1 NATURAL RESOURCE DAMAGES FUNDAMENTALS Joan P. Snyder Stoel Rives, LLP Presented to Oregon Association of Environmental Professionals October 9, 2003
2 Natural Resource Damages Under federal Superfund injury to, destruction of, or loss of natural resources, including the reasonable costs of assessing such injury, destruction or loss resulting from a release of a hazardous substance. 42 USC 9607(a)(4)(C). Under Oregon (mini-superfund) law damages for injury to or destruction of any [public] natural resources caused by a release. ORS (1). Oregon has separate provision for damages from injury, death, contamination or destruction of fish or wildlife resulting from pollution (e.g., fish kills). ORS 468B.060(1).
3 Natural Resource Damages Under federal Oil Pollution Act (OPA, 33 USC 2702(b)(2)) Damages to trustees for injury to, destruction of, loss of or loss of use of, natural resources, including the reasonable costs of assessing the damage from a discharge of oil. Damages to an affected claimant for injury to, or economic losses resulting from, destruction of real or personal property; for loss of subsistence use of natural resources; and for loss of profits or earning capacity. Damages to state or federal governments for loss of revenues from taxes or royalties, damages, and damages for the state s net costs of providing increased public services caused by the oil discharge.
4 Examples Exxon Valdez/New Carissa oil Commencement Bay/Portland Harbor varied, historic contaminants Coeur D Alene Basin mine tailings
5 Use of Damages Must be used only to restore, replace of acquire the equivalent of the damaged resource. 42 USC 9607(f)(1). Purpose of restorative work is to return the resources to their baseline condition, which is the physical, chemical, or biological properties that the injured resources would have exhibited or the services that would have been provided absent the release of hazardous substances. 43 CFR 11.82(b)(1)(I).
6 Important Qualifiers: Under Superfund, Oregon mini-superfund and OPA applies only to the damages caused by or resulting from a release. Under CERCLA: There shall be no recovery where such damages and the release of a hazardous substance from which such damages resulted have occurred wholly before December 11, USC 9607(f)(a). Federal claims must be brought by the federal, state and tribal trustees for the resources at issue, and there is no double recovery.
7 How Do Natural Resource Damages Relate to the Environmental Risk Remedied by a CERCLA Remedial Action? No existing impairment Impairment due to habitat destruction Restoration Plus baseline Impairment due to releases of hazardous substances NRD Restoration Injury by hazardous substances 2003 Presumed restoration start date
8 How are NRD Determined? Agency-down enforcement-driven Commencement Bay Pursuant to OPA (NOAA) or CERCLA (DOI) assessment regulations (which has a rebuttable presumption of correctness) Litigation e.g., Coeur D Alene, Montrose Cooperative NRDA Process Portland Harbor?
9 Timing: When are NRD Determined? Historical View: NRD Assessment is what comes after CERCLA remedial action. Current Trend: NRDA can and should be conducted in concert with RI/FS for remedial action.
10 Have we answered the legal and scientific questions necessary to determine NRD? While there is ample room for disagreement on the facts and the law as it is to be applied to this case, it is undisputed that [the case of NRD for the Coeur D Alene basin] is unique in its size, its history and its complexity. The case is of great importance and calls for the exercise of the greatest care and caution in its consideration, a task that is very difficult when expert witnesses with impeccable qualifications reached opposite conclusions on almost every issue. --Coeur D Alene Tribe and USA v. Asarco, et al. (9/03/03 Opinion)
11 Have we answered the legal and scientific questions necessary to determine NRD? In the Fox River, USFWS valued NRD at $ million. Wisconsin Department of Natural Resources valued it at $55 million.
12 Is a court the right place to determine NRD? After listening to approximately 100 witnesses, 78 days of trial and having reviewed 8,695 exhibits... it is the judgment of this Court that... the liability of certain responsible parties... is evident, but the Defendants are correct when they argue that there has been an exaggerated overstatement by the Federal Government and the Tribe of the conditions that exist and the source of the alleged injury to natural resources.... [T[he Court finds its hands are often tied and justice is dictated by the statutes passed by politicians who at the time could not have imagined the factual scenario pending before this Court. --Coeur D Alene Tribe and USA v. Asarco, et al. (9/03/03 Opinion)
Building a Strong Legal Foundation to Support the Enforcement of a Tribal Trustee s Natural Resource Damage Claims
Building a Strong Legal Foundation to Support the Enforcement of a Tribal Trustee s Natural Resource Damage Claims BY: RICHARD A. DU BEY and BRIAN EPLEY 2015 Tribal Lands and Environment Forum Tuesday,
More informationJoan P. Snyder, Esq. Stoel Rives LLP (503)
Allocation of Liability at a Sediment Cleanup Site by Joan P. Snyder, Esq. Stoel Rives LLP jpsnyder@stoel.com (503) 294-9657 Types of Costs to Recover EPA and DEQ site assessment and oversight Remedial
More informationNatural Resources & Environmental Law on the Reservation Exploring Hot Legal Issues
Natural Resources & Environmental Law on the Reservation Exploring Hot Legal Issues 8th Annual Conference September 20-21, 2004 Hilton Phoenix East Mesa, Arizona Injury to Cultural and Spiritual Resources
More informationPresenting a live 90-minute webinar with interactive Q&A. Today s faculty features:
Presenting a live 90-minute webinar with interactive Q&A Natural Resource Damages Assessment: Valuing and Contesting NRD Injury and Damages Methods for Determining and Quantifying Injury and Damages, Evaluating
More informationMANAGING CLAIMS FOR NATURAL RESOURCE DAMAGES
The article Managing Claims for Natural Resource Damages by Gary P. Gengel and Kegan A. Brown first appeared in the In-House Counsel Committee Newsletter, Vol. 12, No. 2, June 2011, Section of Environment,
More informationPre-ROD Cooperative NRD Assessment and Restoration Update from Portland Harbor
Pre-ROD Cooperative NRD Assessment and Restoration Update from Portland Harbor Joan P. Snyder, Esq. Stoel Rives LLP / Portland, OR Katherine Pease, Esq., Deputy Section Chief and Senior Counselor for Natural
More informationOverview: The CERCLA Process. Connie Sue Martin
Overview: The CERCLA Process Connie Sue Martin Overview Removal and/or Remediation Process Natural Resource Damage Assessment and Restoration CERCLA Comprehensive Environmental Response, Compensation and
More informationBet the Port Litigation: Claims and Damages Considerations for Ports in the Wake of an Environmental Catastrophe
Bet the Port Litigation: Claims and Damages Considerations for Ports in the Wake of an Environmental Catastrophe Bill Jackson Jackson Gilmour & Dobbs, PC (713) 355-5050 bjackson@jgdpc.com Surface Water
More informationPortland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No
P.U.C. Oregon No. E-18 Original Sheet No. 149-1 PURPOSE SCHEDULE 149 ENVIRONMENTAL REMEDIATION COST RECOVERY ADJUSTMENT AUTOMATIC ADJUSTMENT CLAUSE This Schedule recovers the costs and revenues associated
More informationINTRODUCTION TO NRD & FEDERAL FACILITIES
INTRODUCTION TO NRD & FEDERAL FACILITIES W H E N T H E F E D S W E A R A L L T H E H A T S JOHN D.S. GILMOUR Jgilmour@KelleyDrye.com (713) 355-5005 Federal Facilities Overview What are federal facilities?
More informationTony Penn National Oceanic and Atmospheric Administration 1305 East West Highway, #10218 Silver Spring MD 20910
$6800$5
More informationDirector National Pollution Funds Center. Tony Penn DEPUTY CHIEF, ASSESSMENT AND RESTORATION DIVISION, NOAA
U.S. Department of Homeland Security United States Coast Guard MEMORANDUM Director National Pollution Funds Center U.S. Coast Guard Stop 7100 4200 Wilson Blvd, Suite 1000 Arlington, VA 20598-7100 Staff
More informationChapter Finance/ Administration
Chapter 6000 Finance/ Administration Northwest Area Committee Expectations: - Northwest Area Committee members and those responding within the region are expected to be aware of the importance of rapidly
More informationRestoration Planning Guidance Document for Natural Resource Damage Assessment Under the Oil Pollution Act of 1990
Restoration Planning Guidance Document for Natural Resource Damage Assessment Under the Oil Pollution Act of 1990 Damage Assessment and Restoration Program August 1996 RESTORATION PLANNING GUIDANCE DOCUMENT
More informationPublic Claims and Damages Arising from Environmental Harms to Our Rivers, Bays and Estuaries Bill Jackson
Public Claims and Damages Arising from Environmental Harms to Our Rivers, Bays and Estuaries Bill Jackson bjackson@jgdpc.com Complexity of Rivers, Bays and Sediment Sites Risk Based Cleanup: Human
More informationAnderson Brothers, Inc. v. St. Paul Fire and Marine Insurance Co.
Public Land and Resources Law Review Volume 0 Case Summaries 2013-2014 Anderson Brothers, Inc. v. St. Paul Fire and Marine Insurance Co. Katelyn J. Hepburn University of Montana School of Law, katelyn.hepburn@umontana.edu
More informationNatural Resource Damages: Settlement Negotiation Issues and Strategies
Natural Resource Damages: Settlement Negotiation Issues and Strategies November 7, 2016 Tom Campbell Amanda Halter Natural Resources & Trustees are Broadly Defined Land, fish, wildlife, biota, air, water,
More information2016 OSB Environmental & Natural Resource Section Annual CLE. CERCLA Update. Patrick Rowe. October 14, 2016
2016 OSB Environmental & Natural Resource Section Annual CLE CERCLA Update Patrick Rowe October 14, 2016 1000 SW Broadway, Suite 1400 Portland Oregon 97205 503.227.1111 sussmanshank.com AIRBORNE RELEASE
More informationLIMITED ENVIRONMENTAL INDEMNITY AGREEMENT
LIMITED ENVIRONMENTAL INDEMNITY AGREEMENT This LIMITED ENVIRONMENTAL INDEMNITY AGREEMENT is entered into as of the day of, 2011, by ("Indemnitor") and the City of (the "City"). RECITALS A. WHEREAS, Indemnitor
More informationTable of Contents. Title 43 NATURAL RESOURCES. Part XXIX. Oil Spill Prevention and Response
Table of Contents Title 43 NATURAL RESOURCES Part XXIX. Oil Spill Prevention and Response Chapter 1. Natural Resource Damage Assessment... 1 Subchapter A. General Provisions... 1 101. Declaration and Intent...
More informationScaling Compensatory Restoration Actions Guidance Document for Natural Resource Damage Assessment Under the Oil Pollution Act of 1990
Scaling Compensatory Restoration Actions Guidance Document for Natural Resource Damage Assessment Under the Oil Pollution Act of 1990 Damage Assessment and Restoration Program December 1997 NATURAL RESOURCE
More informationSettlement of Sediment Cases: The Passaic River Example Bill Jackson
Settlement of Sediment Cases: The Passaic River Example Bill Jackson bjackson@jgdpc.com UNIQUE DIFFICULTIES OF LITIGATING & RESOLVING SEDIMENT SITES Complexity of Sediment Sites Multiple Responsible Parties
More informationCERCLA s Equitable Allocation Of Liability
Portfolio Media, Inc. 648 Broadway, Suite 200 New York, NY 10012 www.law360.com Phone: +1 212 537 6331 Fax: +1 212 537 6371 customerservice@portfoliomedia.com CERCLA s Equitable Allocation Of Liability
More informationTribal Sovereignty and Natural Resource Damages
Public Land and Resources Law Review Volume 25 Tribal Sovereignty and Natural Resource Damages Allan Kanner Follow this and additional works at: http://scholarship.law.umt.edu/plrlr Recommended Citation
More informationDeepwater Horizon Oil Spill In the Wake of Disaster
Deepwater Horizon Oil Spill In the Wake of Disaster Steve McKinney Chair Environmental & Natural Resources Section Balch & Bingham LLP Chair Section of Environment Energy & Resources American Bar Association
More informationPublic Claims and Damages Arising from Environmental Harms to Our Rivers, Bays and Estuaries
Public Claims and Damages Arising from Environmental Harms to Our Rivers, Bays and Estuaries Bill Jackson bjackson@jgdpc.com Complexity of Rivers, Bays and Sediment Sites Risk Based Cleanup:
More informationRussell S. Kent. Office of the Attorney General
Russell S. Kent Special Counsel for Litigation Office of the Attorney General 1 OPA 33 U.S.C. USC 2701 et seq. Passed in response to the 1989 Exxon Valdez disaster. Chapter 376, The Pollutant Discharge
More informationOf the scientific fields relevant to the environmental
Habitat and Resource Equivalency Analyses in Resource Compensation and Restoration Decision Making Joan P. Snyder and William H. Desvousges, Ph.D. Of the scientific fields relevant to the environmental
More informationMay 31, RE: Claim Number: N10036-OI09 Deepwater Horizon Oil Spill Assessment, Kemp s ridley nesting plan
U.S. Department of Homeland Security United States Coast Guard Director National Pollution Funds Center May 31, 2012 US COAST GUARD MS 7100 4200 Wilson Blvd. Suite 1000 Arlington, VA 20598-7100 Staff Symbol:
More informationJanuary 16, Re: Claim Number N10036-OC15 - Deepwater Horizon Oil Spill 2013/14 Lost Use Assessment
U.S. Department of Homeland Security United States Coast Guard Director United States Coast Guard National Pollution Funds Center Natural Resource Damage (NRD) Claims Division January 16, 2013 U.S. Coast
More informationENVIRONMENTAL NEWS & HIGHLIGHTS July 2016
ENVIRONMENTAL NEWS & HIGHLIGHTS July 2016 Presented by: EXCALIBUR GROUP, LLC Environmental Consultants, Engineers & Liability Management Experts This latest EXCALIBUR bulletin presents several emerging
More informationProcedural Considerations For Insurance Coverage Declaratory Judgment Actions
Procedural Considerations For Insurance Coverage Declaratory Judgment Actions New York City Bar Association October 24, 2016 Eric A. Portuguese Lester Schwab Katz & Dwyer, LLP 1 Introduction Purpose of
More informationNational Pollution Funds Center Determination
National Pollution Funds Center Determination Claim Number and Name: N10036-EP32, 2015 Deepwater Horizon Assessment Costs Claimant: Environmental Protection Agency Claim Type: NRDA, Past and Upfront Assessment
More informationSEMS-RM DOCID #
I. PURPOSE U.S. Environmental Protection Agency and Nevada Division of Environmental Protection National Priorities List Deferral Agreement Anaconda Copper Mine Site, Lyon County, Nevada SEMS-RM DOCID
More informationDirector National Pollution Funds Center
U.S. Department of Homeland Security United States Coast Guard MEMORANDUM Director National Pollution Funds Center U.S. Coast Guard Stop 7100 4200 Wilson Blvd, Suite 1000 Arlington, VA 20598-7100 Staff
More informationJuly 20, RE: Claim Number: N10036-OI11 Deepwater Horizon Oil Spill Assessment, Loggerhead nesting plan
U.S. Department of Homeland Security United States Coast Guard Director United States Coast Guard National Pollution Funds Center U.S. Coast Guard Stop 7100 National Pollution Funds Center 4200 Wilson
More informationTHE NATURAL RESOURCE DAMAGE ASSESSMENT DESKBOOK
THE NATURAL RESOURCE DAMAGE ASSESSMENT DESKBOOK A Legal and Technical Analysis 2 nd Edition Valerie Ann Lee P.J. Bridgen Environment International Ltd. & Acadia Law PLLC ENVIRONMENTAL LAW INSTITUTE Washington,
More informationWaking the Sleeping Giant: Analyzing New Jersey's Pursuit of Natural Resource Damages from Responsible Polluting Parties in the Lower Passaic River
Pace Environmental Law Review Volume 23 Issue 1 Winter 2005-2006 Article 9 January 2006 Waking the Sleeping Giant: Analyzing New Jersey's Pursuit of Natural Resource Damages from Responsible Polluting
More informationNPFC DETERMINATION. Claim History
NPFC DETERMINATION Claim Number and Name: N10036-OI23, Deepwater Horizon Oil Spill Assessment Claimant: U.S. Department of the Interior Type of Claim: Natural Resource Damage Assessment, Upfront Assessment
More information[Docket No. FWS HQ ES ]; [FXHC FF09E33000]
This document is scheduled to be published in the Federal Register on 07/30/2018 and available online at https://federalregister.gov/d/2018-16172, and on govinfo.gov DEPARTMENT OF THE INTERIOR Fish and
More informationGENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2009 SESSION LAW SENATE BILL 836
GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2009 SESSION LAW 2010-179 SENATE BILL 836 AN ACT TO: (1) CLARIFY LIABILITY FOR DAMAGES CAUSED BY THE DISCHARGE OF NATURAL GAS, OIL, OR DRILLING WASTE INTO STATE
More information11. Legal obstacles for contingent valuation methods in environmental litigation
11. Legal obstacles for contingent valuation methods in environmental litigation Brian D. Israel, Jean Martin, Kelly Smith Fayne, and Lauren Daniel 1 INTRODUCTION Contingent valuation surveys, and other
More informationEnvironmental Liability Risk Trends
RISK MANAGEMENT FORUM 2007 GENEVA, 30 SEPT 3 OCT 2007 Environmental Liability Risk Trends Simon White Environmental Branch Manager XL Insurance The Insurance market How does it currently respond to Environmental
More informationDare You to Buy. Kristin White, Associate Legal Counsel Minnesota Department of Transportation
Dare You to Buy Kristin White, Associate Legal Counsel Minnesota Department of Transportation NOTES Why the worry? Environmental law 101 What your organization can do Why the worry? Removal/remediation
More informationMEMORANDUM OF UNDERSTANDING BETWEEN THE NATIONAL POLLUTION FUNDS CENTER UNITED STATES COAST GUARD AND THE
MEMORANDUM OF UNDERSTANDING BETWEEN THE NATIONAL POLLUTION FUNDS CENTER UNITED STATES COAST GUARD AND THE OFFICE OF RESPONSE AND RESTORATION NATIONAL OCEAN SERVICE NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION
More informationUNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 10-Q
For the quarterly period ended: April 5, 2009 OR UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 10-Q x QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE
More informationSummary Klamath Hydroelectric Settlement Agreement
Summary Klamath Hydroelectric Settlement Agreement Summary and Status January 7, 2010 PacifiCorp and over 30 federal, state, tribal, county, irrigation, conservation, and fishing organizations have developed
More informationIntroduction to Financial Assurance. ORCR USEPA July 2012
Introduction to Financial Assurance ORCR USEPA July 2012 Relationship between the EIS/EIA Process and FA The EIA/EIS should include a draft mine operations plan and a preliminary mine reclamation and closure
More informationRestructuring Among the Ruins Conference Athens, Greece May 7-9, 2006 ENVIRONMENTAL ISSUES IN UNITED STATES BANKRUPTCY PROCEEDINGS
Restructuring Among the Ruins Conference Athens, Greece May 7-9, 2006 ENVIRONMENTAL ISSUES IN UNITED STATES BANKRUPTCY PROCEEDINGS Daniel M. Glosband, Esq. Macken Toussaint, Esq. Goodwin Procter LLP Exchange
More informationThe 2010 Oil Spill: Natural Resource Damage Assessment Under the Oil Pollution Act
The 2010 Oil Spill: Natural Resource Damage Assessment Under the Oil Pollution Act Kristina Alexander Legislative Attorney September 8, 2010 Congressional Research Service CRS Report for Congress Prepared
More informationClaimant s Guide. A Compliance Guide for Submitting Claims Under the Oil Pollution Act of 1990
Claimant s Guide A Compliance Guide for Submitting Claims Under the Oil Pollution Act of 1990 CG National Pollution Funds Center Claims US Coast Guard Stop 7605 2703 Martin Luther King JR Ave SE Washington
More informationSPECIMEN. of Financial Impairment of the issuers of such Underlying Insurance;
In consideration of payment of the premium and subject to the Declarations, limitations, conditions, provisions and other terms of this Policy, the Company and the Insured Person agree as follows: Insuring
More informationJohn C. Butler III DIRECTOR
4350 N. Fairfax Dr. Suite 830 Arlington, VA 22203 1673 T 505.660.1746 F 505.989.7021 jbutler@gnarusllc.com www.gnarusllc.com OVERVIEW EXPERIENCE Mr. Butler has extensive experience with environmental and
More informationAGREEMENT BY AND BETWEEN ROCKLIN UNIFIED SCHOOL DISTRICT AND ROCKLIN EDUCATIONAL EXCELLENCE FOUNDATION RECITALS
AGREEMENT BY AND BETWEEN ROCKLIN UNIFIED SCHOOL DISTRICT AND ROCKLIN EDUCATIONAL EXCELLENCE FOUNDATION This agreement ("Agreement") is made by and between Rocklin Unified School District, a public school
More informationNatural Resource. Section 32B.09 discusses the advantages, disadvantages and mechanics of cooperating with the government in an NRD matter.
Natural Resource Damages 32B Brian D. Israel, Esq. Arnold & Porter LLP 555 12th Street, N. Washington, D.C. 20004 (202) 942.6546 brian israel (g) aporter.com This chapter addresses the ability of the government
More information8. Liability Approaches
Liability Approaches 8. Liability Approaches The purpose of liability mechanisms in environmental management is twofold: first, to give polluters an economic incentive to make more careful decisions; and
More informationNatural Resource Valuation and Damage Assessment in Nigeria. A Comparative Analysis
Natural Resource Valuation and Damage Assessment in Nigeria A Comparative Analysis August 2003 Natural Resource Valuation and Damage Assessment in Nigeria A Comparative Analysis Environmental Law Institute
More informationPOST SPILL ENVIRONMENTAL MONITORING
POST SPILL ENVIRONMENTAL MONITORING Lessons learnt from an international perspective Julke Brandt Technical Adviser Meeresumwelt- Symposium, Hamburg, 12 th 13 th June 2018 OUTLINE 1. Introduction to ITOPF
More informationEndangered Species Act
Presentation to Endangered Species Act Non-Federal Compliance Process and Options Amanda Aurora, CWB Senior Scientist / Project Manager SWCA Austin October 15, 2014 Endangered Species Act of 1973 Protects
More informationSARPY COUNTY AND SARPY CITIES WASTEWATER AGENCY
SARPY COUNTY AND SARPY CITIES WASTEWATER AGENCY RESOLUTION APPROVING AGREEMENT WITH HDR FOR ENGINEERING SERVICES RELATED TO THE SOUTHERN SARPY COUNTY WASTEWATER TREATMENT STUDY PHASE 2B WHEREAS, Sarpy
More information79th OREGON LEGISLATIVE ASSEMBLY Regular Session
th OREGON LEGISLATIVE ASSEMBLY--0 Regular Session House Bill 00 Sponsored by Representatives LININGER, BYNUM, LIVELY, Senator TAYLOR; Representatives ALONSO LEON, PILUSO, POWER, SMITH WARNER, SOLLMAN SUMMARY
More informationDEFENSE BASE ACT WORKERS COMPENSATION FOR EMPLOYEES OF U.S. GOVERNMENT CONTRACTORS WORKING OVERSEAS
DEFENSE BASE ACT WORKERS COMPENSATION FOR EMPLOYEES OF U.S. GOVERNMENT CONTRACTORS WORKING OVERSEAS Federal law requires all U.S. government contractors and subcontractors to secure workers compensation
More informationSussman Shank. attorneys. Contractual Tools for Allocating Liability. Patrick G. Rowe
Sussman Shank attorneys llp Contractual Tools for Allocating Liability Patrick G. Rowe 2016 1000 SW Broadway, Suite 1400 Portland Oregon 97205 503.227.1111 CONTRACTUAL TOOLS FOR MITIGATING & ALLOCATING
More informationASBESTOS INDIRECT CLAIM FORM
WRG ASBESTOS PI TRUST 1 Submit completed claims to: WRG Asbestos PI Trust P.O. Box 1390 Wilmington, DE 19899-1390 Instructions for the Asbestos Indirect Claim Form For purposes of this Claim Form, the
More informationSummary Draft Klamath Hydroelectric Settlement Agreement
Summary Draft Klamath Hydroelectric Settlement Agreement Summary and Status September 30, 2009 Klamath River Basin organizations have developed a draft Klamath Hydroelectric Settlement Agreement and sent
More informationOUR WORK. SUPERFUND, COST RECOVERY AND CONTRIBUTION - Overview
SUPERFUND, COST RECOVERY AND CONTRIBUTION - Overview We have represented clients in all types of Superfund matters, including as PRPs at multi-party disposal sites, as both plaintiffs and defendants in
More informationThe 2010 Deepwater Horizon Oil Spill: Natural Resource Damage Assessment Under the Oil Pollution Act
The 2010 Deepwater Horizon Oil Spill: Natural Resource Damage Assessment Under the Oil Pollution Act Adam Vann Legislative Attorney Robert Meltz Legislative Attorney July 24, 2013 Congressional Research
More informationThe Unified Command with the assistance of the NOAA SSC continuously assessed the impact of pollution on the Louisiana shoreline.
Claim Number: Claimant: Type of Claim: Claim Manager: Amount Requested: BACKGROUND CLAIM SUMMARY I DETERMINATION N12062-0001 Douglas E. Renard Real or Personal Property $22,230.00 On August 29, 2012, Hurricane
More informationCLAIM SUMMARY / DETERMINATION
Claim Number: 917012-0001 Claimant: Lac du Flambeau Tribe Type of Claimant: Municipality Type of Claim: Removal Costs Claim Manager: Amount Requested: $9,091.00 FACTS: CLAIM SUMMARY / DETERMINATION Oil
More informationAmendments to Michigan s Cleanup Program
Amendments to Michigan s Cleanup Program Warner Norcross & Judd LLP CLEANUP CRITERIA Only 5 cleanup criteria: Residential Nonresidential (will be the former industrial criteria until new nonresidential
More informationUpdate on Environmental Liability in Real Estate Transactions
Update on Environmental Liability in Real Estate Transactions Watch-Outs and Best Practices for the General Practice Lawyer Environment, Energy and Resources Law Section What You ll Learn This Morning
More informationJohn E. Heintz Partner Insurance Recovery Eye Street NW Washington, D.C
John E. Heintz Partner Insurance Recovery 1825 Eye Street NW Washington, D.C. 20006 +1.202.420.5373 jheintz@ John Heintz is a partner in Blank Rome s policyholder-only insurance recovery practice, formerly
More informationREQUEST FOR QUALIFICATIONS. Environmental Consulting Services To Support Brownfields Revolving Loan Fund Program
REQUEST FOR QUALIFICATIONS Environmental Consulting Services To Support Brownfields Revolving Loan Fund Program MARCH 2019 TREASURE COAST REGIONAL PLANNING COUNCIL BROWNFIELDS PROGRAM REQUEST FOR QUALIFICATIONS
More informationEXCESS LIABILITY COVERAGE FORM
ABCD GAI Administrative Offices 301 E 4th Street Cincinnati OH 45202-4201 513 369 5000 ph 6524 (Ed. 06 97) EXCESS LIABILITY COVERAGE FORM There are provisions in this policy that restrict coverage. Read
More informationOctober 28, SUBJECT: Quarterly Review of Within-year Project Funding Adjustments for Implementation.
Bruce A. Measure Chair Montana Rhonda Whiting Montana W. Bill Booth Idaho James A. Yost Idaho Dick Wallace Vice-Chair Washington Tom Karier Washington Melinda S. Eden Oregon Joan M. Dukes Oregon October
More informationCONSULTANT SERVICES AGREEMENT (Hazardous Material Assessment/ Abatement Consulting Services)
CONSULTANT SERVICES AGREEMENT (Hazardous Material Assessment/ Abatement Consulting Services) This AGREEMENT is made and entered into this day of in the year 20 ( EFFECTIVE DATE ), between the Los Alamitos
More informationPermit for Filming within the Municipality of Skagway Borough
Permit for Filming within the Municipality of Skagway Borough This Filming Permit Agreement ( Agreement ) is between a ( Permittee ) and the Municipality of Skagway Borough (the MOS ) with regard to an
More informationTITLE 39 HEALTH AND SAFETY CHAPTER 81 BASIN ENVIRONMENTAL IMPROVEMENT ACT
TITLE 39 HEALTH AND SAFETY CHAPTER 81 BASIN ENVIRONMENTAL IMPROVEMENT ACT 39-8102. POLICY OF STATE. The Idaho legislature declares that environmental protection and improvement of the Coeur d Alene basin
More informationStephen E. Sellick MANAGING DIRECTOR
4350 N. Fairfax Dr. Suite 830 Arlington, VA 22203 1673 T 202.595.3566 F 866.485.9227 ssellick@gnarusllc.com www.gnarusllc.com OVERVIEW EXPERIENCE Mr. Sellick is the Managing Director and founder of Gnarus
More informationThe Deepwater Horizon Oil Spill and its Economic Impact on the Seafood. Industry. Introduction
Tiajuana Robinson Admiralty Law Professor Hooks November 16, 2012 The Deepwater Horizon Oil Spill and its Economic Impact on the Seafood Industry Introduction The United States has faced many grave tragedies
More informationSteven J. Elie PRACTICE GROUPS EDUCATION PROFESSIONAL SUMMARY. Partner, Los Angeles Office. (213) (213)
Steven J. Elie Partner, Los Angeles Office s.elie@musickpeeler.com (213) 629-7745 (213) 624-1376 PRACTICE GROUPS Environmental & Public Law Litigation Water Law Insurance Land Use White Collar and Government
More informationEffective Coordination and Cooperation Between Ecological Risk Assessments and Natural Resource Damage Assessments: A New Synthesis
Effective Coordination and Cooperation Between Ecological Risk Assessments and atural Resource Damage Assessments: A ew Synthesis Ronald G Gouguet,*7 David W Charters,8 Larry F Champagne,6 Mark Davis,I
More informationState v. Continental Insurance Company
Public Land and Resources Law Review Volume 0 Case Summaries 2012-2013 State v. Continental Insurance Company John M. Newman john.newman@umontana.edu Follow this and additional works at: https://scholarship.law.umt.edu/plrlr
More informationBrownfields Redevelopment and the. Spiegel & McDiarmid LLP and The National Association of Local Government Environmental Professionals
Brownfields Redevelopment and the Threat of CERCLA Liability Elaine C. Lippmann Spiegel & McDiarmid LLP and The National Association of Local Government Environmental Professionals October 19, 2009 Agenda
More informationLabor Management Trust Fiduciary Liability Policy
Labor Management Trust Fiduciary Liability Policy In consideration of the payment of the premium and subject to the Declarations, limitations, conditions, provisions and other terms of this policy, the
More informationUNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 10-Q
UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 10-Q x QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the quarterly period ended:
More informationSession of SENATE BILL No. 73. By Committee on Commerce 1-24
Session of 0 SENATE BILL No. By Committee on Commerce - 0 0 0 AN ACT concerning workers compensation, relating to administrative duties assumed by the secretary of health and environment; legal status
More informationThe Mackinac Straits Oil Pipeline Lessons for Advocacy & Policy Mike Shriberg, Ph.D. Great Lakes Regional Executive Director, National Wildlife
The Mackinac Straits Oil Pipeline Lessons for Advocacy & Policy Mike Shriberg, Ph.D. Great Lakes Regional Executive Director, National Wildlife Federation Enbridge Lakehead Pipeline System Superior, Wisc.
More informationMULTNOMAH COUNTY, OREGON
MULTNOMAH COUNTY, OREGON DEPARTMENT OF COMMUNITY SERVICES LAND USE & TRANSPORTATION PROGRAM RIGHT-OF-WAY PERMIT SECTION 1620 SE 190TH AVENUE PORTLAND, OREGON 97233 503-988-3582 - FAX: 503-988-3389 APPLICATION
More informationASBESTOS INDIRECT CLAIM FORM
OWENS CORNING ASBESTOS PERSONAL INJURY TRUST Submit completed claims to: Owens Corning Asbestos Personal Injury Trust P.O. Box 1072 Wilmington, DE 19899-1072 Instructions for the Asbestos Indirect Claim
More informationNo IN THE UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT. Jose Vera,
Case: 17-35724, 12/07/2017, ID: 10683334, DktEntry: 10, Page 1 of 14 No. 17-35724 IN THE UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT Jose Vera, v. Plaintiff-Appellant, U.S. Department of Interior
More informationGeorge L. Seay, Jr. Wyatt, Tarrant & Combs, LLP 250 West Main Street, Suite 1600 Lexington, KY (859)
The Comprehensive Environmental Response, Compensation, and Liability Act ( Superfund ) and Kentucky House Bill 465: Exemptions and Protection From Liability George L. Seay, Jr. Wyatt, Tarrant & Combs,
More informationIN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF PENNSYLVANIA
Late et al v. United States of America Doc. 44 IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF PENNSYLVANIA CHRISTINA LATE AND NATHAN : ARMOLT, AS PARENTS AND : CIVIL NO. 1:13-CV-0756 NATURAL
More informationCONTRACT FOR SNOW AND ICE MANAGEMENT SERVICES. Updated November 15, 2018
CONTRACT FOR SNOW AND ICE MANAGEMENT SERVICES Updated November 15, 2018 This contract ( Contract ) is entered into by and between [contractor company] ( Contractor ) and [name of property owner] ( Owner
More informationManagement liability corporate legal liability Policy wording
The General terms and conditions and the following terms and conditions all apply to this section. Cover under this section is given on an aggregate basis unless otherwise specified. Special definitions
More informationPotential Process for Recovering Environmental Response Costs From the U.S. Government. A.J. Gravel FTI Consulting, Inc.
Potential Process for Recovering Environmental Response Costs From the U.S. Government A.J. Gravel FTI Consulting, Inc. aj.gravel@fticonsulting.com July 31, 2017 Introduction Table of Contents Overview
More informationIN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF MICHIGAN NATIONAL WILDLIFE FEDERATION,
2:16-cv-11727-GCS-EAS Doc # 1 Filed 05/16/16 Pg 1 of 27 Pg ID 1 IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF MICHIGAN NATIONAL WILDLIFE FEDERATION, Case No. Plaintiff, v. Judge ADMINISTRATOR
More informationMTBE: Coverage For This "Spreading" Problem
Proceedings of the Annual International Conference on Soils, Sediments, Water and Energy Volume 11 Article 11 January 2010 MTBE: Coverage For This "Spreading" Problem John N. Ellison ESQ Anderson Kill
More information[Bank Name] Mitigation Bank CA BEI template_pdt FINAL Draft dot
MITIGATION BANK ENABLING INSTRUMENT Table of Contents RECITALS... 1 AGREEMENT...2 Section I: Purpose and Authorities... 2 A. Purpose...2 B. Authorities... 2 Section II: Definitions... 4 Section III: Stipulations...
More informationExecutive Protection Policy
Employment Practices Coverage Section In consideration of payment of the premium and subject to the Declarations, General Terms and Conditions, and the limitations, conditions, provisions and other terms
More information