Validation Report. Indonesia: Coral Reef Rehabilitation and Management Project Phase II. Independent Evaluation Department

Size: px
Start display at page:

Download "Validation Report. Indonesia: Coral Reef Rehabilitation and Management Project Phase II. Independent Evaluation Department"

Transcription

1 Validation Report Reference Number: PVR-324 Project Number: Loan Number: 1962 September 2014 Indonesia: Coral Reef Rehabilitation and Management Project Phase II Independent Evaluation Department

2 ABBREVIATIONS ADB Asian Development Bank BME benefit monitoring and evaluation CRITC coral reef information and training center CRM coral reef management CRMP coral reef management plan EIRR economic internal rate of return ha hectare HRD human resource development LIPI Lembaga Ilmu Pengetahuan Indonesia (Indonesian Institute of Sciences) MMAF Ministry of Marine Affairs and Fisheries NGO nongovernment organization PCR project completion report PIU project implementation unit PMO project management office NOTE In this report, $ refers to US dollars. Key Words asian development bank, artisan fisheries, associated ecosystems, benefit transfer method, catch per unit effort, coral reef, critical reef ecosystem, indonesia, marine management areas, monitoring, control and surveillance, reef management, social infrastructure facilities, sustainable natural resource management The guidelines formally adopted by the Independent Evaluation Department (IED) on avoiding conflict of interest in its independent evaluations were observed in the preparation of this report. To the knowledge of IED management, there were no conflicts of interest of the persons preparing, reviewing, or approving this report. In preparing any evaluation report, or by making any designation of or reference to a particular territory or geographic area in this document, IED does not intend to make any judgments as to the legal or other status of any territory or area.

3 PROJECT BASIC DATA Project Number: PCR Circulation Date: Nov 2012 Loan Number: 1962 PCR Validation Date: Sep 2014 Project Name: Coral Reef Rehabilitation and Management Project, Phase II Country: Indonesia Approved ($ million) Actual ($ million) Sector: Agriculture and Total Project Costs: natural resources ADB Financing: ($ million) ADF: Loan: (SDR equivalent, million) Borrower: OCR: 0.00 Beneficiaries: Others: Cofinancier: Total Cofinancing: Approval Date: 6 Dec 2002 Effectiveness Date: 11 May Nov 2003 Signing Date: 10 Feb 2003 Closing Date: 31 Dec Dec 2011 Project Officers: Location: From: To: W.D. Zhou M.N. Islam ADB headquarters ADB headquarters Dec 2002 Oct 2005 Sep 2005 Dec 2011 Validator: E. Lopez-Dee, Consultant Peer Reviewer: K. Hewitt, Evaluation Specialist, IED2 Quality Reviewers: E. Gozali, Principal Evaluation Specialist, IED1 M. Grace Agapito, Evaluation Officer, IED1 Director: W. Kolkma, Director, IED1 ADB = Asian Development Bank; ADF = Asian Development Fund; IED1 = Independent Evaluation Department, Division 1; IED2 = Independent Evaluation Department, Division 2; OCR = ordinary capital resources; PCR = project completion report; SDR = special drawing rights. A. Rationale I. PROJECT DESCRIPTION 1. Indonesia s large expanse of marine areas, much of which are fringed by coral reefs, support a wide variety of living aquatic resources. Considered as the coral biodiversity center of the world, its coral reef resources are said to contain 70 genera and 450 species of corals. These resources in turn support many coastal communities, artisans, and industrial fisheries. When this project was being contemplated, the total product of coastal and marine economic activities was estimated at 25% 30% of the country s gross domestic product. Of late, coral reefs have been depleted rapidly mainly due to extensive extractive activities, destructive fishing practices, wanton coastal development for industrial and tourism purposes, and pollution. Since coral reefs provide 90% of fish catch by coastal fishermen who are also increasing in number and who belong to the poorest segment of the society, their rapid deterioration proportionately reduces the fish catch per unit effort. These not only adversely affect the fishermen s incomes; but also further constrain their access to basic social infrastructure like water, sanitation, health care, transport, and even credit. Such is the importance of these reef resources to Indonesia s environment and economy that its planning system has now put stronger emphasis on using these resources with sustainability as its primary concern.

4 2 B. Expected Impacts 2. The project s desired impacts and corresponding performance indicators as defined in its design and monitoring framework were twofold: 1 (i) coral reefs and associated ecosystems rehabilitated, protected, and well managed as evidenced by an annual increase of 2% in live coral cover; and (ii) incidence of poverty in coastal communities lowered with average real per capita income in target coastal communities annually increased by 2%. C. Objectives or Expected Outcomes 3. The projected outcomes and their corresponding performance targets included the following: (i) enhanced national and local capacity to manage coral reef resources and effectively managed priority reef areas as measured by the main coral reef management (CRM) issues in six districts in three provinces being effectively addressed; and (ii) increased income and improved living standards of poor coastal communities of 10,000 households, which at completion should have a 20% growth in real income over the project s life and their living standards subsequently improved. D. Outputs 4. The expected impact and outcomes were to be achieved through the following components: (i) institutional strengthening and project management, and (ii) community-based resource management and development. The first component was to be accomplished by the development of policies, strategies, and guidelines for sustainable CRM at the national and at six district-government levels, leading to the (i) drafting and implementation of CRM strategies; (ii) preparation of their respective coral reef management plans (CRMPs); (iii) delineation of marine management areas in three to six districts; and (iv) formation of community-based monitoring, control, and surveillance units. Another initiative planned was the establishment of a centrally and regionally operated network of coral reef information and training centers (CRITCs) augmented by a functioning benefit monitoring and evaluation (BME) system, and a coral reef research program. Moreover, soft subcomponents on human resource development (HRD) and comprehensive information, education, and communication program were also prescribed at appraisal. The project was mandated to establish and operate a project management office (PMO), a project implementation unit (PIU) in the Indonesian Institute of Sciences (LIPI), and six regional PIUs; procure vehicles and equipment, minor civil works, and consulting services; award contracts for community organizing, training, and surveys; and conduct workshops, seminars, and study tours. 5. Initiatives under the second component were to further the efficacy of coastal community groups purposely organized for CRM and livelihood development in accordance with their respective CRMPs; achieve community-based compliance with and enforcement of sound CRM practices; and provide social infrastructure facilities and services to target beneficiaries. By the end of the project, it was expected that illegal fishing in the project sites would have been reduced by 40% 50%. E. Provision of Inputs 6. The Asian Development Bank (ADB) extended a loan of $33.0 million to finance both foreign and local currency cost components of the project. Disbursements reached $36.7 million after one loan reallocation and a 2-year loan closing date extension. The government s actual 1 ADB Report and Recommendation of the President to the Board of Directors: Proposed Loan to the Republic of Indonesia for the Coral Reef Rehabilitation and Management Project Phase II. Manila.

5 3 contribution amounted to $0.3 million compared to the $6.6 million estimated at appraisal while beneficiaries contribution amounted to $0.6 million compared to the $1.7 million estimated at appraisal. Project expenditures were $37.7 million, 8.8% lower than the appraisal estimate of $41.3 million as the rupiah depreciated against the dollar. Inputs provided were to fund institutional strengthening and project management at $19.8 million, up slightly from $17.53 million at appraisal; and community-based resource management and development at $17.1 million, down from $20.8 million largely because of curtailed contributions from the beneficiaries and lower government counterpart funds. Actual financing by ADB went up by 10.2%, which is equivalent to $36.7 million. The increment was allocated for tsunami assistance, which was not in the original financing plan. 7. Consultancy services were procured in accordance with ADB guidelines although the total amount of $3.9 million exceeded the appraisal estimate of $3.5 million. A total of person-months of consultancy services were used up for the PMO and LIPI project management functions and CRITC operations, comprising person-months of national and 54.0 for international consultants. These exceeded the appraisal requirement by personmonths, which were essentially utilized for the project s 2-year extension. The procurement of goods and services was also carried out consistent with established ADB procedures and expedited by a dedicated procurement committee at the PMO. Village social infrastructure facilities were built with beneficiaries providing labor, local materials, and other in-kind contributions. F. Implementation Arrangements 8. At appraisal, the Ministry of Marine Affairs and Fisheries (MMAF), through its Directorate General of Marine, Coastal and Small Islands, was proposed to be the executing agency having overall project jurisdiction. Within the directorate was the PMO, which was entrusted with the day-to-day project management. In each project province, there were the local PMOs called PIUs; and at the district level, the regional coordination units. Mandated to provide overall coordinative functions at the national level was the National Steering Committee chaired by the National Development Planning Agency (or the BAPPENAS), and at the local level was the Regional Advisory Council chaired by the Provincial Fisheries and Marine Affairs Service. The project s research information, monitoring, and training activities were solely assigned to the LIPI. These arrangements at appraisal were substantively adhered to throughout the project except for one modification. Less than 2 years after loan effectiveness, a number of earthquakeand tsunami-affected fishing villages were added to benefit from the project s multifaceted interventions. 9. Even with this change in scope and geographical coverage, which eventually required reprogramming and reallocation of project resources, the schemes proposed and followed were found to be sufficient in delivering all expected outputs. The project completion report (PCR) 2 further reported that the overall performance of consultants, civil works contractors, equipment suppliers, and nongovernment organizations (NGOs) was satisfactory despite start-up delays. A status quo in the conditions and covenants stipulated in the loan agreement was followed. Of the 58 covenants, 50 were fully and promptly complied with while compliance with four was delayed. Another four, which related to the required number of meetings of field implementation units, and community funds for the maintenance of social infrastructure, were only partially complied with. No project activities were required in relation to the ADB involuntary resettlement policy. 2 ADB Completion Report: Coral Rehabilitation and Management Project Phase II in the Republic of Indonesia. Manila.

6 4 II. EVALUATION OF PERFORMANCE AND RATINGS A. Relevance of Design and Formulation 10. The PCR rated the project highly relevant because it was designed to address the policy, legal, and institutional bottlenecks affecting resource management in the country s reef areas. It adopted a holistic approach to CRM and provided the poor coastal communities with basic social services, social infrastructure, and opportunities to augment their incomes from microenterprises to balance environmental and resource management with socioeconomic development. It placed strong emphasis on the active involvement of intended beneficiaries, local governments, and NGOs in planning and implementing CRM interventions. It continued to be relevant even after its completion as sustained poverty alleviation remained a primary goal in Indonesia s Medium Term Development Program for During and after completion, the project remained in line with the country strategy and program of ADB, which had an overarching poverty reduction objective including environmental management and protection. 11. Expanding its coverage to include tsunami-affected villages in other districts of the country further underscored its relevance. This validation supports the innovative value-adding features and ambition of the project. This validation, therefore, accords the project a highly relevant rating. B. Effectiveness in Achieving Project Outcome and Outputs 12. The outputs under the first component were generally met. As of loan closing, seven of eight districts had formulated their own regulations for CRM. Seven CRMPs instead of six were also prepared, approved at provincial and district levels, and finally integrated into their regional development plans to ensure sustainable implementation and financing. Complementing these outputs were the seven local CRITCs, fully established and equipped to be able to network with the national; and eight regional CRITCs. The project supported this initiative further by organizing a coral reef spatial information system and installing an expanded BME for CRM. Coral reef biomass, biodiversity, and fishing effort data have since been regularly uploaded into the national CRITC server. The project s national and local coral research agenda from 2005 to 2010 yielded 2 national and 21 local research activities. 13. Through its comprehensive HRD program, a total of 2,860 government and civil society personnel were trained on CRM, easily exceeding the targets by more than 50%. Graduate scholarships were also provided to 15 regional field and 10 central office personnel. Comprehensive extension programs on the sustainable use of coral reef resources and livelihood activities were developed and implemented in 57 coastal villages, 12 more than what was planned. The project managed to log a 91% awareness rating among public employees and coastal communities, exceeding the 70% pegged at appraisal. The PMO, national PIU-LIPI, regional coordination units, and PIUs were created, and later provided with trained staff and other necessary resources to function effectively. Also consistent with appraisal targets, consultants were deployed to provide technical assistance (TA). 14. The second targeted outcome of increasing income and improving the living standards of poor coastal communities was likewise achieved. At completion, it was reported that 769 community groups with 7,014 members in 57 coastal villages, compared with the target of groups comprising 10,000 members, were organized and participated in formal CRM training and livelihood development. Women accounted for 28% of total membership.

7 5 Community organizing also yielded 17 site-specific coral reef resources surveys as inputs to CRMP preparation, compared to the target of 10. District executives also designated seven marine management areas with an aggregate area of 130,000 hectares (ha) of coral reefs and associated ecosystems equivalent to 117% of the target. These areas were subsequently patrolled and protected by monitoring, control, and surveillance groups with about 2,000 members and complemented by 20 civilian employees deputized to monitor illegal and destructive fishing activities. As a result, surveyed project sites in 2011 showed a 71% decrease in the frequency of practices destructive to coral reefs, exceeding the target of a 40% 50% reduction in illegal fishing activities. Based on socioeconomic surveys conducted in 44 villages (in the eight project districts) out of the villages targeted, 298 social infrastructure facilities (e.g, village information centers, patrol boats, water supply, sanitation, and jetty wharves) were provided in all 57 project villages to improve the villagers living standards. The PCR reported that each type of facility had a minimum of 4,000 households utilizing it. 15. At completion, 879 village groups with 6,850 members were working in non-fisheriesrelated (e.g., embroidery, handicraft making, etc.) and fisheries-related (e.g., seaweed and grouper cage culture) microenterprises. About 50% of these microenterprises went financially well with the PCR attributing their success to solid cooperation among members, good technical skills, good management, and transparent bookkeeping. Socioeconomic data from 2005 to 2011 revealed that the overall average increase in household income throughout the project sites was 12.6%. While lower than the target of 20%, this validation believes that the project still made a significant difference in uplifting the income status of intended beneficiaries. 16. The PCR rated the project effective in achieving its intended outcomes. The targeted overarching outcome of rehabilitating, protecting, and managing coral reefs and associated ecosystems in the project sites was achieved. The various plans, policies, strategies, and regulatory measures that the project helped formulate enhanced national and local capacity to manage these resources and other priority reef areas. It effectively addressed the two key CRM issues on dynamite fishing and coral reef mining. Although unable to squarely meet the prescribed target, the project still significantly contributed in increasing fishing household income by an average of 12.6%, thus, also improving the living standards of these same groups of beneficiaries. Thus, this validation concurs with the PCR rating of effective for the project. C. Efficiency of Resource Use in Achieving Outcome and Outputs 17. The PCR rated the project efficient. It encountered start-up implementation delays as loan effectiveness, the signing of grant agreements between the MMAF and the district governments, and the procurement of consultant and NGO services took place beyond the prescribed timelines. Yet the project was able to catch up and eventually accomplished its targets with timely adjustments and improvements in management and operations. While this necessitated a reprogramming of project resources and extending the loan closing date, the project stayed on track to meet its targets. The extension was aptly utilized to allow the project s interventions to develop and mature, and to further build the capacity of district level institutions to ensure sustainability. The PCR recalculated the economic internal rate of return (EIRR) based on the actual area coverage of 132,950 hectare (ha) at 29.3% against the appraisal estimate of 19%. The two EIRR estimates were based on two different coverage areas. The appraisal estimate was based on 7,625 ha of sample project area while the PCR estimate was based on a total project area of 132,000 ha. Aggregate efficiency analysis used the benefit transfer method. This validation also notes the (i) proper recognition of economic costs, (ii) proper application of a manufactures unit value index for constant pricing, and (iii) appropriate use of shadow pricing parameters. The estimation of economic benefits both

8 6 at appraisal and completion relied mainly on the transfer benefits method. This validation notes that significant effort has been made to find accurate estimates of per ha benefits from coral reef and mangrove improvements. Nonetheless, the accuracy of these figures is difficult to ascertain. Given the relatively robust EIRR results and the fact that the project did not suffer from cost overrun, this validation concurs with the PCR rating of efficient for the project. D. Preliminary Assessment of Sustainability 18. The PCR rated the project likely sustainable. Fishing households group mobilization and management; participatory planning in the crafting, implementation, and monitoring of local regulatory decrees and social infrastructure facilities; and access to information and technology transfers through different media format were facilitated through the project. These could not have occurred without the comprehensive HRD activities at various levels, which the government and civil society partners have undertaken. These activities paved the way for a smooth collaboration between these entities and the villagers, which at completion remained robust. Socioeconomic surveys showed that (i) the public sector and coastal communities gained heightened awareness on the importance of coral resources, (ii) illegal practices were curtailed, (iii) village level infrastructures were built with each type being utilized by at least 4,000 households and some of them already being maintained through volunteerism, (iv) 50% of microenterprises put up were operating financially well with representative microenterprises posting financial internal rates of return ranging from 20% to 107% against the weighted average cost of capital of 16%, and (v) household incomes and living standards of villagers improved. Women s participation in various skills training and technology transfer activities, where they accounted for 24% of the total number of participants, enabled them to gain confidence and thereafter play important roles in home-based livelihood activities. They became recognized for their contributions in running the affairs of their community groups roles that were traditionally reserved for their male counterparts. Finally, a TA funded by ADB was underway to develop a subsequent initiative designed to sustain, strengthen, and institutionalize the interventions of the project. Hence, this validation subscribes to the likely sustainable rating in the PCR. E. Impact 19. The PCR did not provide a rating for the project s overall impact. Still, the project made a significant difference in coral reef protection and management, and in uplifting the income status and improving the living standards of intended beneficiaries. From various BME and coral reef biomass, biodiversity, and fishing effort reports, the overall average annual growth in live coral in all project sites was estimated at 9.4%, indicating that the appraisal target was achieved. Based on socioeconomic data obtained, the average growth of per capita income during reached 5.3% per year compared to the 2% targeted at appraisal. This positive increment in per capita income could be seen from the increasing trends in the catch per unit effort of fishermen, consistent with the observed improvements in live coral cover. Still, this validation opines that the positive changes that unfolded should not exclusively be attributed to the project. It should be noted that the project benefited from an earlier similar initiative that laid much of the required policy, institutional, and operational groundwork. Following all technical and socioeconomic data obtained, project impact appears to be significant. 20. The PCR indicated that project activities had minimal impact on the environment with no resettlement-related issue. Measures to safeguard the interests of affected indigenous peoples were implemented in accordance with the ADB Indigenous Peoples Policy.

9 7 III. OTHER PERFORMANCE ASSESSMENTS A. Performance of the Borrower and Executing Agency 21. The PCR rated the performance of the borrower and the executing agency satisfactory despite being constrained by start-up delays. The executing agency demonstrated good leadership and strong institutional capacity in implementing the project, thus, earning a satisfactory rating at closing date. The MMAF consistently met the disbursement targets so that the PMO and the PIUs could aptly perform their respective mandates in accordance with ADB procedures. The project performance monitoring system developed for the project turned in timely financial performance and physical progress monitoring reports and, hence, was able to keep track of how it was proceeding. External audit reports and third-party review reports of the contracted NGOs, researchers, and implementing entities at the village level helped ensure that assignments were carried out effectively. This validation supports a satisfactory rating for the performance of the borrower and the executing agency. B. Performance of the Asian Development Bank 22. The administration of the project by ADB was satisfactory. It carried out 1 inception mission, nine review missions, one midterm review mission, and one PCR mission. These missions recommended time-bound action plans that effectively helped the executing agency resolve implementation issues. ADB promptly attended to government requests for modifications in project coverage, cost sharing, consultancy services contract variations, and extension of the loan closing date. This validation agrees to the satisfactory rating accorded to ADB. IV. OVERALL ASSESSMENT, LESSONS, AND RECOMMENDATIONS A. Overall Assessment and Ratings 23. The PCR rated the project successful. The project was highly relevant to the strategies and policies of both the government and ADB for enhanced capacity to sustainably manage and protect critical reef ecosystems and reducing poverty in the country. Its completion has already created a demand for its replication. While the project agonized over initial implementation problems, it still managed to achieve most of the intended targets. Economic benefits in terms of improved income generation evidently accrued to targeted fishing households. Women s status and participation in village organizations were enhanced. The institutions entrusted with natural resources management and regulation became more proficient through the capacity-building activities availed of by their technical staff, better networking facilities and resources, and the assistance provided by NGOs and extension workers. As a result, better and closer collaboration and coordination among implementing agencies, fishing communities, and other stakeholders emerged. At completion, favorable environmental consequences were also observed in terms of lower incidence of illegal fishing activities, improved fish catch, and increased live coral cover in some of the project sites. Overall, this validation rates the project successful.

10 8 Overall Ratings Criteria PCR IED Review Reason for Disagreement and/or Comments Relevance Highly relevant Highly relevant This validation supports innovative value-adding features and goals of the project (para. 11). Effectiveness in Effective Effective achieving project outcome and outputs Efficiency in achieving outcome and outputs Efficient Efficient Preliminary assessment of sustainability Likely sustainable Likely sustainable Overall assessment Successful Successful Impact Not rated Significant Refer to paras Borrower and executing Satisfactory Satisfactory agency Performance of ADB Satisfactory Satisfactory Quality of PCR Satisfactory Refer to para. 27. ADB = Asian Development Bank, IED = Independent Evaluation Department, PCR = project completion report. Source: ADB Independent Evaluation Department. B. Lessons 24. The PCR identified lessons from the implementation of the project that could be valuable to both ADB operations and to the borrower. This validation concurs with the PCR lessons, which essentially serve to reaffirm the benefits of a participatory approach to resource management. Key lessons are as follows: (i) mobilization and organization of coastal community groups and their subsequent participation in planning social infrastructure facilities did help foster a favorable climate for partnership among citizens, national and district governments, and the NGOs; (ii) coordination of implementation arrangements among enforcement and/or regulatory institutions and communities, and the comprehensive awareness campaigns ensured the acceptance of various CRM tasks entrusted to the communities; (iii) empowerment of women created numerous opportunities for them to be part of the decision-making processes and substantively contributed to improving their household income; and (iv) labor and local materials contributed by the fishing households for village level infrastructures or facilities instilled ownership and volunteerism that are necessary for the subprojects sustainability, and lowered investment costs. C. Recommendations for Follow-Up 25. This validation subscribes to the recommendations detailed in the PCR. The capacities of the national and district level institutions, that are charged with the protection and conservation of reef resources and associated ecosystems, and that of the target beneficiaries to organize themselves so they could participate in planning village level investments had been established. Government assistance is needed to further increase the capacity of fishing households to freely access credit, marketing support, and other TA to reduce business failures and optimize returns on community groups investments in microenterprises.

11 9 V. OTHER CONSIDERATIONS AND FOLLOW-UP A. Monitoring and Evaluation Design, Implementation, and Utilization 26. The project design required the establishment of the project performance monitoring system in the PMO. Although the system was established behind schedule, financial performance and physical progress monitoring were regularly undertaken. Baseline data were collected for reef health and socioeconomic surveys. The project carried out a midterm evaluation survey to gauge public awareness, reduction of destructive fishing activities, and extent of live coral cover. Participatory monitoring and evaluation at the community level to ensure that assignments were carried out effectively was also undertaken by the project, along with special studies to investigate the impacts of project implementation. Accordingly, BME indicators were developed and incorporated in the regular reporting to track down project progress. B. Comments on Project Completion Report Quality 27. This validation rates the quality of the PCR satisfactory. The PCR is consistent with Project Administration Instruction 6.07 where it made a systematic and clear assessment of the project s outcomes, impact, relevance, effectiveness, and efficiency. The lessons and recommendations given are well grounded since they were drawn from the specific performances of the different stakeholders and factual evidences gathered from the field. The report presented direct and detailed analysis of the issues, outputs, and outcomes. The design and monitoring framework is clear in presenting the appraisal targets compared with actual performance, enhanced with brief analysis of results. The financial and economic analysis of the microenterprises supported by the project in Appendix 19 was, however, confined only to the most predominant activities and/or components and, hence, could not provide an aggregate quantitative assessment of the project component s viability. However, the assumptions, project parameters, and methodology used in evaluating the project s overall efficiency were observed to be appropriate and up to standards. C. Data Sources for Validation 28. This validation made use of the report and recommendation of the President, PCR, and back-to-office reports. D. Recommendation for Independent Evaluation Department Follow-Up 29. The project was generally successful. It had already set the stage for the implementation of its Phase III. The Independent Evaluation Department may still consider conducting a project performance evaluation report, ideally to focus on documenting the best practices undertaken by the project, confirming evidences that the project indeed empowered fishing households and women, and heightened public awareness on the importance of CRM; while investigating the impacts of village level social infrastructure built in a participatory way. To encourage increased participation by fishing households and investments in microenterprises development, the project performance evaluation report could take a deeper assessment of the financial viability of these investments and recommend practical measures for minimizing business failures.

Indonesia: Sustainable Aquaculture Development for Food Security and Poverty Reduction Project

Indonesia: Sustainable Aquaculture Development for Food Security and Poverty Reduction Project Validation Report Reference Number: PVR-430 Project Number: 35183-013 Loan Number: 2285 November 2015 Indonesia: Sustainable Aquaculture Development for Food Security and Poverty Reduction Project Independent

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

India: Karnataka Urban Development and Coastal Environmental Management Project

India: Karnataka Urban Development and Coastal Environmental Management Project Validation Report Reference Number: PVR-334 Project Number: 30303 Loan Number: 1704 November 2014 India: Karnataka Urban Development and Coastal Environmental Management Project Independent Evaluation

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Coral Reef Rehabilitation and Management Program Coral Triangle Initiative Project (RRP INO 46421) A. Approach and Methodology ECONOMIC AND FINANCIAL ANALYSIS 1. The economic and financial analysis of

More information

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Validation Report Reference Number: PVR-462 Project Number: 42496-013 Loan Number: 2508 December 2016 People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Independent

More information

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project f Validation Report Reference Number: PVR-370 Project Number: 29041 Loan Number: 1947 December 2014 Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project Independent Evaluation Department

More information

Bangladesh: Chittagong Hill Tracts Rural Development Project

Bangladesh: Chittagong Hill Tracts Rural Development Project Validation Report Reference Number: PVR-222 Project Number: 32467 Loan Number: 1771(SF) December 2012 Bangladesh: Chittagong Hill Tracts Rural Development Project Independent Evaluation Department ABBREVIATIONS

More information

Indonesia: Participatory Irrigation Sector Project

Indonesia: Participatory Irrigation Sector Project Validation Report Reference Number: PVR-393 Project Number: 32359 Loan/Grant Numbers: 2064, 2065, and 4229 February 2015 Indonesia: Participatory Irrigation Sector Project Independent Evaluation Department

More information

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones Technical Assistance Report Project Number: 50004-001 Policy and Advisory Technical Assistance (PATA) October 2016 People s Republic of China: Study on Natural Resource Asset Appraisal and Management System

More information

Republic of the Maldives: Preparing Business Strategy for Port Development

Republic of the Maldives: Preparing Business Strategy for Port Development Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed

More information

Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda

Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda Validation Report Reference Number: PVR-471 Project Number: 47337-001 Loan Number: 3080 December 2016 Philippines: Emergency Assistance for Relief And Recovery from Typhoon Yolanda Independent Evaluation

More information

Philippines: Philippine Energy Efficiency Project

Philippines: Philippine Energy Efficiency Project Validation Report Reference Number: PVR-436 Project Number: 42001-013 Loan/Grant Numbers: 2507 and 0142 December 2015 Philippines: Philippine Energy Efficiency Project Independent Evaluation Department

More information

Validation Report. Indonesia: Second Decentralized Health Services Project. Independent Evaluation Department

Validation Report. Indonesia: Second Decentralized Health Services Project. Independent Evaluation Department Validation Report Reference Number: PVR-428 Project Number: 34149 Loan Numbers: 2074 and 2075 November 2015 Indonesia: Second Decentralized Health Services Project Independent Evaluation Department ABBREVIATIONS

More information

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project

Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Validation Report Reference Number: PCV: PHI 2011-15 Project Number: 35379 Loan Number: 2012 July 2011 Philippines: Metropolitan Waterworks and Sewerage System New Water Source Development Project Independent

More information

Nepal: Road Connectivity Sector I Project

Nepal: Road Connectivity Sector I Project Validation Report October 2017 Nepal: Road Connectivity Sector I Project Reference Number: PVR-523 Project Number: 37266-032 Grant Number: 0051 ABBREVIATIONS ADB Asian Development Bank DOR Department of

More information

Mongolia: Regional Road Development Project

Mongolia: Regional Road Development Project Validation Report Reference Number: PVR-481 Project Numbers: 35377-013 and 35377-023 Loan/Grant Numbers: 2087, 2621, and 0199 December 2016 Mongolia: Regional Road Development Project Independent Evaluation

More information

Philippines: Mindanao Basic Urban Services Sector Project

Philippines: Mindanao Basic Urban Services Sector Project Validation Report Reference Number: PCV: PHI 2011-25 Project Number: 30551 Loan Number: 1843 September 2011 Philippines: Mindanao Basic Urban Services Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project Validation Report Reference Number: PVR-360 Project Number: 40198 Loan Number: 2374 December 2014* Viet Nam: Ho Chi Minh CityLong ThanhDauGiay Expressway Technical Assistance Project Independent Evaluation

More information

Viet Nam: Microfinance Development Program (Subprograms 1 and 2)

Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Validation Report Reference Number: PVR-478 Project Numbers: 42235-013 and 42235-023 Loan Numbers: 2877 and 3213 December 2016 Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Independent

More information

Indonesia: Capacity Building in Urban Infrastructure Management Project

Indonesia: Capacity Building in Urban Infrastructure Management Project Validation Report Reference Number: PCV: INO 2008-68 Project Number: 27289 Loan Number: 1572-INO May 2009 Indonesia: Capacity Building in Urban Infrastructure Management Project Independent Evaluation

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 46421 November 2013 Proposed Loan and Administration of Grant Republic of Indonesia: Coral Reef Rehabilitation and Management

More information

Indonesia: Metropolitan Medan Urban Development Project

Indonesia: Metropolitan Medan Urban Development Project Validation Report Reference Number: PCV:INO 2009-09 Project Number: 27358 Loan Number: 1587 May 2009 Indonesia: Metropolitan Medan Urban Development Project Independent Evaluation Department 2 ABBREVIATIONS

More information

Evaluation Approach Project Performance Evaluation Report for Loan 2167 and Grant 0006-SRI: Tsunami-Affected Areas Rebuilding Project September 2015

Evaluation Approach Project Performance Evaluation Report for Loan 2167 and Grant 0006-SRI: Tsunami-Affected Areas Rebuilding Project September 2015 Asian Development Bank 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org www.adb.org/evaluation Evaluation Approach Project Performance

More information

MFF - Bihar Urban Development Investment Program (Facility Concept)

MFF - Bihar Urban Development Investment Program (Facility Concept) India: MFF - Bihar Urban Development Investment Program (Facility Concept) Project Name Project Number 41603-013 Country Project Status Project Type / Modality of Assistance Source of Funding / Amount

More information

Georgia: Emergency Assistance for Post-Conflict Recovery

Georgia: Emergency Assistance for Post-Conflict Recovery Validation Report Reference Number: PCV: GEO 2011-49 Project Number: 32023 Loan Number: 2469-GEO(SF) December 2011 Georgia: Emergency Assistance for Post-Conflict Recovery Independent Evaluation Department

More information

Cambodia: Rural Credit and Savings Project

Cambodia: Rural Credit and Savings Project Project Validation Report Reference Number: CAM 2008-06 Project Number: 30327 Loan Number: 1741 July 2008 Cambodia: Rural Credit and Savings Project Operations Evaluation Department ABBREVIATIONS ADB Asian

More information

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1)

Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Validation Report Reference Number: PVR-326 Project Number: 37066 Loan Number: 2248 October 2014 Multitranche Financing Facility India: Rural Road Sector II Investment Program (Project 1) Independent Evaluation

More information

Pakistan: Decentralization Support Program

Pakistan: Decentralization Support Program Validation Report Reference Number: PCV: PAK 2011-53 Program Number: 34328 Loan Numbers: 1935/1936/1937/1938 December 2011 Pakistan: Decentralization Support Program Independent Evaluation Department ABBREVIATIONS

More information

Maldives: Tsunami Emergency Assistance Project

Maldives: Tsunami Emergency Assistance Project Validation Report Reference Number: PVR 218 Project Number: 39099 Loan Number: 2160 (SF) Grant Number: 0001 December 2012 Maldives: Tsunami Emergency Assistance Project Independent Evaluation Department

More information

Maldives: Information Technology Development Project

Maldives: Information Technology Development Project Validation Report Reference Number: PVR-272 Project Number: 34276 Loan Number: 1882 December 2013 Maldives: Information Technology Development Project Independent Evaluation Department ABBREVIATIONS ADB

More information

Indonesia: Earthquake and Tsunami Emergency Support Project

Indonesia: Earthquake and Tsunami Emergency Support Project Validation Report Reference Number: PVR 237 Project Number: 39127 Grant Number: 0002-SF December 2012 Indonesia: Earthquake and Tsunami Emergency Support Project Independent Evaluation Department ABBREVIATIONS

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO)

Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) Board of Directors IN.247-11 14 October 2011 Validation Report Banking Sector Reform Program (Lao People s Democratic Republic) (Loan 1946-LAO) The attached Report is circulated at the request of the Director

More information

Pakistan: Agribusiness Development Project

Pakistan: Agribusiness Development Project Validation Report Reference Number: PVR-354 Project Number: 33364 Loan Number: 2171 November 2014 Pakistan: Agribusiness Development Project Independent Evaluation Department ABBREVIATIONS ADB ASF DALPMG

More information

Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2)

Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2) Validation Report July 2017 Nepal: Rural Finance Sector Development Cluster Program (Subprogram 2) Reference Number: PVR-497 Project Number: 36169-023 Loan Number: 2641 Grant Number: 0208 ABBREVIATIONS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:INO 34147 TECHNICAL ASSISTANCE (Cofinanced by the Government of the United Kingdom) TO THE REPUBLIC OF INDONESIA FOR INTEGRATION OF POVERTY CONSIDERATIONS IN DECENTRALIZED EDUCATION

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

Indonesia: Rural Income Generation Project

Indonesia: Rural Income Generation Project Validation Report Reference Number: PVR 184 Project Number: 29456 Loan Number: 1583 November 2012 Indonesia: Rural Income Generation Project Independent Evaluation Department ABBREVIATIONS AAHRD Agency

More information

India: Assam Governance and Public Resource Management Sector Development Program

India: Assam Governance and Public Resource Management Sector Development Program Validation Report Reference Number: PVR-335 Project Number: 36308 Loan Numbers: 2141, 2142, and 2442 November 2014 India: Assam Governance and Public Resource Management Sector Development Program Independent

More information

Philippines: Small and Medium Enterprise Development Support Project

Philippines: Small and Medium Enterprise Development Support Project Validation Report Reference Number: PCV: PHI 2011 28 Project Number: 36419 Loan Number: 2186 October 2011 Philippines: Small and Medium Enterprise Development Support Project Independent Evaluation Department

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK FI ASIAN DEVELOPMENT BANK RRP: INO 32176 REPORT AND RECOMMENDATION OF THE PRESIDENT TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO THE REPUBLIC OF INDONESIA FOR THE CORAL REEF REHABILITATION AND MANAGEMENT

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to

More information

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON)

Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) Board of Directors IN.365-10 21 December 2010 Validation Report Rural Finance Project (Mongolia) (Loan 1848-MON) The attached Report is circulated at the request of the Director General, Independent Evaluation

More information

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance Technical Assistance Report Project Number: 47287-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: INO 34149 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO THE REPUBLIC OF INDONESIA FOR PREPARING THE SECOND DECENTRALIZED HEALTH SERVICES PROJECT November 2001

More information

Viet Nam: Health Care in the Central Highlands Project

Viet Nam: Health Care in the Central Highlands Project Validation Report Reference Number: PVR-344 Project Number: 37115 Loan Number: 2076 (SF) October 2014 Viet Nam: Health Care in the Central Highlands Project Independent Evaluation Department ABBREVIATIONS

More information

Validation Report. India: North Karnataka Urban Sector Investment Program, Tranche 1. Independent Evaluation Department

Validation Report. India: North Karnataka Urban Sector Investment Program, Tranche 1. Independent Evaluation Department Validation Report Reference Number: PVR-451 Project Number: 38254-033 Loan Number: 2312 August 2016 India: North Karnataka Urban Sector Investment Program, Tranche 1 Independent Evaluation Department ABBREVIATIONS

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

Indonesia: Coral Reef Rehabilitation and Management Program - Coral Triangle Initiative Project

Indonesia: Coral Reef Rehabilitation and Management Program - Coral Triangle Initiative Project Coral Reef Rehabilitation and Management Program Coral Triangle Initiative Project (RRP INO 46421) Project Administration Manual Project Number: 46421 Loan and Grant Number(s): {LXXXX; GXXXX} November

More information

Afghanistan: Regional Airports Rehabilitation Project (Phase 1)

Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Validation Report Reference Number: PVR 225 Project Number: 37136 Loan Number: 2105 December 2012 Afghanistan: Regional Airports Rehabilitation Project (Phase 1) Independent Evaluation Department ABBREVIATIONS

More information

Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION

Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION Introduction Chapter 1, Page 1 of 9 1. INTRODUCTION 1.1 OVERVIEW Preamble 1.1.1 The African Development Bank is the premier financial development institution in Africa dedicated to combating poverty and

More information

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 Technical Assistance Report Project Number: 40345 April 2008 Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 The views expressed herein are those

More information

PROJECT AGREEMENT. (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF SINDH

PROJECT AGREEMENT. (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF SINDH LOAN NUMBER 2499-PAK (SF) PROJECT AGREEMENT (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK and PROVINCE OF SINDH NORTH SINDH URBAN SERVICES CORPORATION LIMITED DATED

More information

Indonesia: Infrastructure Financing Facility Company Project

Indonesia: Infrastructure Financing Facility Company Project Validation Report December 2017 Indonesia: Infrastructure Financing Facility Company Project Reference Number: PVR-532 Program Number: 42109-013 Loan Number: 2516 ABBREVIATIONS ADB Asian Development Bank

More information

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department

Validation Report. India: Rural Roads Sector I Project. Independent Evaluation Department Validation Report Reference Number: PVR-307 Project Number: 36320 Loan Number: 2018 May 2014 India: Rural Roads Sector I Project Independent Evaluation Department ABBREVIATIONS ADB Asian Development Bank

More information

REQUEST FOR PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: FULL-SIZED PROJECT

REQUEST FOR PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: FULL-SIZED PROJECT REQUEST FOR PROJECT PREPARATION GRANT (PPG) PROJECT TYPE: FULL-SIZED PROJECT THE GEF TRUST FUND Submission Date: 15 February 2008 Re-submission Date: 25 March 2008 GEFSEC PROJECT ID 1 : GEF AGENCY PROJECT

More information

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection Technical Assistance Report Project Number: 47042-001 Policy and Advisory Technical Assistance (PATA) October 2013 People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section F1/BP Page 1 of 3 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ENVIRONMENTAL

More information

Cambodia: Second Power Transmission and Distribution Project

Cambodia: Second Power Transmission and Distribution Project Validation Report Reference Number: PVR-464 Project Number: 37041-013 Loan Number: 2261 December 2016 Cambodia: Second Power Transmission and Distribution Project Independent Evaluation Department ABBREVIATIONS

More information

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan Technical Assistance Report Project Number: 46539 Regional Capacity Development Technical Assistance (R CDTA) August 2014 Improving the Financial Management Capacity of Executing Agencies in Afghanistan

More information

Viet Nam: Northern Power Transmission Expansion Sector Project

Viet Nam: Northern Power Transmission Expansion Sector Project Validation Report Reference Number: PVR-485 Project Number: 38196-013 Loan Number: 2225 December 2016 Viet Nam: Northern Power Transmission Expansion Sector Project Independent Evaluation Department ABBREVIATIONS

More information

Bangladesh: Road Network Improvement and Maintenance Project II

Bangladesh: Road Network Improvement and Maintenance Project II Validation Report Reference Number: PVR-435 Project Number: 34415 Loan Number: 2021 November 2015 Bangladesh: Road Network Improvement and Maintenance Project II Independent Evaluation Department ABBREVIATIONS

More information

Validation Report. Tonga: Economic Support Program. Independent Evaluation Department

Validation Report. Tonga: Economic Support Program. Independent Evaluation Department Validation Report Reference Number: PVR-318 Program Number: 43152-01 Grant Number: 0185 September 2014 Tonga: Economic Support Program Independent Evaluation Department ABBREVIATIONS ADB Asian Development

More information

Validation Report. Nauru: Public Financial Management Reform Program. Independent Evaluation Department

Validation Report. Nauru: Public Financial Management Reform Program. Independent Evaluation Department Validation Report Reference Number: PVR-475 Project Number: 45032-001 Grant Number: 0300 December 2016 Nauru: Public Financial Management Reform Program Independent Evaluation Department ABBREVIATIONS

More information

Mongolia: Developing an Information System for Development Policy and Planning

Mongolia: Developing an Information System for Development Policy and Planning Technical Assistance Report Project Number: 51136-001 Knowledge and Support Technical Assistance (KSTA) September 2017 Mongolia: Developing an Information System for Development Policy and Planning This

More information

OPERATIONS MANUAL BANK POLICIES (BP)

OPERATIONS MANUAL BANK POLICIES (BP) BANK POLICIES (BP) OM Section F1/BP Page 1 of 2 These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. SAFEGUARD POLICY STATEMENT 1. The Asian Development

More information

Cambodia: Small and Medium Enterprise Development Program

Cambodia: Small and Medium Enterprise Development Program Validation Report Reference Number: PCV: CAM 2010-73 Program Number: 36383 Loan Number: 2129(SF) December 2010 Cambodia: Small and Medium Enterprise Development Program Independent Evaluation Department

More information

"Rehabilitation and sustainable development of fisheries and aquaculture affected by the tsunami in Aceh Province, Indonesia" FINAL PROJECT EVALUATION

Rehabilitation and sustainable development of fisheries and aquaculture affected by the tsunami in Aceh Province, Indonesia FINAL PROJECT EVALUATION "Rehabilitation and sustainable development of fisheries and aquaculture affected by the tsunami in Aceh Province, Indonesia" (Project OSRO/INS/601/ARC) FINAL PROJECT EVALUATION 29 March 11 May 2010 Response

More information

Evaluation Approach Project Performance Evaluation Report for ADB Loans 1913/1914 Sri Lanka: Plantation Development Project July 2015 I.

Evaluation Approach Project Performance Evaluation Report for ADB Loans 1913/1914 Sri Lanka: Plantation Development Project July 2015 I. Asian Development Bank. 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org; www.adb.org/evaluation Evaluation Approach Project Performance

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: INO 34115 TECHNICAL ASSISTANCE TO THE REPUBLIC OF INDONESIA FOR FISCAL DECENTRALIZATION November 2001 CURRENCY EQUIVALENTS (as of 31 October 2001) Currency Unit Rupiah (Rp)

More information

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project Technical Assistance Project Number: 50098 Project Preparatory Technical Assistance (PPTA) November 2016 Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project This document is being

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.02 Page 1 of 2 PROJECT ADMINISTRATION MISSIONS A. Introduction 1. ADB missions dispatched for loan and technical assistance (TA) project administration are classified

More information

Solomon Islands: Second Road Improvement (Sector) Project

Solomon Islands: Second Road Improvement (Sector) Project Validation Report Reference Number: PVR-477 Project Number: 43381-012 Grant Numbers: 0175, 0176, 0177, 0207, 0210 December 2016 Solomon Islands: Second Road Improvement (Sector) Project Independent Evaluation

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project Project Design Advance Project Number: 47279-003 September 2016 Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project This document is being disclosed to the public in accordance with ADB's Public

More information

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project Technical Assistance Report Project Number: 51107-001 Transaction Technical Assistance (TRTA) October 2017 Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project This

More information

Institutional Strengthening for Aviation Regulation

Institutional Strengthening for Aviation Regulation Technical Assistance Report Project Number: 43429 Regional capacity development technical assistance (R-CDTA) December 2010 Institutional Strengthening for Aviation Regulation The views expressed herein

More information

Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal Revenue

Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal Revenue Technical Assistance Report Project Number: 46429-001 Capacity Development Technical Assistance (CDTA) April 2013 Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. Page 1 of 1 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction FINANCIAL INTERMEDIATION

More information

Completion Report. Project Number: Loan Number: 1472 August Philippines: Small Towns Water Supply Sector Project

Completion Report. Project Number: Loan Number: 1472 August Philippines: Small Towns Water Supply Sector Project Completion Report Project Number: 27250 Loan Number: 1472 August 2006 Philippines: Small Towns Water Supply Sector Project CURRENCY EQUIVALENTS Currency Unit Philippine peso (P) At Appraisal At Project

More information

GEF-7 REPLENISHMENT POLICY RECOMMENDATIONS (PREPARED BY THE SECRETARIAT)

GEF-7 REPLENISHMENT POLICY RECOMMENDATIONS (PREPARED BY THE SECRETARIAT) Fourth Meeting for the Seventh Replenishment of the GEF Trust Fund April 25, 2018 Stockholm, Sweden GEF/R.7/18 April 2, 2018 GEF-7 REPLENISHMENT POLICY RECOMMENDATIONS (PREPARED BY THE SECRETARIAT) TABLE

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section H5/BP Page 1 of 4 BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ADDITIONAL FINANCING 1. The

More information

Evaluation Study. Midterm Review Process. Operations Evaluation Department

Evaluation Study. Midterm Review Process. Operations Evaluation Department Evaluation Study Reference Number: SES:REG 2008-78 Special Evaluation Study Update December 2008 Midterm Review Process Operations Evaluation Department ABBREVIATIONS ADB Asian Development Bank BTOR back-to-office

More information

Solomon Islands: Transport Sector Development Project

Solomon Islands: Transport Sector Development Project Validation Report September 2018 Solomon Islands: Transport Sector Development Project Reference Number: PVR-582 Project Number: 41171-022 Grant Number: 0243 ABBREVIATIONS ADB Asian Development Bank ADF

More information

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780 Department of Fisheries Ministry of Natural Resources Teone, Funafuti TUVALU Email: proptuv@gmail.com / proptuv@tuvalufisheries.tv

More information

Indonesia: Financial Market Development and Integration Program

Indonesia: Financial Market Development and Integration Program Validation Report January 2018 Indonesia: Financial Market Development and Integration Program Reference Number: PVR-534 Program Number: 44252-013 Loan Number: 2895 ABBREVIATIONS ADB Asian Development

More information

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project

FINAL EVALUATION VIE/033. Climate Adapted Local Development and Innovation Project FINAL EVALUATION VIE/033 Climate Adapted Local Development and Innovation Project PROJECT SUMMARY DATA Country Long project title Short project title LuxDev Code Vietnam Climate Adapted Local Development

More information

Indonesia: Java-Bali Electricity Distribution Performance Improvement Project

Indonesia: Java-Bali Electricity Distribution Performance Improvement Project Validation Report November 2017 Indonesia: Java-Bali Electricity Distribution Performance Improvement Project Reference Number: PVR-535 Program Number: 40061-013 Loan Number: 2619 and 8245 Grant Number:

More information

Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program

Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program Validation Report December 2018 Kazakhstan: MFF-CAREC Corridor 1 (Zhambyl Oblast Section) Investment Program Reference Number: PVR-565 Project Numbers: 41121-023, 41121-033, 41121-043, and 41121-053 MFF

More information

FRAMEWORK AND WORK PROGRAM FOR GEF S MONITORING, EVALUATION AND DISSEMINATION ACTIVITIES

FRAMEWORK AND WORK PROGRAM FOR GEF S MONITORING, EVALUATION AND DISSEMINATION ACTIVITIES GEF/C.8/4 GEF Council October 8-10, 1996 Agenda Item 6 FRAMEWORK AND WORK PROGRAM FOR GEF S MONITORING, EVALUATION AND DISSEMINATION ACTIVITIES RECOMMENDED DRAFT COUNCIL DECISION The Council reviewed document

More information

EAF-Nansen Project (GCP/INT/003/NOR)

EAF-Nansen Project (GCP/INT/003/NOR) EAF-Nansen Project (GCP/INT/003/NOR) Title : Improving the Artisanal Fisheries Management of Liberia and Sierra Leone Funded: EAF-Nansen Total Contribution: USD 50,000 1 Countries: Duration: Liberia and

More information

Periodic Financing Request Report. People s Republic of China: Railway Energy Efficiency and Safety Enhancement Investment Program (MFF): Tranche 4

Periodic Financing Request Report. People s Republic of China: Railway Energy Efficiency and Safety Enhancement Investment Program (MFF): Tranche 4 Periodic Financing Request Report Project Number: 43332 December 2013 People s Republic of China: Railway Energy Efficiency and Safety Enhancement Investment Program (MFF): Tranche 4 CURRENCY EQUIVALENTS

More information

REPORT 2015/174 INTERNAL AUDIT DIVISION

REPORT 2015/174 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2015/174 Audit of management of selected subprogrammes and related capacity development projects in the United Nations Economic and Social Commission for Asia and the Pacific

More information

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857. Project Name. Parent Project Name. Region. Country

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857. Project Name. Parent Project Name. Region. Country Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857 Project

More information

PROJECT AGREEMENT. (Power Distribution Enhancement Investment Program Tranche 1, Investment Project and Support Project) between

PROJECT AGREEMENT. (Power Distribution Enhancement Investment Program Tranche 1, Investment Project and Support Project) between LOAN NUMBERS 2438/2439(SF)-PAK PROJECT AGREEMENT (Power Distribution Enhancement Investment Program Tranche 1, Investment Project and Support Project) between ASIAN DEVELOPMENT BANK and PAKISTAN ELECTRIC

More information

Section 3.07 is deleted and the following is substituted therefor:

Section 3.07 is deleted and the following is substituted therefor: 2 outstanding Loan and the Fixed Spread that will be applied to new Loans (expressed as a percentage per annum), by (ii) the principal amount of the outstanding Loan on which the Borrower shall pay interest

More information

Planning, Budgeting and Financing

Planning, Budgeting and Financing English Version Planning, Budgeting and Financing Post-Disaster Recovery and Reconstruction Activities in Khammouane Province, Lao PDR Developed under the Khammouane Development Project (KDP), Implemented

More information

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project Technical Assistance Report Project Number: 51039-001 Transaction Technical Assistance (TRTA) September 2017 Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

More information

SECTOR ASSESSMENT (SUMMARY): FINANCE (DISASTER RISK MANAGEMENT) 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): FINANCE (DISASTER RISK MANAGEMENT) 1. Sector Performance, Problems, and Opportunities National Disaster Risk Management Fund (RRP PAK 50316) SECTOR ASSESSMENT (SUMMARY): FINANCE (DISASTER RISK MANAGEMENT) A. Sector Road Map 1. Sector Performance, Problems, and Opportunities a. Performance

More information