Florida Governmental Utility Authority (FGUA) Phase Two Due Diligence Evaluation Results. City of Dunnellon September 18, 2017
|
|
- Jasmine Allison
- 5 years ago
- Views:
Transcription
1 Florida Governmental Utility Authority (FGUA) Phase Two Due Diligence Evaluation Results City of Dunnellon September 18, 2017
2 FGUA Acquisition Process - Recap Preliminary Phase I Phase I Preliminary Due Diligence Consult with host government for entry Data requests and site visits; financial, engineering & operations analysis Negotiate and agree upon a preliminary and conditioned purchase price range and general terms of asset acquisition Phase II Perform Detailed Due Diligence - Validating/Adjusting Preliminary Analysis, Finalize Acquisition Terms and Various Agreements, Conduct Required Public Interest Hearings Phase III Financing, Closing, and Transition FGUA finalizes financing; closing of the acquisition pursuant to terms of the asset acquisition agreement FGUA and Seller cooperate in transition of ownership and operations 2
3 Preliminary Phase I Activity Performed Obtained County BOCC Resolution of Support and approval of City requests for FGUA holding period and City right of first purchase Site visits/condition assessments - April 6 and April 11 Review of operational, performance and compliance material Review of all provided financial information Review of recent engineering assessments/reports; preliminary CIP recommendations provided by USW/WT (subject to City guidance) Financial Advisor and Underwriting team reviewed outstanding debt and recommended refunding transaction; identified financing alternatives 3
4 Phase I Activity Performed Con t Preliminary debt capacity analysis provided by PRMG Preliminary consents for grant reassignments from FDEP and SWFWMD (Southwest Florida Water Management District) and positive response from USDA Rural Development Loan Program 4
5 Phase 2 Work Performed Operations / Capital / Engineering Kimley-Horn Work Authorizations approved (acquisition & capital PERs Detailed asset inspection, initial Statement of Conditions report Confirm O&M costs and contract pricing Update CIP Requirement Preliminary Engineering Report for acquisition substantially complete Finance Confirm historical financial results, verify cash balances, update projections (detailed customer billing data pending) Complete draft financial feasibility report including updated debt capacity analysis, system valuation and financing alternatives USDA Loan Application Review grants awarded and outstanding debt terms / obligations; pending new grant opportunities 5
6 Phase 2 Work Performed - Cont Other Purchase / Sale agreement initial draft FA and Bond attorney review of current fund restrictions Continue to lend support as needed to city 6
7 Recap - FGUA Valuation Methodology Income/Debt Capacity Approach Net Transaction Price Determined as follows: Total Utility Revenues (Recurring) - Operating Expenses - Renewal and Replacement Fund (R&R) Deposits (10% of Revenue) - Debt Service Coverage Allowance above R&R Deposit at 40% (if bond financed) - Any Other Funding Requirements from Revenues = Available Net Revenues for Financing (Debt Service Payment Equivalent) = Calculate Bondable Capacity from Available Net Revenues (Principal) - Less Payments from Financing Proceeds - Issue and Acquisition / Transition Costs - Refund of Outstanding City Utility Bonds - Working Capital Deposit - Immediate Capital Needs Required to Be Funded = Net Available to CITY 7
8 Recap - Key Financial Assumptions Rate revenue at currently approved city rates Includes 4% increase adopted for FY2018; Assumes 1% annual elasticity adjustment (nets to 3%) No increase required for transaction; and FGUA increase less than City estimated requirement No additional customer growth assumed for evaluation period Operations and management costs indexed to CPI and ERC changes 5% operating contingency reserve for unexpected revenue shortfalls (e.g., lower consumption) and/or unforeseen expenses (e.g., energy costs, market prices, unexpected repairs) 10% annual transfer to R&R Fund for ongoing capital reinvestment $2.742 million initial deposit to 5-year CIP for capital project priority - Rainbow Springs - City Plant interconnect; grant funds could reduce this and benefit customers 8
9 Key Financial Assumptions Con t Assumes Dunnellon WWTP to be re-rated from.335 mgd to.500 mgd capacity for planned interconnects; plant rerating with Juliet Falls capacity expected to accommodate existing flows, 5-year CIP and known reserved capacity w/ ~ 23% remaining $2.5 Million WMD grant assumed to be assignable for 180 Ave. corridor connections No additional State Springs funding assumed pending SWFWMD recommendations FGUA to refund existing $10.8 Million (FY 2018) City debt plus fund capital with USDA Rural Development Loan at current interest rate (2.75%); $100,000 prepayment penalty with Regions 9
10 Key Financial Assumptions Con t Acquisition total value for loan purpose $ million; cash flows set to 30-year repayment term FGUA assumed to be subrecipient on 2017 CDBG Small Cities grant and State appropriation No capacity impact fees assumed Potential post-closing returns to City in the form of Futures payments on new connections at 50/50 split 10
11 Why 40-Year Amortization Alternative Not Chosen As Valuation Method 30-Year Evaluation Period Typical in Industry Representative of General Service Life Cycle of Assets to be Purchased Remaining Service Life of Existing Assets Estimated at Approx. 26 Years 40-year Evaluation Period Longer than Remaining Service Life of Existing Assets Increasing to a 40-Year Evaluation would: Artificially Increase Overall Debt Burden of the System Decrease Available System Cash Flows Needed to Fund Future Capital Improvements Increase Future Rate Pressure on Existing Customers to Recover Cost of Fully Leveraged System May Require Replacement of Major Assets Before Debt has Been Paid Off Evaluation Considerations: Used USDA Interest Rate as Cost of Capital Benefits Transaction 30-year Evaluation Period allows Funding of Loan Reserve from Cash Flow Results in an overall Stronger Credit / Promotes Rate Sustainability 11
12 The CIP Strategy *Excludes existing City funding and encumbrances for projects in process 12
13 The CIP Strategy Funding Fiscal Year Ending September 30 Description Source Total Capital Improvement Projects: Connect Dunnellon & Rainbow Springs WW 2017 Bonds $ 222,000 $ 2,520,251 $ - $ - $ - $ 2,742,251 Lift Station SCADA on 10 key stations Existing Bonds - 55, ,500 Construct Eastern Force Main (Grant Funded) (180th Corridor) Grant 333,000 2,196, ,529,893 Generator Trailer Mount Existing Bonds , ,717 (2) 6 inch AMT Diesel Sewer Pump R&R ,930 36, ,560 Replacement of service Rainbow Springs and Chatmire R&R 55,500 55,500 55,500 55,500 55, ,500 Connect Rio Vista to Rainbow Springs Water Existing Bonds , ,650 Water Meter Replacement W/ I900 Existing Bonds - 333, , ,600 Water Meter Replacement (Normal R/R) Operating 11,375 11,375 11,375 11,375 11,375 56,875 Water Customer Field Audit Operating 7,830 7,830 7,830 7,830 7,830 39,150 Paint 500,000 Gal RSWTP Operating 6,000 6,000 6,000 6,000 6,000 30,000 Hytovick Water main Relocation Existing Bonds - 126, ,540 City & RBS WTP Interconnection Improvements Existing Bonds - 33, ,300 Well 9 Electrical Upgrade Existing Bonds ,750-27,750 Service Area Improvements (CDBG) CDBG Grant 650, ,000 Service Area Improvements (CDBG) - Match Reserves 25, ,000 CRA - Other Needs Line Replacement Leg. Grant 300, ,000 CRA - Other Needs Line Replacement Existing Bonds 105, ,243 Other Water Renewal and Replacement Projects R&R 148, , , , , ,825 Other Wastewater Renewal and Replacement Projects R&R 174, , , , , ,388 Total Water and Wastewater Projects $ 2,038,803 $ 5,615,682 $ 834,328 - $ 489,409 - $ 435,519 - $ 9,413,742 Funding Sources: Series 2017 Bond Proceeds 2017 Bonds $ 222,000 $ 2,520,251 $ - $ - $ - $ 2,742,251 Existing Bond Proceeds Existing Bonds 149, , ,402 88,800-1,309,385 Grant Funding Grant 333,000 2,196, ,529,893 CDBG Grant CDBG Grant 650, ,000 Legislative Grant Leg. Grant 300, ,000 Renewal and Replacement Fund R&R 333, , , , ,314 1,731,188 Operating Reserves (CDBG Grant Match) Reserves 25, ,000 Reclassify as Operating Expense Operating 25,205 25,205 25,205 25,205 25, ,025 Total Funding Sources $ 2,038,803 $ 5,615,682 $ 834,328 $ 489,409 $ 435,519 $ 9,413,742 13
14 Updated Debt Capacity Valuation Results USDA 30 Year Financing Prior Current Description Estimate Estimate Total Water and Wastewater System Revenues $ 2,907,029 $ 2,942,053 Less Operating Expenses 1,831,759 1,885,007 Net Operating Revenues Before Other Deductions $ 1,075,270 $ 1,057,045 Less Other Deductions (Renewal and Replacements and Debt Service Reserves) 290, ,611 Net Annual Cash Flow for Acquisition/Additional Capital Funding $ 784,567 $ 762,435 Present Value of Net Annual Cash Flow (Principal Amount of Borrow) $ 15,886,931 $ 15,520,912 Plus City's Existing Unencumbered Fund Balance Available for Disbursement 1,183, ,515 Total Available Funds For Disbursement $ 17,070,266 $ 16,242,427 Less Expenditures: Bond/Loan Issue Cost $ 476,608 $ 310,418 Utility Transaction Cost 250, ,478 Working Capital Deposit 451, ,582 Working Capital Deposit - Accounts Receivables Purchase - 221,146 Deposit to Project Fund For Capital Expenditures 2,758,400 2,742,251 Net Available for Purchase After Expenditures $ 13,133,591 $ 12,159,553 Disbursement to City: Less City's Existing Outstanding Debt (10,809,633) (10,809,633) Less Prepayment Penalty for Early Extinguishment of City's Debt - (100,000) Net Surplus/(Deficiency) Above City's Current Outstanding Debt $ 2,323,958 $ 1,249,920 Net to City Including Payment of Accounts Receivable $ 2,323,958 $ 1,471,066 14
15 Summary of Significant Changes / Updates in Phase 2 40-year loan cash flow financing excluded as option per financial advice Net available to city with updated 30-year cash flows is $1.471M with purchase of receivables vs. $2.324M previously Updated 5-year CIP is $9.414M (with committed grants) vs. previous $6.538M (more detailed project definition) Assume use of City residual bond proceeds ($1.309 million) for planned capital work (will require City encumber work to FGUA) Transaction costs updated to $411K from $250K based upon updated effort requirement, including legal work 15
16 Recap of Benefits of Dunnellon-FGUA Partnership Three way intergovernmental partnership with City and Marion County with outsourcing benefits Stabalize customer rates lower than City requirement Potential for Futures payments and City credits with additional State grants High quality, experience and depth of FGUA management, operations and technical support; including knowledge gained of City system High public utility performance standards and strong track record (particularly system reliability and customer service) City transfers managerial demands (headaches) and financial liability; removal of debt defeasance City credit standing FGUA financing can be federally tax exempt and/or low cost governmental loans; purchases and property are State tax exempt; avoids investor owned capital profits (ROE) FGUA is eligible to receive and can benefit from all forms of State, Federal and Water Management district grants/loans 16
17 Benefits of Dunnellon-FGUA Partnership Con t Customers operating costs benefit from geographical proximity and size and capabilities of FGUA contractors and systems (significant resource back up capacity) Interlocal agreement can provide city assurances as to how issues can be addressed, policy priorities, transparency and accountability Transparency of public authority owner and alternatives for on-going involvement of customers Employee transferability Important work (service improvements and capital projects) can get underway very quickly with minimal transition hiccups 17
18 Next Steps If approval to move forward: Determine use of Net Proceeds (cash, rates, other) for agreement purposes Confirm 50/50 split of Futures impact fee payments on rerated capacity Complete submission of USDA financing application with required engineering, valuation and environmental reports Continue work w/ city on additional grant funding; particularly Springs $ ; grant could result in credit to customers/city Work with City Attorney on Purchase and Sale, Transition and Interlocal Agreements (including Marion County consents) Schedule Public Interest Hearing Assist City with customer information outreach including conducting necessary meetings/hearings 18
19 19
P4 Unique Collaborative Water and Sewer Partnership City of Dunnellon Marion County FGUA May 31, 2018 FCCMA Annual Conference
P4 Unique Collaborative Water and Sewer Partnership City of Dunnellon Marion County FGUA May 31, 2018 FCCMA Annual Conference Session Objectives Using a Current Day Case Study - Discuss outsourcing Public-Private
More informationUTILITY RATE STUDY. Public Hearing
UTILITY RATE STUDY Public Hearing. Public January 23, 2018 Resources Management Group, Inc. Utility, Rate, Financial, and Management Consultants Rate Guiding Principles Recognized Revenues Should Be Sufficient
More informationOfficial Minutes of MARION COUNTY BOARD OF COUNTY COMMISSIONERS. July 18, 2011
Official Minutes of MARION COUNTY BOARD OF COUNTY COMMISSIONERS July 18, 2011 The Marion County Board of County Commissioners met in a workshop session in Commission Chambers at 1:10 p.m. on Monday, July
More informationWATER, WASTEWATER, AND RECLAIMED WATER RATE STUDY Public Meeting to Review Study Results. January 5, 2016
WATER, WASTEWATER, AND RECLAIMED WATER RATE STUDY Public Meeting to Review Study Results January 5, 2016. Public Resources Management Group, Inc. Utility, Rate, Financial and Management Consultants Utility
More informationFlorida Governmental Utility Authority Request for Qualifications Utility Operations, Maintenance and Customer Service May 1, 2018
Introduction Florida Governmental Utility Authority Request for Qualifications Utility Operations, Maintenance and Customer Service May 1, 2018 The Florida Governmental Utility Authority (FGUA) is a special
More informationDEPARTMENT OF PUBLIC WORKS UTILITIES
DEPARTMENT OF PUBLIC WORKS UTILITIES Mission Statement: Public Works - Utilities is dedicated to providing water, wastewater, and environmental services to the citizens of Rio Rancho and other City Departments.
More informationFY 2019 TENTATIVE BUDGET Authority Board Meeting April 4, 2018
FY 2019 TENTATIVE BUDGET Authority Board Meeting April 4, 2018 Mission of the Authority is: To provide the region with a sufficient, high quality, safe drinking water supply that is reliable, sustainable
More informationDATE: September 30, TO: Chairman and Members of the Board
DATE: September 30, 2014 TO: Chairman and Members of the Board FROM: Robert Sheets, System Manager SUBJECT: Adopted Fiscal Year 2015 Budget And 2015-2019 Capital Improvement Program INTRODUCTION In my
More informationGlossary of Terms. ADOPTED BUDGET Is the financial plan for the fiscal year beginning July 1.
Glossary of Terms ACCOUNT An entity for recording specific revenues or expenditures, or for grouping related or similar classes of revenues and expenditures and recording them within a fund or department.
More informationAnnual Operating and Debt Service Budget
Annual Operating and Debt Service Budget (Tentative) Prepared By Table of Contents Page OPERATING BUDGET General Fund Summary of Revenues, Expenditures and Changes in Fund Balances 1-3 Budget Narrative
More informationPORT OF THE ISLANDS. Community Improvement District. Annual Operating and Debt Service Budget. Fiscal Year 2015
Annual Operating and Debt Service Budget Version 5 - Final Budget: (Adopted at Board Meeting on 8/15/14) Prepared by: Table of Contents Page # OPERATING BUDGET General Fund Summary of Revenues, Expenditures
More informationWakulla County. Annual Debt Report. For. FY (unaudited) Prepared by the Wakulla County Clerk of Court, Finance Department
Wakulla County Annual Debt Report For FY 2013-2014 (unaudited) Prepared by the Wakulla County Clerk of Court, Finance Department 1 Board of County Commissioners and Citizens of Wakulla County, As your
More informationCITY OF BOYNTON BEACH FY ADOPTED SUMMARY BUDGET
CITY OF BOYNTON BEACH, FLORIDA CITY OF BOYNTON BEACH FY 2017-2018 ADOPTED SUMMARY BUDGET P a g e 1 46 Boynton Beach Mayor and City Commission Commissioner Joe Casello, Commissioner Christina Romelus, Vice
More informationLehigh County Authority Capital Plan. Preliminary Plan: Board Presentation August 28, 2017
Lehigh County Authority 2018-2022 Capital Plan Preliminary Plan: Board Presentation August 28, 2017 1 Project Prioritization Categories Project Category Regulatory New Cust CA/OS AM - Low AM - Med AM -
More informationpresents: PLANNING FOR THE FUTURE INFORMATIONAL OVERVIEW DETAILS PROVIDED BY:
presents: PLANNING FOR THE FUTURE INFORMATIONAL OVERVIEW www.springcreekud.org DETAILS PROVIDED BY: SPRING CREEK UTILITY DISTRICT Development & Infrastructure About Spring Creek Utility District Spring
More informationCommunity Maritime Park Financing Recommendation. April 6, 2009
Community Maritime Park Financing Recommendation April 6, 2009 Recommendation Long Term Financing Approve the issuance of a 30 year fixed rate Capital Improvement Revenue Bond to provide $40 million net
More informationTOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009
TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009 EXECUTIVE SUMMARY The functions and duties of the Oro Valley Water Utility Commission include reviewing and developing
More informationFEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY
FINAL REPORT FEASIBILITY STUDY FOR THE DEVELOPMENT OF A REGIONAL WATER PRODUCTION UTILITY Summary Report BLACK & VEATCH PROJECT NO. 184920 Black & Veatch Holding Company 2013. All rights reserved. PREPARED
More informationWakulla County. 4th Annual Debt Report. For. Fiscal Year Ended September 30, Prepared by the Wakulla County Clerk of Court, Finance Department
Wakulla County 4th Annual Debt Report For Fiscal Year Ended September 30, 2017 Prepared by the Wakulla County Clerk of Court, Finance Department 1 Board of County Commissioners and Citizens of Wakulla
More informationSpring Coast Management Committee FY2020 FDEP Springs Funding Applications Submitted. October 31, 2018
Spring Coast Management Committee FY2020 FDEP Springs Funding Applications Submitted October 31, 2018 Process RECOMMENDED PROJECTS ONLY SCMC and SCSC Approves Application and Evaluation Process FY 2020
More informationCAPITAL IMPROVEMENT PLAN POLICIES
CAPITAL IMPROVEMENT PLAN POLICIES 1. Projects included in the Capital Improvement Plan shall be consistent with the City's Comprehensive Plan. 2. Citizen input is encouraged throughout the process of developing
More informationFrom: Lex Warmath and Elaine Conti, Raftelis Financial Consultants, Inc.
227 West Trade Street Phone 704 373 1199 www.raftelis.com Suite 1400 Fax 704 373 1113 Charlotte, NC 28202 Date: June 21, 2016 To: Mr. Bob Walker, Executive Director From: Lex Warmath and Elaine Conti,
More informationMEMORANDUM. Isaac Brownman, Public Works Director and Sue Smith, Finance Director
MEMORANDUM TO: FROM: Tom Harmer, Town Manager Isaac Brownman, Public Works Director and Sue Smith, Finance Director DATE: February 26, 2018 SUBJECT: Ordinance 2018-09, Amending the FY 2017-2018 Budget
More informationChicopee River CSO Project Springfield Water & Sewer Commission. APWA Congress September 9, CSO Control Plan. CSO Control
Chicopee River CSO Project Springfield Water & Sewer Commission APWA Congress September 9, 2007 CSO Control Plan Typical Approach Different Thinking on Controlling Costs Case Example Springfield MA CSO
More informationFinal Adopted Budget. Fiscal Year Ending September 30, Adopted November 14, 2018 Resolution 19-01
2018 Final Adopted Budget Fiscal Year Ending September 30, 2018 Adopted November 14, 2018 Resolution 19-01 RESOLUTION # 19-01 RESOLUTION OF THE BOARD OF COMMISSIONERS OF THE IMMOKALEE WATER AND SEWER DISTRICT
More informationBudget Policy and Procedures
DATE TITLE Budget Policy and Procedures ORG. AGENCY Blueprint 2000 APPROVED.01 STATEMENT OF POLICY It is the intent of the Blueprint 2000 Intergovernmental Agency (hereinafter called the Agency ) to provide
More informationFiscal Year Budget Proposal
Fiscal Year 20182019 Budget Proposal Board of Directors March 27, 2018 RIVANNA WATER & SEWER AUTHORITY FY 2019 Proposed Budget Table of Contents Budget Highlights Prepared: March 6, 2018 Adopted: Draft
More informationWATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016
WATER UTILITY FINANCIAL PLAN AND RATE STUDY CITY OF WHITEFISH, MT MARCH 2016 The Financial Link Executive Summary - Water In May 2015, the City of Whitefish (City) retained AE2S to complete a Water and
More informationBella Collina. Community Development District. Amended Budget
Amended Budget FY 2018 Table of Contents 1 Water & Sewer Fund 2-6 Water & Sewer Narrative Amended Budget Water & Sewer Actuals FY2018 FY2018 Thru Adopted Increase/ Amended Description 9/30/18 Budget (Decrease)
More informationCITY OF RIVIERA BEACH, FLORIDA UTILITY SPECIAL DISTRICT S SYSTEMS AND OPERATIONS FOR FISCAL YEAR ENDING SEPTEMBER 30, 2010.
UTILITY SPECIAL DISTRICT S SYSTEMS AND OPERATIONS FOR FISCAL YEAR ENDING SEPTEMBER 30, 2010 Overview The service area of the Utility District s Water System includes the entire City of Riviera Beach (approximately
More informationLehigh County Authority Capital Plan. Preliminary Plan Board Presentation August 22, 2016
Lehigh County Authority 2017-2021 Capital Plan Preliminary Plan Board Presentation August 22, 2016 1 Process Review / Approvals Capital Plan Annual Budget Funding / New Borrowing Project Authorizations
More informationCITY. RIALTO W w w. R I a l t o c a. g o v. Fiscal Year 2009/10 Interim Financial Report. 5 months ended November 30, 2009
CITY of RIALTO W w w. R I a l t o c a. g o v Fiscal Year 2009/10 Interim Financial Report 5 months ended November 30, 2009 To: The Mayor and City Council City Administrator From: Chief Financial Officer
More information(per 1,000 gal.) General - American City and County Municipal Cost Index 20-Year Average as of April 2017
TEST YEAR Beginning Fund Balance $ 2018 2,009,742 Target Debt Service Coverage Target Days Operating Reserve 1.10 90 Schedule 1 CURRENT WATER RATES BUDGET FORECAST INFLATION FACTORS Year 1 Year 2 Year
More informationSan Diego County Water Authority Special Board of Directors Meeting September 20, 2012
Overview of Key Terms for a Water Purchase Agreement between the San Diego County Water Authority and Poseidon Resources San Diego County Water Authority Special Board of Directors Meeting 1 September
More informationCost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges
Cost Accounting for Rate & Fee Setting: Calculating Defensible Rates and Charges UNC School of Government EFC 2017 Water & Wastewater Finance Workshop February 28 March 1, 2017 The William & Ida Friday
More informationCAPITAL IMPROVEMENT ELEMENT Inventory Analysis
CAPITAL IMPROVEMENT ELEMENT Inventory Analysis 2.191 INTRODUCTION The principal purpose of this element is to identify the capital improvements that are needed to implement the comprehensive plan and ensure
More informationAppendix T. Financial Policies
Appendix T Financial Policies The Municipality of Anchorage has established financial policies to achieve and maintain a positive long term financial condition. These policies provide guidelines for current
More informationCAPITAL IMPROVEMENT PROGRAM POLICIES
CAPITAL IMPROVEMENT PROGRAM POLICIES 1. Projects included in the Capital Improvement Program shall be consistent with the City's Comprehensive Plan. 2. Citizen input is encouraged throughout the process
More informationSIGNIFICANT BUDGET CHANGES
Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and
More informationFHA Section 542(c) Risk-Sharing Program for Multifamily Housing Program Rules
FHA Section 542(c) Risk-Sharing Program for Multifamily Housing Program Rules Purpose Kentucky Housing Corporation (KHC) has partnered with HOPE of Kentucky, LLC, and the Community Reinvestment Fund, USA
More informationAdopted Budget. Fiscal Year Ending September 30, And. Adopted August 24, 2016
2017 Adopted Budget Fiscal Year Ending September 30, 2017 And Amendment Of Fiscal Year 2016 Budget Ending September 30, 2016 Adopted August 24, 2016 RESOLUTION # 16-11 RESOLUTION OF THE BOARD OF COMMISSIONERS
More informationCITY OF LARAMIE FINANCIAL OUTLOOK. Malea Brown, Administrative Services Director
CITY OF LARAMIE FINANCIAL OUTLOOK Malea Brown, Administrative Services Director Fiscal Year - GENERAL FUND 2 GENERAL FUND Organization Structure HUMAN RESOURCES PATROL POLICE LARC RECORDS DISPATCH ANIMAL
More informationWHEREAS, the ad-hoc committee undertook a study of a number of options for providing increased sewage treatment to PSSGID; and
INTERGOVERNMENTAL AGREEMENT BY AND BETWEEN THE PAGOSA SPRINGS SANITATION GENERAL IMPROVEMENT DISTRICT AND THE PAGOSA AREA WATER AND SANITATION DISTRICT THIS INTERGOVERNMENTAL AGREEMENT ( IGA ) is entered
More informationBUILD FUND, LLC POLICIES & PROCEDURES MANUAL
BUILD FUND, LLC POLICIES & PROCEDURES MANUAL MARCH 14, 2016 Table of Contents FOREWORD... 4 SECTION 1. GENERAL PROVISIONS... 5 1.1 PURPOSE... 5 1.2 OBJECTIVES... 5 1.3 AMENDMENTS and MODIFICATIONS... 5
More informationCITY OF TAMARAC, FLORIDA
Temp. Ord. #2327 September 24, 2015 Page 1 of 3 CITY OF TAMARAC, FLORIDA NO. O-2015- AN OF THE CITY COMMISSION OF THE CITY OF TAMARAC, FLORIDA, ADOPTING THE OPERATING BUDGET, REVENUES AND EXPENDITURES,
More informationUSDA, RURAL DEVELOPMENT FUNDING PROGRAMS
USDA, RURAL DEVELOPMENT FUNDING PROGRAMS COMMUNITY FACILITIES LOAN PROGRAM U. S. Department of Agriculture Rural Development Other Agencies: FSA, NRCS, etc. Housing Programs Community Programs Business
More informationEASTERN MUNICIPAL WATER DISTRICT BIENNIAL BUDGET FISCAL YEARS AND
EASTERN MUNICIPAL WATER DISTRICT BIENNIAL BUDGET FISCAL YEARS 2017-18 AND 2018-19 ADOPTED JUNE 7, 2017 STRATEGIC PLAN... 10 MISSION, VISION, AND GUIDING PRINCIPLES... 10 Mission... 10 Vision... 10 Guiding
More informationFY 2013/14 Preliminary Regional Wastewater, Recycled Water and Recharge Water Program Budget and TYCIP. Regional Committees April 4, 2013
FY 2013/14 Preliminary Regional Wastewater, Recycled Water and Recharge Water Program Budget and TYCIP Regional Committees April 4, 2013 Preliminary TYCIP FY 2014-2023 FY 2013/14 Preliminary Budget Adopted
More informationWaste to Energy. Carroll/Frederick Partnership. Summary of Frederick BoCC meeting February 3, 2009; and, Carroll County financial prospects.
Waste to Energy Carroll/Frederick Partnership Summary of Frederick BoCC meeting February 3, 2009; and, Carroll County financial prospects. Best and Final Offers Best and Final Offers (BAFO) were requested
More informationCity of Leesburg Fiscal Year 2017
1 City of Leesburg Fiscal Year 2017 Recommended Budget Presentation 2 Overview of Presentation Budget Goals Budget Process Budget Assumptions & Estimates Items the Budget Includes Total Budget Budget by
More informationWastewater Utilities. FY Budget Presentation
Utilities FY 2018-19 Budget Presentation 1 Volume Forecast Wastewater Customers by Class Fiscal Year Residential Commercial Wholesale Total Growth 2013 26,995 1.1% 3,091 0.8% 4 30,090 1.1% 2014 27,548
More informationBROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND A Major Fund of Broward County, Florida
BROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND A Major Fund of Broward County, Florida Financial Statements For the Years Ended September 30, 2013 and 2012 BROWARD COUNTY, FLORIDA WATER AND WASTEWATER
More informationWastewater Rate Study. Villa Park, Illinois
Wastewater Rate Study Villa Park, Illinois June 2013 Executive Summary General The Village of Villa Park s Wastewater Utility is responsible for operation and maintenance of the Village s separate sanitary
More informationMARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT. September 2013
MARINA COAST WATER DISTRICT FINANCIAL PLAN AND RATE AND FEE STUDY FINAL REPORT September 2013 10540 TALBERT AVENUE, SUITE 200 EAST FOUNTAIN VALLEY, CALIFORNIA 92708 P. 714.593.5100 F. 714.593.5101 MARINA
More informationSYCAMORE CITY COUNCIL AGENDA February 4, 2013
1. CALL TO ORDER 2. INVOCATION 3. PLEDGE OF ALLEGIANCE 4. APPROVAL OF AGENDA 5. AUDIENCE TO VISITORS SYCAMORE CITY COUNCIL AGENDA February 4, 2013 CITY COMMITTEE MEETINGS No Meetings are Scheduled REGULAR
More informationFINANCIAL POLICIES Originally Adopted by the City Council on September 15, 2014 Revised on May 2, 2016
FINANCIAL POLICIES Originally Adopted by the City Council on September 15, 2014 Revised on May 2, 2016 OPERATING BUDGET The objective of the operating budget policy is to ensure the appropriate levels
More informationPREFERRED FINANCIAL PLAN SCENARIO & WATER RATE DESIGN ALTERNATIVE
Mid Flat Rate Increases Limited CIP through Year 5 Reserves recover by Year 10 Phased In CIP Spending 2. 10 Year Phase In 100% of CIP by Year 10 100% of Reserves by Year 10 3. 5 Year Phase In 100% of CIP
More informationSIGNIFICANT BUDGET CHANGES
Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and
More informationHarris County Municipal Utility District No. 419
Harris County, Texas Independent Auditor's Report and Financial Statements Contents Independent Auditor's Report... 1 Management's Discussion and Analysis... 3 Basic Financial Statements Statement of Net
More informationCost Recovery Policy. Revised January Mount Pleasant Waterworks Cost Recovery Policy
Cost Recovery Policy Revised January 2016 VISION Through the unified and committed efforts of each and every employee, Mount Pleasant Waterworks will be a leader in our industry and community. MISSION
More informationCITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No
CITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No. 112301 April 1st 2016 DFA Infrastructure International Inc. dfa DFA Infrastructure International Inc. 33 Raymond
More informationCITY OF DE PERE REVOLVING LOAN FUND MANUAL. Prepared by the: Planning and Economic Development Department
CITY OF DE PERE REVOLVING LOAN FUND MANUAL Prepared by the: Planning and Economic Development Department In conjunction with the Wisconsin Economic Development Corporation Adopted: January 15, 2013 TABLE
More informationBOYNTON BEACH UTILITIES CONVERSION PROJECT 1/15/2017 1
1/15/2017 1 INTRODUCTION WHY THE SECOND PRESENTATION AND VOTE? PROJECT BACKGROUND AND ORGANIZATION PROJECT TEAM AND DUTIES SCOPE OF PROJECT MAJOR POINTS OF THE PURCHASE AGREEMENT IMPACT TO THE TBE MAINTENANCE
More informationARLINGTON COUNTY, VIRGINIA FINANCIAL & DEBT MANAGEMENT POLICIES
ARLINGTON COUNTY, VIRGINIA FINANCIAL & DEBT MANAGEMENT POLICIES Budgeting, Planning & Reserves Balanced Budget: Arlington County will adopt an annual General Fund budget in which the budgeted revenues
More informationCity of Sanibel. Sewer Expansion Feasibility Study Update GAI #A
City of Sanibel Sewer Expansion Feasibility Study 2011 Update GAI # July 2011 July 12, 2011 GAI Proj. # Mr. Gates Castle Utility Director City of Sanibel 800 Dunlop Road Sanibel, FL 33957 Subject: Sewer
More informationRATE INFORMATION. A. The rates adopted by the Authority will be in accordance with of the Code of Virginia, as amended.
Page 1 of 8 Section 1. PURPOSE The purpose of this policy to explain how the Bedford Regional Water Authority ( Authority ) implements the adopted Rates policy and to provide explanation for each of the
More informationVillage of Baltimore Water & Wastewater Analysis. July 2018
Village of Baltimore Water & Wastewater Analysis July 2018 Table of Contents Introductory Summary... 1 Data... 1 Water Treatment Plant (WTP)... 1 Production... 2 Costs & Debts... 2 Wastewater Treatment
More informationCity of Punta Gorda Utilities O M & R Fund Revenue and Expense Comparison Actual FY 2015 through Budget FY Actual FY 2016.
City of Punta Gorda Utilities O M & R Fund Revenue and Expense Comparison Actual FY 2015 through Budget FY 2018 Revenue: Actual FY 2015 Actual FY 2016 Budget FY 2017 Projected FY 2017 Budget FY 2018 Charges
More informationU.S. Department of Housing and Urban Development Community Planning and Development
U.S. Department of Housing and Urban Development Community Planning and Development Special Attention of: Notice CPD 96-9 All Secretary's Representatives All State/Area Coordinators Issued: December 20,
More information1. Waste Water Treatment Plant Expansion/Capital Improvement Plan. 2. Catawba River Water Treatment Plant (CRWTP) Non-Capacity Costs
Table of Contents Agenda 2 Waste Water Treatment Plant Expansion/Capital Improvement Plan Staff Report 3 WWTP Capital Improvement Plan Update Report 6 Catawba River Water Treatment Plant (CRWTP) Non-Capacity
More informationCITY OF TAMARAC, FLORIDA ORDINANCE NO. O
Ordinance O-2018-12 September 20, 2018 Page 1 of 3 CITY OF TAMARAC, FLORIDA ORDINANCE NO. O-2018-12 AN ORDINANCE OF THE CITY COMMISSION OF THE CITY OF TAMARAC, FLORIDA, ADOPTING THE OPERATING BUDGET, REVENUES
More informationFinance Committee Meeting
Finance Committee Meeting FY16 Strategic Business and Operating Plan and Preliminary Budget Review April 8, 2015 Finance Committee Meeting FY16 Strategic Business Operating Plan and Preliminary Budget
More informationGoals, Objectives, and Policies Capital Improvements Element
Goals, Objectives, and Policies Capital Improvements Element Background Pursuant to Chapter 163.3177(3)(a), F.S. and Sections 9J-5.016(3) (a), (b), and (c), F.A.C., the following represents the goals,
More informationFinal Report Water and Sewer Rate Model Town of Denton, MD
Final Report Water and Sewer Rate Model Town of Denton, MD January 30, 2014 MCET Water and Sewer Rate Model for Denton, MD Page 1 Table of Contents Water and Sewer Rate Model Study Town of Denton, MD January
More informationFY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018
FY 2019 Approved Budget Approved by the Board of Directors on March 1, 2018 DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Enhanced Clarification Facility Lucy Tunnel Boring Machine First Street Tunnel
More informationCHEROKEE COUNTY WATER AND SEWERAGE AUTHORITY CHEROKEE COUNTY, GEORGIA FINANCIAL STATEMENTS FOR THE FISCAL YEAR ENDED AUGUST 31, 2017
CHEROKEE COUNTY WATER AND SEWERAGE AUTHORITY CHEROKEE COUNTY, GEORGIA FINANCIAL STATEMENTS FOR THE FISCAL YEAR ENDED AUGUST 31, 2017 TOGETHER WITH INDEPENDENT AUDITORS REPORTS FINANCIAL STATEMENTS AUGUST
More informationtoho water authorit y Capital Budget Fiscal Years
toho water authorit y Capital Budget Fiscal Years 215-219 TOHOPEKALIGA WATER AUTHORITY 215-219 CAPITAL BUDGET (This page intentionally left blank) - Table of Contents - Introduction Executive Summary...
More informationNORTH HUNTINGDON TOWNSHIP MUNICIPAL AUTHORITY
NORTH HUNTINGDON TOWNSHIP MUNICIPAL AUTHORITY T a p p i n g F e e C a l c u l a t i o n A p r i l 2 0 1 8 5 1 7 3 C A M P B E L L S R U N R O A D P I T T S B U R G H, P A 1 5 2 0 5-9 7 3 3 Table of Contents
More informationPublic Utilities Assessment Gloucester County, Virginia. Page 18
Public Utilities Assessment Gloucester County, Virginia 1 Page 18 Who is RFC/SUNESIS? Raftelis Financial Consultants, Inc. - Founded 1993 - Staff - 30 - Offices - 4 - Leader in financial planning and rate
More informationWater Service for the City of Flint Reference Materials As of April 19, 2017
Water Service for the City of Flint Reference Materials As of April 19, 2017 1. City of Flint Press Release and Related Water Supply Option Analysis Dated April 18, 2017 https://www.cityofflint.com/2017/04/18/mayor-recommends-city-of-flint-stay-with-great-lakes-water-authorityas-primary-water-source/
More informationSIGNIFICANT BUDGET CHANGES
Department of Environmental Services Our Mission: To build and maintain water delivery, sanitary sewer collection, and wastewater treatment systems that provide high-quality water and sewer services and
More informationCOBB COUNTY-MARIETTA WATER AUTHORITY
COBB COUNTY-MARIETTA WATER AUTHORITY MARIETTA, GEORGIA FINANCIAL REPORT FOR THE YEAR ENDED DECEMBER 31, 2013 COBB COUNTY-MARIETTA WATER AUTHORITY FINANCIAL REPORT DECEMBER 31, 2013 TABLE OF CONTENTS Page
More informationUtilities Extension Project (UEP) North 2 Final Assessment Resolutions Water Wastewater Irrigation
Utilities Extension Project (UEP) North 2 Final Assessment Resolutions 126-17 Water 127-17 Wastewater 128-17 Irrigation Special Meeting of the City Council August 2, 2017 1 Executive Summary Utilities
More informationCenterville-Osterville-Marstons Mills Water Department Water Rate Review
Centerville-Osterville-Marstons Mills Water Department Water Rate Review Prepared by Financial Advisory Associates, Inc. 258 Main Street, Suite A2 Buzzards Bay, MA 02532 April 29, 2005 FAA Financial Advisory
More informationThe following is a list of the City s Funds other than General Fund:
City of San Mateo The following is a list of the City s Funds other than General Fund: Fund # Fund Name 20 Grants Fund (Police)* 21 Solid Waste Fund 22 H.O.M.E. Fund 23 Community Development Block Grant
More informationUSDA RURAL DEVELOPMENT. Committed to the future of rural communities
USDA RURAL DEVELOPMENT Committed to the future of rural communities We have a mission We are committed to helping improve the economy and quality of life in rural America. Florida/VI Office Jurisdiction
More informationFinancial Management, Capital Planning, Need for Inflation Adjustments
Your Utility Uses Money as Fuel- Financial Management, Capital Planning, Need for Inflation Adjustments MWEA Lagoon Seminar Presented by: Rich Grant, PE February 2013 Proposed Agenda CONCEPTS User Charges
More informationFINANCIAL PLAN REVIEW AND FORECAST
Napa Sanitation District Cost of Service Rate and Capacity Charge Study Technical Memorandum #2 FINANCIAL PLAN REVIEW AND FORECAST DRAFT March 2018 Contents 1 Introduction 1 1.1 Project Background 1 1.1.1
More informationYORK COUNTY, SOUTH CAROLINA
YORK COUNTY, SOUTH CAROLINA Water and Sewer Financial Planning and Rate Study Report October 25, 2017 1031 S. Caldwell Street Suite 100 Charlotte, NC 28203 Phone 704.373.1199 Fax 704.373.1113 www.raftelis.com
More informationCity of Cocoa FY 2010 Utility Rate Study. Final Report. Water, Sewer & Reclaimed Water Rates, Fees & Charges Study. Prepared by:
p FY 2010 Utility Rate Study Water, Sewer & Reclaimed Water Rates, Fees & Charges Study June 29, 2010 Prepared by: June 29, 2010 W.E. Mack Finance Director 65 Stone Street Cocoa, FL 32922 Re: FY 2010
More informationNWC Tariff Submission for the Period January 2019 to December Submission to the Office of Utilities Regulation (OUR)
NWC Tariff Submission for the Period January 2019 to December 2021 Submission to the Office of Utilities Regulation (OUR) October 2018 Table of Contents 1 Executive Summary 1 1.1 Build-Up of the Revenue
More informationAssistance Program: Miami Dade County PHCD Affordable Housing First Time Homebuyer Program Code: DFLMIAMCY
HOMEOWNERSHIP ASSISTANCE PROGRAM SUMMARY Product Description Allowable Origination Channel Program Name Second mortgage loan program to be used in conjunction with: FHA Fixed Rate Fannie Mae Fixed 30-year
More informationCITY OF PALM BAY, FLORIDA MONTHLY FINANCIAL REPORT (UNAUDITED) MARCH Financial Report Summary
(UNAUDITED) The City of Palm Bay, Florida s (the City ) monthly financial report presents an overview and analysis of the City s financial activities during the month of. March is the sixth month of the
More informationCapital Improvement Program (CIP)
(CIP) Citrus County maintains a (CIP) that covers a five-year period and is updated annually in conjunction with the operating budget. The projects included in this program will enable the County to meet
More informationNORTH TAHOE PUBLIC UTILITY DISTRICT
NORTH TAHOE PUBLIC UTILITY DISTRICT FEBRUARY 14, 2017 REVIEW FINANCIAL DATA 20170214 Financial Update for Board 1 WHERE DID WE COME FROM? WHERE ARE WE HEADED? 20170214 Financial Update for Board 2 20170214
More information2017 WATER AND WASTEWATER IMPACT FEE STUDY CITY OF AZLE, TEXAS
2017 WATER AND WASTEWATER IMPACT FEE STUDY CITY OF AZLE, TEXAS JULY 2017 Prepared by: Weatherford Office Address: 1508 Santa Fe Drive, Suite 203 Weatherford, Texas 76086 (817) 594-9880 www.jacobmartin.com
More informationFY 2018 BUDGET. Presentation to the FOMB June 30, 2017
FY 2018 BUDGET Presentation to the FOMB June 30, 2017 Disclaimer The Puerto Rico Fiscal Agency and Financial Advisory Authority ( AAFAF ), the Puerto Rico Aqueduct and Sewer Authority ( PRASA ), the Government
More informationBAYSHORE SANITARY DISTRICT
BAYSHORE SANITARY DISTRICT San Mateo County, California Annual Budget Fiscal Year 2017-2018 Adopted July 27, 2017 36 Industrial Way Brisbane, California 94005 (415) 467-1144 BAYSHORE SANITARY DISTRICT
More informationBROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND A Major Fund of Broward County, Florida
BROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND A Major Fund of Broward County, Florida Financial Statements For the Years Ended BROWARD COUNTY, FLORIDA WATER AND WASTEWATER FUND FINANCIAL STATEMENTS
More informationPRELIMINARY BUDGET
PRELIMINARY BUDGET 2017-2018 OPERATIONAL FUNDS JULY 31, 2017 EDUCATIO N FUND OPE RATIONS & MAINTE NANCE FUND TRANSPORTAT I ON FUND Operational Funds Revenue Assumptions Property Tax Same as Pre-Preliminary
More information