1 Page 1 of 7 Question 1 Mynor Corporation manufactures and sells a seasonal product that has peak sales in the third quarter. The following information concerns operation for Year 2-the coming year-and for the first two quarters of Year 3: a. The company s single product sells for $8 per unit. Budgeted sales in units for the next six quarters are as follows (all sales are on credit): Budgeted Sales (Units) Year 2 Year 3 Q1 Q2 Q3 Q4 Q1 Q2 40,000 60, ,000 50,000 70,000 80,000 b. Sales are collected in the following pattern: 75% in the quarter the sales are made, and the remaining 25% in the following quarter. On January 1, Year 2, the company s balance sheet showed $65,000 in accounts receivable, all of which will be collected in the first quarter of the year. Bad debts are negligible and can be ignored. c. The company desires an ending inventory finished goods inventory at the end of each quarter equal to 30% of the budgeted sales in units for the next quarter. On December 31, Year 1, the company had 12,000 units on hand. d. Five pounds of raw materials are required to complete one unit of product. The company requires ending raw materials inventory at the end of each quarter equal to 10% of the following quarter s production needs. On December 31, Year 1, the company had 23,000 pounds of raw materials on hand. e. The raw material costs $0.80 per pound. Raw material purchases are paid for in the following pattern: 60% paid in the quarter the purchases are made, and the remaining 40% paid in the following quarter. On January 1, Year 2, the company s balance sheet showed $81,500 in accounts payable for raw material purchases, all of which will be paid for in the first quarter of the year. Prepare the following budgets for the year, showing both quarterly and total figures: 1. A sales budget and a cash receipts budget for expected cash collections. 2. A production budget. 3. A direct material budget in pounds and a cash payment budget for purchases of materials.

2 Page 2 of 7 Question 2 Powerpac Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent Hi300 are required to manufacture each unit of Superman, one of the company s products. The company is now planning raw materials needs for the third quarter and September is the month in which peak sales of Superman occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each month must be equal to 3,000 units of Superman plus 20% of the next month s sales. The finished goods inventory on June 30 is budgeted to be 10,000 units. b. The raw materials inventory on hand at the end of each month must be equal to onehalf of the following month s production needs for raw materials. The raw materials inventory on June 30 is budgeted to be 54,000 cc of solvent of Hi300. c. The company maintains no work in process inventories. d. A sales budget for Superman for the last six months of the year follows. Month Budgeted sales in units July 35,000 August 40,000 September 50,000 October 30,000 November 20,000 December 10, Prepare a production budget for Superman for the months of July to October. 2. Examine the production budget and comment why the company produce more units than it sells in July and August and fewer units than it sells in September and October. 3. Prepare a direct material budget showing the quantity of solvent Hi300 to be purchased for July, August and September and for the third quarter.

3 Page 3 of 7 Question 3 Willison Company produces stuffed toy animals, one of these is Betty Rabbit. Each rabbit takes 0.2 yards of fabric and six ounces of polyfiberfill. Fabric costs $3.50 per yard and polyfiberfill is $0.05 per ounce. Willison has budgeted production of stuffed rabbits for the next four months as follows: October 20,000 November 40,000 December 25,000 January 30,000 Inventory policy require that sufficient fabric be in ending monthly inventory to satisfy 15% of the following month s production needs and sufficient polyfiberfill be in inventory to satisfy 30% of the following month s production needs. Inventory of fabric and polyfiberfill at the beginning of October equals exactly the amount needed to satisfy the inventory policy. Each rabbit produced requires on average 0.10 direct labour hour and the average cost of direct labour is $15.50 per hour. 1. Prepare a direct material budget of fabric for the last quarter of the year, showing purchases in units and in dollars for each month and for the quarter in total. 2. Prepare a direct materials budget of polyfiberfill for the last quarter of the year, showing purchases in units and in dollars for each month and for the quarter in total. 3. Prepare a direct labour budget for the last quarter of the year, showing the hours needed and the direct labour cost for each month and for the quarter in total.

4 Page 4 of 7 Question 4 Allison Manufacturing produces a subassembly used in the production of jet aircraft engines. The assembly is sold to engine manufacturers and aircraft maintenance facilities. Projected sales in units for the coming five months follow: January 40,000 February 50,000 March 60,000 April 60,000 May 62,000 The following data pertains to production policies and manufacturing specifications followed by Allison Manufacturing: a. The finished goods inventory on January 1 is 32,000 units, each costing $ The desired ending inventory for each month is 80% of the next month s sales. b. The data on materials used are as follows: Direct material Usage Per-Unit of Cost of direct material Production Metal 10 lbs $8/lbs s 6 units $5/unit Inventory policy dictates that sufficient materials be on hand at the end of the month to produce 50% of the next month s production needs. This is exactly the amount of material on hand on December 31 of the prior year. c. The direct labour used per unit of output is three hours. The average direct labour cost per hour is $ d. Manufacturing overhead each month is budgeted using direct labour hours. Manufacturing overhead Fixed-Cost ($) Variable-Cost ($/direct labour hour) Supplies Power Maintenance 30, Supervision 16,000 - Depreciation 200,000 - Taxes 12,000 - Others 80,

5 Page 5 of 7 e. Monthly variable selling and administrative expenses are budgeted using units sold. Fixed-Cost ($) Variable-Cost ($/unit sold) Salaries 50,000 - Commissions Depreciation 40,000 - Shipping Other 20, f. The unit selling price of the subassembly is $205. g. All sales and purchases are for cash in the same month. All expenses including direct labour, overhead and selling and administrative except for depreciation, are paid in the same month. The cash balance on January 1 equals $400,000. The firm requires a minimum ending balance of $50,000. If the firm develops cash shortage by the end of the month, sufficient cash is borrowed to cover the shortage. Any cash borrowed is repaid at the end of the quarter, as is the interest due (cash borrowed at the end of the quarter is repaid at the end of the following quarter). The interest rate is 12 percent per annum. No money is owed at the beginning of January. Prepare the following budgets for the first quarter showing both the monthly and total figures. Note: Assume that the company does not maintain any work in progress inventories. 1. Sales budget 2. Production budget 3. Direct material cost budget 4. Direct labour cost budget 5. Overhead budget 6. Selling and administrative expenses budget 7. Budgeted income statement (Hint: The finished goods inventory unit cost is given in part a of the question) 8. Cash budget

6 Page 6 of 7 QUESTION 5 TTC Manufacturing produces a subassembly used in the production of microchip testing machines. The subassembly is sold to manufacturers and chip testing facilities. Projected sales for the coming four months in 2012 follow: January 45,000 February 55,000 March 65,000 April 65,000 The following data pertains to production policies and manufacturing specifications followed by TTC Manufacturing: a) Finished goods inventory on 1 st January is 32,000 units. The desired ending finished goods inventory for each month is 80% of the next month s sales. b) The data on materials used are as follows: Direct Material Per-Unit Usage Cost per Kg ($) A 10 kg 8 B 6 kg 2 Inventory policy dictates that sufficient materials be held on hand at the beginning of the month to produce 50% of that month s estimated sales. This is exactly the amount of material on hand on 1 st January. c) The direct labour used per unit of output is 5 hours for January. There is labour efficiency improvement due to training and learning curve such that the direct labour hours used per unit would decrease by 10% from 1 st February. The average direct labour cost per hour is $9 for January. Due to organizational-wide salary review, the average direct labour cost per hour would increase by 5% with effect from 1 st February. d) Manufacturing overhead each month is estimated using the below formula. Activity is measured in direct labour hours. Manufacturing overhead Fixed-cost component ($) Variable-cost component per direct labour hour ($) Miscellaneous Supplies Utilities Repairs 300, Supervisory salary 160,000 - Depreciation 200,000 - Taxes 12,000 - Others 80, e) The unit selling price of the subassembly is $180.

7 Page 7 of 7 Prepare the following budgets by month for the first quarter: 1. Sales budget (in dollars). 2. Production budget (in units). 3. Direct material budget (in dollars). 4. Direct labour budget (in dollars). 5. Manufacturing-overhead budget (in dollars).

Spring Manufacturing Company Sales Budget 2007

Spring Manufacturing Company Sales Budget 2007 8-56 Comprehensive Profit Plan (90 minutes) 1. Sales Budget Sales Budget Sales (in units) 12,000 9,000 21,000 x Selling Price Per Unit $150 $220 Total Sales Revenue $1,800,000 $1,980,000 $3,780,000 2.

More information

VARIANCE ANALYSIS: ILLUSTRATION

VARIANCE ANALYSIS: ILLUSTRATION VARIANCE ANALYSIS: ILLUSTRATION The following information relates to the production of product Alpha for the month of August Standard Cost Card Budgeted production overhead based on 10,000 units $ $ Selling

More information

Preparing and using budgets

Preparing and using budgets Osborne Books Tutor Zone Preparing and using budgets Chapter activities Osborne Books Limited, 2013 2 p r e p a r i n g a n d u s i n g b u d g e t s t u t o r z o n e 1 The budgeting environment 1.1 Match

More information

January 10,000 units February 15,000 units. 15,000 units

January 10,000 units February 15,000 units. 15,000 units In Class #9.1 Prepare the sales budget Royal Company is preparing budgets for the quarter ending June 30 th. Actual sales for January to March are as follows: Month Sales Budget January 10,000 units February

More information

MANAGEMENT ACCOUNTING

MANAGEMENT ACCOUNTING Series 4 Examination 2009 MANAGEMENT ACCOUNTING Level 3 Tuesday 1 December Subject Code: 3724 S Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer all 5 questions. All questions carry equal marks.

More information

Code No. : Sub. Code : R 3 BA 52/ B 3 BA 52

Code No. : Sub. Code : R 3 BA 52/ B 3 BA 52 (8 pages) Reg. No. :... Sub. Code : R 3 BA 52/ B 3 BA 52 B.B.A. (CBCS) DEGREE EXAMINATION, NOVEMBER 2014. Fifth Semester Business Administration Main MANAGEMENT ACCOUNTING (For those who joined in July

More information

Chapter 16 Fundamentals of Variance Analysis

Chapter 16 Fundamentals of Variance Analysis Chapter 16 Fundamentals of Variance Analysis True / False Questions 1. In essence, the terms "master budget" and "operating budget" mean the same thing and can be used interchangeably. True False 2. Variances

More information

WEEK 6 OPERATING BUDGETS (MANUFACTURING ORGANISATIONS) Case Study. The budgets that you need to prepare include:

WEEK 6 OPERATING BUDGETS (MANUFACTURING ORGANISATIONS) Case Study. The budgets that you need to prepare include: WEEK 6 OPERATING BUDGETS (MANUFACTURING ORGANISATIONS) Case Study manufactures cardboard boxes which are used for transporting very special toys to toy stores all around Australia. You have already been

More information

Flexible Budgets and Standard Costing Variance Analysis

Flexible Budgets and Standard Costing Variance Analysis Flexible Budgets and Standard Costing Variance Analysis 1 Static Budgets and Performance Reports CheeseCo 2 Preparing a Flexible Budget Cost Total Flexible Budgets Formula Fixed 8,000 10,000 12,000 per

More information

Flexible Budgets. and Standard Costing Variance Analysis. Static Budgets and Performance Reports. Flexible Budget Performance Report

Flexible Budgets. and Standard Costing Variance Analysis. Static Budgets and Performance Reports. Flexible Budget Performance Report Static Budgets and Performance Reports Flexible Budgets CheeseCo and Standard Costing Variance Analysis 1 2 Preparing a Flexible Budget Cost Total Flexible Budgets Formula Fixed 8,000 10,000 12,000 per

More information

BUDGETING AND PROFIT PLANNING

BUDGETING AND PROFIT PLANNING BUDGETING AND PROFIT PLANNING Key Terms and Concepts to Know Profit Planning and Budgeting: Profit plan is the steps taken by the business to achieve their planned levels of profits. Budget is a quantitative

More information

ACCA. Paper F2 and FMA. Management Accounting December 2014 to June Interim Assessment Answers

ACCA. Paper F2 and FMA. Management Accounting December 2014 to June Interim Assessment Answers ACCA Paper F2 and FMA Management Accounting December 204 to June 205 Interim Assessment Answers To gain maximum benefit, do not refer to these answers until you have completed the interim assessment questions

More information

Examinations for Academic Year Semester I / Academic Year 2015 Semester II. 1. This question paper consists of Section A and Section B.

Examinations for Academic Year Semester I / Academic Year 2015 Semester II. 1. This question paper consists of Section A and Section B. PROGRAMME COHORT BSc (Hons) Human Resource Management BSc (Hons) Management BHRM/14B/FT BMAN/15A/FT B1, B2 Examinations for Academic Year 2015 2016 Semester I / Academic Year 2015 Semester II MODULE: COST

More information

Let s trace the budgets through for a company called the Hayes Company. Sales Budget The first budget prepared, comes from the Sales Forecast

Let s trace the budgets through for a company called the Hayes Company. Sales Budget The first budget prepared, comes from the Sales Forecast Let s trace the budgets through for a company called the Hayes Company. Sales Budget The first budget prepared, comes from the Sales Forecast Expected sales volume: 3,000 units in the first quarter with

More information

Budgeting. MCQs. Gleim Book. Gleim CD. IMA - Retired IMA - Retired Contains: in a random basis. By: Mohamed hengoo to dvd4arab.

Budgeting. MCQs. Gleim Book. Gleim CD. IMA - Retired IMA - Retired Contains: in a random basis. By: Mohamed hengoo to dvd4arab. Budgeting MCQs Contains: in a random basis Gleim Book Gleim CD IMA - Retired 2005 IMA - Retired 2008 By: Mohamed hengoo to dvd4arab.com members [1] Gleim #: 2.4.208 -- Source: CIA 589 IV-12 A company has

More information

Flexible Budgets and Standard Costing QUESTIONS

Flexible Budgets and Standard Costing QUESTIONS Chapter 21 Flexible Budgets and Standard Costing QUESTIONS 1. Fixed budget performance reports have limited usefulness because they do not reflect differences in revenues and variable costs that can occur

More information

DO NOT OPEN THIS QUESTION PAPER UNTIL YOU ARE TOLD TO DO SO. Performance Pillar. P1 Performance Operations. Wednesday 27 August 2014

DO NOT OPEN THIS QUESTION PAPER UNTIL YOU ARE TOLD TO DO SO. Performance Pillar. P1 Performance Operations. Wednesday 27 August 2014 DO NOT OPEN THIS QUESTION PAPER UNTIL YOU ARE TOLD TO DO SO. Performance Pillar P1 Performance Operations Instructions to candidates Wednesday 27 August 2014 You are allowed three hours to answer this

More information

Performance Pillar. P1 Performance Operations. 24 November 2010 Wednesday Morning Session

Performance Pillar. P1 Performance Operations. 24 November 2010 Wednesday Morning Session Performance Pillar P1 Performance Operations 24 November 2010 Wednesday Morning Session Instructions to candidates You are allowed three hours to answer this question paper. You are allowed 20 minutes

More information

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc. Series 3 Examination 2008 COST ACCOUNTING Level 3 Friday 6 June Subject Code: 3016 Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your answers

More information

FNSACC503A: Assessment 2

FNSACC503A: Assessment 2 FNSACC503A: Assessment 2 What you have to do This assessment will test your understanding of budgeting principles and the preparation of sales budgets, operational budgets and cash budgets for a Manufacturing

More information

Costing and Estimating 1B Financial Principles in Production 1B BKM11B1, BKM1B00, CAE01B1 and FPP11B1

Costing and Estimating 1B Financial Principles in Production 1B BKM11B1, BKM1B00, CAE01B1 and FPP11B1 Department of Commercial Accounting Costing and Estimating 1B Financial Principles in Production 1B BKM11B1, BKM1B00, CAE01B1 and FPP11B1 LAST ASSESSMENT OPPORTUNITY November 2015 Time: 120 minutes Marks

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 17 No of Questions - 07 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 AFM 31130 Strategic

More information

P2 Performance Management

P2 Performance Management Performance Pillar P2 Performance Management 24 November 2010 Wednesday Afternoon Session Instructions to candidates You are allowed three hours to answer this question paper. You are allowed 20 minutes

More information

Planning and Control. Control involves the steps taken by management that attempt to ensure the objectives are attained.

Planning and Control. Control involves the steps taken by management that attempt to ensure the objectives are attained. Profit Planning Planning and Control Planning -- involves developing objectives and preparing various budgets to achieve these objectives. Control involves the steps taken by management that attempt to

More information

Budget & Budgetary Control

Budget & Budgetary Control 4 Budget & Budgetary Control Question 1 A Company manufactures two Products A and B by making use of two types of materials, viz., X and Y. Product A requires 10 units of X and 3 units of Y. Product B

More information

Analysing financial performance

Analysing financial performance NEW for 2015 Osborne Books Tutor Zone Analysing financial performance Exam preparation exercises I n t r o d u c t i o n These questions have been written as practice for selected numerical tasks from

More information

MONDAY, 18 MAY 9.00 AM AM

MONDAY, 18 MAY 9.00 AM AM X209/12/01 NATIONAL QUALIFICATIONS 2015 MONDAY, 18 MAY 9.00 AM 11.30 AM ACCOUNTING HIGHER Candidates should attempt six questions in total, as follows. Section A Question 1 and Question 2 or 3 and Question

More information

Final Examination Semester 2 / Year 2011

Final Examination Semester 2 / Year 2011 Southern College Kolej Selatan 南方学院 Final Examination Semester 2 / Year 2011 COURSE : BASIC COSTING COURSE CODE : ACCT2013 TIME : 2 1/2 HOURS DEPARTMENT : FINANCE AND ACCOUNTING LECTURER : GAN HWI SIN

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME All Rights Reserved No. of Pages - 12 No of Questions - 07 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME YEAR I SEMESTER I (Intake V Group A) END SEMESTER

More information

PAPER 3 : COST ACCOUNTING AND FINANCIAL MANAGEMENT PART I : COST ACCOUNTING QUESTIONS

PAPER 3 : COST ACCOUNTING AND FINANCIAL MANAGEMENT PART I : COST ACCOUNTING QUESTIONS PAPER 3 : COST ACCOUNTING AND FINANCIAL MANAGEMENT PART I : COST ACCOUNTING QUESTIONS Material 1. The following information has been extracted from the records of a cotton merchant, for the month of March,

More information

STANDARD COSTS AND VARIANCE ANALYSIS

STANDARD COSTS AND VARIANCE ANALYSIS STANDARD COSTS AND VARIANCE ANALYSIS Key Terms and Concepts to Know Static or Planning Budgets Used for planning purposes Prepared at the beginning of the period Based on one projected level of activity

More information

Ibrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing)

Ibrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing) Ibrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing) Variances A variance is the difference between a planned, budgeted, or standard cost and the actual cost incurred.

More information

EOQ = = = 8,000 units Reorder level Reorder level = Safety stock + Lead time consumption Reorder level = (ii)

EOQ = = = 8,000 units Reorder level Reorder level = Safety stock + Lead time consumption Reorder level = (ii) Model Test Paper - 1 IPCC Group- I Paper - 3 Cost Accounting and Financial Management May - 2017 1. (a) Primex Limited produces product P. It uses annually 60,000 units of a material Rex costing ` 10 per

More information

CERTIFICATE IN MANAGEMENT ACCOUNTING

CERTIFICATE IN MANAGEMENT ACCOUNTING Series 2 Examination 2007 CERTIFICATE IN MANAGEMENT ACCOUNTING Level 3 Tuesday 29 May Subject Code: 3623/M Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal

More information

(59) MANAGEMENT ACCOUNTING & BUSINESS FINANCE

(59) MANAGEMENT ACCOUNTING & BUSINESS FINANCE All Rights Reserved THE ASSOCIATION OF ACCOUNTING TECHNICIANS OF SRI LANKA FINAL EXAMINATION JULY 2013 (59) MANAGEMENT ACCOUNTING & BUSINESS FINANCE Time: 03 hours Instructions to candidates: (1) This

More information

SECTION I 14,000 14,200 19,170 10,000 8,000 10,400 12,400 9,600 8,400 11,200 13,600 18,320

SECTION I 14,000 14,200 19,170 10,000 8,000 10,400 12,400 9,600 8,400 11,200 13,600 18,320 QUESTION ONE SECTION I The following budget and actual results relates to Cypo Ltd. for the last three quarters for the year ended 31 March 200. Budget: Quarter 2 Quarter 3 Quarter to 30/9/2003 to 31/12/2003

More information

COMMERCE & LAW PROGRAM DIVISION (CLPD) ANSWER KEY TO CS-EXECUTIVE DECEMBER-2014 (ATTEMPT) CODE-C SUBJECT : COST & MANAGEMENT ACCOUNTING

COMMERCE & LAW PROGRAM DIVISION (CLPD) ANSWER KEY TO CS-EXECUTIVE DECEMBER-2014 (ATTEMPT) CODE-C SUBJECT : COST & MANAGEMENT ACCOUNTING COMMERCE & LAW PROGRAM DIVISION (CLPD) ANSWER KEY TO CS-EXECUTIVE DECEMBER-2014 (ATTEMPT) CODE-C SUBJECT : COST & MANAGEMENT ACCOUNTING 1. If the minimum stock level and average stock level of raw material

More information

Fill-in-the-Blank Equations. Exercises

Fill-in-the-Blank Equations. Exercises Chapter 26 Cost Allocation and Activity-Based Costing Study Guide Solutions Fill-in-the-Blank Equations 1. Total budgeted plantwide allocation base 2. Department factory overhead rate 3. Ratio of allocation

More information

MOCK EXAMINATION PRINCIPLES OF ACCOUNTS A-LEVEL PAPER 2

MOCK EXAMINATION PRINCIPLES OF ACCOUNTS A-LEVEL PAPER 2 HONG KONG ASSOCIATION FOR BUSINESS EDUCATION HONG KONG INSTITUTE OF VOCATIONAL EDUCATION (CHAI WAN & TUEN MUN) HONG KONG ADVANCED LEVEL EXAMINATION 2009 MOCK EXAMINATION PRINCIPLES OF ACCOUNTS A-LEVEL

More information

Management Accounting. Pilot Paper 3 Questions and Suggested Solutions

Management Accounting. Pilot Paper 3 Questions and Suggested Solutions Management Accounting Pilot Paper 3 Questions and Suggested Solutions NOTES TO USERS ABOUT PILOT PAPERS Pilot papers are published by Accounting Technicians Ireland. They are intended to provide guidance

More information

Historical information collected from a research in relation to sales of a company are as follows. Year Cost of promotion Sales revenue

Historical information collected from a research in relation to sales of a company are as follows. Year Cost of promotion Sales revenue Question bank 05-SA- English Short Answer Questions Question 01 Activity based costing system is used to allocate fixed production overhead in a more representative manner. Explain following terms in relation

More information

2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL

2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL EXAMINATION NO. 2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL THURSDAY 2 JUNE 2016 TIME ALLOWED : 3 HOURS 9.00 AM - 12.00 NOON INSTRUCTIONS 1. You are allowed

More information

THE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL

THE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL EXAMINATION NO. THE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL MONDAY 2 JUNE 2014 TIME ALLOWED: 3 HOURS

More information

Disclaimer: This resource package is for studying purposes only EDUCATIO N

Disclaimer: This resource package is for studying purposes only EDUCATIO N Disclaimer: This resource package is for studying purposes only EDUCATIO N Chapter 9: Budgeting The Basic Framework of Budgeting Master budget - a summary of a company s plans in which specific targets

More information

(AA32) MANAGEMENT ACCOUNTING AND FINANCE

(AA32) MANAGEMENT ACCOUNTING AND FINANCE All Rights Reserved ASSOCIATION OF ACCOUNTING TECHNICIANS OF SRI LANKA AA3 EXAMINATION - JULY 2015 (AA32) MANAGEMENT ACCOUNTING AND FINANCE Instructions to candidates (Please Read Carefully): (1) Time:

More information

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017)

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017) LCCI International Qualifications Cost Accounting Level 3 Model Answers Series 3 2009 (3017) For further information contact us: Tel. +44 (0) 8707 202909 Email. enquiries@ediplc.com www.lcci.org.uk Cost

More information

Chapter 10 Standard Costs and Variances

Chapter 10 Standard Costs and Variances Chapter 10 Standard Costs and Variances Solutions to Questions 10-1 A quantity standard indicates how much of an input should be used to make a unit of output. A price standard indicates how much the input

More information

(AA22) COST ACCOUNTING AND REPORTING

(AA22) COST ACCOUNTING AND REPORTING All Rights Reserved ASSOCIATION OF ACCOUNTING TECHNICIANS OF SRI LANKA AA2 EXAMINATION - JULY 2016 (AA22) COST ACCOUNTING AND REPORTING Instructions to candidates (Please Read Carefully): (1) Time Allowed:

More information

namibia UniVERSITY OF SCIEnCE AnD TECHnOLOGY FACULTY OF MANAGEMENT SCIENCES DEPARTMENT OF ACCOUNTING, ECONOMICS & FINANCE

namibia UniVERSITY OF SCIEnCE AnD TECHnOLOGY FACULTY OF MANAGEMENT SCIENCES DEPARTMENT OF ACCOUNTING, ECONOMICS & FINANCE namibia UniVERSITY OF SCIEnCE AnD TECHnOLOGY FACULTY OF MANAGEMENT SCIENCES DEPARTMENT OF ACCOUNTING, ECONOMICS & FINANCE QUALIFICATION: BACHELOR OF ECONOMICS AND BACHELOR OF BUSINESS ADMINISTRATION QUALIFICATION

More information

Chapter # 8. Material Costing Material Losses. Sameer Hussain.

Chapter # 8. Material Costing Material Losses. Sameer Hussain. Material Costing Material Losses Syllabus ACCORDING TO UNIVERSITY OF KARACHI: Accounting for: o Waste and scrap materials. o Spoil and defective works. WHAT THE EXAMINER USUALLY ASK? Defective goods: o

More information

Manufacturing Accounts

Manufacturing Accounts All questions copyright of Cambridge International Examinations 1 Manufacturing Accounts All questions copyright of Cambridge International Examinations 2 2 1 The following balances were extracted from

More information

Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 4 Job Costing

Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 4 Job Costing Cost Accounting: A Managerial Emphasis, 16e, Global Edition (Horngren) Chapter 4 Job Costing 4.1 Objective 4.1 1) A cost is considered direct if it can be traced to a particular cost object in a cost effective

More information

Answer to MTP_Intermediate_Syllabus 2008_Jun2014_Set 1

Answer to MTP_Intermediate_Syllabus 2008_Jun2014_Set 1 Paper-8: COST & MANAGEMENT ACCOUNTING SECTION - A Answer Q No. 1 (Compulsory) and any 5 from the rest Question.1 (a) Match the statement in Column 1 with the most appropriate statement in Column 2 : [1

More information

322 Roll No : 1 : Time allowed : 3 hours Maximum marks : 100

322 Roll No : 1 : Time allowed : 3 hours Maximum marks : 100 2/2013/CMA (N/S) Roll No : 1 : Time allowed : 3 hours Maximum marks : 100 Total number of questions : 6 Total number of printed pages : 7 NOTE : 1. Answer ALL Questions. 2. All working notes should be

More information

SAPAN PARIKH COMMERCE CLASSES

SAPAN PARIKH COMMERCE CLASSES CHAPTER WISE BOARD QUESTION PAPER MARGINAL COSTING MARGINAL COSTING - CVP Q.1. A Company produces and sells a single article at `10 each. The marginal cost of production is `6 each and fixed cost is `400

More information

ICAN MID DIET LIVE CLASS FOR MAY DIET 2015 PERFORMANCE MANAGEMENT

ICAN MID DIET LIVE CLASS FOR MAY DIET 2015 PERFORMANCE MANAGEMENT ICAN MID DIET LIVE CLASS FOR MAY DIET 2015 PERFORMANCE MANAGEMENT PERFORMANCE MEASUREMENT NON- FINANCIAL MEASUREMENT PERFOMANCE MEASUREMENT OF A NON- PROFIT ORGANISATION DIVISIONAL PERFORMANCE MEASURE

More information

Cost Accounting. Level 3. Model Answers. Series (Code 3016)

Cost Accounting. Level 3. Model Answers. Series (Code 3016) Cost Accounting Level 3 Model Answers Series 2 2008 (Code 3016) Vision Statement Our vision is to contribute to the achievements of learners around the world by providing integrated assessment and learning

More information

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc. Series 2 Examination 2008 COST ACCOUNTING Level 3 Tuesday 27 May Subject Code: 3616/M Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your answers

More information

MTP_Intermediate_Syllabus 2016_Dec2017_Set 1 Paper 8 Cost Accounting

MTP_Intermediate_Syllabus 2016_Dec2017_Set 1 Paper 8 Cost Accounting Paper 8 Cost Accounting Academics Department, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Paper 8 Cost Accounting Full Marks : 100 Time allowed: 3 hours

More information

CS Executive Programme Module - I December Paper - 2 : Cost and Management Accounting

CS Executive Programme Module - I December Paper - 2 : Cost and Management Accounting ISBN : 978-93-5034-747-8 Solved Scanner Appendix CS Executive Programme Module - I December - 2013 Paper - 2 : Cost and Management Accounting Chapter - 1 : Introduction to Cost and Management Accounting

More information

Chapter 7 Solutions: 7-5

Chapter 7 Solutions: 7-5 Chapter 7 Solutions: 7-5 7 5 1. A llocation ratios: Traditional Gel Machine hours 0.2500 0.7500 Square feet 0.6000 0.4000 No. of employees 0.5625 0.4375 Cost assignment: Power: (0.2500 $90,000) $ 22,500

More information

24 Control through standard costs

24 Control through standard costs 24 Control through standard costs 24.1 Learning objectives After studying this chapter, you should be able to: Discuss the nature of standard costs, including how standards are set. Define budgets and

More information

(a) Calculate planning and operating variances following the recognition of the learning curve effect. (6 marks)

(a) Calculate planning and operating variances following the recognition of the learning curve effect. (6 marks) SECTION A 50 MARKS Question One (a) Calculate planning and operating variances following the recognition of the learning curve effect. (6 marks) Flexed budget Actual output Revised flexed budget Output

More information

2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL

2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL EXAMINATION NO. 2016 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL FRIDAY 2 DECEMBER 2016 TIME ALLOWED: 3 HOURS 9.00 AM - 12.00 NOON INSTRUCTIONS 1. You are allowed

More information

ABOUT AVCORP INDUSTRIES INC. Avcorp designs and builds major airframe structures

ABOUT AVCORP INDUSTRIES INC. Avcorp designs and builds major airframe structures 2007 AVCORP Q1 ABOUT AVCORP INDUSTRIES INC. Avcorp designs and builds major airframe structures for some of the world s leading aircraft companies, including Boeing, Bombardier, and Cessna. With 50 years

More information

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017)

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017) LCCI International Qualifications Cost Accounting Level 3 Model Answers Series 3 2010 (3017) For further information contact us: Tel. +44 (0) 8707 202909 Email. enquiries@ediplc.com www.lcci.org.uk Cost

More information

COURSE CODE: AC 413 (M) 2012 UNIVERSITY OF SWAZILAND DEPARTMENT OF ACCOUNTING MAIN EXAMINATION PAPER ACCOUNTING I COURSE CODE

COURSE CODE: AC 413 (M) 2012 UNIVERSITY OF SWAZILAND DEPARTMENT OF ACCOUNTING MAIN EXAMINATION PAPER ACCOUNTING I COURSE CODE COURSE CODE: AC 413 (M) 2012 UNIVERSITY OF SWAZILAND DEPARTMENT OF ACCOUNTING MAIN EXAMINATION PAPER DEGREEIDIPLOMA AND YEAR OF STUDY TITLE OF PAPER B.COMMIV MANAGEMENT ACCOUNTING I COURSE CODE TIME ALLOWED

More information

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc. Series 4 Examination 2008 COST ACCOUNTING Level 3 Tuesday 11 November Subject Code: 3016 Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your

More information

P8_Practice Test Paper_Syl12_Dec2013_Set 1

P8_Practice Test Paper_Syl12_Dec2013_Set 1 Full Marks: 100 Paper 8 : Cost Accounting and Financial Management Time : 3 hours This question paper is divided into two sections, Section A- Cost Accounting (60 marks) and Section B - Financial Management

More information

Cost Accounting. Level 3. Model Answers. Series (Code 3016) 1 ASE /2/06

Cost Accounting. Level 3. Model Answers. Series (Code 3016) 1 ASE /2/06 Cost Accounting Level 3 Model Answers Series 2 2006 (Code 3016) 1 ASE 3016 2 06 1 3016/2/06 >f0t@w9w2`?[6zbkbwgc# Cost Accounting Level 3 Series 2 2006 How to use this booklet Model Answers have been developed

More information

Managerial Accounting (ACC 212) Uses of Accounting Information II (ACC 240)

Managerial Accounting (ACC 212) Uses of Accounting Information II (ACC 240) Managerial Accounting (ACC 212) Uses of Accounting Information II (ACC 240) Final Exam Review 1) Beginning Raw Materials Inventory $ 3,000 Ending Raw Materials Inventory 4,500 Purchases of Raw Materials

More information

UNIVERSITY OF CAMBRIDGE INTERNATIONAL EXAMINATIONS General Certificate of Education Advanced Level

UNIVERSITY OF CAMBRIDGE INTERNATIONAL EXAMINATIONS General Certificate of Education Advanced Level *8995523676* UNIVERSITY OF MRIGE INTERNTIONL EXMINTIONS General ertificate of Education dvanced Level OUNTING 9706/32 Paper 3 Multiple hoice October/November 2013 1 hour dditional Materials: Multiple hoice

More information

Analysing financial performance

Analysing financial performance Osborne Books Tutor Zone Analysing financial performance Practice assessment 1 Osborne Books Limited, 2013 2 a n a l y s i n g f i n a n c i a l p e r f o r m a n c e t u t o r z o n e Task 1 The following

More information

Paper F5. Performance Management. Monday 13 December Fundamentals Level Skills Module. The Association of Chartered Certified Accountants

Paper F5. Performance Management. Monday 13 December Fundamentals Level Skills Module. The Association of Chartered Certified Accountants Fundamentals Level Skills Module Performance Management Monday 13 December 2010 Time allowed Reading and planning: Writing: 15 minutes 3 hours ALL FIVE questions are compulsory and MUST be attempted. Formulae

More information

Standard Costing and Budgetary Control

Standard Costing and Budgetary Control Standard Costing and Budgetary Control CA Past Years Exam Questions Question : 1 (Nov, 2008) UV Limited presents the following information for November. Calculate the cost Variances. Budgeted production

More information

Budgeting planning. Breakers, Inc. is preparing budgets for the quarter ending June 30. Budgeted sales for the next five months are:

Budgeting planning. Breakers, Inc. is preparing budgets for the quarter ending June 30. Budgeted sales for the next five months are: Budgeting planning We use budgets as a target that we hope or expect to achieve. These are financial and non-financial in nature, but typically offer some quantitative measure We will begin by talking

More information

Online Course Manual By Craig Pence. Module 7

Online Course Manual By Craig Pence. Module 7 Online Course Manual By Craig Pence Copyright Notice. Each module of the course manual may be viewed online, saved to disk, or printed (each is composed of 10 to 15 printed pages of text) by students enrolled

More information

Paper 8- Cost Accounting

Paper 8- Cost Accounting Paper 8- Cost Accounting Dos, The Institute of Cost Accountants of India (Statutory Body under an Act of Parliament) Page 1 Paper 8- Cost Accounting Full Marks : 100 Time allowed: 3 hours Section A Question

More information

Chapter 11 Flexible Budgets and Overhead Analysis

Chapter 11 Flexible Budgets and Overhead Analysis Chapter 11 Flexible Budgets and Overhead Analysis Solutions to Questions 11-1 A static budget is a budget prepared for a single level of activity. The static budget is not adjusted even if the activity

More information

Free of Cost ISBN : Appendix. CMA (CWA) Inter Gr. II (Solution upto Dec & Questions of June 2013 included)

Free of Cost ISBN : Appendix. CMA (CWA) Inter Gr. II (Solution upto Dec & Questions of June 2013 included) Free of Cost ISBN : 978-93-5034-631-0 Appendix CMA (CWA) Inter Gr. II (Solution upto Dec. 2012 & Questions of June 2013 included) Paper - 8 : Cost and Management Accounting Chapter - 3 : Labour Accounting

More information

P1 Performance Operations September 2014 examination

P1 Performance Operations September 2014 examination Operational Level Paper P1 Performance Operations September 2014 examination Examiner s Answers Note: Some of the answers that follow are fuller and more comprehensive than would be expected from a well-prepared

More information

5 Budget & Budgetary Control

5 Budget & Budgetary Control 5 Budget & Budgetary Control 5.1 INTRODUCTION In your studies related to the previous stage of examinations, you were introduced to the concept of Budgeting and Budgetary Control. Having read that chapter

More information

Performance Pillar. P1 Performance Operations. 25 May 2011 Wednesday Morning Session

Performance Pillar. P1 Performance Operations. 25 May 2011 Wednesday Morning Session Performance Pillar P1 Performance Operations 25 May 2011 Wednesday Morning Session Instructions to candidates You are allowed three hours to answer this question paper. You are allowed 20 minutes reading

More information

DO NOT OPEN THIS QUESTION PAPER UNTIL YOU ARE TOLD TO DO SO. Performance Pillar. P1 Performance Operations. 22 May 2013 Wednesday Morning Session

DO NOT OPEN THIS QUESTION PAPER UNTIL YOU ARE TOLD TO DO SO. Performance Pillar. P1 Performance Operations. 22 May 2013 Wednesday Morning Session DO NOT OPEN THIS QUESTION PAPER UNTIL YOU ARE TOLD TO DO SO Performance Pillar P1 Performance Operations 22 May 2013 Wednesday Morning Session Instructions to candidates You are allowed three hours to

More information

Chapter 11 Standard Costs and Variance Analysis

Chapter 11 Standard Costs and Variance Analysis Chapter 11: Standard Costs and Variance Analysis 229 Chapter 11 Standard Costs and Variance Analysis LEARNING OBJECTIVES Chapter 11 addresses the following questions: LO1 LO2 LO3 LO4 LO5 LO6 LO7 LO8 Explain

More information

LO 1: Budgeting. Terms Budget Sales forecast Budget committee Participative budgeting Budgetary slack

LO 1: Budgeting. Terms Budget Sales forecast Budget committee Participative budgeting Budgetary slack Terms Budget Sales forecast Budget committee Participative budgeting Budgetary slack LO 1: Budgeting Long-range planning Master budget Operating budget Financial budget Benefits of Budgeting: Planning

More information

(AA22) COST ACCOUNTING AND REPORTING

(AA22) COST ACCOUNTING AND REPORTING All Rights Reserved ASSOCIATION OF ACCOUNTING TECHNICIANS OF SRI LANKA AA2 EXAMINATION - JANUARY 2017 (AA22) COST ACCOUNTING AND REPORTING Instructions to candidates (Please Read Carefully): (1) Time Allowed:

More information

F2 Management Accounting Mock Examination

F2 Management Accounting Mock Examination F2 Management Accounting Mock Examination Question Paper Time allowed 2 hours Section A ALL 35 questions are compulsory and MUST be answered Section B ALL THREE questions are compulsory and MUST be answered

More information

1,40,000 units ( 1,26,00,000 / 90)

1,40,000 units ( 1,26,00,000 / 90) C.A. FINAL Solution to Q. 1 (i) Statement of the Number of Units of the Product Proposed to be Sold (ii) Selling Price per unit 90 Total Sales Revenue 1,26,00,000 Number of Units of the Product (proposed

More information

CERTIFICATE IN MANAGEMENT ACCOUNTING

CERTIFICATE IN MANAGEMENT ACCOUNTING Series 2 Examination 2011 CERTIFICATE IN MANAGEMENT ACCOUNTING Level 3 Tuesday 12 April Subject Code: 3024 Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer all 5 questions. All questions carry

More information

SERIES 4 EXAMINATION 2001 MANAGEMENT ACCOUNTING THIRD LEVEL. (Code No: 3023) TUESDAY 13 NOVEMBER

SERIES 4 EXAMINATION 2001 MANAGEMENT ACCOUNTING THIRD LEVEL. (Code No: 3023) TUESDAY 13 NOVEMBER SERIES 4 EXAMINATION 2001 MANAGEMENT ACCOUNTING THIRD LEVEL (Code No: 3023) TUESDAY 13 NOVEMBER Instructions to Candidates (d) (e) (f) (g) The time allowed for this examination is 3 hours. Answer 5 questions.

More information

2017 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC 9: COSTING & BUDGETARY CONTROL

2017 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC 9: COSTING & BUDGETARY CONTROL EXAMINATION NO. 2017 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC 9: COSTING & BUDGETARY CONTROL THURSDAY 1 JUNE 2017 TIME ALLOWED: 3 HOURS 9.00 AM - 12.00 NOON INSTRUCTIONS 1. You are allowed

More information

Paper F5 ANSWERS TO EXAMPLES

Paper F5 ANSWERS TO EXAMPLES September-December 2016 Examinations ACCA F5 87 Paper F5 ANSWERS TO EXAMPLES Chapter 1 ANSWER TO EXAMPLE 1 (a) Total overheads $190,000 Total labour hours A 20,000 2 = 40,000 B 25,000 1 = 25,000 C 2,000

More information

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017)

LCCI International Qualifications. Cost Accounting Level 3. Model Answers Series (3017) LCCI International Qualifications Cost Accounting Level 3 Model Answers Series 2 2012 (3017) For further information contact us: Tel. +44 (0) 8707 202909 Email. enquiries@ediplc.com www.lcci.org.uk Cost

More information

standard usage of materials for actual production standard labour time for actual production ( ) x 27,500 = 5,500 (A)

standard usage of materials for actual production standard labour time for actual production ( ) x 27,500 = 5,500 (A) Contributing to the Management of Costs and Enhancement of Value (MCV) (1998 standards) / Management of Performance and Enhancement of Value (PEV) (2003 standards) Suggested Answers SECTION 1 Task 1.1

More information

Managerial Accounting (ACC 212) Uses of Accounting Information II (ACC 240)

Managerial Accounting (ACC 212) Uses of Accounting Information II (ACC 240) Managerial Accounting (ACC 212) Uses of Accounting Information II (ACC 240) Final Exam Review (Yellow) 1) Beginning Raw Materials Inventory $ 1 Ending Raw Materials Inventory 3 Purchases of Raw Materials

More information

Module 3 Introduction

Module 3 Introduction Module 3 Introduction Module 3 Introduction This module is designed to further enhance knowledge about management accounting techniques. In particular, the student is introduced to the role of budgeting,

More information

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc.

Write your answers in blue or black ink/ballpoint. Pencil may be used only for graphs, charts, diagrams, etc. Series 3 Examination 2007 COST ACCOUNTING Level 3 Tuesday 5 June Subject Code: 3716 (S) Time allowed: 3 hours INSTRUCTIONS FOR CANDIDATES Answer 5 questions. All questions carry equal marks. Write your

More information

Accounting Technicians Ireland 2 nd Year Examination: Autumn 2013 Paper: MANAGEMENT ACCOUNTING

Accounting Technicians Ireland 2 nd Year Examination: Autumn 2013 Paper: MANAGEMENT ACCOUNTING Accounting Technicians Ireland 2 nd Year Examination: Autumn 2013 Paper: MANAGEMENT ACCOUNTING Monday 26 th August 2013-2.30 p.m. to 5.30 p.m. INSTRUCTIONS TO CANDIDATES In this examination paper the /

More information

Standard Cost System Practice Problems

Standard Cost System Practice Problems When setting up a standard cost system, the concepts of standards in material, labor, and overhead must be explored in a simple manner to start the process. Practice Standard Cost Variances: Simple Example