Lisburn Primary and Community Care Project

Size: px
Start display at page:

Download "Lisburn Primary and Community Care Project"

Transcription

1 Lisburn Primary and Community Care Project Appointment Business Case DRAFT v0.2 Section 1 Executive Summary 0

2 Contents 1 Executive Summary... 1 Introduction... 1 Project Background... 1 Section 2: Update of the Outline Business Case... 3 Section 3: Authority Requirements... 4 Section 4: Overview of Procurement Process... 5 Section 5: Final Tender Evaluation... 6 Section 6: Value for Money... 7 Section 7: Affordability and Accounting Treatment... 8 Section 8: Contractual Structure Section 9: Risk Allocation Section 10: Post Project Evaluation and Benefits Realisation Section 11: Process from Preferred Bidder to Contract Award Section 12: Conclusions and Recommendations Version Control Version : Description: Owner: Issued: 0.1 Initial Draft incorporating Introduction and Background for CB n/a KPMG to complete 0.2 KPMG Update KPMG 20/05/15 DRAFT

3 1 Executive Summary Introduction 1.1 This Appointment Business Case ( ABC ) has been prepared by the South Eastern Health and Social Care Trust ( SEHSCT or the Authority ) with the assistance of its specialist advisors. It sets out the case for the appointment of a Preferred Bidder for the Lisburn Primary and Community Care Centre ( PCCC ) Project ( the Project ) and the further progression of the Project to the Full Business Case ( FBC ) stage. 1.2 The ABC begins by providing information on the background to the Project along with a summary of, and update to, the original OBC for the Project. It then sets out the detailed Authority construction and service requirements to be met by the private sector developer, presents a summary of the allocation of the key risks underlying the Project, provides a comprehensive report on the procurement process and sets out an overview of the detailed evaluation of the Final Tenders received from the shortlisted private sector bidders. 1.3 The ABC concludes by analysing the value for money and affordability of the recommended Preferred Bidder s Final Tender stage bid submission, summarising the contractual arrangements underpinning the contract to be entered into between the Authority and the recommended Preferred Bidder, and summarises the next steps for the Project in progressing from ABC approval to development and approval of the FBC and thereafter to contract award. It also covers details on the arrangements for post project evaluation and benefits realisation, including how the contract will be monitored and managed post contract award. 1.4 This ABC has been prepared in accordance with the requirements issued by the Department of Health, Social Services and Public Safety ( DHSSPS ) 1, which follow the Northern Ireland Guide to Expenditure Appraisal & Evaluation ( NIGEAE ) and Value for Money ( VFM ) Assessment of Alternative Procurement Options (28 October 2014), guidance issued by the Department of Finance and Personnel ( DFP ). Project Background 1.5 The Project involves the provision of a new circa 10,800 2 sqm PCCC facility in Lisburn which will provide fit for purpose accommodation for GP services, selected acute outpatient services and a large number of multidisciplinary teams, many of which will be relocated from the existing Lisburn Health Centre, Warren Children s Centre and other leased premises, namely TSL House and Bridge Street. 1 As set out in the letter from Bill Pauley (DHSSPS Investment Director) to Martin Kelly (Primary Care Infrastructure Programme Director, Health and Social Care Board) on 14 th August Gross Internal Floor Area excluding communications space allowance DRAFT 1

4 1.6 The main thrust behind the development of the new PCCC is to enable greater management of chronic conditions in the community and closer to patients homes through the co-location and integration of GP practices with multi-disciplinary SEHSCT teams in a functionally suitable building. The Project involves the application of a new model of care utilising a hub and spoke approach, whereby the GP and SEHSCT teams located in the new PCCC facility are considered to be the hub and other individual GP practices in independent premises or smaller SEHSCT health centres within the local area are considered as spokes. 1.7 This hub and spoke model is core to enabling the development and implementation of the new model of service necessary to deliver on the many opportunities for improvement which have been identified under the Transforming Your Care ( TYC ) health service delivery reform agenda. 1.8 On 6 April 2012, the DHSSPS Permanent Secretary wrote to the SEHSCT advising that the Health Infrastructure Board ( HIB ) recommended fast tracking two large primary and community care infrastructure projects, one within the South Eastern Health and Social Care Trust area at Lisburn and one within the Southern Health and Social Care Trust area at Newry. The letter specifically requested the SEHSCT to complete the development of a Strategic Outline Case ( SOC ) and Outline Business Case ( OBC ) for the Lisburn Project, and also specifically highlighted the DHSSPS Minister s desire to seek alternative funding sources, where appropriate, to support the development of health infrastructure. 1.9 The SOC for the development of a PCCC in the Lisburn area was approved by the South Eastern Local Commissioning Group ( LCG ), DHSSPS and DFP within an approval letter dated 1 st August Subsequently the OBC for the Project was prepared by the SEHSCT in conjunction with the Strategic Investment Board ( SIB ) and the SIB s appointed specialist advisers. In accordance with the instruction from the DHSSPS Permanent Secretary this OBC tested alternative procurement routes, including the privately financed Third Party Development ( 3PD ) approach, for the delivery of the Project While the OBC concluded that procurement of a new PCCC facility on the Trust owned Lagan Valley Hospital site using conventional procurement was the lowest cost option in purely quantitative net present cost terms, it was highlighted in the commercial appraisal that that the feasibility of this preferred economic option was reliant on the availability of capital DEL budget in the required timeframes Due to the lack of Capital DEL budget available in the required timescales, the OBC financial analysis went on to suggest that the procurement of a new facility using 3PD had the potential to allow the development of the Lisburn PCCC to be progressed in the required timescales without the requirement for upfront capital DEL budget cover Furthermore, the OBC analysis highlighted that procurement under a 3PD solution provides the opportunity to test whether greater VFM can be achieved through seeking an alternative site for the PCCC through the procurement process. As such, the OBC concluded that while the site at the Lagan Valley Hospital should be retained as an option for prospective 3PD bidders, it would be important that tender documentation also affords bidders the opportunity to propose alternative sites so that any potential to improve VFM can be presented and evaluated by the SEHSCT, DHSSPS and DFP. DRAFT 2

5 1.14 The final version of the OBC was formally submitted to DHSSPS for review and approval following the completion of relevant Board approvals by the SEHSCT and the Health and Social Care Board ( HSCB ) in March While the OBC was not formally approved by the DHSSPS and DFP, the approval to commence a procurement process for the Lisburn Project as a Pathfinder scheme using a 3PD approach, was instead initiated through the issue of a Ministerial Direction from the then DHSSPS Minister (Edwin Poots) to the DHSSPS Permanent Secretary in April The procurement process for the Project was subsequently launched to the market in July 2013 using the EU Competitive Dialogue procurement procedure The 3PD approach involves a revenue funded partnership arrangement with a private sector developer as an alternative to funding from the traditional capital budget allocation. This will result in the SEHSCT entering into a contract for the design, build, finance and maintenance (hard facilities maintenance only) of the new PCCC facility for a lease term of 25 years. Alongside this, the SEHSCT shall enter into sub-lease arrangements with each of the GP practices that have agreed to re-locate to the new PCCC facility. The SEHSCT will then have an option to purchase the PCCC facility at the end of the 25 year term at a pre-agreed purchase price The innovative 3PD approach provided the private sector developers involved in the procurement process the opportunity to either utilise the SEHSCT Lagan Valley Hospital site or to propose their own site for the PCCC development within a certain Authority defined boundary of Lisburn town centre. It also envisaged that third party income ( TPI ) proposals, e.g. health care related or other complimentary retail services, might be incorporated into the proposed solutions brought forward by private sector developers through the procurement process, to improve the patient experience and/or to reduce the overall annual cost of the lease arrangement to the public purse This ABC provides full details of the various stages and outcomes of the 3PD pathfinder procurement process, and the remainder of this section provides a summary of each of the key sections of the ABC. Section 2: Update of the Outline Business Case 1.18 Section 2: Update of the Outline Business Case presents a summary of, and update to, the original OBC, to highlight the progress and changes made since the issue of the Ministerial Direction for the Project in April This section confirms that the strategic context and key objectives for the Project remain unchanged, subject to some minor updates to reflect additional supporting strategy published since the time of the preparation of the OBC along with some minor adjustments to the objectives to reflect the passage of time and minor changes in the overall scope of the Project Population and demographic factors will continue to place considerable pressure on SEHSCT and GP services in the Lisburn area going forward and the resultant need to rationalise the number of service locations and move out of the existing overcrowded accommodation, which is no longer functionally suitable. This section confirms the future service profile and staffing levels in the context of the proposed new integrated model of care for primary and community care centres (namely the hub and spoke model) and summarises a number of discrete DRAFT 3

6 changes to the OBC schedule of accommodation arising from the on-going stakeholder engagement process during the procurement process As a result of on-going GP engagement and correspondence, all GP Practices have now confirmed their intention to co-locate with the SEHSCT at the new PCCC facility. Given the positive confirmation received from the GP Practices, the ABC has been drafted on the assumption that all practices will be re-locating to the new CTCC building At OBC Stage, Option 4b: Lagan Valley Site - New Build on site occupied by Department of Psychiatry, IT Portacabins and Lagan View Conference Centre, was identified as the preferred option in economic terms. This ABC provides a comprehensive update of this preferred economic option and its associated costs to reflect both scope and time changes that have occurred since the OBC which impact on the Project. The quantitative analysis underpinning this ABC, estimate the Net Present Cost ( NPC ) of the Preferred Economic Option (at 01 April 2016 base date) to be 318m. Section 3: Authority Requirements 1.23 This section of the ABC sets out an overview of the Authority Requirements which were issued to Bidders, as part of the Invitation to Submit Final Tenders ( ISFT ) documentation. The Authority Requirements were to be addressed by Bidders as part of their final tender solutions A summary of the Authority s requirements, as detailed in this ABC, is set out below: Volume 1 - General Design and Organisational Principles: This is a design and technical document that set out the overarching design and organisational principles to be addressed by Bidders as they developed their design proposals for the new PCCC building; Volume 2, 3 & 4 Exemplar Information: These are a series of design and technical documents that provide the detailed room data sheets for the various clinical rooms, clinical support rooms and staff and social spaces listed within the Authority s schedule of accommodation (refer Volume 8). This includes details of requirements in regards to space, ceiling heights, air ventilation, lighting, noise, safety, finishes and typical fixtures, furniture and equipment requirements; Volume 5 - General Design and Construction Principles: This is a design and technical document that sets out the construction requirements for the facility; Volume 6 Design Standards: This is a design and technical document that sets out the expected design standards for the facility, and includes exemplar design information on the likes of finishes, fittings and furniture, way-finding, lighting, landscaping, security and artwork. It also includes exemplar room layout information and National Building Specification performance standards; Volume 7 Trust Design Brief: This sets out the SEHSCT s operational objectives and service requirements of the CTCC building and is to be read in conjunction with the other design and technical ITPD documents; Volume 8 Schedule of Accommodation: This sets out the required schedule of accommodation to be provided within the Bidders design on a room by room basis; and DRAFT 4

7 Volume 10 - Lease Schedule 6 (Services): This sets out the hard FM services requirements to be provided by Bidders within their proposed services solution for the operating phase of the Lease. Section 4: Overview of Procurement Process 1.25 This section of the ABC sets out details of the project organisation and governance arrangements that have been in place throughout the procurement process. It provides a summary of the key stages and timelines of the procurement process, including the management of the dialogue process with Bidders and how tenders have been evaluated at each of the key submission points throughout the process This section also includes an overview of the overall governance structure for the Project and extensive stakeholder engagement work undertaken throughout the procurement process and summarises the approach adopted to ensure that the Authority fulfils its statutory obligations in regards to Section 75 ( Equality ) The Lisburn PCCC Project was officially launched to the market in July 2013 and the procurement process undertaken to date, has comprised three distinct stages, as follows: Stage 1: Expressions of Interest and Pre-Qualification ( PQQ ) Stage - July 2013 to October 2013; Stage 2: Competitive Dialogue Stage - November 2013 to February 2015; and Stage 3: Final Tender Stage - February 2015 to June A total of 10 interested bidders responded to the Pre-qualification Questionnaire Package, with five bidders being shortlisted and invited to proceed to the next stage of the procurement process, i.e. the Competitive Dialogue Stage The Competitive Dialogue Stage was carried out over three distinct phases, Stage 2B, 2C and 2D which are summarised below: Stage 2B - The Invitation to Participate in Dialogue ( ITPD ) which incorporated the Invitation to Submit Outline Solutions (ISOS) was issued to the five shortlisted Bidders. Following initial dialogue with each of the five Bidders, the phase concluded with the submission and evaluation of the Stage 2B (ISOS) submissions and the shortlisting of the five Bidders down to three for the next stages of the procurement process; Stage 2C This stage commenced with an Invitation to Continue Dialogue ( ITCD ) being issued to the three Bidders remaining in the process following Stage 2B shortlisting. Following a series of dialogue meetings, each of the three Bidders were required to submit Stage 2C Interim Detailed Solution (ISDS) Submissions. These submissions were not formally evaluated by the Authority, but instead were used as a mechanism to provide structured feedback to each of the Bidders on their developing design and technical and financial solutions; and Stage 2D This stage commenced following the issue of feedback on the Stage 2C Interim ISDS Submissions. It involved a further series of dialogue with the three Bidders culminating in the submission of Stage 2D Detailed Solution submissions which were formally evaluated DRAFT 5

8 by the Authority and its advisors. While no further shortlisting was undertaken as part of the Stage 2D evaluation, detailed feedback was provided to each of the Bidders on all aspects of their Stage 2D submission. Following further dialogue with each of the Bidders this stage was completed with the formal close of dialogue, and all three bidders were invited on 27 February 2015 to submit Final Tenders by 23 March All three Bidders duly submitted Final Tender submissions by the required tender submission deadline. Section 5: Final Tender Evaluation 1.31 Section 5: Final Tender Evaluation provides an overview of the Final Tender Evaluation process undertaken by the SEHSCT in conjunction with the specialist advisers. This section provides an outline of the evaluation process, the award criteria applied, a summary of the work of the various evaluation panels and the overall results of the Final Tender evaluation Final Tender submissions were evaluated in accordance with the award criteria for Final Tenders, as set out in Volume 14 of the Invitation to Submit Final Tenders ( ISFT ) documentation, and which are summarised below: Award Criteria Weighting (%) Design and Technical 20 Financial 75 Legal 05 Total The overall final tender evaluation process for Design and Technical, Financial and Legal teams comprised four main stages to include initial review, issue of clarifications, assessment of relevant components and evaluation sign off An overview of these stages is set out below: Stage 1: Initial Review - CPD Health Projects ( CPD HP ) (formerly DHSSPS Health Estates) undertook an initial review of the Final Tender submissions for completeness and compliance. All of the Final Tender submissions passed the initial review check and were duly subjected to detailed evaluation; Stage 2: Clarifications - Throughout the Final Tender evaluation process the Authority reserved the right to ask Bidders to clarify aspects of their Final Tenders, as considered necessary. Where deemed required by the evaluation panels, written clarifications were issued to Bidders on particular aspects of their Final Tender submissions. The responses received from the clarifications were then considered as part of the Final Tender evaluation process; Stage 3: Assessment - The evaluation panels (namely design & technical, legal, and financial) assessed the relevant components of the Final Tender submissions (along with the responses to any clarifications issued thereon), in accordance with the award criteria DRAFT 6

9 for Final Tenders. Each panel then documented the outcomes of their evaluation work in an appropriate report format for submission to the evaluation co-ordinator at CPD HP; and Stage 4: Evaluation Sign Off - The outcomes of the work of each of the evaluation panels was consolidated into a summary document by the CPD HP evaluation co-ordinator, which set out the outcomes of the overall Final Tender evaluation process for ratification by the Sign Off Group. The Sign Off Group then met with the chairs of each of the evaluation panels to confirm that the evaluation had been appropriately conducted in line with the award criteria for Final Tender and to agree the recommended Preferred Bidder A recommended Preferred Bidder was agreed at the Sign Off Group meeting held on 7th May Sections 6 and 7 of the ABC were then completed on the basis of the outcome from the Sign off Group meeting. Section 6: Value for Money 1.36 This section of the ABC sets out details of the overall Value for Money ( VFM ) assessment for the Project. The VFM assessment comprises both quantitative assessment and an assessment of the qualitative impact of a Conventional Procurement Option ( CPO ), compared to the 3PD solution proposed by the recommended Preferred Bidder The detailed quantitative VFM assessment is based on financial appraisal and not economic appraisal and focusses on a comparison of the Net Present Cost ( NPC ) of the direct financial costs to Northern Ireland of conventional procurement, compared to the NPC of the 3PD solution presented by the recommended Preferred Bidder The CPO financial model presented at OBC stage, has been updated to reflect the refinements made to the Authority Requirements (including Schedule of Accommodation) during the procurement process and the current forecast timetable for the Project. An overview of the key changes to the bases and assumptions underpinning the OBC stage CPO financial model (provided by CPD Health Projects, SEHSCT and specialist technical advisers) to derive the CPO financial model used to inform the ABC stage quantitative VFM assessment, is set out in the ABC The results of the quantitative VFM assessment, presented in the table below, clearly show that 3PD is the best VFM procurement route for the delivery of the Lisburn CTCC Project. Table 1.1: Quantitative VFM Assessment (Comparison of recommended Preferred Bidder s NPC to NPC of CPO at ABC Stage) NPC ( 000) 1 April 2016 CPO NPC 42,627 Recommended Preferred Bidder s NPC of Annual Service Payments and Purchase 34,558 Price on Draft Lease Expiry Total (Cost)/Saving from an NI perspective ( 000) 8,069 Total (Cost)/Saving from an NI perspective (%) 18.9% DRAFT 7

10 1.40 The key reasons for the turnaround in the quantitative VFM assessment since OBC stage, include: improved liquidity in the financial markets and a fall in the all-in cost of debt finance; 3PD solution market test outturn capital costs, lifecycle costs and maintenance costs; and appetite of 3PD contractors to guarantee third party income. Section 7: Affordability and Accounting Treatment 1.41 Section 7 of the ABC sets out the expected accounting and budgetary treatments of the proposed 3PD solution DHSSPS have considered the likely accounting treatment for the Lisburn PCCC Project and provided a preliminary view, indicating that SEHSCT will record the infrastructure assets constructed as part of the Project on its balance sheet For national accounting and departmental budgeting purposes, the treatment of the Project is governed by European System of National and Regional Accounts ( ESA 10 ) and the Manual on Government Deficit and Debt ( MGDD ) Based on the results of the Financial and Legal Evaluation of Final Tender submissions, it is anticipated that the proposed 3PD Draft contract will remain off balance sheet for budgetary purposes. An off balance sheet outcome means that the stream of Annual Payments sought by the Preferred Bidder over the 25 year term of the contract, can be serviced from Resource budgets and therefore, the 3PD solution will not be reliant on upfront Capital budget cover The national accounting and budgetary treatment of the proposed 3PD contract will continue to be monitored as the contractual documentation is refined following Preferred Bidder appointment and the Project progresses towards financial close, currently estimated to occur in April The forecast budgetary requirement to deliver the Project comprises Capital budget to fund the elements of the Project being conventionally procured and Resource DEL to fund the elements currently included within the scope of the proposed 3PD contract Capital budget cover of c. 6.7m (in nominal terms) is required from DHSSPS over the first three years (2016/17 to 2018/19) of the Project to fund the following: Enabling Works in respect of the Lagan valley Hospital site (with the exception of site clearance works - where these costs exceed the uplift in the underlying value of the land, they will need to be partly funded by Resource budget); Supply of ICT equipment; and Supply of Group 2 and 3 Equipment. Thereafter, capital budget cover would be required for equipment replacement (Groups 2, 3 and ICT) costs in line with normal refresh programmes during the 25 year Lease term. DRAFT 8

11 1.48 Table 1.2 highlights that annual resource budget cover of c. 3.3m (in nominal terms) would be required over the first four years of the 3PD Lease. This rises to c. 4.7m in the fifth year of the Lease, predominantly due to increased staff and goods and services costs arising due to the forecast change in demographics. The annual resource budget cover is estimated to peak at 6.6m in the final year of the 25 year Lease term, should the SEHSCT exercise its option to purchase the CTCC premises upon Lease expiry. The cost of the CTCC premises as per the recommended Preferred Bidder s solution has been estimated as 3m. Table 1.2 Forecast Budgetary Impact of the recommended Preferred Option DEL Statement Year /2017 Year /2018 Year /2019 Year /2020 Year /2021 Year /2022 Year /2023 Year /2024 Year /2025 Year / year Total '000 '000 '000 '000 '000 '000 '000 '000 '000 '000 '000 Total DEL Required Total Capital DEL Required 3,449 3, (850) , ,046 9,231 Total Resource DEL Required 14,535 14,421 18,238 18,504 18,917 19,339 21,107 21,584 22,073 22, ,291 Existing DEL Provision Existing Capital DEL Provision Existing Resource DEL Provision 14,107 14,460 14,822 15,192 15,572 15,961 16,360 16,769 17,188 17, ,050 Additional DEL Required Additional Capital DEL required 3,449 3, (850) , ,046 9,231 Additional Resource DEL required 427 (39) 3,416 3,312 3,345 3,378 4,746 4,815 4,884 4,956 33, The additional resource budget cover required by SEHSCT over the 25 year lease term will be partially offset by income received from the GP s in respect of their contribution to the stream of annual service payments sought by the 3PD contractor and the utilities costs and rates payable in respect of the Lisburn PCCC facility The estimated contribution of the GPs towards the stream of annual service payments sought by the 3PD contractor and towards the utilities rates payable in respect of the Lisburn PCCC facility, is currently based on a preliminary PCCC shared space allocation that will be subject to further review and refinement at FBC stage to reflect the final agreed design and associated floor plans relating to the Preferred Bidder s 3PD solution The HSCB funding arrangement agreed with GPs for the Project when coupled with the preliminary shared space allocation, indicates that additional resource budget cover of c. 0.4m per annum will be required in respect of the GP s contribution, from the date the Lease commences (2018/2019). This is in addition to the c. 0.3m of GP reimbursements currently covered by HSCB in respect of GP accommodation within the existing Lisburn Health Centre. DRAFT 9

12 Section 8: Contractual Structure 1.52 This section of the ABC sets out a summary of the main contractual and legal arrangements that are expected to be put in place between the 3PD Contractor and the SEHSCT (the Authority ) for the Lisburn PCCC Project Furthermore, the section also notes that based on a review of financial information presented in the Final Tender stage bid submitted by the recommended Preferred Bidder, their proposed 3PD solution is considered to be bankable. In particular, the recommended Preferred Bidder s proposed solution is deemed to sufficiently developed and robust and there is sufficient support and commitment from debt providers and investors at Final Tender stage, to satisfy the Authority that there is no material risk on financial grounds of a failure to enter into the Agreement for Lease and Lease. Section 9: Risk Allocation 1.54 This section of the ABC provides a summary of the principal risks associated with the Lisburn PCCC Project, to include a discussion on the overall approach to risk transfer and a summary of the proposed risk allocation between the SEHSCT and the 3PD Contractor underpinning the contractual documents in the form of a series of risk matrices The main category of risk retained by the SEHSCT include financial risks and in particular, the ability of the SEHSCT to meet the funding obligations associated with the service payments, purchase price on early termination or other Project related costs, for example, utilities, rates and insurance costs The key categories of risks retained by the 3PD Contractor include design, construction and development and operational risks. Design Risks the ability of the 3PD Contractor to control the design process post after preferred bidder appointment and to deliver a design solution that fully meets the SEHSCT s requirements; and Construction and Development the ability of the 3PD Contractor to control the construction and development programme for the new Lisburn CTCC facility Operating Risks the ability of the 3PD Contractor to make the CTCC facility available for the use to which it intended during the 25 year contract period and therefore avoid triggering unavailability events and the associated financial deductions that would be applied to the 3PD Contractor s Service Payment The section also includes a summary of the risk register being maintained and managed by the SEHSCT via the Project governance arrangements, in particular highlighting the key risks to the Project which remain in SEHSCT ownership and the mitigation strategies identified for these risks. DRAFT 10

13 Section 10: Post Project Evaluation and Benefits Realisation 1.58 This section describes the structures and procedures that will be in place to manage and monitor the Project from Preferred Bidder appointment onwards. Organisational Arrangements 1.59 The internal organisational structures and arrangements that will support the activities to be undertaken during the Preferred Bidder stage, and subsequently during both the construction and operational phase of the Lisburn PCCC Project are summarised below: Preferred Bidder Stage - The organisational arrangements for the management and monitoring of activities to be undertaken during the Preferred Bidder stage shall continue in line with the project governance and management arrangements applied by the SEHSCT during the procurement phase; Construction Stage - It is expected that the existing Project level governance and management arrangements applied by the SEHSCT during the procurement shall continue to apply throughout the construction phase of the Project, albeit the frequency of the meetings of the HIB Procurement Sub-group may reduce during this period; SEHSCT Commissioning Phase - In the circa 2 to 3 month period following building completion and handover the SEHSCT Project Team shall be responsible for undertaking post-completion commissioning activities; Operation Stage - Following completion of the construction phase and the signature of the Lease and Sub-Lease agreements, responsibility for day-to-day management of the Lease with the Contractor (and Sub-Lease arrangements with the GPs) shall rest with a nominated SEHSCT Contract Manager. Benefits Management 1.60 This section also details the anticipated project benefits as well as the arrangements for benefits realisation and sets out the draft Benefits Realisation Plan, which has been devised to facilitate the management and delivery of the agreed benefits. This plan identifies the expected benefits, the timing of the benefits, a means of measuring the achievement of each expected benefit, and the party responsible for each benefit realisation activity Each benefit is assigned to an operational owner who is responsible for the measurement and reporting level of achievement against the profile. The Project Board will monitor the realisation of benefits under the direct control of the SEHSCT Section 11: Process from Preferred Bidder to Contract Award 1.62 This section of the ABC sets out details of the key activities and timelines associated with the process of moving from Preferred Bidder to Contract Award, to include estimated implementation timescales for contract award, construction works, and operation commencement based on the programme outlined in the Preferred Bidder s Final Tender Details are also provided in respect of the following: Preferred Bidder appointment, including the Alcatel period and bidder debriefing; DRAFT 11

14 Requirements for full planning and judicial review periods; Interaction with the Preferred Bidder on reviewable design data process, contractual fine tuning, benchmarking of funding terms and financial model audit requirements; Engagement with GPs by HSCB and SEHSCT; Preparation, submission and approval of the Full Business Case; and Preparation for contract award /financial close The section also highlights the interdependencies with the Enabling Works programme that will be undertaken by the SEHSCT both during the period from Preferred Bidder appointment to contract award and subsequent to contract award and commencement of 3PD contractor construction works On the assumption that the ABC is approved in June 2015 and contract award occurs on 1 st April 2016, the table below provides a high level overview of the key project implementation milestone dates, as estimated based on the details included within the recommended Preferred Bidder s Final Tender submission It should be noted that table below table reflects the three month period required for the completion of the Enabling Works by the SEHSCT subsequent to contact award/financial close, and assumes that the recommended Preferred Bidder s construction programme (as set out within their Final Tender submission received on 23 March 2015) moves out by 3 months as a consequence. Milestone Target Date Contract Award & Financial Close April 2016 Completion of Enabling Works by SEHSCT(i.e. red line site available for handover to 3PD Contractor) & 3PD Contractor Construction Works Commencement July 2016 Practical Completion (i.e. handover by 3PD Contractor) 00July 2018 Term Commencement Date* J00uly 2018 *Being the date 5 days after Practical Completion when the Annual Service Payment to the 3PD Contractor becomes payable by the Authority Section 12: Conclusions and Recommendations 1.67 This ABC reaffirms the strategic drivers for the PCCC as outlined in the OBC, and provides an update on the Project since procurement commencement in This ABC is ultimately seeking approval for the appointment of the recommended Preferred Bidder (as identified through the procurement process) and confirmation that the capital and resource budget cover required for the Lisburn PCCC will be made available There may be additional costs associated with the PCCC which are not factored into the capital and resource budgetary impact analysis presented within the ABC. Such costs may arise, for DRAFT 12

15 example, due to higher than expected inflation, accelerated delivery of the PCCC (and therefore a slightly longer Lease term), construction inflation uplift due to SEHSCT enabling works delays or early termination. The Authority will ensure that DHSSPS and HSCB are given as much notice as possible if it appears likely that additional funding will be required to cover these costs This ABC is being submitted to SEHSCT Board, HSCB Board and DHSSPS for consideration. Thereafter, an update will be provided to the Minister and approval will be sought to progress the Project with the recommended Preferred Bidder. DRAFT 13

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case Greater Bristol Bus Network Major Scheme Business Case Chapter 1 Developing the Full Approval Major Scheme Business Case i ii 1. The Case for Full Approval INTRODUCTION 1.1.1 Bath and North East Somerset,

More information

2015/16 Savings Plan 2 April 2015

2015/16 Savings Plan 2 April 2015 2015/16 Savings Plan 2 April 2015 CONTENTS Section Page 1 DHSSPS Financial Plan for 2015/16 3 2 Implications of DHSSPS Financial Plan for the Western Trust 3 3 Financial Context 3 4 Indicative Workforce

More information

Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009

Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009 Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009 1 CHAPTER 1 EXECUTIVE SUMMARY 1.1 Introduction 1.1.1 This document sets out the Strategic content and Outline Business Case

More information

Date of Issue: 6 th June 2013

Date of Issue: 6 th June 2013 Subject: GUIDANCE ON THE COMPLETION OF REVISED REVENUE BUSINESS CASE TEMPLATES AND POST PROJECT EVALUATION For Action by: Chief Executive of HSC Bodies and NIFRS Directors of Finance of HSC Bodies and

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

Invitation to eahsn.org. Eastern Academic Health Science Network Finance Function Date of issue: 4 September 2017

Invitation to eahsn.org. Eastern Academic Health Science Network Finance Function Date of issue: 4 September 2017 Invitation to Tender Eastern Academic Health Science Network Finance Function Date of issue: 4 September 2017 eahsn.org @TheEAHSN About the Eastern Academic Health Science Network Galvanising people to

More information

Public Private Partnerships in the National Health Service: The Private Finance Initiative

Public Private Partnerships in the National Health Service: The Private Finance Initiative Public Private Partnerships in the National Health Service: The Private Finance Initiative Good Practice Section 3: Technical Issues Contents 1. Introduction 3 2. Risk analysis 4 3. The Public Sector Comparator

More information

CIoS System Strategic Estates Group Briefing

CIoS System Strategic Estates Group Briefing CIoS System Strategic Estates Group Briefing Transformation Board 17/01/2019 Jackie Pendleton, Chief Executive Lead Karl Simkins, CIoS Chief Finance Officer & Estates SRO Final Strategic Estates Group

More information

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES)

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES) Prop Co (NO APPENDICES) 1 CONTENTS 1 Context 4 2 Overview of PropCo 5 2.1 Form of PropCo 5 2.2 Scope of PropCo 5 2.3 Included services 6 2.4 Excluded services 6 2.5 Services to be included subject to confirming

More information

Financing the future HSC achieving sustainability?

Financing the future HSC achieving sustainability? Financing the future HSC achieving sustainability? Julie Thompson Senior Director of Finance, DoH NI Owen Harkin - Vice Chair of HFMA and Director of Finance, NHSCT The Story so Far DHSSPS Policy & Strategy

More information

REPROVISION OF ROOKWOOD NEURO AND SPINAL REHABILITATION

REPROVISION OF ROOKWOOD NEURO AND SPINAL REHABILITATION AGENDA ITEM 2.2 15 May 2012 REPROVISION OF ROOKWOOD NEURO AND SPINAL REHABILITATION Report of Paper prepared by Director of Finance Director of Finance Executive Summary The update report summarises the

More information

Finance, Performance & Resources Committee

Finance, Performance & Resources Committee Finance, Performance & Resources Committee DATE OF MEETING: 31 October 2017 TITLE OF REPORT: Financial Outlook 2018/19 2022/23 EXECUTIVE LEAD: Carol Potter, Director of Finance REPORTING OFFICER: Rose

More information

DIRECTORATE OF ESTATES AND FACILITIES

DIRECTORATE OF ESTATES AND FACILITIES DIRECTORATE OF ESTATES AND FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006

More information

Date: Humber NHS Foundation Trust Estate Strategy December 2016 Review. To approve To ratify To consider To note

Date: Humber NHS Foundation Trust Estate Strategy December 2016 Review. To approve To ratify To consider To note Agenda Item: 10.2 Title of Meeting: Trust Board Public Meeting Date: 7 December 2016 Report on Humber NHS Foundation Trust Estate Strategy 2015-2020 December 2016 Review Status of the Report To approve

More information

Capital Project Approval Request

Capital Project Approval Request Capital Project Approval Request PMP T07 Project Number MAJ 0000 Project Title Project Description Existing Approvals EC Approval Court Approval Approved Gateway 0 To proceed to GW1 Prepare OBC / Feasibility

More information

MPA/MPS Capital Strategy

MPA/MPS Capital Strategy Appendix 1 MPA/MPS Capital Strategy 2005 2010 July 2004 Draft Page 1 of 13 Contents Section 1 Context sheet Page General 3 Capital and Revenue Budgets 3 Section 2 Capital Strategy Introduction 5 Strategic

More information

HUB PROGRAMME DELIVERY OFFICE GUIDANCE NOTE

HUB PROGRAMME DELIVERY OFFICE GUIDANCE NOTE HUB PROGRAMME DELIVERY OFFICE GUIDANCE NOTE Implementation of Performance Metrics for Primary Health Care 29 th October 2013 Versions 1.0 CONTENTS 1. OVERVIEW... 2 2. AREA PERFORMANCE MEASUREMENTS... 3

More information

SOUTH EASTERN HEALTH & SOCIAL CARE TRUST

SOUTH EASTERN HEALTH & SOCIAL CARE TRUST SOUTH EASTERN HEALTH & SOCIAL CARE TRUST Minutes of a meeting of the Audit Committee held on Thursday 3 December 2015 at 12.00 noon in the Boardroom, Trust Headquarters, Ulster Hospital PRESENT: IN ATTENDANCE:

More information

Weston Package Phase 1 Major Scheme Business Case. The Financial Case. Scheme cost, financial risk and funding sources

Weston Package Phase 1 Major Scheme Business Case. The Financial Case. Scheme cost, financial risk and funding sources Weston Package Phase 1 Major Scheme Business Case 6 The Financial Case Scheme cost, financial risk and funding sources 6.1 Introduction This Section sets out how the council proposes to finance the Weston

More information

Zero Waste: Edinburgh and Midlothian - Award of Food Waste Treatment Contract

Zero Waste: Edinburgh and Midlothian - Award of Food Waste Treatment Contract The City of Edinburgh Council 10.00 am, Thursday 13 December 2012 Zero Waste: Edinburgh and Midlothian - Award of Food Waste Treatment Contract Item number Report number Wards City wide Links Coalition

More information

CABINET FUTURE DELIVERY OF FACILITY MANAGEMENT SERVICES

CABINET FUTURE DELIVERY OF FACILITY MANAGEMENT SERVICES Report No: 172/2017 PUBLIC REPORT CABINET 19 th September 2017 FUTURE DELIVERY OF FACILITY MANAGEMENT SERVICES Report of the Director for Places Strategic Aim: Sound financial planning and workforce planning

More information

Irish Water 2019 Revenue Control

Irish Water 2019 Revenue Control An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Irish Water 2019 Revenue Control Information Paper Reference: CRU/17/332 Date Published: 07/12/2017 www.cru.ie Executive Summary The

More information

Manchester Health and Care Commissioning. Finance Committee. Terms of Reference

Manchester Health and Care Commissioning. Finance Committee. Terms of Reference Manchester Health and Care Commissioning Finance Committee Terms of Reference 1.0 Name The Committee shall be known as the Finance Committee. 2.0 Overview The Finance Committee forms a key element of the

More information

Contract Award for Enablement (contract reference: 50259) and Home and Community Support (contract reference: 50254) Cabinet Member for Adults

Contract Award for Enablement (contract reference: 50259) and Home and Community Support (contract reference: 50254) Cabinet Member for Adults AGENDA ITEM: 5 Pages 1 11 Meeting Cabinet Resources Committee Date 19 July 2010 Subject Report of Summary Contract Award for Enablement (contract reference: 50259) and Home and Community Support (contract

More information

OFFICE FOR STANDARDS IN EDUCATION, CHILDREN S SERVICES AND SKILLS

OFFICE FOR STANDARDS IN EDUCATION, CHILDREN S SERVICES AND SKILLS PARLIAMENTARY MEMORANDUM 2018-19 Main Estimate OFFICE FOR STANDARDS IN EDUCATION, CHILDREN S SERVICES AND SKILLS Introduction Ofsted s Main Estimate 2018-19 seeks the necessary resources and cash to inspect

More information

NORTHERN IRELAND FIRE & RESCUE SERVICE BOARD MINUTES OF A MEETING 30 JUNE PM

NORTHERN IRELAND FIRE & RESCUE SERVICE BOARD MINUTES OF A MEETING 30 JUNE PM NORTHERN IRELAND FIRE & RESCUE SERVICE BOARD MINUTES OF A MEETING 30 JUNE 2015 1.30 PM PRESENT: Dr J McKee, Chairman presiding Mr D Ashford, Interim Chief Fire & Rescue Officer Mr J Barbour Cllr M Carr

More information

NORTHERN IRELAND FIRE & RESCUE SERVICE BOARD MINUTES OF A MEETING 31 MARCH AM

NORTHERN IRELAND FIRE & RESCUE SERVICE BOARD MINUTES OF A MEETING 31 MARCH AM NORTHERN IRELAND FIRE & RESCUE SERVICE BOARD MINUTES OF A MEETING 31 MARCH 2015 10.00 AM PRESENT: Dr J McKee, Chairman presiding Mr C Kerr, Interim Chief Fire Officer Cllr D Barbour Mr J Barbour Cllr M

More information

Transactions guidance for trusts undertaking transactions, including mergers and acquisitions

Transactions guidance for trusts undertaking transactions, including mergers and acquisitions Transactions guidance for trusts undertaking transactions, including mergers and acquisitions November 2017 We support providers to give patients safe, high quality, compassionate care within local health

More information

Metz Way to Abbeymead Avenue Improvements: Full Business Case and Due Diligence Assessment Report

Metz Way to Abbeymead Avenue Improvements: Full Business Case and Due Diligence Assessment Report Capability Gloucestershire County Council August, 2016 Metz Way to Abbeymead Avenue Improvements: Full Business Case and Due Diligence Assessment Report Prepared by:... Checked by:... Stephen Payne Nick

More information

Office of Qualifications and Examinations Regulation (Ofqual) Supplementary Estimate 2018/19

Office of Qualifications and Examinations Regulation (Ofqual) Supplementary Estimate 2018/19 Office of Qualifications and Examinations Regulation (Ofqual) Supplementary Estimate 2018/19 Memorandum to the Education Select Committee January 2019 1 Contents Overview... 3 Objectives... 3 Spending

More information

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL EUROPEAN COMMISSION Brussels, 20.12.2011 COM(2011) 907 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL PROGRESS REPORT ON THE DEVELOPMENT OF THE SECOND GENERATION SCHENGEN INFORMATION

More information

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS

BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS BENCHMARKING PPP PROCUREMENT 2017 IN MAURITIUS Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. If yes, please specify the relevant regulatory

More information

Audit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 2

Audit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 2 Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 2 Leaders in building public trust in civic government Audit Department TABLE OF CONTENTS History...5

More information

11.2 From Strategic Outline Case to Outline Business Case and Full Business Case

11.2 From Strategic Outline Case to Outline Business Case and Full Business Case CHAPTER ELEVEN - PROCUREMENT ISSUES 11.1 Introduction 11.1.1 This section of the Business Case sets out the key procurement issues for the Trust. It examines the procurement which the Trust has in place

More information

NORTHERN IRELAND COURTS AND TRIBUNALS SERVICE: ADEQUACY OF THE COURTS ESTATE. A follow-up review of inspection recommendations

NORTHERN IRELAND COURTS AND TRIBUNALS SERVICE: ADEQUACY OF THE COURTS ESTATE. A follow-up review of inspection recommendations NORTHERN IRELAND COURTS AND TRIBUNALS SERVICE: ADEQUACY OF THE COURTS ESTATE A follow-up review of inspection recommendations July 2015 NORTHERN IRELAND COURTS AND TRIBUNALS SERVICE: ADEQUACY OF THE COURTS

More information

ScotWind leasing - new offshore wind leasing for Scotland

ScotWind leasing - new offshore wind leasing for Scotland November 2018 ScotWind leasing - new offshore wind leasing for Scotland Summary of Discussion Document responses and update on leasing design In May 2018 we published a Discussion Document setting out

More information

HPV Health Purchasing Policy 1. Procurement Governance

HPV Health Purchasing Policy 1. Procurement Governance HPV Health Purchasing Policy 1. Procurement Governance Establishing a governance framework for procurement 25 May 2017 1 Health Purchasing Policy 1. Procurement Governance Health Service Compliance Health

More information

Meeting of the City Council 18 September 2013

Meeting of the City Council 18 September 2013 Agenda Item No: 8 Meeting of the City Council 18 September 2013 Report Title Approval of Financial Close and Contract Award for Building Schools for the Future (BSF) Phase 3C Scheme Schools Referring Body

More information

Sandwell and West Birmingham Hospitals NHS Trust Midland Metropolitan Hospital Project

Sandwell and West Birmingham Hospitals NHS Trust Midland Metropolitan Hospital Project Sandwell and West Birmingham Hospitals NHS Trust Midland Metropolitan Hospital Project Outline Business Case Appendix 10b VfM Assessment SWBTB (9/13) 199 (PR) DOCUMENT TITLE: SPONSOR (EXECUTIVE DIRECTOR):

More information

MAYORAL RECOMMENDATION CITY PUBLIC M/6. Director: Ged Fitzgerald Chief Executive. Cabinet Member: Joe Anderson OBE Mayor of Liverpool

MAYORAL RECOMMENDATION CITY PUBLIC M/6. Director: Ged Fitzgerald Chief Executive. Cabinet Member: Joe Anderson OBE Mayor of Liverpool MAYORAL RECOMMENDATION CITY PUBLIC M/6 Cabinet Member: Joe Anderson OBE Mayor of Liverpool Director: Ged Fitzgerald Chief Executive Becky Hellard Director Finance & Resources Date of submission: 24th October

More information

2018/19 Planning, Commissioning Intentions and Governing Body Assurance Framework

2018/19 Planning, Commissioning Intentions and Governing Body Assurance Framework 2018/19 Planning, Commissioning Intentions and Governing Body Assurance Framework Governing Body meeting 11 January 2018 G Author(s) Sponsor Director Purpose of Paper Abigail Tebbs, Deputy Director of

More information

Children and Young People s Services Committee Thursday 4 October 2018

Children and Young People s Services Committee Thursday 4 October 2018 Children and Young People s Services Committee Thursday 4 October 2018 CYPS/11/18/3 Board Room, Education Authority (Antrim) 10.30 am Present In Attendance Apologies Mrs P Carville (Chair), Rev A Adams,

More information

ELLESMERE PORT ONE PUBLIC ESTATE. Summary

ELLESMERE PORT ONE PUBLIC ESTATE. Summary ELLESMERE PORT ONE PUBLIC ESTATE Summary 1. At its meeting on 21 November, the P&I Committee had a short report on progress with the Ellesmere Port One Public Estate (OPE) programme and concluded that

More information

Cabinet. 27 July Classification: Part Exempt (Appendix 1 Exempt) Report of: Corporate Director Place. Housing Capital Projects: Pipeline schemes

Cabinet. 27 July Classification: Part Exempt (Appendix 1 Exempt) Report of: Corporate Director Place. Housing Capital Projects: Pipeline schemes Cabinet 27 July 2017 Report of: Corporate Director Place Classification: Part Exempt (Appendix 1 Exempt) Housing Capital Projects: Pipeline schemes Lead Member Originating Officer(s) Wards affected Community

More information

Investment Appraisal Framework

Investment Appraisal Framework Investment Appraisal Framework Version 6 Revised: August 2017 Review date: July 2018 1 1 Introduction 1.1. NHS foundation trusts (FTs) were created as new legal entities in the form of public benefit corporations

More information

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management 1. Purpose of policy This policy deals with the tendering for all types of expenditure undertaken by Andium Homes, including:

More information

NHS Planning Guidance 2016/ /21

NHS Planning Guidance 2016/ /21 NHS Planning Guidance 2016/17 2020/21 Trust Board Meeting Item: 13 Date: 27 th January 2016 Purpose of the Report: Enclosure: I1 To provide the Board with a summary of the NHS Annual Planning Guidance

More information

Strategic Business Case. Estates Guidance and Activity DataBase

Strategic Business Case. Estates Guidance and Activity DataBase Strategic Business Case Estates Guidance and Activity DataBase November 2016 You may re-use the text of this document (not including logos) free of charge in any format or medium, under the terms of the

More information

Procurement Functional Leadership Quarterly Report, January to March 2014

Procurement Functional Leadership Quarterly Report, January to March 2014 OFFICE OF THE MINISTER FOR ECONOMIC DEVELOPMENT Chair State Sector Reform and Expenditure Control Cabinet Committee Procurement Functional Leadership Quarterly Report, January to March 2014 Proposal 1

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

NSS AUDIT AND RISK COMMITTEE 28 MARCH 2018

NSS AUDIT AND RISK COMMITTEE 28 MARCH 2018 minutes (APPROVED) B/18/91 NHS NATIONAL SERVICES SCOTLAND (NSS) MINUTES OF AUDIT AND RISK COMMITTEE MEETING HELD ON WEDNESDAY 28 MARCH 2018 IN BOARDROOM 2, GYLE SQUARE, EDINBURGH COMMENCING AT 1035HRS

More information

Regulatory Impact Analysis

Regulatory Impact Analysis Regulatory Impact Analysis For the Establishment of a Registration Authority to administer the Statutory Register for Registered Architectural Technologists under The Building Control Act 2007 Page 1 of

More information

16 th November 2018 INVESTMENT INTO COMMUNITY PHARMACY SERVICES

16 th November 2018 INVESTMENT INTO COMMUNITY PHARMACY SERVICES To: Community Pharmacy NI (CPNI) Community Pharmacy Contractors Directorate of Integrated Care Western Office Gransha Park House 15 Gransha Park Clooney Road Londonderry BT47 6FN Tel : 028 9536 3375 Fax

More information

Page Paragraph Content Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement

Page Paragraph Content Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement Page Paragraph Content 3 1-3 Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement 4 8-10 Competition 11 Best value for money 12 Timeliness in paying bills 13 Novel, contentious or

More information

Joint Primary Care Committee 1:00 pm - 23 February 2017 Coach House, Worcester

Joint Primary Care Committee 1:00 pm - 23 February 2017 Coach House, Worcester Agenda item 6 Joint Primary Care Committee 1:00 pm - 23 February 2017 Coach House, Worcester Title of Report Report author Presented by Target CCG Recommendation Purpose GP Access Fund Re-Procurement Denise

More information

Rotherham CCG Interim Strategic Estates Plan September 2015

Rotherham CCG Interim Strategic Estates Plan September 2015 Rotherham CCG Interim Strategic Estates Plan September 2015 Notes to Strategic Estates Plan This document has been produced by NHS PS in conjunction with the NHS Rotherham CCG, NHS England and other NHS

More information

Audit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2017 Qtr 1

Audit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2017 Qtr 1 Audit Department Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2017 Qtr 1 To be leaders in building public trust in our civic government TABLE OF CONTENTS History...1

More information

2017/2018 Financial Planning

2017/2018 Financial Planning 2017/2018 Financial Planning Savings Plan Consultation Document 24 August 2017 Alternative Formats: Some people may need this information in a different format for example a minority language, easy read,

More information

PCRS Operational Plan

PCRS Operational Plan 2018 PCRS Operational Plan Draft Contents Introduction... 2 Primary Care Reimbursement Service... 2 Priorities for 2018... 2 ew Developments... 2 Risks... 3 Overview... 4 Targets for 2018... 4 Key Project

More information

CENTRAL MANCHESTER UNIVERSITY HOSPITALS NHS FOUNDATION TRUST

CENTRAL MANCHESTER UNIVERSITY HOSPITALS NHS FOUNDATION TRUST CENTRAL MANCHESTER UNIVERSITY HOSPITALS NHS FOUNDATION TRUST Agenda Item 8.2 Report of: Paper prepared by: Executive Director of Strategy Director Single Hospital Service Programme Date of paper: 13 March

More information

Decision on Electricity Network Connection Policy

Decision on Electricity Network Connection Policy Decision on Electricity Network Connection Policy DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/09/138 25 August 2009 John Orme (distribution@cer.ie) The Commission for Energy

More information

St Oliver Plunkett Primary School. C2k Contracts & Finance Manager, C2k Implementation and Communications Manager, C2k

St Oliver Plunkett Primary School. C2k Contracts & Finance Manager, C2k Implementation and Communications Manager, C2k MINUTES OF THE C2K PROJECT BOARD MEETING HELD AT C2K HEADQUARTERS TUESDAY 12 TH JANUARY 2010 Present: Mr B Mulholland Mr J Stewart Mr G Byrne Mr R Hanna Ms S Lawler Mr J Wilkinson Mr F Devenny Mr P Mackey

More information

Annex 8. Project Assurance Recommendations

Annex 8. Project Assurance Recommendations Annex 8 Project Assurance Recommendations Contents 1. Project Review Report 2. Recommendations and actions Taken 3. Project Board Roles and Responsibilities This page is intentionally blank BRT North -

More information

Present: Brian McMurray (Chair) In Paddy Anderson (Director of Finance) Geraldine Fahy Attendance: Catherine McKeown (Head of Internal Audit)

Present: Brian McMurray (Chair) In Paddy Anderson (Director of Finance) Geraldine Fahy Attendance: Catherine McKeown (Head of Internal Audit) NORTHERN IRELAND HEALTH AND SOCIAL CARE BUSINESS SERVICES ORGANISATION GOVERNANCE AND AUDIT COMMITTEE Minutes of the Governance and Audit Committee (GAC) which took place on Tuesday, 8 October 2013 at

More information

Audit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 3

Audit Department. Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 3 Winnipeg Police Service Headquarters Construction Project Status of Audit Recommendations 2015 Qtr 3 To be leaders in building public trust in our civic government Audit Department TABLE OF CONTENTS History...5

More information

Value for Money Statement Year to 30 th September 2017

Value for Money Statement Year to 30 th September 2017 Value for Money Statement Year to 30 th September 2017 Introduction The Hyelm Group is committed to finding ways to provide excellent services whilst at the same time seeking to reduce costs and improve

More information

FINANCIAL PLANNING FOR 2020

FINANCIAL PLANNING FOR 2020 FINANCIAL PLANNING FOR 2020 OVERVIEW Whilst the move to Future Council is not driven by the funding position of the Council, the development of a Medium Term Financial Strategy (MTFS) is a key document

More information

2.2 The overall aim of Zero Waste: Midlothian and Edinburgh is:

2.2 The overall aim of Zero Waste: Midlothian and Edinburgh is: Midlothian Council Tuesday 17 December 2013 Item No 12 Zero Waste: Midlothian and Edinburgh Residual Waste Treatment Progress Report Report by John Blair, Director, Resources 1 Purpose of Report The procurement

More information

Audit Committee: Terms of Reference

Audit Committee: Terms of Reference Audit Committee: Terms of Reference Status: Draft Next Review Date: March 2013 Page 1 of 14 Audit Committee Terms of Reference Issue Date: 5 April 2013 Document Number: POL_0100 Prepared by: Head of Assurance

More information

Ayrshire and Arran NHS Board

Ayrshire and Arran NHS Board Paper 16 Ayrshire and Arran NHS Board Monday 21 May 2018 Performance Governance Committee Annual Report 2017/18 Author: Frances Forsyth, Committee Secretary Sponsoring Director: Derek Lindsay, Director

More information

2017/2018 Financial Planning

2017/2018 Financial Planning 2017/2018 Financial Planning Savings Plan Consultation Document August 2017 Alternative Formats: Some people may need this information in a different format for example a minority language, easy read,

More information

Government of Newfoundland and Labrador. Central Region Long Term Care Project Value for Money Assessment

Government of Newfoundland and Labrador. Central Region Long Term Care Project Value for Money Assessment Government of Newfoundland and Labrador Central Region Long Term Care Project Value for Money Assessment Government of Newfoundland and Labrador Central Region Long Term Care Project Limitations Ernst

More information

NHS Fife St Andrews Community Hospital and Health Centre Project Full Business Case. 1. Foreword Executive Summary.. 4

NHS Fife St Andrews Community Hospital and Health Centre Project Full Business Case. 1. Foreword Executive Summary.. 4 CONTENTS Page 1. Foreword.. 3 2. Executive Summary.. 4 3. Strategic Context.. 12 4. The Outline Business Case 18 5. Conventional Procurement Assessment Model 22 6. The Procurement Process.. 27 7. PPP Solution.

More information

Thank you for your Official Information Act request, received on 22 November You requested the following:

Thank you for your Official Information Act request, received on 22 November You requested the following: Reference: 20170386 20 December 2017 Thank you for your Official Information Act request, received on 22 November 2017. You requested the following: I request a copy all advice provided to either the Minister

More information

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA)

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) 2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA) TECHNICAL SPECIFICATIONS 15 July 2016 1 1) Title of the contract The title of the contract is 2nd External

More information

UNIVERSAL SERVICE AND ACCESS FINAL REPORT

UNIVERSAL SERVICE AND ACCESS FINAL REPORT UNIVERSAL SERVICE AND ACCESS FINAL REPORT 0 1 Contents INTRODUCTION... 2 Updates... 4 Electronic Communications Bill... 4 Electronic Communications (Universal Service and Access Fund) Regulations... 12

More information

Annual Audit Letter North West Ambulance Service NHS Trust 13 July 2016

Annual Audit Letter North West Ambulance Service NHS Trust 13 July 2016 Annual Audit Letter 2015-16 North West Ambulance Service NHS Trust 13 July 2016 Contents The contacts at KPMG in connection with this report are: Page Introduction 3 Amanda Latham Director Tel: 0161 246

More information

Ministry Of Health Registration of Interest

Ministry Of Health Registration of Interest Ministry Of Health Registration of Interest Service Outcomes and Service Providers Social Bond Pilot (Note: The ROI for Intermediaries will follow in 2014) Part 1 Instructions and Supporting Information

More information

The Annual Audit Letter for Chorley and South Ribble Clinical Commissioning Group

The Annual Audit Letter for Chorley and South Ribble Clinical Commissioning Group The Annual Audit Letter for Chorley and South Ribble Clinical Commissioning Group Year ended 31 March 2016 June 2016 Fiona Blatcher Engagement Lead T 0161 234 6393 E fiona.c.blatcher@uk.gt.com Gareth Winstanley

More information

2017/18 Financial Plan and Budgets. John Ingham, Chief Finance Officer, NHS Norwich CCG. Discussion and Approval

2017/18 Financial Plan and Budgets. John Ingham, Chief Finance Officer, NHS Norwich CCG. Discussion and Approval Agenda Item: 13 NHS Norwich CCG Governing Body Tuesday 28 th March 2017 Subject: Presented By: 2017/18 Financial Plan and Budgets John Ingham, Chief Finance Officer, NHS Norwich CCG Submitted To: NHS Norwich

More information

NHS Pensions Re-Procurement Programme

NHS Pensions Re-Procurement Programme NHS Pensions Re-Procurement Programme Pensioner Payroll Supplier Boot Camp 7 th October 2015 Introduction to NHS Business Services Authority Steven Pink Director of Change and Commercial Delivery Project

More information

INTEGRATED MEDIUM TERM PLAN Director of Planning and Performance. To present the thb s Draft Integrated Medium Term Plan

INTEGRATED MEDIUM TERM PLAN Director of Planning and Performance. To present the thb s Draft Integrated Medium Term Plan INTEGRATED MEDIUM TERM PLAN 2015-18 BOARD MEETING 29 JANUARY 2015 AGENDA ITEM 2.1 Report of Director of Planning and Performance Paper prepared by Director of Planning and Performance Purpose of Paper

More information

Overview of the framework

Overview of the framework Overview of the framework To meet the infrastructure deficit, the Twelfth Five Year Plan envisages a renewed thrust on investment in infrastructure, particularly in the power sector. The additional thermal

More information

Stage 2 LIFT Business Case New Birmingham Dental Hospital and School of Dentistry Project

Stage 2 LIFT Business Case New Birmingham Dental Hospital and School of Dentistry Project Stage 2 LIFT Business Case New Birmingham Dental Hospital and School of Dentistry Project PUBLIC VERSION 13 th September 2013 Accessible, Responsive Community Healthcare TABLE OF CONTENTS 1 EXECUTIVE SUMMARY...

More information

Redevelopment of MOD Main Building

Redevelopment of MOD Main Building Ministry of Defence Redevelopment of MOD Main Building REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 748 Session 2001-2002: 18 April 2002 LONDON: The Stationery Office 0.00 Ordered by the House of Commons

More information

Report. Chris Ford Joint Chief Finance Officer

Report. Chris Ford Joint Chief Finance Officer Governing Body Meeting held in public Report Date of Meeting: 8 November 2018 Agenda Item: 15.0 Report Title Finance Report as at 30 th September 2018 (Month 6) Report Author Presented By Responsible Director

More information

An international call for research. Taking Stock of Public Private Partnerships and Private Finance Initiatives Around the World

An international call for research. Taking Stock of Public Private Partnerships and Private Finance Initiatives Around the World An international call for research Taking Stock of Public Private Partnerships and Private Finance Initiatives Around the World 2 An international call for research ACCA wishes to commission research with

More information

MINUTES IN ATTENDANCE: Ms Cara Anderson

MINUTES IN ATTENDANCE: Ms Cara Anderson MINUTES Minutes of the 63 rd Meeting of the Public Health Agency board held on Thursday 20 March 2014 at 1:30pm, in Public Health Agency, Conference Rooms, 12/22 Linenhall Street, Belfast, BT2 8BS PRESENT:

More information

WESTMINSTER KINGSWAY CORPORATION. on behalf of PKF, IAS Providers Avnish Savjani on behalf of Buzzacott, External Auditors

WESTMINSTER KINGSWAY CORPORATION. on behalf of PKF, IAS Providers Avnish Savjani on behalf of Buzzacott, External Auditors WESTMINSTER KINGSWAY CORPORATION Draft minutes of the meeting of the Audit Committee held at 6.00 pm on Thursday 6 December 2012 in Room 106 at Westminster Kingsway College, Victoria Centre, London SW1P

More information

Appendix:6.2 MEETING: Paul Sinden Director of Commissioning CONTACT AUTHOR: DETAILS: SUMMARY:

Appendix:6.2 MEETING: Paul Sinden Director of Commissioning CONTACT AUTHOR: DETAILS: SUMMARY: Appendix:6.2 MEETING: Islington Clinical Commissioning Group Governing Body DATE: Wednesday 6 May 2015 TITLE: Strategy and Finance Committee Update for May 2015 LEAD GOVERNING Dr. Jo Sauvage Clinical Vice

More information

Budget Department of Education

Budget Department of Education Budget 2016-17 Department of Education 9 March 2016 Background 1. The Fresh Start Agreement committed the Executive to producing a balanced Budget for 2016-17, agreed by the Assembly, by the end of January

More information

EASTER ROSS PRIMARY CARE RESOURCE CENTRE PFI DEVELOPMENT

EASTER ROSS PRIMARY CARE RESOURCE CENTRE PFI DEVELOPMENT EASTER ROSS PRIMARY CARE RESOURCE CENTRE PFI DEVELOPMENT FULL BUSINESS CASE List of Contents Appendices - Appendix 1 Appendix 2 Appendix 3 Appendix 4 Appendix 5 Appendix 6 Appendix 7 Appendix 8 Appendix

More information

Outline Capital Investment Strategy

Outline Capital Investment Strategy Outline Capital Investment Strategy INDEX FOREWORD 1. INTRODUCTION 2. PURPOSE 3. SUMMARY 4. INFLUENCES ON CAPITAL INVESTMENT 5. CURRENT CAPITAL EXPENDITURE 6. COMMERCIAL PROPERTY INVESTMENT STRATEGY 7.

More information

SPECIAL TENDER CONDITIONS FOR THE

SPECIAL TENDER CONDITIONS FOR THE Page 1 SPECIAL TENDER CONDITIONS FOR THE Integrated Applications Promotion (IAP) Programme (CALL FOR PROPOSALS) FEASIBILITY STUDIES Page 2 A. INTRODUCTION The following documents are available on http://emits.esa.int/

More information

Meeting of the Joint Oireachtas Committee on Housing, Planning and Local Government 27 September 2018

Meeting of the Joint Oireachtas Committee on Housing, Planning and Local Government 27 September 2018 Meeting of the Joint Oireachtas Committee on Housing, Planning and Local Government 27 September 2018 Opening Statement of Eoghan Murphy, TD, Minister for Housing, Planning and Local Government I thank

More information

The STFC Project Management Framework

The STFC Project Management Framework The STFC Project Management Framework Version 5 June 2017 For further information contact: Tony Medland, Programmes Directorate (tony.medland@stfc.ac.uk) Matt Fletcher, National Laboratories Directorate

More information

Myners Principles - Application Principle Best Practice Guidance (CIPFA) Havering Position/Compliance

Myners Principles - Application Principle Best Practice Guidance (CIPFA) Havering Position/Compliance 1. Effective decision-making Administrating authorities should ensure that : (a) Decisions are taken by persons or organisations with the skills, knowledge, advice and resources necessary to make them

More information

Japanese Policy and Implementation on PFI

Japanese Policy and Implementation on PFI Japanese Policy and Implementation on PFI The 3rd Annual Meeting for PPP/PFI Promotion between Japan and Korea October 9th, 2008 History Chart Jul. 1999 Enactment of PFI Law Oct. 1999 Creation of The Committee

More information

INVITATION TO TENDER PROVISION OF HOUSING RELATED SUPPORT SERVICES FOR VULNERABLE PEOPLE (REF: ASC0016)

INVITATION TO TENDER PROVISION OF HOUSING RELATED SUPPORT SERVICES FOR VULNERABLE PEOPLE (REF: ASC0016) Wards Affected: All Wards. ITEM 6 PROCUREMENT & COMMISSIONING 15 DECEMBER 2015 INVITATION TO TENDER PROVISION OF HOUSING RELATED SUPPORT SERVICES FOR VULNERABLE PEOPLE (REF: ASC0016) Responsible Cabinet

More information

Quality and Qualifications Ireland

Quality and Qualifications Ireland Quality and Qualifications Ireland QQI/N37 Note of the thirty seventh Meeting of the Authority (The Board) which took place on Friday, 21 September 2018 at 10.00 a.m. in the Boardroom, QQI Offices, 26/27

More information