VARIANCE ANALYSIS: ILLUSTRATION
|
|
- Albert Harrell
- 5 years ago
- Views:
Transcription
1 VARIANCE ANALYSIS: ILLUSTRATION The following information relates to the production of product Alpha for the month of August Standard Cost Card Budgeted production overhead based on 10,000 units $ $ Selling Price $ Standard cost Materials: 5 kilograms $12.00/kg $60.00 Labour: 4 hours $10.00/hour $40.00 Variable overheads: 4 hours $8.00/hour $32.00 Fixed overheads $28.00 $ Standard profit $ Actual Data Actual materials used 52,800 kg Actual Materials cost $595,200 Actual production output 9,600 units Actual wage cost $475,200 Actual variable cost $288,000 Actual time worked and paid for 43,200 hours Actual fixed costs $290,000 Actual SP per unit $310 Actual sales 9,600 units Required Calculate for the month of August as many variances as the information permits and prepare an operating statement reconciling actual and standard profit. 1
2 SOLUTION MATERIAL VARIANCES TOTAL MATERIAL COST VARIANCE Actual cost of materials purchased Standard quantity of materials for actual activity (kg) Actual production level standard material cost per unit TOTAL COST VARIANCE Price Variance Actual cost of materials purchased Standard cost of materials purchased (Standard price actual quantity purchased) Material price variance 38.4 Usage Variance Actual quantity of materials used (kg) 52,800 Standard quantity of materials for actual quantity (kg) (Standard quantity actual production level) 48,000 Valued at standard price per kg $12.00 Material usage variance LABOUR VARIANCES TOTAL LABOUR COST VARIANCE Actual wage costs Standard time worked for actual production (hrs) (Standard time actual production level) TOTAL COST VARIANCE
3 Rate variance Actual wage costs Standard wage costs (Standard rate actual hours attended) Labour rate variance Efficiency Variance Actual hours worked (hours) 43,200 (Standard time actual production level) 38,400 Valued at standard price per hour $10.00 Labour efficiency variance VARIABLE OVERHEAD VARIANCES TOTAL VARIABLE OVERHEAD COST VARIANCE Actual variable overhead costs (Standard time actual production level) TOTAL COST VARIANCE 19.2 Expenditure variance Actual variable overhead costs Standard variable overhead costs (Standard rate actual hours attended) Efficiency variance Actual hours worked (hours) 43,200 (Standard time actual production level) 38,400 3
4 Valued at standard price per hour $8.00 Variable efficiency variance FIXED OVERHEAD VARIANCES TOTAL FIXED OVERHEAD COST VARIANCE Actual fixed overhead costs Standard fixed overhead applied for actual production (units) (Standard fixed cost actual production level) TOTAL COST VARIANCE Expenditure variance Actual fixed overhead costs Budgeted fixed overhead costs Volume variance Actual production output (units) 9,600 Budgeted production output (units) 10, Valued at standard rate per unit $28.00 Fixed overhead volume variance -$11.20 SALES VARIANCES Price variance Actual sales revenue 2,976.0 Expected sales revenue (Standard selling price actual sales volume) 2,880.0 Sales price variance 96.0 Volume variance Actual sales volume (units) 9, Budgeted sales volume (units) 4
5 10, Valued at standard profit per unit $ Sales volume variance Operating Statement for the month of August 2010 $000s Budgeted profit 1,400.0 Sales volume variance Standard profit on actual sales 1,344.0 Sales price variance 96.0 F A Cost variances Material A - price usage 57.6 Direct labour - rate efficiency 48.0 Variable overheads - expenditure efficiency 38.4 Fixed overhead - expenditure volume efficiency 0.0 Sub total Net variances Actual profit 1,327.6 Actual profit for August Sales: 9,600 units $310 2,976.0 Less: actual costs Material Direct labour Variable overheads Fixed overhead ,648.4 Total
10,000 units x 24 = 240,000, or 5,000 hours x 48 = 240,000. the actual price of materials per kilogram
NVQ/SVQ Level 4 in Accounting Contributing to the Management of Performance and Enhancement of Value (PEV) (2003 standards) June 2006 SUGGESTED ANSWERS Note: The suggested answers may, in parts, be longer
More informationWrite your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.
Series 3 Examination 2008 COST ACCOUNTING Level 3 Friday 6 June Subject Code: 3016 Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your answers
More informationMonday 14 June 2004 (morning) EXAMINATION. Time allowed - 3 hours plus 15 minutes reading time
NVQ/SVQ Level 4 in Accounting Contributing to the Management of Performance and the Enhancement of Value (PEV) (2003 standards) / Management of Costs and the Enhancement of Value (MCV) (1998 standards)
More informationSOLUTIONS TO END-OF-CHAPTER QUESTIONS CHAPTER 13
SOLUTIONS TO END-OF-CHAPTER QUESTIONS CHAPTER 13 DEVELOP YOUR UNDERSTANDING Question 13.1 (a) The total expected costs of the orchard for the past year Fertiliser: 5 doses at 4.00 for 30 trees 600 Labour:
More informationWrite your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.
Series 2 Examination 2008 COST ACCOUNTING Level 3 Tuesday 27 May Subject Code: 3616/M Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your answers
More informationCode No. : Sub. Code : R 3 BA 52/ B 3 BA 52
(8 pages) Reg. No. :... Sub. Code : R 3 BA 52/ B 3 BA 52 B.B.A. (CBCS) DEGREE EXAMINATION, NOVEMBER 2014. Fifth Semester Business Administration Main MANAGEMENT ACCOUNTING (For those who joined in July
More informationTHE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL
EXAMINATION NO. THE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL MONDAY 2 JUNE 2014 TIME ALLOWED: 3 HOURS
More informationPreparing and using budgets
Osborne Books Tutor Zone Preparing and using budgets Chapter activities Osborne Books Limited, 2013 2 p r e p a r i n g a n d u s i n g b u d g e t s t u t o r z o n e 1 The budgeting environment 1.1 Match
More informationWrite your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.
Series 4 Examination 2008 COST ACCOUNTING Level 3 Tuesday 11 November Subject Code: 3016 Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your
More informationWrite your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.
Series 3 Examination 2007 COST ACCOUNTING Level 3 Tuesday 5 June Subject Code: 3716 (S) Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your
More informationWEEK 6 OPERATING BUDGETS (MANUFACTURING ORGANISATIONS) Case Study. The budgets that you need to prepare include:
WEEK 6 OPERATING BUDGETS (MANUFACTURING ORGANISATIONS) Case Study manufactures cardboard boxes which are used for transporting very special toys to toy stores all around Australia. You have already been
More informationStandard Costing and Budgetary Control
Standard Costing and Budgetary Control CA Past Years Exam Questions Question : 1 (Nov, 2008) UV Limited presents the following information for November. Calculate the cost Variances. Budgeted production
More informationstandard usage of materials for actual production standard labour time for actual production ( ) x 27,500 = 5,500 (A)
Contributing to the Management of Costs and Enhancement of Value (MCV) (1998 standards) / Management of Performance and Enhancement of Value (PEV) (2003 standards) Suggested Answers SECTION 1 Task 1.1
More informationPESIT Bangalore South Campus Hosur road, 1km before Electronic City, Bengaluru -100
INTERNAL ASSESSMENT TEST 3 Date : 09/11/2016 Max Marks : 50 Subject & Code : Cost Management (14MBAFM305) Section : Finance Name of faculty : Dr.R.Duraipandian Time: 8:30 10:00 AM Note: Answer all questions
More informationSERIES 4 EXAMINATION 2005 COST ACCOUNTING LEVEL 3. (Code No: 3016) FRIDAY 11 NOVEMBER
SERIES 4 EXAMINATION 2005 COST ACCOUNTING LEVEL 3 (Code No: 3016) FRIDAY 11 NOVEMBER Instructions to Candidates (a) (b) (c) (d) (e) (f) (g) (h) The time allowed for this examination is 3 hours. Answer
More informationStandard Costing and Variance Analysis
Standard Costing and Variance Analysis Standard Costing Standard cost is predetermined cost agreed earlier under specific working conditions. Standard costing is a technique which establishes predetermined
More informationOrdering costs Any two of the following: Postage, Paperwork, Telephone, Internet, , Purchasing Officer's salary
EDUCATION DEVELOPMENT INTERNATIONAL PLC SAMPLE PAPER ANSWERS 2008 COST ACCOUNTING (ASE3017) LEVEL 3 QUESTION 1 (a) (i) Stock holding costs Any two of the following: Insurance, Material handling, Storekeeper's
More informationSUGGESTED ANSWERS SPRING 2015 EXAMINATIONS 1 of 7 FUNDAMENTALS OF COST & MANAGEMENT ACCOUNTING SEMESTER-2
SUGGESTED ANSWERS SPRING 2015 EXAMINATIONS 1 of 7 Q. 2 (a) The Role of the Management Accountant: The management accountant plays a critical role in providing information to management to assist in planning,
More informationCERTIFICATE IN MANAGEMENT ACCOUNTING
Series 2 Examination 2007 CERTIFICATE IN MANAGEMENT ACCOUNTING Level 3 Monday 2 April Subject Code: 3023 Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal
More informationIn Class #8.1 Coverage of manufacturing overhead, standard cost system Required 1 Solution Exhibit 8-1 shows the computations. Summary details are:
In Class #8.1 Coverage of manufacturing overhead, standard cost system Required 1 Solution Exhibit 8-1 shows the computations. Summary details are: Actual Flexible Budget Output units 49,200 49,200 Allocation
More informationMANAGEMENT ACCOUNTING 2. Module Code: ACCT08004
School of Business & Enterprise Paisley & Hamilton Campus Session 015-016 Trimester 1 MANAGEMENT ACCOUNTING Module Code: ACCT08004 Date: 1st January 016 Time: 1400-1600 Answer THREE questions Question
More informationCosting Group 1 Important Questions for IPCC November 2017 (Chapters 10 12)
Costing Group 1 Important Questions for IPCC November 2017 (Chapters 10 12) CHAPTER 10 STANDARD COSTING 1. The standard material cost for a normal mix of one tonne of product Captain based on: Raw Material
More informationICAN MID DIET LIVE CLASS FOR MAY DIET 2015 PERFORMANCE MANAGEMENT
ICAN MID DIET LIVE CLASS FOR MAY DIET 2015 PERFORMANCE MANAGEMENT PERFORMANCE MEASUREMENT NON- FINANCIAL MEASUREMENT PERFOMANCE MEASUREMENT OF A NON- PROFIT ORGANISATION DIVISIONAL PERFORMANCE MEASURE
More informationstate the objectives of variance analysis understand the linkage between individual variances and the difference between budgeted and actual profit
1 INTRODUCTION In this lesson we explain the objective of analysis and provide a practical example of how the difference between budgeted and actual profit can be broken down into its constituent elements
More information2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL
EXAMINATION NO. 2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL FRIDAY 2 DECEMBER 2016 TIME ALLOWED: 3 HOURS 9.00 AM - 12.00 NOON INSTRUCTIONS 1. You are allowed
More informationARTT Business School Ahmed Raza Mir
Question 1 C Plus I Plus V Plus Selling Price 263 242 237 Direct Material (100) (98) (97) Direct Labour (15) (13) (12) Var OH (23) (19) (16) Var Selling OH (12) (8) (10) Commission (13) (12) (12) CM 100
More informationa) It is important to note that Famba will only receive the commission on the ticket price of R (2000 x 12.5% commission = R250)
QUESTION 1: a) It is important to note that Famba will only receive the commission on the ticket price of R2 000. (2000 x 12.5% commission = R250) Breakeven (units) = Fixed cost Marginal income (MI) =
More informationAnalysing financial performance
Osborne Books Tutor Zone Analysing financial performance Practice assessment 1 Osborne Books Limited, 2013 2 a n a l y s i n g f i n a n c i a l p e r f o r m a n c e t u t o r z o n e Task 1 The following
More informationWrite your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.
Series 2 Examination 2011 COST ACCOUNTING Level 3 Thursday 7 April Subject Code: 3017 Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer all 5 questions. All questions carry equal marks. Write your
More informationAccounting Technicians Ireland 2 nd Year Examination: Autumn 2013 Paper: MANAGEMENT ACCOUNTING
Accounting Technicians Ireland 2 nd Year Examination: Autumn 2013 Paper: MANAGEMENT ACCOUNTING Monday 26 th August 2013-2.30 p.m. to 5.30 p.m. INSTRUCTIONS TO CANDIDATES In this examination paper the /
More informationMANAGEMENT ACCOUNTING
Series 4 Examination 2009 MANAGEMENT ACCOUNTING Level 3 Tuesday 1 December Subject Code: 3724 S Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer all 5 questions. All questions carry equal marks.
More informationb Multiple Choice Questions: 1 The scarce factor of production is known as: d a) Key factor b) Limiting factor c) Critical factor d) All of the above
Q.1 a State whether True or False: [Any 8] 1 Functional Budget is a Budget which is established for use over a short period of time. FALSE 2 Total Fixed cost remains constant irrespective of change in
More informationTHE MOMBASA POLYTECHNIC UNIVERSITY COLLEGE
THE MOMBASA POLYTECHNIC UNIVERSITY COLLEGE Faculty of Business & Social Studies DEPARTMENT OF BUSINESS STUDIES BACHELOR OF BUSINESS ADMINISTRATION HBC 2117: COST ACCOUNTING BBA 2 ND YEAR 1 ST SEMESTER
More informationMark Scheme (Results) Series Pearson LCCI Level 3 COST ACCOUNTING (ASE3017)
Mark Scheme (Results) Series 3 2014 Pearson LCCI Level 3 COST ACCOUNTING (ASE3017) LCCI International Qualifications LCCI International Qualifications are awarded by Pearson, the UK s largest awarding
More informationTEST- 16 [Solution] Contract Price `25,00,000. Work Certified `24,00,000
Time Allowed: 1 hour 30 min. September 30, 2018 Total Marks: 50 Marks Answer to Question no.1: Sub- Contracting along with its Advantages 1. Sometimes the contractor may not find it feasible to do the
More informationACCA. Paper F2 and FMA. Management Accounting December 2014 to June Interim Assessment Answers
ACCA Paper F2 and FMA Management Accounting December 204 to June 205 Interim Assessment Answers To gain maximum benefit, do not refer to these answers until you have completed the interim assessment questions
More informationUNIVERSITY OF BOLTON BUSINESS SCHOOL BUSINESS MANAGEMENT PATHWAYS SEMESTER 1 EXAMINATION 2015/2016 FINANCIAL REPORTING FOR MANAGEMENT
BBS023 UNIVERSITY OF BOLTON BUSINESS SCHOOL BUSINESS MANAGEMENT PATHWAYS SEMESTER 1 EXAMINATION 2015/2016 FINANCIAL REPORTING FOR MANAGEMENT MODULE NO: BAM6008 Date: Thursday 14 th January 2016 Time: 10:00am
More informationPaper F5 ANSWERS TO EXAMPLES
September-December 2016 Examinations ACCA F5 87 Paper F5 ANSWERS TO EXAMPLES Chapter 1 ANSWER TO EXAMPLE 1 (a) Total overheads $190,000 Total labour hours A 20,000 2 = 40,000 B 25,000 1 = 25,000 C 2,000
More informationHOMEWORK. 1,40,000 20,000 (4,20,000 4,00,000) = 84,000 (F) WN 2: Calculation of effect on profit due to increase in market share
A.1. A.2. HOMEWORK WN 1: Calculation of effect on the profit due to market size Increasein profitduetogrowth = Growth in unitsdueto size increase Growth in units(total) 1,40,000 = 12,000(4,00,0003%) 20,000
More informationMTP_Intermediate_Syl2016_June2017_Set 1 Paper 10- Cost & Management Accounting and Financial Management
Paper 10- Cost & Management Accounting and Financial Management Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Paper-10: Cost & Management
More informationLCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017)
LCCI International Qualifications Cost Accounting Level 3 Model Answers Series 3 2010 (3017) For further information contact us: Tel. +44 (0) 8707 202909 Email. enquiries@ediplc.com www.lcci.org.uk Cost
More informationIbrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing)
Ibrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing) Variances A variance is the difference between a planned, budgeted, or standard cost and the actual cost incurred.
More informationCost Accounting. Level 3. Model Answers. Series (Code 3016) 1 ASE /2/06
Cost Accounting Level 3 Model Answers Series 2 2006 (Code 3016) 1 ASE 3016 2 06 1 3016/2/06 >f0t@w9w2`?[6zbkbwgc# Cost Accounting Level 3 Series 2 2006 How to use this booklet Model Answers have been developed
More informationPart 1 Examination Paper 1.2. Section A 10 C 11 C 2 A 13 C 1 B 15 C 6 C 17 B 18 C 9 D 20 C 21 C 22 D 23 D 24 C 25 C
Answers Part 1 Examination Paper 1.2 Financial Information for Management June 2007 Answers Section A 1 B 2 A 3 A 4 A 5 D 6 C 7 B 8 C 9 D 10 C 11 C 12 A 13 C 14 B 15 C 16 C 17 B 18 C 19 D 20 C 21 C 22
More informationUNIVERSITY OF BOLTON OFF CAMPUS DIVISION THE UNIVERSITY OF BANKING - HCMC VIETNAM BA (HONS) ACCOUNTANCY SEMESTER 1 EXAMINATIONS 2015/16
OCD006 UNIVERSITY OF BOLTON OFF CAMPUS DIVISION THE UNIVERSITY OF BANKING - HCMC VIETNAM BA (HONS) ACCOUNTANCY SEMESTER 1 EXAMINATIONS 2015/16 STRATEGIC MANAGEMENT ACCOUNTANCY MODULE NO: ACC6005 Date:
More informationCost Accounting. Level 3. Model Answers. Series (Code 3016)
Cost Accounting Level 3 Model Answers Series 4 2005 (Code 3016) Vision Statement Our vision is to contribute to the achievements of learners around the world by providing integrated assessment and learning
More information(AA22) COST ACCOUNTING AND REPORTING
All Rights Reserved ASSOCIATION OF ACCOUNTING TECHNICIANS OF SRI LANKA AA2 EXAMINATION - JANUARY 2019 (AA22) COST ACCOUNTING AND REPORTING Instructions to candidates (Please Read Carefully): (1) Time Allowed:
More informationCHAPTER 11. Cost volume profit analysis for decision making CONTENTS
CHAPTER 11 Cost volume profit analysis for decision making CONTENTS 11.1 Cost behaviour analysis using high low method 11.2 Absorption costing versus direct costing 11.3 CVP analysis 11.4 Impact of change
More informationLCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017)
LCCI International Qualifications Cost Accounting Level 3 Model Answers Series 2 2012 (3017) For further information contact us: Tel. +44 (0) 8707 202909 Email. enquiries@ediplc.com www.lcci.org.uk Cost
More informationMTP_ Inter _Syllabus 2016_ Dec 2017_Set 2 Paper 10 Cost & Management Accounting and Financial Management
Paper 10 Cost & Management Accounting and Financial Management Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Paper 10 Cost & Management
More informationStandard Costing and Budgetary Control CA
Standard Costing and Budgetary Control CA Past Years Exam Answers Answer to Q.1 (Nov, 2008) SP SQAO M 1 ` 6/kg. 500 kgs. = ` 3,000 SP AQ M 2 ` 6/kg. 450 kgs. = ` 2,700 AP AQ M 3 ` 8/kg. 450 kgs. = ` 3,600
More informationINTER CA MAY COSTING Topic: Standard Costing, Budgetary Control, Integral and Non Integral, Materials, Marginal Costing.
INTER CA MAY 218 COSTING Topic: Standard Costing, Budgetary Control, Integral and Non Integral, Materials, Marginal Costing. Note: All questions are compulsory. Test Code M33 Branch: MULTIPLE Date: 21.1.218
More informationWrite your answers in blue or black ink/ballpoint. You can only use pencil for graphs, charts, diagrams, etc.
Cost Accounting ASE3017 Level 3 Wednesday 3 April 2013 Time allowed: 3 hours Information There are 5 questions in this examination. Total marks available: 100 All questions carry equal marks. Instructions
More informationPAPER 10- COST & MANAGEMENT ACCOUNTANCY
PAPER 10- COST & MANAGEMENT ACCOUNTANCY Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Paper 10 - Cost & Management Accountancy Full
More informationTrainee Accountant Webinar. F2 Management Accounting. Variance Analysis
Trainee Accountant Webinar F2 Management Accounting Variance Analysis Presented By: Rosemarie Kelly, Examiner CPA Ireland Skillnet CPA Ireland Skillnet, is a training network that is funded by Skillnets,
More informationAnalysing costs and revenues
Osborne Books Tutor Zone Analysing costs and revenues Practice assessment 1 Osborne Books Limited, 2013 2 a n a l y s i n g c o s t s a n d r e v e n u e s t u t o r z o n e This assessment relates to
More informationStudy the REQUIRED section of each question carefully and extract the data required for your answers from the information supplied.
Series 4 Examination 2010 COST ACCOUNTING Level 3 Monday 6 December Subject Code: 3717/S Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer all 5 questions. All questions carry equal marks. Study
More informationAFM481 - Advanced Cost Accounting Professor Grant Russell Final Exam Material Chapter 11 & 13. Chapter 11: Standard Costs and Variance Analysis
AFM481 - Advanced Cost Accounting Professor Grant Russell Final Exam Material Chapter 11 & 13 Chapter 11: Standard Costs and Variance Analysis Variance Analysis: calculating variances and investigating
More informationAAT Management Accouting: Decision & Control ERRATA SHEET
AAT Management Accouting: Decision & Control ERRATA SHEET Course Book First Edition June 2016 Chapter 4: Illustration 2 (p.87) The direct labour rate variance to reconcile back to the total labour cost
More informationUNIVERSITY OF BOLTON BUSINESS SCHOOL ACCOUNTANCY SEMESTER 1 EXAMINATION 2015/2016 MANAGEMENT ACCOUNTING AND DECISION MAKING MODULE NO: ACC5002
BBS009 UNIVERSITY OF BOLTON BUSINESS SCHOOL ACCOUNTANCY SEMESTER 1 EXAMINATION 2015/2016 MANAGEMENT ACCOUNTING AND DECISION MAKING MODULE NO: ACC5002 Date: Tuesday 12 th January 2016 Time: 2:00pm to 5:00pm
More informationAnalysing financial performance
Osborne Books Tutor Zone Analysing financial performance Chapter activities Osborne Books Limited, 2013 2 a n a l y s i n g f i n a n c i a l p e r f o r m a n c e t u t o r z o n e 1 Management accounting
More informationSERIES 4 EXAMINATION 2001 MANAGEMENT ACCOUNTING THIRD LEVEL. (Code No: 3023) TUESDAY 13 NOVEMBER
SERIES 4 EXAMINATION 2001 MANAGEMENT ACCOUNTING THIRD LEVEL (Code No: 3023) TUESDAY 13 NOVEMBER Instructions to Candidates (d) (e) (f) (g) The time allowed for this examination is 3 hours. Answer 5 questions.
More informationMultiple Choice Questions
Multiple Choice Questions 1. The difference between the actual price and the standard price, multiplied by the actual quantity of materials purchased is the a) direct labor price variance b) direct labor
More informationPAPER 15 - BUSINESS STRATEGY & STRATEGIC COST MANAGEMENT
PAPER 15 - BUSINESS STRATEGY & STRATEGIC COST MANAGEMENT Page 1 LEVEL C The following table lists the learning objectives and the verbs that appear in the syllabus learning aims and examination questions:
More informationSCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016
All Rights Reserved No. of Pages - 17 No of Questions - 07 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 AFM 31130 Strategic
More informationLCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017)
LCCI International Qualifications Cost Accounting Level 3 Model Answers Series 4 2009 (3017) For further information contact us: Tel. +44 (0) 8707 202909 Email. enquiries@ediplc.com www.lcci.org.uk Cost
More informationDefinition of Standard Costing
Standard Costing Cost control leads to cost reduction which is the objective of every firm that is in business. The essence of standard costing is to Set target of costs Try to achieve these targets Compare
More informationNVQ/SVQ Level 4 in Accounting Contributing to the Planning and Control of Resources (PCR) (2003 standards) EXAMINATION
NVQ/SVQ Level 4 in Accounting Contributing to the Planning and Control of Resources (PCR) (2003 standards) Thursday 15 June 2006 (morning) EXAMINATION Time allowed - 3 hours plus 15 minutes reading time
More information2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL
EXAMINATION NO. 2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL THURSDAY 2 JUNE 2016 TIME ALLOWED : 3 HOURS 9.00 AM - 12.00 NOON INSTRUCTIONS 1. You are allowed
More informationMOCK TEST PAPER 1 INTERMEDIATE (IPC): GROUP I PAPER 3: COST ACCOUNTING AND FINANCIAL MANAGEMENT PART I : COST ACCOUNTING
MOCK TEST PAPER 1 INTERMEDIATE (IPC): GROUP I Test Series: February, 2014 PAPER 3: COST ACCOUNTING AND FINANCIAL MANAGEMENT PART I : COST ACCOUNTING Question No. 1 is compulsory. Attempt any five questions
More informationACCY 121 Chapter 16 Practice Quiz Fundamentals of Variance Analysis (1)
ACCY 121 Chapter 16 Practice Quiz Fundamentals of Variance Analysis (1) 101. The Hageness Company has had great difficulty in controlling overhead costs. At a recent convention, the president heard about
More informationPTP_Intermediate_Syllabus 2008_Jun2015_Set 3
Paper 8: Cost & Management Accounting Time Allowed: 3 Hours Full Marks: 100 Question No 1 is Compulsory. Answers any five Questions from the rest. Working Notes should form part of the answer. Question.1
More informationMTP_Intermediate_Syllabus 2016_Dec2017_Set 1 Paper 8 Cost Accounting
Paper 8 Cost Accounting Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Paper 8 Cost Accounting Full Marks : 100 Time allowed: 3 hours
More informationCost Accounting. Level 3. Model Answers. Series (Code 3616) 1 ASE /2/06
Cost Accounting Level 3 Model Answers Series 2 2006 (Code 3616) 1 ASE 3016 2 06 3 3616/2/06 >f0t@w?h2`?[6zbk0j3d# Certificate in Cost Accounting Level 3 - Malaysia Series 2 2006 How to use this booklet
More informationBudget & Budgetary Control
4 Budget & Budgetary Control Question 1 A Company manufactures two Products A and B by making use of two types of materials, viz., X and Y. Product A requires 10 units of X and 3 units of Y. Product B
More informationCERTIFICATE IN MANAGEMENT ACCOUNTING
Series 2 Examination 2007 CERTIFICATE IN MANAGEMENT ACCOUNTING Level 3 Tuesday 29 May Subject Code: 3623/M Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal
More informationAnalysing financial performance
NEW for 2015 Osborne Books Tutor Zone Analysing financial performance Exam preparation exercises I n t r o d u c t i o n These questions have been written as practice for selected numerical tasks from
More informationModule 3 Introduction
Module 3 Introduction Module 3 Introduction This module is designed to further enhance knowledge about management accounting techniques. In particular, the student is introduced to the role of budgeting,
More informationFlexible Budgets and Standard Costing Variance Analysis
Flexible Budgets and Standard Costing Variance Analysis 1 Static Budgets and Performance Reports CheeseCo 2 Preparing a Flexible Budget Cost Total Flexible Budgets Formula Fixed 8,000 10,000 12,000 per
More informationFlexible Budgets. and Standard Costing Variance Analysis. Static Budgets and Performance Reports. Flexible Budget Performance Report
Static Budgets and Performance Reports Flexible Budgets CheeseCo and Standard Costing Variance Analysis 1 2 Preparing a Flexible Budget Cost Total Flexible Budgets Formula Fixed 8,000 10,000 12,000 per
More informationChapter 11 BUDGETING. 1. Introduction. 2. Benefits of budgeting. 3. Principal budget factor
September-December 2016 Examinations ACCA F5 41 Chapter 11 BUDGETING 1. Introduction Budgeting is an essential tool for the management accounting in both planning and controlling future activity. In this
More informationBoth Isitya and Ikopi renders more net profit after further processing and should therefore be processed further.
OCT/NOV MAC2601 1.1 C Units purchased: 1 200 units Purchase price R6.80 Freight charges 0.68 Total 7.48 Value is therefore equal to 1200 units*7.48=r8 976 1.2 B 1.3 B 200 000 / 40 000 = R5 per machine
More informationLecture 16 Flexible Budgets and Variance Analysis
Economics, Management and Entrepreneurship Prof. Pratap K. J. Mohapatra Department of Industrial Engineering & Management Indian Institute of Technology - Kharagpur Lecture 16 Flexible Budgets and Variance
More informationManagement Accounting
Model Answers for Management Accounting THIRD LEVEL Series 2 2002 (Code 3023) LCCI Examinations Board ASP M 1147 >f0t@wjy2[2`ed:yed# Management Accounting Third Level Series 2 2002 How to use this booklet
More informationCOSTING IPCC PAPER 6: ALL CHAPTERS MARKS : 100 ; TIME : 3 Hours ; Level of Test : Level D out of D. Q1 (a) Solve the following:
COSTING IPCC PAPER 6: ALL CHAPTERS MARKS : 100 ; TIME : 3 Hours ; Level of Test : Level D out of D. Q1 (a) Solve the following: [10 Marks]. Dipu Construction Ltd. commenced a contract on November 01, 2003.
More informationRevision of management accounting
1 Revision of management accounting The following topics are covered in this chapter: Standard costing Flexible budgeting Absorption and marginal costing 1.1 STANDARD COSTING LEARNING SUMMARY After studying
More informationManagement Accounting
Management Accounting Level 3 Model Answers Series 4 2007 (Code 3023) Vision Statement Our vision is to contribute to the achievements of learners around the world by providing integrated assessment and
More informationHigher National Diploma in Accountancy Third Year, First Semester Examination 2014 DA3101-Advanced Management Accounting
[All Rights Reserved] SLIATE SLIAE SRI LANKA INSTITUTE OF ADVANCED TECHNOLOGICAL EDUCATION (Established in the Ministry of Higher Education, vide in Act No. 29 of 1995) Higher National Diploma in Accountancy
More information(59) MANAGEMENT ACCOUNTING & BUSINESS FINANCE
All Rights Reserved THE ASSOCIATION OF ACCOUNTING TECHNICIANS OF SRI LANKA FINAL EXAMINATION JULY 2013 (59) MANAGEMENT ACCOUNTING & BUSINESS FINANCE Time: 03 hours Instructions to candidates: (1) This
More informationB.COM. Part-III (HONS.) Sub. : ADVANCE COST ACCOUNTING MODAL PAPER-I. Time Allowed: 3 Hour Max. Marks: 100
B.COM. Part-III (HONS.) Sub. : ADVANCE COST ACCOUNTING MODAL PAPER-I Time Allowed: 3 Hour Max. Marks: 100 Q1 (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) Answers the following questions each having
More informationMTP_Intermediate_Syl2016_June2018_Set 1 Paper 8- Cost Accounting
Paper 8- Cost Accounting DoS, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Cost Accounting Full Marks: 100 Time allowed: 3 hours Section- A Answer the following
More informationRupees Product RAX (552,000 x Rs.360) 198,720,
Question No. 2 (a) Break-even Sales Revenue: SUGGESTED SOLUTIONS/ ANSWERS SPRING 2017 EXAMINATIONS 1 of 8 Calculation of total contribution: Product RAX (552,000 x Rs.216) 119,232,000 0.5 Product MAX (1,200,000
More informationPlease ensure your answers are written clearly, or marks may be lost. Do NOT open this paper until you are told to do so by the supervisor.
Cost Accounting ASE3017 Level 3 Tuesday 19 November 2013 Time allowed: 3 hours Information There are 5 questions in this examination. Total marks available: 100 All questions carry equal marks. Please
More informationElements of costing (ELCO) Question and answer book
Elements of costing (ELCO) Question and answer book October 2018 AAT is a registered charity. No. 1050724 Questions Question 1 If the total cost of 3,000 units is 6,750 and the total cost of 3,900 units
More informationMANAGEMENT ACCOUNTING
SERIES 4 EXAMINATION 2004 MANAGEMENT ACCOUNTING LEVEL 3 (Code No: 3023) FRIDAY 19 NOVEMBER Instructions to Candidates (d) (e) (f) (g) The time allowed for this examination is 3 hours. Answer 5 questions.
More informationSOLUTION COST AND MANAGEMENT NOV 2010
SOLUTION COST AND MANAGEMENT NOV 2010 (a) (A) The Cost Accountant provides financial information for stock valuation purposes and also presents relevant information to management for decision-making and
More informationMTP_Intermediate_Syl2016_June2017_Set 1 Paper 8- Cost Accounting
Paper 8- Cost Accounting Page 1 Page 1 Paper-8: Cost Accounting Full Marks: 100 Time allowed:3 hours Section A Answer the following questions: 1. Choose the correct answer from the given four alternatives:
More informationExaminations for Academic Year 2017 Semester I / Academic Year 2016/2017 Semester II
Programme BSc (Hons) Human Resource Management BSc (Hons) Management (L+G+F+M) Diploma in Procurement and Supply Management COHORT BHRM/12B/13B/14B/ 15A/16A/15B/FT/PT BMANG/F/L/M/12B/13A/ 13B/14A/14B/15A/15B/1
More informationExaminations for 2013/2014 Semester I & 2013 Semester II
Programme MA in Educational Leadership and Management MSc Educational Administration and Technology Cohort MEL/12B/PT Year 2 MET/12B/PT Year 2 Examinations for 2013/2014 Semester I & 2013 Semester II MODULE:
More informationSUGGESTED SOLUTION INTERMEDIATE M 19 EXAM
SUGGESTED SOLUTION INTERMEDIATE M 19 EXAM SUBJECT- COSTING Test Code - PIN 5043 M BRANCH - () (Date :) Head Office : Shraddha, 3 rd Floor, Near Chinai College, Andheri (E), Mumbai 69. Tel : (022) 26836666
More information