs, as mandated under the Electricity Act, MERC's Comments on Draft Tariff Policy.doc 6

7 Thus, the objectives of ABT at the State level have to be defined differently in view of the changing industry structure. Further, selection of an appropriate mechanism for introduction of ABT at the State level will have to be guided by the need to have minimal impact on sector entities and retail consumers while meeting the objectives at the State level. Therefore, State Commissions will have to identify suitable balancing market mechanisms while implementing two part tariffs for generating stations. The term 'ABT at the State level' may be relevant only as a generic term used as a matter of convenience. It should be clear that the objectives and precise mechanism of such a power transfer / exchange balancing and settlement pricing mechanism would be different from the inter-state ABT, the specifics of which would be laid down by the respective State Commissions based on their own assessments Clause 6.3-The draft Policy states that the tariff for captive generation should include variable cost of generation as well as reasonable compensation for capacity charges. It may be pointed out that there is a contradiction inasmuch as such compensation for capacity charges cannot co-exist with the earlier recommendations of an ABT mechanism which already includes a fixed charge. Further, MERC notes that the draft Policy is silent on many aspects of the EA, 2003 provisions regarding captive generation, and is not aware of whether MoP proposes to address any of these outside the Tariff Policy. They include the differing interpretation of both the extent and permissibility of 3rd party sale by captive generators, the kind of Association of Persons entities that would meet the legal test for consideration as captive generation, etc. There are also issues with regard to the extent to which cross subsidy and additional surcharge should be leviable on third party purchasers in a situation of general demand supply gap. MERC has addressed some of these issues, considering the EA, 2003 provisions, in its Order dated on fossil fuel based Captive Power Plants Clause 6.4(1) and (2)-According to the draft Policy, "(1) Pursuant to provisions of section 86 (1) (e) of the Act, the Appropriate Commission may fix a minimum percentage for purchase of energy from such sources taking into account availability of such resources in the region and its impact on retail tariffs. As it will take some time before non conventional technologies can compete with conventional sources in terms of cost of electricity, the State Regulatory Commissions would be able to fix only a modest percentage initially for procurement. Such percentage for purchase of energy should be made applicable for the tariffs to be determined by the SERCs from April 1, (2) Such procurement by Distribution Companies shall be done through competitive bidding process within suppliers offering energy from nonconventional sources. In the long-term, these technologies would need to compete with other sources in terms of costs." MERC's Comments on Draft Tariff Policy.doc 7

8 MERC notes that Section 86(1)(e) of EA, 2003 requires the State Commissions to promote co-generation and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity to any person, and also specify, for purchase of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licence; The draft Policy is silent on some of the important provisions of this Clause. Although the Act recognizes the special grid connectivity requirements in respect of many such generators owing to locational and other factors as a major issue, the draft Tariff Policy (as well as the National Electricity Policy and the CEA draft Regulations on Grid Connectivity) does not address it. It is advisable to do so through broad Policy guidelines. Both before and after the coming into force of the EA, 2003, MERC has considered the matter of grid connectivity in such cases through its Orders on Wind Energy, Bagasse and other non-fossil fuel based Co-generation, etc., and these could serve as one type of approach for the purpose. The Commissions are required to promote sale of electricity from co-generation and renewables, not only to distribution licensees, but also to any other person. The Tariff Policy needs to address the issues relating to such third party sales. In particular, payment of cross-subsidy surcharge to the distribution licensee is not warranted considering the separate status accorded to generation from such sources explicitly in the Act, which enjoins its promotion. Besides, among other things, at the present stage of development of such sources of energy, application of such surcharge may put their viability at risk. This is apart from the fact that, in the widely prevalent scenario of a demand-supply gap, capacity addition and sale to third parties from such sources needs also to be looked at from the angle of avoided cost of generation capacity. The accelerated development of co-generation and renewable sources of energy intended by the statute requires a Policy dispensation which takes these factors and the legal mandate into account. MERC has already put in place a mechanism for a minimum renewables purchase obligation by distribution licensees. However, the prescription in the draft Policy that such obligation be met entirely by competitive bidding does not take into account the present stage of development of renewables, and would arrest their growth to full maturity, thereby defeating the purpose of the Act and depriving both consumers and society at large of financial and other wider benefits in the future. Several uncertainties surround renewable generation, including difficulties in accurately estimating the availability and potential of renewable resources, the still nascent nature of many technologies, inadequate experience in plant operation and consequently significant variations in operating costs, etc. At present, there are relatively few players in the market. In a competitive procurement scenario, on the one hand, it would be difficult to avoid cartel like situations and, on the other hand, it would restrict further development because only those developers who are favourably placed in cost terms would set up these facilities. This is apart from the fact that the country has very limited experience in competitive procurement even with regard to conventional generation. In the present MERC's Comments on Draft Tariff Policy.doc 8

9 situation, therefore, ostensibly competitive signals will not reflect wider social and economic benefits. Unless the tariff determination process takes these into account, the critical mass required to achieve technological maturity and economies of scale and a situation enabling prices to be determined competitively, will not be attained. Therefore, the MERC is strongly of the view that requiring competitive procurement of renewables at the present stage would arrest their development and defeat the purpose of the Act, and is not warranted. (A Note is annexed explaining why the Central Electricity Authority's time-tested normative cost-based methodology for according techno-economic clearance to power projects should be adopted for determining tariffs for renewable and nonconventional energy projects in the initial years.) Thus, the MERC believes that the Tariff Policy should clearly mandate that the State Commissions determine the tariffs for different renewable energy technologies after taking into account factors such as availability of resources, suitability of technology, cost of capital equipment and other State-specific factors such as State concessions, infrastructure facilities, etc. keeping in view the considerations set out above, to make it possible to move to a more competitive regime once maturity is achieved, apart from setting a minimum purchase obligation. This would not only provide certainty and encourage immediate investment in such plants, but would also ensure the development to maturity of different renewable technologies. Finally, the Tariff Policy should recognize the regulatory developments that have already taken place in this field in some States, and ensure that the Policy provisions do not in any way undermine the much needed regulatory clarity and long term certainty offered to the renewable energy sector by earlier Orders of State Commissions (such as in Andhra Pradesh, Maharashtra, Madhya Pradesh, Karnataka., etc.). An explicit provision to that effect should be incorporated. Transmission 2.15 Clause 7.1(5)- According to the draft Policy, in order to meet the revenue requirement of transmission developers other than CTU / STU, a competitively determined annuity may be added to the revenue pool, to be recovered through transmission tariffs. In the MERC's view, the Policy cannot bind the Commission to a competitively determined annuity rather than a cost based approach when EA, 2003 mandates that different such alternatives can be considered. The provisions of the Policy cannot negate the provisions of the Act itself. Distribution 2.16 Clause 8.1(4)- The Act requires approval to tariffs, or the fixing of a ceiling under certain circumstances. When 'rebates' were being given selectively by a licensee, MERC had held them to be unauthorized and did not allow them to be recovered in the ARR, as also now proposed in the Policy. However, such charging of tariffs lower than those approved should require a dispensation from the concerned Commission which may allow it, with certain conditions if necessary. This would avoid future problems which often result from predatory pricing and MERC's Comments on Draft Tariff Policy.doc 9

10 can impact on supply, particularly in a situation where there is more than one distributor Clause 8.1(6)-Contrary to the provisions proposed in the draft Tariff Policy, in fact the licensees cannot have the option of filing for separate revenue requirements for an area where the Commission has issued multiple licenses. The revenue requirements have to be examined in respect of the license as a whole, although the Act permits a differentiation to be made in tariffs as between different geographic areas or categories of consumers depending on the circumstances. These circumstances may include the existence of other licensees in a particular area, and the Commission can consider them appropriately while determining the tariffs Clause 8.1(8)-The provision that requisite tariff changes come into effect from the start of each financial year is not warranted by the Act, and should be removed. It is best left to the Commissions to decide if and when to take up tariff revision suo moto if they feel satisfied that it is necessary on the basis of a scrutiny of revenue requirement filings. Similarly, if tariff revision proposals are made by the licensees themselves, the matter of when the finally approved tariffs will take effect is also a matter that is entirely within the Commission's jurisdiction and cannot be dictated by the Policy, and also depends on a variety of procedural as well as substantive factors Clause 8.2.1(1)-While MERC appreciates the rationale behind not restricting power purchase costs on the basis of linkage to a normative T&D loss level, the relevant provision needs to be reworded and qualified. The word 'normative' is misleading. Instead, admissible power purchase costs should be considered keeping in view reasonably assessed targets and considering the actual circumstances Clause 8.2.1(2)-The draft Policy refers, inter alia, to consumer tariffs linked to different ATC loss levels in a MYT dispensation. The MERC is of the view that, while the intention of incentivising ATC loss reduction can be understood, it is essential to clearly differentiate between commercial losses on the one hand and technical losses on the other and to focus on them separately if results are to be achieved. The concept of ATC does not clearly distinguish between technical impediments, often a result of low investment in the sector, and commercial impediments, often a result of collusive revenue leakage. Hence, technical loss reduction under MYT framework should be treated as distinct from commercial loss reduction which is a function of better governance Clause 8.2.1(3)-The draft Policy provides that if the utility could not charge the applicable tariff, and any uncovered gap on account of unpaid but due subsidy from the State Govt. remains at the end of the year, it should be added in the ARR of the following year. This provision is not mandated by the Act, and would defeat the purpose as well as the letter of Section 65. In fact, to the extent that compensation for any subsidy against tariff required by the State Govt. is not paid MERC's Comments on Draft Tariff Policy.doc 10

11 to the licensee in advance, then to that extent the subsidy cannot be reflected in any reduction in the charges as compared to the approved tariff. There is no question of meeting the gap through the ARR and in future tariff when the law does not provide for any shortfall in the first place by operation of Section 65. Indeed, the proviso to Section 65 ensures that no such direction of the State Govt. shall be operative if the compensation to the licensee is not made in accordance with its provisions. Thus, the last sentence of this Clause should be deleted Clause & The draft Policy refers to the "average cost of supply". It may be noted that Section 61(g) requires that the tariff progressively reflects the cost of supply of electricity, and does not contain any reference to the 'average' cost of supply (in contrast, for instance, to Section 29(2)(e) of the erstwhile ERC Act, 1998) Clause The proposed provisions are self-contradictory inasmuch as they require the need for sustainable use of ground water resources to be taken into account while fixing agricultural tariffs while, at the same time, stating that, State subsidy could be considered to support farmers where the water table condition is adverse. Essentially, this would imply that over-exploitation of ground water resources should be discouraged through the tariff, but can be encouraged through subsidy. Moreover, requiring the level of ground water in different areas to be an explicit determinant of agricultural tariff is also highly impracticable given the wide variations in the ground water table even within micro regions, the differences in pumpset usage between different categories or income classes of farmers, and for several other reasons. If at all, the Policy may provide that agricultural tariff setting may take into account resource implications, such as impacts on ground water exploitation Clause The need and purpose of this provision is not clear, since it presumes that at present connection charges are not considered to be a part of the charges to be determined by the Commission. In fact, all charges under Section 46 and 47 of the Act are to be specified or determined by the Commission, including connection charges. (It may be mentioned that, in a tariff determination Order passed under the erstwhile ERC Act, the MERC had held that the SEB's Commercial Circulars, which dealt with matters impinging directly or indirectly on tariffs or charges to consumers, were all within the Commission's jurisdiction and required its approval. The SEB challenged this contention in the High Court, which upheld the Commission's view) Clause and MERC is of the view that the Policy should not prescribe a detailed formula for the computation of the cross subsidy surcharge. In general, the Commission is in agreement with the earlier recommendations made by the FOIR in this regard. With regard to cross subsidy, FOIR had held that the avoided cost approach would balance the twin objectives of safeguarding the financial viability of the licensee and the promotion of competition, and has recommended it over other methods. However, in adopting the avoided cost of generation MERC's Comments on Draft Tariff Policy.doc 11

12 approach, each Commission would have to look into certain specific and peculiar characteristic of its system. As far as additional surcharge is concerned, in the present scenario of shortage of generation, no generation capacity is likely to get stranded due to migration of load. In the case of intra-state transmission lines and distribution system, assets would continue to be used by the open access consumers by paying wheeling charges even after migration. In such cases, therefore, the question of stranded capacity does not arise. As and when a situation of stranded generation of intra-state generation or transmission assets arises, it would have to be dealt by the State Commissions on a case to case basis Clause In case of prospective/ new consumers in an area supplied by two or more licensees (i.e. in cases where he is not getting supply from any of the licensees but ab-initio obtaining power from some other entity), it may be clarified that the cross-subsidy surcharge be paid to the licensee from whom open access is being availed Clause In modification of the proposed provision, the Policy may suggest that such standby arrangements should be provided on payment of not less than the tariff for the relevant consumer category, but not more than the applicable UI charges. Thus, a band may be indicated rather than a particular rate. (A.M. Khan), Secretary, MERC Encl. Annexure to MERC Comments on Draft Tariff Policy. Mumbai. 5th April, MERC's Comments on Draft Tariff Policy.doc 12

13 ANNEXURE TO MERC COMMENTS ON DRAFT TARIFF POLICY (SEE PARA 2.14) Normative Cost Based Tariff Methodology for Tariff Determination of Renewable Energy Projects in Initial Years Rationale for * Why do the Renewable Energy Technologies need special dispensation? The main problem with renewable energy technology is while a few of them are feasible, both technically and economically, they are not so commercially. Ignoring externalities and purely comparing the financial estimates of per unit life cycle costs of electricity generation from these technologies and the conventional power plants, the two are comparable. But when it comes to estimates of these costs in commercial operations, things change completely. One of the major problems is that several renewable energy units have high capital cost but low short-run costs. Besides, financing structure of these projects complicate the matter further, as principal and interest payments are high during years when debts are being repaid generally 10 years. In a dynamic situation when technology is still evolving commercially, this becomes a significant barrier, even more so when promotional policies change without providing protection to earlier investments. Global Approaches to Supporting Renewable Energy Technologies A usual approach that most governments around the world - with renewable energy programmes - have taken in dealing with these issues is to forcibly create markets for these technologies, by introducing specific laws and regulations favouring their promotion. These technologies have been backed-up with preferential tariffs, subsidies and various other fiscal incentives, in the last 30 years. In Europe, feed-in tariffs have been used very effectively to get renewable energy technologies off the ground. Several governments in Europe have made it obligatory for power utilities to connect local renewable power generating units to the grid, and pay them the feed-in tariffs. These tariffs have been fixed at different levels for different technologies. By securing income and the reducing risk for developers, various governments have successfully boosted their commercial deployment. For example, Germany s relatively high feed-in tariffs have led to its emergence as the world s largest wind turbine market. With a view to spurring investments in renewable energy development - immediately after the 1974 oil crisis - the US government provided investment tax credits and research and development funds to those engaged in renewable energy technology. However, the enactment of the Public Utility Regulatory Policies Act (PURPA) in 1978 was the single most important factor in the development of a commercial renewable energy market in that country. PURPA created a qualifying facility status for these units and co-generation technologies, mandating utilities to purchase power from them at their full-avoided cost. It also encouraged utilities to enter into long-term contracts running into years, with them. As a result, the rates paid to renewable energy units in the US were unusually high in the 1980s. * Based on the book titled ELECTRICITY REFORMS AND GREEN POWER DEVELOPMENT by Dr. Pramod Deo & Shri Shrikant Modak, published by WISE, Pune. MERC's Comments on Draft Tariff Policy.doc 13

14 In contrast, in Britain s Non Fossil Fuel Obligation (NFFO), the potential renewable project developers - after bidding successfully under each renewable energy technology category - have been awarded tariffs as stated in their bids, for a pre-determined period (15 years). Unlike the fixed feed-in tariff approach of other countries, this approach has proved advantageous, spurring cost and tariff reductions. For example, the price of wind electricity dropped in the UK from 8-9 pence to 4 pence in six years in the 1990s. It is, however, not clear whether this drop was due to developers confining their new investments only to clearly advantageous wind-sites or to deployment of more advanced technology, or both. In recent years, the electricity industry has increasingly come under regulatory and economic pressure to become more competitive. In fact, in the mid 1990s, the Federal Energy Regulatory Commission (FERC) ruled against some states in the US for using rate setting mechanisms to set renewable energy rates above the avoided costs. Competitive pressures in the power sector have since increased in that country and elsewhere, seriously affecting the future of renewable energy technologies in several ways. To begin with, as utilities are forced to compete more heavily on price in the short-term, the flexibility to experiment with renewable energy technologies would diminish. In such situations, the premium for short-run cost minimization would increase substantially, squeezing out technologies that are not cost-effective over a short period. Utilities that might otherwise have invested in technologies that are cost-effective in the long run, but carry high short-run costs, would be less likely to do so once there is competitive pressure. Nor would they want to roll out expensive generation together with the less costly, if plant based merit order dispatch is in practice. In such a scenario, they would be more inclined to consider each power source independently and determine whether it is competitive. Similarly, they would have little incentive to spend money on the development of technologies that offer common benefits to all generators. Further, increased competition could potentially have the effect of diminishing the importance of beneficial attributes (it s non-polluting and risk reducing aspects) of renewable energy technologies. For this reason, in countries that promote renewable energy technologies, distributed generation is often relatively unencumbered by the rules of central systems (scheduling, pooling, dispatch). In the UK, embedded power stations, including renewable units, with total registered capacity of up to 50 MW do not have to trade through the pool and are not dispatched through the system operator (grid). However, they have to comply with the distribution code, though not the grid code. As far as excess supply is concerned, they have to sell this to authorized suppliers or the end-users. In NFFOs case, the public electricity suppliers are obliged to buy all power output from renewable units and, in turn, are reimbursed the price difference between the market price and NFFO tariffs. In fact, Sweden, Germany and Denmark have special regulations for renewable energy generation. Under the Swedish system, concession holders are forced to buy all power from small-scale generation at tariff rates representing their avoided costs. MERC's Comments on Draft Tariff Policy.doc 14

15 Regulatory Commissions Role One issue that is unlikely to go down well with economists is the fact that MERC and APERC banked on normative cost based methodology in determining tariffs for nonconventional energy projects. Although the Central Electricity Authority has been using this method for many years for according techno-economic clearance to power projects, it has not been without criticism. The chief criticism against this approach has been that the average costs provide misleading signals to the decision makers. Since regulatory commissions, in the case of market failure or in the absence of market, must take over and perform the role as market would, adopting rules that do not conform to the operating principles of competitive markets goes against the basic function for which the regulatory commissions are set-up. But how serious is the matter as far as the renewable technologies are concerned? The answer perhaps is, not very! The fact that EA 2003, Section 86 (1) (e) spells out that the regulatory commissions must fix a certain percentage for renewable energy in the total consumption of electricity in the area of distribution licensees clearly implies that these projects are to be spared the rigours of market competition. Working backwards, it means all generation planning for supply of electricity to an area must begin by reserving a specific percentage of electricity supply from the renewable sources. Which in turn implies, to that extent the cost concepts such as the opportunity costs, avoided costs or the marginal costs need not apply to these energy sources, as they are put outside the domain of economic selection. However, it does not mean no-holds bar in pricing of power from renewable energy sources. That is where the regulatory function of SERCs acquires significance; especially, since those having information required by these bodies for setting tariffs, as MERC s as well as the experience world over indicates, are unlikely to divulge it to the fullest extent necessary. Which means SERCs would have to base their cost estimates on information other than what they can get from these sources as well as use their own judgment on the veracity of the available information. The ultimate aim of regulatory exercises for renewable energy based power technologies must be to maintain the balance between the need to encourage their growth while maintaining enough pressures on promoters and manufacturers to perform efficiently. Lastly, even when projects based on renewable technologies are commercially viable, it is not necessary that the power sector utilities, whether public or private, would queue up for setting up these units. The investment required is too small for the scale of operations to which these utilities are used to and it may not be worth the efforts as there are ample opportunities available to them for investments in large generating stations. That means the governments would have to adopt more proactive role in promoting these technologies and, in that context, SERCs too would have larger role to play in their advisory capacity to the governments. Finally, were renewable technologies competitive and so were power markets, some of the issues such as banking would not remain as issues, as spot markets would take care of undelivered energy and there would be no need for banking. Of course, these are the matters for the future. For the moment however, regulatory commissions will have to remain proactively (though not over zealously) engaged in the promotion of renewable energy sources. MERC's Comments on Draft Tariff Policy.doc 15

TARIFF POLICY. Ministry of Power Government of India Website :

TARIFF POLICY. Ministry of Power Government of India Website : TARIFF POLICY Ministry of Power Government of India Website : www.powermin.gov.in TARIFF POLICY Ministry of Power Government of India Website : www.powermin.gov.in CONTENTS Page No. 1.0 Introduction 1

More information

Bhopal: Dated 5 th May 2006

Bhopal: Dated 5 th May 2006 Bhopal: Dated 5 th May 2006 No. 1192/MPERC/2006. In exercise of the powers conferred by section 181 (g) read with section 32(3) of the Electricity Act, 2003 enacted by the parliament, the Madhya Pradesh

More information

Distribution Tariff Determination and Rationalization

Distribution Tariff Determination and Rationalization Department of Industrial and Management Engineering Indian Institute of Technology Kanpur 3 rd Capacity Building Programme for Officers of Electricity Regulatory Commissions 23 28 August, 2010 Forum of

More information

CASE No. 28 of Dr Pramod Deo, Chairman Shri A. Velayutham, Member ORDER

CASE No. 28 of Dr Pramod Deo, Chairman Shri A. Velayutham, Member ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005. Tel. 22163964 / 22163965, Fax No. 22163976 E-mail mercindia@mercindia.com

More information

CASE No. 48 of In the matter of Appointment of Committee for study of subsidy, and related matters.

CASE No. 48 of In the matter of Appointment of Committee for study of subsidy, and related matters. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.com

More information

Electricity ( Amendment) Bill 2014

Electricity ( Amendment) Bill 2014 Electricity ( Amendment) Bill 2014 Observations & Comments on Draft Amendments 29 February 2016 Former Technical Member APTEL Former Chairman UERC Agenda for discussion Distribution Separation of Content

More information

M.P. Electricity Regulatory Commission Bhopal

M.P. Electricity Regulatory Commission Bhopal SMP-20/2010 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Wind Electric Generators 1. LEGISLATIVE PROVISIONS 1.1 Section 86(1) (e) of the Electricity Act 2003

More information

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY No. 419 9 Shrawan, 1932(s) Ranchi, Saturday 31th July, 2010 JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION, RANCHI (RENEWABLE PURCHASE OBLIGATION

More information

Chapter 4. Tariff Policy. (Amendments made in the Tariff Policy vide resolution and in corporated)

Chapter 4. Tariff Policy. (Amendments made in the Tariff Policy vide resolution and in corporated) Chapter 4 Tariff Policy (Amendments made in the Tariff Policy vide resolution 31.3.2008 and 20.1.2011 in corporated) 271 272 The Gazette of India EXTRAORDINARY PART I - Section 1 PUBLISHED BY AUTHORITY

More information

CASE No. 150 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Vidarbha Industries Power Limited ORDER

CASE No. 150 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Vidarbha Industries Power Limited ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

PRELIMINARY. (2) These Regulations shall come into force from the date of their publication in the Official Gazette.

PRELIMINARY. (2) These Regulations shall come into force from the date of their publication in the Official Gazette. No. JERC-10/2009:- In exercise of powers conferred on it under Section 61 read with Section 181 of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in this behalf, the Joint State

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION, ITS COMPLIANCE AND IMPLEMENTATION OF RENEWABLE ENERGY CERTIFICATE FRAMEWORK)

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010 UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION No. UPERC/Secy/Regulation/10-787 Lucknow : Dated, 17 th August, 2010 In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity

More information

Karnataka Power Sector Reforms -Overview of Restructuring and Lessons Learnt-

Karnataka Power Sector Reforms -Overview of Restructuring and Lessons Learnt- Karnataka Power Sector Reforms -Overview of Restructuring and Lessons Learnt- Resource persons: Tetra Tech and Dhiya Consulting Pvt. Ltd., August 23, 2010 Bengaluru Contents Reform background Reform drivers

More information

Chhattisgarh State Electricity Regulatory Commission

Chhattisgarh State Electricity Regulatory Commission Øekad 62] jk;iqj]] 'kqøokj] fnukad 4 ekpz 2011 & QkYxqu 13] 'kd 1932 Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur Raipur, Dated March 04, 2011 No. 36/CSERC/2011

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS,

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS, Approach Paper for MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS, 2014 Issued By: Maharashtra Electricity Regulatory

More information

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website: www.mercindia.org.in;

More information

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016 1 BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016 IN THE MATTER OF: Petition under Section 86 read with Section 181 of the Electricity Act, 2003 for amendment of

More information

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Case No. 30 of In the matter of Petition filed by MSETCL for approval of SLDC Budget for FY and FY

Case No. 30 of In the matter of Petition filed by MSETCL for approval of SLDC Budget for FY and FY Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th floor, Cuffe Parade, Mumbai 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission Notification no. UPERC / Secy / CNCE Regulation, 2009/ 696 Dated: 22.3.2010 In exercise of powers conferred under section 181 read with section 9, 61, 86

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017 ELECTRICITY ACT, 2003 No. MERC/Legal/2017/1771 - In exercise of

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : /

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : / CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi 110 001 : 011-23353503/23752958 Public Notice No. : L-1/94/CERC/2011 Dated: 26 th June, 2015

More information

Shri P. Subrahmanyam, Chairman Shri Jayant Deo, Member Dr Pramod Deo, Member ORDER

Shri P. Subrahmanyam, Chairman Shri Jayant Deo, Member Dr Pramod Deo, Member ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005. Tel. 22163964 / 22163965, Fax No. 22163976 E-mail mercindia@mercindia.com

More information

Overview of the framework

Overview of the framework Overview of the framework Need for a framework The highways sector in India is witnessing a significant interest from both domestic as well as foreign investors following the policy initiatives taken by

More information

Captive Power Generation In India

Captive Power Generation In India Captive Power Generation In India Structure, Requirement, Important Judicial Decisions and Proposed Draft Amendment Matrugupta Mishra & Hemant Singh, Partners Praxis Counsel Advocates and Solicitors New

More information

Case No. 52 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Mahati Hydro Power Projects Pvt. Ltd.

Case No. 52 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Mahati Hydro Power Projects Pvt. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. (Date of Order: )

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. (Date of Order: ) HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA IN THE MATTER OF:- (Date of Order: 25.07.2018) Petition No.: 26/2018(Suo-Moto) CORAM Sh. S.K.B.S. Negi Chairman Sh. Bhanu Pratap Singh Member

More information

SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal

SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Municipal Solid Waste based power generating plants in Madhya Pradesh June 2016 1. LEGISLATIVE PROVISIONS

More information

BRIEF ANALYSIS ON NEW OPEN ACCESS REGULATIONS IN THE STATE OF MAHARASHTRA

BRIEF ANALYSIS ON NEW OPEN ACCESS REGULATIONS IN THE STATE OF MAHARASHTRA BRIEF ANALYSIS ON NEW OPEN ACCESS REGULATIONS IN THE STATE OF MAHARASHTRA ETERNITY LEGAL 1207, Dalamal Tower, Free Press Journal Road, Nariman Point, Mumbai 400021 Tel: +91 22 6747 9001 Email: legalupdates@eternitylegal.com

More information

New and Renewable Energy Department Vallabh Bhavan, Bhopal

New and Renewable Energy Department Vallabh Bhavan, Bhopal New and Renewable Energy Department Vallabh Bhavan, Bhopal English Translation of Policy for implementation of Small Hydel-Power based Electricity Projects in Madhya Pradesh, 2011 (As Amended on 15th February

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION. Notification No. 13 of 2005

GUJARAT ELECTRICITY REGULATORY COMMISSION. Notification No. 13 of 2005 GUJARAT ELECTRICITY REGULATORY COMMISSION OPEN ACCESS REGULATION Notification No. 13 of 2005 In exercise of the powers conferred on it by Section 181 read with Sections 39(2)(d), 40(c), 42 (2)(3)(4), 86(1)(c)

More information

Notified on : 22 January 2010 Bhopal, Dated: 9 th December, 2009

Notified on : 22 January 2010 Bhopal, Dated: 9 th December, 2009 Notified on : 22 January 2010 Bhopal, Dated: 9 th December, 2009 No. 2734/MPERC/2009. In exercise of powers conferred under Section 181(2) (zd) read with Section 45 and 61 of the Electricity Act, 2003

More information

Overview of the framework

Overview of the framework Overview of the framework Need for a framework Economic growth and trade expansion in recent years have enhanced the relevance of port sector as a critical element in globalisation of the Indian economy.

More information

GOVERNMENT OF KERALA

GOVERNMENT OF KERALA 183 GOVERNMENT OF KERALA Kerala Small Hydro Power Policy 2012 1. Order G.O.(P) 25/2012/PD Dated: Thiruvananthapuram, 03.10.2012 2. Title Kerala Small Hydro Power Policy 2012 3. Objective To increase the

More information

Electricity Act 2003 Amendments. Presentation to Carriage & Content Separation Proposals and Issues. Anish De

Electricity Act 2003 Amendments. Presentation to Carriage & Content Separation Proposals and Issues. Anish De Electricity Act 2003 Amendments Presentation to Carriage & Content Separation Proposals and Issues Anish De IIT Kanpur, April 20, 2014 Key Issues 1. Is carriage and content separation practicable in the

More information

No. 14/1/2016-Trans Government of India Ministry of Power. Office Memorandum

No. 14/1/2016-Trans Government of India Ministry of Power. Office Memorandum No. 14/1/2016-Trans Government of India Ministry of Power Shram Shakti Bhawan, Rafi Marg, New Delhi, dated s" December, 2016 Office Memorandum Subject: Guidelines on Cross Border Trade of Electricity At

More information

2 FSA PROPOSAL,S ARE VAGUE WITH INCONSISTENT INFORMATION AND NO EXPLANATION

2 FSA PROPOSAL,S ARE VAGUE WITH INCONSISTENT INFORMATION AND NO EXPLANATION Sri R.K.Agarwal, Hon. Chairman, 30 Andhra Pradesh Spinning Mills Association, and 99 others Regd. No. 39201, 1 st Floor, 105 Surya Towers, Sardar Patel Road, Secunderabad 500 003, Sl.No Objection/Suggestion

More information

Scanned by CamScanner

Scanned by CamScanner Scanned by CamScanner Maharashtra Electricity Regulatory Commission intends to enact MERC (Forecasting, Scheduling and Deviation. Accordingly, the Hon ble Commission has circulated the draft of the proposedmerc

More information

Comments and Suggestions for the Draft Amendment in the provisions relating to Captive Generating Plant in Electricity Rules, 2005

Comments and Suggestions for the Draft Amendment in the provisions relating to Captive Generating Plant in Electricity Rules, 2005 Comments and Suggestions for the Draft Amendment in the provisions relating to Captive Generating Plant in Electricity Rules, 2005 by Prayas (Energy Group), 23 rd June 2018 With the proliferation of captive

More information

Case No. 125 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

Case No. 125 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

MYPD Methodology Eskom Response to Consultation Paper

MYPD Methodology Eskom Response to Consultation Paper MYPD Methodology Eskom Response to Consultation Paper 2 June 2016 Introduction Eskom is pleased to provide comments Eskom has provided detailed responses to the consultation paper on the review of the

More information

Power Purchase Obligation (Compliance by purchase of Renewable Energy/Renewable Energy Certificates) Regulations, 2012 (Regulation No. 1 of 2012).

Power Purchase Obligation (Compliance by purchase of Renewable Energy/Renewable Energy Certificates) Regulations, 2012 (Regulation No. 1 of 2012). ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION RENEWABLE POWER PURCHASE OBLIGATION (COMPLIANCE BY PURCHASE OF RENEWABLE ENERGY/RENEWABLE ENERGY CERTIFICATES) REGULATIONS, 2012 Regulation No. 1 of 2012

More information

Overview of the framework

Overview of the framework Overview of the framework To meet the infrastructure deficit, the Twelfth Five Year Plan envisages a renewed thrust on investment in infrastructure, particularly in the power sector. The additional thermal

More information

Model Concession Agreement for Highways: An Overview

Model Concession Agreement for Highways: An Overview Model Concession Agreement for Highways: An Overview - Gajendra Haldea The highways sector in India is witnessing significant interest from both domestic as well as foreign investors following the policy

More information

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA. NOTIFICATION Shimla, the 22 nd November, 2018

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA. NOTIFICATION Shimla, the 22 nd November, 2018 THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA NOTIFICATION Shimla, the 22 nd November, 2018 No. HPERC-F(1)-1/2018- Whereas section 61 of the Electricity Act, 2003 (36 of 2003), provides

More information

Case No. 56 of In the matter of

Case No. 56 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964/ 65/ 69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

M.P. Electricity Regulatory Commission Bhopal

M.P. Electricity Regulatory Commission Bhopal SMP-74/2015 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Wind Electric Generators 1. LEGISLATIVE PROVISIONS Section 86(1) (e) of the Electricity Act 2003 mandates

More information

Power Sector Reform India The Long Road Ahead

Power Sector Reform India The Long Road Ahead Power Sector Reform India The Long Road Ahead Rahul Tongia Department of Engineering & Public Policy/ School of Computer Science University February 19, 2003 2 Outline Overview of the Indian power sector

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 E-mail: mercindia@merc.gov.in Website:

More information

Case No. 27 of In the matter of

Case No. 27 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Meghalaya State Electricity Regulatory Commission

Meghalaya State Electricity Regulatory Commission Meghalaya State Electricity Regulatory Commission SHILLONG Notification Dated: 12 th March, 2015 No.MSERC/RPO/2015/02: In exercise of power conferred under section 61, 66, 86(1)(e) and 181 of the Electricity

More information

non-rate-regulated entities; and rate-regulated entities that do not recognise such balances?

non-rate-regulated entities; and rate-regulated entities that do not recognise such balances? Questions for respondents Question 1 What information about the entity s rate-regulated activities and the rate-regulatory environment do you think preparers of financial statements need to include in

More information

Ventus 2 VCT plc. Strategy Note Executive Summary

Ventus 2 VCT plc. Strategy Note Executive Summary 1 Executive Summary This note summarises the outcome of a strategy review undertaken by the Board of Ventus 2 VCT plc (the Company ) over the past year during the period when the last of the Company s

More information

ED/2013/7 Exposure Draft: Insurance Contracts

ED/2013/7 Exposure Draft: Insurance Contracts Ian Laughlin Deputy Chairman 31 October 2013 Mr. Hans Hoogervorst Chairman IFRS Foundation 30 Cannon Street London EC4M 6XH United Kingdom Dear Mr. Hoogervorst, ED/2013/7 Exposure Draft: Insurance Contracts

More information

GUIDELINES FOR ASPIRING NEW GENERATION APPLICANTS

GUIDELINES FOR ASPIRING NEW GENERATION APPLICANTS Tel: +264 61 374300 8 Bismarck Street P O Box 2923, Windhoek Fax: +264 61 374305/4 Windhoek Namibia Website: www.ecb.org.na GUIDELINES FOR ASPIRING NEW GENERATION APPLICANTS Version 4, 28 September 2007

More information

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No.

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No. 2 EXECUTIVE SUMMARY The Tata Power Company Limited ( Tata Power ) is a company established in 1919. On April 1, 2000, The Tata Hydro-Electric Power Supply Company Limited (established in 1910) and The

More information

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT Energy Department Government of Bihar 2012 ( 1 ) Table of Content 1. Objective 2. Title and Enforcement 3. Scope and Coverage 4. Nodal Agency 5. Classification

More information

CHAPTER I: PRELIMINARY Short title, commencement and interpretation

CHAPTER I: PRELIMINARY Short title, commencement and interpretation Notification dated 20.2.2009 Bhopal: dated 31 st January, 2009 No. 254-MPERC-2009. In exercise of the powers conferred by Section 181 read with Subsection (b) of Section 86 of the Electricity Act 2003

More information

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, "Metro Plaza", Bittan Market, Bhopal - 462 016 Petition No.55 of 2012 PRESENT: Rakesh Sahni, Chairman IN THE MATTER OF: C.S. Sharma, Member

More information

Case No.17 (3), 3,4 & 5 of 2002

Case No.17 (3), 3,4 & 5 of 2002 BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai-400 005 Tel. (022) 22163964/65 Fax 22163976 Email: mercindia@mercindia.com Website:

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM. PRESENT: Sri.T.M. Manoharan, Chairman

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM. PRESENT: Sri.T.M. Manoharan, Chairman KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Sri.T.M. Manoharan, Chairman Petition No. 1893/DD (T)/Jhabua/2016/KSERC in OP No. 13/2015 In the matter of Procurement of 865

More information

Support mechanisms for RES-e

Support mechanisms for RES-e Support mechanisms for RES-e Regional ECREEE Training Workshop on National Renewable Energy Policy and Incentive Schemes Praia, 9-11 April 2012 Sofía Martínez International Relations Department Table of

More information

BIHAR ELECTRICITY REGULATORY COMMISSION

BIHAR ELECTRICITY REGULATORY COMMISSION BIHAR ELECTRICITY REGULATORY COMMISSION Bihar Electricity Regulatory Commission (Renewable Purchase Obligation, its Compliance and REC Framework Implementation) Regulations, 2010. NOTIFICATION The 16 th

More information

KINGDOM OF CAMBODIA NATION RELIGION KING ELECTRICITY AUTHORITY OF CAMBODIA REGULATIONS

KINGDOM OF CAMBODIA NATION RELIGION KING ELECTRICITY AUTHORITY OF CAMBODIA REGULATIONS KINGDOM OF CAMBODIA NATION RELIGION KING ELECTRICITY AUTHORITY OF CAMBODIA REGULATIONS ON GENERAL PRINCIPLES FOR REGULATING ELECTRICITY TARIFFS IN THE KINGDOM OF CAMBODIA Under Electricity Law of The Kingdom

More information

Provisional translation

Provisional translation Provisional translation Principles for Responsible Institutional Investors Japan s Stewardship Code Summary of Comments on the English Translation of the Draft of the Revised Version of the Code and Our

More information

Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018

Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018 Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018 S No. Existing provision/ Draft amended proposed Modified proposed

More information

GOVERNMENT OF MADHYA PRADESH

GOVERNMENT OF MADHYA PRADESH 206 Compendium of State Government Policies on Renewable Energy Sector in India GOVERNMENT OF MADHYA PRADESH Wind Power Project Policy of Madhya Pradesh, 2012 (As Amended on 21 st February 2013) 1. Order

More information

F. No. 53/15/2016 -WE Ministry of New & Renewable Energy. Evaluation of Generation Based Incentives Scheme for Wind Power Projects

F. No. 53/15/2016 -WE Ministry of New & Renewable Energy. Evaluation of Generation Based Incentives Scheme for Wind Power Projects F. No. 53/15/2016 -WE Ministry of New & Renewable Energy Evaluation of Generation Based Incentives Scheme for Wind Power Projects The GBI scheme was initially introduced in 11th Plan on 17.12.2009 with

More information

Article 2. National Treatment and Quantitative Restrictions

Article 2. National Treatment and Quantitative Restrictions 1 ARTICLE 2 AND THE ILLUSTRATIVE LIST... 1 1.1 Text of Article 2 and the Illustrative List... 1 1.2 Article 2.1... 2 1.2.1 Cumulative application of Article 2 of the TRIMs Agreement, Article III of the

More information

PRINCIPLES FOR THE SUPERVISION OF OPERATORS OF COLLECTIVE INVESTMENT SCHEMES

PRINCIPLES FOR THE SUPERVISION OF OPERATORS OF COLLECTIVE INVESTMENT SCHEMES PRINCIPLES FOR THE SUPERVISION OF OPERATORS OF COLLECTIVE INVESTMENT SCHEMES Technical Committee of the International Organization of Securities Commissions September 1997 1 I. INTRODUCTION The collective

More information

(Website: ORDER. Case No. 55 and 56 of 2003

(Website:  ORDER. Case No. 55 and 56 of 2003 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005 (Tel: 22163964/65/69 Fax: 22163976) (Email: mercindia@mercindia.com) (Website: www.mercindia.com)

More information

Rajasthan Electricity Regulatory Commission

Rajasthan Electricity Regulatory Commission Rajasthan Electricity Regulatory Commission Vidyut Viniyamak Bhawan, Near State Motor Garage, Sahkar Marg, JAIPUR -302001 Phone: EPBX 0141-2741299, Fax: 0141-2741018 Website: www.rerc.rajasthan.gov.in

More information

Access Arrangement Information. Standard Access Contract Demonstration of Code Compliance

Access Arrangement Information. Standard Access Contract Demonstration of Code Compliance Access Arrangement Information Standard Access Contract Demonstration of Code Compliance ELECTRICITY NETWORKS CORPORATION ( WESTERN POWER ) ABN 18 540 492 861 {Outline: This document is included in Western

More information

CASE No. 107 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana

CASE No. 107 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra Veej Grahak Sanghatana Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 and all powers enabling it in this behalf, the Uttar Pradesh Electricity

More information

M.P. Electricity Regulatory Commission Bhopal

M.P. Electricity Regulatory Commission Bhopal SMP-12/2013 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Wind Electric Generators 1. LEGISLATIVE PROVISIONS 1.1 Section 86(1) (e) of the Electricity Act 2003

More information

Vidarbha Industries Power Limited - Transmission

Vidarbha Industries Power Limited - Transmission Vidarbha Industries Power Limited - Transmission Revised Petition towards: Approval of Capital Cost and Determination of Aggregate Revenue Requirement ( ARR ) for the period FY 14-15 to FY 15-16 Filed

More information

Our commentary focuses on five main issues. Supplementary comments relating to specific paragraphs or issues are provided in the appendix.

Our commentary focuses on five main issues. Supplementary comments relating to specific paragraphs or issues are provided in the appendix. Comments on the Revised Discussion Draft on Transfer Pricing Aspects of Intangibles by the Confederation of Netherlands Industry and Employers (VNO-NCW) We are pleased to see the significant progress which

More information

Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL.

Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL. Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL. GUVNL has floated two tenders for procurement of power from

More information

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR ************

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR ************ ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR - 751 012 ************ Present : Shri B. K. Das, Chairperson Shri K.C. Badu, Member Shri B.K. Misra, Member Case No.

More information

Perspective on Financing Wind Energy Projects. June 16, 2016

Perspective on Financing Wind Energy Projects. June 16, 2016 Perspective on Financing Wind Energy Projects June 16, 2016 Agenda 2 1 Risk Matrix 3 Context Setting Way Forward KEY SEGMENTS IN THIS PRESENTATION 3 Indian Energy Sector Landscape Bank Lending Sector wise

More information

Following Industry Consultation

Following Industry Consultation Report to Authority Proposed Revisions to the Balancing Principles Statement, Balancing Services Adjustment Data Methodology Statement, Procurement Guidelines, System Management Action Flagging Methodology

More information

USAID-Funded Nepal Hydropower Development Project (NHDP)

USAID-Funded Nepal Hydropower Development Project (NHDP) USAID-Funded Nepal Hydropower Development Project (NHDP) Electricity Regulatory Commission and the Emerging Legal, Policy, and Regulatory Framework for Hydropower in Nepal Arun Anandan Regulatory Advisor

More information

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION No. / /2017/MPERC.- In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other powers enabling

More information

Pension Schemes Bill Delegated Powers

Pension Schemes Bill Delegated Powers Pension Schemes Bill Delegated Powers Memorandum from DWP to the Delegated Powers and Regulatory Reform Committee November 2014 1 Introduction The Pension Schemes Bill was introduced in the House of Commons

More information

GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010

GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010 GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010 No. 1/17/09-EB(PR)/450.- Whereas the State of Punjab is presently facing acute power shortages. And therefore,

More information

KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2017 HESCOM ANNUAL PERFORMANCE REVIEW FOR FY16

KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2017 HESCOM ANNUAL PERFORMANCE REVIEW FOR FY16 KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2017 OF HESCOM ANNUAL PERFORMANCE REVIEW FOR FY16 & REVISION OF ANNUAL REVENUE REQUIREMENT FOR FY18 & REVISION OF RETAIL SUPPLY TARIFF FOR FY18

More information

Before the Karnataka Electricity Regulatory Commission, Bangalore. In the matter of Determination of Tariff in respect of Renewable Sources of Energy

Before the Karnataka Electricity Regulatory Commission, Bangalore. In the matter of Determination of Tariff in respect of Renewable Sources of Energy Before the Karnataka Electricity Regulatory Commission, Bangalore Dated 18 th January 2005 Present: 1. K.P. Pandey, Chairman 2. Sri H.S.Subramanya, Member 3. Sri S.D.Ukkali, Member In the matter of Determination

More information

Consolidated FDI Policy (The article was published in the journal of Bombay Chartered Accountants Society in June 2010)

Consolidated FDI Policy (The article was published in the journal of Bombay Chartered Accountants Society in June 2010) Consolidated FDI Policy 2010 Bombay Chartered Accountants Society Naresh Ajwani (The article was published in the journal of Bombay Chartered Accountants Society in June 2010) 1. Ministry of Commerce and

More information

1.1 These regulations shall extend to whole of the State of Punjab.

1.1 These regulations shall extend to whole of the State of Punjab. THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION The, 2018 No.PSERC/Secy/Regu. - In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other

More information

Scheme Financing Infrastructure Projects through the India Infrastructure Finance Company Limited (IIFCL)

Scheme Financing Infrastructure Projects through the India Infrastructure Finance Company Limited (IIFCL) Government of India Scheme Financing Infrastructure Projects through the India Infrastructure Finance Company Limited (IIFCL) Published by The Secretariat for the Committee on Infrastructure Planning Commission,

More information

Uttar Pradesh Electricity Regulatory Commission 2 nd Floor, Kisan Mandi Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow

Uttar Pradesh Electricity Regulatory Commission 2 nd Floor, Kisan Mandi Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow Uttar Pradesh Electricity Regulatory Commission 2 nd Floor, Kisan Mandi Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow 226 010 No. UPERC/Secy/Regulation/06-2102 Lucknow: 6 th October, 2006 In exercise of

More information

Georgian National Electricity Regulatory Commission

Georgian National Electricity Regulatory Commission Georgian National Electricity Regulatory Commission Resolution # 3 1 July, 1998 Tbilisi On Approval of the Electricity Tariff Methodology, Setting Rules and Procedures. On the recent stage of the reform

More information

Leading Renewable Energy Generation Company

Leading Renewable Energy Generation Company Leading Renewable Energy Generation Company Disclaimer Certain statements in this presentation concerning our future growth prospects are forward looking statements, which involve a number of risks and

More information

Case No. 1 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member

Case No. 1 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Competitive Bidding Guidelines for procurement of Electricity

Competitive Bidding Guidelines for procurement of Electricity Chapter 8 Competitive Bidding Guidelines for procurement of Electricity (Contains amendments dated 30.3.2006, 18.8.2006, 27.9.2007, 27.3.2009 and 21.7.2010) 345 346 Guidelines for Determination of Tariff

More information

User Commitment for Generator Focused Anticipatory Investment (GFAI)

User Commitment for Generator Focused Anticipatory Investment (GFAI) All Industry Parties Patrick Hynes Electricity Charging & Capacity Development Manager patrick.hynes@nationalgrid.com Direct tel.: 01926 656319 22 nd May 2015 Dear Colleagues, User Commitment for Generator

More information

Case No. 56 of In the matter of Compliance of directives issued to MSEDCL under Order dated May 17, 2007 passed in Case No. 82 of 2006.

Case No. 56 of In the matter of Compliance of directives issued to MSEDCL under Order dated May 17, 2007 passed in Case No. 82 of 2006. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964-65-69 Fax 22163976 Email: mercindia@mercindia.org.in Website:

More information

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of

More information